Combined Notice of Filings #1, 44670-44671 [2024-11048]

Download as PDF 44670 Federal Register / Vol. 89, No. 99 / Tuesday, May 21, 2024 / Notices accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. r. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202)502–6595 or OPP@ ferc.gov. Dated: May 15, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–11149 Filed 5–20–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. RM93–11–000] ddrumheller on DSK120RN23PROD with NOTICES1 Revisions to Oil Pipeline Regulations Pursuant to the Energy Policy Act of 1992; Notice of Annual Change in the Producer Price Index for Finished Goods The Commission’s regulations include a methodology for oil pipelines to change their rates through use of an index system that establishes ceiling levels for such rates. The Commission bases the index system, found at 18 CFR 342.3, on the annual change in the Producer Price Index for Finished Goods (PPI–FG), minus point two one percent (PPI–FG¥0.21%). The Commission determined in the January 2022 Order 1 that PPI–FG¥0.21% is the appropriate oil pricing index factor for pipelines to use for this period. The regulations provide that the Commission will publish annually an index figure reflecting the final change in the PPI–FG after the Bureau of Labor Statistics publishes the final PPI–FG in May of each calendar year. The annual average PPI–FG index figures were 250.9 for 2022 and 254.6 for 2023.2 1 Five-Year Rev. of the Oil Pipeline Index, 178 FERC ¶ 61,023, at P 105 (January 2022 Order), reh’g denied, 179 FERC ¶ 61,100 (2022). 2 Bureau of Labor Statistics (BLS) publishes the final figure in mid-May of each year. This figure is publicly available from the Division of Industrial Prices and Price Indexes of the BLS, at 202–691– 7705, and in print in August in Table 1 of the VerDate Sep<11>2014 18:13 May 20, 2024 Jkt 262001 Thus, the percent change (expressed as a decimal) in the annual average PPI–FG from 2022 to 2023, minus 0.21 percent, is positive 0.012647.3 Oil pipelines must multiply their July 1, 2023, through June 30, 2024, index ceiling levels 4 by positive 1.012647 5 to compute their index ceiling levels for July 1, 2024, through June 30, 2025, in accordance with 18 CFR 342.3(d). For guidance in calculating the ceiling levels for each 12-month period beginning January 1, 1995,6 see Explorer Pipeline Company, 71 FERC ¶ 61,416, at n.6 (1995). In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov). From the Commission’s Home Page on the internet, this information is available on eLibrary. The full text of this document is available on eLibrary in PDF and Microsoft Word format for viewing, printing, and/or downloading. To access this document in eLibrary, type the docket number excluding the last three digits of this document in the docket number field. User assistance is available for eLibrary and the Commission’s website during normal business hours from FERC Online Support at 202–502–6652 (toll free at 1–866–208–3676) or email at ferconlinesupport@ferc.gov, or the Public Reference Room at (202) 502– 8371, TTY (202)502–8659. Email the Public Reference Room at public.referenceroom@ferc.gov. Dated: May 15, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–11147 Filed 5–20–24; 8:45 am] BILLING CODE 6717–01–P annual data supplement to the BLS publication Producer Price Indexes via the internet at https:// www.bls.gov. To obtain the BLS data, scroll down to ‘‘Data Tools’’ and click on ‘‘BLS Popular Series.’’ At the next screen, under the heading ‘‘Price Indexes,’’ select the box, ‘‘PPI Finished Goods 1982=100 (Unadjusted)¥WPUFD49207,’’ then scroll to the bottom of this screen and click on Retrieve data. 3 [254.6–250.9]/250.9 = 0.014747¥0.0021 = 0.012647. 4 See January 2022 Order, 178 FERC ¶ 61,023, reh’g denied, 179 FERC ¶ 61,100; see also Revisions to Oil Pipeline Reguls. Pursuant to the Energy Pol’y Act of 1992, 178 FERC ¶ 61,046 (2022). 5 1 + 0.012647 = 1.012647. 6 For a listing of all prior multipliers issued by the Commission, see the Commission’s website, https:// www.ferc.gov/industries-data/oil/generalinformation/oil-pipeline-index. PO 00000 Frm 00046 Fmt 4703 Sfmt 4703 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following exempt wholesale generator filings: Docket Numbers: EG24–177–000. Applicants: Hornet Solar LLC. Description: Hornet Solar LLC submits Notice of Self-Certification of Exempt Wholesale Generator Status. Filed Date: 5/13/24. Accession Number: 20240513–5293. Comment Date: 5 p.m. ET 6/3/24. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER24–1259–001. Applicants: Occidental Power Marketing, L.P. Description: Tariff Amendment: Deficiency Letter Response to be effective 2/16/2024. Filed Date: 5/14/24. Accession Number: 20240514–5044. Comment Date: 5 p.m. ET 6/4/24. Docket Numbers: ER24–1261–001. Applicants: Occidental Power Services, Inc. Description: Tariff Amendment: Deficiency Letter Response to be effective 2/16/2024. Filed Date: 5/14/24. Accession Number: 20240514–5045. Comment Date: 5 p.m. ET 6/4/24. Docket Numbers: ER24–1262–001. Applicants: Occidental Chemical Corporation. Description: Tariff Amendment: Deficiency Letter Response to be effective 2/16/2024. Filed Date: 5/14/24. Accession Number: 20240514–5046. Comment Date: 5 p.m. ET 6/4/24. Docket Numbers: ER24–1263–001. Applicants: OTCF, LLC. Description: Tariff Amendment: Deficiency Letter Response to be effective 2/16/2024. Filed Date: 5/14/24. Accession Number: 20240514–5052. Comment Date: 5 p.m. ET 6/4/24. Docket Numbers: ER24–1469–002. Applicants: PJM Interconnection, L.L.C. Description: Tariff Amendment: Amendment to ER24–1469–001 re: Metadata Correction to be effective 1/1/ 2024. Filed Date: 5/14/24. Accession Number: 20240514–5114. Comment Date: 5 p.m. ET 6/4/24. Docket Numbers: ER24–1580–001. Applicants: Alabama Power Company, Georgia Power Company, Mississippi Power Company. E:\FR\FM\21MYN1.SGM 21MYN1 ddrumheller on DSK120RN23PROD with NOTICES1 Federal Register / Vol. 89, No. 99 / Tuesday, May 21, 2024 / Notices Description: Tariff Amendment: Alabama Power Company submits tariff filing per 35.17(b): Double Run Solar LGIA Amended Amendment Filing to be effective 3/6/2024. Filed Date: 5/14/24. Accession Number: 20240514–5094. Comment Date: 5 p.m. ET 6/4/24. Docket Numbers: ER24–1700–001. Applicants: Alabama Power Company, Georgia Power Company, Mississippi Power Company. Description: Tariff Amendment: Alabama Power Company submits tariff filing per 35.17(b): EDF Renewables (Rock House Solar) LGIA Amended Amendment Filing to be effective 3/22/ 2024. Filed Date: 5/14/24. Accession Number: 20240514–5095. Comment Date: 5 p.m. ET 6/4/24. Docket Numbers: ER24–1755–001. Applicants: Alabama Power Company, Georgia Power Company, Mississippi Power Company. Description: Tariff Amendment: Alabama Power Company submits tariff filing per 35.17(b): Shelby Solar Park LGIA Amended Amendment Filing to be effective 4/2/2024. Filed Date: 5/14/24. Accession Number: 20240514–5093. Comment Date: 5 p.m. ET 6/4/24. Docket Numbers: ER24–1756–001. Applicants: Alabama Power Company, Georgia Power Company, Mississippi Power Company. Description: Tariff Amendment: Alabama Power Company submits tariff filing per 35.17(b): Sawmill Junction Solar Park A&R LGIA Amended Amendment Filing to be effective 4/4/ 2024. Filed Date: 5/14/24. Accession Number: 20240514–5092. Comment Date: 5 p.m. ET 6/4/24. Docket Numbers: ER24–2002–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: Revisions to Modify Adder for Offers Greater Than $1000/MWh to be effective 7/14/2024. Filed Date: 5/14/24. Accession Number: 20240514–5026. Comment Date: 5 p.m. ET 6/4/24. Docket Numbers: ER24–2003–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: Revisions to Allow Nomination of Candidate LTCRs for FSEs and GFA Carve Outs to be effective 7/14/2024. Filed Date: 5/14/24. Accession Number: 20240514–5027. Comment Date: 5 p.m. ET 6/4/24. Docket Numbers: ER24–2005–000. VerDate Sep<11>2014 18:13 May 20, 2024 Jkt 262001 Applicants: AEP Texas Inc. Description: § 205(d) Rate Filing: AEPTX-Saragosa Del Sol Energy Generation Interconnection Agreement to be effective 4/23/2024. Filed Date: 5/14/24. Accession Number: 20240514–5056. Comment Date: 5 p.m. ET 6/4/24. Docket Numbers: ER24–2006–000. Applicants: AEP Texas Inc. Description: § 205(d) Rate Filing: AEPTX–BRP Blue Topaz 2 Generation Interconnection Agreement to be effective 4/22/2024. Filed Date: 5/14/24. Accession Number: 20240514–5063. Comment Date: 5 p.m. ET 6/4/24. Docket Numbers: ER24–2007–000. Applicants: ISO New England Inc., New England Power Pool Participants Committee. Description: § 205(d) Rate Filing: ISO New England Inc. submits tariff filing per 35.13(a)(2)(iii: Rev to Section II of ISO Tariff Related to Comp. with Order 2023 and 2023–A to be effective 12/31/ 9998. Filed Date: 5/14/24. Accession Number: 20240514–5109. Comment Date: 5 p.m. ET 6/4/24. Docket Numbers: ER24–2008–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2024–05–14_SA 4288 Ameren ILPanther Solar B912 GIA (J1306) to be effective 7/14/2024. Filed Date: 5/14/24. Accession Number: 20240514–5152. Comment Date: 5 p.m. ET 6/4/24. Docket Numbers: ER24–2009–000. Applicants: ISO New England Inc., New England Power Pool Participants Committee. Description: Compliance filing: ISO New England Inc. submits tariff filing per 35: Revisions in Compliance with Order Nos. 2023 and 2023–A to be effective 8/12/2024. Filed Date: 5/14/24. Accession Number: 20240514–5156. Comment Date: 5 p.m. ET 6/4/24. Docket Numbers: ER24–2010–000. Applicants: AMP Transmission, LLC, AES US Services, LLC, PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: AMP Transmission, LLC submits tariff filing per 35.13(a)(2)(iii: AES Ohio submits Interconnection Agreement, SA No. 7241 to be effective 5/7/2024. Filed Date: 5/14/24. Accession Number: 20240514–5158. Comment Date: 5 p.m. ET 6/4/24. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ PO 00000 Frm 00047 Fmt 4703 Sfmt 4703 44671 fercgensearch.asp) by querying the docket number. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: May 14, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–11048 Filed 5–20–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. AD10–12–015] Increasing Market and Planning Efficiency Through Improved Software; Supplemental Notice of Technical Conference on Increasing Real-Time and Day-Ahead Market and Planning Efficiency Through Improved Software As first announced in the Notice of Technical Conference issued in this proceeding on February 29, 2024, Commission staff will convene a technical conference on July 9, 10, and 11, 2024 to discuss opportunities for increasing real-time and day-ahead market and planning efficiency of the bulk power system through improved software. Attached to this Supplemental Notice is the agenda for the technical E:\FR\FM\21MYN1.SGM 21MYN1

Agencies

[Federal Register Volume 89, Number 99 (Tuesday, May 21, 2024)]
[Notices]
[Pages 44670-44671]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-11048]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Combined Notice of Filings #1

    Take notice that the Commission received the following exempt 
wholesale generator filings:

    Docket Numbers: EG24-177-000.
    Applicants: Hornet Solar LLC.
    Description: Hornet Solar LLC submits Notice of Self-Certification 
of Exempt Wholesale Generator Status.
    Filed Date: 5/13/24.
    Accession Number: 20240513-5293.
    Comment Date: 5 p.m. ET 6/3/24.

    Take notice that the Commission received the following electric 
rate filings:

    Docket Numbers: ER24-1259-001.
    Applicants: Occidental Power Marketing, L.P.
    Description: Tariff Amendment: Deficiency Letter Response to be 
effective 2/16/2024.
    Filed Date: 5/14/24.
    Accession Number: 20240514-5044.
    Comment Date: 5 p.m. ET 6/4/24.

    Docket Numbers: ER24-1261-001.
    Applicants: Occidental Power Services, Inc.
    Description: Tariff Amendment: Deficiency Letter Response to be 
effective 2/16/2024.
    Filed Date: 5/14/24.
    Accession Number: 20240514-5045.
    Comment Date: 5 p.m. ET 6/4/24.

    Docket Numbers: ER24-1262-001.
    Applicants: Occidental Chemical Corporation.
    Description: Tariff Amendment: Deficiency Letter Response to be 
effective 2/16/2024.
    Filed Date: 5/14/24.
    Accession Number: 20240514-5046.
    Comment Date: 5 p.m. ET 6/4/24.

    Docket Numbers: ER24-1263-001.
    Applicants: OTCF, LLC.
    Description: Tariff Amendment: Deficiency Letter Response to be 
effective 2/16/2024.
    Filed Date: 5/14/24.
    Accession Number: 20240514-5052.
    Comment Date: 5 p.m. ET 6/4/24.

    Docket Numbers: ER24-1469-002.
    Applicants: PJM Interconnection, L.L.C.
    Description: Tariff Amendment: Amendment to ER24-1469-001 re: 
Metadata Correction to be effective 1/1/2024.
    Filed Date: 5/14/24.
    Accession Number: 20240514-5114.
    Comment Date: 5 p.m. ET 6/4/24.

    Docket Numbers: ER24-1580-001.
    Applicants: Alabama Power Company, Georgia Power Company, 
Mississippi Power Company.

[[Page 44671]]

    Description: Tariff Amendment: Alabama Power Company submits tariff 
filing per 35.17(b): Double Run Solar LGIA Amended Amendment Filing to 
be effective 3/6/2024.
    Filed Date: 5/14/24.
    Accession Number: 20240514-5094.
    Comment Date: 5 p.m. ET 6/4/24.

    Docket Numbers: ER24-1700-001.
    Applicants: Alabama Power Company, Georgia Power Company, 
Mississippi Power Company.
    Description: Tariff Amendment: Alabama Power Company submits tariff 
filing per 35.17(b): EDF Renewables (Rock House Solar) LGIA Amended 
Amendment Filing to be effective 3/22/2024.
    Filed Date: 5/14/24.
    Accession Number: 20240514-5095.
    Comment Date: 5 p.m. ET 6/4/24.

    Docket Numbers: ER24-1755-001.
    Applicants: Alabama Power Company, Georgia Power Company, 
Mississippi Power Company.
    Description: Tariff Amendment: Alabama Power Company submits tariff 
filing per 35.17(b): Shelby Solar Park LGIA Amended Amendment Filing to 
be effective 4/2/2024.
    Filed Date: 5/14/24.
    Accession Number: 20240514-5093.
    Comment Date: 5 p.m. ET 6/4/24.

    Docket Numbers: ER24-1756-001.
    Applicants: Alabama Power Company, Georgia Power Company, 
Mississippi Power Company.
    Description: Tariff Amendment: Alabama Power Company submits tariff 
filing per 35.17(b): Sawmill Junction Solar Park A&R LGIA Amended 
Amendment Filing to be effective 4/4/2024.
    Filed Date: 5/14/24.
    Accession Number: 20240514-5092.
    Comment Date: 5 p.m. ET 6/4/24.

    Docket Numbers: ER24-2002-000.
    Applicants: Southwest Power Pool, Inc.
    Description: Sec.  205(d) Rate Filing: Revisions to Modify Adder 
for Offers Greater Than $1000/MWh to be effective 7/14/2024.
    Filed Date: 5/14/24.
    Accession Number: 20240514-5026.
    Comment Date: 5 p.m. ET 6/4/24.

    Docket Numbers: ER24-2003-000.
    Applicants: Southwest Power Pool, Inc.
    Description: Sec.  205(d) Rate Filing: Revisions to Allow 
Nomination of Candidate LTCRs for FSEs and GFA Carve Outs to be 
effective 7/14/2024.
    Filed Date: 5/14/24.
    Accession Number: 20240514-5027.
    Comment Date: 5 p.m. ET 6/4/24.

    Docket Numbers: ER24-2005-000.
    Applicants: AEP Texas Inc.
    Description: Sec.  205(d) Rate Filing: AEPTX-Saragosa Del Sol 
Energy Generation Interconnection Agreement to be effective 4/23/2024.
    Filed Date: 5/14/24.
    Accession Number: 20240514-5056.
    Comment Date: 5 p.m. ET 6/4/24.

    Docket Numbers: ER24-2006-000.
    Applicants: AEP Texas Inc.
    Description: Sec.  205(d) Rate Filing: AEPTX-BRP Blue Topaz 2 
Generation Interconnection Agreement to be effective 4/22/2024.
    Filed Date: 5/14/24.
    Accession Number: 20240514-5063.
    Comment Date: 5 p.m. ET 6/4/24.

    Docket Numbers: ER24-2007-000.
    Applicants: ISO New England Inc., New England Power Pool 
Participants Committee.
    Description: Sec.  205(d) Rate Filing: ISO New England Inc. submits 
tariff filing per 35.13(a)(2)(iii: Rev to Section II of ISO Tariff 
Related to Comp. with Order 2023 and 2023-A to be effective 12/31/9998.
    Filed Date: 5/14/24.
    Accession Number: 20240514-5109.
    Comment Date: 5 p.m. ET 6/4/24.

    Docket Numbers: ER24-2008-000.
    Applicants: Midcontinent Independent System Operator, Inc.
    Description: Sec.  205(d) Rate Filing: 2024-05-14_SA 4288 Ameren 
IL-Panther Solar B912 GIA (J1306) to be effective 7/14/2024.
    Filed Date: 5/14/24.
    Accession Number: 20240514-5152.
    Comment Date: 5 p.m. ET 6/4/24.

    Docket Numbers: ER24-2009-000.
    Applicants: ISO New England Inc., New England Power Pool 
Participants Committee.
    Description: Compliance filing: ISO New England Inc. submits tariff 
filing per 35: Revisions in Compliance with Order Nos. 2023 and 2023-A 
to be effective 8/12/2024.
    Filed Date: 5/14/24.
    Accession Number: 20240514-5156.
    Comment Date: 5 p.m. ET 6/4/24.

    Docket Numbers: ER24-2010-000.
    Applicants: AMP Transmission, LLC, AES US Services, LLC, PJM 
Interconnection, L.L.C.
    Description: Sec.  205(d) Rate Filing: AMP Transmission, LLC 
submits tariff filing per 35.13(a)(2)(iii: AES Ohio submits 
Interconnection Agreement, SA No. 7241 to be effective 5/7/2024.
    Filed Date: 5/14/24.
    Accession Number: 20240514-5158.
    Comment Date: 5 p.m. ET 6/4/24.

    The filings are accessible in the Commission's eLibrary system 
(https://elibrary.ferc.gov/idmws/search/fercgensearch.asp) by querying 
the docket number.
    Any person desiring to intervene, to protest, or to answer a 
complaint in any of the above proceedings must file in accordance with 
Rules 211, 214, or 206 of the Commission's Regulations (18 CFR 385.211, 
385.214, or 385.206) on or before 5:00 p.m. Eastern time on the 
specified comment date. Protests may be considered, but intervention is 
necessary to become a party to the proceeding.
    eFiling is encouraged. More detailed information relating to filing 
requirements, interventions, protests, service, and qualifying 
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676 
(toll free). For TTY, call (202) 502-8659.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].

    Dated: May 14, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-11048 Filed 5-20-24; 8:45 am]
BILLING CODE 6717-01-P