Colorado Interstate Gas Company, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Totem Enhanced Deliverability Project, 51512 [2024-13401]
Download as PDF
51512
Federal Register / Vol. 89, No. 118 / Tuesday, June 18, 2024 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP24–124–000]
Colorado Interstate Gas Company,
LLC; Notice of Schedule for the
Preparation of an Environmental
Assessment for the Totem Enhanced
Deliverability Project
On April 8, 2024, Colorado Interstate
Gas Company, LLC (CIG) filed an
application in Docket No. CP24–124–
000 requesting a (Certificate of Public
Convenience and Necessity pursuant to
Section 7(c) and Authorization pursuant
to Section 7(b) of the Natural Gas Act to
modify and enhance the existing Totem
natural gas storage field in Adams
County, Colorado. The proposed project
is known as the Totem Enhanced
Deliverability Project (Project).
On April 22, 2024, the Federal Energy
Regulatory Commission (Commission or
FERC) issued its Notice of Application
for the Project. Among other things, that
notice alerted agencies issuing federal
authorizations of the requirement to
complete all necessary reviews and to
reach a final decision on a request for
a federal authorization within 90 days of
the date of issuance of the Commission
staff’s environmental document for the
Project.
This notice identifies Commission
staff’s intention to prepare an
environmental assessment (EA) for the
Project and the planned schedule for the
completion of the environmental
review.1
Schedule for Environmental Review
Issuance of EA November 8, 2024
90-day Federal Authorization Decision
Deadline 2 February 6, 2025
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Project Description
CIG proposes to modify and enhance
the existing Totem natural gas storage
field to increase the maximum
withdrawal rate by about 50 million
standard cubic feet of natural gas per
day and increase both the maximum
lotter on DSK11XQN23PROD with NOTICES1
1 40
CFR 1501.10 (2020)
Commission’s deadline applies to the
decisions of other federal agencies, and state
agencies acting under federally delegated authority,
that are responsible for federal authorizations,
permits, and other approvals necessary for
proposed projects under the Natural Gas Act. Per
18 CFR 157.22(a), the Commission’s deadline for
other agency’s decisions applies unless a schedule
is otherwise established by federal law.
2 The
VerDate Sep<11>2014
17:57 Jun 17, 2024
Jkt 262001
total inventory and base gas capacity of
the field by one billion cubic feet.
The Project would consist of the
following facilities and activities:
• Installation of six new injection/
withdrawal (I/W) wells, each with a
wellhead and meter yard and 0.42
mile of 6-inch-diameter lateral
pipeline to connect the new wells
to gathering lines;
• Conversion of one existing I/W well to
an observation well;
• Along Line 254F–1:
Æ Replacement of 0.62 mile of 8-inchdiameter gathering pipeline with
approximately 0.72 miles of 12inch-diameter gathering pipeline to
connect the Totem Compressor
Station to existing and new I/W
wells;
Æ Replacement of approximately 0.12
mile of existing 6-inch-diameter
pipeline with approximately 0.08
mile of new 4-inch and 6-inchdiameter pipeline to interconnect
with the new segment;
Æ Installation of 7 new tap valves/
lateral tie-ins;
Æ Replacement of the launcher/
receiver facilities;
• Along Line 254–2:
Æ Replacement of approximately 0.28
mile of existing 6-inch and 10inch-diameter pipeline with
approximately 0.26 mile of new 3inch, 4-inch and 6-inch-diameter
pipeline to interconnect;
Æ Installation of 7 new tap valves/
lateral tie-ins;
• Abandonment in place of
approximately 0.4 mile of 3-inch
diameter on Line 254F–7;
• Installation of approximately 0.68
miles of new permanent access road
that will encircle each of the new I/
W wells;
• Piping modifications at the existing
Totem Compressor Station; and
• Injection of approximately 1 billion
cubic feet of additional base gas.
Background
On May 22, 2024, the Commission
issued a Notice of Scoping Period
Requesting Comments on
Environmental Issues for the Proposed
Totem Enhanced Deliverability Project
(Notice of Scoping). The Notice of
Scoping was sent to affected
landowners; federal, state, and local
government agencies; elected officials;
environmental and public interest
groups; Native American tribes; other
interested parties; and local libraries
and newspapers. Although there have
not been any issues raised for the
Project as of the issuance of this notice,
all substantive comments received will
be addressed in the EA.
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
service provides automatic notification
of filings made to subscribed dockets,
document summaries, and direct links
to the documents. Go to https://
www.ferc.gov/ferc-online/overview to
register for eSubscription.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP24–124), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: June 12, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–13401 Filed 6–17–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 298–081]
Southern California Edison Company;
Notice of Availability of Environmental
Assessment
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s (Commission)
regulations, 18 CFR part 380, the Office
E:\FR\FM\18JNN1.SGM
18JNN1
Agencies
[Federal Register Volume 89, Number 118 (Tuesday, June 18, 2024)]
[Notices]
[Page 51512]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-13401]
[[Page 51512]]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP24-124-000]
Colorado Interstate Gas Company, LLC; Notice of Schedule for the
Preparation of an Environmental Assessment for the Totem Enhanced
Deliverability Project
On April 8, 2024, Colorado Interstate Gas Company, LLC (CIG) filed
an application in Docket No. CP24-124-000 requesting a (Certificate of
Public Convenience and Necessity pursuant to Section 7(c) and
Authorization pursuant to Section 7(b) of the Natural Gas Act to modify
and enhance the existing Totem natural gas storage field in Adams
County, Colorado. The proposed project is known as the Totem Enhanced
Deliverability Project (Project).
On April 22, 2024, the Federal Energy Regulatory Commission
(Commission or FERC) issued its Notice of Application for the Project.
Among other things, that notice alerted agencies issuing federal
authorizations of the requirement to complete all necessary reviews and
to reach a final decision on a request for a federal authorization
within 90 days of the date of issuance of the Commission staff's
environmental document for the Project.
This notice identifies Commission staff's intention to prepare an
environmental assessment (EA) for the Project and the planned schedule
for the completion of the environmental review.\1\
---------------------------------------------------------------------------
\1\ 40 CFR 1501.10 (2020)
---------------------------------------------------------------------------
Schedule for Environmental Review
Issuance of EA November 8, 2024
90-day Federal Authorization Decision Deadline \2\ February 6, 2025
---------------------------------------------------------------------------
\2\ The Commission's deadline applies to the decisions of other
federal agencies, and state agencies acting under federally
delegated authority, that are responsible for federal
authorizations, permits, and other approvals necessary for proposed
projects under the Natural Gas Act. Per 18 CFR 157.22(a), the
Commission's deadline for other agency's decisions applies unless a
schedule is otherwise established by federal law.
If a schedule change becomes necessary, additional notice will be
provided so that the relevant agencies are kept informed of the
Project's progress.
Project Description
CIG proposes to modify and enhance the existing Totem natural gas
storage field to increase the maximum withdrawal rate by about 50
million standard cubic feet of natural gas per day and increase both
the maximum total inventory and base gas capacity of the field by one
billion cubic feet.
The Project would consist of the following facilities and
activities:
Installation of six new injection/withdrawal (I/W) wells, each
with a wellhead and meter yard and 0.42 mile of 6-inch-diameter lateral
pipeline to connect the new wells to gathering lines;
Conversion of one existing I/W well to an observation well;
Along Line 254F-1:
[cir] Replacement of 0.62 mile of 8-inch-diameter gathering
pipeline with approximately 0.72 miles of 12-inch-diameter gathering
pipeline to connect the Totem Compressor Station to existing and new I/
W wells;
[cir] Replacement of approximately 0.12 mile of existing 6-inch-
diameter pipeline with approximately 0.08 mile of new 4-inch and 6-
inch-diameter pipeline to interconnect with the new segment;
[cir] Installation of 7 new tap valves/lateral tie-ins;
[cir] Replacement of the launcher/receiver facilities;
Along Line 254-2:
[cir] Replacement of approximately 0.28 mile of existing 6-inch and
10- inch-diameter pipeline with approximately 0.26 mile of new 3-inch,
4-inch and 6-inch-diameter pipeline to interconnect;
[cir] Installation of 7 new tap valves/lateral tie-ins;
Abandonment in place of approximately 0.4 mile of 3-inch
diameter on Line 254F-7;
Installation of approximately 0.68 miles of new permanent
access road that will encircle each of the new I/W wells;
Piping modifications at the existing Totem Compressor Station;
and
Injection of approximately 1 billion cubic feet of additional
base gas.
Background
On May 22, 2024, the Commission issued a Notice of Scoping Period
Requesting Comments on Environmental Issues for the Proposed Totem
Enhanced Deliverability Project (Notice of Scoping). The Notice of
Scoping was sent to affected landowners; federal, state, and local
government agencies; elected officials; environmental and public
interest groups; Native American tribes; other interested parties; and
local libraries and newspapers. Although there have not been any issues
raised for the Project as of the issuance of this notice, all
substantive comments received will be addressed in the EA.
Additional Information
In order to receive notification of the issuance of the EA and to
keep track of formal issuances and submittals in specific dockets, the
Commission offers a free service called eSubscription. This service
provides automatic notification of filings made to subscribed dockets,
document summaries, and direct links to the documents. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
Additional information about the Project is available from the
Commission's Office of External Affairs at (866) 208-FERC or on the
FERC website (www.ferc.gov). Using the ``eLibrary'' link, select
``General Search'' from the eLibrary menu, enter the selected date
range and ``Docket Number'' excluding the last three digits (i.e.,
CP24-124), and follow the instructions. For assistance with access to
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at [email protected]. The eLibrary link on the FERC
website also provides access to the texts of formal documents issued by
the Commission, such as orders, notices, and rule makings.
Dated: June 12, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-13401 Filed 6-17-24; 8:45 am]
BILLING CODE 6717-01-P