McCallum Enterprises I, Limited Partnership, Shelton Canal Company; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Relicensing and Deadline for Submission of Final Amendments, 57146-57147 [2024-15301]
Download as PDF
57146
Federal Register / Vol. 89, No. 134 / Friday, July 12, 2024 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
lotter on DSK11XQN23PROD with NOTICES1
Combined Notice of Filings #1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER17–1329–003.
Applicants: J.P. Morgan Ventures
Energy Corporation.
Description: Compliance filing:
Update to Market Based Rate Tariff to be
effective 11/20/2023.
Filed Date: 7/5/24.
Accession Number: 20240705–5059.
Comment Date: 5 p.m. ET 7/26/24.
Docket Numbers: ER21–2364–003.
Applicants: Albemarle Beach Solar,
LLC.
Description: Informational Filing
Pursuant to Schedule 2 of the PJM
Interconnection, L.L.C. Open Access
Transmission Tariff and Requests for
Waiver and Expedited Action.
Filed Date: 7/1/24.
Accession Number: 20240701–5470.
Comment Date: 5 p.m. ET 7/22/24.
Docket Numbers: ER24–2463–000.
Applicants: New York Independent
System Operator, Inc.
Description: Petition for Prospective
Tariff Waiver, for a Shortened Comment
Period and for Expedited Action of New
York Independent System Operator, Inc.
Filed Date: 7/2/24.
Accession Number: 20240702–5234.
Comment Date: 5 p.m. ET 7/12/24.
Docket Numbers: ER24–2467–000.
Applicants: Spanish Peaks Solar LLC.
Description: Baseline eTariff Filing:
Market-Based Rate Application to be
effective 9/2/2024.
Filed Date: 7/3/24.
Accession Number: 20240703–5202.
Comment Date: 5 p.m. ET 7/24/24.
Docket Numbers: ER24–2468–000.
Applicants: Entergy Louisiana, LLC,
Entergy Mississippi, LLC, Entergy New
Orleans, LLC, Entergy Texas, Inc.,
Entergy Services, LLC, Entergy
Arkansas, LLC.
Description: 205(d) Rate Filing:
Entergy Louisiana, LLC submits tariff
filing per 35.13(a)(2)(iii: MSS–4R Clean
Up Filing to be effective 5/14/2024.
Filed Date: 7/3/24.
Accession Number: 20240703–5224.
Comment Date: 5 p.m. ET 7/24/24.
Docket Numbers: ER24–2469–000.
Applicants: Southwest Power Pool,
Inc.
Description: 205(d) Rate Filing: 4226
Lazbuddie Wind Energy & SPS Facilities
Service Agr to be effective 9/3/2024.
Filed Date: 7/5/24.
VerDate Sep<11>2014
16:35 Jul 11, 2024
Jkt 262001
Accession Number: 20240705–5039.
Comment Date: 5 p.m. ET 7/26/24.
Docket Numbers: ER24–2470–000.
Applicants: Tenaska Virginia
Partners, L.P.
Description: Tenaska Virginia
Partners, L.P. submits Request for
Limited Tariff Waiver of the 90-day
prior notice requirement set forth in
Schedule 2 to the PJM Interconnection,
L.L.C. Open Access Transmission Tariff.
Filed Date: 7/3/24.
Accession Number: 20240703–5230.
Comment Date: 5 p.m. ET 7/24/24.
Docket Numbers: ER24–2471–000.
Applicants: California Independent
System Operator Corporation.
Description: 205(d) Rate Filing: 2024–
07–05 Applicant Participating
Transmission Owner Agrmt—SunZia to
be effective 9/4/2024.
Filed Date: 7/5/24.
Accession Number: 20240705–5117.
Comment Date: 5 p.m. ET 7/26/24.
Docket Numbers: ER24–2472–000.
Applicants: PJM Interconnection,
L.L.C.
Description: 205(d) Rate Filing:
Original WMPA, Service Agreement No.
7301; AG1–210 to be effective 6/4/2024.
Filed Date: 7/5/24.
Accession Number: 20240705–5123.
Comment Date: 5 p.m. ET 7/26/24.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene, to
protest, or to answer a complaint in any
of the above proceedings must file in
accordance with Rules 211, 214, or 206
of the Commission’s Regulations (18
CFR 385.211, 385.214, or 385.206) on or
before 5:00 p.m. Eastern time on the
specified comment date. Protests may be
considered, but intervention is
necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Dated: July 5, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–15297 Filed 7–11–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 6066–042]
McCallum Enterprises I, Limited
Partnership, Shelton Canal Company;
Notice of Application Tendered for
Filing With the Commission and
Establishing Procedural Schedule for
Relicensing and Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 6066–042.
c. Date filed: April 15, 2024.
d. Applicants: McCallum Enterprises
I, Limited Partnership (McCallum) and
Shelton Canal Company (Shelton).
e. Name of Project: Derby Dam
Hydroelectric Project (Derby Project or
project).
f. Location: On the Housatonic River
in Fairfield and New Haven Counties,
Connecticut.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Joseph W.
Szarmach Jr., McCallum Enterprises I,
Limited Partnership, 2874 Main Street,
Stratford, CT 06614; telephone at (203)
368–1745; email at joseph.szarmach@
gmail.com.
i. FERC Contact: Brandi WelchAcosta, Project Coordinator, New
England Branch, Division of
Hydropower Licensing; telephone at
(202) 502–8964; email at brandi.welchacosta@ferc.gov.
j. The application is not ready for
environmental analysis at this time.
k. Project Description: The existing
Derby Project consists of: (1) a 23.7-foothigh, 675-foot-long dam made of
concrete capped cut stone with
flashboards of varying heights, ranging
from 1.8-foot-high to 2.2-foot-high, and
a crest elevation of 25.2 feet National
Geodetic Vertical Datum of 1988 (NGVD
88); (2) a 400-foot-long earth dike with
a maximum height of 10 feet, located at
E:\FR\FM\12JYN1.SGM
12JYN1
Federal Register / Vol. 89, No. 134 / Friday, July 12, 2024 / Notices
the east abutment and oriented in a
northwest-southwest direction; (3) a
reservoir (Lake Housatonic) with a
normal maximum water surface
elevation of 25.2 feet NGVD 88 and a
usable storage capacity of 500 acre-feet;
(4) a gatehouse (Derby gatehouse); (5) a
gatehouse (Shelton gatehouse) and 130foot-long, 94-foot-wide headrace
channel extending downstream from the
dam; (6) a navigation lock located at the
west abutment, which constitutes the
first 70 feet of the Shelton canal; (7) a
powerhouse (Shelton powerhouse) at
the west abutment, in the existing
Shelton canal and lock structure, and
located approximately 130 feet
downstream of the Shelton gatehouse,
containing two horizontal A–C tube
Kaplan turbines with two direct drive
generators with a total rated capacity of
7.8 megawatts (MW) and a rated flow of
4,600 cubic feet per second; (8) a 775foot-long, 13.8 kilovolt underwater
transmission line tying into the existing
United Illuminating Company system;
and (9) appurtenant facilities.
The current license requires the
implementation of an August 5, 1987
recreation plan that includes: (1) fishing
access with an information kiosk
downstream of the dam on the east
shoreline; (2) fishing access with an
information kiosk at the project’s
tailrace (west shoreline); (3) canoe
portage and associated warning signs at
the project’s tailrace; (4) an information
kiosk at the entrance to the project; and
(5) picnic tables and benches with
scenic views of the river.
The current license requires the
project to operate in a run-of-river mode
such that outflow from the project
approximates inflow to the
impoundment. The project bypasses
approximately 350 feet of the
Housatonic River. The average annual
generation of the project was
approximately 25,147 megawatt-hours
from 2006 through 2016.
McCallum and Shelton propose to
continue operating the project in a runof-river mode. McCallum and Shelton
also propose to: (1) develop an
operation monitoring plan; (2) develop
an impoundment refill plan; (3) install
and operate an upstream fish passage
facility with an automated fish lift; (4)
install a new 0.4-MW minimum flow
turbine within the upstream fish
passage facility; (5) develop a fishway
operation and maintenance plan; (6)
install and operate one or more
upstream eel passage facilities; (7)
install and operate a downstream fish
passage facility; (8) install a seasonal
0.75-inch partial depth trashrack
overlay; and (9) implement downstream
eel passage measures.
l. In addition to publishing the full
text of this notice in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
notice, as well as other documents in
the proceeding (e.g., license application)
via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document (P–6066).
For assistance, contact FERC at
FERCOnlineSupport@ferc.gov, (866)
208–3676, or (202) 502–8659 (TTY).
You may also register online at
https://ferconline.ferc.gov/FERCOnline.
aspx to be notified via email of new
filings and issuances related to this or
other pending projects. For assistance,
contact FERC Online Support.
m. The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
n. Procedural schedule: The
application will be processed according
to the following preliminary schedule.
Revisions to the schedule will be made
as appropriate.
Milestone
Target date
Issue Deficiency Letter and Request for Additional Information ....................................................
Issue Scoping Document 1 for comments ......................................................................................
Request Additional Information (if necessary) ................................................................................
Issue Acceptance Letter .................................................................................................................
Issue Scoping Document 2 (if necessary) ......................................................................................
Issue Notice of Ready for Environmental Analysis .........................................................................
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
DEPARTMENT OF ENERGY
Dated: July 5, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[Docket No. ER24–2394–000]
[FR Doc. 2024–15301 Filed 7–11–24; 8:45 am]
lotter on DSK11XQN23PROD with NOTICES1
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
Cataract Coast, LLC; Supplemental
Notice That Initial Market-Based Rate
Filing Includes Request for Blanket
Section 204 Authorization
This is a supplemental notice in the
above-referenced proceeding of Cataract
Coast, LLC’s application for marketbased rate authority, with an
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
part 34, of future issuances of securities
and assumptions of liability.
VerDate Sep<11>2014
16:35 Jul 11, 2024
Jkt 262001
PO 00000
57147
Frm 00025
Fmt 4703
Sfmt 4703
August 2024.
November 2024.
December 2024.
December 2024.
January 2025.
January 2025.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is July 25,
2024.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
E:\FR\FM\12JYN1.SGM
12JYN1
Agencies
[Federal Register Volume 89, Number 134 (Friday, July 12, 2024)]
[Notices]
[Pages 57146-57147]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-15301]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 6066-042]
McCallum Enterprises I, Limited Partnership, Shelton Canal
Company; Notice of Application Tendered for Filing With the Commission
and Establishing Procedural Schedule for Relicensing and Deadline for
Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 6066-042.
c. Date filed: April 15, 2024.
d. Applicants: McCallum Enterprises I, Limited Partnership
(McCallum) and Shelton Canal Company (Shelton).
e. Name of Project: Derby Dam Hydroelectric Project (Derby Project
or project).
f. Location: On the Housatonic River in Fairfield and New Haven
Counties, Connecticut.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mr. Joseph W. Szarmach Jr., McCallum
Enterprises I, Limited Partnership, 2874 Main Street, Stratford, CT
06614; telephone at (203) 368-1745; email at [email protected].
i. FERC Contact: Brandi Welch-Acosta, Project Coordinator, New
England Branch, Division of Hydropower Licensing; telephone at (202)
502-8964; email at [email protected].
j. The application is not ready for environmental analysis at this
time.
k. Project Description: The existing Derby Project consists of: (1)
a 23.7-foot-high, 675-foot-long dam made of concrete capped cut stone
with flashboards of varying heights, ranging from 1.8-foot-high to 2.2-
foot-high, and a crest elevation of 25.2 feet National Geodetic
Vertical Datum of 1988 (NGVD 88); (2) a 400-foot-long earth dike with a
maximum height of 10 feet, located at
[[Page 57147]]
the east abutment and oriented in a northwest-southwest direction; (3)
a reservoir (Lake Housatonic) with a normal maximum water surface
elevation of 25.2 feet NGVD 88 and a usable storage capacity of 500
acre-feet; (4) a gatehouse (Derby gatehouse); (5) a gatehouse (Shelton
gatehouse) and 130-foot-long, 94-foot-wide headrace channel extending
downstream from the dam; (6) a navigation lock located at the west
abutment, which constitutes the first 70 feet of the Shelton canal; (7)
a powerhouse (Shelton powerhouse) at the west abutment, in the existing
Shelton canal and lock structure, and located approximately 130 feet
downstream of the Shelton gatehouse, containing two horizontal A-C tube
Kaplan turbines with two direct drive generators with a total rated
capacity of 7.8 megawatts (MW) and a rated flow of 4,600 cubic feet per
second; (8) a 775-foot-long, 13.8 kilovolt underwater transmission line
tying into the existing United Illuminating Company system; and (9)
appurtenant facilities.
The current license requires the implementation of an August 5,
1987 recreation plan that includes: (1) fishing access with an
information kiosk downstream of the dam on the east shoreline; (2)
fishing access with an information kiosk at the project's tailrace
(west shoreline); (3) canoe portage and associated warning signs at the
project's tailrace; (4) an information kiosk at the entrance to the
project; and (5) picnic tables and benches with scenic views of the
river.
The current license requires the project to operate in a run-of-
river mode such that outflow from the project approximates inflow to
the impoundment. The project bypasses approximately 350 feet of the
Housatonic River. The average annual generation of the project was
approximately 25,147 megawatt-hours from 2006 through 2016.
McCallum and Shelton propose to continue operating the project in a
run-of-river mode. McCallum and Shelton also propose to: (1) develop an
operation monitoring plan; (2) develop an impoundment refill plan; (3)
install and operate an upstream fish passage facility with an automated
fish lift; (4) install a new 0.4-MW minimum flow turbine within the
upstream fish passage facility; (5) develop a fishway operation and
maintenance plan; (6) install and operate one or more upstream eel
passage facilities; (7) install and operate a downstream fish passage
facility; (8) install a seasonal 0.75-inch partial depth trashrack
overlay; and (9) implement downstream eel passage measures.
l. In addition to publishing the full text of this notice in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this notice, as well
as other documents in the proceeding (e.g., license application) via
the internet through the Commission's Home Page (https://www.ferc.gov)
using the ``eLibrary'' link. Enter the docket number excluding the last
three digits in the docket number field to access the document (P-
6066). For assistance, contact FERC at [email protected],
(866) 208-3676, or (202) 502-8659 (TTY).
You may also register online at https://ferconline.ferc.gov/FERCOnline.aspx to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
m. The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
n. Procedural schedule: The application will be processed according
to the following preliminary schedule. Revisions to the schedule will
be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Issue Deficiency Letter and Request for August 2024.
Additional Information.
Issue Scoping Document 1 for comments........ November 2024.
Request Additional Information (if necessary) December 2024.
Issue Acceptance Letter...................... December 2024.
Issue Scoping Document 2 (if necessary)...... January 2025.
Issue Notice of Ready for Environmental January 2025.
Analysis.
------------------------------------------------------------------------
o. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: July 5, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-15301 Filed 7-11-24; 8:45 am]