Alaska Electric Light & Power Company; Notice of Intent To Prepare an Environmental Assessment, 38122-38123 [2024-09829]
Download as PDF
khammond on DSKJM1Z7X2PROD with NOTICES
38122
Federal Register / Vol. 89, No. 89 / Tuesday, May 7, 2024 / Notices
Accession Number: 20240430–5195.
Comment Date: 5 p.m. ET 5/21/24.
Docket Numbers: ER24–1889–000.
Applicants: NMRD Data Center III,
LLC.
Description: § 205(d) Rate Filing:
NMRD DC III MBR Tariff and Notice of
Cancel filing to be effective 5/1/2024.
Filed Date: 4/30/24.
Accession Number: 20240430–5196.
Comment Date: 5 p.m. ET 5/21/24.
Docket Numbers: ER24–1890–000.
Applicants: BRP Capital & Trade LLC.
Description: Compliance filing: Notice
of Change in Status to be effective 6/30/
2024.
Filed Date: 4/30/24.
Accession Number: 20240430–5200.
Comment Date: 5 p.m. ET 5/21/24.
Docket Numbers: ER24–1891–000.
Applicants: Idaho Power Company.
Description: § 205(d) Rate Filing: RS
No. 175—Concurrence—Jackpot
Holdings, LLC SFA to be effective 5/1/
2024.
Filed Date: 4/30/24.
Accession Number: 20240430–5216.
Comment Date: 5 p.m. ET 5/21/24.
Docket Numbers: ER24–1892–000.
Applicants: Idaho Power Company.
Description: § 205(d) Rate Filing: RS
No. 176—Concurrence—Franklin Solar
SFA to be effective 5/1/2024.
Filed Date: 4/30/24.
Accession Number: 20240430–5219.
Comment Date: 5 p.m. ET 5/21/24.
Docket Numbers: ER24–1893–000.
Applicants: Duke Energy Florida,
LLC.
Description: § 205(d) Rate Filing:
Annual Filing of Cost Factor Updates to
be effective 5/1/2024.
Filed Date: 4/30/24.
Accession Number: 20240430–5230.
Comment Date: 5 p.m. ET 5/21/24.
Docket Numbers: ER24–1894–000.
Applicants: Stanton Clean Energy,
LLC.
Description: Initial rate filing: FERC
Rate Schedule No. 1, Stanton OUC PPA
to be effective 5/1/2024.
Filed Date: 4/30/24.
Accession Number: 20240430–5276.
Comment Date: 5 p.m. ET 5/21/24.
Docket Numbers: ER24–1895–000.
Applicants: New England Power Pool
Participants Committee.
Description: § 205(d) Rate Filing: May
2024 Membership Filing to be effective
4/1/2024.
Filed Date: 4/30/24.
Accession Number: 20240430–5280.
Comment Date: 5 p.m. ET 5/21/24.
Docket Numbers: ER24–1896–000.
Applicants: Cavalry Energy Center,
LLC.
Description: Compliance filing: Notice
of Non-Material Change in Status and
VerDate Sep<11>2014
15:55 May 06, 2024
Jkt 262001
MBR Tariff Revisions to be effective 6/
30/2024.
Filed Date: 4/30/24.
Accession Number: 20240430–5290.
Comment Date: 5 p.m. ET 5/21/24.
Docket Numbers: ER24–1897–000.
Applicants: Northampton Generating
Company, L.P.
Description: Compliance filing:
Northampton Change in Status to be
effective 5/1/2024.
Filed Date: 4/30/24.
Accession Number: 20240430–5292.
Comment Date: 5 p.m. ET 5/21/24.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/fercgen
search.asp) by querying the docket
number.
Any person desiring to intervene, to
protest, or to answer a complaint in any
of the above proceedings must file in
accordance with Rules 211, 214, or 206
of the Commission’s Regulations (18
CFR 385.211, 385.214, or 385.206) on or
before 5:00 p.m. Eastern time on the
specified comment date. Protests may be
considered, but intervention is
necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Dated: April 30, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–09836 Filed 5–6–24; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 1904–078; Project No. 1855–
050; Project No. 1892–030]
Great River Hydro, LLC; Notice of
Reasonable Period of Time for Water
Quality Certification Application
On April 19, 2024, the Vermont
Agency of Natural Resources (Vermont
ANR) filed with the Federal Energy
Regulatory Commission (Commission)
notice that it received complete requests
for Clean Water Act section 401(a)(1)
water quality certifications from Great
River Hydro, LLC in conjunction with
the above captioned projects, on April
18, 2024. Pursuant to section 5.23(b) of
the Commission’s regulations,1 we
hereby notify Vermont ANR of the
following:
Date of Receipt of the Certification
Request: April 18, 2024.
Reasonable Period of Time to Act on
the Certification Request: One year,
April 18, 2025.
If Vermont ANR fails or refuses to act
on the water quality certification
requests on or before the above date,
then the certifying authority is deemed
waived pursuant to section 401(a)(1) of
the Clean Water Act, 33 U.S.C.
1341(a)(1).
Dated: April 30, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–09831 Filed 5–6–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2307–086]
Alaska Electric Light & Power
Company; Notice of Intent To Prepare
an Environmental Assessment
On October 13, 2023, and
supplemented on April 26, 2024, Alaska
Electric Light & Power Company
(licensee) filed an application for a noncapacity amendment for the Annex
Creek and Salmon Creek Hydroelectric
Project No. 2307. The project is located
on Annex and Salmon Creeks in the
City and Borough of Juneau, Alaska. The
project occupies federal land within the
Tongass National Forest, administered
by the U.S. Forest Service.
The licensee proposes to replace the
upper Salmon Creek penstock, which
1 18
Frm 00105
Fmt 4703
Sfmt 4703
CFR 5.23(b).
E:\FR\FM\07MYN1.SGM
07MYN1
Federal Register / Vol. 89, No. 89 / Tuesday, May 7, 2024 / Notices
runs from the valvehouse to the
abandoned upper powerhouse. The
licensee states that the penstock, which
is over 100 years old, must be replaced
to ensure safe and reliable operation of
the project for the remainder of the
project license. As proposed, the
licensee would replace the entire upper
penstock with modern welded steel
pipe that meets modern engineering and
construction standards. Additionally,
the licensee states that penstock bridges
over Salmon Creek that have not been
recently rebuilt would be replaced with
new bridges to support the new
penstock. A Notice of Application for
Non-Capacity Amendment of License
Accepted for Filing, Soliciting
Comments, Motions to Intervene, and
Protests was issued on April 30, 2024.
This notice identifies Commission
staff’s intention to prepare an
environmental assessment (EA) for the
project. The planned schedule for the
completion of the EA is October 2024.1
Revisions to the schedule may be made
as appropriate. The EA will be issued
and made available for review by all
interested parties. All comments filed
on the EA will be reviewed by staff and
considered in the Commission’s final
decision on the proceeding.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members, and
others to access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Any questions regarding this notice
may be directed to Marybeth Gay at
(202) 502–6125 or Marybeth.gay@
ferc.gov.
Dated: April 30, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–09829 Filed 5–6–24; 8:45 am]
khammond on DSKJM1Z7X2PROD with NOTICES
BILLING CODE 6717–01–P
1 42 U.S.C. 4336a(g)(1)(B) requires lead federal
agencies to complete EAs within 1 year of the
agency’s decision to prepare an EA. This notice
establishes the Commission’s intent to prepare an
EA for the project; therefore, the EA must be issued
within 1 year of the issuance date of this notice.
VerDate Sep<11>2014
15:55 May 06, 2024
Jkt 262001
38123
Ormat Dixie Valley LLC, Steamboat
Hills LLC, Ormesa LLC, EGP Stillwater
Federal Energy Regulatory
Solar PV II, LLC, ONGP LLC, ORNI 43
Commission
LLC, Viridity Energy Solutions Inc.,
VESI Pomona Energy Storage, Inc.,
Combined Notice of Filings #1
ORNI 37 LLC, Enel Cove Fort, LLC,
Mammoth Three LLC, ORNI 47 LLC,
Take notice that the Commission
received the following electric corporate Mammoth One LLC, USG Oregon LLC,
EGP Stillwater Solar, LLC, Enel
filings:
Stillwater, LLC, ORNI 14 LLC, ORNI 39,
Docket Numbers: EC24–74–000.
Applicants: Kimmel Road Solar, LLC, LLC, ORNI 18 LLC, Heber Geothermal
Company LLC.
BCD 2024 Fund 3 Lessee, LLC.
Description: Notice of Non-Material
Description: Joint Application for
Change
in Status of Heber Geothermal
Authorization Under Section 203 of the
Company LLC, et al.
Federal Power Act of Kimmel Road
Filed Date: 4/25/24.
Solar, LLC, et al.
Accession Number: 20240425–5331.
Filed Date: 4/29/24.
Comment Date: 5 p.m. ET 5/16/24.
Accession Number: 20240429–5451.
Docket Numbers: ER19–1575–011;
Comment Date: 5 p.m. ET 5/20/24.
ER10–2488–028; ER13–1586–023;
Take notice that the Commission
ER14–2871–022; ER15–463–021; ER15–
received the following exempt
621–021; ER15–622–021; ER16–72–017;
wholesale generator filings:
ER16–182–017; ER16–902–014; ER17–
Docket Numbers: EG24–170–000.
47–014; ER17–48–015; ER18–47–014;
Applicants: Peacock Energy Project,
ER18–2240–010; ER18–2241–010;
LLC.
ER19–427–010; ER19–1660–010; ER19–
Description: Peacock Energy Project,
1662–010; ER19–1667–010; ER20–71–
LLC submits Notice of Self-Certification
010; ER20–72–010; ER20–75–010;
of Exempt Wholesale Generator Status.
ER20–76–012; ER20–77–010; ER20–79–
Filed Date: 4/29/24.
010; ER21–1368–006; ER21–1369–007;
Accession Number: 20240429–5402.
ER21–1371–007; ER21–1373–008;
Comment Date: 5 p.m. ET 5/20/24.
ER21–1376–008; ER21–2782–007;
Take notice that the Commission
ER22–149–007; ER22–1439–008; ER22–
received the following electric rate
1440–008; ER22–1441–008; ER22–1442–
filings:
006; ER22–2419–004; ER22–2420–004;
Docket Numbers: ER10–2354–016.
ER23–562–004; ER23–1048–004; ER23–
Applicants: Midway-Sunset
2001–003.
Cogeneration Company.
Applicants: Sagebrush ESS II, LLC,
Description: Notice of Non-Material
Lockhart ESS, LLC, TGP Energy
Change in Status of Midway-Sunset
Management II, LLC, Lockhart Solar PV
Cogeneration Company.
II, LLC, Lockhart Solar PV, LLC, EdSan
Filed Date: 4/30/24.
1B Group 3, LLC, EdSan 1B Group 2,
Accession Number: 20240430–5258.
LLC, EdSan 1B Group 1 Sanborn, LLC,
Comment Date: 5 p.m. ET 5/21/24.
EdSan 1B Group 1 Edwards, LLC,
Sagebrush Line, LLC, Sagebrush ESS,
Docket Numbers: ER16–131–005;
LLC, ES 1A Group 3 Opco, LLC, ES 1A
ER10–2294–009; ER11–3808–008;
Group 2 Opco, LLC, Edwards Sanborn
ER11–3980–008; ER11–4500–011;
Storage II, LLC, Edwards Sanborn
ER12–128–009; ER13–413–009; ER13–
Storage I, LLC, Valley Center ESS, LLC,
534–008; ER13–2103–006; ER13–2414–
Voyager Wind IV Expansion, LLC,
005; ER14–325–008; ER15–2330–005;
ER20–2696–000; ER17–737–002; ER17– Painted Hills Wind Holdings, LLC,
2471–006; ER17–2472–006; ER17–2548– Tehachapi Plains Wind, LLC, Oasis
Alta, LLC, Coachella Wind Holdings,
001; ER18–301–005; ER18–664–006;
ER22–645–000; ER18–2214–003; ER18– LLC, Coachella Hills Wind, LLC, Terra2216–003; ER18–2435–005; ER19–1047– Gen VG Wind, LLC, Mojave 16/17/18
LLC, Mojave 3/4/5 LLC, LUZ Solar
004; ER20–2977–002; ER22–1882–003;
Partners IX, Ltd., Garnet Wind, LLC,
ER22–2178–003; ER22–2799–002;
Yavi Energy, LLC, Voyager Wind II,
ER22–2800–002; ER22–2801–002;
LLC, Terra-Gen Mojave Windfarms,
ER23–1238–002; ER23–1239–002;
ER23–1773–003; ER24–561–001; ER24– LLC, DifWind Farms LTD VI, Voyager
Wind I, LLC, Cameron Ridge II, LLC,
564–001.
San Gorgonio Westwinds II—
Applicants: VESI 12 LLC, VESI 23
Windustries, LLC, Ridgetop Energy,
LLC, Pomona Energy Storage 2 LLC,
LLC, Pacific Crest Power, LLC, San
USG Nevada LLC, ORNI 36 LLC, VESI
Gorgonio Westwinds II, LLC, Cameron
25 LLC, VESI 24 LLC, VESI 21 LLC,
Ridge, LLC, TGP Energy Management,
ORNI 50 LLC, VESI 10 LLC, ORNI 34
LLC, Oasis Power Partners, LLC, Alta
LLC, VESIVEC LLC, ORNI 41 LLC,
Oak Realty, LLC.
Plumsted 537 LLC, Stryker 22, LLC.,
DEPARTMENT OF ENERGY
PO 00000
Frm 00106
Fmt 4703
Sfmt 4703
E:\FR\FM\07MYN1.SGM
07MYN1
Agencies
[Federal Register Volume 89, Number 89 (Tuesday, May 7, 2024)]
[Notices]
[Pages 38122-38123]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-09829]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2307-086]
Alaska Electric Light & Power Company; Notice of Intent To
Prepare an Environmental Assessment
On October 13, 2023, and supplemented on April 26, 2024, Alaska
Electric Light & Power Company (licensee) filed an application for a
non-capacity amendment for the Annex Creek and Salmon Creek
Hydroelectric Project No. 2307. The project is located on Annex and
Salmon Creeks in the City and Borough of Juneau, Alaska. The project
occupies federal land within the Tongass National Forest, administered
by the U.S. Forest Service.
The licensee proposes to replace the upper Salmon Creek penstock,
which
[[Page 38123]]
runs from the valvehouse to the abandoned upper powerhouse. The
licensee states that the penstock, which is over 100 years old, must be
replaced to ensure safe and reliable operation of the project for the
remainder of the project license. As proposed, the licensee would
replace the entire upper penstock with modern welded steel pipe that
meets modern engineering and construction standards. Additionally, the
licensee states that penstock bridges over Salmon Creek that have not
been recently rebuilt would be replaced with new bridges to support the
new penstock. A Notice of Application for Non-Capacity Amendment of
License Accepted for Filing, Soliciting Comments, Motions to Intervene,
and Protests was issued on April 30, 2024.
This notice identifies Commission staff's intention to prepare an
environmental assessment (EA) for the project. The planned schedule for
the completion of the EA is October 2024.\1\ Revisions to the schedule
may be made as appropriate. The EA will be issued and made available
for review by all interested parties. All comments filed on the EA will
be reviewed by staff and considered in the Commission's final decision
on the proceeding.
---------------------------------------------------------------------------
\1\ 42 U.S.C. 4336a(g)(1)(B) requires lead federal agencies to
complete EAs within 1 year of the agency's decision to prepare an
EA. This notice establishes the Commission's intent to prepare an EA
for the project; therefore, the EA must be issued within 1 year of
the issuance date of this notice.
---------------------------------------------------------------------------
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members, and others to access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
Any questions regarding this notice may be directed to Marybeth Gay
at (202) 502-6125 or [email protected].
Dated: April 30, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-09829 Filed 5-6-24; 8:45 am]