Bangor-Pacific Hydro Associates; Notice of Authorization for Continued Project Operation, 49168 [2024-12755]
Download as PDF
49168
Federal Register / Vol. 89, No. 113 / Tuesday, June 11, 2024 / Notices
Applicants: Cheniere Corpus Christi
Pipeline, LP.
Description: § 4(d) Rate Filing:
Cheniere Corpus Christi EPC Rate
Change to be effective 8/1/2024.
Filed Date: 6/3/24.
Accession Number: 20240603–5149.
Comment Date: 5 p.m. ET 6/17/24.
Docket Numbers: RP24–824–000.
Applicants: Natural Gas Pipeline
Company of America LLC.
Description: § 4(d) Rate Filing:
Negotiated Rate Agreements Filings—
Various Shippers on 06/04/2024 to be
effective 7/1/2024.
Filed Date: 6/4/24.
Accession Number: 20240604–5064.
Comment Date: 5 p.m. ET 6/17/24.
Any person desiring to intervene, to
protest, or to answer a complaint in any
of the above proceedings must file in
accordance with Rules 211, 214, or 206
of the Commission’s Regulations (18
CFR 385.211, 385.214, or 385.206) on or
before 5:00 p.m. Eastern time on the
specified comment date. Protests may be
considered, but intervention is
necessary to become a party to the
proceeding.
khammond on DSKJM1Z7X2PROD with NOTICES
Filings in Existing Proceedings
Docket Numbers: RP24–805–001.
Applicants: Tennessee Gas Pipeline
Company, L.L.C.
Description: Tariff Amendment:
Amendment to Negotiated Rate and
Non-Conforming Agreements Filing to
be effective 7/1/2024.
Filed Date: 6/3/24.
Accession Number: 20240603–5183.
Comment Date: 5 p.m. ET 6/17/24.
Any person desiring to protest in any
the above proceedings must file in
accordance with Rule 211 of the
Commission’s Regulations (18 CFR
385.211) on or before 5:00 p.m. Eastern
time on the specified comment date.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/fercgen
search.asp) by querying the docket
number.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
VerDate Sep<11>2014
17:09 Jun 10, 2024
Jkt 262001
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Dated: June 4, 2024,
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–12680 Filed 6–10–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2600–000]
Bangor-Pacific Hydro Associates;
Notice of Authorization for Continued
Project Operation
The license for the West Enfield
Hydroelectric Project No. 2600 was
issued for a period ending May 31,
2024.
Section 15(a)(1) of the FPA, 16 U.S.C.
808(a)(1), requires the Commission, at
the expiration of a license term, to issue
from year-to-year an annual license to
the then licensee(s) under the terms and
conditions of the prior license until a
new license is issued, or the project is
otherwise disposed of as provided in
section 15 or any other applicable
section of the FPA. If the project’s prior
license waived the applicability of
section 15 of the FPA, then, based on
section 9(b) of the Administrative
Procedure Act, 5 U.S.C. 558(c), and as
set forth at 18 CFR 16.21(a), if the
licensee of such project has filed an
application for a subsequent license, the
licensee may continue to operate the
project in accordance with the terms
and conditions of the license after the
minor or minor part license expires,
until the Commission acts on its
application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 2600
is issued to Bangor-Pacific Hydro
Associates for a period effective June 1,
2024, through May 31, 2025, or until the
issuance of a new license for the project
or other disposition under the FPA,
whichever comes first.
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
If issuance of a new license (or other
disposition) does not take place on or
before May 31, 2025, notice is hereby
given that, pursuant to 18 CFR 16.18(c),
an annual license under section 15(a)(1)
of the FPA is renewed automatically
without further order or notice by the
Commission, unless the Commission
orders otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that Bangor-Pacific Hydro Associates is
authorized to continue operation of the
West Enfield Hydroelectric Project
under the terms and conditions of the
prior license until the issuance of a
subsequent license for the project or
other disposition under the FPA,
whichever comes first.
Dated: June 5, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–12755 Filed 6–10–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 7189–015]
Green Lake Water Power Company;
Notice of Revised Procedural Schedule
for Environmental Assessment for the
Proposed Project Relicense
On March 31, 2022, Green Lake Water
Power Company filed an application for
a subsequent license to continue to
operate and maintain the 424-kilowatt
Green Lake Hydroelectric Project No.
7189 (Green Lake Project). On May 31,
2023, Commission staff issued a notice
of intent to prepare an environmental
assessment (EA) to evaluate the effects
of relicensing the Green Lake Project.
The notice included an anticipated
schedule for issuing the EA. By notice
issued April 11, 2024, the schedule for
completing the EA was revised. The
revised due date for the EA was to be
May 2024.
On May 28, 2024, the Maine
Department of Environmental Protection
filed its Clean Water Act section 401
water quality certification (certification)
for the Green Lake Project with the
Commission. In order for staff to fully
consider the certification, the
procedural schedule for completing the
EA is being revised as follows. Further
revisions to the schedule may be made
as appropriate.
Milestone
Issue EA ....................
E:\FR\FM\11JNN1.SGM
11JNN1
Target date
September 2024.
Agencies
[Federal Register Volume 89, Number 113 (Tuesday, June 11, 2024)]
[Notices]
[Page 49168]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-12755]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2600-000]
Bangor-Pacific Hydro Associates; Notice of Authorization for
Continued Project Operation
The license for the West Enfield Hydroelectric Project No. 2600 was
issued for a period ending May 31, 2024.
Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the
Commission, at the expiration of a license term, to issue from year-to-
year an annual license to the then licensee(s) under the terms and
conditions of the prior license until a new license is issued, or the
project is otherwise disposed of as provided in section 15 or any other
applicable section of the FPA. If the project's prior license waived
the applicability of section 15 of the FPA, then, based on section 9(b)
of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth
at 18 CFR 16.21(a), if the licensee of such project has filed an
application for a subsequent license, the licensee may continue to
operate the project in accordance with the terms and conditions of the
license after the minor or minor part license expires, until the
Commission acts on its application. If the licensee of such a project
has not filed an application for a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b), to continue project operations
until the Commission issues someone else a license for the project or
otherwise orders disposition of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 2600 is issued to
Bangor-Pacific Hydro Associates for a period effective June 1, 2024,
through May 31, 2025, or until the issuance of a new license for the
project or other disposition under the FPA, whichever comes first.
If issuance of a new license (or other disposition) does not take
place on or before May 31, 2025, notice is hereby given that, pursuant
to 18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA
is renewed automatically without further order or notice by the
Commission, unless the Commission orders otherwise.
If the project is not subject to section 15 of the FPA, notice is
hereby given that Bangor-Pacific Hydro Associates is authorized to
continue operation of the West Enfield Hydroelectric Project under the
terms and conditions of the prior license until the issuance of a
subsequent license for the project or other disposition under the FPA,
whichever comes first.
Dated: June 5, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-12755 Filed 6-10-24; 8:45 am]