Combined Notice of Filings #1, 44663-44664 [2024-11155]
Download as PDF
44663
Federal Register / Vol. 89, No. 99 / Tuesday, May 21, 2024 / Notices
ddrumheller on DSK120RN23PROD with NOTICES1
Army Corps of Engineers’ (Corps) New
Cumberland Locks and Dam on the
Ohio River in Hancock County, West
Virginia. The project would occupy 2
acres of federal land administered by
the Corps.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Joel Herm, P.O.
Box 224, Rhinebeck, NY 12572, (917)
244–3607, joel@currenthydro.com or
Norm Bishop, P.O. Box 224, Rhinebeck,
NY 12572, (303) 475–0608.
i. FERC Contact: Jay Summers at (202)
502–8764; or email at jay.summers@
ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: July 7, 2024.1
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, you may submit a
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
1 The Commission’s Rules of Practice and
Procedure provide that if a filing deadline falls on
a Saturday, Sunday, holiday, or other day when the
Commission is closed for business, the filing
deadline does not end until the close of business
on the next business day. 18 CFR 385.2007(a)(2).
Because the 60-day filing deadline falls on a
Sunday (i.e., July 7, 2024), the filing deadline is
extended until the close of business on Monday,
July 8, 2024.
VerDate Sep<11>2014
18:13 May 20, 2024
Jkt 262001
to: Debbie-Anne A. Reese, Acting
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Debbie-Anne A.
Reese, Acting Secretary, Federal Energy
Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852. All
filings must clearly identify the project
name and docket number on the first
page: New Cumberland Hydroelectric
Project (P–15045–002).
m. The application is not ready for
environmental analysis at this time.
n. The New Cumberland Project
would use the Corps’ existing New
Cumberland Locks and Dam and would
consist of the following new facilities:
(1) a 101-foot-wide, 193-foot-long
reinforced concrete powerhouse; (2) a
90-foot-wide by 350-foot-long intake
section with trash racks; (3) two
identical Kaplan pit turbine-generators
with a combined capacity of 19.99
megawatts; (4) a 13.8-kilovolt (kV), 180foot-long underground utilidor crossing
under the Norfolk Southern railway and
transitioning to a 350-foot overhead
transmission to the powerhousesubstation; (5) a 90-foot-wide by 90-footlong powerhouse-substation; (6) a 1,050foot-long, 34.5-kV, three-phase overhead
transmission line connecting the
powerhouse-substation to the existing
35-kV transmission line, east of
Hancock County Bus Garage
interconnection point in West Virginia;
and (7) appurtenant facilities.
o. Copies of the application may be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits
in the docket number field to access the
document (P–2535). For assistance,
contact FERC Online Support at
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll-free) or (202) 502–
8659 (TTY).
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
PO 00000
Frm 00039
Fmt 4703
Sfmt 4703
rehearing, the public is encouraged to
contact OPP at (202) 502–6595, or OPP@
ferc.gov.
q. Procedural schedule and final
amendments: the application will be
processed according to the following
preliminary schedule. Revisions to the
schedule will be made as appropriate.
Milestone
Issue Deficiency Letter (if
necessary).
Request Additional Information (if necessary).
Issue Scoping Document 1
for comments.
Request Additional Information (if necessary).
Issue Scoping Document 2 (if
necessary).
Target date
August 2024.
August 2024.
November
2024.
January 2025.
February
2025.
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: May 14, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–11049 Filed 5–20–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG24–178–000.
Applicants: Gransolar Texas One,
LLC.
Description: Gransolar Texas One,
LLC submits Notice of Self-Certification
of Exempt Wholesale Generator Status.
Filed Date: 5/15/24.
Accession Number: 20240515–5023.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: EG24–179–000.
Applicants: BT Jungmann, LLC.
Description: BT Jungmann, LLC
submits Notice of Self-Certification of
Exempt Wholesale Generator Status.
Filed Date: 5/15/24.
Accession Number: 20240515–5025.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: EG24–180–000.
Applicants: Desert Quartzite, LLC.
Description: Desert Quartzite, LLC
submits Notice of Self-Certification of
Exempt Wholesale Generator Status.
Filed Date: 5/15/24.
Accession Number: 20240515–5050.
Comment Date: 5 p.m. ET 6/5/24.
E:\FR\FM\21MYN1.SGM
21MYN1
ddrumheller on DSK120RN23PROD with NOTICES1
44664
Federal Register / Vol. 89, No. 99 / Tuesday, May 21, 2024 / Notices
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER24–1656–000;
ER24–1657–000.
Applicants: McNair Creek Hydro
Limited Partnership, Furry Creek Power
Ltd.
Description: Second Supplement to
03/29/2024, Furry Creek Power Ltd., et
al., tariff filing.
Filed Date: 5/10/24.
Accession Number: 20240510–5240.
Comment Date: 5 p.m. ET 5/31/24.
Docket Numbers: ER24–2014–000.
Applicants: Western Interconnect
LLC.
Description: Tariff Amendment:
Notice of Cancellation of OATT to be
effective 5/16/2024.
Filed Date: 5/15/24.
Accession Number: 20240515–5024.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24–2015–000.
Applicants: New York Independent
System Operator, Inc.
Description: 205(d) Rate Filing:
NYISO 205: Market Revenue Offset for
ICAP Demand Curves to be effective 7/
15/2024.
Filed Date: 5/15/24.
Accession Number: 20240515–5027.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24–2016–000.
Applicants: MATL LLP.
Description: Compliance filing: Order
2023 Compliance Filing (RM22–14) to
be effective 12/31/9998.
Filed Date: 5/15/24.
Accession Number: 20240515–5028.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24–2017–000.
Applicants: PacifiCorp.
Description: Compliance filing: Order
Nos. 2023, 2023–A Compliance Filing to
be effective 11/2/2024.
Filed Date: 5/15/24.
Accession Number: 20240515–5039.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24–2018–000.
Applicants: Louisville Gas and
Electric Company.
Description: Compliance filing: FERC
Order No. 2023 Compliance Filing to be
effective 8/1/2024.
Filed Date: 5/15/24.
Accession Number: 20240515–5054.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24–2019–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: 205(d) Rate Filing: 2024–
05–15_SA 4287 City of Columbia, MOBoone Stephens Solar GIA (J1191) to be
effective 5/6/2024.
Filed Date: 5/15/24.
Accession Number: 20240515–5064.
VerDate Sep<11>2014
18:13 May 20, 2024
Jkt 262001
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24–2020–000.
Applicants: Tri-State Generation and
Transmission Association, Inc.
Description: 205(d) Rate Filing: Initial
Filing of Service Agreement FERC No.
112 to be effective 5/1/2024.
Filed Date: 5/15/24.
Accession Number: 20240515–5075.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24–2021–000.
Applicants: Southwest Power Pool,
Inc.
Description: 205(d) Rate Filing: 4266
Beeline Solar Energy GIA to be effective
5/13/2024.
Filed Date: 5/15/24.
Accession Number: 20240515–5079.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24–2022–000.
Applicants: Black Hills Power, Inc.
Description: Compliance filing: Order
2023 Joint Open Access Transmission
Tariff Revisions to be effective 8/1/2024.
Filed Date: 5/15/24.
Accession Number: 20240515–5090.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24–2023–000.
Applicants: Black Hills Colorado
Electric, LLC.
Description: Compliance filing: Order
2023 Open Access Transmission Tariff
Revisions to be effective 9/1/2024.
Filed Date: 5/15/24.
Accession Number: 20240515–5095.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24–2024–000.
Applicants: Arizona Public Service
Company.
Description: Tariff Amendment: Rate
Schedule No. 261—Notice of
Cancellation to be effective 7/15/2024.
Filed Date: 5/15/24.
Accession Number: 20240515–5101.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24–2025–000.
Applicants: Wilderness Line
Holdings, LLC.
Description: Compliance filing: Order
No. 2023 Compliance Filing to be
effective 5/15/2024.
Filed Date: 5/15/24.
Accession Number: 20240515–5113.
Comment Date: 5 p.m. ET 6/5/24.
Take notice that the Commission
received the following electric securities
filings:
Docket Numbers: ES24–38–000.
Applicants: LS Power Grid California,
LLC.
Description: Application Under
Section 204 of the Federal Power Act for
Authorization to Issue Securities of LS
Power Grid California, LLC.
Filed Date: 5/14/24.
Accession Number: 20240514–5181.
Comment Date: 5 p.m. ET 6/4/24.
PO 00000
Frm 00040
Fmt 4703
Sfmt 4703
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene, to
protest, or to answer a complaint in any
of the above proceedings must file in
accordance with Rules 211, 214, or 206
of the Commission’s Regulations (18
CFR 385.211, 385.214, or 385.206) on or
before 5:00 p.m. Eastern time on the
specified comment date. Protests may be
considered, but intervention is
necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Dated: May 15, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–11155 Filed 5–20–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 1904–078; Project No. 1855–
050; Project No. 1892–030]
Great River Hydro, LLC; Notice of
Reasonable Period of Time for Water
Quality Certification Application
On April 23, 2024, Great River Hydro,
LLC filed with the Federal Energy
Regulatory Commission (Commission)
documentation that it filed requests for
Clean Water Act section 401(a)(1) water
quality certifications with the New
Hampshire Department of
Environmental Services (New
Hampshire DES) in conjunction with
the above captioned projects. The
documentation indicates that New
E:\FR\FM\21MYN1.SGM
21MYN1
Agencies
[Federal Register Volume 89, Number 99 (Tuesday, May 21, 2024)]
[Notices]
[Pages 44663-44664]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-11155]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #1
Take notice that the Commission received the following exempt
wholesale generator filings:
Docket Numbers: EG24-178-000.
Applicants: Gransolar Texas One, LLC.
Description: Gransolar Texas One, LLC submits Notice of Self-
Certification of Exempt Wholesale Generator Status.
Filed Date: 5/15/24.
Accession Number: 20240515-5023.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: EG24-179-000.
Applicants: BT Jungmann, LLC.
Description: BT Jungmann, LLC submits Notice of Self-Certification
of Exempt Wholesale Generator Status.
Filed Date: 5/15/24.
Accession Number: 20240515-5025.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: EG24-180-000.
Applicants: Desert Quartzite, LLC.
Description: Desert Quartzite, LLC submits Notice of Self-
Certification of Exempt Wholesale Generator Status.
Filed Date: 5/15/24.
Accession Number: 20240515-5050.
Comment Date: 5 p.m. ET 6/5/24.
[[Page 44664]]
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER24-1656-000; ER24-1657-000.
Applicants: McNair Creek Hydro Limited Partnership, Furry Creek
Power Ltd.
Description: Second Supplement to 03/29/2024, Furry Creek Power
Ltd., et al., tariff filing.
Filed Date: 5/10/24.
Accession Number: 20240510-5240.
Comment Date: 5 p.m. ET 5/31/24.
Docket Numbers: ER24-2014-000.
Applicants: Western Interconnect LLC.
Description: Tariff Amendment: Notice of Cancellation of OATT to be
effective 5/16/2024.
Filed Date: 5/15/24.
Accession Number: 20240515-5024.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24-2015-000.
Applicants: New York Independent System Operator, Inc.
Description: 205(d) Rate Filing: NYISO 205: Market Revenue Offset
for ICAP Demand Curves to be effective 7/15/2024.
Filed Date: 5/15/24.
Accession Number: 20240515-5027.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24-2016-000.
Applicants: MATL LLP.
Description: Compliance filing: Order 2023 Compliance Filing (RM22-
14) to be effective 12/31/9998.
Filed Date: 5/15/24.
Accession Number: 20240515-5028.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24-2017-000.
Applicants: PacifiCorp.
Description: Compliance filing: Order Nos. 2023, 2023-A Compliance
Filing to be effective 11/2/2024.
Filed Date: 5/15/24.
Accession Number: 20240515-5039.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24-2018-000.
Applicants: Louisville Gas and Electric Company.
Description: Compliance filing: FERC Order No. 2023 Compliance
Filing to be effective 8/1/2024.
Filed Date: 5/15/24.
Accession Number: 20240515-5054.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24-2019-000.
Applicants: Midcontinent Independent System Operator, Inc.
Description: 205(d) Rate Filing: 2024-05-15_SA 4287 City of
Columbia, MO-Boone Stephens Solar GIA (J1191) to be effective 5/6/2024.
Filed Date: 5/15/24.
Accession Number: 20240515-5064.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24-2020-000.
Applicants: Tri-State Generation and Transmission Association, Inc.
Description: 205(d) Rate Filing: Initial Filing of Service
Agreement FERC No. 112 to be effective 5/1/2024.
Filed Date: 5/15/24.
Accession Number: 20240515-5075.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24-2021-000.
Applicants: Southwest Power Pool, Inc.
Description: 205(d) Rate Filing: 4266 Beeline Solar Energy GIA to
be effective 5/13/2024.
Filed Date: 5/15/24.
Accession Number: 20240515-5079.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24-2022-000.
Applicants: Black Hills Power, Inc.
Description: Compliance filing: Order 2023 Joint Open Access
Transmission Tariff Revisions to be effective 8/1/2024.
Filed Date: 5/15/24.
Accession Number: 20240515-5090.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24-2023-000.
Applicants: Black Hills Colorado Electric, LLC.
Description: Compliance filing: Order 2023 Open Access Transmission
Tariff Revisions to be effective 9/1/2024.
Filed Date: 5/15/24.
Accession Number: 20240515-5095.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24-2024-000.
Applicants: Arizona Public Service Company.
Description: Tariff Amendment: Rate Schedule No. 261--Notice of
Cancellation to be effective 7/15/2024.
Filed Date: 5/15/24.
Accession Number: 20240515-5101.
Comment Date: 5 p.m. ET 6/5/24.
Docket Numbers: ER24-2025-000.
Applicants: Wilderness Line Holdings, LLC.
Description: Compliance filing: Order No. 2023 Compliance Filing to
be effective 5/15/2024.
Filed Date: 5/15/24.
Accession Number: 20240515-5113.
Comment Date: 5 p.m. ET 6/5/24.
Take notice that the Commission received the following electric
securities filings:
Docket Numbers: ES24-38-000.
Applicants: LS Power Grid California, LLC.
Description: Application Under Section 204 of the Federal Power Act
for Authorization to Issue Securities of LS Power Grid California, LLC.
Filed Date: 5/14/24.
Accession Number: 20240514-5181.
Comment Date: 5 p.m. ET 6/4/24.
The filings are accessible in the Commission's eLibrary system
(https://elibrary.ferc.gov/idmws/search/fercgensearch.asp) by querying
the docket number.
Any person desiring to intervene, to protest, or to answer a
complaint in any of the above proceedings must file in accordance with
Rules 211, 214, or 206 of the Commission's Regulations (18 CFR 385.211,
385.214, or 385.206) on or before 5:00 p.m. Eastern time on the
specified comment date. Protests may be considered, but intervention is
necessary to become a party to the proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
Dated: May 15, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-11155 Filed 5-20-24; 8:45 am]