Merced Irrigation District; Notice of Waiver Period for Water Quality Certification Application, 45652-45653 [2024-11373]
Download as PDF
45652
Federal Register / Vol. 89, No. 101 / Thursday, May 23, 2024 / Notices
Project Description
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP24–80–000]
Mississippi Hub, LLC; Notice of
Schedule for the Preparation of an
Environmental Assessment for the MS
Hub Capacity Expansion Project
On March 5, 2024, Mississippi Hub,
LLC (MS Hub) filed an application in
Docket No. CP24–80–000 requesting a
Certificate of Public Convenience and
Necessity pursuant to section 7(c) of the
Natural Gas Act to construct and operate
certain facilities related to natural gas
storage and compression. The proposed
project is known as the MS Hub
Capacity Expansion Project (Project) and
would add up to 0.7 billion cubic feet
(Bcf) per day of injection capacity and
up to 1.0 Bcf per day of delivery
capacity to MS Hub’s existing MS Hub
Storage Facility infrastructure, as well
as perform related modifications within
Simpson, Covington, and Jefferson
Davis Counties, Mississippi.
On March 18, 2024, the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Notice
of Application for the Project. Among
other things, that notice alerted agencies
issuing federal authorizations of the
requirement to complete all necessary
reviews and to reach a final decision on
a request for a federal authorization
within 90 days of the date of issuance
of the Commission staff’s environmental
document for the Project.
This notice identifies Commission
staff’s intention to prepare an
environmental assessment (EA) for the
Project and the planned schedule for the
completion of the environmental
review.1
Schedule for Environmental Review
Issuance of EA August 16, 2024
90-day Federal Authorization Decision
Deadline 2 November 14, 2024
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
lotter on DSK11XQN23PROD with NOTICES1
1 40
CFR 1501.10 (2020).
2 The Commission’s deadline applies to the
decisions of other federal agencies, and state
agencies acting under federally delegated authority,
that are responsible for federal authorizations,
permits, and other approvals necessary for
proposed projects under the Natural Gas Act. Per
18 CFR 157.22(a), the Commission’s deadline for
other agency’s decisions applies unless a schedule
is otherwise established by federal law.
VerDate Sep<11>2014
18:47 May 22, 2024
Jkt 262001
Within Simpson County, MS Hub
would construct: (a) three new gas
storage caverns and expand the capacity
of two existing gas storage caverns,
thereby increasing the certificated
working gas capacity at its MS Hub
Storage Facility by approximately 33.9
Bcf; (b) approximately 14,000
horsepower (hp) of electric motordriven compression and 16,500 hp of
gas-fired compression and ancillary
equipment at its existing Gas Handling
Facility; (c) additional solution mining
equipment at its existing Leaching
Facility; (d) a filter separator and skid at
the existing Southern Natural Gas
(‘‘SONAT’’) Meter Station site; and (e)
four raw water wells and three saltwater
disposal wells. Within Covington
County, MS Hub would construct: (a)
meter skids, flow control skids, and
filter separators on the existing
Transcontinental Pipeline (‘‘Transco’’)
and Southeast Supply Header (‘‘SESH’’)
Meter Station sites; and (b) one booster
compressor station (‘‘MS Hub Booster
Station’’), including gas-fired
compressor units totaling 40,458 hp,
approximately 2 miles northwest of the
existing Transco Meter Station. Within
Jefferson Davis County, MS Hub would
construct two saltwater disposal wells.
Background
On April 10, 2024, the Commission
issued a Notice of Scoping Period
Requesting Comments on
Environmental Issues for the Proposed
MS Hub Capacity Expansion Project
(Notice of Scoping). The Notice of
Scoping was sent to affected
landowners; federal, state, and local
government agencies; elected officials;
environmental and public interest
groups; Native American tribes; other
interested parties; and local libraries
and newspapers. In response to the
Notice of Scoping, the Commission
received comments from Mississippi
Department of Wildlife, Fisheries, and
Parks; Mississippi Department of
Environmental Quality; Southern
Natural Gas Company, L.L.C.;
Mississippi Department of Archives and
History; and Mississippi Hub, LLC. The
primary issues raised by the
commenters are the need to perform a
Mississippi Natural Heritage Program
review, and corrections to the Project
description within the Notice of
Scoping. All substantive comments will
be addressed in the EA.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
formal issuances and submittals in
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
specific dockets, the Commission offers
a free service called eSubscription. This
service provides automatic notification
of filings made to subscribed dockets,
document summaries, and direct links
to the documents. Go to https://
www.ferc.gov/ferc-online/overview to
register for eSubscription.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202)502–6595 or OPP@
ferc.gov.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP24–80), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: May 17, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–11377 Filed 5–22–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2467–020]
Merced Irrigation District; Notice of
Waiver Period for Water Quality
Certification Application
On April 15, 2024, Merced Irrigation
District submitted to the Federal Energy
Regulatory Commission (Commission) a
copy of its application for a Clean Water
Act section 401(a)(1) water quality
certification filed with the California
State Water Resources Control Board
(California Water Board), in conjunction
with the above captioned project.
E:\FR\FM\23MYN1.SGM
23MYN1
Federal Register / Vol. 89, No. 101 / Thursday, May 23, 2024 / Notices
Pursuant to 40 CFR 121.6 and section
4.34(b)(5) of the Commission’s
regulations,1 we hereby notify the
California Water Board of the following:
Date of Receipt of the Certification
Request: April 15, 2024.
Reasonable Period of Time to Act on
the Certification Request: One year
(April 15, 2025).
If the California Water Board fails or
refuses to act on the water quality
certification request on or before the
above date, then the agency certifying
authority is deemed waived pursuant to
section 401(a)(1) of the Clean Water Act,
33 U.S.C. 1341(a)(1).
Dated: May 17, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–11373 Filed 5–22–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 15230–002]
lotter on DSK11XQN23PROD with NOTICES1
Pike Island Hydropower Corporation;
Notice of Application Tendered for
Filing With the Commission and
Soliciting Additional Study Requests
and Establishing Procedural Schedule
for Licensing and a Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Original Major
License.
b. Project No.: 15230–002.
c. Date Filed: May 14, 2024.
d. Submitted By: Pike Island
Hydropower Corporation.
e. Name of Project: Pike Island
Hydroelectric Project (Pike Island
Project).
f. Location: The Pike Island Project
would be located at the U.S. Army
Corps of Engineers’ (Corps) Pike Island
Locks and Dam on the Ohio River in
Belmont County, Ohio. The project
would occupy 2 acres of Federal land
administered by the Corps.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Joel Herm, P.O.
Box 224, Rhinebeck, NY 12572, (917)
244–3607, joel@currenthydro.com or
Norm Bishop, P.O. Box 224, Rhinebeck,
NY 12572, (303) 475–0608.
i. FERC Contact: Jay Summers at (202)
502–8764; or email at jay.summers@
ferc.gov.
1
18 CFR 4.34(b)(5).
VerDate Sep<11>2014
18:47 May 22, 2024
Jkt 262001
j. Cooperating agencies: Federal,
State, local, and Tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: July 13, 2024.1
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, you may submit a
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Debbie-Anne A. Reese, Acting
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Debbie-Anne A.
Reese, Acting Secretary, Federal Energy
Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852. All
filings must clearly identify the project
name and docket number on the first
page: Pike Island Hydroelectric Project
(P–15230–002).
m. The application is not ready for
environmental analysis at this time.
1 The Commission’s Rules of Practice and
Procedure provide that if a filing deadline falls on
a Saturday, Sunday, holiday, or other day when the
Commission is closed for business, the filing
deadline does not end until the close of business
on the next business day. 18 CFR 385.2007(a)(2).
Because the 60-day filing deadline falls on a
Saturday (i.e., July 13, 2024), the filing deadline is
extended until the close of business on Monday,
July 15, 2024.
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
45653
n. The Pike Island Project would use
the Corps’ existing Pike Island Locks
and Dam and would consist of the
following new facilities: (1) a 101-footwide, 193-foot-long reinforced concrete
powerhouse; (2) a 90-foot-wide by 110foot-long intake section with trash racks;
(3) two Kaplan pit turbine-generators
with a combined capacity of 19.99
megawatts; (4) a 95-foot-wide, 150-footlong tailrace channel; (5) a 13.8-kilovolt
(kV), 550-foot-long underground utilidor
crossing under River Road; (5) a 2,223
foot-long, 69-kV, three phase overhead
transmission line connecting the
powerhouse substation to the 69-kV
Glenn Run-Tiltonsville interconnection
point in Ohio; and (7) appurtenant
facilities.
o. Copies of the application may be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits
in the docket number field to access the
document (P–2535). For assistance,
contact FERC Online Support at
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll-free) or (202) 502–
8659 (TTY).
You may also register online at https://
www.ferc.gov/docs-filing/esubscription.
asp to be notified via email of new
filings and issuances related to this or
other pending projects. For assistance,
contact FERC Online Support.
p. The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595, or OPP@
ferc.gov.
q. Procedural schedule and final
amendments: the application will be
processed according to the following
preliminary schedule. Revisions to the
schedule will be made as appropriate.
Milestone
Issue Deficiency Letter (if necessary).
Request Additional Information
(if necessary).
Issue Scoping Document 1 for
comments.
Request Additional Information
(if necessary).
Issue Scoping Document 2 (if
necessary).
E:\FR\FM\23MYN1.SGM
23MYN1
Target date
August 2024.
August 2024.
November 2024
January 2025
February 2025
Agencies
[Federal Register Volume 89, Number 101 (Thursday, May 23, 2024)]
[Notices]
[Pages 45652-45653]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-11373]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2467-020]
Merced Irrigation District; Notice of Waiver Period for Water
Quality Certification Application
On April 15, 2024, Merced Irrigation District submitted to the
Federal Energy Regulatory Commission (Commission) a copy of its
application for a Clean Water Act section 401(a)(1) water quality
certification filed with the California State Water Resources Control
Board (California Water Board), in conjunction with the above captioned
project.
[[Page 45653]]
Pursuant to 40 CFR 121.6 and section 4.34(b)(5) of the Commission's
regulations,\1\ we hereby notify the California Water Board of the
following:
---------------------------------------------------------------------------
\1\ 18 CFR 4.34(b)(5).
---------------------------------------------------------------------------
Date of Receipt of the Certification Request: April 15, 2024.
Reasonable Period of Time to Act on the Certification Request: One
year (April 15, 2025).
If the California Water Board fails or refuses to act on the water
quality certification request on or before the above date, then the
agency certifying authority is deemed waived pursuant to section
401(a)(1) of the Clean Water Act, 33 U.S.C. 1341(a)(1).
Dated: May 17, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-11373 Filed 5-22-24; 8:45 am]
BILLING CODE 6717-01-P