Download as PDF 45654 Federal Register / Vol. 89, No. 101 / Thursday, May 23, 2024 / Notices Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. Dated: May 17, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–11371 Filed 5–22–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 14276–016] lotter on DSK11XQN23PROD with NOTICES1 FFP Project 92, LLC, Lock 11 Hydro Partners, LLC; Notice of Application of Transfer of License and Soliciting Comments, Motions To Intervene, and Protests On February 29, 2024, FFP Project 92, LLC (transferor) filed an application for a transfer of license of the 2,640kilowatt Kentucky River Lock & Dam No. 11 Hydroelectric Project No. 14276. The project is located on the Kentucky River in Estill and Madison counties, Kentucky and does not occupy Federal land. Pursuant to 16 U.S.C. 801, the applicants seek Commission approval to transfer the license for the project from FFP Project 92, LLC to Lock 11 Hydro Partners, LLC (transferee). The transferee will be required by the Commission to comply with all the requirements of the license as though it were the original licensee. The applicants also propose to change the name of the project to College Hill Hydroelectric Project. Applicants Contact: David Brown Kinloch, Address: 414 S Wenzel Street, Louisville, KY 40204, Phone: (502) 589– 0975. FERC Contact: Steven Sachs, Phone: (202) 502–8666, Email: Steven.Sachs@ ferc.gov. Deadline for Filing Comments, Motions To Intervene, and Protests: 30 days from the date that the Commission issues this notice. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) VerDate Sep<11>2014 18:47 May 22, 2024 Jkt 262001 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via U.S. Postal Service must be addressed to, Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to, Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number P–14276–016. Comments emailed to Commission staff are not considered part of the Commission record. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: May 17, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–11372 Filed 5–22–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP24–88–000] Rover Pipeline LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Rover-Bulger Delivery Meter Station Project On March 8, 2024, Rover Pipeline LLC (Rover), filed an application in Docket No. CP24–88–000 requesting a Certificate of Public Convenience and Necessity pursuant to section 7(c) of the Natural Gas Act to construct and operate certain natural gas pipeline facilities. The proposed project is known as the Rover-Bulger Delivery Meter Station Project (Project). Rover would construct, own and operate a new delivery point at Rover’s Bulger Compressor Station on their Burgettstown Lateral in Washington County, Pennsylvania. PO 00000 Frm 00029 Fmt 4703 Sfmt 4703 On March 20, 2024, the Federal Energy Regulatory Commission (Commission or FERC) issued its Notice of Application for the Project. Among other things, that notice alerted agencies issuing federal authorizations of the requirement to complete all necessary reviews and to reach a final decision on a request for a federal authorization within 90 days of the date of issuance of the Commission staff’s environmental document for the Project. This notice identifies Commission staff’s intention to prepare an environmental assessment (EA) for the Project and the planned schedule for the completion of the environmental review.1 Schedule for Environmental Review Issuance of EA: July 15, 2024. 90-Day Federal Authorization Decision Deadline: 2 October 13, 2024. If a schedule change becomes necessary, additional notice will be provided so that the relevant agencies are kept informed of the Project’s progress. Project Description Rover proposes to construct, own, and operate a new pipeline delivery point interconnection at the Rover-Bulger Delivery Meter Station, entirely within Rover’s existing Bulger Compressor Station in Washington County, Pennsylvania. The Rover-Bulger Delivery Meter Station Project would allow for delivery of natural gas to ETC Northeast Pipeline LLC’s (ETC Northeast) cryogenic processing facility for processing and re-injection of the processed natural gas into Rover’s pipeline via the existing RoverRevolution Receipt Meter Station. According to Rover, the project’s interconnection would allow delivery of up to 400,000 dekatherms of natural gas assets per day to ETC Northeast. Rover does not have the authority to construct facilities pursuant to blanket certificate authority under part 157, subpart F of the Commission’s regulations, therefore, Rover was required to file an application under part 157 of the Commission’s regulations. Background On April 2, 2024, the Commission issued a Notice of Scoping Period 1 40 CFR 1501.10 (2020). Commission’s deadline applies to the decisions of other federal agencies, and state agencies acting under federally delegated authority, that are responsible for federal authorizations, permits, and other approvals necessary for proposed projects under the Natural Gas Act. Per 18 CFR 157.22(a), the Commission’s deadline for other agency’s decisions applies unless a schedule is otherwise established by Federal law. 2 The E:\FR\FM\23MYN1.SGM 23MYN1 Federal Register / Vol. 89, No. 101 / Thursday, May 23, 2024 / Notices lotter on DSK11XQN23PROD with NOTICES1 Requesting Comments on Environmental Issues for the Proposed Rover-Bulger Delivery Meter Station Project (Notice of Scoping). The Notice of Scoping was sent to affected landowners; federal, state, and local government agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. In response to the Notice of Scoping, the Commission received comments from Ascent Resources—Utica, LLC., BP Energy Company, and Sweat Law Offices on behalf of the Board of Supervisors of Smith Township, Washington County, Pennsylvania. The primary issues raised by Ascent Resources—Utica, LLC and BP Energy Company are concern for operational and economic harm resulting from the removal of ethane from Rover’s gas stream. Sweat Law Offices on behalf of the Board of Supervisors of Smith Township, Washington County, Pennsylvania commented that there have been complaints from residents and members from adjoining municipalities regarding noise from ETC Northeast’s activities that are directly related to Rover. All substantive comments will be addressed in the EA. Additional Information In order to receive notification of the issuance of the EA and to keep track of formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This service provides automatic notification of filings made to subscribed dockets, document summaries, and direct links to the documents. Go to https:// www.ferc.gov/ferc-online/overview to register for eSubscription. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the ‘‘eLibrary’’ link, select ‘‘General Search’’ from the eLibrary menu, enter the selected date range and ‘‘Docket VerDate Sep<11>2014 18:47 May 22, 2024 Jkt 262001 Number’’ excluding the last three digits (i.e., CP24–88–000), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Dated: May 17, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–11376 Filed 5–22–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Filings Instituting Proceedings Docket Numbers: RP24–770–000. Applicants: Midcontinent Express Pipeline LLC. Description: § 4(d) Rate Filing: NonConforming Amendment (Spotlight) May 2024 to be effective 6/1/2024. Filed Date: 5/16/24. Accession Number: 20240516–5135. Comment Date: 5 p.m. ET 5/28/24. Docket Numbers: RP24–771–000. Applicants: MoGas Pipeline LLC. Description: § 4(d) Rate Filing: MoGas Negotiated Rate Agreement Filing to be effective 6/1/2024. Filed Date: 5/17/24. Accession Number: 20240517–5042. Comment Date: 5 p.m. ET 5/29/24. Docket Numbers: RP24–772–000. Applicants: Rockies Express Pipeline LLC. Description: Compliance filing: REX 2024–05–17 Annual Penalty Charge Reconciliation to be effective N/A. Filed Date: 5/17/24. Accession Number: 20240517–5077. Comment Date: 5 p.m. ET 5/29/24. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. The filings are accessible in the Commission’s eLibrary system (https:// PO 00000 Frm 00030 Fmt 4703 Sfmt 4703 45655 elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: May 17, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–11378 Filed 5–22–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER18–1182–009. Applicants: System Energy Resources, Inc. Description: Compliance filing: SERI Compliance (ER18–1182 et al.) to be effective 11/1/2023. Filed Date: 5/17/24. Accession Number: 20240517–5068. Comment Date: 5 p.m. ET 6/7/24. Docket Numbers: ER11–2036–015; ER19–1795–002; ER19–1798–002; ER19–1793–002; ER19–1797–002; ER19–1796–002; ER19–1799–002; ER18–2327–007; ER19–902–003; ER19– 1597–005; ER20–902–002; ER20–1593– 005; ER20–1594–004; ER20–1596–005; ER20–1597–005; ER20–1599–005; ER20–1620–003; ER21–2767–002; ER22–414–003; ER22–1518–002; ER23– 495–004; ER23–1631–001. Applicants: Cavalier Solar A, LLC, AES CE Solutions, LLC, Laurel Mountain BESS, LLC, AES Marketing and Trading, LLC, Skipjack Solar Center, LLC, AES Solutions Management, LLC, Richmond Spider E:\FR\FM\23MYN1.SGM 23MYN1

Agencies

[Federal Register Volume 89, Number 101 (Thursday, May 23, 2024)]
[Notices]
[Pages 45654-45655]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-11376]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP24-88-000]


Rover Pipeline LLC; Notice of Schedule for the Preparation of an 
Environmental Assessment for the Rover-Bulger Delivery Meter Station 
Project

    On March 8, 2024, Rover Pipeline LLC (Rover), filed an application 
in Docket No. CP24-88-000 requesting a Certificate of Public 
Convenience and Necessity pursuant to section 7(c) of the Natural Gas 
Act to construct and operate certain natural gas pipeline facilities. 
The proposed project is known as the Rover-Bulger Delivery Meter 
Station Project (Project). Rover would construct, own and operate a new 
delivery point at Rover's Bulger Compressor Station on their 
Burgettstown Lateral in Washington County, Pennsylvania.
    On March 20, 2024, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
environmental document for the Project.
    This notice identifies Commission staff's intention to prepare an 
environmental assessment (EA) for the Project and the planned schedule 
for the completion of the environmental review.\1\
---------------------------------------------------------------------------

    \1\ 40 CFR 1501.10 (2020).
---------------------------------------------------------------------------

Schedule for Environmental Review

    Issuance of EA: July 15, 2024.
    90-Day Federal Authorization Decision Deadline: \2\ October 13, 
2024.
---------------------------------------------------------------------------

    \2\ The Commission's deadline applies to the decisions of other 
federal agencies, and state agencies acting under federally 
delegated authority, that are responsible for federal 
authorizations, permits, and other approvals necessary for proposed 
projects under the Natural Gas Act. Per 18 CFR 157.22(a), the 
Commission's deadline for other agency's decisions applies unless a 
schedule is otherwise established by Federal law.
---------------------------------------------------------------------------

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    Rover proposes to construct, own, and operate a new pipeline 
delivery point interconnection at the Rover-Bulger Delivery Meter 
Station, entirely within Rover's existing Bulger Compressor Station in 
Washington County, Pennsylvania. The Rover-Bulger Delivery Meter 
Station Project would allow for delivery of natural gas to ETC 
Northeast Pipeline LLC's (ETC Northeast) cryogenic processing facility 
for processing and re-injection of the processed natural gas into 
Rover's pipeline via the existing Rover-Revolution Receipt Meter 
Station. According to Rover, the project's interconnection would allow 
delivery of up to 400,000 dekatherms of natural gas assets per day to 
ETC Northeast. Rover does not have the authority to construct 
facilities pursuant to blanket certificate authority under part 157, 
subpart F of the Commission's regulations, therefore, Rover was 
required to file an application under part 157 of the Commission's 
regulations.

Background

    On April 2, 2024, the Commission issued a Notice of Scoping Period

[[Page 45655]]

Requesting Comments on Environmental Issues for the Proposed Rover-
Bulger Delivery Meter Station Project (Notice of Scoping). The Notice 
of Scoping was sent to affected landowners; federal, state, and local 
government agencies; elected officials; environmental and public 
interest groups; Native American Tribes; other interested parties; and 
local libraries and newspapers. In response to the Notice of Scoping, 
the Commission received comments from Ascent Resources--Utica, LLC., BP 
Energy Company, and Sweat Law Offices on behalf of the Board of 
Supervisors of Smith Township, Washington County, Pennsylvania. The 
primary issues raised by Ascent Resources--Utica, LLC and BP Energy 
Company are concern for operational and economic harm resulting from 
the removal of ethane from Rover's gas stream. Sweat Law Offices on 
behalf of the Board of Supervisors of Smith Township, Washington 
County, Pennsylvania commented that there have been complaints from 
residents and members from adjoining municipalities regarding noise 
from ETC Northeast's activities that are directly related to Rover. All 
substantive comments will be addressed in the EA.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of formal issuances and submittals in specific dockets, the 
Commission offers a free service called eSubscription. This service 
provides automatic notification of filings made to subscribed dockets, 
document summaries, and direct links to the documents. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the ``eLibrary'' link, select 
``General Search'' from the eLibrary menu, enter the selected date 
range and ``Docket Number'' excluding the last three digits (i.e., 
CP24-88-000), and follow the instructions. For assistance with access 
to eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 
502-8659, or at [email protected]. The eLibrary link on the 
FERC website also provides access to the texts of formal documents 
issued by the Commission, such as orders, notices, and rule makings.

    Dated: May 17, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-11376 Filed 5-22-24; 8:45 am]
BILLING CODE 6717-01-P