Actions Taken at the June 13, 2024 Meeting, 52198-52199 [2024-13652]
Download as PDF
ddrumheller on DSK120RN23PROD with NOTICES1
52198
Federal Register / Vol. 89, No. 120 / Friday, June 21, 2024 / Notices
the state intends to operate the line
itself, it will be considered a common
carrier. However, if the state contracts
with an operator to provide service over
the line, only the operator incurs a
common carrier obligation. Id.
Therefore, because MBTA has
contracted with Bay Colony to provide
service on the Dover Secondary Track
and the Millis Industrial Track pursuant
to the 1982 Modified Certificate and the
1987 Modified Certificate, and because
there is no indication that MBTA
intended to provide service itself, or has
ever provided service itself, MBTA does
not have a common carrier obligation on
any part of the Line.
Expedited Consideration and Effective
Date. As described above, in requesting
expedited consideration, Bay Colony
and Mass Coastal request that any Board
authority granted to them be effective
upon issuance of the Board’s decision.
This request is reasonable under the
circumstances. Accordingly, the
exemptions will be effective on the date
that this decision is published in the
Federal Register.
Relatedly, the Board’s regulations
require Bay Colony to provide
appropriate parties with 60 days’ notice
of a planned termination of modified
certificate operations. See 49 CFR
1150.24. Bay Colony shall provide
notice of its termination of modified
certificate operations on the Line to the
appropriate parties, and to the Board in
Docket No. FD 29963. The notice also
shall indicate that Mass Coastal will
now be providing common carrier
service on the Line. To allow Mass
Coastal to begin providing the common
carrier service authorized in this
decision, the Board will, on its own
motion, waive the 60-day advance
notice requirement under 49 CFR
1150.24, and will instead require only
seven days’ notice.
It is ordered:
1. In Docket No. FD 36746, under 49
U.S.C. 10502, the Board exempts Bay
Colony’s acquisition of the Easement
and operation of the Millis Industrial
Track from the prior approval
requirements of 49 U.S.C. 10902, as
explained above.
2. In Docket No. FD 36746, the Board
confirms that the Remaining Dover
Secondary Track, between milepost 7.2
and milepost 7.3, remains subject to the
1982 Modified Certificate, as explained
above.
3. In Docket No. FD 36747, under 49
U.S.C. 10502, the Board exempts Mass
Coastal’s acquisition and operation of
the Line from the prior approval
requirements of 49 U.S.C. 10902, as
explained above.
VerDate Sep<11>2014
17:46 Jun 20, 2024
Jkt 262001
4. Bay Colony shall provide notice
pursuant to 49 CFR 1150.24 of its
termination of modified certificate
operations on the Line to the
appropriate parties, and to the Board in
Docket No. FD 29963.
5. The 60-day advance notice
requirement under 49 CFR 1150.24 is
waived, as explained above. Instead,
Bay Colony must provide the notice
required by 49 CFR 1150.24 at least
seven days in advance of the planned
termination.
6. Notice of the exemptions will be
published in the Federal Register.
7. The exemptions will be effective on
June 21, 2024. Petitions for
reconsideration must be filed by July 11,
2024.
Decided: June 14, 2024.
By the Board, Board Members Fuchs,
Hedlund, Primus, and Schultz.
Brendetta Jones,
Clearance Clerk.
[FR Doc. 2024–13671 Filed 6–20–24; 8:45 am]
BILLING CODE 4915–01–P
SUSQUEHANNA RIVER BASIN
COMMISSION
Actions Taken at the June 13, 2024
Meeting
Susquehanna River Basin
Commission
ACTION: Notice.
AGENCY:
As part of its regular business
meeting held on June 13, 2024, in
Harrisburg, Pennsylvania, the
Commission approved the applications
of certain water resources projects and
took additional actions, as set forth in
the SUPPLEMENTARY INFORMATION below.
DATES: June 13, 2024.
ADDRESSES: Susquehanna River Basin
Commission, 4423 N Front Street,
Harrisburg, PA 17110–1788.
FOR FURTHER INFORMATION CONTACT:
Jason E. Oyler, General Counsel and
Secretary, telephone: (717) 238–0423,
ext. 1312, fax: (717) 238–2436; email:
joyler@srbc.gov. Regular mail inquiries
may be sent to the above address. See
also the Commission website at
www.srbc.gov.
SUMMARY:
In
addition to the actions taken on projects
identified in the summary above, these
actions were also taken: (1) elected
Commission officers for FY2025; (2)
reconciled and adopted the FY2025
budget; (3) adopted Policy 2024–01,
‘‘SRBC Procurement Procedures’’, (4)
adopted a resolution to allow the
Commission to use a reserve fund as a
SUPPLEMENTARY INFORMATION:
PO 00000
Frm 00189
Fmt 4703
Sfmt 4703
line of credit, (5) adopted the 2025–2027
Water Resources Program; and (6)
actions on 19 regulatory program
projects.
Project Applications Approved
1. Project Sponsor: Berwick
Enterprises, Inc. Project Facility: The
Bridges Golf Club, Berwick Township,
Adams County, Pa. Application for
renewal of consumptive use of up to
0.249 mgd (30-day average) (Docket No.
19950102).
2. Project Sponsor and Facility: BKV
Operating, LLC (Meshoppen Creek),
Washington Township, Wyoming
County, Pa. Application for renewal of
surface water withdrawal of up to 2.160
mgd (peak day) (Docket No. 20190602).
3. Project Sponsor and Facility: BKV
Operating, LLC (Susquehanna River),
Washington Township, Wyoming
County, Pa. Application for renewal of
surface water withdrawal of up to 2.914
mgd (peak day) (Docket No. 20190603).
4. Project Sponsor and Facility: BKV
Operating, LLC (unnamed tributary to
Middle Branch Wyalusing Creek), Forest
Lake Township, Susquehanna County,
Pa. Application for renewal of surface
water withdrawal of up to 0.648 mgd
(peak day) (Docket No. 20190604).
5. Project Sponsor: Byler Golf
Management, Inc. Project Facility: Iron
Valley Golf Club, Cornwall Borough,
Lebanon County, Pa. Applications for
renewal of consumptive use of up to
0.300 mgd (30-day average) and
groundwater withdrawals (30-day
averages) of up to 0.300 mgd from Well
Lb-814 and 0.140 mgd from Well B
(Docket No. 20200902).
6. Project Sponsor: Cowanesque
Valley Recreation Association. Project
Facility: River Valley Country Club,
Westfield Township, Tioga County, Pa.
Application for renewal of consumptive
use of up to 0.099 mgd (30-day average)
(Docket No. 20020602).
7. Project Sponsor and Facility:
Dillsburg Area Authority, Carroll
Township, York County, Pa.
Application for renewal of groundwater
withdrawal of up to 0.280 mgd (30-day
average) from Well 5A (Docket No.
19980703).
8. Project Sponsor and Facility: EQT
ARO LLC (Pine Creek), McHenry
Township, Lycoming County, Pa.
Application for renewal of surface water
withdrawal of up to 1.500 mgd (peak
day) (Docket No. 20190601).
9. Project Sponsor and Facility:
Keystone Clearwater Solutions, LLC
(Lycoming Creek), Lewis Township,
Lycoming County, Pa. Application for
renewal of surface water withdrawal of
up to 1.250 mgd (peak day) (Docket No.
20190608).
E:\FR\FM\21JNN1.SGM
21JNN1
ddrumheller on DSK120RN23PROD with NOTICES1
Federal Register / Vol. 89, No. 120 / Friday, June 21, 2024 / Notices
10. Project Sponsor and Facility: Lear
Corporation Pine Grove, Pine Grove
Borough, Schuylkill County, Pa.
Application for renewal of consumptive
use of up to 0.160 mgd (30-day average)
(Docket No. 19940501).
11. Project Sponsor: Londonderry
Township. Project Facility: Sunset Golf
Course, Londonderry Township,
Dauphin County, Pa. Application for
renewal of consumptive use of up to
0.181 mgd (30-day average) (Docket No.
20190613). Located in an
Environmental Justice area.
12. Project Sponsor and Facility:
Lycoming County Water and Sewer
Authority, Fairfield Township,
Lycoming County, Pa. Application for
groundwater withdrawal of up to 0.216
mgd from Well PW–2 (30-day average).
13. Project Sponsor and Facility:
Mount Joy Borough Authority, Mount
Joy Borough, Lancaster County, Pa.
Application for renewal of groundwater
withdrawal of up to 1.020 mgd (30-day
average) from Well 3 (Docket No.
20070607), and modification of Docket
Nos. 20110617, 20110617–1, and
20110617–2 for Wells 1 and 2 by adding
conditions related to Well 3 and
proposed operations.
14. Project Sponsor: Pennsylvania—
American Water Company. Project
Facility: Philipsburg/Moshannon
District, Rush Township, Centre County,
Pa. Applications for renewal of
groundwater withdrawals (30-day
averages) of up to 0.600 mgd from Cold
Stream Well 1, 0.432 mgd from Cold
Stream Well 2, and 0.374 mgd from
Cold Stream Well 3 (Docket No.
19890302).
15. Project Sponsor and Facility:
Seneca Resources Company, LLC (Tioga
River), Richmond Township, Tioga
County, Pa. Application for surface
water withdrawal of up to 3.000 mgd
(peak day).
16. Project Sponsor and Facility:
Shippensburg Borough Authority,
Southampton Township, Franklin
County, Pa. Application for renewal of
groundwater withdrawal of up to 1.900
mgd from Well 2 (Docket No.
19940504).
17. Project Sponsor and Facility: SWN
Production Company, LLC (North
Branch Mehoopany Creek), Forkston
Township, Wyoming County, Pa.
Application for surface water
withdrawal of up to 2.500 mgd (peak
day).
18. Project Sponsor and Facility:
Tower City Borough Authority, Porter
Township, Schuylkill County, Pa.
Applications for renewal of
groundwater withdrawals (30-day
averages) of up to 0.086 mgd from Well
5 and 0.070 mgd from Well 6 (Docket
VerDate Sep<11>2014
17:46 Jun 20, 2024
Jkt 262001
No. 19920301). Located in an
Environmental Justice area.
19. Project Sponsor and Facility:
Town of Erwin, Steuben County, N.Y.
Applications for renewal of
groundwater withdrawals (30-day
averages) of up to 1.700 mgd from Well
4 and 0.634 mgd from Well 6 (Docket
Nos. 19990503 and 20070602,
respectively). Located in an
Environmental Justice area.
Authority: Public Law 91–575, 84
Stat. 1509 et seq., 18 CFR parts 806, 807,
and 808.
Dated: June 17, 2024.
Jason E. Oyler,
General Counsel and Secretary to the
Commission.
[FR Doc. 2024–13652 Filed 6–20–24; 8:45 am]
BILLING CODE 7040–01–P
SUSQUEHANNA RIVER BASIN
COMMISSION
Projects Approved for Consumptive
Uses of Water
Susquehanna River Basin
Commission.
ACTION: Notice.
AGENCY:
This notice lists Approvals by
Rule for projects by the Susquehanna
River Basin Commission during the
period set forth in DATES.
DATES: May 1–31, 2024.
ADDRESSES: Susquehanna River Basin
Commission, 4423 North Front Street,
Harrisburg, PA 17110–1788.
FOR FURTHER INFORMATION CONTACT:
Jason E. Oyler, General Counsel and
Secretary to the Commission, telephone:
(717) 238–0423, ext. 1312; fax: (717)
238–2436; email: joyler@srbc.net.
Regular mail inquiries may be sent to
the above address.
SUPPLEMENTARY INFORMATION: This
notice lists the projects, described
below, receiving approval for the
consumptive use of water pursuant to
the Commission’s approval by rule
process set forth in 18 CFR 806.22(f) for
the time period specified above.
SUMMARY:
Water Source Approval—Issued Under
18 CFR 806.22(f)
1. RENEWAL—Chesapeake
Appalachia, L.L.C.; Pad ID: Herbert
Drilling Pad; ABR–201404001.R2;
Harford and Lenox Townships,
Susquehanna County, Pa.; Consumptive
Use of Up to 7.5000 mgd; Approval
Date: May 6, 2024.
2. Pennsylvania General Energy
Company, L.L.C.; Pad ID: COP Tract 726
Pad F; ABR–202405001; Plunketts Creek
Township, Lycoming County, Pa.;
PO 00000
Frm 00190
Fmt 4703
Sfmt 4703
52199
Consumptive Use of Up to 4.0000 mgd;
Approval Date: May 12, 2024.
3. RENEWAL—Beech Resources, LLC;
Pad ID: Premier Well Site; ABR–
201905002.R1; Lycoming and Old
Lycoming Townships, Lycoming
County, Pa.; Consumptive Use of Up to
3.0000 mgd; Approval Date: May 12,
2024.
4. RENEWAL—Chesapeake
Appalachia, L.L.C.; Pad ID: Freed; ABR–
201204014.R2; Albany Township,
Bradford County, Pa.; Consumptive Use
of Up to 7.5000 mgd; Approval Date:
May 12, 2024.
5. RENEWAL—Chesapeake
Appalachia, L.L.C.; Pad ID: Molly J 2;
ABR–201905001.R1; Monroe Township,
Bradford County, Pa.; Consumptive Use
of Up to 7.5000 mgd; Approval Date:
May 12, 2024.
6. RENEWAL—Chesapeake
Appalachia, L.L.C.; Pad ID: Reilly; ABR–
201204015.R2; Colley Township,
Sullivan County, Pa.; Consumptive Use
of Up to 7.5000 mgd; Approval Date:
May 12, 2024.
7. RENEWAL—Coterra Energy Inc.;
Pad ID: PetersenH P1; ABR–
201205002.R2; Dimock Township,
Susquehanna County, Pa.; Consumptive
Use of Up to 5.0000 mgd; Approval
Date: May 12, 2024.
8. RENEWAL—Seneca Resources
Company, LLC; Pad ID: PHC 4H; ABR–
20090501.R3; Lawrence Township,
Clearfield County, Pa.; Consumptive
Use of Up to 4.0000 mgd; Approval
Date: May 12, 2024.
9. RENEWAL—Seneca Resources
Company, LLC; Pad ID: PHC 5H; ABR–
20090502.R3; Lawrence Township,
Clearfield County, Pa.; Consumptive
Use of Up to 4.0000 mgd; Approval
Date: May 12, 2024.
10. RENEWAL—SWN Production
Company, LLC; Pad ID: Gaylord Pad;
ABR–201204020.R2; Jackson Township,
Susquehanna County, Pa.; Consumptive
Use of Up to 4.9990 mgd; Approval
Date: May 12, 2024.
11. RENEWAL—SWN Production
Company, LLC; Pad ID: Glover Pad;
ABR–201204019.R2; Thompson
Township, Susquehanna County, Pa.;
Consumptive Use of Up to 4.9990 mgd;
Approval Date: May 12, 2024.
12. RENEWAL—SWN Production
Company, LLC; Pad ID: Page Pad; ABR–
201204021.R2; Jackson Township,
Susquehanna County, Pa.; Consumptive
Use of Up to 4.9990 mgd; Approval
Date: May 12, 2024.
13. RENEWAL—SWN Production
Company, LLC; Pad ID: Preston-Perkins;
ABR–201204025.R2; Stevens Township,
Bradford County, Pa.; Consumptive Use
of Up to 4.9990 mgd; Approval Date:
May 12, 2024.
E:\FR\FM\21JNN1.SGM
21JNN1
Agencies
[Federal Register Volume 89, Number 120 (Friday, June 21, 2024)]
[Notices]
[Pages 52198-52199]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-13652]
=======================================================================
-----------------------------------------------------------------------
SUSQUEHANNA RIVER BASIN COMMISSION
Actions Taken at the June 13, 2024 Meeting
AGENCY: Susquehanna River Basin Commission
ACTION: Notice.
-----------------------------------------------------------------------
SUMMARY: As part of its regular business meeting held on June 13, 2024,
in Harrisburg, Pennsylvania, the Commission approved the applications
of certain water resources projects and took additional actions, as set
forth in the Supplementary Information below.
DATES: June 13, 2024.
ADDRESSES: Susquehanna River Basin Commission, 4423 N Front Street,
Harrisburg, PA 17110-1788.
FOR FURTHER INFORMATION CONTACT: Jason E. Oyler, General Counsel and
Secretary, telephone: (717) 238-0423, ext. 1312, fax: (717) 238-2436;
email: [email protected]. Regular mail inquiries may be sent to the above
address. See also the Commission website at www.srbc.gov.
SUPPLEMENTARY INFORMATION: In addition to the actions taken on projects
identified in the summary above, these actions were also taken: (1)
elected Commission officers for FY2025; (2) reconciled and adopted the
FY2025 budget; (3) adopted Policy 2024-01, ``SRBC Procurement
Procedures'', (4) adopted a resolution to allow the Commission to use a
reserve fund as a line of credit, (5) adopted the 2025-2027 Water
Resources Program; and (6) actions on 19 regulatory program projects.
Project Applications Approved
1. Project Sponsor: Berwick Enterprises, Inc. Project Facility: The
Bridges Golf Club, Berwick Township, Adams County, Pa. Application for
renewal of consumptive use of up to 0.249 mgd (30-day average) (Docket
No. 19950102).
2. Project Sponsor and Facility: BKV Operating, LLC (Meshoppen
Creek), Washington Township, Wyoming County, Pa. Application for
renewal of surface water withdrawal of up to 2.160 mgd (peak day)
(Docket No. 20190602).
3. Project Sponsor and Facility: BKV Operating, LLC (Susquehanna
River), Washington Township, Wyoming County, Pa. Application for
renewal of surface water withdrawal of up to 2.914 mgd (peak day)
(Docket No. 20190603).
4. Project Sponsor and Facility: BKV Operating, LLC (unnamed
tributary to Middle Branch Wyalusing Creek), Forest Lake Township,
Susquehanna County, Pa. Application for renewal of surface water
withdrawal of up to 0.648 mgd (peak day) (Docket No. 20190604).
5. Project Sponsor: Byler Golf Management, Inc. Project Facility:
Iron Valley Golf Club, Cornwall Borough, Lebanon County, Pa.
Applications for renewal of consumptive use of up to 0.300 mgd (30-day
average) and groundwater withdrawals (30-day averages) of up to 0.300
mgd from Well Lb-814 and 0.140 mgd from Well B (Docket No. 20200902).
6. Project Sponsor: Cowanesque Valley Recreation Association.
Project Facility: River Valley Country Club, Westfield Township, Tioga
County, Pa. Application for renewal of consumptive use of up to 0.099
mgd (30-day average) (Docket No. 20020602).
7. Project Sponsor and Facility: Dillsburg Area Authority, Carroll
Township, York County, Pa. Application for renewal of groundwater
withdrawal of up to 0.280 mgd (30-day average) from Well 5A (Docket No.
19980703).
8. Project Sponsor and Facility: EQT ARO LLC (Pine Creek), McHenry
Township, Lycoming County, Pa. Application for renewal of surface water
withdrawal of up to 1.500 mgd (peak day) (Docket No. 20190601).
9. Project Sponsor and Facility: Keystone Clearwater Solutions, LLC
(Lycoming Creek), Lewis Township, Lycoming County, Pa. Application for
renewal of surface water withdrawal of up to 1.250 mgd (peak day)
(Docket No. 20190608).
[[Page 52199]]
10. Project Sponsor and Facility: Lear Corporation Pine Grove, Pine
Grove Borough, Schuylkill County, Pa. Application for renewal of
consumptive use of up to 0.160 mgd (30-day average) (Docket No.
19940501).
11. Project Sponsor: Londonderry Township. Project Facility: Sunset
Golf Course, Londonderry Township, Dauphin County, Pa. Application for
renewal of consumptive use of up to 0.181 mgd (30-day average) (Docket
No. 20190613). Located in an Environmental Justice area.
12. Project Sponsor and Facility: Lycoming County Water and Sewer
Authority, Fairfield Township, Lycoming County, Pa. Application for
groundwater withdrawal of up to 0.216 mgd from Well PW-2 (30-day
average).
13. Project Sponsor and Facility: Mount Joy Borough Authority,
Mount Joy Borough, Lancaster County, Pa. Application for renewal of
groundwater withdrawal of up to 1.020 mgd (30-day average) from Well 3
(Docket No. 20070607), and modification of Docket Nos. 20110617,
20110617-1, and 20110617-2 for Wells 1 and 2 by adding conditions
related to Well 3 and proposed operations.
14. Project Sponsor: Pennsylvania--American Water Company. Project
Facility: Philipsburg/Moshannon District, Rush Township, Centre County,
Pa. Applications for renewal of groundwater withdrawals (30-day
averages) of up to 0.600 mgd from Cold Stream Well 1, 0.432 mgd from
Cold Stream Well 2, and 0.374 mgd from Cold Stream Well 3 (Docket No.
19890302).
15. Project Sponsor and Facility: Seneca Resources Company, LLC
(Tioga River), Richmond Township, Tioga County, Pa. Application for
surface water withdrawal of up to 3.000 mgd (peak day).
16. Project Sponsor and Facility: Shippensburg Borough Authority,
Southampton Township, Franklin County, Pa. Application for renewal of
groundwater withdrawal of up to 1.900 mgd from Well 2 (Docket No.
19940504).
17. Project Sponsor and Facility: SWN Production Company, LLC
(North Branch Mehoopany Creek), Forkston Township, Wyoming County, Pa.
Application for surface water withdrawal of up to 2.500 mgd (peak day).
18. Project Sponsor and Facility: Tower City Borough Authority,
Porter Township, Schuylkill County, Pa. Applications for renewal of
groundwater withdrawals (30-day averages) of up to 0.086 mgd from Well
5 and 0.070 mgd from Well 6 (Docket No. 19920301). Located in an
Environmental Justice area.
19. Project Sponsor and Facility: Town of Erwin, Steuben County,
N.Y. Applications for renewal of groundwater withdrawals (30-day
averages) of up to 1.700 mgd from Well 4 and 0.634 mgd from Well 6
(Docket Nos. 19990503 and 20070602, respectively). Located in an
Environmental Justice area.
Authority: Public Law 91-575, 84 Stat. 1509 et seq., 18 CFR parts
806, 807, and 808.
Dated: June 17, 2024.
Jason E. Oyler,
General Counsel and Secretary to the Commission.
[FR Doc. 2024-13652 Filed 6-20-24; 8:45 am]