Comtu Falls Corporation; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments, 58148-58149 [2024-15732]
Download as PDF
ddrumheller on DSK120RN23PROD with NOTICES1
58148
Federal Register / Vol. 89, No. 137 / Wednesday, July 17, 2024 / Notices
equipped with a trashrack with 1-inch
clear bar spacing; (4) a 5,717 foot-long,
42-inch-diameter steel penstock; (5) a
55.7-foot-long, 24-foot-wide, brick and
concrete powerhouse with a Francis
turbine-generator unit with an
authorized installed capacity of 1,000
kilowatts (kW); (6) a tailrace; (7) a stepup transformer; (8) a 100-foot-long, 12.4
kilovolt transmission line; and (9)
appurtenant facilities.
The current license requires Ashuelot
Hydro to operate the project in
instantaneous run-of-river mode, so that
flow in the Minnewawa Brook, as
measured immediately downstream
from the project tailrace, approximates
the instantaneous sum of the inflow to
the project impoundment. The current
license also requires that Ashuelot
Hydro release a minimum flow of 4
cubic feet per second, as measured
immediately downstream from the
Minnewawa Dam, or inflow to the
impoundment, whichever is less. The
minimum flow is released from the lowlevel outlet valve into a bypassed reach
of Minnewawa Brook between the dam
and the tailrace. The average annual
generation of the project between 2003
through 2023 was 3,945 megawatthours.
Ashuelot Hydro propose to: (1)
continue operating the project in a runof-river mode; (2) install a new 75-kW
fixed geometry turbine-generator unit in
the existing powerhouse; (3) install a tap
and isolation valve to the existing
penstock; and (4) increase the height of
the flashboards on the spillway by one
foot and maintain the impoundment
water surface elevation at 1071.2 feet
NGVD 29 (i.e., one foot above its current
level of 1070.2 feet NGVD 29).
o. Copies of the application may be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document (P–7887). For assistance,
contact FERC Online Support at
FERCOnlineSupport@ferc.gov or call
tollfree, (866) 208–3676 or (202) 502–
8659 (TTY).
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
VerDate Sep<11>2014
19:21 Jul 16, 2024
Jkt 262001
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
p. Procedural schedule and final
amendments: The application will be
processed according to the following
preliminary schedule. Revisions to the
schedule will be made as appropriate.
Milestone
Target date
Issue Deficiency Letter (if
necessary).
Request for Additional Information.
Issue Acceptance Letter ..
Issue Scoping Document
1 for comments.
Request Additional Information (if necessary).
Issue Scoping Document
2 (if necessary).
August 2024.
August 2024.
December 2024.
December 2024.
January 2025.
March 2025.
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: July 11, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–15731 Filed 7–16–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. P–7888–024]
Comtu Falls Corporation; Notice of
Application Tendered for Filing With
the Commission and Soliciting
Additional Study Requests and
Establishing Procedural Schedule for
Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
Minor License.
b. Project No.: 7888–024.
c. Date Filed: June 27, 2024.
d. Applicant: Comtu Falls Corporation
(Comtu Corporation).
e. Name of Project: Comtu Falls
Hydroelectric Project.
f. Location: On the Black River in
Windsor County, Vermont.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
PO 00000
Frm 00047
Fmt 4703
Sfmt 4703
h. Applicant Contacts: Celeste Fay,
Director Regulatory Affairs, Comtu Falls
Corporation, P.O. Box 7580, Boulder,
CO 80306; (413) 262–9466; email at
celeste@gravityrenewables.com; or
Jonathon Petrillo, VP Business
Development, Comtu Falls Corporation,
P.O. Box 7580, Boulder, CO 80306; (413)
262–9466; email at jon@
gravityrenewables.com.
i. FERC Contact: Nathan Tatum at
202–502–8838, or nathan.tatum@
ferc.gov.
j. Cooperating Agencies: Federal,
state, local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: August 26, 2024.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, you may submit a
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Debbie-Anne A. Reese, Acting
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Debbie-Anne A.
Reese, Acting Secretary, Federal Energy
Regulatory Commission, 12225 Wilkins
Avenue, Rockville, MD 20852. All
filings must clearly identify the project
name and docket number on the first
page: Comtu Falls Project (P–7888–024).
E:\FR\FM\17JYN1.SGM
17JYN1
ddrumheller on DSK120RN23PROD with NOTICES1
Federal Register / Vol. 89, No. 137 / Wednesday, July 17, 2024 / Notices
m. The application is not ready for
environmental analysis at this time.
n. The Comtu Project consists of the
following: (1) a 4-foot-high, 128-footlong concrete gravity dam (Comtu Falls
Dam) topped with 2-foot-high wooden
flashboards with a crest elevation of
394.4 feet North American Vertical
Datum of 1988 at the top of the
flashboards; (2) a 0.4-acre
impoundment; (3) an intake structure on
the west side of the dam equipped with
a trashrack with 1.5-inch clear bar
spacing and a slide gate; (4) a 6-foothigh, 6-foot wide, 65-foot-long
reinforced concrete penstock; (5) a
powerhouse with one Kaplan turbine
generator unit with an authorized
installed capacity of 460 kilowatts; (6) a
0.6/4.61 kilovolt (kV), 300 kilo-voltamperes transformer; (7) a 20-foot-long,
4.16-kV transmission line; and (8)
appurtenant facilities.
Comtu Corporation operates the
project in a run-of-river mode using an
automatic pond level control system to
regulate turbine operation, such that
outflow from the project approximates
inflow. The current license requires
Comtu Corporation to release a
continuous minimum flow of 4 cubic
feet per second or inflow, whichever is
less, over the project dam and to release
all inflow over the dam when inflow is
less than 44 cubic feet per second. The
project had an average annual
generation of 2,340 megawatt-hours
between 2011 and 2020.
The current license also requires
Comtu Corporation to provide
downstream fish passage at the project
from April 1 to June 15. Comtu
Corporation operates a downstream fish
passage facility consisting of a 3-footwide, 2-foot-deep notch in the spillway
that discharges to a concrete plunge
pool.
Comtu Corporation proposes to
continue operating the project in a runof-river mode. Comtu Corporation also
proposes to: (1) increase the current
year-round 0.5-inch aesthetic flow over
the spillway to 1 inch or 10 cfs; (2)
operate the existing downstream fish
passage facility from April 1 to June 15
and from September 15 to November 15;
and (3) develop a flow management and
monitoring plan.
o. Copies of the application may be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document (P–7888). For assistance,
contact FERC Online Support at
FERCOnlineSupport@ferc.gov or call
tollfree, (866) 208–3676 or (202) 502–
8659 (TTY).
VerDate Sep<11>2014
19:21 Jul 16, 2024
Jkt 262001
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
p. Procedural schedule and final
amendments: The application will be
processed according to the following
preliminary schedule. Revisions to the
schedule will be made as appropriate.
Milestone
Target date
Issue Deficiency Letter (if necessary).
Request for Additional Information.
Issue Acceptance Letter .............
Issue Scoping Document 1 for
comments.
Request Additional Information
(if necessary).
Issue Scoping Document 2 (if
necessary).
August 2024.
August 2024.
December 2024.
December 2024.
January 2025.
March 2025.
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: July 11, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–15732 Filed 7–16–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 9650–036]
Factory Falls, Inc.; Notice of
Application Tendered for Filing With
the Commission and Soliciting
Additional Study Requests and
Establishing Procedural Schedule for
Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
PO 00000
Frm 00048
Fmt 4703
Sfmt 4703
58149
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
Minor License.
b. Project No.: 9650–036.
c. Date filed: June 28, 2024.
d. Applicant: Factory Falls, Inc.
(Factory Falls).
e. Name of Project: Gilman Dam
Hydroelectric Project.
f. Location: On the Black River,
Windsor County, Vermont.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: William
Handly, Factory Falls, Inc., 286 South
Street, Springfield, Vermont 05156;
Phone at (802) 885–5360 or email at
bhandly@vermontel.net.
i. FERC Contact: Erin Kimsey at (202)
502–8621, or erin.kimsey@ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: August 27, 2024.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, you may submit a
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Debbie-Anne A. Reese, Acting
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
E:\FR\FM\17JYN1.SGM
17JYN1
Agencies
[Federal Register Volume 89, Number 137 (Wednesday, July 17, 2024)]
[Notices]
[Pages 58148-58149]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-15732]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. P-7888-024]
Comtu Falls Corporation; Notice of Application Tendered for
Filing With the Commission and Soliciting Additional Study Requests and
Establishing Procedural Schedule for Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Subsequent Minor License.
b. Project No.: 7888-024.
c. Date Filed: June 27, 2024.
d. Applicant: Comtu Falls Corporation (Comtu Corporation).
e. Name of Project: Comtu Falls Hydroelectric Project.
f. Location: On the Black River in Windsor County, Vermont.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contacts: Celeste Fay, Director Regulatory Affairs,
Comtu Falls Corporation, P.O. Box 7580, Boulder, CO 80306; (413) 262-
9466; email at [email protected]; or Jonathon Petrillo, VP
Business Development, Comtu Falls Corporation, P.O. Box 7580, Boulder,
CO 80306; (413) 262-9466; email at [email protected].
i. FERC Contact: Nathan Tatum at 202-502-8838, or
[email protected].
j. Cooperating Agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See, 94 FERC ]
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: August 26, 2024.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support
at [email protected], (866) 208-3676 (toll free), or (202)
502-8659 (TTY). In lieu of electronic filing, you may submit a paper
copy. Submissions sent via the U.S. Postal Service must be addressed
to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier must be addressed to: Debbie-
Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission,
12225 Wilkins Avenue, Rockville, MD 20852. All filings must clearly
identify the project name and docket number on the first page: Comtu
Falls Project (P-7888-024).
[[Page 58149]]
m. The application is not ready for environmental analysis at this
time.
n. The Comtu Project consists of the following: (1) a 4-foot-high,
128-foot-long concrete gravity dam (Comtu Falls Dam) topped with 2-
foot-high wooden flashboards with a crest elevation of 394.4 feet North
American Vertical Datum of 1988 at the top of the flashboards; (2) a
0.4-acre impoundment; (3) an intake structure on the west side of the
dam equipped with a trashrack with 1.5-inch clear bar spacing and a
slide gate; (4) a 6-foot-high, 6-foot wide, 65-foot-long reinforced
concrete penstock; (5) a powerhouse with one Kaplan turbine generator
unit with an authorized installed capacity of 460 kilowatts; (6) a 0.6/
4.61 kilovolt (kV), 300 kilo-volt-amperes transformer; (7) a 20-foot-
long, 4.16-kV transmission line; and (8) appurtenant facilities.
Comtu Corporation operates the project in a run-of-river mode using
an automatic pond level control system to regulate turbine operation,
such that outflow from the project approximates inflow. The current
license requires Comtu Corporation to release a continuous minimum flow
of 4 cubic feet per second or inflow, whichever is less, over the
project dam and to release all inflow over the dam when inflow is less
than 44 cubic feet per second. The project had an average annual
generation of 2,340 megawatt-hours between 2011 and 2020.
The current license also requires Comtu Corporation to provide
downstream fish passage at the project from April 1 to June 15. Comtu
Corporation operates a downstream fish passage facility consisting of a
3-foot-wide, 2-foot-deep notch in the spillway that discharges to a
concrete plunge pool.
Comtu Corporation proposes to continue operating the project in a
run-of-river mode. Comtu Corporation also proposes to: (1) increase the
current year-round 0.5-inch aesthetic flow over the spillway to 1 inch
or 10 cfs; (2) operate the existing downstream fish passage facility
from April 1 to June 15 and from September 15 to November 15; and (3)
develop a flow management and monitoring plan.
o. Copies of the application may be viewed on the Commission's
website at https://www.ferc.gov using the ``eLibrary'' link. Enter the
docket number excluding the last three digits in the docket number
field to access the document (P-7888). For assistance, contact FERC
Online Support at [email protected] or call tollfree, (866)
208-3676 or (202) 502-8659 (TTY).
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
p. Procedural schedule and final amendments: The application will
be processed according to the following preliminary schedule. Revisions
to the schedule will be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Issue Deficiency Letter (if necessary).. August 2024.
Request for Additional Information...... August 2024.
Issue Acceptance Letter................. December 2024.
Issue Scoping Document 1 for comments... December 2024.
Request Additional Information (if January 2025.
necessary).
Issue Scoping Document 2 (if necessary). March 2025.
------------------------------------------------------------------------
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: July 11, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-15732 Filed 7-16-24; 8:45 am]