Commission Information Collection Activities (Ferc-725y); Comment Request; Extension, 60409-60411 [2024-16386]

Download as PDF ddrumheller on DSK120RN23PROD with NOTICES1 Federal Register / Vol. 89, No. 143 / Thursday, July 25, 2024 / Notices disaster area and must provide appropriate supporting documentation, if requested. The applicable federally declared disaster area under this declaration is the area in which assistance to individuals or public assistance has been authorized under FEMA’s disaster declaration for Texas Hurricane Beryl DR–4798–TX. See the disaster declaration available at https:// www.fema.gov/disaster/4798. Affected applicants that have already timely submitted applications under the FY 2024 CEVSS Program competition may resubmit applications on or before the extended application deadline of August 5, 2024, but are not required to do so. If a new application is not submitted, the Department will use the application that was submitted by the original deadline. If a new application is submitted, the Department will consider the application that is last submitted and timely received by 11:59:59 p.m., Eastern Time, on August 5, 2024. Any application submitted by an affected applicant under the extended deadline must contain evidence (e.g., the applicant organization mailing address) that the applicant is located in the applicable federally declared disaster area and, if requested, the applicant must provide appropriate supporting documentation. The application period is not extended for all applicants. Applications from applicants that are not affected, as defined above, will not be accepted past the original July 29, 2024 deadline. Note: All information in the NIA for this competition remains the same, except for the deadline for the transmittal of applications for affected applicants and the deadline for intergovernmental review. Program Authority: 20 U.S.C. 1161t; 20 U.S.C. 1138–1138d; and the explanatory statement accompanying Division D of the Further Consolidated Appropriations Act, 2024 (Pub. L. 118– 47). Accessible Format: On request to the program contact person listed under FOR FURTHER INFORMATION CONTACT, individuals with disabilities can obtain this notice, the NIA, and a copy of the application package in an accessible format. The Department will provide the requestor with an accessible format that may include Rich Text Format (RTF) or text format (txt), a thumb drive, an MP3 file, braille, large print, audiotape, compact disc, or other accessible format. Electronic Access to This Document: The official version of this document is the document published in the Federal Register. You may access the official VerDate Sep<11>2014 19:41 Jul 24, 2024 Jkt 262001 edition of the Federal Register and the Code of Federal Regulations at www.govinfo.gov. At this site you can view this document, as well as all other Department documents published in the Federal Register, in text or Portable Document Format (PDF). To use PDF you must have Adobe Acrobat Reader, which is available free at the site. You may also access Department documents published in the Federal Register by using the article search feature at www.federalregister.gov. Specifically, through the advanced search feature at this site, you can limit your search to documents published by the Department. Nasser Paydar, Assistant Secretary for Postsecondary Education. [FR Doc. 2024–16376 Filed 7–24–24; 8:45 am] BILLING CODE 4000–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. IC24–16–000] Commission Information Collection Activities (Ferc–725y); Comment Request; Extension Federal Energy Regulatory Commission. ACTION: Notice of information collection and request for comments. AGENCY: In compliance with the requirements of the Paperwork Reduction Act of 1995, the Federal Energy Regulatory Commission (Commission or FERC) is soliciting public comment on the currently approved information collection, FERC– 725Y, Mandatory Reliability Standard (Personnel Performance, Training, and Qualifications). DATES: Comments on the collection of information are due September 23, 2024. ADDRESSES: You may submit copies of your comments (identified by Docket No. IC24–16–000) by one of the following methods: Electronic filing through https:// www.ferc.gov, is preferred. • Electronic Filing: Documents must be filed in acceptable native applications and print-to-PDF, not in scanned or picture format. • For those unable to file electronically, comments may be filed by USPS mail or by other delivery methods: Æ Mail via U.S. Postal Service Only: Federal Energy Regulatory Commission, SUMMARY: PO 00000 Frm 00061 Fmt 4703 Sfmt 4703 60409 Secretary of the Commission, 888 First Street NE, Washington, DC 20426. Æ All other delivery services: Federal Energy Regulatory Commission, Office of the Secretary, 12225 Wilkins Avenue, Rockville, MD 20852. Instructions: All submissions must be formatted and filed in accordance with submission guidelines at: https:// www.ferc.gov. For user assistance, contact FERC Online Support by email at ferconlinesupport@ferc.gov, or by phone at (866) 208–3676 (toll-free). Docket: Users interested in receiving automatic notification of activity in this docket or in viewing/downloading comments and issuances in this docket may do so at https://www.ferc.gov. FOR FURTHER INFORMATION CONTACT: Jean Sonneman may be reached by email at DataClearance@FERC.gov, telephone at (202) 502–6362. SUPPLEMENTARY INFORMATION: Title: FERC–725Y, Mandatory Reliability Standard (Personnel Performance, Training, and Qualifications). OMB Control No.: 1902–0279. Type of Request: Three-year extension of the FERC–725Y information collection requirements with no changes to the reporting requirements. Abstract: The FERC–725Y information collection is intended to help ensure the safe and reliable operation of the interconnected grid through the retention of suitably trained and qualified personnel in positions that can impact the reliable operation of the Bulk-Power System. The Commission uses the FERC–725Y to implement the Congressional mandate of the Energy Policy Act of 2005 to develop mandatory and enforceable Reliability Standards to better ensure the reliability of the nation’s BulkPower System. FERC–725Y ensures that personnel performing or supporting real-time operations on the Bulk Electric System (BES) are trained using a systematic approach. The Reliability Standard requires entities to maintain records subject to review by the Commission and North American Electric Reliability Corporation (NERC) to ensure compliance with the Reliability Standard. Reliability Standard PER–003–2 purpose is to ensure that System Operators performing the reliabilityrelated tasks of the Reliability Coordinator, Balancing Authority and Transmission Operator are certified through the NERC System Operator Certification Program when filling a Realtime operating position responsible for control of the Bulk Electric System. • R1. Each Reliability Coordinator shall staff its Real-time operating E:\FR\FM\25JYN1.SGM 25JYN1 60410 Federal Register / Vol. 89, No. 143 / Thursday, July 25, 2024 / Notices positions performing Reliability Coordinator reliability-related tasks with System Operators who have demonstrated minimum competency in the areas listed by obtaining and maintaining a valid NERC Reliability Operator certificate. • R2. Each Transmission Operator shall staff its Real-time operating positions performing Transmission Operator reliability-related tasks with System Operators who have demonstrated minimum competency in the areas listed by obtaining and maintaining one of the following valid NERC certificates. • R3. Each Balancing Authority shall staff its Real-time operating positions performing Balancing Authority reliability-related tasks with System Operators who have demonstrated minimum competency in the areas listed by obtaining and maintaining one of the following valid NERC certificates. Reliability Standard PER–005–2 requires entities to maintain records subject to review by the Commission and NERC to ensure compliance with the Reliability Standard. This Reliability Standard contains of six Requirements: • R1 requires reliability coordinators, balancing authorities, and transmission operators to develop and implement a training program for system operators. • R2 requires transmission owners to develop and implement a training program for system operators. • R3 requires reliability coordinators, balancing authorities, transmission operators and transmission owners to verify the capabilities of their identified personnel. • R4 requires reliability coordinators, balancing authorities, transmission operators and transmission owners to provide those personnel with emergency operations training using simulation technology. • R5 requires reliability coordinators, balancing authorities, and transmission operators develop and implement training for system operators whose job functions can impact BES real-time reliability tasks. • R6 requires applicable generator operators to develop and implement training for certain of their dispatch personnel at a centrally located dispatch center. Reliability Standard PER–006–1 ensures that personnel are trained on specific topics essential to reliability to perform or support Real-Time operations of the Bulk Electric System. • R1 identifies generator operator plant personnel responsible for Realtime control and carrying out Operating instructions are trained on the operational functionality of Protection Number and type of respondents 3 I (1) Systems and Remedial Action Schemes that affect the output of generating facility(ies) it operates. Type of Respondents: Transmission owners and generator owners. Estimate of Annual Burden 1: Our estimate below regarding the number of respondents is based on the NERC compliance registry as of April 16, 2024. In general, the number of respondents has increased from previous renewal as each entity may have multiple responsibilities under these standards and those responsibilities are counted separately. When the original PER–003–0 was approved in Order No. 693 the associated manhours were part of the 83 NERC Reliability Standards approved at one time.2 In the two revisions done PER–003–1 and PER–003–2 it was determined at that there was no change in burden specific to PER–003. To increase clarity, manhours associated with the original PER–003–0 are being moved from the 725A collection and being added into the 725Y collection. The next update to 725A (2024) will reflect the change in burden associated with PER–003 and moving manhours from 725A into 725Y. The Commission estimates the additional annual reporting burden and cost as follows: Annual number of responses per respondent Total number of responses Avg. burden & cost per response 4 Total annual burden hours & total annual cost ($) Cost per respondent ($) (2) I (1) * (2) = (3) I (4) (3) * (4) = (5) (5) ÷ (1) FERC–725Y in Docket No. IC24–16–000 Reliability Standard PER–003–2 Annual Review of Credentials. Record Retention ................. 12 (RC) ................................ 98 (BA) ................................ 165 (TOP) ............................ (RC, BA, TOP) 275 ............. Total .............................. .............................................. 1 1 1 1 12 98 165 275 60 60 60 60 hrs. hrs. hrs. hrs. $4,637.40 $4,637.40 $4,637.40 $2,735.40 ... ... ... ... 720 hrs. $55,648.80 ............ 5,880 hrs. $454,465.20 ....... 9.900 hrs. $765,171.00 ....... 16,500 hrs. $752,235.00 ..... $4,637.40 4,637.40 4,637.40 2,735.40 I........................ I........................ I ................................ 33,000 hrs. $2,027,520.00 .. ........................ FERC–725Y (Reliability Standard PER–005–2) Annual Evaluation, Update of Training Program. Annual Evaluation and Update of Training Program. Retention of Records ........... ddrumheller on DSK120RN23PROD with NOTICES1 Total .............................. 12 (RC) ................................ 98 (BA) ................................ 165 (TOP) ............................ 324 (TO) .............................. 1028 (GOP) ......................... (RC, BA, TOP, TO, GOP) 1627. (RC, BA, TOP, TO, GOP) 1627. 1 1 1 1 1 1 12 98 165 324 1028 1627 14 hrs.; $1,082.06 .. 14 hrs.; $1,082.06 .. 14 hrs.; $1,082.06 .. 14 hrs.; $1,082.06 .. 14 hrs.; $1,082.06 .. 8 hrs.; $364.72 ....... 168 hrs.; $12,984.72 ........... 1,372 hrs.; $106,041.88 ...... 2,310 hrs.; $178,539.90 ...... 4,536 hrs.; $350,587.44 ...... 14,392 hrs.; $1,112,357.68 13,016 hrs.; $593,399.44 .... 1,082.06 1,082.06 1,082.06 1,082.06 1,082.06 364.72 1 1627 10 hrs.; $455.90 ..... 16,270 hrs.; $741,749.30 .... 455.90 .............................................. ........................ ........................ ................................ 68,892 hrs.; $3,095,660.36 ........................ 1,082.06 FERC–725Y (Reliability Standard PER–006–1) GOP; Reporting, Recordkeeping Req. GOP; Reporting Req. R1 ..... 1028 ..................................... 1 1028 14 hrs.; $1,082.06 .. 14,392 hrs.; $1,112,357.68 1028 ..................................... 1 1028 5 hrs.; $386.45 ....... 5,140 hrs.; $397,270.60 ...... 1 Burden is defined as the total time, effort, or financial resources expended by persons to generate, maintain, retain, or disclose or provide information to or for a federal agency. For further VerDate Sep<11>2014 20:40 Jul 24, 2024 Jkt 262001 explanation of what is included in the information collection burden, reference 5 Code of Federal Regulations 1320.3. PO 00000 Frm 00062 Fmt 4703 Sfmt 4703 386.45 2 Order No. 693 Mandatory Reliability Standards for the Bulk-Power System—approved March 16, 2007. E:\FR\FM\25JYN1.SGM 25JYN1 Federal Register / Vol. 89, No. 143 / Thursday, July 25, 2024 / Notices GOP; Recordkeeping Req ... Total .............................. Number and type of respondents 3 Annual number of responses per respondent Total number of responses Avg. burden & cost per response 4 Total annual burden hours & total annual cost ($) Cost per respondent ($) (1) (2) (1) * (2) = (3) (4) (3) * (4) = (5) (5) ÷ (1) 5 1028 ................................... 1 1028 10 hrs.; $455.90 ..... 10,280 hrs.; $468,665.20 .... .............................................. ........................ ........................ ................................ 29,812 hrs.; $1,978,293.48 Comments: Comments are invited on: (1) whether the collection of information is necessary for the proper performance of the functions of the Commission, including whether the information will have practical utility; (2) the accuracy of the agency’s estimate of the burden and cost of the collection of information, including the validity of the methodology and assumptions used; (3) ways to enhance the quality, utility and clarity of the information collection; and (4) ways to minimize the burden of the collection of information on those who are to respond, including the use of automated collection techniques or other forms of information technology. Dated: July 19, 2024. Debbie-Anne A. Reese, Acting Secretary. LLC informed the Commission that the exemption from licensing for the Steels Pond Project No. 3265, originally issued October 18, 1983,1 has been partially transferred to Steels Pond Hydro LLC. The project is located on the North Branch of the Contoocook River in Hillsborough County, New Hampshire. The transfer of an exemption does not require Commission approval. 2. Steels Pond Hydro LLC, located at 230 Park Avenue, Suite 447, New York, New York 10169 is now the coexemptee of the Steels Pond Project No. 3265 with the New Hampshire Water Resource Board. Dated: July 18, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–16297 Filed 7–24–24; 8:45 am] BILLING CODE 6717–01–P [FR Doc. 2024–16386 Filed 7–24–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Federal Energy Regulatory Commission [Docket No. CP24–490–000] [Project No. 3265–004] New Hampshire Water Resource Board and Steels Pond Hydro, Inc., New Hampshire Water Resource Board and Steels Pond Hydro LLC; Notice of Partial Transfer of Exemption ddrumheller on DSK120RN23PROD with NOTICES1 1. By letter filed July 8, 2024, Steels Pond Hydro, Inc. and Steels Pond Hydro 3 For PER–003–2, PER–005–2 and PER–006–1: RC = Reliability Coordinator; BA = Balancing Authority; TOP = Transmission Operator; TO = Transmission Owner; GOP = Generator Operator. The NERC compliance registry table April 16, 2024, was used to perform analysis. 4 The estimated hourly cost (salary plus benefits) is a combination based on the Bureau of Labor Statistics (BLS), as of 2023. The estimates for cost per response are loaded hourly wage figure (includes benefits) based on two occupational categories for 2023 found on the Bureau of Labor Statistics website (https://www.bls.gov/oes/current/ naics2_22.htm): • Electrical Engineer (Occupation Code: 17– 2071): $77.29 (to calculate the reporting requirements). • Office and Administrative Support (Occupation Code: 43–0000): $45.59 (to calculate the recordkeeping requirements). 5 The number of US unique GOPs is 1028 taken from the NERC compliance registry information of April 16, 2024. VerDate Sep<11>2014 19:41 Jul 24, 2024 60411 Jkt 262001 EcoEléctrica, L.P.; Notice of Application and Establishing Intervention Deadline Take notice that on July 5, 2024, EcoEléctrica, L.P. (EcoEléctrica), 641 Road 337, Km. 3.7, Bo. Tallaboa Poniente, Peñuelas, Puerto Rico 00624, filed an application under section 3(a) of the Natural Gas Act (NGA), and part 153 of the Commission’s regulations to amend its authorization granted by the Commission on June 19, 2014, for its LNG Supply Pipeline Project. Specifically, EcoEléctrica seeks authorization to increase the sendout capacity on its LNG Supply Pipeline to the existing off-site liquefied natural gas (LNG) Truck Loading Facility from 250 gallons per minute (gpm) to 500 gpm during periods of simultaneous trailer loading. The Project is designed to meet the increasing demand for LNG from the Truck Loading Facility and its downstream users. EcoEléctrica states 1 New Hampshire Water Resource Board and Steels Pond Hydro, Inc., 25 FERC ¶ 62,055 (1983) (Order Granting Exemption from Licensing of a Small Hydroelectric Project of 5 Megawatts or Less). PO 00000 Frm 00063 Fmt 4703 Sfmt 4703 455.90 ........................ that the requested capacity increase will only require minor modifications to the existing LNG facility at its LNG terminal, all as more fully set forth in the application which is on file with the Commission and open for public inspection. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov). From the Commission’s Home Page on the internet, this information is available on eLibrary. The full text of this document is available on eLibrary in PDF and Microsoft Word format for viewing, printing, and/or downloading. To access this document in eLibrary, type the docket number excluding the last three digits of this document in the docket number field. User assistance is available for eLibrary and the Commission’s website during normal business hours from FERC Online Support at (202) 502–6652 (toll free at 1–866–208–3676) or email at ferconlinesupport@ferc.gov, or the Public Reference Room at (202) 502– 8371, TTY (202) 502–8659. Email the Public Reference Room at public.referenceroom@ferc.gov. Any questions regarding the proposed project should be directed to Carlos A. Reyes, President & General Manager, EcoEléctrica, L.P., 641 Road 337, Km. 3.7, Bo. Tallaboa Poniente, Peñuelas, Puerto Rico 00624, by phone at (787) 759–0202 or by email at carlos.reyes@ ecoelectrica.com. Pursuant to section 157.9 of the Commission’s Rules of Practice and Procedure,1 within 90 days of this Notice the Commission staff will either: complete its environmental review and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) 1 18 E:\FR\FM\25JYN1.SGM CFR 157.9. 25JYN1

Agencies

[Federal Register Volume 89, Number 143 (Thursday, July 25, 2024)]
[Notices]
[Pages 60409-60411]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-16386]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. IC24-16-000]


Commission Information Collection Activities (Ferc-725y); Comment 
Request; Extension

AGENCY: Federal Energy Regulatory Commission.

ACTION: Notice of information collection and request for comments.

-----------------------------------------------------------------------

SUMMARY: In compliance with the requirements of the Paperwork Reduction 
Act of 1995, the Federal Energy Regulatory Commission (Commission or 
FERC) is soliciting public comment on the currently approved 
information collection, FERC-725Y, Mandatory Reliability Standard 
(Personnel Performance, Training, and Qualifications).

DATES: Comments on the collection of information are due September 23, 
2024.

ADDRESSES: You may submit copies of your comments (identified by Docket 
No. IC24-16-000) by one of the following methods:
    Electronic filing through https://www.ferc.gov, is preferred.
     Electronic Filing: Documents must be filed in acceptable 
native applications and print-to-PDF, not in scanned or picture format.
     For those unable to file electronically, comments may be 
filed by USPS mail or by other delivery methods:
    [cir] Mail via U.S. Postal Service Only: Federal Energy Regulatory 
Commission, Secretary of the Commission, 888 First Street NE, 
Washington, DC 20426.
    [cir] All other delivery services: Federal Energy Regulatory 
Commission, Office of the Secretary, 12225 Wilkins Avenue, Rockville, 
MD 20852.
    Instructions: All submissions must be formatted and filed in 
accordance with submission guidelines at: https://www.ferc.gov. For 
user assistance, contact FERC Online Support by email at 
[email protected], or by phone at (866) 208-3676 (toll-free).
    Docket: Users interested in receiving automatic notification of 
activity in this docket or in viewing/downloading comments and 
issuances in this docket may do so at https://www.ferc.gov.

FOR FURTHER INFORMATION CONTACT: Jean Sonneman may be reached by email 
at [email protected], telephone at (202) 502-6362.

SUPPLEMENTARY INFORMATION: 
    Title: FERC-725Y, Mandatory Reliability Standard (Personnel 
Performance, Training, and Qualifications).
    OMB Control No.: 1902-0279.
    Type of Request: Three-year extension of the FERC-725Y information 
collection requirements with no changes to the reporting requirements.
    Abstract: The FERC-725Y information collection is intended to help 
ensure the safe and reliable operation of the interconnected grid 
through the retention of suitably trained and qualified personnel in 
positions that can impact the reliable operation of the Bulk-Power 
System. The Commission uses the FERC-725Y to implement the 
Congressional mandate of the Energy Policy Act of 2005 to develop 
mandatory and enforceable Reliability Standards to better ensure the 
reliability of the nation's Bulk-Power System. FERC-725Y ensures that 
personnel performing or supporting real-time operations on the Bulk 
Electric System (BES) are trained using a systematic approach. The 
Reliability Standard requires entities to maintain records subject to 
review by the Commission and North American Electric Reliability 
Corporation (NERC) to ensure compliance with the Reliability Standard.
    Reliability Standard PER-003-2 purpose is to ensure that System 
Operators performing the reliability-related tasks of the Reliability 
Coordinator, Balancing Authority and Transmission Operator are 
certified through the NERC System Operator Certification Program when 
filling a Realtime operating position responsible for control of the 
Bulk Electric System.
     R1. Each Reliability Coordinator shall staff its Real-time 
operating

[[Page 60410]]

positions performing Reliability Coordinator reliability-related tasks 
with System Operators who have demonstrated minimum competency in the 
areas listed by obtaining and maintaining a valid NERC Reliability 
Operator certificate.
     R2. Each Transmission Operator shall staff its Real-time 
operating positions performing Transmission Operator reliability-
related tasks with System Operators who have demonstrated minimum 
competency in the areas listed by obtaining and maintaining one of the 
following valid NERC certificates.
     R3. Each Balancing Authority shall staff its Real-time 
operating positions performing Balancing Authority reliability-related 
tasks with System Operators who have demonstrated minimum competency in 
the areas listed by obtaining and maintaining one of the following 
valid NERC certificates.
    Reliability Standard PER-005-2 requires entities to maintain 
records subject to review by the Commission and NERC to ensure 
compliance with the Reliability Standard. This Reliability Standard 
contains of six Requirements:
     R1 requires reliability coordinators, balancing 
authorities, and transmission operators to develop and implement a 
training program for system operators.
     R2 requires transmission owners to develop and implement a 
training program for system operators.
     R3 requires reliability coordinators, balancing 
authorities, transmission operators and transmission owners to verify 
the capabilities of their identified personnel.
     R4 requires reliability coordinators, balancing 
authorities, transmission operators and transmission owners to provide 
those personnel with emergency operations training using simulation 
technology.
     R5 requires reliability coordinators, balancing 
authorities, and transmission operators develop and implement training 
for system operators whose job functions can impact BES real-time 
reliability tasks.
     R6 requires applicable generator operators to develop and 
implement training for certain of their dispatch personnel at a 
centrally located dispatch center.
    Reliability Standard PER-006-1 ensures that personnel are trained 
on specific topics essential to reliability to perform or support Real-
Time operations of the Bulk Electric System.
     R1 identifies generator operator plant personnel 
responsible for Real-time control and carrying out Operating 
instructions are trained on the operational functionality of Protection 
Systems and Remedial Action Schemes that affect the output of 
generating facility(ies) it operates.
    Type of Respondents: Transmission owners and generator owners.
    Estimate of Annual Burden \1\: Our estimate below regarding the 
number of respondents is based on the NERC compliance registry as of 
April 16, 2024. In general, the number of respondents has increased 
from previous renewal as each entity may have multiple responsibilities 
under these standards and those responsibilities are counted 
separately.
---------------------------------------------------------------------------

    \1\ Burden is defined as the total time, effort, or financial 
resources expended by persons to generate, maintain, retain, or 
disclose or provide information to or for a federal agency. For 
further explanation of what is included in the information 
collection burden, reference 5 Code of Federal Regulations 1320.3.
---------------------------------------------------------------------------

    When the original PER-003-0 was approved in Order No. 693 the 
associated manhours were part of the 83 NERC Reliability Standards 
approved at one time.\2\ In the two revisions done PER-003-1 and PER-
003-2 it was determined at that there was no change in burden specific 
to PER-003. To increase clarity, manhours associated with the original 
PER-003-0 are being moved from the 725A collection and being added into 
the 725Y collection. The next update to 725A (2024) will reflect the 
change in burden associated with PER-003 and moving manhours from 725A 
into 725Y.
---------------------------------------------------------------------------

    \2\ Order No. 693 Mandatory Reliability Standards for the Bulk-
Power System--approved March 16, 2007.
---------------------------------------------------------------------------

    The Commission estimates the additional annual reporting burden and 
cost as follows:

--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                             Annual number                                          Total annual burden
                                       Number and type of    of responses    Total number     Avg. burden & cost    hours & total annual     Cost per
                                        respondents \3\     per respondent   of responses      per response \4\           cost ($)        respondent ($)
                                     (1)..................             (2)     (1) * (2) =  (4)..................  (3) * (4) = (5)......       (5) / (1)
                                                                                       (3)
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                           FERC-725Y in Docket No. IC24-16-000 Reliability Standard PER-003-2
--------------------------------------------------------------------------------------------------------------------------------------------------------
Annual Review of Credentials.......  12 (RC)..............               1              12  60 hrs. $4,637.40....  720 hrs. $55,648.80..       $4,637.40
                                     98 (BA)..............               1              98  60 hrs. $4,637.40....  5,880 hrs.                   4,637.40
                                                                                                                    $454,465.20.
                                     165 (TOP)............               1             165  60 hrs. $4,637.40....  9.900 hrs.                   4,637.40
                                                                                                                    $765,171.00.
Record Retention...................  (RC, BA, TOP) 275....               1             275  60 hrs. $2,735.40....  16,500 hrs.                  2,735.40
                                                                                                                    $752,235.00.
                                    --------------------------------------------------------------------------------------------------------------------
    Total..........................  .....................  ..............  ..............  .....................  33,000 hrs.            ..............
                                                                                                                    $2,027,520.00.
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                       FERC-725Y (Reliability Standard PER-005-2)
--------------------------------------------------------------------------------------------------------------------------------------------------------
Annual Evaluation, Update of         12 (RC)..............               1              12  14 hrs.; $1,082.06...  168 hrs.; $12,984.72.        1,082.06
 Training Program.                   98 (BA)..............               1              98  14 hrs.; $1,082.06...  1,372 hrs.;                  1,082.06
                                                                                                                    $106,041.88.
                                     165 (TOP)............               1             165  14 hrs.; $1,082.06...  2,310 hrs.;                  1,082.06
                                                                                                                    $178,539.90.
                                     324 (TO).............               1             324  14 hrs.; $1,082.06...  4,536 hrs.;                  1,082.06
                                                                                                                    $350,587.44.
                                     1028 (GOP)...........               1            1028  14 hrs.; $1,082.06...  14,392 hrs.;                 1,082.06
                                                                                                                    $1,112,357.68.
Annual Evaluation and Update of      (RC, BA, TOP, TO,                   1            1627  8 hrs.; $364.72......  13,016 hrs.;                   364.72
 Training Program.                    GOP) 1627.                                                                    $593,399.44.
Retention of Records...............  (RC, BA, TOP, TO,                   1            1627  10 hrs.; $455.90.....  16,270 hrs.;                   455.90
                                      GOP) 1627.                                                                    $741,749.30.
                                    --------------------------------------------------------------------------------------------------------------------
    Total..........................  .....................  ..............  ..............  .....................  68,892 hrs.;           ..............
                                                                                                                    $3,095,660.36.
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                       FERC-725Y (Reliability Standard PER-006-1)
--------------------------------------------------------------------------------------------------------------------------------------------------------
GOP; Reporting, Recordkeeping Req..  1028.................               1            1028  14 hrs.; $1,082.06...  14,392 hrs.;                 1,082.06
                                                                                                                    $1,112,357.68.
GOP; Reporting Req. R1.............  1028.................               1            1028  5 hrs.; $386.45......  5,140 hrs.;                    386.45
                                                                                                                    $397,270.60.

[[Page 60411]]

 
GOP; Recordkeeping Req.............  \5\ 1028.............               1            1028  10 hrs.; $455.90.....  10,280 hrs.;                   455.90
                                                                                                                    $468,665.20.
                                    --------------------------------------------------------------------------------------------------------------------
    Total..........................  .....................  ..............  ..............  .....................  29,812 hrs.;           ..............
                                                                                                                    $1,978,293.48.
--------------------------------------------------------------------------------------------------------------------------------------------------------

    Comments: Comments are invited on: (1) whether the collection of 
information is necessary for the proper performance of the functions of 
the Commission, including whether the information will have practical 
utility; (2) the accuracy of the agency's estimate of the burden and 
cost of the collection of information, including the validity of the 
methodology and assumptions used; (3) ways to enhance the quality, 
utility and clarity of the information collection; and (4) ways to 
minimize the burden of the collection of information on those who are 
to respond, including the use of automated collection techniques or 
other forms of information technology.
---------------------------------------------------------------------------

    \3\ For PER-003-2, PER-005-2 and PER-006-1: RC = Reliability 
Coordinator; BA = Balancing Authority; TOP = Transmission Operator; 
TO = Transmission Owner; GOP = Generator Operator. The NERC 
compliance registry table April 16, 2024, was used to perform 
analysis.
    \4\ The estimated hourly cost (salary plus benefits) is a 
combination based on the Bureau of Labor Statistics (BLS), as of 
2023. The estimates for cost per response are loaded hourly wage 
figure (includes benefits) based on two occupational categories for 
2023 found on the Bureau of Labor Statistics website (https://www.bls.gov/oes/current/naics2_22.htm):
     Electrical Engineer (Occupation Code: 17-2071): $77.29 
(to calculate the reporting requirements).
     Office and Administrative Support (Occupation Code: 43-
0000): $45.59 (to calculate the recordkeeping requirements).
    \5\ The number of US unique GOPs is 1028 taken from the NERC 
compliance registry information of April 16, 2024.

    Dated: July 19, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-16386 Filed 7-24-24; 8:45 am]
BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.