Twentymile Pumped Storage, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 47151-47152 [2024-11995]
Download as PDF
Federal Register / Vol. 89, No. 106 / Friday, May 31, 2024 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
khammond on DSKJM1Z7X2PROD with NOTICES
Combined Notice of Filings #1
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG24–188–000.
Applicants: Timbermill Wind, LLC.
Description: Timbermill Wind, LLC
submits Notice of Self-Certification of
Exempt Wholesale Generator Status.
Filed Date: 5/24/24.
Accession Number: 20240524–5109.
Comment Date: 5 p.m. ET 6/14/24.
Docket Numbers: EG24–189–000.
Applicants: Prosperity Wind, LLC.
Description: Prosperity Wind, LLC
submits Notice of Self-Certification of
Exempt Wholesale Generator Status.
Filed Date: 5/24/24.
Accession Number: 20240524–5110.
Comment Date: 5 p.m. ET 6/14/24.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER20–1298–007.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: Compliance filing: 2024–
05–24_MISO TO’s Order 864
Compliance RE NIPSCO to be effective
1/27/2020.
Filed Date: 5/24/24.
Accession Number: 20240524–5056.
Comment Date: 5 p.m. ET 6/14/24.
Docket Numbers: ER23–1851–007.
Applicants: PJM Interconnection,
L.L.C.
Description: Tariff Amendment:
Status Report—Amended ISA–CSA, SA
Nos. 6917–6918; Queue No. AD1–031 to
be effective 10/26/2023.
Filed Date: 5/24/24.
Accession Number: 20240524–5098.
Comment Date: 5 p.m. ET 6/14/24.
Docket Numbers: ER23–2359–007.
Applicants: PJM Interconnection,
L.L.C.
Description: Tariff Amendment:
Amendment to ISA/CSA SA Nos. 6967
& 6968; AD2–100/131—Docket ER23–
2359 to be effective 9/6/2023.
Filed Date: 5/24/24.
Accession Number: 20240524–5105.
Comment Date: 5 p.m. ET 6/14/24.
Docket Numbers: ER24–1316–001.
Applicants: Duke Energy Carolinas,
LLC.
Description: Tariff Amendment:
DEC—Response to Deficiency Letter to
be effective 5/1/2024.
Filed Date: 5/23/24.
Accession Number: 20240523–5221.
Comment Date: 5 p.m. ET 6/13/24.
VerDate Sep<11>2014
17:22 May 30, 2024
Jkt 262001
Docket Numbers: ER24–2092–000.
Applicants: Public Service Company
of New Hampshire.
Description: 205(d) Rate Filing: Two
Party Small Generator IA Brookfield
White Pine Hydro LLC to be effective 5/
24/2024.
Filed Date: 5/23/24.
Accession Number: 20240523–5213.
Comment Date: 5 p.m. ET 6/13/24.
Docket Numbers: ER24–2093–000.
Applicants: PJM Interconnection,
L.L.C.
Description: 205(d) Rate Filing:
Designated Entity Agreement, SA No.
7236 between PJM and BGE to be
effective 4/25/2024.
Filed Date: 5/24/24.
Accession Number: 20240524–5063.
Comment Date: 5 p.m. ET 6/14/24.
Docket Numbers: ER24–2094–000.
Applicants: PJM Interconnection,
L.L.C.
Description: 205(d) Rate Filing:
Designated Entity Agreement, SA No.
7237 between PJM and ACE to be
effective 4/25/2024.
Filed Date: 5/24/24.
Accession Number: 20240524–5065.
Comment Date: 5 p.m. ET 6/14/24.
Docket Numbers: ER24–2095–000.
Applicants: Niagara Mohawk Power
Corporation, New York Independent
System Operator, Inc.
Description: 205(d) Rate Filing:
Niagara Mohawk Power Corporation
submits tariff filing per 35.13(a)(2)(iii:
NMPC 205: Amended Interconnection
Agreement between NMPC, Empire
Power (SA333) to be effective 5/25/
2024.
Filed Date: 5/24/24.
Accession Number: 20240524–5087.
Comment Date: 5 p.m. ET 6/14/24.
Docket Numbers: ER24–2096–000.
Applicants: New York Independent
System Operator, Inc.
Description: 205(d) Rate Filing:
NYISO 205: Modeling Improvements for
Capacity Accreditation to be effective 7/
24/2024.
Filed Date: 5/24/24.
Accession Number: 20240524–5102.
Comment Date: 5 p.m. ET 6/14/24.
Docket Numbers: ER24–2097–000.
Applicants: NextEra Energy Seabrook,
LLC.
Description: 205(d) Rate Filing:
Construction Services Agreement NEES
& NECEC to be effective 5/25/2024.
Filed Date: 5/24/24.
Accession Number: 20240524–5104.
Comment Date: 5 p.m. ET 6/14/24.
Docket Numbers: ER24–2098–000.
Applicants: Pacific Gas and Electric
Company.
Description: 205(d) Rate Filing: May
2024 Western WDT Service Agreement
PO 00000
Frm 00031
Fmt 4703
Sfmt 4703
47151
Biannual Filing (SA 17) to be effective
8/1/2024.
Filed Date: 5/24/24.
Accession Number: 20240524–5128.
Comment Date: 5 p.m. ET 6/14/24.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/fercgen
search.asp) by querying the docket
number.
Any person desiring to intervene, to
protest, or to answer a complaint in any
of the above proceedings must file in
accordance with Rules 211, 214, or 206
of the Commission’s Regulations (18
CFR 385.211, 385.214, or 385.206) on or
before 5:00 p.m. Eastern time on the
specified comment date. Protests may be
considered, but intervention is
necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Dated: May 24, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–12000 Filed 5–30–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 15305–000]
Twentymile Pumped Storage, LLC;
Notice of Preliminary Permit
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Competing Applications
On March 10, 2023, Twentymile
Pumped Storage, LLC, filed an
application for a preliminary permit,
pursuant to section 4(f) of the Federal
Power Act (FPA), proposing to study the
E:\FR\FM\31MYN1.SGM
31MYN1
khammond on DSKJM1Z7X2PROD with NOTICES
47152
Federal Register / Vol. 89, No. 106 / Friday, May 31, 2024 / Notices
feasibility of the Twentymile Pumped
Storage Project to be located near the
town of Oak Creek in Routt County,
Colorado. The sole purpose of a
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project will have an
above ground upper reservoir and an
underground lower reservoir. A net
hydraulic head of approximately 1,300
feet is expected between the maximum
water level in the upper reservoir and
minimum water level in the
underground lower reservoir. Initial
filling of the upper reservoir will use
existing available water located
currently in the mine. The existing
sealed voids of tunnels and galleries at
mine sites will become the lower
reservoir. The upper surface reservoir
will have a surface elevation of
approximately 7,600 feet msl and will
be connected to the lower reservoir via
an underground water conveyance
system-penstock, access shafts and
tunnels, and ventilation shafts, with a
new underground powerhouse
containing reversible pump-turbine
generator units. The single penstock
would be 16 feet in diameter that
bifurcates to two units in the
powerhouse.
The approximate storage volume of
the upper reservoir will be
approximately 1,550 acre-feet. The
lower reservoir would have a surface
elevation of 6,000 feet msl with a
storage volume of approximately 1,550
acre-feet. A new, approximately 1.8mile long 230-kilovolt (kV) overhead
interconnection line will extend from
the powerhouse to a substation. The
powerhouse would contain two turbines
and generators, with a generating
capacity of 250 megawatts (MW) based
on available hydraulic head and water
to fill the reservoirs. Each turbine is
rated for 133 MW, and each generator is
rated for 125 MW. The estimated
average annual generation is 547,500
MWh.
Applicant Contact: Ushakar Jha,
Twentymile Pumped Storage, LLC, 100
S Olive St., West Palm Beach, Florida
33401; email: ushakar@
ryedevelopment.com; phone: (503) 309–
2496.
FERC Contact: Lee Baker; email:
everard.baker@ferc.gov; phone: (202)
502–8554.
Deadline for filing comments, motions
to intervene, competing applications
VerDate Sep<11>2014
17:22 May 30, 2024
Jkt 262001
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
ferconline.ferc.gov/eFiling.aspx.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://ferconline.ferc.gov/
QuickComment.aspx. You must include
your name and contact information at
the end of your comments. For
assistance, please contact FERC Online
Support. In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Debbie-Anne A. Reese,
Acting Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Debbie-Anne A.
Reese, Acting Secretary, Federal Energy
Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852.
The first page of any filing should
include docket number P–15305–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of the Commission’s website at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–15305) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Dated: May 24, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–11995 Filed 5–30–24; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[FRL OP–OFA–128]
Environmental Impact Statements;
Notice of Availability
Responsible Agency: Office of Federal
Activities, General Information 202–
564–5632 or https://www.epa.gov/nepa.
Weekly receipt of Environmental Impact
Statements (EIS)
Filed May 20, 2024 10 a.m. EST
Through May 24, 2024 10 a.m. EST
Pursuant to 40 CFR 1506.9.
Notice: Section 309(a) of the Clean Air
Act requires that EPA make public its
comments on EISs issued by other
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
Federal agencies. EPA’s comment letters
on EISs are available at: https://
cdxapps.epa.gov/cdx-enepa-II/public/
action/eis/search.
EIS No. 20240090, Final Supplement,
BR, UT, Glen Canyon Dam Long-Term
Experimental and Management Plan,
Review Period Ends: 07/01/2024,
Contact: Wayne Pullan 801–524–
3600.
EIS No. 20240091, Final, BOEM, NJ,
Atlantic Shores Offshore Wind South,
Review Period Ends: 07/01/2024,
Contact: Kimberly Sullivan 702–338–
4766.
EIS No. 20240092, Draft, FERC, TN,
Ridgeline Expansion Project,
Comment Period Ends: 07/15/2024,
Contact: Office of External Affairs
866–208–3372.
Dated: May 24, 2024.
Cindy S. Barger,
Director, NEPA Compliance Division, Office
of Federal Activities.
[FR Doc. 2024–11965 Filed 5–30–24; 8:45 am]
BILLING CODE 6560–50–P
ENVIRONMENTAL PROTECTION
AGENCY
[Petitions IV–2024–1; FRL–11985–01–R4]
Clean Air Act Operating Permit
Program; Order on Petition for
Objection to State Operating Permit for
DCP Operating Company L.P. (Mobile
County, Alabama)
Environmental Protection
Agency (EPA).
ACTION: Notice of final order on petition.
AGENCY:
The EPA Administrator
signed an order dated May 10, 2024,
granting in part and denying in part the
petition dated January 8, 2024, from
Mobile Environmental Justice Action
Coalition and GASP. The petition
requested that EPA object to Clean Air
Act (CAA) title V operating permit
issued by the Alabama Department of
Environmental Management (ADEM) to
DCP Operating Company L.P. for its
natural gas treatment and processing
facility located in Mobile Bay, Mobile
County, Alabama.
FOR FURTHER INFORMATION CONTACT: Art
Hofmeister, Air Permits Section, EPA
Region 4, (404) 562–9115,
hofmeister.art@epa.gov. The final order
and petitions are available at: https://
www.epa.gov/title-v-operating-permits/
title-v-petition-database.
SUPPLEMENTARY INFORMATION: EPA
received a petition from Mobile
Environmental Justice Action Coalition
and GASP dated January 8, 2024,
requesting that EPA object to the
SUMMARY:
E:\FR\FM\31MYN1.SGM
31MYN1
Agencies
[Federal Register Volume 89, Number 106 (Friday, May 31, 2024)]
[Notices]
[Pages 47151-47152]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-11995]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 15305-000]
Twentymile Pumped Storage, LLC; Notice of Preliminary Permit
Application Accepted for Filing and Soliciting Comments, Motions To
Intervene, and Competing Applications
On March 10, 2023, Twentymile Pumped Storage, LLC, filed an
application for a preliminary permit, pursuant to section 4(f) of the
Federal Power Act (FPA), proposing to study the
[[Page 47152]]
feasibility of the Twentymile Pumped Storage Project to be located near
the town of Oak Creek in Routt County, Colorado. The sole purpose of a
preliminary permit, if issued, is to grant the permit holder priority
to file a license application during the permit term. A preliminary
permit does not authorize the permit holder to perform any land-
disturbing activities or otherwise enter upon lands or waters owned by
others without the owners' express permission.
The proposed project will have an above ground upper reservoir and
an underground lower reservoir. A net hydraulic head of approximately
1,300 feet is expected between the maximum water level in the upper
reservoir and minimum water level in the underground lower reservoir.
Initial filling of the upper reservoir will use existing available
water located currently in the mine. The existing sealed voids of
tunnels and galleries at mine sites will become the lower reservoir.
The upper surface reservoir will have a surface elevation of
approximately 7,600 feet msl and will be connected to the lower
reservoir via an underground water conveyance system-penstock, access
shafts and tunnels, and ventilation shafts, with a new underground
powerhouse containing reversible pump-turbine generator units. The
single penstock would be 16 feet in diameter that bifurcates to two
units in the powerhouse.
The approximate storage volume of the upper reservoir will be
approximately 1,550 acre-feet. The lower reservoir would have a surface
elevation of 6,000 feet msl with a storage volume of approximately
1,550 acre-feet. A new, approximately 1.8-mile long 230-kilovolt (kV)
overhead interconnection line will extend from the powerhouse to a
substation. The powerhouse would contain two turbines and generators,
with a generating capacity of 250 megawatts (MW) based on available
hydraulic head and water to fill the reservoirs. Each turbine is rated
for 133 MW, and each generator is rated for 125 MW. The estimated
average annual generation is 547,500 MWh.
Applicant Contact: Ushakar Jha, Twentymile Pumped Storage, LLC, 100
S Olive St., West Palm Beach, Florida 33401; email:
[email protected]; phone: (503) 309-2496.
FERC Contact: Lee Baker; email: [email protected]; phone:
(202) 502-8554.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, notices of intent, and competing
applications using the Commission's eFiling system at https://ferconline.ferc.gov/eFiling.aspx. Commenters can submit brief comments
up to 6,000 characters, without prior registration, using the eComment
system at https://ferconline.ferc.gov/QuickComment.aspx. You must
include your name and contact information at the end of your comments.
For assistance, please contact FERC Online Support. In lieu of
electronic filing, you may submit a paper copy. Submissions sent via
the U.S. Postal Service must be addressed to: Debbie-Anne A. Reese,
Acting Secretary, Federal Energy Regulatory Commission, 888 First
Street NE, Room 1A, Washington, DC 20426. Submissions sent via any
other carrier must be addressed to: Debbie-Anne A. Reese, Acting
Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first page of any filing should include
docket number P-15305-000.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of the
Commission's website at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-15305) in the docket number field to access
the document. For assistance, contact FERC Online Support.
Dated: May 24, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-11995 Filed 5-30-24; 8:45 am]
BILLING CODE 6717-01-P