Aroostook Power, Inc.; Notice of Application for Non-Capacity Amendment of License Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests, 50322-50323 [2024-12984]

Download as PDF lotter on DSK11XQN23PROD with NOTICES1 50322 Federal Register / Vol. 89, No. 115 / Thursday, June 13, 2024 / Notices Applicants: Scale Microgrid Solutions, LLC. Description: Petition for Declaratory Order of Scale Microgrid Solutions, LLC. Filed Date: 6/5/24. Accession Number: 20240605–5237. Comment Date: 5 p.m. ET 7/5/24. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER24–377–003. Applicants: Devon Energy Production Company, LP. Description: Compliance filing: Amendment to Market Base Rate Filing to be effective 12/26/2023. Filed Date: 6/7/24. Accession Number: 20240607–5072. Comment Date: 5 p.m. ET 6/28/24. Docket Numbers: ER24–377–004. Applicants: Devon Energy Production Company, LP. Description: Compliance filing: Second Amendment to Market Based Rate Filing to be effective 12/26/2023. Filed Date: 6/7/24. Accession Number: 20240607–5107. Comment Date: 5 p.m. ET 6/28/24. Docket Numbers: ER24–2204–000. Applicants: Pacific Gas and Electric Company. Description: 205(d) Rate Filing: Amendment to WAPA Cottonwood and Round Mountain O&M Agreement (RS 242) to be effective 5/8/2024. Filed Date: 6/7/24. Accession Number: 20240607–5000. Comment Date: 5 p.m. ET 6/28/24. Docket Numbers: ER24–2205–000. Applicants: Pacific Gas and Electric Company. Description: 205(d) Rate Filing: Amendment to Port of Stockton (SA 117) to be effective 7/2/2024. Filed Date: 6/7/24. Accession Number: 20240607–5001. Comment Date: 5 p.m. ET 6/28/24. Docket Numbers: ER24–2206–000. Applicants: Southwest Power Pool, Inc. Description: 205(d) Rate Filing: 3949R1 Platteview Solar Interim GIA to be effective 6/4/2024. Filed Date: 6/7/24. Accession Number: 20240607–5036. Comment Date: 5 p.m. ET 6/28/24. Docket Numbers: ER24–2207–000. Applicants: Southwest Power Pool, Inc. Description: 205(d) Rate Filing: 2142R6 Golden Spread Electric Cooperative, Inc. NITSA to be effective 6/1/2024. Filed Date: 6/7/24. Accession Number: 20240607–5037. Comment Date: 5 p.m. ET 6/28/24. VerDate Sep<11>2014 19:28 Jun 12, 2024 Jkt 262001 Docket Numbers: ER24–2208–000. Applicants: Southwest Power Pool, Inc. Description: 205(d) Rate Filing: Revisions to WEIS Tariff Regarding the Market Power Test to be effective 12/31/ 9998. Filed Date: 6/7/24. Accession Number: 20240607–5042. Comment Date: 5 p.m. ET 6/28/24. Docket Numbers: ER24–2209–000. Applicants: Evergy Missouri West, Inc. Description: 205(d) Rate Filing: Notice of Succession to be effective 6/8/2024. Filed Date: 6/7/24. Accession Number: 20240607–5061. Comment Date: 5 p.m. ET 6/28/24. Docket Numbers: ER24–2210–000. Applicants: Dogwood Energy LLC. Description: Tariff Amendment: Notice of Cancellation of Participation Agreement Rate Schedule to be effective 6/8/2024. Filed Date: 6/7/24. Accession Number: 20240607–5070. Comment Date: 5 p.m. ET 6/28/24. Docket Numbers: ER24–2211–000. Applicants: Alabama Power Company, Georgia Power Company, Mississippi Power Company. Description: 205(d) Rate Filing: Alabama Power Company submits tariff filing per 35.13(a)(2)(iii: Granceil Solar LGIA Filing to be effective 5/24/2024. Filed Date: 6/7/24. Accession Number: 20240607–5094. Comment Date: 5 p.m. ET 6/28/24. Docket Numbers: ER24–2212–000. Applicants: Golden Fields Solar IV, LLC. Description: 205(d) Rate Filing: Second Amendment to Amended and Restated Shared Facilities Agreement No. 1 to be effective 6/8/2024. Filed Date: 6/7/24. Accession Number: 20240607–5118. Comment Date: 5 p.m. ET 6/28/24. Docket Numbers: ER24–2213–000. Applicants: Tri-State Generation and Transmission Association, Inc. Description: 205(d) Rate Filing: Initial Filing of Rate Schedule FERC No. 371 to be effective 8/6/2024. Filed Date: 6/7/24. Accession Number: 20240607–5131. Comment Date: 5 p.m. ET 6/28/24. Docket Numbers: ER24–2214–000. Applicants: Golden Fields Solar III, LLC. Description: 205(d) Rate Filing: Certificate of Concurrence to be effective 6/8/2024. Filed Date: 6/7/24. Accession Number: 20240607–5142. Comment Date: 5 p.m. ET 6/28/24. Docket Numbers: ER24–2215–000. PO 00000 Frm 00070 Fmt 4703 Sfmt 4703 Applicants: PJM Interconnection, L.L.C. Description: 205(d) Rate Filing: Original GIA, Service Agreement No. 7256; AE2–139 to be effective 5/8/2024. Filed Date: 6/7/24. Accession Number: 20240607–5145. Comment Date: 5 p.m. ET 6/28/24. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: June 7, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–12987 Filed 6–12–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2367–057] Aroostook Power, Inc.; Notice of Application for Non-Capacity Amendment of License Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed E:\FR\FM\13JNN1.SGM 13JNN1 lotter on DSK11XQN23PROD with NOTICES1 Federal Register / Vol. 89, No. 115 / Thursday, June 13, 2024 / Notices with the Commission and is available for public inspection: a. Application Type: Non-Capacity Amendment of License. b. Project No: 2367–057. c. Date Filed: September 29, 2023, and supplemented on February 2, 2024, and April 16, 2024. d. Applicant: Aroostook Power, Inc. e. Name of Project: Aroostook River Hydroelectric Project. f. Location: The project is located on the Aroostook River and the Millinocket Stream, in Piscataquis and Aroostook counties, Maine. The project does not occupy any Federal lands. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Kevin Quilliam, Aroostook Power, Inc., 326 First Street, Suite 27, Annapolis, MD 21403, (410) 231–3996, kevin.quilliam@ inclimesolutions.com. i. FERC Contact: Maryam Akhavan, (202) 502–6110, maryam.akhavan@ ferc.gov. j. Deadline for filing comments, motions to intervene, and protests: July 8, 2024. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include the docket number P–2367–057. Comments emailed to Commission staff are not considered part of the Commission record. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person whose name appears on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that VerDate Sep<11>2014 19:28 Jun 12, 2024 Jkt 262001 may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Request: Aroostook Power, Inc. (licensee) requests Commission approval to remove the Millinocket Lake Storage Dam Development, including the storage dam and associated lands and facilities, from the license for the Aroostook River Hydroelectric Project No. 2367, which otherwise consists of the Caribou Development. The licensee does not plan to make any physical changes to the project. The Commission is reviewing the Millinocket Lake Storage Dam Development to determine whether it is subject to the Commission’s mandatory licensing jurisdiction under section 23 of the Federal Power Act (FPA). l. Locations of the Application: This filing may be viewed on the Commission’s website at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. Agencies may obtain copies of the application directly from the applicant. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214, respectively. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, PO 00000 Frm 00071 Fmt 4703 Sfmt 4703 50323 and telephone number of the person commenting, protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. Any filing made by an intervenor must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. p. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: June 7, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–12984 Filed 6–12–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Filings Instituting Proceedings Docket Numbers: RP24–829–000. Applicants: Midwestern Gas Transmission Company. Description: 4(d) Rate Filing: Negotiated Rate Agreement—AES Indiana FA1560 to be effective 7/1/ 2024. Filed Date: 6/7/24. Accession Number: 20240607–5076. Comment Date: 5 p.m. ET 6/20/24. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. E:\FR\FM\13JNN1.SGM 13JNN1

Agencies

[Federal Register Volume 89, Number 115 (Thursday, June 13, 2024)]
[Notices]
[Pages 50322-50323]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-12984]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2367-057]


Aroostook Power, Inc.; Notice of Application for Non-Capacity 
Amendment of License Accepted for Filing, Soliciting Comments, Motions 
To Intervene, and Protests

    Take notice that the following hydroelectric application has been 
filed

[[Page 50323]]

with the Commission and is available for public inspection:
    a. Application Type: Non-Capacity Amendment of License.
    b. Project No: 2367-057.
    c. Date Filed: September 29, 2023, and supplemented on February 2, 
2024, and April 16, 2024.
    d. Applicant: Aroostook Power, Inc.
    e. Name of Project: Aroostook River Hydroelectric Project.
    f. Location: The project is located on the Aroostook River and the 
Millinocket Stream, in Piscataquis and Aroostook counties, Maine. The 
project does not occupy any Federal lands.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
    h. Applicant Contact: Kevin Quilliam, Aroostook Power, Inc., 326 
First Street, Suite 27, Annapolis, MD 21403, (410) 231-3996, 
[email protected].
    i. FERC Contact: Maryam Akhavan, (202) 502-6110, 
[email protected].
    j. Deadline for filing comments, motions to intervene, and 
protests: July 8, 2024.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, and protests using the Commission's 
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. 
Commenters can submit brief comments up to 6,000 characters, without 
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. For assistance, please contact FERC Online 
Support at [email protected], (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, you may submit a 
paper copy. Submissions sent via the U.S. Postal Service must be 
addressed to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 
20426. Submissions sent via any other carrier must be addressed to: 
Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory 
Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first 
page of any filing should include the docket number P-2367-057. 
Comments emailed to Commission staff are not considered part of the 
Commission record.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person whose name appears on the official service 
list for the project. Further, if an intervenor files comments or 
documents with the Commission relating to the merits of an issue that 
may affect the responsibilities of a particular resource agency, they 
must also serve a copy of the document on that resource agency.
    k. Description of Request: Aroostook Power, Inc. (licensee) 
requests Commission approval to remove the Millinocket Lake Storage Dam 
Development, including the storage dam and associated lands and 
facilities, from the license for the Aroostook River Hydroelectric 
Project No. 2367, which otherwise consists of the Caribou Development. 
The licensee does not plan to make any physical changes to the project. 
The Commission is reviewing the Millinocket Lake Storage Dam 
Development to determine whether it is subject to the Commission's 
mandatory licensing jurisdiction under section 23 of the Federal Power 
Act (FPA).
    l. Locations of the Application: This filing may be viewed on the 
Commission's website at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. You may also register 
online at https://www.ferc.gov/docs-filing/esubscription.asp to be 
notified via email of new filings and issuances related to this or 
other pending projects. For assistance, call 1-866-208-3676 or email 
[email protected], for TTY, call (202) 502-8659. Agencies may 
obtain copies of the application directly from the applicant.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214, respectively. In determining the appropriate action to take, the 
Commission will consider all protests or other comments filed, but only 
those who file a motion to intervene in accordance with the 
Commission's Rules may become a party to the proceeding. Any comments, 
protests, or motions to intervene must be received on or before the 
specified comment date for the particular application.
    o. Filing and Service of Documents: Any filing must (1) bear in all 
capital letters the title ``COMMENTS'', ``PROTEST'', or ``MOTION TO 
INTERVENE'' as applicable; (2) set forth in the heading the name of the 
applicant and the project number of the application to which the filing 
responds; (3) furnish the name, address, and telephone number of the 
person commenting, protesting or intervening; and (4) otherwise comply 
with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, motions to intervene, or protests must set forth their 
evidentiary basis. Any filing made by an intervenor must be accompanied 
by proof of service on all persons listed in the service list prepared 
by the Commission in this proceeding, in accordance with 18 CFR 
385.2010.
    p. The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].

    Dated: June 7, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-12984 Filed 6-12-24; 8:45 am]
BILLING CODE 6717-01-P