Factory Falls, Inc.; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments, 58149-58150 [2024-15736]

Download as PDF ddrumheller on DSK120RN23PROD with NOTICES1 Federal Register / Vol. 89, No. 137 / Wednesday, July 17, 2024 / Notices m. The application is not ready for environmental analysis at this time. n. The Comtu Project consists of the following: (1) a 4-foot-high, 128-footlong concrete gravity dam (Comtu Falls Dam) topped with 2-foot-high wooden flashboards with a crest elevation of 394.4 feet North American Vertical Datum of 1988 at the top of the flashboards; (2) a 0.4-acre impoundment; (3) an intake structure on the west side of the dam equipped with a trashrack with 1.5-inch clear bar spacing and a slide gate; (4) a 6-foothigh, 6-foot wide, 65-foot-long reinforced concrete penstock; (5) a powerhouse with one Kaplan turbine generator unit with an authorized installed capacity of 460 kilowatts; (6) a 0.6/4.61 kilovolt (kV), 300 kilo-voltamperes transformer; (7) a 20-foot-long, 4.16-kV transmission line; and (8) appurtenant facilities. Comtu Corporation operates the project in a run-of-river mode using an automatic pond level control system to regulate turbine operation, such that outflow from the project approximates inflow. The current license requires Comtu Corporation to release a continuous minimum flow of 4 cubic feet per second or inflow, whichever is less, over the project dam and to release all inflow over the dam when inflow is less than 44 cubic feet per second. The project had an average annual generation of 2,340 megawatt-hours between 2011 and 2020. The current license also requires Comtu Corporation to provide downstream fish passage at the project from April 1 to June 15. Comtu Corporation operates a downstream fish passage facility consisting of a 3-footwide, 2-foot-deep notch in the spillway that discharges to a concrete plunge pool. Comtu Corporation proposes to continue operating the project in a runof-river mode. Comtu Corporation also proposes to: (1) increase the current year-round 0.5-inch aesthetic flow over the spillway to 1 inch or 10 cfs; (2) operate the existing downstream fish passage facility from April 1 to June 15 and from September 15 to November 15; and (3) develop a flow management and monitoring plan. o. Copies of the application may be viewed on the Commission’s website at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document (P–7888). For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or call tollfree, (866) 208–3676 or (202) 502– 8659 (TTY). VerDate Sep<11>2014 19:21 Jul 16, 2024 Jkt 262001 You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. p. Procedural schedule and final amendments: The application will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate. Milestone Target date Issue Deficiency Letter (if necessary). Request for Additional Information. Issue Acceptance Letter ............. Issue Scoping Document 1 for comments. Request Additional Information (if necessary). Issue Scoping Document 2 (if necessary). August 2024. August 2024. December 2024. December 2024. January 2025. March 2025. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. Dated: July 11, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–15732 Filed 7–16–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 9650–036] Factory Falls, Inc.; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments Take notice that the following hydroelectric application has been filed PO 00000 Frm 00048 Fmt 4703 Sfmt 4703 58149 with the Commission and is available for public inspection. a. Type of Application: Subsequent Minor License. b. Project No.: 9650–036. c. Date filed: June 28, 2024. d. Applicant: Factory Falls, Inc. (Factory Falls). e. Name of Project: Gilman Dam Hydroelectric Project. f. Location: On the Black River, Windsor County, Vermont. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)–825(r). h. Applicant Contact: William Handly, Factory Falls, Inc., 286 South Street, Springfield, Vermont 05156; Phone at (802) 885–5360 or email at bhandly@vermontel.net. i. FERC Contact: Erin Kimsey at (202) 502–8621, or erin.kimsey@ferc.gov. j. Cooperating agencies: Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the instructions for filing such requests described in item l below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See, 94 FERC ¶ 61,076 (2001). k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission’s regulations, if any resource agency, Indian Tribe, or person believes that an additional scientific study should be conducted in order to form an adequate factual basis for a complete analysis of the application on its merit, the resource agency, Indian Tribe, or person must file a request for a study with the Commission not later than 60 days from the date of filing of the application, and serve a copy of the request on the applicant. l. Deadline for filing additional study requests and requests for cooperating agency status: August 27, 2024. The Commission strongly encourages electronic filing. Please file additional study requests and requests for cooperating agency status using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. E:\FR\FM\17JYN1.SGM 17JYN1 ddrumheller on DSK120RN23PROD with NOTICES1 58150 Federal Register / Vol. 89, No. 137 / Wednesday, July 17, 2024 / Notices Submissions sent via any other carrier must be addressed to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852. All filings must clearly identify the project name and docket number on the first page: Gilman Dam Hydroelectric Project (P–9650–036). m. The application is not ready for environmental analysis at this time. n. The existing Gilman Dam Project consists of the following: (1) a 190-footlong, 7-foot-high concrete gravity dam (Gilman Dam) that includes a spillway with a crest elevation of 421 feet mean sea level (msl); (2) an impoundment with a surface area of 1.0 acre at an elevation of 421 feet msl; (3) an intake structure equipped with a headgate and trashrack with 1.5-inch clear bar spacing; (4) a 175-foot-long, 6-footdiameter penstock; (5) a 40-foot-long, 50-foot-wide, brick and concrete powerhouse with a Vertical Francis turbine-generator unit with an authorized installed capacity of 125 kilowatts; (6) a 50-foot-long tailrace; (7) a 0.6 kilovolt (kV) generator lead; (8) a 0.6/4.16 kV step-up transformer; (9) a 4.16 kV transmission line; (10) a downstream fish passage facility for Atlantic Salmon; and (11) appurtenant facilities. The current license requires Factory Falls to operate the project in instantaneous run-of-river mode, so that flow in the Black River, as measured immediately downstream from the project tailrace, approximates the instantaneous sum of the inflow to the project impoundment. The current license also requires Factory Falls to release a minimum flow of 9 cubic feet per second (cfs) over the spillway or through the fish passage facility during passage season, and 40 cfs in an uncontrolled bypass channel on the west side of the dam, and to operate the downstream fish passage from April 1 through June 15. The project has an average annual generation of 550 megawatt-hours. Factory Falls propose to continue operating the project in a run-of-river mode. Factory Falls also propose to increase the minimum flow over the spillway from 9 cfs to 10 cfs by maintaining the impoundment 1 inch above the spillway crest. o. Copies of the application may be viewed on the Commission’s website at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document (P–9650). For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or call VerDate Sep<11>2014 19:21 Jul 16, 2024 Jkt 262001 tollfree, (866) 208–3676 or (202) 502– 8659 (TTY). You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. p. Procedural schedule and final amendments: The application will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate. Issue Deficiency Letter (if necessary). Request Additional Information. Issue Acceptance Letter ......... Issue Scoping Document 1 for comments. Request Additional Information (if necessary). Issue Scoping Document 2 (if necessary). August 2024. August 2024. January 2025. January 2025. March 2025. March 2025. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. Dated: July 11, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–15736 Filed 7–16–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP24–487–000] LA Storage, LLC; Notice of Amendment of Application and Establishing Intervention Deadline Take notice that on June 28, 2024, LA Storage, LLC (LA Storage), 1500 Post Oak Blvd. Suite 1000, Houston, TX 77056, filed an application under section 7(c) of the Natural Gas Act (NGA), and Part 157 of the Commission’s regulations requesting PO 00000 Frm 00049 Fmt 4703 Sfmt 4703 authorization to amend the certificate of public convenience and necessity issued by the Commission on September 23, 2022, in Docket No. CP21–44–000,1 authorizing LA Storage to construct and operate the Hackberry Storage Project (September 2022 Order). Specifically, LA Storage seeks an amendment to reduce the diameter of the previously authorized Hackberry Pipeline from 42 inches to 36 inches. The Hackberry Storage Project is located in Cameron and Calcasieu Parishes, Louisiana all as more fully set forth in the application which is on file with the Commission and open for public inspection. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov). From the Commission’s Home Page on the internet, this information is available on eLibrary. The full text of this document is available on eLibrary in PDF and Microsoft Word format for viewing, printing, and/or downloading. To access this document in eLibrary, type the docket number excluding the last three digits of this document in the docket number field. User assistance is available for eLibrary and the Commission’s website during normal business hours from FERC Online Support at (202) 502–6652 (toll free at 1–866–208–3676) or email at ferconlinesupport@ferc.gov, or the Public Reference Room at (202) 502– 8371, TTY (202) 502–8659. Email the Public Reference Room at public.referenceroom@ferc.gov. Any questions regarding the proposed project should be directed to Jerrod L. Harrison, Assistant General Counsel Sempra Infrastructure, 488 8th Avenue, San Diego, CA, 92101 by phone at 619– 696–2987, or by email at jharrison@ sempraglobal.com. Pursuant to section 157.9 of the Commission’s Rules of Practice and Procedure,2 within 90 days of this Notice the Commission staff will either: complete its environmental review and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) 1 See LA Storage, LLC, 180 FERC ¶ 61,188 (2022); LA Storage, LLC, 183 FERC ¶ 62,128 (2023). 2 18 CFR 157.9. E:\FR\FM\17JYN1.SGM 17JYN1

Agencies

[Federal Register Volume 89, Number 137 (Wednesday, July 17, 2024)]
[Notices]
[Pages 58149-58150]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-15736]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 9650-036]


Factory Falls, Inc.; Notice of Application Tendered for Filing 
With the Commission and Soliciting Additional Study Requests and 
Establishing Procedural Schedule for Relicensing and a Deadline for 
Submission of Final Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Subsequent Minor License.
    b. Project No.: 9650-036.
    c. Date filed: June 28, 2024.
    d. Applicant: Factory Falls, Inc. (Factory Falls).
    e. Name of Project: Gilman Dam Hydroelectric Project.
    f. Location: On the Black River, Windsor County, Vermont.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: William Handly, Factory Falls, Inc., 286 
South Street, Springfield, Vermont 05156; Phone at (802) 885-5360 or 
email at [email protected].
    i. FERC Contact: Erin Kimsey at (202) 502-8621, or 
[email protected].
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item l below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See, 94 FERC ] 
61,076 (2001).
    k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's 
regulations, if any resource agency, Indian Tribe, or person believes 
that an additional scientific study should be conducted in order to 
form an adequate factual basis for a complete analysis of the 
application on its merit, the resource agency, Indian Tribe, or person 
must file a request for a study with the Commission not later than 60 
days from the date of filing of the application, and serve a copy of 
the request on the applicant.
    l. Deadline for filing additional study requests and requests for 
cooperating agency status: August 27, 2024.
    The Commission strongly encourages electronic filing. Please file 
additional study requests and requests for cooperating agency status 
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support 
at [email protected], (866) 208-3676 (toll free), or (202) 
502-8659 (TTY). In lieu of electronic filing, you may submit a paper 
copy. Submissions sent via the U.S. Postal Service must be addressed 
to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.

[[Page 58150]]

Submissions sent via any other carrier must be addressed to: Debbie-
Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 
12225 Wilkins Avenue, Rockville, MD 20852. All filings must clearly 
identify the project name and docket number on the first page: Gilman 
Dam Hydroelectric Project (P-9650-036).
    m. The application is not ready for environmental analysis at this 
time.
    n. The existing Gilman Dam Project consists of the following: (1) a 
190-foot-long, 7-foot-high concrete gravity dam (Gilman Dam) that 
includes a spillway with a crest elevation of 421 feet mean sea level 
(msl); (2) an impoundment with a surface area of 1.0 acre at an 
elevation of 421 feet msl; (3) an intake structure equipped with a 
headgate and trashrack with 1.5-inch clear bar spacing; (4) a 175-foot-
long, 6-foot-diameter penstock; (5) a 40-foot-long, 50-foot-wide, brick 
and concrete powerhouse with a Vertical Francis turbine-generator unit 
with an authorized installed capacity of 125 kilowatts; (6) a 50-foot-
long tailrace; (7) a 0.6 kilovolt (kV) generator lead; (8) a 0.6/4.16 
kV step-up transformer; (9) a 4.16 kV transmission line; (10) a 
downstream fish passage facility for Atlantic Salmon; and (11) 
appurtenant facilities.
    The current license requires Factory Falls to operate the project 
in instantaneous run-of-river mode, so that flow in the Black River, as 
measured immediately downstream from the project tailrace, approximates 
the instantaneous sum of the inflow to the project impoundment. The 
current license also requires Factory Falls to release a minimum flow 
of 9 cubic feet per second (cfs) over the spillway or through the fish 
passage facility during passage season, and 40 cfs in an uncontrolled 
bypass channel on the west side of the dam, and to operate the 
downstream fish passage from April 1 through June 15. The project has 
an average annual generation of 550 megawatt-hours.
    Factory Falls propose to continue operating the project in a run-
of-river mode. Factory Falls also propose to increase the minimum flow 
over the spillway from 9 cfs to 10 cfs by maintaining the impoundment 1 
inch above the spillway crest.
    o. Copies of the application may be viewed on the Commission's 
website at https://www.ferc.gov using the ``eLibrary'' link. Enter the 
docket number excluding the last three digits in the docket number 
field to access the document (P-9650). For assistance, contact FERC 
Online Support at [email protected] or call tollfree, (866) 
208-3676 or (202) 502-8659 (TTY).
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].
    p. Procedural schedule and final amendments: The application will 
be processed according to the following preliminary schedule. Revisions 
to the schedule will be made as appropriate.

------------------------------------------------------------------------
 
------------------------------------------------------------------------
Issue Deficiency Letter (if necessary).  August 2024.
Request Additional Information.........  August 2024.
Issue Acceptance Letter................  January 2025.
Issue Scoping Document 1 for comments..  January 2025.
Request Additional Information (if       March 2025.
 necessary).
Issue Scoping Document 2 (if necessary)  March 2025.
------------------------------------------------------------------------

    Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

    Dated: July 11, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-15736 Filed 7-16-24; 8:45 am]
BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.