Application for Authorization To Export Electric Energy; ATNV Energy, LP, 47936-47937 [2024-12189]

Download as PDF 47936 Federal Register / Vol. 89, No. 108 / Tuesday, June 4, 2024 / Notices Specifically, through the advanced search feature at this site, you can limit your search to documents published by the Department. Richard J. Lucas, Principal Deputy Assistant Secretary, Delegated the Authority to Perform the Duties and Functions of the Office of Finance and Operations Assistant Secretary. [FR Doc. 2024–12190 Filed 6–3–24; 8:45 am] BILLING CODE 4000–01–P DEPARTMENT OF ENERGY [GDO Docket No. EA–510] Application for Authorization To Export Electric Energy; MFT Energy US Power LLC Grid Deployment Office, Department of Energy. ACTION: Notice of application. AGENCY: MFT Energy US Power LLC (the Applicant) has applied for authorization to transmit electric energy from the United States to Mexico pursuant to the Federal Power Act. DATES: Comments, protests, or motions to intervene must be submitted on or before July 5, 2024. ADDRESSES: Comments, protests, motions to intervene, or requests for more information should be addressed by electronic mail to Electricity.Exports@hq.doe.gov. FOR FURTHER INFORMATION CONTACT: Janessa Zucchetto, (240) 474–8226, Electricity.Exports@hq.doe.gov. SUPPLEMENTARY INFORMATION: The United States Department of Energy (DOE) regulates electricity exports from the United States to foreign countries in accordance with section 202(e) of the Federal Power Act (FPA) (16 U.S.C. 824a(e)) and regulations thereunder (10 CFR 205.300 et seq.). Sections 301(b) and 402(f) of the DOE Organization Act (42 U.S.C. 7151(b) and 7172(f)) transferred this regulatory authority, previously exercised by the nowdefunct Federal Power Commission, to DOE. Section 202(e) of the FPA provides that an entity which seeks to export electricity must obtain an order from DOE authorizing that export (16 U.S.C. 824a(e)). On April 10, 2023, the authority to issue such orders was delegated to the DOE’s Grid Deployment Office (GDO) by Delegation Order No. S1–DEL–S3–2023 and Redelegation Order No. S3–DEL–GD1–2023. On April 9, 2024, MFT Energy US Power LLC filed an application (Application or App.) with DOE to ddrumheller on DSK120RN23PROD with NOTICES1 SUMMARY: VerDate Sep<11>2014 17:15 Jun 03, 2024 Jkt 262001 transmit electric energy from the United States to Mexico for a ten-year term. App. at 1. According to the Application, MFT Energy US Power LLC ‘‘is a limited liability company organized under the laws of the state of Delaware’’ with its principal place of business in Chicago, Illinois. Id. The Applicant states that it ‘‘does not own or control any electric power generation or transmission facilities and does not have a franchised electric power service area.’’ Id. Further, MFT Energy US Power LLC represents that it ‘‘operates as a power marketer’’ and holds market-based rate authority provided by the Federal Energy Regulatory Commission (FERC). Id. at 1–2. The Applicant states it ‘‘will purchase surplus electric energy from entities within the United States to be exported to Mexico.’’ Id. at 4. Because the electric energy proposed to be exported will be surplus, the Applicant asserts its exports ‘‘will not impair the sufficiency of electric supply within the United States.’’ Id. Further, the Applicant states that ‘‘all electricity exported by Applicant will be transmitted pursuant to arrangements with utilities that own and operate existing transmission facilities and will be consistent with all applicable export limits on those transmitting facilities and with other terms and conditions contained in the applicable Presidential Permits.’’ App. at 5. Therefore, the Applicant asserts its exports will not impede the regional coordination of the electric grid. Id. The existing international transmission facilities to be utilized by the Applicant have been previously authorized by Presidential permits issued pursuant to Executive Order 10485, as amended, and are appropriate for open access transmission by third parties. See App. at Exhibit C. Procedural Matters: Any person desiring to be heard in this proceeding should file a comment or protest to the Application at Electricity.Exports@ hq.doe.gov. Protests should be filed in accordance with Rule 211 of Federal Energy Regulatory Commission’s (FERC’s) Rules of Practice and Procedure (18 CFR 385.211). Any person desiring to become a party to this proceeding should file a motion to intervene at Electricity.Exports@ hq.doe.gov in accordance with FERC Rule 214 (18 CFR 385.214). Comments and other filings concerning MFT Energy US Power LLC’s Application should be clearly marked with GDO Docket No. EA–510. Additional copies are to be provided directly to Simon Fisker Rathjen, MFT Energy US Power LLC, 70 W Madison PO 00000 Frm 00045 Fmt 4703 Sfmt 4703 Street, Chicago, Illinois 60602, sr@mftenergy.com and uspower@mftenergy.com; James C. Beh, Jones Day, 51 Louisiana Ave. NW, Washington, DC 20001, jcbeh@jonesday.com; and Brooke M. Proto, Jones Day, 51 Louisiana Ave. NW, Washington, DC 20001, bmproto@ jonesday.com. A final decision will be made on the requested authorization after the environmental impacts have been evaluated pursuant to DOE’s National Environmental Policy Act Implementing Procedures (10 CFR part 1021) and after DOE evaluates whether the proposed action will have an adverse impact on the sufficiency of supply or reliability of the United States electric power supply system. Copies of this Application will be made available, upon request, by accessing the program website at https://www.energy.gov/gdo/pendingapplications-0 or by emailing Electricity.Exports@hq.doe.gov. Signing Authority: This document of the Department of Energy was signed on May 29, 2024, by Maria Robinson, Director, Grid Deployment Office, pursuant to delegated authority from the Secretary of Energy. That document with the original signature and date is maintained by DOE. For administrative purposes only, and in compliance with requirements of the Office of the Federal Register, the undersigned DOE Federal Register Liaison Officer has been authorized to sign and submit the document in electronic format for publication, as an official document of the Department of Energy. This administrative process in no way alters the legal effect of this document upon publication in the Federal Register. Signed in Washington, DC, on May 30, 2024. Treena V. Garrett, Federal Register Liaison Officer, U.S. Department of Energy. [FR Doc. 2024–12186 Filed 6–3–24; 8:45 am] BILLING CODE 6450–01–P DEPARTMENT OF ENERGY [GDO Docket No. EA–512] Application for Authorization To Export Electric Energy; ATNV Energy, LP Grid Deployment Office, Department of Energy. ACTION: Notice of application. AGENCY: ATNV Energy, LP (the Applicant) has applied for authorization to transmit electric energy from the United States to Mexico pursuant to the Federal Power Act. SUMMARY: E:\FR\FM\04JNN1.SGM 04JNN1 Federal Register / Vol. 89, No. 108 / Tuesday, June 4, 2024 / Notices Comments, protests, or motions to intervene must be submitted on or before July 5, 2024. ADDRESSES: Comments, protests, motions to intervene, or requests for more information should be addressed by electronic mail to Electricity.Exports@hq.doe.gov. FOR FURTHER INFORMATION CONTACT: Janessa Zucchetto, (240) 474–8226, Electricity.Exports@hq.doe.gov. SUPPLEMENTARY INFORMATION: The United States Department of Energy (DOE) regulates electricity exports from the United States to foreign countries in accordance with section 202(e) of the Federal Power Act (FPA) (16 U.S.C. 824a(e)) and regulations thereunder (10 CFR 205.300 et seq.). Sections 301(b) and 402(f) of the DOE Organization Act (42 U.S.C. 7151(b) and 7172(f)) transferred this regulatory authority, previously exercised by the nowdefunct Federal Power Commission, to DOE. Section 202(e) of the FPA provides that an entity which seeks to export electricity must obtain an order from DOE authorizing that export (16 U.S.C. 824a(e)). On April 10, 2023, the authority to issue such orders was delegated to the DOE’s Grid Deployment Office (GDO) under Delegation Order No. S1–DEL–S3–2023 and Redelegation Order No. S3–DEL–GD1–2023. On April 11, 2024, ATNV Energy, LP filed an application (Application or App.) with DOE to transmit electric energy from the United States to Mexico for a five-year term. App. at 1. According to the Application, ATNV Energy, LP is ‘‘a Delaware limited partnership with its principal place of business in Houston, Texas.’’ Id. ATNV Energy, LP states it is a ‘‘power marketer that does not own or operate a transmission system,’’ and its owners do not own or control an interest in any electric generation, transmission, or distribution facilities. Id. at 1, 4. The Applicant represents that it is ‘‘authorized to sell wholesale energy, capacity, and ancillary services at market-based rates’’ and is subject to the Federal Energy Regulatory Commission’s jurisdiction. Id. at 2. ATNV Energy, LLP states it ‘‘will purchase the electric power to be exported in the markets in which it participates, on a firm or interruptible basis,’’ and ‘‘[a]ny power purchased by the Applicant for export would be surplus to the needs of those entities selling power to the Applicant.’’ Id. at 3–4. The Applicant also asserts its exports will comply with all North American Electric Reliability Corporation requirements and exports ddrumheller on DSK120RN23PROD with NOTICES1 DATES: VerDate Sep<11>2014 17:15 Jun 03, 2024 Jkt 262001 limits imposed by DOE. Id. at 4. For these reasons, the Applicant contends that its exports ‘‘will not impair or tend to impede the sufficiency of electric supply in the United States or the regional coordination of electric utility planning or operations.’’ Id. at 5. The existing international transmission facilities to be utilized by the Applicant have been previously authorized by Presidential permits issued pursuant to Executive Order 10485, as amended, and are appropriate for open access transmission by third parties. See App. at Attachment 1. Procedural Matters: Any person desiring to be heard in this proceeding should file a comment or protest to the Application at the email address provided previously. Protests should be filed in accordance with Rule 211 of FERC’s Rules of Practice and Procedure (18 CFR 385.211). Any person desiring to become a party to this proceeding should file a motion to intervene at the previously provided email address in accordance with FERC Rule 214 (18 CFR 385.214). Comments and other filings concerning ATNV Energy, LP’s Application should be clearly marked with GDO Docket No. EA–512. Additional copies are to be provided directly to Kolby Kettler, ATNV Energy, LP, 1321 Upland Dr., Ste. 2100, Houston, TX 77043, kolby@ atnvenergy.com; Sarah Tucker, Sidley Austin LLP, 1501 K Street NW, Washington, DC 20005, stucker@ sidley.com; and Keturah Brown, Sidley Austin LLP, 1501 K Street, NW, Washington, DC 20005, keturah.brown@ sidley.com. A final decision will be made on the requested authorization after the environmental impacts have been evaluated pursuant to DOE’s National Environmental Policy Act Implementing Procedures (10 CFR part 1021) and after DOE evaluates whether the proposed action will have an adverse impact on the sufficiency of supply or reliability of the United States electric power supply system. Copies of this Application will be made available, upon request, by accessing the program website at https://www.energy.gov/gdo/pendingapplications-0 or by emailing Electricity.Exports@hq.doe.gov. Signing Authority: This document of the Department of Energy was signed on May 29, 2024, by Maria Robinson, Director, Grid Deployment Office, pursuant to delegated authority from the Secretary of Energy. That document with the original signature and date is maintained by DOE. For administrative purposes only, and in compliance with PO 00000 Frm 00046 Fmt 4703 Sfmt 4703 47937 requirements of the Office of the Federal Register, the undersigned DOE Federal Register Liaison Officer has been authorized to sign and submit the document in electronic format for publication, as an official document of the Department of Energy. This administrative process in no way alters the legal effect of this document upon publication in the Federal Register. Signed in Washington, DC, on May 30, 2024. Treena V. Garrett, Federal Register Liaison Officer, U.S. Department of Energy. [FR Doc. 2024–12189 Filed 6–3–24; 8:45 am] BILLING CODE 6450–01–P DEPARTMENT OF ENERGY [GDO Docket No. EA–511] Application for Authorization To Export Electric Energy; ATNV Energy, LP Grid Deployment Office, Department of Energy. ACTION: Notice of application. AGENCY: ATNV Energy, LP (the Applicant) has applied for authorization to transmit electric energy from the United States to Canada pursuant to the Federal Power Act. DATES: Comments, protests, or motions to intervene must be submitted on or before July 5, 2024. ADDRESSES: Comments, protests, motions to intervene, or requests for more information should be addressed by electronic mail to Electricity.Exports@hq.doe.gov. FOR FURTHER INFORMATION CONTACT: Janessa Zucchetto, (240) 474–8226, Electricity.Exports@hq.doe.gov. SUPPLEMENTARY INFORMATION: The United States Department of Energy (DOE) regulates electricity exports from the United States to foreign countries in accordance with section 202(e) of the Federal Power Act (FPA) (16 U.S.C. 824a(e)) and regulations thereunder (10 CFR 205.300 et seq.). Sections 301(b) and 402(f) of the DOE Organization Act (42 U.S.C. 7151(b) and 7172(f)) transferred this regulatory authority, previously exercised by the nowdefunct Federal Power Commission, to DOE. Section 202(e) of the FPA provides that an entity which seeks to export electricity must obtain an order from DOE authorizing that export (16 U.S.C. 824a(e)). On April 10, 2023, the authority to issue such orders was delegated to the DOE’s Grid Deployment Office (GDO) under Delegation Order SUMMARY: E:\FR\FM\04JNN1.SGM 04JNN1

Agencies

[Federal Register Volume 89, Number 108 (Tuesday, June 4, 2024)]
[Notices]
[Pages 47936-47937]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-12189]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

[GDO Docket No. EA-512]


Application for Authorization To Export Electric Energy; ATNV 
Energy, LP

AGENCY: Grid Deployment Office, Department of Energy.

ACTION: Notice of application.

-----------------------------------------------------------------------

SUMMARY: ATNV Energy, LP (the Applicant) has applied for authorization 
to transmit electric energy from the United States to Mexico pursuant 
to the Federal Power Act.

[[Page 47937]]


DATES: Comments, protests, or motions to intervene must be submitted on 
or before July 5, 2024.

ADDRESSES: Comments, protests, motions to intervene, or requests for 
more information should be addressed by electronic mail to 
[email protected].

FOR FURTHER INFORMATION CONTACT: Janessa Zucchetto, (240) 474-8226, 
[email protected].

SUPPLEMENTARY INFORMATION: The United States Department of Energy (DOE) 
regulates electricity exports from the United States to foreign 
countries in accordance with section 202(e) of the Federal Power Act 
(FPA) (16 U.S.C. 824a(e)) and regulations thereunder (10 CFR 205.300 et 
seq.). Sections 301(b) and 402(f) of the DOE Organization Act (42 
U.S.C. 7151(b) and 7172(f)) transferred this regulatory authority, 
previously exercised by the now-defunct Federal Power Commission, to 
DOE.
    Section 202(e) of the FPA provides that an entity which seeks to 
export electricity must obtain an order from DOE authorizing that 
export (16 U.S.C. 824a(e)). On April 10, 2023, the authority to issue 
such orders was delegated to the DOE's Grid Deployment Office (GDO) 
under Delegation Order No. S1-DEL-S3-2023 and Redelegation Order No. 
S3-DEL-GD1-2023.
    On April 11, 2024, ATNV Energy, LP filed an application 
(Application or App.) with DOE to transmit electric energy from the 
United States to Mexico for a five-year term. App. at 1.
    According to the Application, ATNV Energy, LP is ``a Delaware 
limited partnership with its principal place of business in Houston, 
Texas.'' Id. ATNV Energy, LP states it is a ``power marketer that does 
not own or operate a transmission system,'' and its owners do not own 
or control an interest in any electric generation, transmission, or 
distribution facilities. Id. at 1, 4. The Applicant represents that it 
is ``authorized to sell wholesale energy, capacity, and ancillary 
services at market-based rates'' and is subject to the Federal Energy 
Regulatory Commission's jurisdiction. Id. at 2.
    ATNV Energy, LLP states it ``will purchase the electric power to be 
exported in the markets in which it participates, on a firm or 
interruptible basis,'' and ``[a]ny power purchased by the Applicant for 
export would be surplus to the needs of those entities selling power to 
the Applicant.'' Id. at 3-4. The Applicant also asserts its exports 
will comply with all North American Electric Reliability Corporation 
requirements and exports limits imposed by DOE. Id. at 4. For these 
reasons, the Applicant contends that its exports ``will not impair or 
tend to impede the sufficiency of electric supply in the United States 
or the regional coordination of electric utility planning or 
operations.'' Id. at 5.
    The existing international transmission facilities to be utilized 
by the Applicant have been previously authorized by Presidential 
permits issued pursuant to Executive Order 10485, as amended, and are 
appropriate for open access transmission by third parties. See App. at 
Attachment 1.
    Procedural Matters: Any person desiring to be heard in this 
proceeding should file a comment or protest to the Application at the 
email address provided previously. Protests should be filed in 
accordance with Rule 211 of FERC's Rules of Practice and Procedure (18 
CFR 385.211). Any person desiring to become a party to this proceeding 
should file a motion to intervene at the previously provided email 
address in accordance with FERC Rule 214 (18 CFR 385.214).
    Comments and other filings concerning ATNV Energy, LP's Application 
should be clearly marked with GDO Docket No. EA-512. Additional copies 
are to be provided directly to Kolby Kettler, ATNV Energy, LP, 1321 
Upland Dr., Ste. 2100, Houston, TX 77043, [email protected]; Sarah 
Tucker, Sidley Austin LLP, 1501 K Street NW, Washington, DC 20005, 
[email protected]; and Keturah Brown, Sidley Austin LLP, 1501 K 
Street, NW, Washington, DC 20005, [email protected].
    A final decision will be made on the requested authorization after 
the environmental impacts have been evaluated pursuant to DOE's 
National Environmental Policy Act Implementing Procedures (10 CFR part 
1021) and after DOE evaluates whether the proposed action will have an 
adverse impact on the sufficiency of supply or reliability of the 
United States electric power supply system.
    Copies of this Application will be made available, upon request, by 
accessing the program website at https://www.energy.gov/gdo/pending-applications-0 or by emailing [email protected].
    Signing Authority: This document of the Department of Energy was 
signed on May 29, 2024, by Maria Robinson, Director, Grid Deployment 
Office, pursuant to delegated authority from the Secretary of Energy. 
That document with the original signature and date is maintained by 
DOE. For administrative purposes only, and in compliance with 
requirements of the Office of the Federal Register, the undersigned DOE 
Federal Register Liaison Officer has been authorized to sign and submit 
the document in electronic format for publication, as an official 
document of the Department of Energy. This administrative process in no 
way alters the legal effect of this document upon publication in the 
Federal Register.

    Signed in Washington, DC, on May 30, 2024.
Treena V. Garrett,
Federal Register Liaison Officer, U.S. Department of Energy.
[FR Doc. 2024-12189 Filed 6-3-24; 8:45 am]
BILLING CODE 6450-01-P