Coordination of Federal Authorizations for Electric Transmission Facilities, 35312-35382 [2024-08157]
Download as PDF
35312
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
DEPARTMENT OF ENERGY
10 CFR Part 900
[DOE–HQ–2023–0050]
RIN 1901–AB62
Coordination of Federal Authorizations
for Electric Transmission Facilities
Grid Deployment Office, U.S.
Department of Energy.
ACTION: Final rule.
AGENCY:
The Department of Energy
(DOE) is amending its regulations for
the timely coordination of Federal
authorizations for proposed interstate
electric transmission facilities pursuant
to the Federal Power Act (FPA).
Specifically, DOE is establishing an
integrated and comprehensive
Coordinated Interagency Transmission
Authorizations and Permits Program
(CITAP Program); making participation
in the Integrated Interagency PreApplication (IIP) Process a precondition for assistance under the
CITAP Program; re-establishing the IIP
Process as an iterative and collaborative
process between the proponent of a
proposed electric transmission project
and Federal and State agencies to
develop information needed for Federal
authorizations; requiring the project
proponent to engage in robust
engagement with the public,
communities of interest, and Indian
Tribes during the IIP Process; aligning
and harmonizing the IIP Process and
implementation of the FPA with the
Fixing America’s Surface Transportation
Act; and ensuring that DOE may carry
out its statutory obligation to prepare a
single environmental review document
sufficient for the purposes of all Federal
authorizations necessary to site a
proposed project.
DATES: This rule is effective May 31,
2024.
FOR FURTHER INFORMATION CONTACT: Liza
Reed, U.S. Department of Energy, Grid
Deployment Office, 4H–065, 1000
Independence Avenue SW, Washington,
DC 20585. Telephone: (202) 586–2006.
Email: CITAP@hq.doe.gov.
SUPPLEMENTARY INFORMATION:
ddrumheller on DSK120RN23PROD with RULES2
SUMMARY:
I. Executive Summary
II. Background and Authority
III. Summary of the Final Rule
IV. Tribal Sovereignty
V. Terminology and Clarification Changes
VI. Discussion of Comments
A. General
B. Purpose and Scope
C. Qualifying Projects
D. Purpose and Scope of IIP Process
E. Public Participation in the IIP Process
F. Timing of IIP Process and NOI Issuance
G. IIP Process Initiation Request
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
H. Standard and Project-Specific Schedules
I. Selection of NEPA Lead and Joint Lead
Agencies and Environmental Review
J. Section 106 of the NHPA
K. Definitions
L. Resource Reports
M. Administrative Docket
N. Interaction With FPA 216(a) and FPA
216(b)
O. Miscellaneous
P. Out of Scope Comments
VII. Section-by-Section Analysis
VIII. Regulatory Review
A. Review Under Executive Orders 12866,
13563, and 14094
B. Review Under the Regulatory Flexibility
Act
C. Review Under the Paperwork Reduction
Act of 1995
D. Review Under the National
Environmental Policy Act of 1969
E. Review Under Executive Order 12988
F. Review Under Executive Order 13132
G. Review Under Executive Order 13175
H. Review Under the Unfunded Mandates
Reform Act of 1995
I. Review Under Executive Order 12630
J. Review Under Executive Order 13211
K. Review Under the Treasury and General
Government Appropriations Act, 1999
L. Review Under the Treasury and General
Government Appropriations Act, 2001
IX. Congressional Notification
X. Rehearing
XI. Approval by the Office of the Secretary
of Energy
I. Executive Summary
In this final rule, the Department of
Energy (DOE) is amending its
regulations under section 216(h) of the
Federal Power Act (16 U.S.C. 824p(h))
(FPA) to establish a Coordinated
Interagency Transmission
Authorizations and Permits Program
(CITAP Program) under which DOE will
coordinate and expedite Federal
authorizations and environmental
reviews required to site proposed
electric transmission facilities, which
may include reviews pursuant to the
National Environmental Policy Act of
1969 (Pub. L. 91–190, as amended, 42
U.S.C. 4321 et seq.) (NEPA), the
National Historic Preservation Act (Pub.
L. 89–665, as amended, 54 U.S.C. 30010
et seq.) (NHPA), the Endangered Species
Act of 1973 (Pub. L. 93–205, as
amended, 16 U.S.C. 1531 et seq.) (ESA),
and evaluations necessary for
authorizations under the Federal Land
Policy and Management Act (Pub. L.
94–579, as amended, 43 U.S.C. 1701 et
seq.). DOE coordination under this final
rule will increase the efficiency and
effectiveness of the Federal
authorization and review process for
proposed electric transmission facilities
by establishing pre-application
procedures designed to collect the
information needed to perform efficient
and timely Federal authorization and
PO 00000
Frm 00002
Fmt 4701
Sfmt 4700
environmental reviews, reducing
duplication of effort through
preparation of a single environmental
review document as the basis for all
Federal decisions, and setting binding
schedules for the completion of all
Federal authorizations and
environmental reviews. In doing so, this
final rule aims to reduce the time it
takes to site and permit the electric
transmission infrastructure needed to
ensure the delivery of reliable, resilient
and low-cost electricity to American
homes and businesses.
Actions to enable more rapid
deployment of electric transmission are
more important than ever. As DOE
documented in its 2023 National
Transmission Needs Study, additional
transmission capacity is needed in
nearly every region of the country to
improve the reliability and resilience of
electric service, alleviate high costs
caused by transmission congestion and
constraints that prevents low-cost
energy from reaching customers, and
access new low-cost low carbon energy
supplies to serve increasing electricity
demands.1 Over the past decade
additional transmission capacity has
been added at half the rate of the
previous three decades, at a time when
electricity demand is increasing and
new diverse sources of electricity
generation are needed to serve that
demand and meet Federal, State, and
consumer goals to reduce greenhouse
gas emissions from the electricity
sector.2 Accelerating the current pace of
transmission infrastructure investment
and deployment is needed to meet these
objectives and will generate multiple
benefits to the public, including
improved reliability and resilience,
lower electricity costs, additional
economic activity, and reduced
greenhouse gas emissions. By enabling
rapid development of transmission
capacity, the CITAP Program will help
increase access to a diversity of
generation sources, reduce transmission
congestion and power-sector emissions,
and deliver reliable, affordable power
that future consumers will need when
and where they need it.
On August 23, 2023, in accordance
with section 216(h) of the FPA and a
1 United States Department of Energy, National
Transmission Needs Study (Feb. 2023), available at:
https://www.energy.gov/sites/default/files/2023-02/
022423-DRAFTNeedsStudyforPublicComment.pdf.
2 Jenkins, J.D. et al. (2022) Electricity transmission
is key to unlock the full potential of the Inflation
Reduction Act, Zenodo. Available at: https://
zenodo.org/record/7106176#:∼:text=
Previously%2C%20REPEAT%20
Project%20estimated%20that
%20IRA%20could%20cut,from%20electric
%20vehicles%2C%20heat%20pumps%2C%20and
%20other%20electrification.
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES2
May 2023 Memorandum of
Understanding (MOU) among nine
Federal agencies committing to expedite
the siting, permitting, and construction
of electricity transmission infrastructure
through more effective implementation
of section 216(h) of the FPA, DOE
issued a notice of proposed rulemaking
(NOPR), to establish the CITAP
Program. (88 FR 57011).3 Under the
CITAP Program, the entity or individual
heading the project (‘‘project
proponent’’) will work with DOE and
other Federal agencies to gather
materials necessary to inform the
completion of authorizations and
environmental reviews. These materials
include thirteen reports the project
proponent will prepare that describe the
proposed project and its potential
impacts on resources including land,
water, plant and animal life (‘‘resource
reports’’); a summary of the proposed
project that will include details on
which Federal authorizations or permits
may be necessary and the anticipated
timeline to completion of acquiring the
described authorizations and permits;
and proposed project participation and
public engagement plans, which will
outline opportunities for the public to
participate in project authorization
decisions and ensure sufficient
engagement with both communities of
interest and relevant stakeholders. This
process of collaborative information
gathering is referred to as the
‘‘Integrated Interagency Pre-Application
Process’’ or ‘‘IIP Process.’’
Under the CITAP Program, DOE will
set intermediate milestones and
ultimate deadlines for the review of
relevant authorizations and
environmental reviews that provide for
their completion within two years and
establish DOE as the lead agency for the
preparation of a single environmental
review document, in compliance with
NEPA, that supports the decisions of all
relevant Federal entities.4 This final rule
3 The nine 2023 MOU signatory agencies are
USDA, DOC, DOD, DOE, DOI, EPA, Federal
Permitting Steering Improvement Steering Council
(Permitting Council), CEQ, and the Office of
Management and Budget (OMB). The 2023 MOU is
publicly available at https://www.whitehouse.gov/
wp-content/uploads/2023/05/Final-TransmissionMOU-with-signatures-5-04-2023.pdf.
4 Section 900.2 of the final rule defines ‘‘Federal
entity’’ as any Federal agency or department. That
section also defines ‘‘relevant Federal entity’’ as a
Federal entity with jurisdictional interests that may
have an effect on a proposed electric transmission
project, that is responsible for issuing a Federal
authorization for the proposed project, that has
relevant expertise with respect to environmental
and other issues pertinent to or potentially affected
by the proposed project, or that provides funding
for the proposed project. The term includes
participating agencies. The term includes a Federal
entity with either permitting or non-permitting
authority; for example, those entities with which
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
confirms the CITAP Program and the
restructured and improved IIP Process
as described in the NOPR and adopts
revisions to the NOPR proposals in
response to comments regarding issues
such as the Federal evaluation
timelines, approaches to environmental
reviews, and levels of details required
for the Program.
The IIP Process is a projectproponent-driven process. Accordingly,
the time to complete the IIP Process and
begin the time bound, two-year Federal
authorization and environmental review
period depends on the preparation and
responsiveness of the project proponent.
This final rule establishes a series of
checkpoints in the IIP Process (the three
anchor meetings described below) and
requirements for the pre-application
materials that project proponents must
develop to proceed through the Process
(principally, resource reports and public
participation and engagement plans,
which are to be developed with
guidance from Federal entities). The
timeline for completing the preapplication process and proceeding
through these checkpoints will depend,
in large part, on the readiness and
responsiveness of project proponents.
As discussed further below, DOE has
revised the NOPR proposals in this final
rule to reduce the time reserved for DOE
to review and respond to the requested
information within the IIP Process to
just over six months. Coupled with the
two-year timeline that DOE and
signatories to the 2023 Memorandum of
Understanding Regarding Facilitating
Federal Authorizations for Electric
Transmission Facilities (2023 MOU)
agreed to for review of applications and
related environmental review, DOE
expects that the CITAP Program will
substantially reduce the time necessary
for permitting of transmission facilities.
In response to the NOPR, DOE
received 50 comments during the public
comment period, as well as stakeholder
input during the public webinar and
additional briefing provided by the Grid
Deployment Office in DOE that will be
administering the CITAP Program. In
this final rule, DOE is making several
changes to the regulatory text proposed
in the NOPR in response to public
comments.
DOE received 27 comments in
support of the CITAP Program, and
several specifically supporting the IIP
Process, the Federal decision-making
timeline, and the requirement for the
thirteen resource reports. Commenters
consultation or review must be completed before a
project may commence, such as DOD for an
examination of military test, training or operational
impacts.
PO 00000
Frm 00003
Fmt 4701
Sfmt 4700
35313
specifically lauded the resource reports
for their early and meaningful public
engagement components, their
effectiveness in coordinating decisionmaking across different Federal
agencies, and their essential role in
allowing the subsequent authorization
and environmental review processes to
be completed within two years.
Commenters also affirmed the need for
DOE to serve as the Lead Agency for
NEPA review, section 106 of the NHPA,
and section 7 of the ESA for projects in
the CITAP Program to ensure that its
objective of making transmission
permitting processing more effective
and efficient is realized.
The received comments were also
instrumental in identifying
opportunities to streamline the IIP
Process further to ensure that these
objectives are met. The IIP Process
proposed in the NOPR would have
provided, at a maximum, 240 days for
DOE evaluation and determinations of
completeness and readiness to move to
the next steps in the process. In
response to comments requesting more
efficiency, in this final rule that timeline
has been reduced by 55 days by
streamlining notification and convening
timelines to now total 185 days at a
maximum. Additional reductions to
documentation timelines, which do not
impact decision making, total 45 days,
reducing all IIP Process activity by 100
days. As noted previously, however, the
total timeline to complete the IIP
Process will vary in each individual
case based on the project proponent’s
preparation and responsiveness and the
project’s readiness to proceed to Federal
authorization and environmental
reviews. Project proponents will move
most quickly through the IIP Process
and Federal authorization and
environment review processes by
ensuring their projects are ready to
proceed and by ensuring they are
responsive to DOE and Federal agency
requests for information.
Section VI of this document discusses
several other major issues raised by
commenters and provides DOE’s
responses.
II. Background and Authority
The electric transmission system is
the backbone of the United States’
electricity system, connecting electricity
generators to distributors and customers
across the nation. Electric transmission
facilities often traverse long distances
and cross multiple jurisdictions,
including Federal, State, Tribal, and
private lands. To receive Federal
financial support or build electric
transmission facilities on or through
Federal lands and waters, project
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
35314
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
developers often must secure
authorizations from one or multiple
Federal agencies, which can take
considerable time and result in costly
delays.
Recognizing the need for increased
efficiency in the authorization process
for transmission facilities, the Energy
Policy Act of 2005 (Pub. L. 109–58)
(EPAct) established a national policy to
enhance coordination and
communication among Federal agencies
with authority to site electric
transmission facilities. Section 1221(a)
of EPAct added a new section 216 to
Part II of the FPA, which sets forth
provisions relevant to the siting of
interstate electric transmission facilities.
Section 216(h) of the FPA,
‘‘Coordination of Federal Authorizations
for Transmission Facilities,’’ requires
DOE to coordinate all Federal
authorizations and related
environmental reviews needed for siting
interstate electric transmission projects,
including NEPA reviews, permits,
special use authorizations,
certifications, opinions, or other
approvals required under Federal law.
Among other things, it authorizes
DOE to act as the lead agency for
Federal coordination and reviews and
requires the Secretary of Energy, to the
maximum extent practicable under
Federal law, to coordinate the Federal
authorization and review process with
any Indian Tribes, multi-state entities,
and State agencies that have their own
separate permitting and environmental
reviews. 16 U.S.C. 824p(h)(2)–(3).
Relatedly, section 216(h) requires the
Secretary to provide an ‘‘expeditious’’
pre-application mechanism for
prospective project proponents; directs
the Secretary to establish prompt and
binding intermediate milestones and
ultimate deadlines for the review of, and
Federal authorization decisions relating
to, the proposed facility; and provides a
mechanism through which a project
proponent or any State where the
facility would be located may appeal to
the President for review, if an agency
fails to act within those deadlines or
denies an application. 16 U.S.C.
824p(h)(4), (h)(6). The statute also
directs the Secretary to prepare, in
consultation with the affected agencies,
a single environmental review
document to be used as the basis for all
decisions on the proposed project under
Federal law, and to determine, for each
Federal land use authorization that must
be issued, whether the duration of such
authorization is commensurate with the
facility’s anticipated use. 16 U.S.C.
824p(h)(5)(A); (h)(8)(A).
As discussed in the proposed rule, in
May 2023 DOE entered into an
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
implementing MOU with eight other
agencies to unlock these benefits. The
2023 MOU expanded upon prior efforts
to ensure pre-construction coordination
and provides updated direction to
Federal agencies in expediting the
siting, permitting, and construction of
electric transmission facilities. DOE
subsequently published a NOPR in
August 2023 to update and expand on
its existing pre-application mechanism
provided in regulations at 10 CFR part
900. Through this rule, DOE amends its
section 216(h) implementing regulations
to more effectively implement this
authority and better coordinate review
of Federal authorizations for proposed
interstate electric transmission facilities.
For the reasons explained in the
following sections, in this final rule,
DOE adopts its proposal in the NOPR,
with modifications discussed below.
III. Summary of the Final Rule
This final rule is needed for DOE to
update its regulations implementing
section 216(h) to establish the CITAP
Program, improve the IIP Process, and
provide for the coordinated review of
applications for Federal authorizations
necessary to site transmission facilities.
DOE’s previous implementing
regulations structured the IIP Process
around two anchor meetings: the Initial
and Close-Out meetings. To inform
Federal agency coordination, project
proponents were required to submit a
project summary, an affected
environmental resources and impacts
summary, a summary of early
identification of project issues, and data
including maps and geospatial
information. Additionally, the
regulations included a process for
identifying the NEPA lead agency and
for establishing a preliminary NEPA
review schedule. These regulations did
not establish DOE as the lead agency for
NEPA review, nor address important
environmental and resource reviews
under NHPA or ESA. Notably, these
regulations did not establish a process
through which DOE would set binding
milestones for environmental reviews
and Federal permitting and
authorization decisions.
In this final rule, DOE first establishes
a comprehensive and integrated CITAP
Program. The CITAP Program is the
vehicle through which DOE will
implement its authority as defined in
Section 216(h) of the FPA, beginning
with the IIP Process through the DOEled environmental review and including
DOE’s coordination of the schedule for
the Federal decisions on permits and
authorizations.
Under the CITAP Program, DOE: (i)
provides for an effective IIP Process to
PO 00000
Frm 00004
Fmt 4701
Sfmt 4700
facilitate timely submission of materials
necessary to inform Federal
authorizations and related
environmental reviews required under
Federal law; (ii) sets intermediate
milestones and ultimate deadlines for
the review of such authorizations and
environmental reviews; and (iii) serves
as the lead agency for the preparation of
a single environmental review
document in compliance with NEPA,
designed to serve the needs of all
relevant Federal entities and effectively
inform their corresponding Federal
authorization decisions. These elements
of the CITAP Program are described in
more detail throughout this rule.
Second, pursuant to the FPA, DOE
makes the IIP Process a mandatory
precondition for participation in the
CITAP Program. A project proponent’s
participation in the IIP Process is
necessary for the success of the other
elements of the CITAP Program and for
the Secretary’s satisfaction of the
statutory obligations imposed by section
216(h) and affords a unique opportunity
for project proponents to provide
essential information and to coordinate
with Federal entities prior to
submission of applications for Federal
authorizations. DOE has determined
that it will not be able to fulfill its role
as lead agency under section 216(h)—
including the establishment of binding
deadlines—for projects that do not
complete the IIP Process. DOE does not
require the participation of any Federal
or non-Federal entity in the IIP Process;
rather Federal entities have agreed to
participate through the 2023 MOU and
non-Federal entities may participate at
their discretion. As discussed further
below, DOE concludes that the benefits
of participating in the IIP Process, and
the resulting access to the CITAP
Program, justify the costs to project
proponents. The CITAP Program will
substantially accelerate the process by
which transmission projects are
permitted and developed, and the
benefits of the expected reduction in
permitting timelines are likely to
significantly exceed the cost of
participating in the IIP Process.
Third, this final rule improves the IIP
Process to ensure that it provides project
proponents and Federal entities an
opportunity to identify as early as
possible potential environmental and
community impacts associated with a
proposed project. The IIP Process is
intended to ensure that necessary
information is provided to the relevant
Federal entities in a timely and
coordinated fashion; it is also intended
to avoid the duplication of cost and
effort that project proponents and
Federal entities face in navigating the
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
series of authorizations necessary to site
a transmission line and to allow both
the project proponent and the Federal
entities to avoid time- and resourceconsuming pitfalls that would otherwise
appear during the application process.
Accordingly, DOE requires that project
proponents submit resource reports and
public participation and engagement
plans, developed with guidance from
Federal entities, and participate in a
series of iterative meetings to ensure
that Federal entities have ample
opportunities to provide this guidance.
The resource reports are intended to
develop data and materials that will
facilitate Federal entities’ review of the
project proponent’s applications under
the applicable Federal statutes. The
early engagement facilitated by the
submission of public participation and
engagement plans will inform a project
proponent’s development of a proposed
project. This early engagement begins
before an application is submitted to the
Federal Government and provides
opportunities for Tribes and
communities to express their views
early in the process and to share their
concerns directly with project
proponents. However, the IIP Process
does not relieve the relevant Federal
entities of their legal obligation to
comply with applicable requirements to
consult with Tribes and engage with
communities. This rule provides that
the total time for DOE reviews and
responses in the IIP Process is 185
days.5 Based on that timeline for DOE
decision-making, DOE expects that a
prepared and responsive project
proponent could complete the IIP
Process within a year.
Fourth, pursuant to Congress’s
express directive in section 216(h)(4),
DOE introduces the standard schedule
and project-specific schedules, through
which DOE will establish binding
intermediate milestones and ultimate
deadlines for Federal authorizations and
related environmental reviews. The
standard schedule identifies the steps
generally needed to complete decisions
on all Federal environmental reviews
and authorizations for a proposed
electric transmission project, including
recommended timing for each step so as
to allow final decisions on all Federal
authorizations within two years of the
publication of a notice of intent (NOI) to
prepare an environmental review
document. This document serves as a
template for the development of project5 This excludes meeting information summaries,
which DOE does not categorize as review and
response time that could impact a project timeline,
because preparation of required information for
subsequent IIP Process steps can happen in parallel.
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
specific schedules. During the IIP
Process, DOE and relevant Federal
entities will prepare a project-specific
schedule, informed by the standard
schedule, that establishes prompt and
binding intermediate milestones and
ultimate deadlines for the review of, and
Federal authorization decisions relating
to, a proposed electric transmission
project, accounting for relevant factors
particular to the specific proposed
project, including the need for early and
meaningful consultation with
potentially affected Indian Tribes and
engagement with stakeholders.
Fifth, DOE simplifies the
development of an administrative
record by incorporating the IIP Process
administrative file into a single docket
that contains all the information
assembled and utilized by the relevant
Federal entities as the basis for Federal
authorizations and related reviews. DOE
will maintain that docket, which will be
available to the public upon request
except as restricted due to
confidentiality or protected information
processes. Access to, and restrictions of
access to, the docket will be addressed
at the time of project-specific
implementation.
Sixth, DOE amends its regulations to
provide that DOE will serve as the lead
NEPA agency and that, in collaboration
with any NEPA joint lead agency 6
determined pursuant to procedures
established by these regulations and the
2023 MOU and in coordination with the
relevant Federal entities, DOE will
prepare a single environmental review
document to serve as the NEPA
document for all required Federal
authorizations. DOE will also serve as
lead for consultation under section 106
of the NHPA and section 7 of the ESA
for projects in the CITAP Program,
unless the relevant Federal entities
designate otherwise. As additional
projects utilize the CITAP Program, DOE
anticipates that it will be able to
improve upon its NEPA processes,
ultimately leading to greater efficiencies
for both project proponents and Federal
agencies. Relatedly, the rule provides
that DOE and the relevant Federal
entities shall issue, except where
inappropriate or inefficient, a joint
decision document.
Finally, DOE provides that the
primary scope of the CITAP Program is
6 As discussed in section V.D of this document,
DOE is replacing the term ‘‘NEPA co-lead agency’’
from the proposed regulatory text with ‘‘NEPA joint
lead agency’’ in this final rule. The change is nonsubstantive. For clarity and readability, DOE uses
the term ‘‘NEPA joint lead agency’’ throughout the
preamble in place of ‘‘NEPA co-lead agency’’ even
when discussing a comment or document that
originally referred to a ‘‘NEPA co-lead agency.’’
PO 00000
Frm 00005
Fmt 4701
Sfmt 4700
35315
on-shore high-voltage or regionally or
nationally significant transmission
projects that are expected to require
preparation of an environmental impact
statement (EIS) and establishes
procedures through which projects
outside of that primary scope can seek
a determination of qualifying-project
status from the Grid Deployment Office
on a case-by-case basis.
IV. Tribal Sovereignty
DOE affirms the sovereignty of
Federally recognized Indian Tribes and
confirms that this final rule makes no
changes to Federal agencies’
government-to-government
responsibilities. Tribal sovereignty
refers to Federally recognized Indian
Tribes’ original, inherent authority to
govern themselves, their lands, and
their resources. Because of their unique
status as sovereigns, Federally
recognized Tribes have a direct,
government-to-government relationship
with the Federal government. The
United States has a general, ongoing
trust relationship with Indian Tribes as
well as with the Native Hawaiian
Community. Neither section 216(h) nor
this final rule in any way alters that
relationship.
Tribal and Native Hawaiian
consultation is a process for
communication between the Federal
government and Indian Tribes and the
Native Hawaiian Community that is
grounded in the government-togovernment or the government-tosovereign relationship, respectively.
Tribal and Native Hawaiian
consultation may be required as part of
compliance with section 106 of the
NHPA, or may arise from other Federal
authorities such as Executive Order
13007 or the Presidential Memorandum
on Uniform Standards for Tribal
Consultation (2022). Agencies often
consult with Indian Tribes and the
Native Hawaiian Community in
conjunction with fulfilling their
obligations under NEPA. Consistent
with these requirements and authorities,
during implementation of the CITAP
Program, DOE commits to undertake
Tribal and Native Hawaiian
consultation as appropriate. Also as
appropriate, DOE commits to designate
Indian Tribes with special expertise
regarding a qualifying project, including
knowledge about sacred sites that the
project could affect, that are eligible, to
become cooperating agencies under
NEPA, and to consult with Indian
Tribes and Native Hawaiian
Organizations as required by the NHPA
in the Section 106 process. Finally, DOE
clarifies that the IIP Process, resource
reports, and other submissions are not
E:\FR\FM\01MYR2.SGM
01MYR2
35316
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
intended to, nor will they, satisfy DOE’s
or other Federal agencies’ legal
obligations and responsibilities under
the relevant statutes, such as NEPA,
NHPA, and ESA. The Federal agencies
remain legally responsible for their
compliance with the applicable statutes.
V. Terminology and Clarification
Changes
In this final rule, DOE has made a
number of changes to ensure consistent
use of terminology across part 900.
ddrumheller on DSK120RN23PROD with RULES2
A. ‘‘Project Area’’ v. ‘‘Study Corridor’’ v.
‘‘Route’’
The proposed rule used several terms
related to areas. In this final rule, DOE
has ensured that the usage of these
terms is consistent. DOE clarifies here
their meaning and use. For the area
containing the study corridors selected
by the project proponent for in-depth
consideration and the immediate
surroundings of the end points of the
proposed electric transmission facility,
DOE uses the term ‘‘project area.’’ For a
location within a project area where
multiple transmission line designs may
be contemplated, DOE used the term
‘‘study corridor’’; within the project
area, there may be multiple study
corridors. Within a given study corridor,
DOE refers to ‘‘potential routes’’ or
‘‘route segments’’; within the study
corridor, there may be multiple
potential routes or route segments.
Notably, DOE revises the definition of
project area from what was proposed by
replacing ‘‘containing all study
corridors’’ with ‘‘containing the study
corridors selected by the project
proponent for in-depth consideration’’
to clarify the scope of this term.
Additionally, to clarify the role of study
corridors, DOE added to the study
corridors definition that ‘‘study corridor
does not necessarily coincide with
‘permit area,’ ‘area of potential effect,’
‘action area,’ or other defined terms that
are specific to types of regulatory
review.’’
The proposed rule used multiple
terms to refer to a route of an electric
transmission line that is considered
during the IIP Process, including
‘‘proposed route’’ and ‘‘potential route.’’
This final rule replaces these
synonymous terms with ‘‘potential
route.’’
B. ‘‘Potential Project’’ v. ‘‘Qualifying
Project’’ v. ‘‘Transmission Facility’’
The proposed rule used several terms
to refer to an electric transmission
facility that is proposed to be sited and
constructed, including ‘‘transmission
facility’’ and ‘‘electric transmission
facility.’’ This final rule replaces these
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
terms with ‘‘proposed electric
transmission facility,’’ which is
shortened to ‘‘proposed facility’’ when
the identity of the facility is clear from
the context.
Similarly, the proposed rule included
a variety of phrases to refer to an electric
transmission project, including
‘‘qualifying project,’’ ‘‘electric
transmission project,’’ ‘‘proposed
qualifying project,’’ ‘‘proposed
undertaking’’ and ‘‘project.’’ This final
rule replaces these terms with
‘‘proposed electric transmission
project,’’ which is shortened to
‘‘proposed project’’ when the identity of
the project is clear from the context.
While the revision replaces the defined
term ‘‘qualifying project’’ in a number of
instances, the revision has no
substantive effect, because any proposed
electric transmission project that is
accepted into the IIP Process must
involve a proposed electric transmission
facility that is a qualifying project.
C. ‘‘Plants’’ v. ‘‘Vegetation’’
The proposed rule used several terms
to describe plant life, such as ‘‘plant
life,’’ ‘‘plants’’ and ‘‘vegetation.’’ DOE
has revised this final rule to consistently
use the term ‘‘plants,’’ except where the
rule uses an established term of art such
as ‘‘vegetation management’’ or for
consistency with Resource Report
naming across agencies.
D. ‘‘NEPA Co-Lead Agency’’ vs ‘‘NEPA
Joint Lead Agency’’
The proposed rule used the term
‘‘NEPA co-lead agency’’ to refer to a
Federal entity that may be designated
under § 900.11 to share the
responsibilities of DOE as lead agency
in preparing an environmental review
document. DOE has revised the final
rule to replace that term with ‘‘NEPA
joint lead agency’’ to better conform
with the terminology used in NEPA, as
amended by Section 321 of the Fiscal
Responsibility Act of 2023 (Pub. L. 118–
5). The change is non-substantive and
only reflects a difference in terminology.
VI. Discussion of Comments
A. General
In response to the NOPR, DOE
received 50 sets of comments from the
following persons and groups:
Advanced Energy United (AEU), Alan
Leiserson, American Clean Power
Association (ACP), American Council
on Renewable Energy (ACORE),
American Electric Power Service
Corporation (AEP), Americans for a
Clean Energy Grid (ACEG), Arizona
Game and Fish Department (AZGFD),
Arizona State Historic Preservation
PO 00000
Frm 00006
Fmt 4701
Sfmt 4700
Office (Arizona SHPO), California
Energy Commission and California
Public Utilities Commission (CEC/
CPUC), Center for Biological Diversity
(CBD), Clean Air Task Force (CATF),
Clean Energy Buyers Association
(CEBA), ClearPath, Colorado Governor’s
Office, Conrad Ko, Conservation and
Renewable Energy Coalition (CARE—
comprised of the National Wildlife
Federation, The National Audubon
Society, Environmental Law and Policy
Center, and The Nature Conservancy),
Delaware Division of Historical and
Cultural Affairs (Delaware SHPO),
EarthGrid PBC, Edison Electric Institute
(EEI), Environmental Defense Fund
(EDF), Gallatin Power Partners, LLC
(Gallatin Power), Grid United LLC (Grid
United), Idaho Governor’s Office of
Energy and Mineral Resources, Idaho
Power, James Birdwell, Kentucky SHPO,
Kris Pastoriza, Land Trust Alliance
(LTA), Large Public Power Council, Los
Angeles Department of Water and Power
(LADWP), mkron mkron, National
Association of Manufacturers, National
Association of Tribal Historic
Preservation Officers (NATHPO), New
Mexico Department of Cultural Affairs
Historic Preservation Division (NM
SHPO), New York Transmission Owners
(NYTO), New York University School of
Law Institute for Policy Integrity (Policy
Integrity), Niskanen Center, Oceti
Sakowin Power Authority (OSPA), Pew
Charitable Trusts, PJM Interconnection,
LLC (PJM), Public Interest Organizations
(PIOs, comprised of Earthjustice,
Natural Resources Defense Council, NW
Energy Coalition, Southern
Environmental Law Center, Sustainable
FERC Project, and WeACT for
Environmental Justice) (PIO), Santa
Rosa Rancheria Tachi Yokut Tribe, Scott
Cooley, Solar Energy Industries
Association (SEIA), State of Colorado
Governor’s Office, State of Idaho Energy
Office, Stoel Rives, LLP, StopPATH WV,
Todd Simmons, VEIR, Inc, and an
anonymous commenter.
Of the 50 comments, 27 expressed
general support for the proposed rule
and many supported specific aspects,
including the IIP Process, the Federal
decision-making timelines, and the
requirement for the thirteen resource
reports.7 Commenters specifically
7 Advanced Energy United; American Clean
Power Association; American Council on
Renewable Energy; American Electric Power
Service Corporation; American Electric Power
Service Corporation; Americans for a Clean Energy
Grid; Arizona Game and Fish Department;
California Energy Commission joint with California
Public Utilities Commission; Clean Air Task Force;
Clean Energy Buyers Association; Colorado Energy
Office; Conrad Ko; Delaware State Historic
Preservation Office; Edison Electric Institute;
Environmental Defense Funds; Gallatin Power
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
lauded the resource reports for their
early and meaningful public
engagement components, their
effectiveness in coordinating decisionmaking across different Federal
agencies, and their essential role in
streamlining environmental permitting
processes to two years.
Six commenters, NATHPO, Santa
Rosa Rancheria Tachi Yokut Tribe,
StopPath WV, James Birdwell,
ClearPath, and mkron mkron were not
supportive of the rulemaking.
The comments and DOE’s responses
are discussed in detail in the subsequent
subsections.
B. Purpose and Scope of Rule
DOE’s Proposal
In the NOPR, DOE proposed to
establish the CITAP Program; made the
IIP Process a mandatory precondition to
participate in the CITAP Program;
described the procedures and timing of
the IIP Process; provided a process to set
deadlines and milestones for projects;
designated DOE as the lead NEPA
agency for the purposes of preparing a
single environmental impact statement;
provided for earlier coordination of and
consultation between relevant Federal
entities, relevant non-Federal entities,
and others pursuant to section 106 of
the NHPA; designated DOE as a co-lead
agency for the section 106 process; and
clarified applicability to qualifying
projects. Finally, DOE proposed to
include a provision stating that
participation in the IIP Process does not
alter any requirements to obtain
necessary Federal authorizations for
electric transmission facilities nor does
it alter any responsibilities of the
relevant Federal entities for
environmental review or consultation
under applicable law.
ddrumheller on DSK120RN23PROD with RULES2
Summary of Public Comments
DOE received several comments
regarding DOE’s authority to establish
the CITAP Program, the ability of the
proposed CITAP Program to meet the
goals established by Congress in EPAct
2005, and the scope of the proposed
CITAP Program.
Regarding DOE’s authority to
establish the CITAP Program, EDF,
PIOs, and CATF observed that the
CITAP Program is consistent with the
statutory language of section 216(h) of
the FPA and with the 2023 MOU. Pew
Charitable Trusts expressed their
Partners, LLC; Grid United, LLC; New York
Transmission Owners; Niskanen Center; PJM
Interconnection, L.L.C.; Public Interest
Organizations; Scott Cooley; Solar Energy Industries
Association; State of Idaho; Stoel Rives; The Pew
Charitable Trusts; and Todd Simmons.
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
support for several key elements of the
proposed rule, including the creation of
a new framework for coordinated
Federal authorizations.
PIOs commented that DOE’s proposed
rule appropriately effectuates the
congressional intent underlying section
216(h) of the FPA, and that DOE has
sufficiently explained its proposed
changes in the rule text by
demonstrating awareness of changing its
policies and providing sound reasons
for doing so. PIOs also noted that
although agencies do not need to
demonstrate that the reasons for the new
policies are better than the reasons for
the old policies, they believed DOE has
done so in the proposed rule. On the
other hand, NATHPO and the Santa
Rosa Rancheria Tachi Yokut Tribe
requested that DOE withdraw the
proposed rule. NATHPO and the Santa
Rosa Rancheria Tachi Yokut Tribe
found the proposed rule ‘‘opaque’’ and
stated that they were unable to
determine if the rule represented a
threat to Tribal Nations’ cultural
resources and sacred places.
Additionally, NATHPO and the Santa
Rosa Rancheria Tachi Yokut Tribe
objected to the rule on the grounds that
it contained ‘‘numerous fundamental
flaws,’’ but only provided two
examples, one concerning the
Communities of Interest report and one
concerning the Tribal Interests report.
Specifically, regarding Communities of
Interest, the commenters expressed
concern not with the proposed rule text,
but with a comment from DOE staff
which the commenters believed
indicated this resource report would
fulfill NHPA ‘‘Section 106
responsibilities for determining the
impact of projects on Tribal Nations’
cultural resources and sacred places.’’
Regarding Resource Report 13, the
commenters expressed concerns with a
comment from DOE staff which the
commenters believe indicated, contrary
to the proposed rule text, that this
resource report would not include ‘‘the
effect of projects on Tribal Nations’
cultural resources.’’ These concerns are
discussed in further detail and
addressed in sections VI.J and VI.L.xiii
of this document. Finally, NATHPO and
the Santa Rosa Rancheria Tachi Yokut
Tribe argued that DOE did not
effectively engage with Tribal Historic
Preservation Officers (THPOs) while
drafting the proposed rule.
Regarding the ability of the proposed
CITAP Program to meet the stated goals
of coordinating Federal authorizations
and completing environmental review
within a 2-year schedule, PIOs stated
they believe the proposed rule will
improve efficiency in Federal permitting
PO 00000
Frm 00007
Fmt 4701
Sfmt 4700
35317
for transmission projects that are
urgently needed to address the climate
crisis, improve reliability, and reduce
congestion, and that the rule will
accelerate the development of
infrastructure that will provide the
foundation for a clean and equitable
energy grid. Pew Charitable Trusts
stated that it believes that the proposed
rule offers an appropriately streamlined
approach to coordinating and
facilitating transmission project
authorizations. Pew Charitable Trusts
further noted that previous studies of
various types of infrastructure projects
and environmental reviews suggest that
an open, transparent, and
comprehensive review process can work
to the benefit of the public and
developers. Pew Charitable Trusts
supported that the schedule can be
altered by DOE depending on the
complexity of the review and other
factors. ACEG recommended adding
‘‘prompt and binding’’ to describe the
milestones and deadlines DOE will set
in the schedule for Federal decisionmaking. The State of Idaho agreed that
Federal efforts to reduce the time
required for transmission project
developers to receive decisions on
Federal authorizations are needed and
agreed that such actions should be
encouraged. However, it also cautioned
that those efforts should be
implemented in a way that avoids
diminishing the benefits of such reform
by the addition of new permitting
processes or requirements. In contrast,
StopPATH WV asked why the NOPR
was written in a way that presumes
project approval, expressed concern that
it was not clear how this rulemaking
would speed up timelines, and asserted
that if agencies could not change the
project or deny it, then this would be a
bureaucratic waste of time. Kris
Pastoriza requested clarification on how
the CITAP Program would change the
jurisdiction of the Federal Energy
Regulatory Commission (FERC).
Regarding DOE’s role as a lead agency
for environmental review and
preparation of a single EIS, DOE
received several comments in support of
the role and the consistency of this
designation with existing regulations
and legislation. EDF commented that
the rule is consistent with Section 107
of the Fiscal Responsibility Act of 2023,
which amended NEPA to require the
designation of a lead agency to
coordinate and schedule environmental
review, as well as the related
amendments to NEPA implementing
regulations proposed by the Council for
Environmental Quality. AEP, SEIA, Pew
Charitable Trusts, EEI, and CEBA each
E:\FR\FM\01MYR2.SGM
01MYR2
35318
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES2
commented in support of DOE serving
as the lead agency for developing a
single environmental review document.
SEIA noted that currently a lack of
coordination among agencies causes
unpredictability and inefficiency in the
environmental review process and
effective coordination will provide a
more predictable and efficient process,
a reduction in unnecessary delays and
costs, and heightened allowance for
more robust environmental reviews.
ACEG recommended replacing the
phrase ‘‘environmental impact
statement’’ with ‘‘NEPA document’’
because that phrasing more closely
matches the statutory language in
section 216(h)(5)(A) and because it
accounts for the breadth of reviews
organized under the CITAP Program.
EEI recommended that DOE must also
rely on the expertise of Federal agencies
to ensure certainty and minimize risk of
post record decision litigation.
Regarding the authority of the
Director of the Grid Deployment Office
to waive requirements, PIOs
recommended establishing specific,
transparent criteria by which the
Director of the Grid Deployment Office
can waive the review requirements for
a proposed project that are deemed
unnecessary, duplicative, or
impracticable and further argued for the
establishment of an appeal process for
said waivers. PIOs further provided that
if DOE declines to implement criteria
and an appeals process that this final
rule should eliminate the waiver
provision.
DOE Response
In this final rule, DOE retains the
proposal in the NOPR to establish the
CITAP Program, which requires the IIP
Process for CITAP Program
participation, sets binding schedules for
Federal decision making, and through
which DOE will serve as lead agency for
environmental review and document
preparation. In response to comments,
DOE makes minor changes to this final
rule for clarification but retains the full
intent and scope of the proposed rule.
With respect to NATHPO’s comment
regarding outreach, DOE believes that it
engaged with appropriate entities
regarding the rulemaking. DOE met with
the Advisory Council for Historic
Preservation in developing the language
of the proposed rule and specifically
with respect to addressing potential
impacts on cultural resources and
consistency of the CITAP Program with
the requirements of the NHPA. Further,
DOE developed the NOPR with
substantive engagement from other
Federal entities through the interagency
review process. DOE then provided a
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
45-day public comment period during
which DOE noticed and provided a
public webinar open to anyone to
attend, and organized briefings with
interested groups to introduce the
proposed rule and listen to comments,
to which NATHPO, THPOs, and State
Historical Preservation Officers (SHPOs)
were invited. In this final rule, DOE has
made changes to provide additional
clarity in the rule text and resolve
ambiguity when possible. In particular,
DOE clarifies certain issues relating to
Tribal sovereignty, cultural resources,
and the section 106 process in response
to specific concerns raised by NATHPO,
Santa Rosa Rancheria Tachi Yokut
Tribe, and other commenters.
In response to the State of Idaho’s
concerns and Kris Pastoriza’s question
regarding DOE implementing its
coordinating authority, this final rule
neither establishes new permitting
requirements nor alters FERC’s siting
authority over transmission lines.
Rather, DOE will be coordinating
agencies’ exercise of their existing
authorities. This final rule maintains the
NOPR provision that the IIP Process
does not alter any requirements to
obtain necessary Federal or non-Federal
authorizations for electric transmission
facilities. Similarly, DOE disagrees with
the assertion that the proposed rule
presumes project approval. The CITAP
Program as described in the proposed
rule and confirmed in this final rule
coordinates and sets a schedule for
Federal decision-making for qualified
projects; it does not presume or require
the outcome of such Federal decisions.
Regarding DOE’s schedule setting role
in the CITAP Program, DOE agrees with
ACEG’s recommendation to align the
language of this final rule with the
authorizing statute and includes
‘‘prompt and binding’’ in the
description of milestones in this final
rule.
Regarding DOE serving as lead agency
for environmental review and
development of a single EIS designed to
serve the needs of all relevant Federal
agencies and inform all Federal
authorization decisions on the proposed
qualifying project, DOE acknowledges
that it will rely on other Federal
agencies’ expertise and believes the
CITAP Program and IIP Process
confirmed in this final rule will ensure
this occurs. DOE agrees with ACEG’s
recommendation to align the language
with the authorizing statute and changes
‘‘EIS’’ to ‘‘environmental review
document’’ throughout this final rule.
DOE makes no changes to the
proposal to allow the Director of the
Grid Deployment Office to waive
requirements of the CITAP Program, nor
PO 00000
Frm 00008
Fmt 4701
Sfmt 4700
does DOE adopt specific criteria for
such waivers. The purpose of the CITAP
Program and IIP Process is to allow DOE
to perform a coordinating function for
electric transmission facilities seeking
Federal authorizations. Giving the
Director the discretion to waive
requirements of the CITAP Program
helps ensure that this coordination
function promotes efficiency and
reduces duplication, as Congress
intended in FPA section 216(h). In
addition, it is important to note that a
waiver granted by the Director under the
CITAP Program would not waive
Federal requirements for authorizations
or permits. For these reasons, DOE is
not persuaded that a lack of specific
criteria for waivers in this final rule will
substantively harm any entity or party.
C. Qualifying Projects
DOE’s Proposal
Section 216(h) of the FPA authorizes
DOE to perform its coordinating
function for all transmission facilities
seeking Federal authorizations. In the
NOPR, DOE proposed to prioritize the
subset of these facilities that benefit the
most from DOE’s coordinating role and
provide the most benefits to the
American public from expeditious
environmental review.
In the NOPR, DOE proposed to define
the subset of proposed electric
transmission facilities for which to
perform its coordinating function—
called ‘‘qualifying projects’’—by
defining two types of qualification:
qualification by attribute and
qualification by request. For
qualification by attribute (set out in
paragraph (1) of the proposed definition
of ‘‘qualifying project’’), DOE proposed
in the NOPR to categorize a proposed
electric transmission facility as a
‘‘qualifying project’’ based on the
presence of certain enumerated
attributes: it must be high-voltage
(defined as 230 kV or above) or
‘‘regionally or nationally significant’’; it
will be used for the transmission of
electric energy in interstate or
international commerce for sale at
wholesale; it will need one or more
Federal authorizations expected to
require preparation of an environmental
impact statement (EIS) pursuant to
NEPA; it will not require authorization
under section 8(p) of the Outer
Continental Shelf Lands Act; the
developer will not require a
construction or modification permit
from FERC pursuant to section 216(b) of
the FPA; and the proposed transmission
facility will not be wholly located
within the Electric Reliability Council of
Texas interconnection.
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES2
DOE proposed that, if a proposed
electric transmission facility did not
qualify for the CITAP Program by
attribute it could still qualify by request,
as provided by paragraph (2) of the
proposed definition of qualifying project
and under the process set out in
proposed § 900.3 of the NOPR. Under
that process, DOE proposed that the
project proponent file a request for
coordination under the CITAP Program
with the Director of the Grid
Deployment Office. Then, the Director
of the Grid Deployment Office, in
consultation with the relevant Federal
entities, determine, within 30 calendar
days of receipt of the request, whether
the proposed electric transmission
facility is a ‘‘qualifying project.’’ In the
NOPR, DOE proposed that proposed
electric transmission facilities requiring
a permit from FERC could be qualifying
projects if the request came from the
FERC Chair. DOE also proposed that
projects proposed for authorization
under section 8(p) of the Outer
Continental Shelf Lands Act (43 U.S.C.
1331 et seq.) independent of any
generation project may be qualifying
projects at the discretion of MOU
signatory agencies.
DOE proposed to exclude from both
types of qualification, and from the
CITAP Program altogether, any project
proposed to be authorized under section
8(p) of the Outer Continental Shelf
Lands Act in conjunction with a
generation project and any project for
which the proposed transmission
facility is wholly located within the
Electric Reliability Council of Texas
interconnection.
Summary of Public Comments
DOE received several comments on
the proposed definition of ‘‘qualifying
project.’’
Starting with the qualification by
attribute in paragraph (1) of the
definition, DOE received several
comments on the specific proposed
attributes. Both AEP and Niskanen
Center supported the proposed highvoltage threshold of 230 kV or above.
On the other hand, CEC/CPUC opposed
limiting eligibility based on a voltage
threshold and instead suggest
expanding eligibility to proposed
electric transmission facilities at any
voltage level.
With regard to DOE’s proposal for
qualification by attribute to require that
a proposed electric transmission facility
that does not satisfy the voltage
threshold must be ‘‘regionally or
nationally significant,’’ both Niskanen
Center and ClearPath asserted that this
alternative criterion is ambiguous.
ClearPath recommended removing the
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
alternative criterion altogether and only
allowing for high-voltage transmission
lines (i.e., those that satisfy the 230 kV
or above threshold) to be ‘‘qualifying
projects.’’ Niskanen Center
recommended instead that DOE adopt
factors that it will consider when
determining whether a proposed
transmission facility is ‘‘regionally or
nationally significant.’’ Specifically,
Niskanen Center suggested these factors:
‘‘(i) a reduction in the congestion costs
for generating and delivering energy; (ii)
a mitigation of weather and variable
generation uncertainty; (iii) an
enhanced diversity of supply; (iv) any
reduced or avoided carbon emissions
from the increased use of clean energy;
and (v) an increased market liquidity
and competition.’’
Moving to the other attributes, CEC/
CPUC asked DOE to clarify how it will
determine whether all or part of a
proposed electric transmission facility
will be ‘‘used for the transmission of
electric energy in interstate or
international commerce for sale at
wholesale.’’ Further, CEC/CPUC
recommended that DOE expand the
attribute list to include a proposed
electric transmission facility that will be
used in intrastate commerce because,
according to CEC/CPUC, intrastate
transmission lines can traverse lands
managed by several Federal agencies,
such that DOE coordination under the
CITAP Program would provide benefits
to these projects as well. In the
alternative, CEC/CPUC asked that DOE
clarify how a proposed intrastate
transmission facility, such as an
onshore, intrastate transmission facility
built to support offshore wind
development, that traverses Federal
lands, could be a ‘‘qualifying project.’’
On the proposed attribute that the
proposed electric transmission facility
would need one or more Federal
authorizations that require preparation
of an EIS pursuant to NEPA, AEP
supported the proposal whereas
Niskanen Center and PIOs
recommended expanding the proposal
to include proposed electric
transmission facilities for which
preparation of either an environmental
assessment (EA) or an EIS is anticipated.
PIOs also encouraged DOE to define
which proposed electric transmission
facilities are ‘‘expected’’ to require
preparation of an EIS and which are
expected to require preparation of an
EA. In support of the recommendation
to expand eligibility to include
proposed electric transmission facilities
for which preparation of an EA is
expected (in addition to those for which
preparation of an EIS is expected), PIOs
argued that FERC regulations only
PO 00000
Frm 00009
Fmt 4701
Sfmt 4700
35319
require preparation of an EA for
proposed electric transmission facilities
sited within an existing right-of-way. If
DOE adopts the proposal without PIOs’
recommended expansion, PIOs
explained that such proposed electric
transmission facilities may be excluded
from the CITAP Program, resulting in
the CITAP Program not providing its
full purported benefits. Similar to
Niskanen Center and PIOs, CEC/CPUC
recommended that DOE expand the
definition of ‘‘qualifying project’’ such
that any proposed electric transmission
facility for which multiple Federal
agency approvals will be required are
eligible, regardless of what type of
document is required under NEPA.
On qualification by request—i.e.,
when a project proponent seeks
qualifying-project status through a
request to the Director of the Grid
Deployment Office—several
commenters expressed concern about
DOE’s level of discretion in the
proposal. EEI requested examples of the
types of proposed electric transmission
facilities that may be deemed
‘‘qualifying projects’’ by request. PIOs
argued that the proposal appears to be
wholly discretionary, making it difficult
for project proponents, relevant
regulators, and members of the public to
understand what proposed electric
transmission facilities may be eligible to
participate in the CITAP Program. PIOs
suggested that DOE establish criteria for
how DOE will evaluate requests, which
would assist project proponents in
making well-grounded requests for
participation in the CITAP Program.
According to PIOs, these criteria should
be: if the proposed electric transmission
facility will benefit from DOE’s
coordination in terms of expeditious
authorizations; if DOE’s coordination
will provide benefits that exceed the
costs; and, if Federal and non-Federal
regulators have sufficient resources to
dedicate to the project’s participation in
the CITAP Program. PIOs also suggested
that DOE require project proponents to
explain what portions of their proposed
electric transmission facility do not
meet the ‘‘qualifying project’’ definition
(i.e., the attributes) and how the CITAP
Program will facilitate Federal
authorizations for the project or be
otherwise beneficial. Further, PIOs
recommended that DOE adopt a
requirement that the Director of the Grid
Deployment Office explain in writing
the determination of whether a project
is deemed a ‘‘qualifying project’’ by
request. PIOs also recommended that if
DOE rejects a request to participate in
the CITAP Program, project proponents
should be allowed to appeal the
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
35320
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
decision to the Secretary of Energy.
Similarly, ACP commented that the
proposed rule lacked clarity regarding
what can qualify as an ‘‘other project’’
and recommended that DOE provide
further detail on the aspects which it
will consider when making this
determination.
As proposed, qualification by request
included a limitation in § 900.3(d): for a
proposed electric transmission facility
seeking a permit from FERC pursuant to
section 216(b) of the Federal Power Act,
DOE may only consider a request for
coordination if the requestor is FERC
acting through its chair. ACORE
recommended that DOE provide more
detailed guidance for this category of
proposed electric transmission facilities
and for DOE to authorize relevant
project proponents to submit a petition
requesting such a request from the FERC
Chair. Likewise, CEBA urged DOE to
clarify the relationship between the
section 216(b) and section 216(h)
processes and to explain how the FERC
Chair can request that a proposed
electric transmission facility be eligible
to participate in the CITAP Program
under section 216(h). Both qualification
by attribute and qualification by request
included limitations related to offshore
transmission facilities. For qualification
by attribute, one listed attribute
provided that the proposed electric
transmission facility would not require
authorization under section 8(p) of the
Outer Continental Shelf Lands Act.
Likewise, for qualification by request,
DOE proposed to exclude electric
transmission facilities proposed to be
authorized under section 8(p) of the
Outer Continental Shelf Lands Act in
conjunction with a generation project.
However, projects proposed to be
authorized under section 8(p) of the
Outer Continental Shelf Lands Act
could be allowed at the discretion of the
MOU signatory agencies (as defined in
the proposed rule) if the proposed
offshore transmission facility is
independent of any generation project.
A number of commenters expressed
concerns regarding DOE’s treatment of
proposed offshore transmission
facilities. Broadly, ACP, ACORE, and
PIOs contended that DOE must explain
why the limitations on offshore
transmission facilities are included and
how the CITAP Program will apply to
offshore transmission facilities in
practice. ACP and ACORE suggested
that DOE establish a process to allow
potential State-proposed transmission
facilities to participate in the CITAP
Program before a project developer is
selected and include a process to enable
the Bureau of Ocean Energy
Management or a State to engage or
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
request that a project participate in the
CITAP Program.
More specific to DOE’s proposal,
NYTOs opposed the offshore
transmission facility-related attribute,
asserting that its inclusion prevents
proposed offshore transmission facilities
from benefiting from the CITAP Program
for project sections located closer to
shore as well as for project sections that
fall under the scope of the Outer
Continental Shelf Lands Act. PIOs
suggested removing the limitations in
qualification by request and instead
allowing for proposed offshore
transmission facilities to take advantage
of the CITAP Program without the
approval of the MOU signatories. At a
minimum, PIOs suggested removing the
limitation that proposed offshore
transmission facilities tied to generation
projects cannot participate in the CITAP
Program. Moreover, both PIOs and
ACORE requested that DOE revise its
proposal from requiring agreement from
all MOU signatories and instead only
requiring agreement from relevant MOU
signatories participating in the
environmental review or authorization.
Finally, other commenters proposed
revisions to DOE’s proposed definition
of ‘‘qualifying project’’ based on
advanced transmission technologies and
undergrounding. VEIR recommended
that DOE include superconductors in its
definition of ‘‘qualifying projects’’
because, according to VEIR, a
superconductor can transfer more power
at lower voltages than qualifying highvoltage transmission lines. EarthGrid
asserted that underground transmission
projects should be considered as a
distinct category. And CBD suggested
that DOE require that a proposed
electric transmission facility be strictly
necessary and that non-transmission
alternatives could not adequately
address the issue addressed by the
proposed electric transmission facility
before allowing the project to participate
in the CITAP Program.
DOE Response
In this final rule, DOE retains the
proposal in the NOPR to provide two
types of qualification (qualification by
attribute and qualification by request)
for proposed electric transmission
facilities to be ‘‘qualifying projects.’’ In
response to commenters, DOE is making
the following revisions to the details of
those two types of qualification.
First, consistent with commenters’
suggestions, DOE has adopted factors
that DOE may consider when
determining that a proposed electric
transmission facility is a qualifying
project. For qualification by attribute,
this final rule includes factors that DOE
PO 00000
Frm 00010
Fmt 4701
Sfmt 4700
may consider when assessing if a
proposed electric transmission facility is
regionally or nationally significant.
Similarly, for qualification by request,
this final rule includes factors that DOE
may consider when assessing if a
proposed electric transmission facility is
a qualifying project. Second, this final
rule removes the requirement that
projects seeking a permit from FERC
under FPA section 216(b) may only be
accepted into the CITAP Program if
requested by FERC acting through its
chair and states that the coordination
between FERC and DOE on projects
seeking permits under FPA section
216(b) will be consistent with the
relevant delegation order governing
DOE’s coordination authority under
FPA section 216(h), which may change
from time to time. Third, this final rule
also states that if DOE does not
determine that a project is qualifying
project, DOE will provide the reasons
for its finding in writing.
DOE believes that the definition of
‘‘qualifying project’’ adopted in this
final rule appropriately balances the
value of focusing DOE’s resources on
those proposed electric transmission
facilities for which Federal coordination
will be most impactful with the aims of
the broad grant of authority to DOE
under FPA section 216(h). By initially
limiting the definition of ‘‘qualifying
project’’ to those proposed electric
transmission facilities that qualify by
attribute, i.e., those that are high-voltage
or regionally or nationally significant
and that possess the other listed
attributes, DOE is targeting for Federal
coordination those complex proposed
electric transmission facilities that will
reap the greatest benefits from the
CITAP Program. DOE believes that these
proposed electric transmission facilities
are also likely to provide substantial
benefits to consumers in the form of
congestion relief, emissions reductions,
and increased reliability and resilience,
among other benefits, to ensure reliable,
affordable power can be delivered to
consumers when and where they need
it. Qualification by request provides
DOE with additional flexibility to
consider whether projects that do not
meet the targeted attributes may be
appropriate for participation in the
CITAP Program as well, consistent with
DOE’s authority under section 216(h) to
coordinate for all transmission facilities
seeking Federal authorizations.
As for specific aspects of the NOPR
proposal, starting with qualification by
attribute and the voltage threshold
therein (i.e., proposed electric
transmission facilities must be 230 kV
or above), DOE declines to adopt the
suggestion by CEC/CPUC to expand
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
eligibility to proposed transmission
facilities at any voltage level. Such an
expansion, although permissible by the
statute, would not be the most effective
use of DOE’s authority because it would
likely result in DOE providing
coordination for proposed transmission
facilities that would benefit less from
the program. For example, DOE could
be obligated to provide coordination for
less complex proposed electric
transmission facilities for which there is
a low risk of protracted Federal
authorization and review timelines and
thereby have fewer resources to dedicate
to those transmission facilities with
more complex permitting requirements
and/or more Federal authorizations and
thus more risk of protracted review
timelines in the absence of DOE
coordination. Nonetheless, DOE
acknowledges that voltage alone does
not determine complexity nor whether
the proposed transmission facility may
benefit from participation in the CITAP
Program. That is why this final rule
provides multiple avenues for lowervoltage proposed transmission facilities
to be ‘‘qualifying projects,’’ whether
because they are ‘‘regionally or
nationally significant’’ or because they
are determined to be qualifying projects
by request to the Director of the Grid
Deployment Office, on a case-by-case
basis. In addition, satisfying the highvoltage threshold alone does not make
a proposed transmission facility a
‘‘qualifying project;’’ it still must
demonstrate the attributes listed in this
final rule.
As for the alternative criterion under
qualification by attribute—whether the
proposed transmission facility is
‘‘regionally or nationally significant’’—
DOE declines to remove this criterion
but agrees that the proposal was
ambiguous and therefore adopts
clarifying revisions in this final rule.
DOE believes that this alternative to the
voltage threshold is important to ensure
that lower-voltage transmission facilities
that may benefit from participation in
the CITAP Program have an avenue to
be ‘‘qualifying projects,’’ as explained in
the prior paragraph. Nevertheless, DOE
appreciates commenters’ requests for
greater transparency and thus adopts
factors to guide DOE’s determination
whether a proposed transmission
facility is ‘‘regionally or nationally
significant.’’
In particular, DOE adopts regulations
in this final rule that provide that, in
determining whether a proposed
transmission facility is ‘‘regionally or
nationally significant,’’ DOE will
consider whether a proposed
transmission facility will reduce
congestion costs, mitigate uncertainty,
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
and enhance supply diversity. These
factors are consistent with the
overarching goals of focusing the CITAP
Program on proposed transmission
facilities for which DOE’s coordination
will be most impactful. The adopted
regulations provide that DOE may
consider other factors as well. This
discretion is important to ensure that
DOE has flexibility to best use its
resources to provide Federal
coordination where consistent with the
goals of the CITAP Program and
available resources. As explained in
DOE’s 2023 Needs Study, transmission
infrastructure improvements can benefit
consumers by improving grid reliability,
resource adequacy, and resilience of the
power system, as well as reducing
congestion and losses and enabling
access to clean, diverse energy supply.
While transmission that addresses
unnecessarily high costs to consumers
may be regionally or nationally
significant, so too may be transmission
that reduces the vulnerability of the
electric system to disruptive events,
which risk high costs and service
interruptions. The benefits of
transmission also extend beyond the
power system—to increased
employment, tax revenues, and other
economic development benefits. These
benefits are all relevant to DOE’s
determination of whether a transmission
line is ‘‘regionally or nationally
significant.’’
Although Niskanen Center suggested
two additional factors for DOE to list as
part of its determination as to whether
a proposed electric transmission facility
is ‘‘regionally or nationally significant’’
beyond those adopted herein
(specifically focused on reduced or
avoided carbon emissions and increased
market liquidity and competition from
the proposed electric transmission
facility), DOE declines to adopt
additional factors. For one, project
proponents are unlikely to have
substantial information at the stage of
development recommended for
initiation of the IIP Process for DOE to
evaluate vis-a`-vis these recommended
factors. If such information is available,
though, DOE may nevertheless consider
it because, as explained above, DOE is
maintaining discretion to consider other
factors as part of its assessment of
whether a proposed transmission
facility is ‘‘regionally or national
significant.’’
As for the proposed attribute
concerning whether all or part of a
proposed transmission facility will be
‘‘used for the transmission of electric
energy in interstate or international
commerce for sale at wholesale,’’ DOE
declines to provide further clarification
PO 00000
Frm 00011
Fmt 4701
Sfmt 4700
35321
in this final rule because this
determination will be made based on
the facts and circumstances of the
proposed electric transmission facility
seeking DOE coordination at the time of
application. DOE expects that this
determination will be informed by
relevant precedent interpreting similar
language in other provisions of the FPA,
though DOE is not bound by that
precedent in interpreting its own
regulatory language.
DOE declines to expand the listed
attributes of a qualifying proposed
electric transmission facility to also
include intrastate transmission
facilities. As previously explained,
DOE’s intent in defining a subset of
electric transmission facilities for which
DOE will conduct Federal coordination
is to focus on where the CITAP Program
is likely to be most impactful. While
intrastate transmission facilities can
have significant benefits, they are
generally less likely to be the types of
facilities that DOE expects will reap the
greatest benefits from DOE’s
coordination or that would provide the
greatest benefits to consumers as a result
of more efficient permitting of critical
transmission infrastructure.
Nonetheless, DOE does not prohibit
proponents of intrastate transmission
facilities (e.g., high-voltage intrastate
transmission facilities that may require
multiple Federal authorizations) from
seeking qualification by request.
Regarding the proposed attribute that
a proposed electric transmission facility
would need one or more Federal
authorizations that require preparation
of an EIS pursuant to NEPA, DOE
declines to make the changes suggested
by Niskanen Center, PIOs, and CEC/
CPUC. As explained above, DOE is
aiming to identify as ‘‘qualifying
projects’’ those proposed electric
transmission facilities for which DOE
coordination under the CITAP Program
is likely to be most impactful and to
yield the greatest benefits for
consumers. DOE believes that focusing
on proposed electric transmission
facilities for which preparation of an EIS
is expected is an appropriate factor for
narrowing the list of potential electric
transmission facilities for DOE
coordination because an EIS is typically
needed for more complex projects.
Preparation of an EIS is also a longer,
more involved process and one that
poses a greater risk of delays absent
interagency coordination. Note that,
although qualification by attribute is
limited to those for which an EIS is
likely required, qualification by request
does not have this limitation, such that
a project proponent is permitted to
request DOE coordination even if an EIS
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
35322
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
is not expected and seek a
determination from the Director of the
Grid Deployment Office on eligibility
for the CITAP Program. As for the
request that DOE define which proposed
transmission facilities are expected to
require an EIS, DOE declines to do so
in this final rule. DOE and its fellow
agencies will apply NEPA and its
implementing regulations and will
follow applicable regulations pursuant
to NEPA, as will other relevant Federal
agencies, to determine whether an EIS
needs to be prepared, and those same
regulations will inform any expectations
as to whether an EIS is likely to be
required.
Regarding qualification by request,
DOE agrees with commenters that
criteria regarding the types of proposed
electric transmission facilities that may
be deemed ‘‘qualifying projects’’ under
this process would be beneficial to
project proponents, and ultimately to
DOE in identifying the subset of projects
that best suit the CITAP Program’s goals.
Consequently, DOE adopts criteria in
this final rule that the Director of the
Grid Deployment Office may consider
when evaluating a request to determine
whether a proposed electric
transmission facility is a ‘‘qualifying
project.’’ DOE will consider whether a
proposed electric transmission facility
will benefit from coordination under the
CITAP program, reduce congestion
costs, mitigate uncertainty, and enhance
supply diversity. These factors are
consistent with the overarching goals of
focusing the CITAP Program on
proposed electric transmission facilities
for which DOE’s coordination will be
most impactful, to the ultimate benefit
of consumers via reduced congestion
and enhanced reliability and resilience,
among other benefits. DOE believes the
remaining discretion for DOE to
determine which proposed electric
transmission facilities are ‘‘qualifying
projects’’ is consistent with the statutory
framework that permits DOE to
coordinate the Federal authorizations
necessary for any transmission facility
and the aim of the section 216(h) itself,
notably the timely permitting of
transmission projects.
DOE agrees that it should explain its
determinations of whether qualification
by request is granted in writing and
consequently establishes a requirement
for such an explanation in this final
rule.
DOE makes no revisions in response
to the suggestion that an appeals process
be incorporated into the rule text for
non-qualifying projects. DOE notes that
any project not accepted under
qualification by attribute may seek
qualification by request of the Director
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
of the Grid Deployment Office, and that
this final rule does not disallow projects
from resubmitting materials.
Turning to the proposed limitation to
qualification by request for a proposed
electric transmission facility seeking a
permit from FERC pursuant to section
216(b) of the FPA, which stated that
DOE may only consider a request for
coordination if the requestor is FERC
acting through its chair, DOE revises its
proposal in this final rule to clarify that
the request for Federal coordination for
proposed transmission facilities seeking
a permit from FERC under section
216(b) must be consistent with
Delegation Order No. 1–DEL–FERC–
2006 or any similar, subsequent
delegation to FERC, which depend on
the mutual and continuing agreement of
both agencies. With respect to CEBA
and ACORE’s requests for more detail
on the procedures for the FERC Chair to
request that a proposed electric
transmission facility be eligible to
participate in the CITAP Program, such
procedures will depend on the state of
any delegations of DOE’s authority
under FPA section 216(h); therefore,
DOE finds that clarifying these
procedures is best done through
guidance outside the rulemaking
process. Similarly, with respect to
ACORE’s request to be able to submit a
petition for the FERC Chair to request
DOE to consider a request for assistance
under the proposed section, the removal
of that section in this final rule obviates
the need for such a process to be
established by DOE and the
establishment of any processes at FERC
are outside the scope of this rulemaking.
With respect to the treatment of
offshore transmission facilities,
commenters expressed concerns with
the limitations related to offshore
transmission facilities and sought
further explanation, at a minimum. DOE
adopts the proposal to exclude
transmission facilities proposed to be
authorized under section 8(p) of the
Outer Continental Shelf Lands Act in
conjunction with a generation project.
DOE and the 2023 MOU signatories
determined that offshore transmission
facilities connected to generation
projects should not be eligible for
participation in the CITAP Program
because the authorizations of, and
permits for, these transmission facilities
are typically included in the
authorizations and permits for the
connected generation projects.
Coordinating Federal authorizations for
generation projects, and reducing
timelines for joint transmissiongeneration projects with interdependent
permitting requirements, are beyond the
scope of the 2023 MOU and the CITAP
PO 00000
Frm 00012
Fmt 4701
Sfmt 4700
Program. This limitation allows DOE to
focus its resources on addressing known
challenges for transmission facility
permitting.
With respect offshore transmission
facilities whose Federal authorizations
and project development are
independent of generation development,
DOE is finalizing an approach
consistent with the 2023 MOU. For
qualification by attribute, DOE declines
to remove the requirement that the
proposed electric transmission facility
will not require authorization under
section 8(p) of the Outer Continental
Shelf Lands Act. Excluding offshore
transmission from the qualification by
attribute will facilitate a more efficient
allocation of resources. Shared offshore
transmission is a nascent industry with
unique and unsettled permitting issues.
Considering proposed offshore
transmission facilities as potentially
eligible for the CITAP Program in
consultation with the MOU signatories,
which is provided under qualification
by request, will allow DOE to adopt a
more tailored and responsive approach
to this new industry.
In order for offshore transmission
facilities to be eligible for the CITAP
Program via qualification by request,
DOE proposed, and adopts here, the
requirement that the MOU signatories
must agree to DOE coordination for
offshore transmission facilities for the
reasons explained in the prior
paragraph. DOE declines to only require
agreement from those MOU signatories
that are authorizing Federal agencies.
DOE is unpersuaded that a single, nonauthorizing agency would unilaterally
hold up a proposed offshore
transmission facility’s eligibility for the
CITAP Program, such that those
agencies should not be allowed to
participate in the eligibility decision
making. Instead, DOE believes that
continuing the coordination
demonstrated by the MOU is consistent
with the spirit of the CITAP Program
and important for keeping all relevant
agencies involved in ongoing
development of offshore transmission
permitting.
DOE also declines to establish a
process to allow potential State-awarded
transmission facilities to participate and
to enable the Bureau of Ocean Energy
Management or a State to request that a
project participate, as ACP and ACORE
suggested. At this time, DOE is focusing
the CITAP Program on addressing welldocumented and understood Federal
authorization issues via improved
coordination for a subset of proposed
electric transmission facilities for which
DOE coordination is likely to be most
impactful. DOE is not persuaded that
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
creating a process for entities other than
the project proponent to request
participation for a proposed project in
the CITAP Program is necessary to
provide the benefits of the program to a
project. DOE may consider revising its
approach to offshore transmission
facilities in future rulemakings pursuant
to FPA section 216(h).
Concerning commenters’ proposed
revisions to the definition of ‘‘qualifying
project’’ based on advanced
transmission technologies or
undergrounding, DOE declines to adopt
such revisions. As explained throughout
this section, DOE’s approach is targeted
towards proposed transmission facilities
that are likely facing the types of
permitting challenges for which FPA
section 216(h) and the CITAP Program
were created. Commenters provide no
evidence to suggest that superconductor
permitting or undergrounding are
unique as to warrant special recognition
within the definition of ‘‘qualifying
project.’’ This is not to say that a
proponent of a transmission facility that
contains these features cannot also be a
‘‘qualifying project’’ under DOE’s
adopted definition.
Finally, DOE declines to adopt CBD’s
suggestion that DOE impose a necessity
test for proposed electric transmission
facilities compared to non-transmission
alternatives as a gateway to
participation in the CITAP Program.
Congress directed DOE to coordinate the
authorizations necessary for the siting of
transmission lines. DOE understands
that to mean that Congress believes
transmission lines are necessary and
that Congress did not intend to supplant
existing transmission planning
processes. Through the CITAP Program,
DOE will coordinate authorizations for
transmission lines, which remain
subject to the statutes relevant to their
authorization, including NEPA.
Through these statutes and their
associated environmental review
processes that DOE will coordinate,
reasonable alternatives will be
considered by the appropriate Federal
agency as appropriate, which may or
may not include non-transmission
alternatives.
ddrumheller on DSK120RN23PROD with RULES2
D. Purpose and Scope of the IIP Process
DOE’s Proposal
Under the proposed rule, the IIP
Process is intended for qualifying
project proponents who have
sufficiently advanced their project such
that they have identified potential study
corridors and/or potential routes and
the proposed locations of any
intermediate substations. DOE proposed
to establish the IIP Process as a
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
mandatory prerequisite for coordination
under the CITAP Program and require
the submission of thirteen project
proponent resource reports that will
serve as inputs, as appropriate, into the
relevant Federal analyses and facilitate
early identification of project issues.
Within these resource reports, DOE
proposed to require reasonably
foreseeable information in three of
them: in the General Project Summary,
DOE proposed to require reasonably
foreseeable plans for future expansion of
facilities and specific generation
resources that are known or reasonably
foreseen to be developed or
interconnected; in the air quality and
noise effects report, DOE proposed to
require estimates on reasonably
foreseeable emissions construction,
operation, and maintenance, and
reasonably foreseeable changes in
greenhouse gas emissions and indirect
emissions; and in the Reliability,
Resilience, and Safety report, DOE
proposed to require a description of the
reasonably foreseeable impacts from a
failure of the proposed facility.
DOE also proposed to also establish
the IIP Process as an iterative process
anchored by three meetings, which
function as milestones in the process:
the initial meeting, review meeting, and
close-out meeting. DOE proposed in the
NOPR to require the project proponent
to submit an initiation request
containing certain information to DOE
to initiate the IIP Process, including a
summary of the qualifying project not to
exceed 10 single-spaced pages and a
project participation plan not to exceed
10 single-spaced pages. DOE also
proposed to require the proponent to
submit meeting review requests
containing certain information to DOE
prior to each of the three meetings. DOE
proposed that the project proponent
submit incomplete information so long
as an acceptable reason for the absence
of the information and an acceptable
timeline for filing it is provided, and it
provided the Director with discretion to
waive any requirement imposed on a
project proponent if the Director
determines that that the requirement is
unnecessary, duplicative, or
impracticable under the relevant
circumstances.
The proposed rule explained that the
IIP Process would ensure early
interaction between the project
proponent, relevant Federal entities,
and relevant non-Federal entities, and
that DOE would, to the maximum extent
practicable and consistent with Federal
law, coordinate the IIP Process with any
relevant non-Federal entities. DOE also
proposed in the NOPR that the IIP
Process did not preclude additional
PO 00000
Frm 00013
Fmt 4701
Sfmt 4700
35323
communications between the project
proponent and relevant Federal entities
outside the IIP Process meetings.
Additionally, the NOPR proposed to
provide a process by which a person
may submit confidential information
during the IIP Process or to request
designation of information containing
Critical Electric Infrastructure
Information (CEII); these provisions
established the mechanisms through
which the IIP Process complied with 10
CFR 1004.11 and 1004.13.
In the NOPR, DOE specifically sought
comment on the page limitations and on
the resource report requirements to
avoid, to the maximum extent
practicable, duplication in these
requirements.
Summary of Public Comments
DOE received several comments that
addressed the purpose and scope of the
IIP Process including comments on the
IIP Process as a prerequisite for DOE
coordination; the level of detail required
during the IIP Process and in resource
reports, including page limits and
reasonably foreseeable impacts; the role
of the three anchor meetings;
participation of Federal and non-Federal
entities; and protection of confidential
information and/or CEII. Comments to
specific resource report requirements
are addressed in section VI.L of this
document on an individual report basis.
DOE received many comments in
support of the proposed IIP Process.
Grid United, PIOs, State of Colorado
Governor’s Office, EEI, ACP, ACORE,
PJM, and CEBA expressed support for
the revitalized IIP Process proposed in
the NOPR. PIOs stated that the IIP
Process will help Federal agencies
coordinate information exchange that is
necessary to fulfill their individual
statutory mandates, avoid duplication of
cost and effort for project proponents,
and reduce the potential for unexpected
delays later in the permitting process.
PIOs also agreed with DOE that, by
increasing the pace of transmission
development through the IIP Process,
the proposed rule will confer significant
public benefits. The State of Colorado
Governor’s Office recognized that the IIP
Process would provide developers a
uniform mechanism for projects to
identify siting constraints and
opportunities, engage with Indian
Tribes, local communities, and other
stakeholders, and to gather information
that would serve as inputs, as
appropriate, into Federal authorization
decisions. EEI and ACP recognized the
potential benefits to be gained from the
IIP Process and encouraged DOE to
move swiftly to both finalize the
proposed approach and commit to
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
35324
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
working closely with project proponents
to ensure that the IIP Process produces
the promised results. EEI stated its
belief that by collaborating with electric
companies, DOE can significantly
increase the efficiency of the process
and reduce the time needed for NEPA
reviews while ensuring environmental
integrity and project deployment.
ACP and ACORE both supported the
mandatory nature of the IIP Process as
a prerequisite to participation in the
CITAP Program, provided that it serves
its intended objective of enhancing
coordination, reducing permitting
timelines, and minimizing duplication.
ACP and ACORE noted that the IIP
Process’s early environmental review
could conserve resources for public and
private participations. PJM noted that
the requirement should help avoid the
current multi-agency piecemeal
approach.
DOE also received comments
generally in support of the
establishment of the resource reports.
AEU and the CARE Coalition expressed
support for the thirteen resource reports
proposed by DOE. AEU commented that
the resource reports provided a
comprehensive and wide-ranging
analysis of the project. CARE Coalition
commented that the resource reports
were sufficiently comprehensive and
detailed to enable Federal agencies,
State and Tribal authorities,
stakeholders, and the public to
adequately review the project. AZGFD
explained that the heightened
consideration for resources through
submitting 13 resource reports early in
the process enables coordination and
prevents implementation delays. It also
stated that in some cases, adequate
assessment of resources could take
multiple years and multiple revisions
before Federal environmental review is
complete.
However, while commenters were
broadly supportive, some commenters
suggested changes to the level of detail
required during the IIP Process and
resource reports, indicating these would
add flexibility and avoid what they
perceived as unnecessary or
burdensome tasks. Pew Charitable
Trusts, in response to potential
opposition to the level of information
required in the pre-application phase,
cited previous studies that conclude
that a transparent and thorough siting
process can benefit both the public and
developers. AEP emphasized that an IIP
Process should only be mandatory if it
(1) informs the NEPA process and (2)
minimizes duplication by project
proponents and Federal entities. AEP
noted that the IIP Process should also
conserve the resources of project
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
developers by actively encouraging
permitting authorities to rely on the IIP
Process’s early environmental review.
AEP also urged DOE to coordinate with
transmission developers to enhance
efficiency and protect environmental
objectives. ACP cautioned against a
burdensome pre-application phase and
encouraged DOE to demand a level of
information that is appropriate for
NEPA scoping and consistent with the
project’s development. ACEG agreed
with these assertions, adding that the
level of information required in the IIP
Process should be appropriate to
support the relevant Federal entities’
reviews and consultations, including
under NEPA, ESA, and NHPA. ACEG
emphasized the importance of
reasonable and flexible demands.
Similarly, CEBA cautioned against an
IIP Process that was too complicated or
time consuming. ACORE noted that the
timeline for the submission of
information in the IIP Process should
align with when developers have the
needed information and recommended
that DOE provide some flexibility in
those instances when the full scope of
the information required in the IIP
reports is not yet available. The NYTOs
also suggested DOE should ensure that
its data requests and sufficiency
determinations align with the reliable
data and information standards now set
forth in sections 102(E) and 106(b)(3) of
NEPA. These NEPA standards
emphasize the use of reliable data and
explicitly provide in NEPA section
106(b)(3)(B) that in making a
determination regarding the level of
review under NEPA, an agency ‘‘is not
required to undertake new scientific or
technical research unless the new
scientific or technical research is
essential to a reasoned choice among
alternatives, and the overall costs and
time frame of obtaining it are not
unreasonable.’’ Similarly, Grid United
recommended that DOE should consider
section 106(b)(3) of NEPA in
determining the level of information
that is sufficient for each IIP Process
meeting. AEP cautioned against a CITAP
or IIP Process that duplicates or exceeds
State regulatory application
requirements.
Several comments addressed the level
of detail required in the resource reports
and the burden this would represent to
the project proponent. ACP expressed
concerns with the level of time and
effort required for the development and
submission of DOE’s proposed resource
reports so early in the process, when
their usefulness in NEPA’s EIS review
process is uncertain, and urged DOE to
consider that there may be limited
PO 00000
Frm 00014
Fmt 4701
Sfmt 4700
information available in the early stages
of permitting. ACP requested that the
mandatory ‘‘shall’’ language be changed
to ‘‘should’’ or ‘‘to the extent
practicable.’’ ACEG, SEIA, and CEBA
noted that DOE needs to strike a balance
between requiring enough information
to be helpful in streamlining the review
but not making requirements so strict
that project proponents are discouraged.
ACEG stated that information required
in the resource reports must be limited
to the information available at the time
of submission, as this is a preliminary
stage and developers should not be
discouraged from applying if they do
not yet have all the information. ACEG
recommended that the detail of each
resource report must be commensurate
with the level of available information
at the time of the submission.
Relatedly, DOE received several
comments regarding the requirements
that project proponents account for
reasonably foreseeable effects. PIOs
commented in support of the proposed
rule’s requirement to assess climate
impacts. PIOs explained that the
proposed rule’s requirements that
resource reports account for generation
resources that are reasonably foreseen to
be developed or interconnected and for
reasonably foreseeable changes in
emissions will ensure a rigorous
environmental analysis that properly
accounts for the project’s climate
impacts and are well-founded in
NEPA’s plain text and implementing
regulations, CEQ guidance, and judicial
precedent. Policy Integrity provided
similar rationale and additionally
indicated that providing such data
would be ‘‘relatively easy’’ for
proponents. Policy Integrity elaborated
that FERC has historically required such
estimates from transmission developers,
that developers have previously
submitted these data and analysis to
both DOE and FERC, and that power
system emissions estimates are
accessible through readily available
modeling software. Along similar lines,
AEU commented that the resource
reports are comprehensive and require a
wide-ranging analysis of the project, and
that the requirement to describe
reasonably foreseeable generation
resources is especially beneficial
because it illustrates the project’s value
and benefits to the larger regional and
interregional grid.
On the other hand, CATF suggested
that instead of requiring project
proponents to describe reasonably
foreseeable generation resources, DOE
should request this specific information
only for generator interconnections
designed to connect specific generation
resources to the bulk power system.
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
CATF explained that it may be difficult
for certain qualifying projects to
determine the scope of what generation
resources are reasonably foreseeable.
Accordingly, CATF recommended that
DOE not require project proponents to
determine associated generation
resources where burdensome,
speculative, and of limited value to
decision makers, and revise the
provision to include only ‘‘specific’’
generation resources. CATF cited to
judicial decisions to support the
proposition that an analysis of
foreseeable generation is not required
where the generation would likely have
occurred even absent the project.
ClearPath offered additional criticisms
of the foreseeable generation
requirement. ClearPath urged DOE not
to exceed its jurisdiction to conduct
environmental reviews by including
additional requirements without
consulting CEQ, and stated that DOE’s
requirements to consider indirect
impacts of the project and identify
effects from existing or reasonably
foreseeable projects are beyond DOE’s
statutory authority and are contrary to
CEQ Guidance. ClearPath recommended
that DOE limit IIP Process requirements,
and subsequent review in an EIS, to
only an electric transmission line and
its attendant facilities within Federal
jurisdiction. Finally, the NM SHPO
inquired generally about foreseeable
generation, and whether foreseeable
development will be considered in the
assessment of historic properties under
NHPA section 106 and its implementing
regulations.
DOE also received comments on the
iterative nature of the IIP Process and
the role and scope of the three anchor
meetings. While ACP approved of the
general structure of anchor meetings,
ACP emphasized the importance of
flexibility in order to accommodate
proposed projects that already have
conducted significant Federal and State
outreach or have agency-specific
reporting that may differ in approach
and timing to the IIP. ACP also
suggested that DOE clarify how
potential route changes can be
accommodated without restarting the
process, and that the final rule provide
specific criteria that DOE and relevant
Federal entities would follow in their
consideration of adding, deleting, or
modifying these routes.
ACEG suggested that DOE amend the
proposed rule to strike or significantly
modify its ‘‘sufficiency’’ standard for
scheduling meetings, which DOE
proposed to be required for scheduling
each of the three required anchor
meeting requests. ACEG and NYTOs
commented that DOE should only find
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
a meeting request insufficient when the
information provided in the meeting
request is insufficient to support a
productive meeting, e.g., a review
meeting request should only require
sufficient information to hold a
productive discussion on the initial
resource reports. For an example,
NYTOs stated that as an ‘‘initial review
meeting’’ is intended to identify issues
of concern, information gaps or data
needs—the existence of information
gaps or the need for additional data,
itself, should not be an appropriate basis
for declining to proceed with a review
meeting. ACEG expressed concerns that
the current approach could allow an
application to be indefinitely ‘‘parked’’
by unreasonable or overly burdensome
demands for more information for
purposes of a sufficiency determination.
Similarly, Idaho Power asked,
recognizing that review under the IIP
Process is iterative, what controls there
are to avoid continued and repeated
refinement of analysis. Idaho Power also
asked if the resource report requirement
change infers the project proponent will
have already identified potential
resource concerns by consulting with
relevant, Federal land managers.
DOE requested comments on page
limits for certain submission in the
NOPR and received seven responses.
CBD and the CARE Coalition both
expressed a general concern with page
limits on environmental reviews, with
CBD stating that arbitrary limits risk
sacrificing detail, undermining public
participation, and causing delays. The
Kentucky SHPO stated that page limits
may be applicable if resource reports
will serve only as background
information, but page limits may not
comply with NHPA or applicable State
statutes if documentation is intended to
be utilized by the project proponent or
Federal agency for section 106
consultation materials. AZGFD noted
that the NOPR only mentions page
limits in the documents Summary of the
Qualifying Project and Project
Participation Plan, required by § 900.5,
and recommended that DOE not include
page limits for resource reports. ACP
expressed concern with imposing page
limits on project summaries and
participations plans required by § 900.5
and instead recommended that DOE
allow for flexibility and allow for pagelimit carve outs for appendices where
appropriate. Gallatin Power stated that
the page limits for the Summary of the
Qualifying Project and Project
Participation Plan are reasonable but
noted that the scope of transmission
projects will vary greatly and suggested
that DOE allow project proponents to
PO 00000
Frm 00015
Fmt 4701
Sfmt 4700
35325
request additional pages if deemed
necessary. The CEC/CPUC stated that
the page limit for the Summary of the
Qualifying Project is appropriate but the
limit for the Project Participation Plan
may be limiting. Similarly, EDF raised
a concern that the ten-page limitation
for a Project Participation Plan might
constrain the level of detail needed to
comprehensively and holistically assess
the project’s impact and may signal to
project proponents that only a cursory
assessment is needed.
DOE received one comment regarding
the participation of relevant Federal
entities. EEI noted that transmission
projects that interconnect, parallel, or
cross facilities owned or operated by
Federal power marketing
administrations, such as Bonneville
Power Administration and the Western
Area Power Administration, may also be
qualifying projects under the CITAP
Program as proposed. EEI suggested that
in such cases, the Federal power
marketing administrations must be
involved in some manner as relevant
Federal entities, either as joint lead
agency with DOE or otherwise, and
should remain actively involved in the
coordination process. EEI further noted
that providing a coordination role for
Federal power marketing
administrations is consistent with
section 216(h).
DOE received comments from ACEG,
AEP, and PIOs that addressed
participation of relevant non-Federal
entities. AEP urged DOE to be mindful
of the important and necessary roles
State and local decisionmakers play in
the proposed transmission project
approval process. ACEG and PIOs
generally supported the clear and
increased role for non-Federal entities,
including Indian Tribes, SHPOs, and
THPOs, in the IIP Process but noted that
the important role of these additional
entities in the process can also
complicate reviews. ACEG
recommended that DOE ensure that
these non-Federal entities not only have
but also use their seat at the IIP Process
table and have necessary resources to
fully participate in the process. PIOs
stated that such improved coordination
will be essential to ensure that resource
reports provide all the necessary
analysis and information to enable
project proponents to receive all
relevant authorizations. ACEG also
noted that one way DOE can facilitate
this participation is by effectively
implementing its grant funding
opportunities for transmission siting
and permitting participation.
Regarding confidential information
and/or CEII, the CARE Coalition
recommended that DOE specifically
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
35326
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
invite comments from Indian Tribes
regarding best practices around outreach
by project proponents and prioritize
Tribal recommendations. The CARE
Coalition also recommended that DOE
create a list of best practices; add free,
prior, and informed consent (FPIC) to
that list; and add language stating
agencies must apply FPIC to all
interactions between agencies and
Tribal governments. The CARE
Coalition believes that these changes
will ensure that agencies adhere to both
the United Nations Declaration on the
Rights of Indigenous Peoples and the
Federal trust responsibility to Tribal
governments. Relatedly, PIOs
recommended that DOE adopt language
from the Washington State Attorney
General’s Centennial Accord Plan,
Indigenous Knowledge requirements,
and requirements from the 2022 Biden
Memorandum on Uniform Consultation
Standards. The CARE Coalition
recommended that DOE add a separate
provision requiring agencies to clearly
articulate the levels of confidentiality
afforded to the public and governmental
engagement for the information shared
therein. The CARE Coalition
recommended that DOE ensure that
sacred sites, locations, and Indigenous
Knowledge are protected from public
disclosure to the greatest extent
practicable. The NM SHPO added that
agency officials should address
concerns about confidentiality with
Tribes.
DOE received comments requesting
clarification on how the proposed rule
would affect transmission projects that
are already in the permitting process
from Stoel Rives LLP and Idaho Power
and a comment from Gallatin Power
regarding the interaction of the IIP
Process with other permitting processes.
Stoel Rives argued that these projects
should also be eligible for DOE’s
improved and expedited approval
process, under the CITAP Program or
otherwise. Stoel Rives encouraged DOE
to consider these projects in this final
rule and provide a roadmap detailing
how they can be integrated into the
process. Gallatin Power raised a concern
that under the current provisions, a
project proponent will not be able to
submit applications to relevant Federal
agencies for necessary Federal
authorizations until after the completion
of the IIP Process. Gallatin Power
contended that the submission of an
authorization application and
supporting materials allows for the
developer to identify its interest in a
right-of-way path impacting Federal
land and be designated the ‘‘first-inline’’ for review. Forcing the application
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
submittal to later in the process could
result in multiple developers attempting
to complete the IIP Process, including
the intensive resource reports, for the
same lands at the same time. This
would create substantial inefficiencies
for both the project proponents and the
agencies involved. Gallatin Power
suggested that to avoid this, DOE should
either continue to allow developers to
submit applications to Federal agencies
prior to initiating the IIP Process or
institute a similar ‘‘first-in-line’’
approach based on when projects are
proposed for the CITAP Program.
Gallatin Power also proposed that the
transmission projects that have already
submitted applications for
authorizations to relevant Federal
agencies should not be forced to redo
their application process or have their
applications invalidated until the IIP
Process is completed. They argued that
doing so would be highly disruptive to
development efforts and
counterproductive to DOE’s goals.
DOE also received comments
regarding studies that may be
undertaken during the IIP Process. The
CEC/CPUC encouraged early
coordination and review of a project
proponent’s supporting study methods
for the IIP Process because reviewing
study methods and securing necessary
approvals for field review, before a
proponent has conducted its studies,
could reduce later delays. Additionally,
the CEC/CPUC encouraged DOE to help
other Federal agencies set schedules for
timely study authorizations and afford
exemptions to allow project proponents
to initiate the IIP/CITAP Process if other
Federal agency authorizations are
delayed. Idaho Power asked DOE to
clarify if the level of study is assumed
to be desktop/GIS-informed or if there
an expectation that field surveys will be
completed for all project alternatives.
Idaho Power also asked if DOE would be
the final arbiter of completeness for
studies or if each relevant Federal land
management agency would have the
authority to request additional
information. Gallatin Power commented
that DOE should clarify when the
project proponent will receive
authorization from Federal agencies to
complete field resource surveys.
Gallatin Power further stated that a lack
of structure could allow for the
permitting timelines to remain the same
since uncertainty would be shifted to
before the start of the rule’s proposed
two-year NEPA deadline.
Five commenters provided responses
to DOE’s request regarding the
duplicative aspects of the NOPR. ACP
commented that project proponents
should be permitted to incorporate by
PO 00000
Frm 00016
Fmt 4701
Sfmt 4700
reference existing data, environmental
reviews, and public engagement efforts
to streamline the process. ACEG
recommended that the specific language
regarding incorporation by reference be
clarified so that incorporation by
reference is permissible for all data, not
just material in other resource reports
and provided some suggested edits to
the provision. CEC/CPUC stated that
duplicative aspects of reports should be
eliminated to limit inconsistencies in
review, providing as an example that
the Cultural Resources resource report,
the Tribal Resources resource report, the
Communities of Interest resource report,
and the Socioeconomic resource report
all overlap but may not be reviewed by
the same agency subject matter experts,
which may result in inconsistent
evaluations.
ClearPath stated that the requirement
for project proponents to list and
describe all dwellings and related
structures or other structures normally
or intended to be inhabited by humans
within a 0.5-mile-wide corridor
centered on the proposed transmission
line was duplicative of information
regarding affected landowners required
in General Project Description resource
report and should be omitted.
ACP recommended that DOE not
require the public disclosure of names
of people project proponents spoke to in
preparing the resource reports, as this is
overly onerous and lack of detail in this
section should not be a basis to legally
challenge DOE’s eventual
determination.
DOE Response
In this final rule, DOE retains the
purpose and scope of the IIP Process as
proposed in the NOPR, including the
three-anchor-meeting structure and
information requirements for
progressing through the process, with
minor revisions. DOE revises this final
rule for clarity and to reduce
burdensome and duplicative
requirements in response to comments,
as described below. DOE revises the
page limits in this final rule to allow for
project proponents to request a waiver.
DOE makes no other revisions in
response to these comments but notes
that revisions to resource reports and IIP
Process meetings in response to other,
specific comments received on those
aspects are addressed in sections VI.N
and G of this document.
DOE declines to act on those
comments urging greater flexibility in
the IIP Process and in the content of
resource reports because it believes such
measures are unnecessary. This final
rule confirms the provisions in the
NOPR that provide for sufficient
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
flexibility: the three anchor meetings,
which provide structured opportunities
to discuss and establish expectations;
the provision permitting the project
proponent to submit resource reports
missing discrete pieces of information
so long as the project proponent
provides an acceptable reason for the
omission and an acceptable timeline for
curing the omission; and the provision
granting the Director of the Grid
Deployment Office with discretion to
waive any requirement imposed on a
project proponent if the Director of the
Grid Deployment Office determines that
that it is unnecessary, duplicative, or
impracticable under the relevant
circumstances. DOE finds that together
these provisions provided the flexibility
necessary to respond to a wide variety
of circumstances.
Regarding comments from ACP,
ACEG, ACORE, SEIA, and CEBA on the
level of detail requested in resource
reports and specifically the availability
of information based on project maturity
and compliance with NEPA regulations,
DOE makes no revisions in response to
these comments. First, DOE believes the
level of detail in the resource reports is
necessary for DOE to implement its
authority under section 216(h), which
includes both environmental review and
the coordination of decision making
with relevant Federal entities. Second,
this final rule adopts the proposed
provision that project proponents may
address and justify omissions or
incomplete information. DOE believes
this provides sufficient flexibility to
accommodate project differences
without further revision. Regarding
ACP’s request to modify language from
shall to ‘‘should’’ or ‘‘to the extent
practicable’’, where DOE intends to
impose a mandatory obligation, it uses
appropriate language, including ‘‘shall.’’
Regarding the inclusion of reasonably
foreseeable effects, DOE declines to
make changes to the requirements that
project proponents identify certain
reasonably foreseeable effects. DOE’s
obligations under NEPA, as well as
corresponding obligations under section
106 of the NHPA and the ESA, require
the Department to consider the
reasonably foreseeable effects of major
Federal actions affecting the quality of
the human environment, as noted in
PIOs’ comment. While the scope of any
NEPA review will be determined at the
close of the IIP Process and on a caseby-case basis, the information required
for inclusion within the resource reports
discussed in this section is likely to be
relevant for preparation of
environmental review documents
necessary for authorizations subject to
this rule. In order to assist DOE in fully
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
considering this relevant information,
DOE seeks input from project
proponents to identify reasonably
foreseeable generation projects that may
be caused by a Federal authorization.
Even when DOE determines a particular
generation resource to be outside the
scope of review DOE may still need to
identify the resource and explain its
conclusion. The language of the rule
tracks these statutory obligations, and is
consistent with the Secretary of Energy’s
authority under section 216(h) to
require the submission of all data
considered necessary.
Regarding the iterative nature and
level of information requested for the
three anchor meetings, DOE makes
minor changes in this final rule
regarding the discussion of and criteria
for modifying study corridors in
response to comments. DOE restates that
the IIP Process is designed to allow for
flexibility throughout the process while
maintaining sufficient review periods to
ensure that the project proponent is
taking the steps necessary to complete
the required Federal authorization
processes.
In response to ACP’s concern on how
route changes will be accommodated
without restarting the IIP Process, DOE
believes the iterative nature of the IIP
Process provides mechanisms to
account for route changes, including:
meetings, the use of analysis areas for
resource report assessments (discussed
in section VI.K.ii of this document in
detail), study corridors that may contain
multiple routes, and the resubmission of
resources reports, none of which require
a restart to the IIP Process. Accordingly,
DOE makes no changes in response.
Regarding ACP’s request for criteria on
adding or deleting routes, DOE revises
the rule for clarity. First, DOE relocates
the list of criteria from the initial
meeting to § 900.4, Purpose and Scope
of the IIP Process, and clarifies in the
text that these are the initial list of
criteria the project proponent should
consider when developing potential
study corridors and potential routes for
the IIP Process. The change encourages
the project proponent to utilize the
criteria in identifying routes and
corridors throughout the IIP Process,
rather than just after the initial meeting.
Second, DOE removes ‘‘deleting’’ from
the initial meeting discussion topic to
clarify that the IIP Process does not
include a Federal entity deleting any
corridors or routes. This final rule
retains the requirement for DOE and
other agencies to identify other criteria
for adding or modifying potential routes
and includes that the agencies should
also identify criteria for potential study
corridors as well. DOE makes no further
PO 00000
Frm 00017
Fmt 4701
Sfmt 4700
35327
revisions as these changes sufficiently
clarify the criteria recommended and
how they will be considered, and any
additional criteria will be discussed on
a project-by-project basis.
DOE makes no changes to the final
rule in response to comments from
ACEG and NYTO regarding establishing
a standard for determining the
sufficiency of materials required for
each IIP Process meeting. DOE requests
the information it deems necessary and
sufficient for each meeting as described
in the rule and has chosen not to
provide a specific standard in order to
maintain flexibility to evaluate
submitted materials depending on the
specific needs and circumstances of
each project. As previously noted, IIP
Process materials may be submitted
with omissions provided that the
omission is noted, a reason is given, and
reasonable timeline for curing the
omission is provided. Additionally, the
final rule confirms the proposed
provisions through which DOE will
provide reasons for finding the
submissions deficient and how such
deficiencies may be addressed by the
project proponent. DOE believes these
provisions provide flexibility for a wide
range of project circumstances.
Regarding concerns from Idaho Power
and ACEG that projects could be
‘‘parked’’ in the IIP Process, DOE makes
no revisions to the final rule. This final
rule confirms the intended iterative
nature of the IIP Process and the
interests of DOE in engaging in
communications that are not limited to
the three anchor meetings. These
provisions are intended to prevent the
situation described by the commenters
where a request is rejected due to
information or knowledge gaps or
continued study refinement, by
providing a communication mechanism
through which such gaps could be
discussed in advance. Additionally, as
previously explained, DOE provides
sufficient flexibility to the IIP Process to
accommodate unique circumstances.
Regarding Idaho Power’s question as
to whether project proponents are
expected to engage with agencies prior
to the IIP Process, DOE responds that
project proponents may choose to
consult with relevant entities prior to
IIP Process at their discretion, but are
not required or expected to do so.
Regarding page limits, DOE believes
that the limitation on the number of
pages in the Summary of the Qualifying
Project and the Project Participation
Plan is generally useful and appropriate,
but agrees with commenters that some
complex projects may require additional
pages to address pertinent information
for the project and the project
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
35328
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
proponent’s outreach. Accordingly, DOE
revises this final rule to allow for project
proponents to request waivers to the
page limitations of the Summary of the
Qualifying Project and the Project
Participation Plan. As the proposed rule
established no specific page limitations
on the environmental review document
or resource reports, DOE makes no
additional revisions in response to
comments on those documents but
acknowledges that relevant statutory
page limits for environmental review
documents will be followed.
Regarding the participation of
relevant Federal entities, DOE has made
no changes in response to EEI’s
suggestion to include Federal power
marketing administrations because DOE
has determined that such a scenario is
already allowed by the regulatory text in
the definition of relevant Federal entity.
Regarding the participation of
relevant non-Federal entities, DOE
agrees that not all relevant non-Federal
entities will have the resources available
to participate in the IIP Process. DOE
makes no changes to this final rule,
however, because provisions for costrecovery and contribution of funds,
which may assist in those entities’
participation, are already included in
the IIP Process. The recommendation of
coordination of grant funding is outside
the scope of this rulemaking, which is
limited to implementation of DOE’s
coordinating authority under section
216(h) of the FPA. DOE has made no
changes in response to this comment.
DOE encourages non-Federal entities
with authority to make permitting
decisions regarding proposed electric
transmission projects (e.g., State siting
authorities) to actively participate in the
CITAP Program, and will continue to
seek ways to support such participation
as the Program is implemented.
Regarding confidentiality of
information and recommendations from
the CARE Coalition among others, DOE
makes no changes to this final rule. DOE
finds that existing statutory provisions
referenced in the proposed rule and
confirmed in this final rule provide a
framework for the protection of certain
sensitive information from public
disclosure. DOE recognizes that Indian
Tribes are entitled to decline to provide
information potentially at issue in the
resource reports and IIP Process, and
notes that this final rule does not
mandate that Indian Tribes provide any
material or information to project
proponents. DOE will work with Indian
Tribes to access relevant material and
incorporate it into relevant decisionmaking while protecting the
confidential and sensitive nature of that
information as necessary and legally
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
permitted. Additionally, as noted in
section IV of this document, DOE
affirms the sovereignty of Federally
recognized Indian Tribes and confirms
that the rule makes no changes to
Federal agencies’ government-togovernment responsibilities. DOE
commits to undertake Tribal
consultation as appropriate, including
as required by applicable authorities
such as Executive Order 13007 or the
Presidential Memorandum on Uniform
Standards for Tribal Consultation, and
commits to designate Indian Tribes with
special expertise regarding a qualifying
project, including knowledge about
sacred sites that the project could affect,
that are eligible, to become cooperating
agencies under NEPA. DOE declines to
include in the final rule best practices
around outreach by project proponents
or to import existing requirements
related to Tribal engagement into this
rule. The form and scope of outreach
may vary by project and DOE believes
these issues are best addressed on a
project-by-project basis or in guidance
outside of this rule.
Regarding participation of projects
already undergoing a permitting
process, DOE notes that nothing in the
definition of qualifying project excludes
such projects from participation and
that the flexibility provided for in the
IIP Process will allow DOE to determine
accommodations for such projects on a
project-by-project basis. DOE disagrees
with Gallatin Power’s interpretation that
the CITAP Program would disallow or
invalidate permitting applications
previously submitted prior to initiation
of the IIP Process or submitted during
the IIP Process. DOE acknowledges that
some applications for authorizations
may already be submitted prior to
initiation of the IIP Process or may be
submitted during the IIP Process and
accommodates for such scenarios in the
rule. For example, this final rule
confirms the NOPR provisions that the
initiation request and the review
meeting request require the project
proponent to provide a list of
anticipated and completed dates of
applications for authorizations or
permits. Further, the rule specifically
provides in § 900.5(h)(2) that at the
initial meeting DOE will identify any
Federal applications that must be
submitted during the IIP Process to
enable relevant Federal entities to begin
work on the review process. DOE finds
that these provisions sufficiently
provide that this final rule will not
impede developers’ strategies for
seeking authorizations for their projects.
Nowhere in the rule does DOE indicate
that these applications will be
PO 00000
Frm 00018
Fmt 4701
Sfmt 4700
invalidated or require resubmission, nor
does DOE have authority to do so.
Regarding study methods and
approvals as raised by CEC/CPUC, Idaho
Power, and Gallatin Power, DOE revises
this final rule to provide clarity on the
extent to which analysis of alternatives
is expected (discussed in more detail in
section VI.L.xi of this document) and to
specify that required or recommended
surveys or studies will be discussed in
the IIP Process during the initial and
review meeting. DOE makes no further
revisions to this final rule in response
to these comments as study methods
and authorization timelines are specific
to project circumstances and DOE will
address these on a project-by-project
basis. DOE clarifies here that DOE leads
the IIP Process and will determine the
completeness of documents and studies
for the purpose of progressing through
the milestones, while relevant Federal
entities maintain statutory authority for
determining the completeness of
information needed for their decisionmaking.
Regarding the duplicative nature of
some resources reports, DOE makes
minor revisions in response to these
comments. DOE agrees that
incorporation by reference should
extend to publicly available sources,
such as existing data and environmental
reviews, but only if they exist in
electronic form (to ensure relevant
entities can reasonably access the
material), and revises this final rule to
allow for such references. In response to
the request to combine resource reports
to assure consistent review, DOE makes
no revisions in response to this
comment as DOE believes the division
of resource reports will provide specific
information pertinent to that resource
topic that is necessary for DOE to
implement its coordination authority.
Further DOE believes the coordination
of reviews within the IIP Process with
relevant Federal entities will provide
consistency of evaluation, and notes
that the review of project proponent
resource reports does not replace or
supplant Federal entities’
responsibilities to evaluate necessary
information for decision making on
authorizations and permits under their
purview. Regarding the request to
remove duplication in reporting of
affected landowners and dwellings
proximate to the proposed route, DOE
makes no revisions in this final rule.
DOE does not agree that these are
duplicative requests, as affected
landowner describes a person or entity
and dwelling describes a building.
In response to ACP’s concern about
the burden of providing detailed
information on all persons contacted in
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
development of the resource reports,
DOE agrees that this provision
represents an unnecessary burden on
project proponents and removes it from
this final rule.
E. Public Participation in the IIP Process
DOE’s Proposal
The proposed rule included several
provisions addressing public
participation. In the NOPR, DOE
proposed the project proponent submit,
as part of the initiation request, a project
participation plan. The proposed project
participation plan included the project
proponent’s history of engagement with
communities of interest and
stakeholders, and a public engagement
plan for the project proponent’s future
engagement with communities of
interest and with Indian Tribes that
would be affected by a proposed
qualifying project. Before the review
and close-out meetings, DOE proposed
that the project proponent provide an
updated public engagement plan to
reflect any activities during the IIP
Process. Additionally, the proposed rule
required the standard schedule to take
into consideration the need for early
and meaningful consultation with
Indian Tribes and engagement with
stakeholders and communities of
interest. Likewise, the project-specific
schedule was required to account for
early and meaningful consultation with
Indian Tribes and engagement with
stakeholders.
ddrumheller on DSK120RN23PROD with RULES2
Summary of Public Comments
DOE received several comments
addressing public participation during
the IIP Process, including the
requirement of project proponents to
plan for and report on engagement with
various groups, and recommendations
for modifications, clarifications,
expansions, and reductions of the
proposed public engagement reporting
requirements.
Many commenters supported DOE’s
requirement to have a project proponent
submit project participation and
engagement plans. ACP, AEU, ACEG,
SEIA, Pew Charitable Trusts, CEBA, and
PIOs all expressed support for the
requirement, expressing that such
engagement would build trust and allow
prompt response to concerns. PIOs
expressed that they believe DOE is
correct to require project proponents to
furnish ‘‘specific information on the
proponent’s engagement with
communities of interest and with Indian
Tribes’’ and that requiring a public
participation plan is well-grounded in
binding Federal authorities.
Additionally, PIOs expressed
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
appreciation to DOE for noting that
project proponent outreach efforts are
merely complementary and not
substitutive for Federal agencies’ own
engagement with communities and
Indian Tribes nor are they substitutive
for formal requirements under NEPA or
other laws that provide formal avenues
for community input. ACP supported
DOE’s efforts to encourage early and
consistent engagement by project
proponents with affected communities,
as this represents a best practice for
identifying, mitigating, and avoiding
risks of sometimes-contentious
transmission project development.
DOE received several comments
recommending changes to the role of
public participation and the scope of
participants. EDF stated that the project
participation plan is too narrowly
focused, as public input should be
expansive and not limited to ‘‘project
engineering and route planning.’’ The
CARE Coalition encouraged DOE to
require that project participation and
public engagement plans include
information about engagement with
advocates for the public interest, such as
advocates for wildlife protection, who
may not be covered under the definition
of ‘‘communities of interest.’’ The CARE
Coalition argued that the inclusion of
these groups and individuals in the
project participation and public
engagement plans would help develop
resource reports, reduce litigation risk,
reduce delays, and reduce overall
project costs. PIOs recommended that
DOE require separate engagement plans
for Indian Tribes and communities of
interest.
Commenters requested more guidance
on public engagement, including
parameters, minimum requirements,
metrics, and best practices. EDF
commented that proposed rule does not
require the project proponent to strictly
define communities of interest and
recommended that the communities
considered should be based on CEQ’s
Climate and Economic Justice Screening
Tool or a comparable tool. EDF further
recommended refining the public
engagement plan to include mandatory
deadlines or frequency of outreach
requirements, to specify when
communities of interest will have an
opportunity to raise concerns, and to list
additional tools that would facilitate
communication in order to improve the
efficacy of the plan. EDF expressed
concern that the project participation
plan did not require project proponents
to engage with communities before
substantive plans were solidified or
require that input from communities of
interest is taken into account in the
beginning stages of plan development.
PO 00000
Frm 00019
Fmt 4701
Sfmt 4700
35329
Similarly, Niskanen Center was
concerned that the proposed rule did
not have sufficient notification or
consultation requirements regarding the
proposed public engagement plan, such
that a project proponent would actually
have to engage early or meaningfully
with impacted parties or communities
of interest. Niskanen Center accordingly
recommended adopting notice
requirements with defined timing and
linked to specific milestones such as the
notice of an initiation request. The
CARE Coalition recommended that DOE
adopt a definition of ‘‘early and
meaningful engagement’’ similar to
EPA’s definition of ‘‘meaningful
involvement’’ in its Environmental
Justice 2020 Glossary and stated that
providing a definition will ensure that
engagement with communities does not
simply consist of ‘‘check-the-box’’
exercises without meaningfully
engaging with communities that are
disproportionately and adversely
affected by certain Federal activities.
ACP suggested that DOE should provide
additional clarity as to what specific
steps are required for engagement, and
what DOE considers as ‘‘successful’’
engagement, and AEU echoed this
comment. ACP, AEU and ACEG
requested that DOE expressly recognize
that engagement with potentially
affected parties does not necessarily
mean that all parties will reach a
consensus on all issues. The CARE
Coalition suggested DOE require
submission of an ‘‘Applicant Code of
Conduct’’ with additional information
collection and sharing requirements for
engagement, which would bring the rule
into better alignment with FERC’s
proposed backstop permitting rule.
Similarly, PIOs suggested that DOE
require project proponents to adhere to
a rigorous ethical code of conduct.
Additionally, EDF suggested that the
proposed rule might benefit from the
expertise of DOE’s Office of Economic
Impact and Diversity.
The CARE Coalition, CBD, and CEBA
suggested including best practices for
public engagement and providing
guidelines for project proponents as to
what activities are considered
engagement.
Commenters also expressed concern
about the extent and approach to public
engagement. AEP cautioned against a
CITAP Program or IIP Process that
duplicates or exceeds the RTO
stakeholder process or required State
and local permitting functions that
ensure robust community and
landowner engagement and outreach.
ClearPath expressed opposition to
requirements in the project participation
plan and public engagement plan that
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
35330
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
create duplicative engagement
requirements and institute different
standards of engagement for different
population segments. ClearPath
specifically took issue with the different
standards for ‘‘communities of interest’’
and ‘‘stakeholders’’ in the plans and
suggested that the distinction was
counterproductive to development of
transmission projects and possibly
unconstitutional. ClearPath also
recommended amending the
requirement that a project participation
plan must include ‘‘[a] description of
. . . any entities and organizations
interested in the proposed
undertaking.’’ ClearPath stated that it
was impossible to describe any
interested entities and organizations
because DOE did not provide a
threshold for what actions constitute a
demonstration of interest. ClearPath
recommended reevaluating whether this
requirement was feasible and overly
burdensome. StopPATH WV expressed
its view that the project participation
plan described in the NOPR is one-sided
given that the developer and agencies
have primary decision-making power
and suggested that the name should be
changed.
DOE received three comments
regarding the role of community
benefits plans. Alan Leiserson
commented that the public engagement
plans should require that the project
proponent propose a community benefit
plan and consider affected
communities’ suggestions for it. EDF
also proposed that CITAP project
participation plans and public
engagement plans be required to include
information on any potential
community benefits agreements and the
process that would be used to work with
communities of interest in developing
such agreements. EDF reasoned that
information about any community
benefit agreement or plan would
support the CITAP review process and
allow for coordinated review of the
compliance of those plans with any
other legal requirements. ACP
supported DOE’s efforts to encourage
early and consistent engagement by
project sponsors with affected
communities. ACP expressed that DOE
should consider environmental
mitigation and community benefits
developed under this community
engagement process as project
mitigation and/or design features in
NEPA reviews.
PIOs, CARE Coalition, CBD, and
Policy Integrity recommended that DOE
incorporate additional opportunities for
public participation in the IIP Process.
PIOs stated that communities and
organizations with relevant expertise
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
should be allowed to participate in the
three required meetings. CARE Coalition
and PIOs suggested that DOE add an
opportunity for public comment on
project proponents’ compliance with
their participation plans and provide a
mechanism for affected communities to
make concerns known if proponents
interact with the communities in a
manner that is aggressive, coercive,
dishonest, or otherwise unethical or if
stakeholders disagree with project
proponents over the scope or nature of
a project’s impacts. Similarly, CBD
suggested including junctures at which
the public could provide input into the
resource reports and public
participation plan. Policy Integrity also
recommended that DOE modify the
proposed IIP Process to allow for early
public comments, arguing that early
community feedback and expert opinion
could reveal pitfalls in a project in the
pre-application stage. Without this step,
Policy Integrity expressed concern that
the public would have no voice until
after the participating agencies have
deliberated and potentially come to a
consensus on certain issues in the preapplication stage. For example, Policy
Integrity noted that agencies may deem
project proponents’ Alternatives Report
as complete once they ratify it during
the IIP Process, without any
consideration for public input.
Additionally, Policy Integrity argued
that its proposed revision would bring
the IIP Process into closer alignment
with the pre-filing process for natural
gas infrastructure at FERC, which
accepts formal public comment, and
suggested the consolidated
administrative docket be allowed to
provide public feedback.
DOE Response
In this final rule, DOE retains the
proposals in the NOPR to require a
project participation plan and a public
engagement plan, and the provisions in
the NOPR addressing engagement with
communities of interest, Indian Tribes,
potentially affected landowners, and
stakeholders. In response to these
comments, DOE makes minor changes
to this final rule to clarify the scope of
topics on which project proponents
should seek public engagement, for the
reasons discussed below. Revisions to
the definitions of communities of
interest, potentially affected
landowners, stakeholders, and to the
resource reports are addressed in
sections VI.J and VI.K of this document
in response to other comments.
Regarding the role of public
participation and the scope of
participants, DOE makes minor changes
in response to these comments. DOE
PO 00000
Frm 00020
Fmt 4701
Sfmt 4700
clarifies that the project participation
plan may include—but is not limited
to—engagement related to project
engineering and route planning and
strikes ‘‘project engineering and route
planning’’ from this final rule to reflect
this. DOE makes no changes in response
to the request to require engagement
with advocates for the public interest
because DOE believes further expanding
the required engagement creates an
undue burden on project proponents
without substantial benefit to
communities of interest. Furthermore,
DOE understands that these advocates
may, and often do, act as representatives
on behalf of communities of interest and
are therefore likely to be engaged
through those relationships. DOE is
unpersuaded that two public
engagement plans, one for communities
of interest and another for Tribal
engagement, are necessary and believes
that the proposed resource report
requirements for communities of
interest and Tribal interests allow for
sufficient differentiation on the topics
for DOE’s consideration.
Regarding requests for minimum
standards, deadlines, frequency, specific
steps, use of tools for identifying
communities of interest, and notice
requirements, from CARE Coalition,
CBD, CEBA, EDF, and Niskanen Center,
DOE makes no revisions in this final
rule in response to these comments.
DOE believes the provisions for public
engagement in the proposed rule and
confirmed here establish sufficiently
clear expectations for project proponent
activities while maintaining flexibility
for the project proponent to shape
engagement consistent with the project
circumstances and development. These
provisions as proposed and now
finalized sufficiently support the goals
of the CITAP Program by encouraging
engagement on the part of the project
proponent to identify concerns early
and to allow for the project proponent
to consider adjustments in a timely and
responsive manner. Additionally, these
provisions are complementary and
additional to Federal agencies’ own
engagement with communities and
Indian Tribes and the requirements
under NEPA or other laws that provide
formal avenues for public input
including notice and consultation
requirements. DOE is not persuaded that
additional requirements are necessary or
appropriate for the IIP Process.
Regarding codes of conduct, DOE has
determined that defining a singular code
within the regulatory text is
unnecessary at this time. In its role
coordinating the IIP Process and the
CITAP Program, DOE will work closely
with project proponents, relevant
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
Federal entities, communities, and other
stakeholders. In that role, DOE will
endeavor to ensure that project
proponents engage in good faith with all
participants. In contrast to FERC, DOE
does not have specific statutory
authority regarding eminent domain and
thus alignment with all aspects of
FERC’s proposed rulemaking pursuant
to engagement practices is not
appropriate but may be addressed on a
project-by-project basis where relevant.
With experience, DOE may find it
appropriate to provide code-of-conduct
or ethical guidance and may rely on the
resources provided by commenters.
DOE also clarifies, in response to EDF’s
concern, that offices across the agency,
including the Office of Energy Justice
and Equity (formerly Economic Impact
and Diversity), were consulted in the
development of the rule.
DOE declines to define ‘‘successful,’’
as requested by ACP, or ‘‘early and
meaningful’’ engagement as requested
by the CARE Coalition, because DOE
believes the required information on
engagement (including what groups and
individuals were engaged, how they
were identified, topics that were raised,
and the project proponent’s responses)
provides sufficient clarity and
additional definitions are unnecessary.
DOE declines to include the statement
requested by ACP, AEU and ACEG that
engagement with potentially affected
parties does not necessarily mean that
all parties will reach a consensus on all
issues because DOE is not persuaded
that the proposed rule indicates that all
parties will reach a consensus on all
issues and therefore finds such a
statement unnecessary.
DOE believes that best practices are
best provided in guidance rather than
regulatory text to allow for flexibility
and evolution of such practices and
makes no changes in this final rule in
response to the comments by CARE
Coalition, CBD, and CEBA. In the future,
DOE may issue guidance for
community-led engagement, measuring
engagement, identifying communities of
interest, and ethical and meaningful
engagement, which may include or
reference the sources provided by
commenters as necessary for
implementation of the CITAP Program.
In response to ClearPath’s concern
about different standards of engagement,
DOE reiterates that the various
requirements, including the resource
reports and public engagement plan, are
tailored to fulfill various, not mutually
exclusive, purposes to facilitate
transmission authorizations pursuant to
the CITAP Program, and are not
intended to, nor do they, establish a
hierarchy of treatment and
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
consideration of impacts across
population segments.
In response to StopPath WV’s
objection to the project participation
plan, DOE declines to change the name
of the project participation plan because
DOE is not persuaded that the phrase
implies any decision-making authority.
Regarding the role of community
benefits and community benefits plans,
DOE makes no changes to this final rule.
DOE believes that the public
participation provisions proposed and
confirmed here are sufficient to allow
project proponents to engage with
communities in the development of
plans or agreements and for compliance
to be evaluated in the CITAP Program
where relevant for Federal permitting or
authorization decisions. DOE does not
agree that additional requirements are
needed, as the comments suggest that
the situations described are not
universal but rather depend on the
project, and therefore are best addressed
on a project-by-project basis.
Regarding recommendations for
inclusion of expert groups in the IIP
Process meetings and providing avenues
for public comments, DOE makes no
changes in this final rule in response to
these comments. First, as noted
previously, DOE believes the provisions
in the proposed rule and confirmed here
are sufficient to support the goals of the
CITAP Program. DOE has structured the
three IIP Process meetings to serve as
milestones for coordination between the
project proponent and the relevant
Federal and non-Federal entities to
ensure DOE can meet its obligations
under FPA section 216(h) and DOE does
not intend to use these meetings to
solicit feedback from communities of
interest or receive expert input from
other organizations. The public
participation plan is designed with the
intent to identify issues well ahead of
the IIP Process meetings for this reason,
as the meetings themselves are not
intended to serve as avenues for broader
input. Second, as noted by DOE
throughout the rule and supported by
commenters, the CITAP Program public
participation requirements are
complementary and additional to
Federal agencies’ own engagement with
communities and Indian Tribes and the
requirements under NEPA or other laws
that provide formal avenues for public
input and public comment, including
on project impacts.
DOE disagrees with Policy Integrity’s
interpretation that agencies will make
decisions on Federal authorizations
during the IIP Process. Federal agency
decisions remain subject to distinct
decision-making processes with
requirements under NEPA and other
PO 00000
Frm 00021
Fmt 4701
Sfmt 4700
35331
laws that provide formal avenues for
public input. Furthermore, with respect
to Policy Integrity’s specific concern
regarding project proponent’s
Alternatives resource report, as
discussed in further detail below, see
section VI.K.xi of this document, the
project proponent’s Alternatives
resource report must discuss
alternatives identified and considered
by the project proponent. However,
while a project proponent’s study
corridors, potential routes, and range of
potential routes are relevant
information, they do not displace the
overall alternatives development
process that must take place in
consultation with relevant Federal and
non-Federal entities, stakeholders, and
the public. That process remains subject
to public comment pursuant to NEPA
and other laws.
F. Timing of IIP Process and NOI
Issuance
DOE’s Proposal
The proposed rule included several
provisions addressing the IIP Process
timeline. In the NOPR, DOE proposed
to, within 15 calendar days of receiving
an IIP Process initiation request, notify
relevant Federal entities and relevant
non-Federal entities of the initiation
request along with a determination that
the recipient is either a relevant Federal
entity or a relevant non-Federal entity
and whether the project proponent
should participate in the IIP Process.
Also, DOE proposed to, within 30
calendar days of receiving the request,
notify the project proponent and all
relevant Federal entities and relevant
non-Federal entities whether the
initiation request meets the applicable
requirements. If the request is found to
meet the applicable requirements, DOE
proposed, in consultation with the
identified relevant Federal entities, to
convene the IIP Process initial meeting
within 30 days of providing notice to
the project proponent.
In the NOPR, DOE proposed to,
within 15 calendar days after the initial
meeting with the project proponent and
relevant entities, prepare and deliver a
draft initial meeting summary to the
project proponent, relevant federal
entities, and any non-Federal entities
that participated in the meeting. The
proposed rule provided a period of 15
calendar days after receipt of the draft
initial meeting summary for relevant
entities to review and provide
corrections to DOE.
In the NOPR, DOE proposed, within
15 calendar days of the close of the 15day review period, to prepare a final
meeting summary that incorporates
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
35332
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
received corrections, as appropriate, and
incorporate the final summary into the
consolidated administrative docket.
DOE proposed in the NOPR to, within
60 calendar days after receiving a
project proponent’s review meeting
request, notify the project proponent
and all relevant Federal entities and
relevant non-Federal entities that the
review meeting request has been
accepted. In the NOPR, DOE proposed,
within 30 calendar days after DOE
provides notice that the review meeting
request has been accepted, to convene
the review meeting with the project
proponent and relevant Federal
agencies.
DOE proposed in the NOPR to, within
15 calendar days after the review
meeting, prepare and deliver a draft
review meeting summary to the project
proponent, relevant Federal entities,
and any non-Federal entities that
participated in the meeting. In the
NOPR, DOE proposed to provide a
period of 15 calendar days after receipt
of the draft review meeting summary for
relevant entities to review and provide
corrections to DOE.
DOE proposed in the NOPR to, within
15 calendar days of the close of the 15day review period, prepare a final
review meeting summary that
incorporates received corrections, as
appropriate, and to incorporate the final
summary into the consolidated
administrative docket.
In the NOPR, DOE proposed to,
within 60 calendar days after receipt of
the close-out meeting request, notify the
project proponent and all relevant
Federal entities and relevant nonFederal entities that the close-out
meeting request has been accepted. DOE
also proposed to, within 30 calendar
days of DOE notifying the project
proponent that the close-out meeting
request has been accepted, convene the
close-out meeting with the project
proponent and all relevant Federal
entities.
DOE proposed in the NOPR to, within
15 calendar days after the close-out
meeting, prepare and deliver a draft
close-out meeting summary to the
project proponent, relevant federal
entities, and any non-Federal entities
that participated in the meeting. In the
NOPR, DOE provided a period of 15
calendar days after receipt of the draft
close-out meeting summary for relevant
entities to review and provide
corrections to DOE.
In the NOPR, DOE proposed to,
within 15 calendar days of the close of
the 15-day review period, prepare a
final close-out meeting summary that
incorporates received corrections, as
appropriate, and to incorporate the final
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
summary into the consolidated
administrative docket.
Summary of Public Comments
DOE received comments from PIOs,
SEIA, ClearPath, and AEU that
expressed general support for DOE’s
proposed IIP Process timelines.
Several commenters suggested
specific changes to the IIP Process
timelines proposed in the NOPR. Grid
United and ACP recommended reducing
the time between receipt of an initiation
request and the date of the initial
meeting to no more than 30 calendar
days. NYTOs recommended that DOE
adopt a 60-day maximum period
between receipt of a review meeting
request and the convening of the review
meeting because a significant amount of
the information would have already
been reviewed as part of the initial
meeting.
ACEG suggested that DOE reduce the
45-day summary and report process
after each of the three anchor meetings
(initial meeting, the review meeting, and
the close-out meeting) and further
suggested that DOE require a real-time
wrap-up at the end of each meeting
during which DOE would provide a
meeting summary and participating
entities would immediately make any
needed corrections. ACEG also
recommended that DOE reduce the
number of days between the initiation
request and initial meeting to 15 days,
and reduce the number of days between
the close out meeting request and that
meeting to 30 days. Grid United also
suggested shortening the meeting
summary process by emphasizing closeout and action item discussions at the
meeting and designating a 15-day
period, thereafter, for finalizing the
meeting report.
Several commenters requested more
information on the total timeline for the
IIP Process and the CITAP Program.
ACP recommended that the IIP Process
include a general timetable to ensure
that it does not add unnecessary costs
or delays. Similarly, ACEG and CEBA
recommended that the rule establish a
presumptive one-year limit for
completion of the IIP Process. ACORE
commented that it supports ACEG’s
recommendation that DOE commit that
any transmission project will be fully
authorized in under three years and not
longer than five years (from initiation of
the pre-application process through
issuance of all required Federal
authorizations, including any required
notice to proceed). CEBA argued that,
ideally, the IIP Process and application
process, including all environmental
review procedures, would be completed
within three years. CEBA added that
PO 00000
Frm 00022
Fmt 4701
Sfmt 4700
DOE should work with the project
developer on a joint schedule that may
better accommodate the unique nature
of the proposed project. Similarly,
ClearPath suggested that the IIP Process
timeline in the rule could serve as a
baseline and that DOE should allow a
project proponent to submit a proposed
IIP Process schedule. EDF noted that the
IIP Process could take more than one
year given the lack of specific deadlines
for specific IIP Process steps. EDF stated
that there are IIP Process requirements
such as the project participation plan
that require significant effort and time to
develop and that this development time
is not captured in the IIP Process
schedule. EDF recommended that DOE
consider specifying a time period for
when a developer must resubmit its
review meeting request and close-out
meeting request if either request does
not meet the specified requirements.
CEBA noted that the burden of
completing the IIP Process in a timely
manner is highly dependent on the level
of effort and resources brought to bear
by the project proponent and suggested
that DOE should anticipate and
recognize a broad diversity of project
proposals and afford maximum
flexibility for the developer. CEBA
further encouraged DOE to ensure that
the IIP Process does not become too
complicated and time consuming,
which could undermine the objective
reflected in recent law to shorten the
Federal authorization process. Gallatin
Power stated that a lack of structure
could allow for the permitting timelines
to remain the same because timeline
uncertainty would be shifted to before
the start of the rule’s proposed two-year
NEPA deadline.
PJM noted that although the NOPR
describes the CITAP Program deadlines
as ‘‘binding,’’ the May 2023 MOU
contemplates a process to modify the
project-specific deadlines. PJM believes
that due to this and the fact that the
extensive, mandatory IIP Process is not
factored into the two-year timeline, the
actual review and approval process will
most likely take longer than two years.
Hence, PJM requested that DOE
carefully reexamine that the proposed
revisions will actually aid in
accelerating the current process in a
way that will ensure that, at a
minimum, the CITAP Program is able,
in all but the most unusual of cases, to
be completed within the two-year time
frame or less.
Four commenters, NYTOs, Grid
United, ACEG, and ClearPath, expressed
concern over the lack of a deadline for
DOE to issue the NOI. Grid United
recommended that the presumptive
deadline should be 90 days after the
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES2
close-out meeting. The NYTOs
recommended a presumptive deadline
of 45 days after either the close-out
meeting or the project proponent’s
completion of applicable filing
procedures for each involved Federal
agency. ACEG suggested that DOE
require the NOI to be issued within 90
days of the project proponent filing all
applications and resource reports. ACP
recommended that DOE ensure that as
little time as possible elapses between
submittal of an application for an EIS
Scoping NOI, and the subsequent
publication in the Federal Register.
DOE Response
This final rule makes several revisions
to the DOE decision-making timelines
that reduce the total time for DOE
reviews and responses in the IIP Process
by 55 days and the total time for all IIP
Process steps by 100 days. DOE also
revises this final rule to establish a
deadline for DOE and any NEPA joint
lead agency to issue an NOI to prepare
an environmental review document for
the proposed project. That deadline is
established as within 90 days of the
later of the IIP Process close-out meeting
or the receipt of a complete application
for a Federal authorization for which
NEPA review will be required. DOE
makes no revisions to establish
timelines for project proponents or to
set a timeline for the IIP Process or
overall CITAP Program. DOE recognizes
that some of the IIP Process is within
the government’s control, and, where
reasonable, for those pieces of the
process this final rule adopts shorter
timelines. For other pieces of the
process, however, the pace is dictated
by the project proponent (or factors
outside anyone’s control, like inclement
weather). For those pieces, DOE has not
set timelines.
Regarding reducing time between
meeting requests and meeting
convenings, DOE makes several
revisions. DOE agrees that the deadlines
for determining the sufficiency of the
initiation request and convening the
initial meeting can be moved forward to
streamline evaluation and coordination.
To simplify the initiation request review
and reduce the timeline, in this final
rule DOE is combining the deadline for
providing notice to Federal and nonFederal entities under § 900.5(f) of the
NOPR with the deadline for providing
notice of the sufficiency determination.
Further, this final rule reduces the
timeline for making a sufficiency
determination on the initiation request
from 30 calendar days after receiving
the initiation request to 20 calendar
days. Finally, DOE revises the timeline
for convening the initial meeting from
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
30 calendar days after providing notice
of the sufficiency determination to 15
calendar days. In sum, the revisions
reduce the maximum time period
between receiving the initiation request
and the initial meeting from 60 calendar
days to 35 calendar days.
DOE also agrees that the other IIP
Process meetings can be convened in
less time. Accordingly, the final rule
revises the timeline for convening the
review meeting and close-out meeting
from within 30 calendar days of
sufficiency determination to within 15
calendar days. Regarding NYTO’s
comment that the time between a review
meeting request and the review meeting
could be reduced, in this final rule DOE
shortens the period from 90 days to 75
days by convening the review meeting
within 15 days rather than 30 days.
However, DOE maintains the review
period for the meeting request at a
maximum of 60 days because DOE and
the relevant Federal and relevant nonFederal entities will be reviewing both
the meeting request and the draft
submission of the 13 resource reports,
which will be substantial and will
benefit from careful review. The review
meeting timeline may be significantly
reduced if the project proponent
chooses to submit resource reports in
advance, and communicates with DOE,
as provided for in the IIP Process.
DOE declines to adopt an immediate
meeting summary review process as
suggested by ACEG and Grid United
because the content of each of the
meetings is likely to be substantial, with
multiple subject matter experts likely to
attend from the relevant Federal entities
and relevant non-Federal entities. DOE
does not agree that immediate
summaries will adequately capture an
initial draft of the meeting outcomes.
DOE also wishes to clarify that the
meeting summary timelines do not add
to the total time of the IIP Process
because they are not precursors to any
subsequent milestones. That is, while
DOE is preparing summaries of each
meeting, preparation or revisions to the
resource reports or other materials
needed for subsequent IIP Process steps
can and should continue. Nonetheless,
DOE does agree that these timelines
should be reduced. Consequently, this
final rule changes the deadline for DOE
to deliver a meeting summary from 15
calendar days after the meeting to 10
calendar days after the meeting, for all
three of the IIP Process meetings.
Similarly, this final rule shortens the
deadline for a project proponent and
other entities to review the meeting
summary from 15 calendar days after
receiving the summary to 10 calendar
days after receiving the summary.
PO 00000
Frm 00023
Fmt 4701
Sfmt 4700
35333
Finally, the deadline for DOE to provide
the final meeting summary is changed
from 15 calendar days after the period
for corrections to 10 calendar days after
the period for corrections. DOE notes
that since these deadlines are expressed
as calendar days, not work days, DOE is
declining additional reductions to
ensure the expectations can be met. In
sum, the revisions reduce the maximum
time period between the conclusion of
an IIP Process meeting and the
finalization of the meeting summary
from 45 calendar days to 30 calendar
days.
In response to comments requesting a
general timetable or presumptive
timeline for the IIP Process or the CITAP
Program, DOE makes no changes in this
final rule. In the proposed rule and
confirmed here, DOE provides decisionmaking timelines for DOE’s
responsibilities in the IIP Process,
leaving the timing of project proponent
actions to trigger the next milestone
flexible to account for differences in
projects. When factoring the changes
described above, the maximum total
time for DOE reviews and responses in
the IIP Process in this final rule is 185
days. Based on that timeline for DOE
decision-making, DOE expects that a
prepared and responsive project
proponent could readily complete the
IIP Process within a year.
DOE does not agree that this final rule
should set a total time for the IIP
Process or CITAP Program. DOE has
chosen to set expeditious timelines for
the actions it and its fellow agencies can
control. But the time required for each
IIP process will ultimately depend on
the needs and capabilities of the project
proponent. Some projects will be able to
move quickly and complete the process
well within a year, while others may
need more time. Even the best-prepared
project proponents may need time to
accommodate re-routing or design
changes that result from unforeseen
developments in the land acquisition
process, the interconnection process, or
other activities that they pursue in
parallel to the IIP Process and that are
not entirely within their control. DOE
makes no revisions to establish
timelines for project proponents to
resubmit materials in response to EDF’s
request to accommodate project
proponents with different capabilities.
DOE is also declining to make revisions
in response to ClearPath’s or CEBA’s
recommendations to allow for
individualized IIP Process schedules;
again, the overall schedule for the IIP
Process will ultimately be determined
by the project proponent. Regarding
PJM’s comment that the IIP Process is
not accounted for in the two-year
E:\FR\FM\01MYR2.SGM
01MYR2
35334
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
schedule described in the 2023 MOU,
DOE confirms that this is accurate and
reflects the agreement in the 2023 MOU.
DOE clarifies that the two-year timeline
begins with the publication of an NOI to
prepare an environmental review
document; the IIP Process is intended to
precede the publication of the NOI. As
discussed in this section and section
VI.H addressing the standard schedule
and project-specific schedules, DOE has
reviewed the timelines set out in this
rule and modified certain timelines in
the IIP Process to further streamline
where appropriate.
In response to comments requesting a
timeline for NOI issuance, DOE revises
this final rule to state that DOE will
issue an NOI within 90 days of the later
of the IIP Process close-out meeting or
the receipt of a complete application for
a Federal authorization for which NEPA
review will be required. This 90-day
timeline aligns with recommended
performance schedules established by
the Federal Permitting Improvement
Steering Council (FPISC). DOE does not
adopt the recommendation to time the
issuance of the NOI on the receipt of all
applications, because some applications
may require more information or project
development before filing. For instance,
both the FPISC-recommended
performance schedules 8 and DOE’s
draft standard schedule indicate that
applications for Clean Water Act (33
U.S.C. 1251 et seq.) (CWA) or Rivers and
Harbors Act (33 U.S.C. 401 et seq.)
permit applications may be filed after
the NOI is issued.9
G. IIP Process Initiation Request
DOE’s Proposal
ddrumheller on DSK120RN23PROD with RULES2
To participate in the CITAP Program,
DOE proposed to require a project
proponent to submit an IIP Process
initiation request to DOE that included
a summary of the qualifying project;
associated maps, geospatial information,
and studies (provided in electronic
format); a project participation plan; and
a statement regarding the proposed
qualifying project’s status pursuant to
Title 41 of the Fixing America’s Surface
Transportation Act (FAST–41) (42
U.S.C. 4370m–2(b)(2)).
8 ‘‘Recommended Performance Schedules.’’
Permitting Dashboard: Federal Infrastructure
Projects, FEDERAL PERMITTING IMPROVEMENT
STEERING COUNCIL, Nov. 2023,
www.permits.performance.gov/sites/
permits.dot.gov/files/2023-11/RPS_
November%202023.pdf.
9 ‘‘Draft Standard Schedule.’’ Grid Deployment
Office, United States Department of Energy, Aug.
2023, www.energy.gov/sites/default/files/2023-08/
CITAP-Standard-Schedule-Draft.pdf.
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
Summary of Public Comments
DOE received two comments on the
contents of the initiation request for the
IIP Process. LTA recommended that
DOE add sufficient and satisfactory title
work for the real property through
which an electric transmission facility
will pass to the list of required materials
for an initiation request in order to
identify conserved lands. ACEG stated
that additional clarity is needed on how
the CITAP program will align with
FAST–41 and stated that a project
proponent might not be able to state
whether the project is covered under
FAST–41 in the IIP Process initiation
request. ACEG also stated it is unclear
how DOE will coordinate with FPISC if
the project is covered under the CITAP
Program and FAST–41.
DOE Response
In this final rule DOE maintains the
required initiation request materials
proposed in the NOPR with no
revisions.
In response to the request to add title
work to the requirements, DOE does not
make this revision because DOE
believes this would be overly
burdensome on the project proponent at
the initiation stage of the IIP Process,
when a project proponent may not have
a finalized route.
In response to the request for more
information on alignment with FAST–
41, DOE first provides clarification on
the provision in the proposed rule. In
the proposed rule, DOE would request
the status of a project under FAST–41
at the time of the initiation request. But
this provision would not ask the project
proponent to speculate as to whether
the project may be covered in the future.
DOE believes the project proponent will
be able to state if the project has applied
for coverage under FAST–41 and if a
coverage determination has been made
at the time of the initiation request, and
therefore DOE makes no changes in this
final rule. Additionally, DOE provides
no revisions regarding coordination
with the Permitting Council because, as
noted by the commenter, a project’s
FAST–41 status may change during the
CITAP Program and therefore DOE
expects that coordination between the
Permitting Council and DOE will vary
on a project-by-project basis. Examples
of such coordination are described in
the 2023 MOU, and DOE designed the
CITAP Program timelines to work in
harmony with the Permitting Council
processes accordingly.
PO 00000
Frm 00024
Fmt 4701
Sfmt 4700
H. Standard and Project-Specific
Schedules
DOE’s Proposal
In the NOPR, DOE proposed to
establish intermediate milestones and
ultimate deadlines for Federal
authorizations and related
environmental reviews through the
introduction of standard and projectspecific schedules in accordance with
the terms of FPA section 216(h)(4) and
of the 2023 MOU. Specifically, DOE
proposed to periodically publish a
standard schedule identifying the steps
needed to complete decisions on all
Federal environmental reviews and
authorizations for a qualifying project
along with the recommended timing for
each step. In addition, DOE proposed to
establish project-specific schedules for
each project participating in the IIP
Process, to set binding deadlines by
which Federal authorizations and
related environmental reviews for a
particular project must be completed.
DOE proposed to base the projectspecific schedule on the standard
schedule, to develop it in consultation
with the project proponent and other
Federal agencies, and to finalize it at the
conclusion of the IIP Process.
Summary of Public Comments
DOE received several comments
regarding the standard schedule and the
development of project-specific
schedules. Two commenters supported
these provisions. The State of Colorado
Governor’s Office stated its belief that
the standard schedule and the projectspecific schedule will provide added
flexibility to each project and expressed
hope that doing so will minimize the
time of the approval process. ClearPath
expressed its support for the
development of the standard schedule
to serve as a baseline for developing
project-specific schedules.
Three commenters raised concerns
that the two-year timeline in the
standard schedule and presumed for the
project-specific schedules was too long,
and a fourth commenter, PJM,
commented in favor of the two-year
timeline, but expressed concerns that it
may still not adequately expedite the
Federal permitting process. OSPA stated
that the proposed two-year EIS process
is still too long. Alan Leiserson
recommended that the standard
schedule deadline should be set at one
year, or as soon thereafter as practicable,
to be consistent with section 216(h).
AEP recommended setting one-year
timelines for environmental assessments
and two years for environmental impact
statements. PJM proposed that DOE
clarify in the proposed revisions that
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
while developing the binding, projectspecific milestones the relevant agencies
will endeavor to shorten the two-year
timeline based on the proposed project’s
scope and location in conjunction with
the relevant statutory requirements.
On the other hand, two commenters
raised concerns that the two-year
timeline was too short. CBD cautioned
against setting any timelines for
environmental reviews because it could
cause agencies to cut corners and result
in increased opposition to proposed
projects. Similarly, AZGFD expressed
concerns that expediting the approval
process to facilitate rapid transmission
infrastructure development may have
unforeseen impacts on wildlife
resources. AZGFD argued that although
establishing a standard schedule would
help in streamlining the process, some
projects might require additional time
for completion of the NEPA analysis
and identification of appropriate
conservation measures. AZGFD
encouraged DOE to have provisions for
independent process-specific
timeframes, rather than a standard
schedule, to allow adequate time for
evaluation and assessment of potential
impacts. AZGFD requested DOE to
provide clear guidelines on
establishment of review times for
cooperating or participating agencies
with statutory authority or special
expertise related to proposed actions.
AZGFD further mentioned that it is
unclear whether the proposed two-year
timeframe applies to the IIP Process, the
NEPA process, or the combined process.
Three commenters suggested the
project proponent provide more input
into the development of the projectspecific schedule. ClearPath
recommended that DOE allow project
proponents to propose a project-specific
schedule. Similarly, ACEG and Grid
United proposed that the project
proponent have the opportunity to
provide DOE and the relevant entities
with a draft project-specific schedule
before the initial meeting, which would
be discussed at the initial meeting. Grid
United also suggested requiring ongoing
consultation between the project
proponent, DOE, and the relevant
agencies as part of finalizing the projectspecific schedule. PJM suggested that
DOE include a provision for revisiting
the CITAP Program at least every two
years to gauge whether the process is
meeting its intended goals.
DOE Response
In this final rule, DOE retains without
revision the proposal in the NOPR to
publish a standard schedule for
completing environmental review and
decision making for Federal
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
authorizations for qualifying projects
within two-years and to develop a
proposed schedule with the NEPA joint
lead agency and the relevant Federal
entities on a project-specific basis
during the IIP Process.
Regarding requests to reduce the twoyear time frame to complete
environmental reviews, DOE makes no
changes to this final rule because DOE
maintains its conviction that, as a
general matter, for transmission projects
of the type that meet the qualifying
project definition, a two-year timeframe
is the shortest practicable length of time
necessary to consider applications for
authorizations under relevant Federal
laws and complete the necessary
environmental reviews. Accordingly,
DOE concludes that a two-year timeline
is likely to be consistent with DOE’s
statutory obligations under FPA section
216(h). However, DOE notes that the
rule does not preclude DOE, in
consultation with relevant agencies,
from setting project-specific timelines
that are shorter than the two-year
timeline, should such a timeline be
practicable.
Regarding concerns that the two-year
timeframe is too short and could reduce
the quality of environmental review or
impact wildlife resources, DOE makes
no changes to final rule because the
CITAP Program does not alter any
Federal environmental review standards
or responsibilities towards wildlife
resources. Additionally, this two-year
timeline is consistent with the timelines
established by the Fiscal Responsibility
Act of 2023. Further, DOE notes that the
standard schedule is a general
framework for environmental review
and authorizations, but that the
proposed and now this final rule require
that DOE develop a schedule specific to
each project that addresses the unique
permitting and review requirements for
that project. In addition, as explained in
the proposed rule, DOE anticipates that
the IIP Process will inform the
environmental review process, such that
a two-year timeline is reasonable. DOE
believes this structure sufficiently
addresses AZGFD’s concerns.
Regarding the request to establish a
standard schedule for EAs, DOE makes
no changes to this final rule because the
CITAP Program focuses DOE resources
on projects expecting to complete an
EIS, and adjustments, including to
schedules, for any project requiring an
EA will be addressed on a projectspecific basis. Accordingly, DOE finds it
unnecessary to establish a timeline for
EAs in the text of this final rule but
notes that the rule does not prevent DOE
from publishing a standard schedule for
EAs if the agency finds it necessary.
PO 00000
Frm 00025
Fmt 4701
Sfmt 4700
35335
Regarding the suggestions that DOE
allow the project proponent to propose
a project-specific schedule or provide
additional opportunities for the project
proponent to discuss the project-specific
schedule with DOE and the relevant
Federal entities, DOE notes that nothing
in the rule prevents the project
proponent from proposing a schedule
but DOE maintains the statutory
authority to set and maintain the
schedule. Additionally, as proposed and
finalized here, DOE requires the project
proponent to submit information on the
intended or desired timelines for
various Federal applications as part of
each meeting request during the IIP
Process. DOE is required to present a
proposed project-specific schedule at
the review meeting and a final projectspecific schedule at the close-out
meeting. Project proponents are
encouraged to communicate with DOE
and relevant entities throughout the IIP
Process. Project proponents are
welcome to submit any information they
believe will help DOE create the projectspecific schedule, including a draft
schedule, through any of these
mechanisms. DOE believes these
requirements provide sufficient
opportunity for the project proponent to
give input on the schedule and therefore
makes no changes to the rule in
response to these comments.
In response to PJM’s suggestion that
DOE revisit the CITAP Program every
two years, DOE makes no revisions in
this final rule. DOE will evaluate the
CITAP Program as appropriate, which
may be based on time, the number of
projects DOE has coordinated in the
process, or other relevant factors.
I. Selection of NEPA Lead and Joint
Lead Agencies and Environmental
Review
DOE’s Proposal
Section 216(h)(2) of the FPA
authorizes DOE to act as the lead agency
to coordinate Federal authorizations and
related environmental reviews required
to site an interstate electric transmission
facility. DOE proposed in the NOPR that
DOE serve as the NEPA lead agency to
prepare an EIS to serve the needs of all
relevant entities. In the NOPR, DOE
proposed that a NEPA joint lead agency
may be designated no later than the IIP
Process review meeting. The NEPA joint
lead agency, if any, would be the
Federal entity with the most significant
interest in the management of the
Federal lands or waters that would be
traversed or affected by the qualifying
project, and DOE would make this
determination in consultation with all
Federal entities that manage Federal
E:\FR\FM\01MYR2.SGM
01MYR2
35336
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES2
lands or waters affected. The proposed
rule also provided that for all qualifying
projects, DOE and the relevant Federal
entity or entities would serve as co-lead
agencies for consultation under the ESA
and for compliance with section 106 of
the NHPA.
After the IIP Process close-out
meeting and once an application has
been received in accordance with the
project-specific schedule, the proposed
rule would require DOE and the NEPA
joint lead agency to prepare an EIS for
the qualifying project, which is meant to
serve the needs of all relevant Federal
entities. The proposed rule would also
require DOE and the NEPA joint lead
agency to consider the materials
developed throughout the IIP Process;
consult with relevant Federal entities
and relevant non-Federal entities; draft
the EIS, working with contractors, as
appropriate; publish all completed
environmental review documents; and
identify the full scope of alternatives for
analysis in consultation with the
relevant Federal entities.
Finally, the proposed rule would also
require the Federal entities or nonFederal entities that are responsible for
issuing a Federal authorization for the
qualifying project to identify all
information and analysis needed to
make the authorization decision,
identify all alternatives that need to be
included, and to use the EIS as the basis
for their Federal authorization decision
on the qualifying project to the extent
permitted by law.
Summary of Public Comments
DOE received several comments
addressing NEPA lead and joint lead
designation and the environmental
review DOE will undertake following
the IIP Process.
Regarding the proposal to establish
DOE as the NEPA lead agency, PJM and
the State of Colorado Governor’s Office
expressed support. The State of
Colorado Governor’s Office noted that
DOE as the lead NEPA agency could
effectively lead an iterative, interagency
process to ensure applications for
Federal authorizations are ready for
review and can meet the specified
timelines. It also noted that having one
agency leading the NEPA process
reduces duplication of work and
improves efficiency.
DOE received comments from CBD,
PIOs, and Gallatin Power regarding the
process for designation of a joint lead
agency. CBD expressed concern that
DOE would not have the expertise to
evaluate impacts of transmission
projects on ecosystems, species, and the
environment, and recommended that
the rules should require the designation
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
of a land use agency as the NEPA joint
lead agency. Gallatin Power commented
that DOE should designate a joint lead
agency that has experience permitting
transmission projects during the
promulgation of the rule and should
implement a practice of identifying a
joint lead agency prior to an IIP Initial
Meeting instead of after the completion
of the IIP Process. Gallatin Power argues
that these joint lead agency designations
will allow DOE to rely on Federal
agencies with substantial experience in
permitting and enable DOE to expedite
approvals through the adoption of
invaluable insights and best practices.
PIOs challenged the proposed rule’s
assumption that only one agency can
serve as a joint lead agency on the basis
that the assumption is a departure from
the statute and CEQ regulations both of
which allow multiple agencies to serve
as ‘‘joint lead agencies.’’ PIOs
encouraged DOE to consider whether
allowing multiple joint lead agencies
could better comport with NEPA and
CEQ regulations and better realize the
proposed rule’s goal of improving
efficiency in Federal analysis and
decision-making.
Three commenters suggested that the
CITAP Program issue a joint record of
decision for projects. CATF, PIOs, and
SEIA recommended that DOE should
ensure that the CITAP Program is in
alignment with the congressional
direction and best practices for NEPA.
They recommended that DOE provide
that, where feasible, agency decisions
should be issued together in a joint
record of decision, or provide greater
clarity as to why DOE declines to
require a joint record of decision. These
commenters noted that requiring a joint
record of decision aligns with recent
revisions to NEPA and CEQ’s NEPA
regulations and promotes efficiency and
coordination. They also suggested that a
joint record of decision effectuates
Congressional direction that the basis
for all decisions under Federal law use
DOE’s environmental review and
reduces confusion about how to seek
judicial review.
Multiple commenters submitted
comments on the scope of
environmental reviews and
considerations. AEP agreed that DOE
should carry out its statutory obligation
to prepare a single EIS sufficient for the
purposes of all Federal authorizations
necessary to site a qualifying project.
AEP further added that, to the extent
practicable, the EIS should also include
any relevant information to satisfy state
permitting requirements to avoid
duplication of reporting requirements.
PIOs noted that the rule’s inclusion of
a requirement to assess climate impacts
PO 00000
Frm 00026
Fmt 4701
Sfmt 4700
is well-founded in NEPA’s plain text, its
implementing regulations, authoritative
guidance, and judicial precedent. PIOs
further stated that DOE has both the
authority and the responsibility to
require assessments of climate related
impacts, as NEPA’s plain text explicitly
includes ‘‘reasonable foreseeable
environment effects.’’ However, PIOs
also stated that DOE should use existing
regulatory and scientific tools that CEQ
makes available to assist other Federal
agencies with their legally required
analysis, and that the resulting analysis
of climate impacts need not be perfect.
AZGFD noted that when completing the
IIP Process and developing the EIS, it is
important to ensure that adequate
consideration is given to wildlife and
wildlife habitat resources along the
project route, that effects to those
resources and areas are not generalized
for the full project route, and that, as
necessary, suitable conservation
measures are identified for specific
areas and resources. AZGFD stated that
it is also important to consider the
varying purposes, management plans,
and land use goals or mandates for
lands managed by different Federal
agencies. Hence, AZGFD requested
further information on how the
proposed rule and development of a
single EIS by DOE will ensure that
wildlife and wildlife habitat resources
are considered and accommodated
through the IIP Process. ACP mentioned
that CEQ is simultaneously conducting
revisions to its regulations
implementing NEPA and suggested that
DOE should ensure that the CITAP
Program and any potential DOE
rulemaking aligns with CEQ’s NEPA
rulemaking.
DOE received multiple
recommendations for streamlining
environmental review. OSPA asserted
that a Programmatic Environmental
Impact Statement (PEIS) would
dramatically speed the deployment of
transmission in chronically underserved
areas of the Upper Great Plains.
Similarly, ACP suggested that DOE
develop resource-specific programmatic
NEPA reviews to reduce the
administrative burden and legal risk of
project-specific reviews. AEP
recommended allowing for greater use
of programmatic reviews and categorical
exclusions. Alan Leiserson said DOE
should use more categorical exclusions
for clean energy projects. AEP
recommended modifying thresholds for
Federal agencies when determining
what requires development of an
environmental document. OSPA
additionally recommended that DOE
should expressly make EIS underlying
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES2
data available to Federal and nonFederal permitting entities for purposes
of developing a PEIS. OSPA
recommended that THPOs explicitly
have access to this data as well as well
as any consultants hired by THPOs.
Three commenters suggested DOE
include statements about what
information or resources could be used
in the environmental review. ACP
argued that the resource reports are
useful beyond the IIP Process and so
this final rule should require that
materials and findings in resource
reports be used in the NEPA EIS
process. ACP further noted that ideally
this authority for consideration of the
resource reports would be DOE’s alone
rather than DOE and the joint lead
agency. AEP recommended stating that
Federal agencies can use existing data
and studies in determining when to
develop an environmental document.
AEP also recommended allowing for
greater project proponent involvement
in preparing environmental documents.
DOE received the following additional
comments:
CBD recommended that DOE
prioritize development on already
degraded lands, existing rights of way,
and other areas where communities will
not object to new infrastructure. ACORE
noted that there may be projects that do
not participate in the CITAP Program,
but that will still have DOE as the lead
agency. Accordingly, ACORE
recommended that DOE clarify which of
CEQ’s NEPA provisions, including
timing requirements, would apply to
these types of projects.
DOE Response
In this final rule, DOE confirms its
role as NEPA lead agency, the process
for selecting a joint lead agency, and the
responsibilities DOE will undertake for
environmental review, with minor
revisions in response to these
comments. DOE revises this final rule to
state that DOE and relevant Federal
entities shall issue, except where
inappropriate or inefficient, a joint
decision document.
Regarding the joint lead agency
selection process, DOE makes no
revisions in response to these
comments. As proposed and confirmed
here, the designation of a joint lead
agency will be determined by DOE and
Federal entities that manage Federal
lands or waters by no later than the IIP
Process review meeting. DOE believes
the process for designating a joint lead,
if any, is consistent with NEPA
implementing regulations and provides
flexibility to identify the relevant
expertise among the relevant entities.
Further, since the rule requires DOE to
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
engage Federal land- and watermanagement agencies in the process,
DOE is not persuaded that including a
joint lead requirement is necessary, as
suggested by CBD and Gallatin Power,
and instead believes it is best to leave
that determination up to the Federal
entities on a project-specific basis.
Regarding the timing of the designation,
DOE notes that this final rule confirms
the same timing as the proposed rule,
requiring the designation by the review
meeting, not the completion of the IIP
Process as indicated by the commenter.
DOE does not agree that a designation
requirement is appropriate before the
initial meeting because DOE believes
the initial meeting provides important
project information that could inform
any joint lead designation. In response
to the PIO’s comment about multiple
joint leads, DOE maintains the
presumption in the rule that no more
than one joint lead agency will be
designated to ensure efficiency and
effectiveness, which will enable DOE to
meet its coordination and scheduling
obligations under FPA section 216(h).
In response to the recommendation
that the CITAP Program issue joint
records of decision, DOE agrees with the
commenters that this would be
consistent with NEPA as amended by
the Fiscal Responsibility Act of 2023.
DOE also agrees that a policy in favor of
joint records of decision would be
consistent with the purpose of FPA
section 216(h) and would enhance
DOE’s coordinating function.
Accordingly, DOE revises this final rule
to provide that, except where
inappropriate or inefficient, the Federal
agencies shall issue a joint record of
decision that includes all relevant
Federal authorizations and, to ensure
consistency with the requirements of
section 216(h), includes, if applicable,
the determination by the Secretary of
Energy of a duration for each land use
authorization issued under section
216(h)(8)(A)(i).
Regarding the scope of environmental
reviews, DOE makes no changes to this
final rule because the rule as proposed
did not change any of DOE or other
Federal entities’ responsibilities to
comply with existing NEPA regulations
and environmental review laws. DOE
will endeavor to incorporate State
requirements in the environmental
review and makes no revisions to
address this because DOE believes this
will be accomplished through the
inclusion of relevant non-Federal
entities in the IIP Process. Similarly,
DOE will endeavor to follow NEPA best
practices and use available tools and
does not find that these comments
require any revisions to the rule.
PO 00000
Frm 00027
Fmt 4701
Sfmt 4700
35337
Regarding ACP’s request to require
the use of resource reports in the
preparation of the environmental review
document, AEP’s request that DOE
include a provision that existing data
can be used, and AEP’s
recommendation that DOE allow for
greater project proponent involvement
in preparing environmental documents,
DOE makes no changes in this final rule.
Data requirements for environmental
reviews are outside of scope of this
rulemaking, which concerns only the
implementation of DOE’s coordinating
authority under FPA section 216(h) and
does not address the substance of NEPA
compliance by DOE or its fellow
agencies. But DOE reiterates that the
purpose of the resource reports is to
inform environmental review (and
agency authorizations), and affirms its
commitment to adhering to best
practices for leveraging existing data
sources. Comments suggesting revised
environmental review thresholds, the
use of categorical exclusions, and PEISs,
are likewise outside the scope of this
rulemaking.
In response to CBD’s request that DOE
prioritize development on already
degraded lands, DOE makes no changes
to this final rule as this is beyond the
scope of DOE’s coordinating authority.
While DOE and its fellow agencies may
encourage development on degraded
lands, DOE lacks authority to impose
any requirement to that effect in the
final rule. In response to ACORE’s
request for more information on how
DOE will serve as lead agency for
projects that are not in the CITAP
Program, DOE makes no changes to this
final rule as this is beyond the scope of
the rulemaking, which is the
implementation of DOE’s coordinating
authority under FPA section 216(h).
J. Section 106 of the NHPA
DOE’s Proposal
In the NOPR, DOE explained that the
project proponent resource reports are
intended to develop data and materials
that will facilitate Federal entities’
review of the project proponent’s
applications under a number of Federal
statutes, including section 106 of the
NHPA. DOE also explained that this
initial information-gathering phase
precedes the formal consultation
process under section 106. DOE
proposed to authorize project
proponents, as applicants to the CITAP
Program, to begin section 106
consultation during the IIP Process, but
only at such time as a project is
sufficiently well developed to allow
formal consultation to begin. DOE
proposed to make this determination
E:\FR\FM\01MYR2.SGM
01MYR2
35338
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES2
within 45 days of the IIP Process review
meeting. Finally, DOE affirmed that
DOE would remain legally responsible
for all findings and determinations
charged to the agency under section
106.
Summary of Public Comments
DOE received multiple comments
related to section 106 of the NHPA.
First, multiple commenters requested
clarification regarding whether, and the
extent to which, the resource reports
would fulfill agencies’ and project
proponents’ section 106 obligations. For
instance, the Kentucky SHPO sought
clarification of whether the resource
reports will serve as only background
information, or if they are intended to
be utilized by the project proponent or
agencies for section 106 consultation
materials, as their purpose would affect
DOE’s ability to impose page limits. It
also stated that it is unclear whether
DOE proposes to frontload NPS National
Historic Landmarks (NHL) review under
section 106, and that doing so is not
feasible from a regulatory standpoint.
The NM SHPO commented that it is not
clear, as proposed, whether the rule
authorizes the project proponent to
initiate consultation with the SHPO and
elicit comments on the resource reports,
and noted that it may not be possible to
account for all of the section 106
impacts of a project at the initiation
stage. The NM SHPO suggested that this
may need to be stipulated in a
Programmatic Agreement and asked
how other agency reviews will be
conducted. Relatedly, the Arizona
SHPO stated that DOE intends to
authorize all project proponents to act
on its behalf and with procedures that
deviate from the standard 36 CFR 800
Subpart B compliance process, and
hence it advised that DOE consult with
the National Conference of State
Historic Preservation Officers
(NCSHPO), NATHPO, and ACHP to
develop a CITAP Program Alternative in
accordance with 36 CFR 800.14. DOE
also received comments from the
Delaware SHPO and NM SHPO
suggesting that DOE consult with ACHP
and other entities regarding NHPA
compliance.
DOE also received comments on the
resource reports as they relate to section
106. The Delaware SHPO recommended
that the requirements of the proposed
‘‘Resource Report 4: Cultural Resources’’
be explicitly defined as cultural
resources identification and evaluation
level surveys, determined necessary
through consultation with consulting
parties, that meet the relevant Secretary
of the Interior Standards and applicable
State and Tribal guidelines. The
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
Delaware SHPO expressed concern that
the provision in its current form might
lead to a scenario wherein the project
proponent could be required to redo
cultural resource reports if initiation
occurs after the submission and review
of resource reports, which would cause
duplication of effort, leading to
unnecessary delays and frustration for
all parties. Conversely, NATHPO and
the Santa Rosa Rancheria Tachi Yokut
Tribe expressed concern regarding a
comment by Department of Energy staff
because they believed it indicated that
the Communities of Interest resource
report would satisfy section 106
conditions for examining the impacts of
projects on Tribal Nations’ cultural
resources and sacred places. The
commenters also stated that the
proposed resource reports are not a
Program Alternative approved by the
ACHP under 36 CFR 800 and cannot be
used to satisfy DOE requirements under
NHPA section 106.
DOE received comments on the
timing of the section 106 process in
relation to the CITAP Program process.
The Delaware SHPO noted that the
current CITAP Program’s schedule
would cause the project to experience
significant delays when complying with
section 106 of NHPA. The Delaware
SHPO explained that, as proposed,
project proponents would be required to
complete resource reports to allow DOE
to determine whether there is an
undertaking. But, the Delaware SHPO
argued, the presence of historic
properties is not a determining factor to
establish an undertaking. Rather, the
Delaware SHPO noted that, per 36 CFR
800.3(a) and 800.16(y), an undertaking
is an action with a Federal nexus, which
is the type of activity with the potential
to cause an effect on historic property.
The Delaware SHPO stated that all
above-ground transmission lines eligible
for the CITAP Program would be
undertakings and the initiation of
consultation should occur concurrently
with or immediately after the first
CITAP Program meeting for a project.
This process would set up the project
proponent, DOE, and all consulting
parties to begin consultation on the
level of survey needed to identify
historic properties early in the process.
The Delaware SHPO noted that earlier
consultation will allow the project to
meet CITAP and NEPA deadlines and
further noted that, with larger
transmission projects, multiple SHPOs
and numerous consulting parties will be
involved and that property access
would need to be arranged for surveys
and longer reports, all of which may
require longer review times. In addition,
PO 00000
Frm 00028
Fmt 4701
Sfmt 4700
if a memorandum of agreement is
needed due to any adverse effects to
historic properties, negotiating and
executing such an agreement could be
time-consuming.
DOE received comments from the
Arizona SHPO and the Kentucky SHPO
indicating that only one agency could be
selected as lead agency for section 106
consultations as the process did not
allow for co-lead agencies.
Finally, DOE received comments
regarding SHPOs’ resource constraints.
The Arizona SHPO expressed concerns
that due to staffing and budgeting
constraints it would not have adequate
resources to conduct preliminary review
of NHPA section 106 for project
proponents prior to the establishment of
a Federal undertaking by Federal
agency.
DOE Response
In this final rule, DOE maintains the
structure and purpose of the resource
reports. DOE revises this final rule as
discussed below to adjust the timeline
for DOE to make a determination of an
undertaking pursuant to section 106 and
to designate DOE as the lead agency for
section 106.
DOE clarifies that the resource reports
are not intended to fulfill the agencies’
section 106 responsibilities. Instead, the
information provided in the Cultural
Resources resource report, and the other
resource reports as applicable, will
contribute to the satisfaction of DOE’s
and relevant Federal entities’
obligations under section 106. As the
lead agency for section 106, DOE
remains legally responsible for all
findings and determinations charged to
the agency under section 106. The
function of the resource reports is to
gather information to contribute to
DOE’s subsequent section 106
compliance. DOE appreciates that
project proponents may not have access
to all information required for DOE’s
section 106 compliance at the time the
proponents submit their resource
reports. This final rule adopts, as
proposed, that a project proponent may
file incomplete information but must
address the reason for the omission. The
final rule also provides the Director of
the Grid Deployment Office the
discretion to allow the project to
proceed to the next milestone and
provides that the Director of the Grid
Deployment Office may waive
requirements as appropriate, providing
flexibility to the IIP Process to
accommodate unique circumstances.
Regarding the comments on particular
resource reports, DOE declines to revise
the definition of cultural resources in
the Cultural Resources resource report
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
in this final rule. That resource report is
intended to inform not only DOE’s
section 106 compliance but also the
environmental review document. Given
that the timing of consultation under
section 106 may vary based on the
project and that this resource report is
intended to fulfill multiple purposes,
DOE necessarily retains its broader
scope. Additionally, as previously
noted, neither the Communities of
Interest resource report nor any other
resource report is intended to fulfill
DOE’s or relevant Federal entities’
obligations under section 106.
As for the comments related to
program alternatives, DOE submitted
the proposed and final rules for
interagency review under E.O. 12866
and intends to work collaboratively
with ACHP and other relevant entities
to develop mechanisms for efficient and
effective implementation of section 106,
which may include program
alternatives. DOE, however, does not
modify this final rule to provide for a
particular program alternative under the
section 106 implementing regulations 10
nor does DOE intend for the resource
reports to serve as a program alternative;
DOE wishes to inform its approach
through initial implementation and
further collaboration with relevant
entities. DOE believes this part provides
sufficient flexibility to allow for an
appropriate alternative without
specifying one at this time.
DOE agrees that initiating the NHPA
section 106 consultation process earlier
than DOE had proposed may be feasible
and beneficial for certain project
proposals that are sufficiently mature
for DOE to determine there is an
undertaking pursuant to the regulations
implementing section 106.11 DOE has
accordingly revised this final rule to
remove the requirement that DOE make
the undertaking determination only
after the IIP Process review meeting. As
revised, the final rule allows DOE to
make the determination at any point in
the IIP Process, but no later than 10
calendar days following the close of the
10-day review period.
Regarding resource constraint
concerns, DOE understands the staffing
and budgeting constraints that SHPOs
and THPOs may face. DOE does not
intend for the IIP Process to create
additional or preliminary review
requirements for SHPOs and THPOs,
and has designed the IIP Process with
the intention of avoiding doing so.
Rather, the intent of the IIP Process is
to align the NHPA section 106 review
with other Federal permitting and
10 See
11 See
36 CFR 800.14.
36 CFR 800.3(a) and 800.16(y).
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
authorization processes. DOE notes that
SHPOs and THPOs may consult with
DOE and other relevant Federal agencies
as to the range of possible assistance
and resources that may be available.
Finally, DOE modifies this final rule
to indicate that DOE intends to serve as
lead agency for section 106 of the NHPA
as section 106 does not provide for a colead agency. The modification aligns
this final rule and regulatory path with
section 106’s statutory language and
procedures.
K. Definitions
i. Affected Landowner
DOE’s Proposal
In the NOPR, DOE proposed to define
‘‘affected landowner’’ as an owner of
real property interests who is usually
referenced in the most recent county or
city tax records, and whose real
property (1) is located within either 0.25
miles of a proposed study corridor or
route of a qualifying project or at a
minimum distance specified by State
law, whichever is greater; or (2) contains
a residence within 3,000 feet of a
proposed construction work area for a
qualifying project.
Summary of Public Comments
Commenters made multiple
suggestions for revisions to the
definition.
ACP recommended that DOE use the
term ‘‘potentially impacted landowner’’
instead of ‘‘affected landowner,’’ given
that ‘‘affected landowner’’ might carry
some implication of an obligation for
compensation.
ClearPath recommended that DOE
adopt the definition of ‘‘affected
landowner’’ used in FERC’s natural gas
pipeline permitting regulations and
FERC’s proposed rule for implementing
section 216(b) of the FPA. ClearPath
suggested that the effective use of
‘‘affected landowner’’ in FERC’s natural
gas pipeline permitting demonstrates
that definition’s legal durability and
thereby bolsters the legal durability and
predictability of this final rule.
Some commenters recommended that
DOE revise the distances included in
the proposed definition of affected
landowner. To that end, SEIA, for
instance, expressed support for a rule
that considers the proposed project
scale, geographic considerations, and
resource usage of landowners to
determine if a landowner falls under an
‘‘affected landowner.’’ Niskanen Center
described the definition of ‘‘affected
landowner’’ as nebulous and thus
impracticable and overly burdensome,
and recommended proximity qualifiers
and a measure of immediate impact to
PO 00000
Frm 00029
Fmt 4701
Sfmt 4700
35339
the definition. LTA recommended that
the rule should move away from a onesize-fits-all distance for the definition of
landowner, and instead require project
proponents to engage with communities
of interest to assist in identifying
potential impacts to landowners and the
distance within which notifications to
landowners would be appropriate. LTA
specifically proposed that DOE expand
the definition of ‘‘affected landowner’’
to include areas that a community of
interest has identified as having one or
more resources likely to be impacted by
a proposed project. Grid United
commented that the specific distances
expressed in the definition of ‘‘analysis
area’’ were not standard for high voltage
transmission lines and could result in
unnecessary data collection, burdens,
and complexity for the project. Grid
United suggested lowering the distances
in the definition to 500 feet and likewise
recommended establishing 500 feet as a
presumptive radius for identification of
affected resources unless existing
practices dictated otherwise. ACP
commented that the 0.25-mile distance
provided is both too broad and too rigid
and proposed that DOE remove
references to a particular distance from
the definition and instead base the
required distance on the physical
characteristics of the project and
resource evaluated in each report.
Commenters also recommended that
DOE include or omit certain
considerations from the definition. LTA
recommended that DOE remove the
reference to county and city tax records
because many owners of real property
interests are not listed in these records.
LTA also suggested that DOE explicitly
include in the definition of ‘‘affected
landowner’’ conservation easement
holders and landowners whose
viewshed or other ecosystem services
may be impacted by the transmission
facility. ACP requested that DOE
explicitly exclude landowners affected
through owning mineral estate property
interests, given the possibility of a
project involving broad areas of
potentially unoccupied land, and
exclude additional areas of potential
construction work, including roads and
ancillary facilities, that may be
preliminary prior to completion of a
NEPA review.
Finally, PIOs recommended that DOE
require project proponents to provide a
landowner bill of rights in transmission
permitting processes to ensure affected
landowners are informed of their rights
in dealings with the proponent and
attached a draft landowner bill of rights
they submitted for FERC’s proposed
backstop permitting rule for reference.
PIOs outlined that the landowner bill of
E:\FR\FM\01MYR2.SGM
01MYR2
35340
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES2
rights should include any information
on requirements to obtain party status
prior to appeal, how to obtain such
status, and if and how a party can
participate in the presidential appeal
process.
DOE Response
In this final rule, DOE revises the
definition of affected landowner, for the
reasons described below, to the
following:
Potentially affected landowner means
an owner of a real property interest that
is potentially affected directly (e.g.,
crossed or used) or indirectly (e.g.,
changed in use) by a project right-ofway, potential route, or proposed
ancillary or access site, as identified in
§ 900.6.
At the outset, DOE clarifies that the
project proponent is responsible for
identifying potentially affected
landowners based on the definition
provided in this final rule. Nevertheless,
as provided in this final rule, the project
proponent must provide, as part of the
IIP Process, the methodology by which
potentially affected landowners were
identified, which will allow DOE to
evaluate the completeness of the
process. Additionally, while the project
proponent makes this determination,
this final rule provides avenues for
communities of interest and
stakeholders to comment on the
proposed project and engage with the
project proponent; this definition does
not limit those avenues.
DOE has also made edits to this
definition in response to comments.
First, DOE agrees with ACP that, at this
stage, landowners are not necessarily
affected, but are only ‘‘potentially’’
affected. Accordingly, DOE changes the
defined term from ‘‘affected landowner’’
to ‘‘potentially affected landowner’’ and
includes a reference to ‘‘potential
indirect and direct effects’’ in the new
definition.
Second, in response to ClearPath’s
comment, DOE has also revised the
definition in this final rule to broaden
how real property interests can be
potentially impacted by the proposed
project, which aligns more closely with
FERC’s definition of ‘‘affected
landowner.’’ DOE declines to adopt the
exact same definition as FERC,
reflecting that FERC’s permitting and
siting rules do not have an identical
purpose to this final rule, which is to
coordinate Federal authorizations for
transmission facilities.
Relatedly, DOE agrees with the
commenters that suggested DOE revise
the distance referenced in the affected
landowner definition. DOE agrees that
in certain instances the distances in the
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
proposed rule will be overinclusive and
overly burdensome, but also that a onesize-fits-all distance will not adequately
capture all landowners that are
potentially affected by the transmission
project. Because a single distance does
not provide sufficient flexibility to
account for differences in projects, DOE
declines to adopt the 500-foot
presumptive distance proposed by Grid
United. Instead, DOE has removed
distances from the definition of
‘‘potentially affected landowner,’’ and
provides that a potentially affected
landowner is one whose real property
interest is either potentially affected
directly or indirectly by the proposed
project. In addition, this final rule
requires the project proponent to
describe the methodology used to
identify potentially affected
landowners. This definition allows
project proponents to more precisely
identify landowners who are most likely
to be potentially affected by the project,
because those real property interests
may not always align with the distances
included in the proposed rule and any
prescribed distances may be under or
overinclusive depending on the
particulars of a project.
Additionally, DOE agrees with LTA’s
comment that the reference to county
and city tax records should be removed.
As LTA noted, tax records may not,
depending on the circumstances,
accurately include the potentially
affected real property interests.
Accordingly, DOE has revised this final
rule to remove the requirement that the
owner of the real property interests is
one who is usually referenced in the
most recent county or city tax records.
However, this final rule does not
preclude the project proponent from
referencing recent tax records. DOE
declines to require the involvement of
communities of interest in the
identification of potentially affected
landowners because this is an
unnecessary step for identifying real
property interests. The term ‘‘potentially
affected landowners’’ is not intended to
refer to all potential impacts; therefore,
additional engagement on impacts of a
proposed project is not needed to satisfy
this definition. Stakeholders and
communities of interest are among the
terms that capture a broader scope of
potential impacts. This final rule also
does not preclude project proponents
from involving communities of interest
in this process.
DOE also declines LTA’s suggestion to
include conservation easement holders
and landowners whose viewshed or
other ecosystem services may be
impacted by the proposed electric
transmission facility. DOE defines
PO 00000
Frm 00030
Fmt 4701
Sfmt 4700
potentially affected landowners in the
context of real property interests. In
some cases, conservation easements
may be considered a real property
interest and certain landowners whose
viewshed or other ecosystem services
may be affected may fall within the
definition of a potentially affected
landowner, but DOE declines to require
that project proponents always include
these landowners since these
landowners may not always be owners
of real property interests that are
potentially affected. Additionally, DOE
has not adopted ACP’s suggestion to
explicitly exclude mineral interest
holders from the definition, as notice to
such parties is still important for
understanding reasonably foreseeable
effects related to mineral entry and
exploration. Nor has DOE adopted
ACP’s recommendation to exclude
additional areas of potential
construction work, because these areas
are potentially relevant for
environmental review and these
landowners could be affected by the
project.
Finally, DOE declines to require
project proponents to provide a
landowner bill of rights. DOE disagrees
with PIOs that a landowner bill of rights
is needed or useful for this process,
because DOE’s exercise of its authority
under section 216(h) does not confer
eminent domain authority. Although
DOE declines to require the provision of
a landowner bill of rights, in response
to PIOs’ request that such a bill of rights
include information on the rehearing
and review process and the presidential
appeals process, DOE notes that these
topics are discussed in Sections VI.O.i
and ii of this document, respectively.
However, in response to both PIOs and
LTA, DOE encourages all interested
parties to proactively engage
transparently and in good faith with
appropriate stakeholders, including
potentially affected landowners, and
may issue best practices on engagement
as discussed in section VI.E of this
document.
ii. Analysis Area
DOE’s Proposal
The NOPR did not provide a
definition for ‘‘analysis area’’ nor did it
use this specific term. However, DOE
sought comment from the public on
whether distances included in the
proposed rule were appropriate, which
informed the definition of this term and
are discussed below.
Summary of Public Comments
DOE requested specific comment on
whether distances included in the
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
proposed rule were appropriate and
received numerous recommendations
on changes to distances in this final
rule.
ACEG commented that the 0.25-mile
distance is too narrow in some contexts
or overly broad in others (e.g., affected
landowners), and that the distance
should be determined by the impacts of
the project. Pew Charitable Trusts
recommended that DOE allow greater
flexibility, stating that while the
proposed distance comports with the
distance FERC would use for project
notification requirements in the context
of National Interest Electric
Transmission Corridors (NIETCs), some
cases warrant a wider area of review,
including in areas that include National
Wildlife Refuges, designated wilderness
areas, cultural resources, or indigenous
sacred sites. Pew Charitable Trusts
suggested that the distance proposal
could be managed like the standard
template schedule, which is open to
change depending on the project.
DOE received three comments
specifically on the Land Use,
Recreation, and Aesthetics resource
report. LTA supported the use of a 0.25mile distance, but because the distance
will vary based on the specifics of each
project and site, proposed that project
proponents also consider an area that a
community of interest, including
experts from local conservation
organizations, has identified as having
one or more resources likely to be
impacted by a proposed project.
PIOs submitted that whether 0.25
miles is a sufficient distance is largely
dependent on the nature of the impacts
that DOE is attempting to identify. PIOs
stated that wilderness areas are
particularly vulnerable to visual impacts
and proposed that DOE use distances of
5–10 miles for when considering visual
impacts of proposed projects. Relatedly,
PIOs noted that certain areas preserved
for wildlife habitat may be vulnerable to
adverse impacts from transmission
projects at distances greater than 0.25
miles, and accordingly, recommended
that areas with valuable habitat for
migratory birds, such as National
Wildlife Refuges, should generally be
identified no less than 10 miles from the
proposed transmission project, and that
DOE should consult with the relevant
agencies and organizations to identify
appropriate distances.
The CARE Coalition stated that the
0.25-mile distance in the Land Use,
Recreation, and Aesthetics resource
report is arbitrary and unsuitable for
several of the resources listed in that
section, including visual resources and
wildlife habitat. Referencing research at
Argonne National Laboratory, the CARE
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
Coalition suggested that a minimum
distance of 10 miles for 500 kV or
greater lines and at least five miles for
230–500 kV lines be used to identify
sensitive visual resources. Additionally,
citing concerns over project impacts to
bird species, the CARE Coalition
recommended DOE require proponents
to identify key habitats for migratory
birds and mammals, such as National
Parks and National Wildlife Refuges,
within 10 miles of proposed projects or
consult with the U.S. Fish and Wildlife
Service (USFWS) to identify adequate
distances for critical migratory bird
nesting and stopover habitats, as well as
for large mammal migration corridors.
The CEC/CPUC also stated that a 0.25mile distance is often too narrow and
may not capture all indirect impacts,
including visual impacts on National
Historical Landmarks. CEC/CPUC
recommended that distances should be
developed with consideration to the
scale and scope of the proposed project
and the specific resources evaluated.
The Arizona SHPO and CEC/CPUC
proposed that DOE align distance
requirements with the Area of Potential
Effect (APE) under section 106 of the
NHPA. The Arizona SHPO
recommended that DOE provide
guidance to project proponents to
develop study areas that conform to the
NEPA definition of affected
environment as applicable to resource
type, and for cultural resource
assessments, includes the definition of
an APE. Relatedly, the Kentucky SHPO
further noted that an APE of 0.25 miles
may be acceptable, depending on the
type of transmission activities proposed,
whether it is new construction or a
rebuild, the applicable SHPO’s
guidance/standards, and any known
resources near the proposed project
area. On the other hand, the NM SHPO
stated that the 0.25-mile distance is not
adequate to address effects to cultural
resources and landscapes, National
Historic Trails, and National
Monuments, especially in western states
where the viewshed is expansive.
DOE Response
In this final rule, DOE removes the
distances proposed, and adds a defined
term, ‘‘analysis area.’’ This approach
allows the participants in the IIP
Process to determine the appropriate
analysis area based on project-specific
factors.
DOE agrees with the many
commenters who indicated the
distances should allow for more
flexibility. Accordingly, DOE has
determined that specific distances
should be removed from the final rule,
as the appropriate distances for various
PO 00000
Frm 00031
Fmt 4701
Sfmt 4700
35341
analyses depend on the relevant
physical characteristics and needs of the
given project and resource at issue.
Instead, as discussed in the revisions to
§§ 900.5 and 900.8, DOE and the project
proponent must, at the initial meeting,
establish initial analysis areas for each
resource as determined by projectspecific factors like ecology, land use
and ownership, and other physical
characteristics of the landscape. The
proposed analysis areas for each
resource may then be refined and
finalized during the IIP Process review
meeting. DOE confirms that
establishment of such analysis areas for
wildlife, fish, and plant life will involve
not only the project proponent but the
appropriate Federal and non-Federal
entities, like the USFWS and relevant
State and local agencies, to ensure
analysis areas are adequate and
consistent with those agencies’
requirements and appropriate guidance.
Relatedly, DOE declines to align the
distance requirements with the APE
under section 106 of the NHPA or to
add any other method of identifying
distances, including relying on
distances identified by communities of
interest, in favor of providing greater
flexibility for the reasons stated above.
DOE notes that where a legal standard
exists for defining the area of analysis
for a particular resource, as in the case
of the APE for historic properties, the
determination of the analysis area for
that resource will take into account that
legal standard.
DOE is adding the defined term
‘‘analysis area’’ to account for the
removal of the distances, and provide a
consistent use of terminology
throughout the final rule that accounts
for the project’s characteristics and
needs and the resources at issue. DOE
defines analysis area to mean an area
established for a resource report at the
IIP Process initial meeting and modified
at the IIP Process review meeting, as
applicable. Discussion of specific uses
of this term is included in section VII of
this document.
iii. Communities of Interest
DOE’s Proposal
In the NOPR, DOE proposed to add a
definition for ‘‘communities of interest’’
to ensure broad coverage of potentially
impacted populations during the public
engagement process and establishment
of the public engagement plan. In the
NOPR, DOE also proposed to define
communities of interest to include
disadvantaged, fossil energy, rural,
Tribal, indigenous, geographically
proximate, or communities with
environmental justice concerns that
E:\FR\FM\01MYR2.SGM
01MYR2
35342
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES2
could be affected by the qualifying
project.
Summary of Public Comments
DOE received multiple comments
suggesting amendments or clarifications
to the definition of ‘‘communities of
interest’’ in the proposed rule.
ClearPath opposed DOE’s definition
of communities of interest, commenting
that the definition is ambiguous and
lacks ‘‘legal durability.’’ ClearPath
pointed specifically to the phrase
‘‘geographically proximate’’ as
ambiguous and commented that the
phrase, ‘‘communities with
environmental justice concerns’’
provides no methodology for project
proponents to adequately identify these
communities. Niskanen Center
proposed that further guidance on the
term might include precise parameters
such as defining it as being within 0.25
miles of a study corridor or potential
route. Niskanen Center also indicated
that the precise meaning of the terms
‘‘disadvantaged,’’ ‘‘fossil energy,’’
‘‘rural,’’ ‘‘geographically proximate,’’ or
‘‘communities with environmental
justice concerns’’ is unclear, potentially
leading to confusion and litigation in
the IIP Process and CITAP Program.
EDF stated that the broad proposed
definition of ‘‘communities of interest’’
could potentially overlook key
differences among and within the
identified communities. Referencing
several White House commitments and
executive orders concerning impacts on
communities with environmental justice
concerns, EDF advised DOE to ensure it
carefully addresses the concerns of
those communities in the proposed rule.
PIOs lauded the proposed rule’s
definition of communities of interest for
broadly including Indigenous
communities. Similar to EDF’s
comments, PIOs maintained that DOE
revise its definition of ‘‘communities of
interest’’ to better reflect environmental
justice issues. PIOs recommended that
DOE remove the term ‘‘disadvantaged,’’
specifically include ‘‘communities of
Color’’ and ‘‘low-income or low-wealth
communities’’ in the definition, and
capitalize the terms ‘‘Color’’ and
‘‘Indigenous.’’
PIOs also suggested that DOE clarify
and ‘‘equitably describe’’ the definition
of ‘‘fossil energy’’ and align the
definition of ‘‘overburdened’’ with the
U.S. Environmental Protection Agency
(EPA) EJ 2020 Glossary. PIOs then urged
DOE to specifically require project
proponents to describe how they will
reach out to communities of interest
about mitigation and require the
resource report to describe proposed
measures or community concerns. PIOs
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
also recommended that DOE require
project proponents to solicit community
comments regarding their preferred
form of mitigation and to respond to
those comments.
Policy Integrity suggested that for
project proponents to identify
communities of interest more
accurately—especially given that DOE
does not define ‘‘disadvantaged,’’ ‘‘fossil
energy,’’ ‘‘rural,’’ or ‘‘communities with
‘‘environmental justice concerns’’—DOE
should provide administrable criteria,
such as project proponents locating
‘‘disadvantaged’’ communities via the
Climate and Economic Justice Screening
Tool. Policy Integrity also recommended
that DOE consider allowing
communities to self-identify, which
would ensure that communities are not
excluded because of limitations of
existing identification tools or methods.
The commenter also indicated it would
be more appropriate for DOE to
adjudicate whether a community should
be considered as having environmental
justice concerns based on evidence
submitted rather than allowing the
project proponent to make this
determination.
LTA suggested that the definition of
communities of interest should include
local nonprofit conservation
organizations to ensure that the
conservation and working lands
community is included early in the IIP
Process.
Finally, NATHPO and the Santa Rosa
Rancheria Tachi Yokut Tribe
commented that categorizing Tribal
Nations as ‘‘Communities of Interest’’
fails to recognize the sovereignty of
Tribal Nations. By doing so, NATHPO
and the Santa Rosa Rancheria Tachi
Yokut Tribe argued that the proposed
rule neglects distinct nation-to-nation
responsibilities.
DOE Response
In this final rule DOE has revised the
definition of ‘‘communities of interest’’
to improve readability and ensure
consistency with the Inflation
Reduction Act (Pub. L. 117–169) (IRA)
but has retained the communities
identified in the proposed rule, as
discussed below. DOE notes that the
project proponent is responsible for
identifying communities of interest and
taking the required actions with respect
to these communities for purposes of
complying with the proponent’s
responsibilities under these regulations,
but through the IIP Process, DOE and
the relevant Federal entities and
relevant non-Federal entities will have
the opportunity to assess the processes
by which proponents identify and
engage with communities of interest.
PO 00000
Frm 00032
Fmt 4701
Sfmt 4700
To improve the readability of the
definition, DOE has revised the
structure of the definition to provide a
list of the types of communities that are
communities of interest. To that end, to
clarify that the communities listed in
the definition is the exclusive set of
communities to which this definition
applies, this final rule edits the
definition to note that communities of
interest ‘‘means’’ rather than ‘‘includes’’
the listed communities. Finally, DOE
has changed the reference to ‘‘fossil
energy’’ communities to ‘‘energy
communities’’ to align the terminology
with that used throughout the IRA’s
programs.
DOE appreciates the comments
regarding the scope of ‘‘communities of
interest’’ and the communities included
in the definition. DOE declines to revise
the communities included within the
definition beyond the revision to ‘‘fossil
energy’’ communities discussed above.
DOE declines to prescribe a particular
distance for ‘‘geographically proximate’’
communities for reasons similar to those
explained above in connection with
‘‘analysis area.’’ For any given project or
community, a set 0.25-mile distance
could be over- or under-inclusive.
Instead, the current definition provides
flexibility and broad coverage for the
project proponent to identify the
communities that could be affected by a
given project.
DOE also declines to provide
definitions for the terms used in the
definition of communities of interest, or
to otherwise narrow the definition. As
written, the definition of communities
of interest provides broad coverage of
various communities and flexibility to
consider relevant groups that may fall
within such communities. Because the
ways in which a project may affect
certain communities varies, DOE
believes that the definition in this final
rule appropriately provides flexibility to
encompass the potentially varied
affected communities of interest.
Relatedly, DOE declines to provide
particular criteria that a project
proponent must consider in identifying
communities of interest, to permit
communities to self-identify or to
require that proponents engage further
with community members, or to
administer in the first instance whether
a particular community qualifies, in
favor of providing flexibility to the
project proponent and the ability of
DOE and the relevant Federal entities
and relevant non-Federal entities to
assess and refine the identification as
needed throughout the IIP Process.
DOE declines to remove or replace the
term ‘‘disadvantaged’’ and declines to
include ‘‘communities of Color’’ and
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
‘‘low-income or low-wealth
communities.’’ The term provides
flexibility for the project proponent to
consider a broad range of disadvantaged
communities that could be affected by
the proposed project. Consistent with its
usage throughout this rule, as well as in
rules promulgated by other agencies
such as FERC, DOE declines to
capitalize the term ‘‘indigenous.’’
Whether or not the term is capitalized,
project proponents have the same
responsibilities to these communities.
Additionally, DOE declines to include
nonprofit groups, as requested by LTA,
as the definition is focused on
communities, not organizations or
entities. Nevertheless, this final rule
does not preclude an organization from
representing a community during IIP
Process engagement, and additionally
provides a definition of stakeholder that
could include the type of organization
LTA describes.
Lastly, DOE affirms the sovereignty of
Indian Tribes. DOE clarifies that the
inclusion of Tribal communities in the
definition of communities of interest is
not intended to, nor does it, neglect the
nation-to-nation responsibilities of
Federal agencies when engaging with
Indian Tribes, which are distinct from
the project proponent’s responsibilities
under the CITAP Program. The CITAP
Program and final rule make no changes
to Federal agencies’ nation-to-nation
responsibilities. DOE’s intent in
including Tribal communities in the
definition is to establish an expectation
that project proponents engage with and
consider the impacts of proposed
projects on Tribal communities.
iv. Other Definition Changes
ddrumheller on DSK120RN23PROD with RULES2
1. Mitigation Approach and Mitigation
Strategies or Plans
DOE’s Proposal
The NOPR included definitions for
two terms, ‘‘landscape mitigation
approach’’ and ‘‘landscape mitigation
strategies or plans.’’ In the NOPR, DOE
proposed to define landscape mitigation
approach to mean an approach that
applies the mitigation hierarchy to
develop mitigation measures for impacts
to resources from a qualifying project at
the relevant scale, however narrow or
broad, that is necessary to sustain those
resources, or otherwise achieve
established resources. Among other
things, the definition explained that the
mitigation hierarchy refers to an
approach that first seeks to avoid, then
minimize impacts, and then, when
necessary, compensate for residual
impacts; while a landscape mitigation
approach identifies the needs and
baseline conditions of targeted
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
resources, potential impacts from the
qualifying project, cumulative impacts
of past and likely projected disturbances
to those resources, and future
disturbance trends, then uses this
information to identify priorities for
mitigation measures across the relevant
area to provide the maximum benefit to
the impacted resources.
In the NOPR, DOE proposed to define
landscape mitigation strategies or plans
as documents developed through, or
external to, the NEPA process that apply
a landscape mitigation approach to
identify appropriate mitigation
measures in advance of potential
impacts to resources from qualifying
projects.
Summary of Public Comments
ACP recommended that DOE cabin
the definition of landscape mitigation
approach. Specifically, ACP suggested
that the definition include a materiality
threshold for all references to impacts to
limit overreach and include language
regarding the practicability of such an
approach. ACP elaborated that the
definition should also permit mitigation
efforts to be conducted following
stakeholder engagement, allow for a
deferral of such approach to mitigation
in lieu of agency-driven mitigation
approaches, and, where stakeholder
engagement efforts are ongoing, allow
for those processes to fully inform the
selected mitigation measures.
DOE Response
In this final rule, DOE has revised
‘‘landscape mitigation approach’’ to a
more general term ‘‘mitigation
approach’’ and removed the defined
term ‘‘landscape mitigation strategies or
plans.’’
DOE revised the definition for
‘‘landscape mitigation approach’’
because limiting mitigation approaches
to only landscape-level approaches and
strategies may not be sufficiently
flexible to account for the variety of
needs implicated by this rule. Rather
than prescribe a single approach, DOE
believes that this final rule should
create an opportunity for consideration
and discussion of multiple types of
proposed mitigation for a given
proposed project. In addition, DOE has
revised this definition for clarity and to
more closely align with existing NEPA
regulations regarding mitigation.
DOE declines to implement ACP’s
suggestion to include a materiality
threshold and a discussion of the
practicability of any proposed
mitigation approaches to limit
overreach, because no decisions are
being made on mitigation during the IIP
Process. Instead, as part of the IIP
PO 00000
Frm 00033
Fmt 4701
Sfmt 4700
35343
Process, the project proponent is
expected to bring to DOE and any
relevant Federal entities and relevant
non-Federal entities a proposed
mitigation approach, which will
facilitate the development of a shared
understanding of project needs and
expectations.
DOE also disagrees with ACP’s
suggestion to include stakeholder
engagement in development of proposed
mitigation approaches both ongoing and
future. This final rule encourages
stakeholder engagement by the project
proponent throughout the IIP Process
and the rule does not preclude the
engagement described in ACP’s
comment. DOE avoids codifying a
particular mitigation approach process
in regulatory text, as this process may
inaccurately indicate a preference or
priority for the approach.
Because the revisions to mitigation
approach rendered ‘‘landscape
mitigation strategies or plans’’
redundant, DOE has removed this
defined term from this final rule.
2. MOU Signatory Agency
DOE’s Proposal
In the NOPR, DOE proposed to define
‘‘MOU Signatory Agency’’ to mean a
signatory of the interagency
Memorandum of Understanding
executed in May 2023, titled
‘‘Memorandum of Understanding among
the U.S. Department of Agriculture,
Department of Commerce, Department
of Defense, Department of Energy, the
Environmental Protection Agency, the
Council on Environmental Quality, the
Federal Permitting Improvement
Steering Council, Department of the
Interior, and the Office of Management
and Budget Regarding Facilitating
Federal Authorizations for Electric
Transmission Facilities.’’
Summary of Public Comments
ACP submitted that, in addition to the
nine agencies that signed the 2023
MOU, the definition should include any
signatories to similar or subsequent
MOUs entered into in the future.
DOE Response
DOE agrees with ACP’s comment that
MOU Signatory Agency should be
sufficiently broad to cover not only
those signatories to the MOU executed
in May 2023, but also to cover
signatories to potential similar or
subsequent MOUs entered into pursuant
to section 216(h)(7)(B)(i) of the FPA
later in time. This final rule revises this
definition to provide this flexibility,
such that if a future MOU includes
additional or different agencies, the
E:\FR\FM\01MYR2.SGM
01MYR2
35344
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
definition in this final rule will not need
to be revised accordingly.
3. Relevant Non-Federal Entity
DOE’s Proposal
In the NOPR, DOE proposed to define
‘‘non-Federal entity’’ as an Indian Tribe,
multi-State governmental entity, State
agency, or local government agency, and
to define ‘‘relevant non-Federal entity’’
as a non-Federal entity with relevant
expertise or jurisdiction within the
project area, that is responsible for
issuing an authorization for the
qualifying project, that has special
expertise with respect to environmental
and other issues pertinent to or
potentially affected by the qualifying
project, or that provides funding for the
qualifying project. The NOPR also
proposed to provide that term includes
an entity with either permitting or nonpermitting authority, such as an Indian
Tribe, Native Hawaiian Organization, or
State or Tribal Historic Preservation
Offices, with whom consultation must
be completed in accordance with
section 106 of the NHPA prior to
approval of a permit, right-of-way, or
other authorization required for a
Federal authorization.
ddrumheller on DSK120RN23PROD with RULES2
Summary of Public Comments
DOE received two comments on the
definition of relevant non-Federal
entity. AZGFD recommended that DOE
include State wildlife agencies as
standard non-Federal entities engaged
in the IIP Process. AZGFD noted that
State wildlife agencies can provide
project-specific special expertise on
wildlife species occurrence and
distributions, areas of potential concern,
wildlife connectivity, and more, as well
as advise on potential conservation
measures to avoid, minimize, or offset
potential impacts. PIOs commented that
DOE should expand the definition to
allow certain members of the public to
participate in the IIP Process. PIOs
noted that, as drafted, the definition
excludes community groups or public
interest organizations because they are
not regulators, even if they have special
expertise with respect to environmental
and other issues pertinent to or
potentially affected by the qualifying
project. Instead, the proposed rule
would consider these entities as
stakeholders, who, as PIOs argued, have
significantly less access to the IIP
Process compared with relevant nonFederal entities. PIOs believe that
allowing community and public interest
groups with special expertise to
participate in the IIP Process would
further the rule’s aim to create an
opportunity to identify as early as
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
possible potential environmental and
community impacts associated with a
proposed project. Relatedly, PIOs
recommended that DOE define the term
‘‘special expertise’’ to help project
proponents, affected communities, and
public interest organizations in better
understanding what groups may meet
this definition and allow community or
public interest groups to request that
they be permitted to participate in the
IIP/CITAP Process by explaining what
special expertise they possess.
DOE Response
DOE revises the definition of relevant
non-Federal entity to replace ‘‘special
expertise’’ with ‘‘relevant expertise’’ to
avoid confusion with the NEPA-defined
term ‘‘special expertise.’’ DOE declines
any further revisions to the definition of
relevant non-Federal entity that would
expand its scope in this final rule.
First, DOE notes that because State
wildlife agencies are likely to have
relevant expertise or jurisdiction within
the proposed project area, may be
responsible for issuing an authorization
for the qualifying project, may have
relevant expertise with respect to
environmental and other issues
pertinent to or potentially affected by
the qualifying project, or may provide
funding for the qualifying project, such
agencies may meet the definition of a
relevant non-Federal entity. The list of
non-Federal entities included in the
definition merely provides examples
and is not a comprehensive list.
Next, DOE appreciates the expertise of
community groups and public interest
organizations. Rather than expand the
definition of relevant non-Federal
entity, DOE believes that the IIP Process,
coupled with existing avenues for
public comment, will best integrate the
expertise and input of community
groups and public interest
organizations. The IIP Process provides
for timely and focused pre-application
meetings with relevant Federal entities
and relevant non-Federal entities, as
well as for early identification of
potential siting constraints and
opportunities, and seeks to promote
thorough and consistent stakeholder
engagement by a project proponent. The
IIP process is not, however, intended to
supplant existing public comment
processes afforded by relevant statutes,
such as NEPA. DOE believes that it has
appropriately defined relevant nonFederal entity to provide the necessary
information to fulfill its obligations
under section 216(h) and facilitate the
pre-application process, while still
providing sufficient avenues for others
to participate as stakeholders and
through those existing public-comment
PO 00000
Frm 00034
Fmt 4701
Sfmt 4700
processes. DOE declines to provide a
definition for special expertise because
the term has been removed from the
rule. DOE does not expand the
definition of non-Federal entity to
explicitly include non-regulating or
non-permitting entities as the current
definition may already include those
entities as long as they meet additional
criteria.
4. Stakeholder
DOE’s Proposal
In the NOPR, DOE proposed to define
the term ‘‘stakeholder’’ to mean any
relevant non-Federal entity, any nongovernmental organization, affected
landowner, or other person potentially
affected by a proposed qualifying
project.
Summary of Public Comments
ACP commented that the proposed
definition of ‘‘stakeholder’’ is overly
broad, including its reference to anyone
‘‘potentially affected by the proposed
qualifying project.’’ ACP suggested that
DOE narrow the definition to a party
able to show some cognizable interest
potentially being affected by the project.
DOE Response
In this final rule, DOE revises the
definition of ‘‘stakeholder’’ to provide
that the term means any relevant nonFederal entity, interested nongovernmental organization, potentially
affected landowner, or other interested
person or organization.
In part, DOE has revised this
definition to reflect the revision to
terminology used in this final rule, i.e.,
replacing ‘‘affected landowner’’ with
‘‘potentially affected landowner,’’ for
the reasons explained above. DOE has
also revised the definition to provide
more precise parameters for who is a
stakeholder for purposes of this final
rule, in some instances narrowing the
definition and in others, broadening it.
Specifically, the definition clarifies that
only ‘‘interested,’’ rather than ‘‘all,’’
non-governmental organizations are
stakeholders, which appropriately limits
coverage to only those nongovernmental organizations that have
interest in the proposed project.
Additionally, DOE revises the definition
to provide that any other stakeholders
must be ‘‘interested’’ and provides that
stakeholders may be interested persons
or organizations. This revision broadens
the scope of other stakeholders beyond
only persons, allowing those
organizations that do not fall within the
scope of relevant non-Federal entity,
non-governmental organization, or
potentially affected landowner to be
considered stakeholders. DOE believes
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
this revision is appropriate given the
diversity of entities that may be affected
by or interested in a proposed project.
Additionally, the revision broadens the
definition beyond those who are
potentially affected to those who are
interested. Again, DOE believes this
expansion is appropriate in light of
various entities that may have equities
in a proposed project. For instance, LTA
raised in its comment that local
conservation organizations may have
relevant expertise and views on a
proposed project.
DOE disagrees with ACP’s proposal to
narrow the definition to only those
parties able to show some cognizable
interest potentially being affected by the
project. First, DOE does not discern a
practical difference in requiring that an
interest be ‘‘cognizable,’’ and believes
that DOE’s definition is consistent with
ACP’s intent to ensure stakeholders
have an interest in or are potentially
affected by a proposed project. Second,
DOE believes ACP’s proposal is
unnecessarily narrow and may
potentially exclude relevant persons,
organizations, or entities from the
CITAP Program, including relevant nonFederal entities. Finally, DOE clarifies
that this definition does not determine
who is a party or has standing to
challenge a relevant authorization or
related environmental review document
issued under section 216(h).
5. Study Corridor
DOE’s Proposal
DOE proposed to define study
corridor as a contiguous area (not to
exceed one mile in width) within the
project area where alternative routes or
route segments may be considered for
further study.
ddrumheller on DSK120RN23PROD with RULES2
Summary of Public Comments
DOE received two comments on the
definition of the term study corridor.
ACP recommended that the definition
regarding consideration of NEPA
alternative routes should be restricted to
only those within the study corridor.
ACP also recommended that the
definition of study corridor be limited to
alternative routes already within
consideration of the study corridors,
because, as ACP argued, this would
cabin the scope of review and is
necessary to avoid potential litigation
risk if the rule were to require
proponents to consider all potential
alternative routes. OSPA requested that
this final rule allow for study corridors
wider than one mile to consider more
alternative transmission paths. OSPA
described that the one-mile width
restriction is inconsistent with the broad
definition of ‘‘project area,’’ which may
limit the evaluation of potential
transmission sites. OSPA therefore
urged DOE to either change the
definition or allow proponents to
request exemptions from the one-mile
restriction.
DOE Response
In this final rule, DOE revises the
definition of study corridor to clarify the
role of study corridors and the
relationship between this term and
other NEPA-related terms, as provided
in section IV of this document.
DOE declines to revise the definition
as ACP recommended. First, DOE
clarifies that the project area may
contain multiple study corridors and
that those study corridors may include
multiple potential routes. Additionally,
DOE notes that study corridors are
proposed by the project proponent, and
the number of such study corridors will
be driven by the project proponent,
depending on the level of development
of the project design at the time of IIP
Process initiation. While these study
corridors are developed by the project
proponent, nothing in this rule commits
DOE to limiting NEPA alternatives to
these study corridors. The definition
suffices to allow DOE and the relevant
Federal entities to evaluate the study
corridor and potential NEPA
alternatives through the IIP Process.
DOE declines to implement OSPA’s
recommendation that the definition
allow for study corridors wider than one
mile. DOE assesses that the one-mile
distance suffices to provide DOE and
the relevant Federal entities with the
information necessary to make the
relevant determinations and issue the
relevant authorizations, while avoiding
overburdening the project proponent.
6. Resilience
DOE’s Proposal
As noted, DOE proposed to require
the submission of 13 resource reports,
Resource report name
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
one of which would be titled Reliability,
Resilience, and Safety.
Summary of Public Comments
One anonymous commenter noted
that DOE did not provide a definition of
the term ‘‘resilience’’ and requested that
DOE define the term.
DOE Response
DOE declines in the final rule to
provide a definition for the term
‘‘resilience.’’ This term does not appear
outside of the Reliability, Resilience,
and Safety resource report and its
meaning is evident from the substance
of that report.
7. Proposed Facility
DOE’s Proposal
In the NOPR, DOE used the term
‘‘proposed facility’’ to delineate the
scope of certain information project
proponents would be required to
submit. For instance, the NOPR
proposed in § 900.3(b) to require the
project proponent to provide a concise
description of the proposed facility and
a list of anticipated relevant Federal and
non-Federal entities involved in the
proposed facility.
Summary of Public Comments
CARE Coalition requested that DOE
provide a definition of the term
‘‘proposed facility.’’
DOE Response
DOE declines in the final rule to
provide a definition for proposed
facility. DOE believes that the meaning
of this term is sufficiently clear from the
context and notes that through the IIP
Process, project proponents will be able
to refine the scope of the proposed
facility as needed.
L. Resource Reports
The PIOs noted that DOE’s resource
reports are similar to the resource
reports required under FERC’s proposed
rule regarding FERC’s siting authority in
NIETCs, per FPA section 216(b). The
PIOs recommended that DOE align the
numbering of resource reports with the
numbering in FERC’s proposed rule.
DOE agrees with the suggested
numbering change and has renumbered
the reports accordingly. The following
table catalogs the renumbering.
Proposed rule numbering
General Project Description ..............................
Water Use and Quality ......................................
Fish, Wildlife, and Vegetation ............................
Cultural Resources ............................................
Socioeconomics .................................................
Geological Resources .......................................
Resource
Resource
Resource
Resource
Resource
Resource
PO 00000
Report
Report
Report
Report
Report
Report
Frm 00035
1
2
3
4
5
6
...........................................
...........................................
...........................................
...........................................
...........................................
...........................................
Fmt 4701
Sfmt 4700
35345
Final rule numbering
Resource
Resource
Resource
Resource
Resource
Resource
E:\FR\FM\01MYR2.SGM
Report
Report
Report
Report
Report
Report
01MYR2
1.
2.
3.
4.
5.
8.
35346
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
Resource report name
Proposed rule numbering
Soil Resources ..................................................
Land Use, Recreation, and Aesthetics ..............
Communities of interest .....................................
Air Quality and Noise Effects ............................
Alternatives ........................................................
Reliability, Resilience, and Safety .....................
Tribal Interests ...................................................
Resource
Resource
Resource
Resource
Resource
Resource
Resource
In this final rule, DOE also makes
non-substantive edits to the proposed
rule text of the resource reports to
clarify the intent of the reports and
clearly state the information that must
be included in the reports. Across the
resource reports, DOE reorganizes the
proposed paragraphs to state the
purpose of the resource report in the
introductory paragraph (e.g., paragraph
(j)) and list all requirements for the
resource report in subparagraphs (e.g.,
paragraphs (j)(1), (2), etc.).
DOE’s responses to comments on the
resource report requirements as well as
additional changes to the resource
report requirements are discussed as
follows. The ordering of the discussion
follows the ordering of the resource
reports in the NOPR.
provide the names and mailing
addresses of all affected landowners;
summarize any relevant potential
avoidance, minimization, and
conservation measures; and describe
how the project will reduce capacity
constraints and congestion on the
transmission system, meet unmet
demand, or connect generation
resources to load, as appropriate.
ddrumheller on DSK120RN23PROD with RULES2
i. General Project Description Resource
Report
DOE’s Proposal
In the NOPR, DOE proposed to
require the submission of a resource
report containing a general project
description. The NOPR proposed that
this report describe facilities associated
with the project, special construction
and operation procedures, construction
timetables, future plans for related
construction, compliance with
regulations and codes, and permits that
must be obtained.
In the NOPR, DOE proposed 12 topics
that would be required as part of the
report. The NOPR required that the
project proponent: describe and provide
location maps of all relevant facilities,
access roads, and infrastructure;
describe specific generation resources
that are known or reasonably foreseen to
be developed or interconnected; identify
other companies that may construct
facilities related to the project and
where those facilities would be located;
provide certain information regarding
the facilities identified; provide certain
information if the project is considering
abandonment of certain resources;
describe proposed construction and
restoration methods; describe estimated
workforce requirements; describe
reasonably foreseeable plans for future
expansion of facilities; describe all
authorizations required and identify
environmental mitigation requirements;
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
Report
Report
Report
Report
Report
Report
Report
7 ...........................................
8 ...........................................
9 ...........................................
10 .........................................
11 .........................................
12 .........................................
13 .........................................
Summary of Public Comments
DOE received one comment
addressing the General Project
Description resource report that is not
already addressed in other sections of
the discussion. ClearPath opposed the
requirement that project proponents
‘‘describe how the project will reduce
capacity constraints and congestion on
the transmission system, meet unmet
demand, or connect generation
resources (including the expected type
of generation, if known) to load, as
appropriate,’’ arguing that this
information is outside the scope of
Federal jurisdiction under FPA 216(h).
That comment and others addressing
reasonable and foreseeable generation
are discussed in section VI.D of this
document.
DOE Response and Summary of Other
Changes
In this final rule, DOE retains the
scope and purpose of this resource
report with no revisions in response to
ClearPath’s comment because
information may be helpful for
understanding the project proponent’s
purpose and need and the potential
scope of the environmental review,
consistent with DOE’s coordinating
obligations under FPA section 216(h).
Additionally, DOE is eliminating a
requirement from the NOPR for this
report to include correspondence with
the USFWS and National Marine
Fisheries Service regarding potential
impacts of the proposed facility on
federally listed threatened and
endangered species and their designated
critical habitats because that
correspondence is already required in
Resource Report 3: Fish, Wildlife, and
Vegetation, thereby reducing
duplication of requirements.
PO 00000
Frm 00036
Fmt 4701
Sfmt 4700
Final rule numbering
Resource
Resource
Resource
Resource
Resource
Resource
Resource
Report
Report
Report
Report
Report
Report
Report
9.
10.
7.
11.
12.
13.
6.
ii. Water Use and Quality Resource
Report
DOE’s Proposal
In the NOPR, DOE proposed requiring
project proponents to submit a report on
existing water resources that may be
impacted by the proposed project, the
impacts of the proposed project on those
resources, and proposed mitigation,
enhancement, or protective measures to
address those impacts.
Summary of Changes
DOE did not receive any comments on
the Water Use and Quality Report that
have not been addressed in another
section of this final rule. However, DOE
has made several changes to the
requirements for the resource report
between the NOPR and this final rule.
In keeping with the discussion in
section VI.K.ii of this document, DOE is
replacing two distances included in the
proposed rule with ‘‘in the applicable
analysis area’’ to give DOE, the project
proponent, and appropriate Federal and
non-Federal entities flexibility to set
these distances based on the physical
characteristics and needs of the project.
A project proponent must now identify
the location of known public and
private groundwater supply wells or
springs within the applicable analysis
area rather than within ‘‘150 feet of
proposed construction areas.’’ A project
proponent must now identify any
downstream potable water intake
sources within the applicable analysis
area, rather than ‘‘three miles
downstream’’ of a surface water
crossing.
DOE is making several terminology
changes to clarify the scope of the
analyses required by the report. The
report now requires the project
proponent to identify surface water
resources crossed by a ‘‘potential route’’
rather than ‘‘the project.’’ The report
also requires wetland maps showing
‘‘study corridors and potential routes’’
rather than just a ‘‘proposed route.’’
Finally, the report requires
identification of aquifers and wellhead
protection area crossed by a ‘‘potential
route,’’ rather than ‘‘proposed
facilities.’’
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
Lastly, DOE is relocating a
requirement to indicate whether a water
quality certification under section 401
of the CWA will be required for any
potential routes. This requirement was
proposed for the General Project
Description resource report but has been
moved into the requirements for this
report because it deals directly with
water resources.
iii. Fish, Wildlife, and Vegetation
Resource Report
DOE’s Proposal
In the NOPR, DOE proposed to
require the submission of a resource
report on fish, wildlife, and vegetation.
As proposed, DOE required this report
to include a description of aquatic life,
wildlife, and vegetation in the proposed
project area; expected impacts on these
resources including potential effects on
biodiversity; and proposed mitigation,
enhancement, avoidance, or protection
measures. DOE also proposed that this
resource report may require species
surveys to determine significant habitats
or communities of species of special
concern to Federal, Tribe, State or local
agencies, or field surveys to determine
the presence of suitable habitat. Finally,
DOE proposed requiring the project
proponent to provide a description of
the proposed measures to avoid and
minimize incidental take of Federally
protected species, including eagles and
migratory birds as part of this resource
report.
ddrumheller on DSK120RN23PROD with RULES2
Summary of Public Comments
DOE received two comments on the
Fish, Wildlife, and Vegetation resource
report, from AZGFD and the CARE
Coalition.
AZGFD encouraged DOE to include
State wildlife sensitive species,
especially those classified as of Greatest
Conservation Need in individual State
Wildlife Action Plans. AZGFD also
recommended that potential impacts
from habitat loss and fragmentation,
including potential impacts on wildlife
connectivity, identified habitat linkages
or wildlife corridors, be analyzed in the
report, considering that transmission
infrastructure affects wildlife
movements and habitat use. It suggested
that DOE provide guidance in the rule
regarding coordination with State
wildlife agencies on conservation
measures necessary for adequate
wildlife connectivity.
The CARE Coalition suggested that
the report should describe known
migratory corridors for large mammals
within three kilometers of the proposed
line. The CARE Coalition also suggested
that project proponents should consult
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
with USFWS to determine a distance at
which the project proponent should
identify Federally listed or proposed
endangered or threatened species and
critical habitats in the report.
DOE Response and Summary of Other
Changes
DOE makes minor revisions in
response to these comments. In
response to AZGFD’s request to include
classifications like ‘‘Greatest
Conservation Need,’’ DOE revises this
final rule to request relevant
information on ‘‘State, Tribal, and local
species of concern and those species’
habitats’’ because DOE believes this
broader terminology addresses the
concern raised by the commenter and
additionally extends to consider
species, habitats, or communities of
species of concern to Federal, Tribal,
State, or local agencies. DOE also agrees
that habitat fragmentation impacts are
relevant to the resource report and
revises this final rule to include
information on the potential effects of
the proposed project on habitats,
including effects related to habitat loss
and fragmentation. Regarding AZGFD’s
request for guidance on coordination
with State wildlife agencies, DOE makes
no changes to this final rule as such
coordination will depend on project
specific circumstances, for example if a
wildlife agency in the State participates
as a relevant non-Federal entity in the
IIP Process.
In response to CARE Coalition’s
request to include mammalian
migratory corridors, DOE makes no
revisions to this final rule. DOE believes
the detail requested in the resource
report is sufficient to provide such
information if it is relevant to the
project.
DOE is also making changes to the
proposed rule text that are not in
response to a specific comment. DOE is
making several changes to clarify the
scope of the analyses required in the
report. The rule now requires the project
proponent to identify aquatic habitats in
the ‘‘applicable analysis area’’ rather
than in the ‘‘affected area’’ and cabins
the requirement to identify terrestrial
habitats to only those terrestrial habitats
in the project area. The rule also
requires information on essential fish
habitat which may be adversely affected
by ‘‘potential routes,’’ rather than ‘‘the
project.’’
In keeping with the discussion in
section VI.K.ii of this document, DOE is
replacing four distances and areas
included in the proposed rule with ‘‘in
the applicable analysis area’’ to give
DOE, the project proponent, and
appropriate Federal and non-Federal
PO 00000
Frm 00037
Fmt 4701
Sfmt 4700
35347
entities flexibility to set these distances
based on the physical characteristics
and needs of the project. DOE is now
requiring a project proponent to identify
aquatic habitats that occur in the
‘‘applicable analysis area’’ rather than in
the ‘‘affected area.’’ Additionally, DOE
is requiring the project proponent to
identify proposed or designated critical
habitats that potentially occur in the
‘‘applicable analysis area’’ rather than
the ‘‘project area.’’ DOE is also now
requiring a project proponent to identify
the location of potential bald and golden
eagle nesting and roosting sites,
migratory bird flyways, and any sites
important to migratory bird breeding,
feeding, and sheltering within the
‘‘applicable analysis areas,’’ rather than
within ‘‘10 miles of the proposed project
area.’’ While 10 miles is currently the
USFWS standard, DOE opts to leave
establishment of these boundaries
flexible for future project needs as well
as any future updates to USFWS
requirements. Likewise, DOE is
requiring the project proponent to
identify all Federally designated
essential fish habitat that occurs in the
‘‘applicable analysis area’’ whereas in
the proposed text, the scope of that
identification was undefined.
Lastly, the rule clarifies the role of
surveys in the resource report. The rule
provides that the project proponent
must include the results of any
appropriate surveys that have already
been conducted and provide protocols
for future surveys. The rule maintains
the provision that if potentially suitable
habitat is present, species-specific
surveys may be required.
iv. Cultural Resources Resource Report
DOE’s Proposal
In the NOPR, DOE proposed to
require the submission of a resource
report on cultural resources, which
would contribute to the satisfaction of
DOE’s and other relevant Federal
entities’ obligations under section 106 of
the NHPA. The NOPR required the
resource report to describe known
cultural and historic resources in the
affected environment, including those
listed or eligible for listing on the
National Register of Historic Places
(NRHP), potential adverse effects to
those resources, and recommended
avoidance and minimization measures
to address those potential effects. It also
required the resource report to
document the project proponent’s initial
communications and engagement with
and comments from Indian Tribes,
indigenous peoples, THPOs, SHPOs,
communities of interest, and other
relevant entities, and provide details
E:\FR\FM\01MYR2.SGM
01MYR2
35348
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
regarding surveys. Finally, the NOPR
required that the project proponent
request confidential treatment for all
materials filed with DOE containing
location, character, and ownership
information about cultural resources.
ddrumheller on DSK120RN23PROD with RULES2
Summary of Public Comments
DOE received one comment on the
Cultural Resources Resource Report
from NM SHPO that is not otherwise
addressed in section VI.J of this
document.
NM SHPO appreciated DOE’s
requirement for project proponents to
consider treatments to avoid, minimize,
or mitigate harmful impacts to the
landscape, but encouraged DOE to also
require project proponents to consider
these treatments for individual historic
properties eligible for or listed in the
NRHP. This inclusion would require
that resource reports begin with historic
contexts for landscape-level evaluations
and that other Federal agencies examine
landscape-level eligibility and effects
during the review of resource reports.
The NM SHPO noted that in New
Mexico, consultants are required to
meet State documentation guidelines
before accessing cultural resource
records to produce a cultural resources
report, and subsequently questioned
whether DOE’s regulation will
acknowledge or supersede State
statutes, regulations, or guidelines.
DOE Response and Summary of Other
Changes
DOE makes no revisions in response
to NM SHPO’s comment. DOE clarifies
that while the CITAP Program is
intended to facilitate coordination with
relevant State statutes, regulations, and
guidelines, the rule does not supersede
State statutes, regulations, or guidelines.
Regarding the NM SHPO’s request that
the rule should consider treatments to
mitigate harmful impacts on certain
individual properties, DOE notes that
the rule does not preclude this sort of
action, but makes no revisions to
mandate a particular approach to
mitigation because DOE believes these
approaches are more appropriate to
discuss in the context of project-specific
circumstances. The updated definition
of mitigation approach in this final rule
is intended to create an opportunity for
consideration and discussion of
multiple types of mitigation strategies
for a proposed project. DOE also notes
that no decisions are made on
mitigation during the IIP Process; rather,
the IIP Process facilitates the
development of a shared understanding
of project needs and expectations.
DOE is also making several changes to
the proposed rule text that are not in
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
response to a specific comment. In
keeping with the discussion in section
VI.K.ii of this document, DOE is now
requiring a summary of known cultural
and historic resources in the ‘‘applicable
analysis area’’ rather than in the
‘‘affected environment.’’
Furthermore, in the requirement to
provide a summary of known cultural
and historic resources, DOE is adding as
an example of those resources,
properties of religious and cultural
significance to Indian Tribes, and any
material remains of past human life or
activities that are of an archeological
interest. This change was made to
broaden and clarify the definition of
cultural resources included in the rule.
v. Socioeconomics Resource Report
appropriate Federal and non-Federal
entities flexibility to set these distances
based on the physical characteristics
and needs of the project. The rule now
requires the project proponent to
describe the socioeconomic resources
that may be affected in the ‘‘applicable
analysis area’’ rather than in the
‘‘project area.’’ Likewise, the rule
requires the project proponent to
evaluate the impact of any substantial
migration of people into the ‘‘applicable
analysis area’’ rather than the ‘‘proposed
project area.’’ Finally, the rule replaces
‘‘impact area’’ with ‘‘applicable analysis
area’’ in several instances because
‘‘impact area’’ is not defined in the rule.
vi. Geological Resources and Hazards
Resource Report
DOE’s Proposal
In the NOPR, DOE proposed to
require the submission of a resource
report on socioeconomics. DOE
proposed to require in this resource
report the identification and
quantification of the impacts of
constructing and operating the proposed
project on the demographics and
economics of communities in the
project area, including minority and
underrepresented communities.
DOE’s Proposal
Summary of Public Comments
DOE received one comment
addressing the required elements of the
Socioeconomics resource report.
ClearPath recommended that DOE
exclude the requirement for project
proponents to ‘‘evaluate the impact of
any substantial migration of people into
the proposed project area on
governmental facilities and services and
describe plans to reduce the impact on
the local infrastructure’’ because it is
ambiguous and beyond DOE’s statutory
authority. Furthermore, ClearPath noted
the project proponent is not responsible
for minimizing the impact on local
infrastructure from the significant
migration of people.
Summary of Changes
DOE Response
DOE makes no revisions in response
to this comment because DOE finds this
information is commonly requested for
evaluating the impacts of infrastructure
permitting.12
DOE is making several changes to the
proposed rule text that are not in
response to a specific comment. In
keeping with the discussion in section
VI.K.ii of this document, DOE is
replacing multiple areas of study
included in the proposed rule with ‘‘in
the applicable analysis area’’ to give
DOE, the project proponent, and
12 See,
PO 00000
for example, 10 CFR 380.16(g).
Frm 00038
Fmt 4701
Sfmt 4700
The NOPR proposed requiring project
proponents to submit a resource report
on geological resources that might be
affected by the proposed project and
geological hazards that might put the
proposed project at risk. As written, the
NOPR required the resource report to
include a description of methods to
reduce the effects on geological
resources and reduce the risks posed by
the hazards.
DOE did not receive any comments on
the Geological Resources resource report
that have not been addressed in another
section of this final rule. However, DOE
has made minor changes to the
requirements and description for the
resource report between the NOPR and
this final rule.
The title of this resource report has
been updated to ‘‘Geological Resources
and Hazards’’ to better reflect the scope
of the report. Additionally, in keeping
with the discussion in section VI.K.ii of
this document, DOE is clarifying that
the project proponent only needs to
describe geological resources and
hazards ‘‘in the applicable analysis
area.’’ The proposed rule did not
provide a definite boundary for these
identifications.
vii. Soil Resources Resource Report
DOE’s Proposal
The NOPR proposed requiring project
proponents to submit a resource report
on soil resources that might be affected
by the proposed project, the effect on
those soils, and measures proposed to
avoid, minimize, or mitigate impact.
Summary of Changes
DOE did not receive any comments on
the Soil Resources resource report that
have not been addressed in another
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
Summary of Public Comments
inclusion of this resource report and
commented specifically in support of
retaining multiple provisions of this
report.
DOE received responses on whether
revisions were needed to paragraph
(m)(8) from LTA and CEC/CPUC. The
CEC/CPUC advised DOE to divide
§ 900.6(m)(8) into two sections: one
about conservation lands and another
about lands with protective covenants
due to distinct management practices.
LTA recommended adding
‘‘conservation or agricultural lands
subject to state statutorily enabled
conservation or agricultural easements
or restrictions’’ to the list of examples.
CEC/CPUC recommended DOE include
lands conserved and held by local focus
on land use restrictions, and include
more specific provisions that
agricultural conservation lands
described should only include those
with formal designations.
LTA recommended requiring the
project proponent to describe ‘‘an area
a Community of Interest has identified
as having one or more resources likely
to be impacted by a proposed project’’
in addition to the specifically listed
areas under the list of Federal
designations in paragraph (10). LTA also
recommended adding to the specifically
listed areas ‘‘National Forests and
Grasslands’’ and ‘‘lands in easement
programs managed by the Natural
Resource Conservation Service or the
U.S. Forest Service’’ to this paragraph.
LTA recommended DOE revise its
request for a detailed operations and
maintenance plan for vegetation
management to include, ‘‘that utilizes
native species to the maximum extent
practical.’’
ACP stated that the requirement that
proponents identify all residences and
buildings within 200 feet of the edge of
the proposed transmission line
construction right-of-way was
‘‘excessively onerous’’ and impractical.
ACP suggested that the transmission
right-of-way is a more appropriate
boundary than the construction right-ofway.
AZGFD recommended that this
resource report identify potential
impacts to access for State wildlife
agencies to carry out their
responsibilities, outdoor recreation, and
recreational access. AZGFD urged DOE
to coordinate with State wildlife
agencies to ensure actions do not
prevent State agencies from conducting
their responsibilities.
DOE received several comments on
required elements of the Land Use,
Recreation, and Aesthetics Resource
Report. LTA expressed support for the
DOE Response and Summary of Other
Changes
DOE retains the scope and purpose of
the Land Use, Recreation, and
section of this final rule. However, DOE
has made one substantive change to the
requirements for the resource report
between the NOPR and this final rule.
The NOPR proposed that a project
proponent would need to list and
describe soil series for any ‘‘site larger
than five acres.’’ However, because
almost all projects in the CITAP
Program would cover more than five
acres, this distinction would not set an
effective boundary on the area of the
requirement. Therefore, this final rule
requires identification and description
of soil series within ‘‘the applicable
analysis area’’ to allow DOE, the project
proponent, and relevant Federal and
non-Federal entities to determine the
scope of the analysis needed.
viii. Land Use, Recreation, and
Aesthetics Resource Report
ddrumheller on DSK120RN23PROD with RULES2
DOE’s Proposal
DOE proposed to require the
submission of a resource report on land
use, recreation, and aesthetics. DOE also
proposed to require in this resource
report a description of the existing uses
of land on, and within various
distances, the proposed project and
changes to those land uses and impacts
to inhabitants and users that would
occur if the project were approved. The
NOPR also required the report to
describe proposed mitigation measures,
including protection and enhancement
of existing land use.
DOE sought comment on whether
further revisions were needed to
proposed § 900.6(m)(8), which proposed
that the project proponent identify, by
milepost and length of crossing, the area
of direct effect of each proposed facility
and operational site on lands owned or
controlled by Federal or State agencies
with special designations not otherwise
mentioned in other resource reports, as
well as lands controlled by private
preservation groups (examples include
sugar maple stands, orchards and
nurseries, landfills, hazardous waste
sites, nature preserves, game
management areas, remnant prairie, oldgrowth forest, national or State forests,
parks, designated natural, recreational
or scenic areas, registered natural
landmarks, or areas managed by Federal
entities under existing land use plans as
Visual Resource Management Class I or
Class II areas), and identify if any of
those areas are located within 0.25 mile
of any proposed facility.
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
PO 00000
Frm 00039
Fmt 4701
Sfmt 4700
35349
Aesthetics Resource Report with minor
revisions in response to these
comments.
In response to the comments on
revisions to paragraph (8), which
includes a list of example specially
designated areas, DOE has made overall
changes to the structure and language of
the paragraph to improve the clarity and
readability of the requested information,
to reduce emphasis on the specific types
of land ownership or use, and to clarify
that the resource report provides details
regarding lands with explicit status
through Federal, state, or local formal
designation, as well as lands owned or
controlled by Federal, State or local
agencies or private preservation groups.
DOE has also added that the proposed
list is not exhaustive of the types of
lands that should be identified in this
section, but rather identifies examples
of the types of lands that may meet the
criteria now more clearly listed. DOE
disagrees with CEC/CPUC that this
resource report should only include
lands with a formal agricultural
conservation designations because the
intent of this provision and its list of
examples is to capture lands with
special status not typically
contemplated by Federal or State law
but agrees with LTA that ‘‘conservation
or agricultural lands subject to State
statutorily enabled conservation or
agricultural easements or restrictions’’ is
a helpful additional example and
includes this in this final rule.
In response to comments on the list of
Federal statutory designations in
paragraph (10), DOE makes minor
revisions to include forests and
grasslands. DOE agrees that specifically
listed areas should include Forest and
Grasslands and lands in easement
programs managed by the Natural
Resource Conservation Service or the
U.S. Forest Service and includes those
in this final rule. DOE does not include
areas identified by communities of
interest because the intent of this
resource report requirement is to
identify areas that fall under specific
Federal statutes and regulations to assist
DOE in implementing its environmental
review and coordination authority. In
response to LTA’s request that the
vegetation management provision
include a prioritization of the use of
native species, DOE makes no revisions
in this final rule because DOE believes
specific prescriptions for project
management practices should be
addressed on a project-specific basis.
In response to ACP’s comment on the
appropriate area for building
identification DOE revises the proposed
distance-based requirement but
maintains construction right-of-way
E:\FR\FM\01MYR2.SGM
01MYR2
35350
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
because the effects of construction on
buildings is information that DOE
believes is necessary to inform DOE’s
environmental review.
In response to AZGFD’s request that
this final rule consider impacts to State
wildlife agencies, DOE makes no
revisions because the agency believes
that the text is sufficiently clear on the
need for project proponents to provide
such information in the resource report.
Further, DOE believes that the
coordination with non-Federal entities
in the IIP Process sufficiently addresses
the concern of coordination with State
wildlife agencies and makes no further
revisions.
DOE is also making several changes to
the proposed rule text that are not in
response to a specific comment. DOE
significantly reorganizes portions of the
resource report requirements for clarity
but does not make any substantive
changes through the reorganization.
In keeping with the discussion in
section VI.K.ii of this document, DOE is
replacing multiple distances included in
the proposed rule with ‘‘in the
applicable analysis area’’ to give DOE,
the project proponent, and appropriate
Federal and non-Federal entities
flexibility to set these distances based
on the physical characteristics and
needs of the project. A project
proponent must now identify certain
planned development within ‘‘the
applicable analysis area’’ rather than
within ‘‘0.25 mile of proposed
facilities.’’ Likewise, the requirement for
a project proponent to identify directly
affected areas that are owned or
controlled by a governmental entity or
private preservation group within ‘‘0.25
miles of any proposed facility’’ has been
changed to within ‘‘applicable analysis
areas.’’ The final rule also requires the
project proponent to identify resources
within ‘‘the applicable analysis area’’
that are included in or designated for
study for inclusion in certain Federal
land and water management statutes.
The proposed rule asked for the project
proponent to identify the same types of
resources ‘‘crossed by or within 0.25
mile of the proposed transmission
project facilities.’’
ix. Communities of Interest Resource
Report
ddrumheller on DSK120RN23PROD with RULES2
DOE’s Proposal
DOE proposed to require the
submission of a resource report on
communities of interest. DOE proposed
to require in this resource report a
summary of known information about
the presence of communities of interest
that could be affected by the qualifying
project; identification and description of
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
the potential impacts of constructing,
operating, and maintaining the project
on communities of interest; a
description of any proposed measures
intended to avoid, minimize, or mitigate
such impacts or community concerns;
and a discussion of any
disproportionate and/or adverse human
health or environmental impacts to
communities of interest.
DOE agrees with EDF that ‘‘known’’ is
not consistent with the intent of the
information request and revises this
final rule to require ‘‘best available
information on’’ rather than EDF’s
proposed cure because this is consistent
with the standard of information
gathering for environmental reviews.
Summary of Public Comments
DOE’s Proposal
DOE received three comments on the
Communities of Interest Resource
Report that are not already addressed in
the discussion regarding the definition
of communities of interest in section
VI.K.iii of this document.
LTA expressed support for retaining
this resource report. ClearPath opposed
the addition of this resource report
because ‘‘by proposing separate
requirements for Communities of
Interest in Project Participation plans
and outreach plans, the DOE is
conceding that stakeholder engagement
requirements are deficient.’’ ClearPath
claims that the proposal represents
duplicative requirements and
paperwork for project proponents and
establishes a hierarchy of treatment and
consideration of project impacts across
population segments that could have
concerns regarding equal treatment and
discrimination.
Regarding the requirement that the
project proponent ‘‘[s]ummarize known
information about the presence of
communities of interest that could be
affected by the qualifying project,’’ EDF
noted that the phrase ‘‘known
information’’ may present a loophole,
and instead the project proponent
should be required to investigate,
observe, and understand the concerns of
communities of interest. EDF also
indicated that regulations should
specify that there is a responsibility to
avoid, minimize, or mitigate any health
or environmental impacts identified.
DOE proposed to require the
submission of a resource report on air
quality and noise effects. DOE proposed
to require in this resource report the
identification of the effects of the project
on the existing air quality and noise
environment and describe proposed
measures to mitigate the effects.
DOE Response
DOE retains the Communities of
Interest resource report with minor
revisions in response to these
comments. DOE does not agree that this
resource report is duplicative with the
public engagement plan and clarifies
that this resource report is aimed at
identifying negative impacts to
communities of interest and mitigation
measures while the public participation
plan is aimed at ensuring sufficient
engagement. ClearPath’s concerns about
the disparate treatment in the public
engagement plan are discussed in
further detail in section VI.E of this
document.
PO 00000
Frm 00040
Fmt 4701
Sfmt 4700
x. Air Quality and Noise Effects
Resource Report
Summary of Public Comments
DOE received three comments in
response to the Air Quality and Noise
Effects resource report proposal.
Policy Integrity stated that the NOPR
is unclear regarding local air pollutants
and non-power-sector emissions and
advised DOE to require project
proponents to comprehensively estimate
the associated changes to GHG
emissions and local air pollution from
their transmission project and
alternatives, such as indirect upstream
GHG emissions from methane leakage.
Additionally, the commenter suggested
that the need to estimate and describe
impacts from changes to criteria
pollutants should not depend on
whether they remain below the Clean
Air Act’s National Ambient Air Quality
Standards (NAAQS), stating that the
EPA has recognized that there is no safe
level of exposure. In contrast, ClearPath
strongly opposed Air Quality and Noise
Effects resource report’s proposed
requirement that project proponents
estimate direct, indirect, and
‘‘reasonably foreseeable’’ generation
resource-related project emissions.
ClearPath described the proposed
requirements as vague and as lacking a
robust process for proponents to follow,
such that proponents are unlikely to
understand and comply.
AZGFD recommended that DOE
require the identification of air and
noise related potential impacts on all
wildlife resources, in addition to the
Federally-listed species or sensitive
wildlife habitats currently identified.
DOE Response and Summary of Other
Changes
DOE retains the Air Quality and Noise
Effects resource report in full in this
final rule with no changes in response
to these comments.
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
Regarding local air pollutants and
emissions, DOE makes no changes in
response to the comment. DOE believes
the rule makes clear that it requires
information regarding non-GHG
emissions and non-power-sector
emissions. In this resource report,
project proponents must identify
reasonably foreseeable emissions caused
by the project, regardless of whether
those emissions occur in NAAQS nonattainment areas. DOE believes that
requirement provides adequate
guidance to project proponents.
Regarding the impacts on wildlife
resources, DOE believes the impacts to
wildlife are sufficiently addressed in the
Fish, Wildlife, and Vegetation resources
report and makes no revisions to this
report.
DOE is making several changes to the
proposed rule text that are not in
response to a specific comment. DOE
significantly reorganizes portions of the
resource report requirements for clarity
but does not make any substantive
changes through the reorganization.
In keeping with the discussion in
section VI.K.ii of this document, DOE is
replacing multiple areas of study
included in the proposed rule with ‘‘in
the applicable analysis area’’ to give
DOE, the project proponent, and
appropriate Federal and non-Federal
entities flexibility to set these distances
based on the physical characteristics
and needs of the project. A project
proponent is now required to describe
existing air quality in ‘‘the applicable
analysis area’’ rather than in the
‘‘project area.’’ Likewise, a project
proponent is required to identify air
quality impacts on communities and the
environment in the ‘‘applicable analysis
area,’’ rather than the ‘‘project area.’’
Finally, the proposed rule clarifies that
a project proponent is required to
describe existing noise levels at noisesensitive areas in the ‘‘applicable
analysis area,’’ instead of leaving the
study area undefined.
xi. Alternatives Resource Report
ddrumheller on DSK120RN23PROD with RULES2
DOE’s Proposal
DOE proposed to require the
submission of a resource report on
alternatives. DOE proposed to require
this resource report to include a
description of alternatives identified by
the project proponent during its initial
analysis, which may inform the relevant
Federal entities’ subsequent analysis of
alternatives, address alternative routes
and alternative design methods, and
compare the potential environmental
impacts and potential impacts to
cultural and historic resources of such
alternatives to those of the proposed
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
project. DOE also proposed that the
project proponent include all of the
alternatives identified by the project
proponent, including those the
proponent chose not to examine or not
examine in greater detail, and an
explanation for the project proponent’s
choices regarding the identification and
examination of alternatives. The NOPR
proposed to require that project
proponents demonstrate whether and
how environmental benefits and costs
were weighed against economic benefits
and costs to the public, and
technological and procedural
constraints in developing the
alternatives, as well as explain the costs
to construct, operate, and maintain each
alternative, the potential for each
alternative to meet project deadlines,
and the potential environmental
impacts of each alternative.
Summary of Public Comments
DOE received three comments
addressing the Alternatives Resource
Report that are not already addressed in
other sections.
Niskanen Center noted that the
alternatives report would benefit from
clarifying language and revisions to
avoid ambiguity regarding the definition
of alternatives and the extent to which
they should be included in the resource
report and provided recommendations.
Niskanen Center also requested
clarifying language if the Alternatives
resource report is the only report that is
required to include an alternatives
analysis, and that if not, DOE should
clearly state its request for such analysis
in each report.
ACP expressed concerns regarding the
NOPR not reflecting the intersections
between state, Tribal, and Federal siting
authorities, specifically noting the
overlapping timetables that can be
difficult to predict. ACP provided as an
example that if State siting precedes
Federal siting, only a single route might
be approved which would materially
limit the required NEPA alternative and
potentially increase overall legal risk if
opponents claim that the failure to
adequately consider proposed
alternatives violates NEPA or the
Administrative Procedure Act. ACP
recommended that DOE explicitly
address these limited alternatives that
may be established through a State
siting process, as well as ensure that
Federal reviews account for the
potential scope of State siting
determinations and not require
consideration of alternatives that are
impossible or implausible.
The CARE Coalition urged DOE to
specifically require the consideration of
alternative transmission technologies
PO 00000
Frm 00041
Fmt 4701
Sfmt 4700
35351
(ATTs), such as dynamic line ratings,
power flow controllers, advanced
conductors, and battery storage, in the
report. The commenter explained that
failure to consider ATTs excludes a
potentially low-cost alternative that may
prevent or reduce environmental harm.
DOE Response
DOE maintains the Alternatives
resource report but makes substantial
revisions in response to these comments
to reduce ambiguity on the scope and
purpose.
In response to Niskanen Center’s
comment, DOE confirms that this
resource report is the only resource
report that requires an alternatives
analysis. Other resource reports are
intended to address the potential study
corridors or routes along which the
project proponent is considering siting
the electric transmission facility. Those
resource reports do not need to address
alternative study corridors or alternative
routes that the project proponent has
eliminated from consideration.
The Alternatives resource report is
intended to provide an overview of the
study corridors and routes that were
initially considered for the proposed
project, but that ultimately were not
chosen for further study by the project
proponent. In keeping with this intent,
in this final rule, DOE is requiring a
project proponent to identify all study
corridors that were considered as part of
the proposed project, as well as all
routes contained within those study
corridors. Within that broad group of
study corridors and routes, DOE
requires the project proponent to
identify those alternative study
corridors and routes that the project
proponent eliminated from further
study under an initial screening, and the
reasons why those corridors and routes
were eliminated.
For the remaining alternative study
corridors and routes, DOE requires
analyses of certain impacts of siting the
electric facility in the corridor or along
the route. Likewise, DOE requires a
discussion of the costs, timelines, and
technological and procedural
constraints of siting the electric facility
in the corridor or along the route.
Finally, DOE requires the project
proponent to demonstrate whether and
how environmental benefits and costs
were weighed against economic benefits
and costs to the public for the route or
corridor.
In response to ACP’s concern about
overlapping timetables and limitations
to alternatives, DOE makes no
additional revisions because, as clarified
above, the Alternatives resource report
addresses the project proponent’s
E:\FR\FM\01MYR2.SGM
01MYR2
35352
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
approach to Alternatives which may
inform, but does not supplant, DOE’s
consideration of appropriate alternatives
for its environmental review.
In response to CARE Coalition’s
request that DOE include ATTs, DOE
declines to specify the consideration of
specific evolving technologies in its
regulatory test.
xii. Reliability, Resilience, and Safety
Resource Report
DOE’s Proposal
DOE proposed to require the
submission of a resource report on
potential hazards to the public from
failures of the proposed electric
transmission facility due to accidents,
intentional destructive acts, and natural
catastrophes. DOE also proposed
requiring the report to describe how
these events would affect reliability,
benefits to reliability from the project,
and what procedures and design
features could be used to reduce risks to
the facility and the public.
Summary of Changes
DOE did not receive any comments on
the Reliability, Resilience, and Safety
resource report that have not been
addressed in another section of this
final rule. However, in this final rule
DOE significantly reorganizes portions
of the proposed resource report
requirements for clarity but does not
make any substantive changes through
the reorganization.
ddrumheller on DSK120RN23PROD with RULES2
xiii. Tribal Interests Resource Report
DOE’s Proposal
DOE proposed to require the
submission of a resource report on
Tribal interests. DOE proposed to
require in this resource report the
identification of the Indian Tribes,
indigenous communities, and their
respective interests that may be affected
by the proposed transmission facilities,
including those Indian Tribes and
indigenous communities that may
attach religious and cultural
significance to historic properties
within the right-of-way or in the project
area as well as any underlying Federal
land management agencies. DOE also
proposed to require in this resource
report a discussion of potential impacts
on Indian Tribes and Tribal interests
and of traditional cultural and religious
resources that could be affected by the
proposed project, to the extent Indian
Tribes are willing to share this
information. Additionally, DOE
proposed that certain specific site or
location information that may create a
risk of harm, theft, or destruction, or
otherwise violate Federal law should be
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
submitted separately, and that the
project proponent must request
confidential treatment for all material
filed with DOE containing location,
character, and ownership information
about Tribal resources.
Summary of Public Comments
DOE received four comments
regarding the Tribal Interests Resource
Report that are not already addressed in
previous discussions. Most comments
are addressed in section VI.J of this
document in response to the approach
to compliance with section 106 of the
NHPA.
LTA expressed support for this
resource report and urged DOE to
collaborate with Indian Tribes to ensure
that the language used in the report
adequately protects their interests. The
Santa Rosa Rancheria Tachi Yokut Tribe
and NATHPO expressed concern with a
comment by DOE staff, which the
commenters believe indicated, contrary
to the proposed rule text, that the Tribal
Interests resource report would not
contain cultural resources, examples of
Tribal resources provided in the
proposed rule (e.g., water rights, access
to property, wildlife and ecological
resources) are Tribal cultural resources.
The commenters stated that this
comment reflects a fundamental lack of
understanding about what is a Tribal
cultural resource. Relatedly, the NM
SHPO noted that resources identified in
other resource reports, such as the
Water Use and Quality resource report
and the Fish, Wildlife, and Vegetation
resource report, may also be of
traditional and cultural significance and
eligible for the NRHP.
DOE Response
In this final rule DOE retains the
Tribal Interests resource report with
minor revisions for clarity in response
to comments. First, DOE did not intend
to indicate that the Tribal Interests
resource report would not contain
cultural resources. Second, DOE sought
comment from Indian Tribes and will
coordinate with Indian Tribes in
accordance with the Federal
Government’s nation-to-nation
responsibilities, pursuant to DOE’s
authority under FPA 216(h).
In response to the concern raised by
Santa Rosa Rancheria Tachi Yokut Tribe
and NATHPO that the resource report
requirements reflect a misunderstanding
about tribal cultural resources, DOE
revises the report for clarity. DOE
acknowledges that the Tribal Interests
and Cultural Resources resource reports
may contain some resources that
overlap in part but clarifies that they are
intended to support different purposes
PO 00000
Frm 00042
Fmt 4701
Sfmt 4700
and request different details. DOE
expects that certain cultural resources
may be described in both resource
reports and revises the Cultural
Resources resource report to clarify that
cultural and historic resources include,
among other things, properties of
religious and cultural significance to
Indian Tribes.
M. Administrative Docket
DOE’s Proposal
To better coordinate Federal
authorizations, DOE proposed to
maintain a consolidated administrative
docket containing meeting requests,
meeting summaries, resource reports,
other information assembled during the
IIP Process, and all information
assembled by relevant Federal entities
for authorizations and reviews after
completion of the IIP Process.
Summary of Public Comments
Commenters, such as EEI, PJM, and
the CARE Coalition, expressed support
for a consolidated administrative
docket. PJM believes that a consolidated
administrative docket will ensure all
Federal entities are working from a
single, complete record for reviews and
decisions. One commenter, Niskanen
Center, proposed that the administrative
docket be public, while the CARE
Coalition proposed the rule provide
more details to clarify access to the
administrative docket to ensure
stakeholder participation. Another
commenter, StopPATH WV, proposed
DOE make the administrative docket
information available to landowners
that may be impacted by the proposed
project.
DOE Response
DOE maintains the features and
purpose of the administrative docket in
this final rule with minor revisions.
DOE agrees that the public should have
access to the administrative docket for
the proposed project and revises this
final rule to provide that ‘‘Upon request,
any member of the public may be
provided materials included in the
docket, excluding any materials
protected as CEII or as confidential
under other processes (e.g., confidential
business information and information
developed during consultation with
Tribes).’’
N. Interaction With FPA 216(a) and FPA
216(b)
Summary of Public Comments
Seven commenters provided
comments on the interaction of the
proposed rule with DOE’s process for
designating NIETCs, per FPA section
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
216(a), and FERC’s pending regulations
regarding its siting authority in NIETCs,
per FPA section 216(b), referred to by
some commenters as ‘‘backstop siting.’’
PIOs praised DOE’s proposed rule for
its alignment with FERC’s proposed
backstop permitting rule. PIOs
anticipated that this coordination would
support a consistent, predictable, and
rigorous Federal review and permitting
process and offer certainty to project
proponents, as they seek necessary
authorizations. Additionally, PIOs
anticipated that alignment would ensure
project proponents could easily engage
in both processes if necessary, citing
potential scenarios in which a project
seeking a FERC permit needs multiple
Federal authorizations and could benefit
from the IIP Process or a project
undergoing the IIP Process decides it
needs a FERC permit. PIOs argued that
in these cases, alignment across
processes would allow project
proponents to effectively engage in both
processes, while reducing duplication.
PIOs identified several similarities
between proposed requirements under
DOE’s CITAP Program and FERC’s
proposed rule. PIOs stated that DOE’s
proposed IIP Process plays a similar role
to FERC’s pre-filing process.
Additionally, PIOs noted that DOE’s
resource reports are similar to those
required under FERC’s rule and
recommended that DOE align the
numbering of resource reports with the
numbering in FERC’s proposed rule.
Several commenters supported
alignment of the CITAP Program’s
requirements with FPA sections 216(a)
and 216(b) regulations. ACEG, CEBA
and the CARE Coalition urged DOE to
align the CITAP Program with NIETC
designation and FERC’s backstop siting
authority. CEBA suggested this would
avoid duplication and ensure processes
are clear and remain streamlined across
relevant Federal agencies. ACEG stated
it would ensure effective and efficient
implementation; the CARE Coalition
argued that this coordination would
provide certainty and transparency for
stakeholders, predictability for project
proponents, and a reduction in
associated project permitting costs.
LADWP recommended that DOE align
the information required by the resource
reports during the IIP Process with the
information required by the resource
reports under FERC’s proposed backstop
permitting rule. LADWP suggested that
alignment of this information would
result in a more efficient permitting
process. Similarly, ACORE
recommended that DOE provide a
mechanism for any information
submitted under the NIETC program to
be incorporated into the IIP Process.
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
ACP commented that since proposed
electric transmission projects seeking
Federal ‘‘backstop’’ siting authority
under section 216(b) of the FPA would
not be eligible for the CITAP Program,
DOE should ensure, in conjunction with
FERC, that any subsequent NEPA
rulemakings will allow for each agency
to use an EIS prepared by the other
agency as this would help to minimize
the potential for duplicative reviews.
Similarly, EDF recommended that in the
event a transmission facility requires a
construction or modification permit
from FERC pursuant to section 216(b) of
the FPA, DOE should conduct a single
coordinated environmental review with
FERC. EDF explained that the benefits
of such a coordinated review have
already been recognized by DOE in its
‘‘Building a Better Grid Initiative to
Upgrade and Expand the Nation’s
Electric Transmission Grid To Support
Resilience, Reliability, and
Decarbonization’’ NOI, wherein DOE
states that ‘‘DOE and FERC intend to
work together, as appropriate, to
establish coordinated procedures that
facilitate efficient information gathering
related to the scope of activities under
review pursuant to these authorities.’’
EDF believes that by coordinating, to the
greatest extent practicable, pre-filing
and application processes, DOE and
FERC can work with project proponents
to identify and resolve issues as quickly
as possible, share information in a
timely fashion, and expedite reviews
conducted pursuant to these authorities,
NEPA, and other requirements. ACEG
added that to avoid fragmentation in the
review process, and to comply with
section 216(h) of the FPA, DOE must
prepare a single document for the
project’s NEPA review, which will serve
as the basis for decision-making under
both NIETC and CITAP.
Two comments requested more
information. ACEG and CEBA requested
clarification on how a project proponent
can initiate the CITAP Program while
seeking project-specific NIETC
designation and how a CITAP Program
project can apply for backstop siting.
ACEG explained that a project in a
NIETC could need to transition to
backstop siting years into the CITAP
Program review process, and CEC/CPUC
similarly requested clarification on what
will happen to a CITAP Program
application once a project becomes
eligible for backstop siting. CEBA
offered its interpretation of the NOPR,
understanding that projects could
participate in the section 216(h) process
if the project has not triggered or
received section 216(b) FERC backstop
authority. ACEG explained that project
PO 00000
Frm 00043
Fmt 4701
Sfmt 4700
35353
proponents are likely to seek NIETC
designation to unlock funding
opportunities available to projects in
designated corridors. ACEG encouraged
DOE to streamline the processes by
allowing project proponents to submit a
single application to initiate both
processes.
Conrad Ko suggested the routes of any
applicant for a transmission line
construction permit to be automatically
designated as a NIETC and for the entire
United States should be designated a
NIETC.
DOE Response
DOE makes no revisions to the rule in
response to these comments, except to
renumber the resource reports to align
with the numbering in FERC’s proposed
rule. DOE intends to coordinate
interagency efforts to the greatest extent
possible, pursuant to its authority under
FPA section 216(h). The responsibility
for coordinating Federal authorization
under section 216(h) for projects seeking
a permit under FPA section 216(b) has
been delegated to FERC, pursuant to
Delegation Order No. S1–DEL–FERC–
2006. DOE’s current approach to the
environmental analysis for designation
of NIETCs under section 216(a) may be
found in the Guidance on Implementing
Section 216(a) of the Federal Power Act
to Designate National Interest Electric
Transmission Corridors issued in
December 2023.13
DOE does not find that any provisions
in this rule would preclude the use of
an EIS prepared by another agency,
including FERC, should such a
circumstance arise. DOE agrees with
commenters that projects within a
NIETC may qualify for the CITAP
Program; however, if a project within a
NIETC seeks a permit from FERC under
FPA section 216(b), FPA section 216(h)
coordination will proceed consistent
with Delegation Order No. S1–DEL–
FERC–2006. DOE has endeavored to
align the environmental review
procedures for NIETC designation and
the CITAP Program to the greatest extent
possible, and additionally align with
FERC’s proposed procedures for
implementing section 216(b), as
observed by PIOs, to minimize the
chance that such transitions create
duplicative work or unnecessary delay.
Deviations among the regulations,
13 ‘‘U.S. Department of Energy Grid Deployment
Office Guidance on Implementing Section 216(a) of
the Federal Power Act to Designate National
Interest Electric Transmission Corridors.’’ National
Interest Electric Transmission Corridor Designation
Process, United States Department of Energy, 19
Dec. 2023, www.energy.gov/sites/default/files/202312/2023-12-15GDONIETCFinalGuidance
Document.pdf.
E:\FR\FM\01MYR2.SGM
01MYR2
35354
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
particularly the specific contents of the
thirteen resource reports, reflect the
differences in authorizations and
permits DOE expects to coordinate and
provide for in its single environmental
review under FPA section 216(h).
This final rule maintains the
provision that the Director of the Grid
Deployment Office may waive
requirements of the CITAP Program,
which provides flexibility for
transitioning between processes without
requiring duplicative work. Nothing in
this final rule precludes the reuse or
concurrent submission of resource
reports or other project materials for a
proposed project in a NIETC, whether
under consideration for designation or
already designated, seeking CITAP
Program participation. DOE declines to
further specify the coordination
between NIETCs and the CITAP
Program because it is outside the scope
of the rulemaking. DOE has sufficiently
established the requirements and
restrictions on qualifying project
designation and further details on
interactions with other DOE programs
are implementation issues that will be
determined as needed. DOE may
provide additional guidance outside of
this rule regarding the interactions of
various DOE and FERC authorities in
section 216 of the FPA.
O. Miscellaneous
ddrumheller on DSK120RN23PROD with RULES2
i. Presidential Appeal
Summary of Public Comments
DOE received comments regarding the
presidential appeals process and review.
PIOs commented that the language in
the proposed rule was consistent with
the FPA but requested clarification on
the process to inform project proponents
and members of the public. PIOs
requested that DOE clarify how the
appeal to the President might work, and
whether and how a project proponent
might appeal the President’s decision.
AEU explained that the FPA section
216(h) allows for an appeal to the
President of the United States which
appears to be an extreme step in a
process that should be handled through
a judicial or administrative hearing. The
association emphasized that
transmission developers should have
the ability to appeal if the approval
process is not proceeding according to
the schedule set by DOE through no
fault of their own and the proposed rule
should either describe how an appeal to
the President would proceed or lay out
a specific appeal process for a project
developer. AEU also expressed concerns
regarding recourse if the timeframe from
NOI through issuance of the EIS is not
met. AEP similarly recommended
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
enabling project proponents to petition
the court if Federal agencies fail to
comply with applicable deadlines.
DOE Response
Section 216(h) of the FPA authorizes
the President to hear and consider
appeals under that section. The 2023
MOU describes the procedures for
Presidential appeals. The Presidential
appeals provision of section 216 of the
FPA and the procedures described in
the MOU, including any process by
which such a decision may be appealed,
are outside the scope of DOE’s authority
and thus outside the scope of this
rulemaking.
In response to AEP’s request that DOE
enable project proponents to petition a
court if Federal agencies fail to comply
with applicable deadlines, DOE notes
that it does not, through this rule, have
the authority to authorize, or prohibit,
project proponents from filing court
petitions regarding of Federal agency
adherence to applicable deadlines.
ii. Rehearing and Judicial Review
Summary of Public Comments
PIOs urged DOE to explain the
implications of section 313 of the FPA,
including (1) the FPA’s judicial review
provision, in which challenges are first
brought to the agency, and then litigated
in a court of appeals under shorter
timelines than most Federal agency
decisions, which are subject to review
in district courts within six years, and
(2) the exhaustion requirements of the
FPA, under which courts only recognize
claims raised in a rehearing application.
PIOs also asked DOE to explain whether
the FPA’s judicial review provisions
require a potential challenger to
intervene before DOE, to raise any
substantive concerns during the DOE
process even if DOE lacks substantive
expertise with the challenger’s
concerns, to seek rehearing within thirty
days, and to seek judicial review in a
court of appeals within sixty days of a
rehearing decision. PIOs also
recommended that DOE (1) encourage
parties, in both pre- and postapplication outreach, to provide
comment on transmission applications,
(2) provide language for doing so, and
(3) grant party status to any party that
submits a timely comment.
DOE Response
Section 313 of the FPA contains
rehearing and judicial review provisions
applicable to orders issued by DOE
under the FPA, including any order
issued under section 216(h). 16 U.S.C.
PO 00000
Frm 00044
Fmt 4701
Sfmt 4700
825l.14 Section 313(a) provides that any
person aggrieved by an order must first
apply for rehearing within 30 days of
the issuance of such order. Upon
receiving the application, section 313
authorizes DOE to grant or deny
rehearing or to abrogate or modify its
order without a further hearing. DOE
has 30 days to act upon the application
for rehearing or the application is
deemed to have been denied. Under
section 313(b), a party may then proceed
to seek judicial review in the courts of
appeals, by filing a petition for review
in such a court within 60 days of the
order on the application for rehearing.
Thus, any party that wishes to ensure
the availability of judicial review of any
relevant authorization or related
environmental review document issued
under section 216(h) should raise in
rehearing before DOE all challenges to
such authorization or document,
including those actions undertaken by
DOE in its role as the lead agency for
purposes of environmental review.
Subject to any further process, DOE
intends to treat as a party any person or
entity that comments on any relevant
authorization or related environmental
review document. Because these topics
relate to procedures outside the scope of
this rule and may depend on specific
factual circumstances, DOE declines at
this time to establish model language
regarding rehearing and review.
Nevertheless, DOE supports interested
parties making comments on
transmission applications in the CITAP
Program, including pursuant to NEPA
and other review processes that afford
opportunities for comment and
participation. Because of the various
avenues for comment and participation
and because the CITAP Program does
not limit the public comments that can
be made through the existing avenues
for public input, DOE finds it is
unnecessary to provide standardized
language for providing comments as
suggested by commenters.
iii. Role of States
Summary of Public Comments
DOE received two comments related
to the roles of states in siting
14 Section 313 refers to ‘‘an order issued by the
[Federal Power] Commission.’’ 16 U.S.C. 825l(a)–
(b). In 1977, Congress dissolved the Federal Power
Commission and transferred its authorities to DOE
and FERC. See Department of Energy Organization
Act, Public Law 95–91, 91 Stat. 565 (Aug. 4, 1977).
The rehearing and judicial review provisions of
section 313 apply to DOE as a successor to the
Federal Power Commission. See Ctr. for Biological
Diversity v. Dep’t of Energy, No. CV 08–
168AHM(MANX), 2008 WL 4602721, at *5–6 (C.D.
Cal. Oct. 16, 2008); Pa. Pub. Util. Comm’n v.
Bodman, No. CIV. 1:CV–07–2002, 2008 WL
3925840, at *3–5 (M.D. Pa. Aug. 21, 2008).
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
transmission lines. AEP emphasized the
importance of respecting the roles and
responsibilities of states and localities
in transmission project approval. CEC/
CPUC encouraged the coordination of
Federal and State permitting processes,
explaining that most major transmission
facilities in California will require both
Federal and State environmental review
and approval. To align these processes
and inform coordination, CEC/CPUC
recommended that DOE support projectspecific MOUs between State and
Federal permitting authorities.
DOE Response
DOE agrees with the commenters on
the importance of states in the siting of
transmission lines. Accordingly, and
consistent with section 216(h), the IIP
Process is designed to encourage and
facilitate states’ participation. Moreover,
nothing in the IIP Process supersedes
any State siting or permitting authority.
DOE may develop project-specific
MOUs as appropriate and necessary;
such individual decisions are outside
the scope of this rulemaking.
iv. Effective Date
Summary of Public Comments
Idaho Power requested clarification
on when the CITAP Program outlined in
the proposed rule would go into effect.
DOE Response
DOE intends for the CITAP Program
to take effect on the day this final rule
takes effect: 30 days after publication of
the rule in the Federal Register.
v. Costs and Benefits of Conservation
Summary of Public Comment
AZGFD requested additional
information about DOE’s assessment of
potential costs and benefits of the
CITAP program. AZGFD stated that it
was unclear whether DOE has assessed
and evaluated the costs associated with
implementation of conservation
measures for offsetting potential impacts
to resources. If DOE did not include this
analysis, AZGFD recommends that DOE
account for the cost of conservation
measures.
ddrumheller on DSK120RN23PROD with RULES2
DOE Response
DOE makes no changes in this final
rule in response to this comment. DOE
believes that the CITAP Program, as
finalized in this rulemaking, is designed
to enhance coordination of decisionmaking efforts for the purposes of
improved speed and efficiency of
Federal permitting and authorizations
overall, but will not materially impact
the outcomes of specific decisions,
which would include any conservation
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
measures required to be undertaken.
DOE’s assessment of the final rule’s
anticipated costs and benefits is
presented in section VIII of this
document.
vi. Burden Estimates Under the
Paperwork Reduction Act of 1995
Summary of Public Comment
Gallatin Power expressed concern that
the cost burden estimated in the NOPR
seemed ‘‘significantly lower than
current market rates.’’ Gallatin Power
acknowledged that the median hourly
rate was used to calculate the cost
burden, but explained that, in its
experience, ‘‘these hourly wages are
significantly more when contracting
with a subject matter expert, at an
industry-accepted firm.’’ Gallatin Power
also expressed concern that the cost and
time estimates did not identify a size for
the transmission project given that
‘‘these costs and time estimates would
vary greatly among project lengths and
locations.’’
DOE Response
DOE makes no changes in this final
rule in response to this comment.
Although Gallatin Power expressed
concern about the burden analysis, it
did not challenge DOE’s approach as
unreasonable nor did it provide an
alternative approach for DOE to
consider. As Gallatin Power
acknowledges, costs and time estimates
can vary widely among projects. Given
that estimates can vary widely by
project, DOE believes it was reasonable
to use the most recently available
median hourly wage for management
analysts according to the Bureau of
Labor Statistics, for the proposed
rulemaking and in this final rule,
consistent with DOE’s previous burden
analysis for this collection. Though this
revised collection changes the volution
and subject matter of the information
collection, including requesting analysis
from a range of experts, many of the
median wages reported by BLS for
environmental and scientific
consultants are below the management
analysis median wage proposed by DOE,
further supporting DOE’s use of this
occupation as a basis for estimation.
Regarding the size of transmission
project, DOE estimated an average
burden for a qualifying project under
CITAP, which represents a wide range
of length and size, based on the special
expertise in environmental evaluation of
transmission projects within DOE.
DOE’s assessment of the final rule’s
estimated burden is in section VIII of
this document.
PO 00000
Frm 00045
Fmt 4701
Sfmt 4700
35355
P. Out of Scope Comments
Summary of Public Comments
DOE received six additional
comments not addressed above. NAM
noted it supports a diverse approach to
powering communities and operations,
and urged DOE to follow its findings in
the draft National Transmission Needs
Study released in February 2023.
The State of Colorado Governor’s
Office stated that the proposed rule does
not consider the need to minimize the
potential of the challenges from private
citizens and groups alleging deficiencies
in project review under NEPA and other
statutes nor DOE’s ability to facilitate
interstate transmission development in
the face of opposition from certain states
or organizations.
EEI suggested DOE consider how its
implementation of section 216(h) can
support electric companies working to
meet State timelines for reducing
emissions in the electric grid through its
implementation of section 216(h) and
for DOE and other agencies to consider
IRA funds to increase the training of
personnel or to provide grants to other
agencies.
Kris Pastoriza requested clarification
on a statement on FERC’s website, a
definition for or list of ‘‘interstate
transmission lines.’’
Gallatin Power asked DOE to clarify
whether designated DOE staff would be
assigned to qualifying projects who
could help move the permitting process
along and would facilitate knowledge
retention.
EDF recommended DOE consider colocation of transmission projects within
abandoned rights-of-way. In addition,
EDF recommended DOE develop a
record of right-of-way locations and to
consider publishing this information on
an interactive map for ease of use by the
public. EDF believes the CITAP Program
presents the perfect opportunity to
develop this information. EDF believes
this proposal would be consistent with
the objective to ensure NEPA reviews
are not duplicative because the
information about rights-of-way would
be more readily available for
transmission projects.
DOE Response
DOE finds these comments to be out
of scope of the rulemaking, which
addresses the implementation of DOE’s
authority to coordinate Federal
environmental review and decisionmaking on transmission project
authorizations and permits. The
findings of the Needs Study are outside
the scope of this rulemaking, as are the
potential of challenges alleging
deficiencies in NEPA review, as well as
E:\FR\FM\01MYR2.SGM
01MYR2
35356
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
any interpretations of FERC’s authority.
Regarding EEI’s request that DOE
consider State emissions reductions
statutes in its implementation of section
216(h), DOE’s authority is limited to
coordination of environmental reviews
and decision-making; project
proponents remain responsible for
meeting or complying with any State
emissions reductions statutes.
Additionally, regarding Gallatin Power’s
request that DOE clarify which DOE
staff will be assigned to qualifying
projects, whether there will be certain
designated staff assigned to these
projects will depend on the particular
project and is best addressed on a
project-by-project basis. Regarding
EDF’s recommendation for DOE to
consider co-location within abandoned
rights-of-way, project proponents
remain responsible for proposed routes,
and they may consider co-location as
appropriate. Regarding EDF’s
recommendation for DOE to use the
CITAP Program as an opportunity to
develop a database of rights-of-way,
DOE finds it unnecessary to adopt any
regulatory text to address this
recommendation but may, through
implementation of the program, develop
various tools to inform the public.
VII. Section-by-Section Analysis
ddrumheller on DSK120RN23PROD with RULES2
§ 900.1
Purpose and Scope
Section 900.1 provides a process for
the timely and coordinated submission
of information necessary for decisionmaking for Federal authorizations for
siting of proposed electric transmission
facilities pursuant to section 216(h) of
FPA. This final rule revises § 900.1 to
update the purpose of part 900,
reference the establishment of the
CITAP Program, and improve
readability. These changes reflect DOE’s
understanding that Congress intended
DOE to make the process to obtain
multiple Federal authorizations more
efficient and reduce administrative
delays, which requires clear authority,
process, and timelines. The changes in
this section reflect DOE’s intent to carry
out the full scope of the authority that
Congress provided. Paragraph (a) is
added to establish the overarching
CITAP Program and provide a roadmap
to authorities and processes throughout
part 900. This paragraph states that DOE
will act as a lead agency for preparing
an environmental review document for
any qualifying project. Paragraph (a), as
well as revised paragraph (d), identify
DOE’s role in establishing and
monitoring adherence to intermediate
milestones and final deadlines, as
required by section 216(h).
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
This final rule revises the current
regulatory text of § 900.1 by dividing it
into paragraphs (b) through (d). Portions
of the text dealing with the IIP Process
have been updated to clarify that the
process will require submission of
materials necessary for Federal
authorizations and that the IIP Process
should be initiated prior to the
submission of any application for a
Federal authorization. The changes also
clarify that the IIP Process is integrated
into the CITAP Program.
In this final rule, DOE is adding
paragraph (e) to clarify the intended
relationship between the early
coordination envisioned by the IIP
Process and the duties prescribed by
section 106 of the NHPA and the
implementing regulations at 36 CFR part
800. In particular, this section clarifies
that nothing in the IIP Process is
intended to abrogate the obligations of
Federal agencies under 36 CFR part 800.
Additionally, this section authorizes a
project proponent as an applicant to the
CITAP Program to initiate section 106
consultation during that proponent’s
involvement in the IIP Process.
DOE redesignates paragraphs (a) and
(e) of current § 900.2 as new paragraphs
(f) and (g) of this section because the
paragraphs contain general propositions
regarding part 900 and are better suited
to the general ‘‘Purpose and Scope’’
section. This final rule adds a new
paragraph (f) to establish that DOE and
the relevant Federal entities shall issue
a joint decision document except where
inappropriate or inefficient. This
revision is to be consistent with NEPA
regulations, including the Fiscal
Responsibility Act of 2023, which
codified processes to streamline the
environmental review process and
facilitate one Federal decision, be
consistent with the Congressional intent
of FPA 216(h), and enhance DOE’s
coordinating function. This final rule
revises new paragraph (g) to clarify that
DOE will serve as lead agency for
consultation under section 7 of the ESA
and section 106 of the NHPA unless the
relevant Federal entities designate
otherwise. This revision aligns the lead
agency designation with the authorizing
statutes.
This final rule also adds paragraph (h)
to afford the Director of DOE’s Grid
Deployment Office, or that person’s
delegate, flexibility necessary to ensure
that part 900 does not result in
unnecessary, duplicative, or
impracticable requirements. DOE added
this paragraph to authorize the Director
to waive any such requirements.
Further, this paragraph specifically
contemplates a scenario in which a
Federal entity is the principal project
PO 00000
Frm 00046
Fmt 4701
Sfmt 4700
developer. Under such circumstances,
DOE has added language to indicate that
the Director will consider modifications
to the requirements under this part as
may be necessary under the
circumstances.
§ 900.2 Definitions
DOE redesignated § 900.3 as § 900.2
for the purpose of providing the
definitions of terms before those terms
occur in the body of the regulation.
Section 900.2 provides definitions for
various terms used throughout part 900.
This final rule amends or adds the
following definitions:
• Revises the term ‘‘affected
landowner’’ to ‘‘potentially affected
landowner’’ and revises the substance of
that definition to include any owner of
a real property interest whose interest is
potentially affected by a project right-ofway, potential route, or proposed
ancillary or access site. Adds a
definition of ‘‘analysis area’’ to serve as
a reference in locating the points in the
IIP Process that analysis areas are
established and modified.
• Adds a definition for
‘‘authorization’’ to provide clarity in
several places where that term occurs.
Amends the definition for ‘‘Federal
authorization’’ to account for the new
definition of ‘‘authorization.’’
• Adds a definition for ‘‘communities
of interest’’ to ensure broad coverage of
potentially impacted populations during
the public engagement process and
establishment of the public engagement
plan. Adds a definition for
‘‘participating agencies’’ to serve as
shorthand for the group of agencies that
will serve various roles under the
amendments to the coordination of
Federal authorizations.
• Adds a definition of ‘‘NEPA joint
lead agency’’ to identify where
information about the designation of a
NEPA joint lead agency occurs in the
rule.
• Removes the term ‘‘OE–1,’’ meaning
the Assistant Secretary for DOE’s Office
of Electricity Delivery and Energy
Reliability, and replaces it with the
definition for ‘‘Director,’’ meaning the
Director of DOE’s Grid Deployment
Office or that person’s delegate. Under
section 1.14(D) of Delegation Order No.
S1–DEL–S3–2023 and section 1.9(D) of
Redelegation Order No. S3–DEL–GD1–
2023 the Secretary of Energy delegated
authority to exercise authority under
section 216(h) to the Grid Deployment
Office. That authority had previously
been delegated to DOE’s Office of
Electricity Delivery and Energy
Reliability. The same substitution is
made throughout part 900 to reflect that
delegation change.
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
• Revises the reference to the
definition of ‘‘Indian Tribe’’ in the
United States Code to the correct
reference following the 2016 editorial
reclassification. This change does not
amend the definition. Adds the
definitions for ‘‘relevant Federal entity’’
and ‘‘relevant non-Federal entity’’ using
the substance of the definitions from
‘‘Federal entity’’ and ‘‘non-Federal
entity,’’ respectively. These changes are
intended to show that the terms only
mean Federal or non-Federal entities
with some relation to a particular
qualifying project. These changes are
updated throughout part 900.
• Revises the definition for ‘‘regional
mitigation approach’’ to a more general
term of ‘‘mitigation approach.’’ DOE
revised this term because regional-level
approaches and strategies may be too
limiting for the needs at hand; instead,
DOE wants to create the opportunity for
discussion of all types of proposed
mitigation for a given proposed project.
In addition, DOE has revised the
substance of this definition to clarify the
meaning and more closely align with
existing NEPA regulations regarding
mitigation. Because the revisions to
mitigation approach rendered ‘‘regional
mitigation strategies or plans’’
redundant, DOE has removed that
definition.
• Revises the definition for ‘‘MOU
signatory agency’’ to mean any Federal
entity that has entered into the currently
effective MOU under section
216(h)(7)(B)(i) of the FPA. This change
decouples the term from any particular
MOU and keeps the rule current
without requiring changes to the
regulatory text. The term references the
2023 MOU as an example.
• Revises the definition for
‘‘qualifying project’’ in a number of
ways. First, the revised definition
removes the qualifier ‘‘non-marine’’
before high voltage transmission line
and electric transmission line to match
potential scope of the Program with that
agreed to in the MOU. Second, the
revised definition includes several
factors for determining if a transmission
line is regionally or nationally
significant. Third, the revised definition
limits the term to projects that are
expected to require preparation of an
EIS because the Federal coordination
will be most impactful for such projects
due to their complexity. Fourth, in
accordance with the 2023 MOU, this
final rule revises the definition to state
that the term does not include any
transmission facility authorized under
section 8(p) of the Outer Continental
Shelf Lands Act (43 U.S.C. 1337(p)). The
exception to that restriction included in
the 2023 MOU is provided for in the
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
changes to § 900.3 and discussed further
in that section. Fifth, in accordance with
the 2023 MOU, the term excludes a
transmission facility that are seeking a
construction or modification permit
from FERC pursuant to section 216(b) of
the FPA. Sixth, the revised definition
excludes projects located wholly within
the Electric Reliability Council of Texas
interconnection, as required by section
216(k) (16 U.S.C. 824p(k)). This
exclusion is also located in § 900.2(c) of
the current rule, but it is not replicated
it in this definition for clarity. Seventh,
the revision provides a mechanism
under § 900.3 by which a project that
does not meet the definition of a
qualifying project under the first
paragraph of the term may still
participate in the Program. This change
is discussed in more detail in the
following section.
• Revises the definition for ‘‘project
area’’ to clarify the scope of this term.
• Removes the definitions of ‘‘DOE’’
and ‘‘NEPA’’ because those terms are
acronyms best addressed in the
regulatory text rather than as
definitions.
• Removes the definition of ‘‘FPA’’
because that term no longer occurs in
the regulatory text.
• Removes the definitions for ‘‘early
identification of project issues,’’ ‘‘IIP
resources report,’’ ‘‘IIP process
administrative file,’’ ‘‘lead 216(h)
agency,’’ ‘‘MOU principals,’’ and ‘‘other
projects’’ because those terms no longer
occur in part 900.
• Removes the definition for ‘‘NEPA
Lead Agency’’ because that term is selfexplanatory in the context in which it
occurs.
• Revises the term ‘‘stakeholder’’ for
clarity and readability and includes
‘‘organization’’ in the definition to
clarify that stakeholders are not just
individuals.
• Revises the term ‘‘study corridor’’ to
clarify that the term does not coincide
with ‘‘permit area,’’ ‘‘area of potential
effect,’’ ‘‘action area,’’ or other terms
specific to certain types of regulatory
review.
§ 900.3 Applicability to Other Projects
Section 900.2 of the current rule,
titled ‘‘Applicability,’’ provides an
application process by which a project
proponent may seek DOE assistance
under part 900 for an ‘‘other project.’’
This final rule redesignates § 900.2 as
§ 900.3 and retains a mechanism by
which projects that do not otherwise
qualify as ‘‘qualifying projects’’ may be
treated.
Section 900.2(b) is revised and
redesignated as § 900.3(a)–(c) to more
clearly communicate the process by
PO 00000
Frm 00047
Fmt 4701
Sfmt 4700
35357
which a project proponent may request
that a facility be approved as a
qualifying project. In particular, this
final rule removes the definition of the
term ‘‘other project’’ and instead
includes the substance of that term in
paragraph (a) of the revised section.
Paragraphs (a) and (e) of current
§ 900.2 are redesignated as paragraphs
§ 900.1(f) and (g), respectively, because
those paragraphs contain general
propositions regarding part 900 and are
better suited to the general ‘‘Purpose
and Scope’’ section. This final rule
removes the first sentence of current
§ 900.2(e) as it is unnecessary because
part 900 does not purport to affect other
Federal law requirements except in
specific, articulated instances.
Current paragraphs § 900.2 (g) and (h)
are relocated to § 900.4 as paragraphs (e)
and (f), respectively, because § 900.4
provides a general background to the IIP
Process, and the substance of those
paragraphs is more relevant to the IIP
Process than the rest of part 900.
Current § 900.2(d) is redesignated as
paragraph (e) and a new paragraph (d)
is added. New paragraph (d) provides
factors that the Director of GDO may
consider when determining if a
proposed electric transmission facility
should be considered a qualifying
project and accepted into the CITAP
Program.
Redesignated paragraph (e) is further
amended. Whereas the current version
of that paragraph provides that the
section does not apply to a transmission
facility that will require a construction
or modification permit from FERC, this
final rule amends the paragraph to allow
such projects to take advantage of part
900, provided that the request to be
included in the CITAP Program is
submitted by a person with relevant
authority under Delegation Order No.
S1–DEL–FERC–2006 or any subsequent,
similar delegation.
In addition, this final rule removes
paragraph (f), which describes the IIP
process as a complementary process that
does not supplant existing preapplication processes, because this final
rule establishes the IIP Process as the
mandatory precondition for
coordination under section 216(h).
This final rule adds new paragraphs
(f) and (g)(1) that allow a project
proposed to be authorized under
Section 8(p) of the Outer Continental
Shelf Lands Act to receive coordination
assistance under part 900, provided that
the project is not to be authorized in
connection to a generation project and
that all 2023 MOU signatories agree to
the project’s inclusion in the CITAP
Program. These additions reflect the
terms of the 2023 MOU.
E:\FR\FM\01MYR2.SGM
01MYR2
35358
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES2
Finally, current paragraph (c) is
moved to paragraph (g)(2) to improve
the readability of the section.
§ 900.4 Purpose and Scope of IIP
Process
Section 900.4 of the current rule states
the purpose and structure of the IIP
Process. This final rule divides this
section into §§ 900.4, 900.5, 900.8, and
900.9 to improve readability. Section
900.4(a) of the current rule remains in
§ 900.4 but is further divided into
paragraphs (a), (b), and (c) to improve
readability.
Sections 900.4(j)(3)(i) through (iv) are
redesignated as § 900.4(a)(1) through (8)
and amended to reflect a new purpose.
Current § 900.4(j)(3) requires the Federal
entities at the initial meeting to identify
reasonable criteria for adding, deleting,
or modifying preliminary routes within
the study corridors and lists nine
criteria that should be included in the
criteria that Federal entities identify. In
contrast, new § 900.4(a) provides that
those criteria should instead be used by
the project proponent when identifying
potential study corridors and potential
routes. The change encourages the
project proponent to utilize the criteria
in identifying routes and corridors
throughout the IIP Process, rather than
just after the initial meeting. This final
rule retains the requirement for DOE
and other agencies to identify other
criteria for adding or modifying
potential routes and includes that the
agencies should also identify criteria for
potential study corridors as well.
Additionally, § 900.4(b) establishes
the IIP Process as a prerequisite for
coordination, consistent with the
statutory language and the revisions to
the purpose of part 900 in § 900.1. This
final rule adds a new paragraph (d) to
clarify that the IIP Process does not
preclude additional communications
between the project proponent and
relevant Federal entities outside of the
meetings envisioned by the IIP Process.
The paragraph further emphasizes that
DOE intends for the IIP Process to be an
iterative process and that each
milestone in the process is designed to
improve upon the materials that Federal
entities have available for authorization
and environmental review decisions.
This rule redesignates § 900.2(g) and
(h) as § 900.4(e) and (f), respectively,
because § 900.4 provides a general
background to the IIP Process, and the
substance of those paragraphs is more
relevant to the IIP Process than the rest
of part 900. Section § 900.4 gives new
authority to the Director to request
additional information from a project
proponent during the IIP Process to
ensure that DOE can collect the
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
information needed to adequately
complete the IIP Process.
Finally, this final rule adds new
paragraphs (h) and (i), which provide
processes by which a person may
submit confidential information during
the IIP Process or to request designation
of information containing Critical
Electric Infrastructure Information
(CEII). These provisions establish the
mechanisms through which the IIP
Process complies with 10 CFR 1004.11
and 1004.13.
§ 900.5 Initiation of IIP Process
Section 900.5 is composed of current
§ 900.4(b), (c), (e), (g), (h), (i), and (j).
This final rule revises these provisions
to enumerate the documents and
information required to initiate the IIP
Process, expedite that process, ensure
that community impacts from the
project are identified early, and improve
the overall readability and clarity of the
provisions.
Currently, an initiation request to
begin the IIP Process must include a
summary of the qualifying project; a
summary of affected environmental
resources and impacts, including
associated maps, geospatial information,
and studies; and a summary of early
identification of project issues. This
final rule revises the contents of the
request. First, this final rule updates the
contents required in the summary of the
qualifying project in paragraph (b) to
include project proponent details;
identification of any environmental and
engineering firms and subcontractors
under contract to develop the qualifying
project; and a list of anticipated relevant
Federal and non-Federal entities to
ensure sufficient information is
provided for DOE to review and to
include all necessary agencies in the
process. This final rule also adds new
requirements for additional maps as part
of the initiation request, as detailed in
paragraph (c). DOE believes the
additional information in paragraphs (b)
and (c) is necessary to properly identify
the relevant agencies for efficient
coordination.
Additional requirements are added in
this final rule to require submission of
a project participation plan as part of
the initiation request. This plan is in
place of the summary of early
identification of project issues currently
required under the current regulation.
The project participation plan, as
detailed in paragraph (d), will include
the project proponent’s history of
engagement and a public engagement
plan for the project proponent’s future
engagement with communities of
interest and with Indian Tribes that
would be affected by a proposed
PO 00000
Frm 00048
Fmt 4701
Sfmt 4700
qualifying project. The plan would
include specific information on the
proponent’s engagement with
communities of interest and with Indian
Tribes that would be affected by a
proposed qualifying project. An updated
public engagement plan would be
required at the end of the IIP Process to
reflect any activities during that process.
The addition of a public engagement
plan that includes communities of
interest and Indian Tribes that could be
affected by a proposed qualifying
project, would ensure that the project
proponent follows best practices around
outreach. Moreover, by including this
plan in the IIP Process, the regulation
will provide relevant Federal entities an
opportunity to provide input into the
project proponent’s engagement efforts,
and to ensure that the project proponent
engages with all communities of interest
and Indian Tribes that could be affected
by the proposed qualifying project. The
engagement complements Tribal
consultation and public engagement
undertaken by the relevant Federal
entities and would not substitute for
Federal agencies engaging in Nation-toNation consultation with Indian Tribes
and public engagement with
stakeholders and communities of
interest.
This final rule adds a new paragraph
(e), to require submission of a statement
regarding the project’s status under Title
41 of the Fixing America’s Surface
Transportation Act (FAST–41) (42
U.S.C. 4370m et seq.) as part of the
initiation request. This statement is
intended to facilitate coordination
between the IIP Process and the FAST–
41 Process. This final rule adds
requirements for project proponents to
indicate whether their proposed project
currently is a FAST–41 ‘‘covered
project.’’
This final rule adds paragraph (f),
which gives DOE 20 days from the
receipt of the initiation request to
determine whether the initiation request
is sufficient and whether the proposed
electric transmission facility is a
qualifying project. In that same
timeframe, paragraph (f) requires DOE to
provide relevant Federal entities and
relevant non-Federal entities with a
copy of the initiation request and notify
the project proponent and all relevant
Federal entities and relevant nonFederal entities whether the initiation
request is sufficient and whether the
proposed facility is a qualifying project.
This final rule adds a new paragraph
(g), to provide clarity to the process that
DOE and the project proponent must
follow if DOE determines that the
initiation request is insufficient or that
the proposed facility is not a qualifying
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
project. Paragraph (g) dictates that DOE
must give the project proponent the
rationales for the determinations. It also
provides that the project proponent may
file a request for coordination with the
Director of the GDO as provided in
§ 900.3, if DOE determines that the
proposed facility is not a qualifying
project.
This final rule removes the
requirement to submit an affected
environmental resources and impacts
summary as part of the initiation
request. As discussed in more detail in
the next section, that summary is
replaced by thirteen resource reports
submitted after the IIP Process initial
meeting.
Section 900.5(j) is redesignated as
§ 900.5(h), and the content of that
section is amended to reflect a new
timeline for convening the IIP Process
initial meeting and updates to the
discussions that must occur at the
meeting. The timeline for convening the
initial meeting has been reduced from
within 45 days of providing notice to
the project proponent and the relevant
Federal and non-Federal entities that it
has received an IIP Process initiation
request to within 15 days of providing
notice under paragraph (f) that the
initiation request meets the
requirements of the section.
Likewise, the contents of the initial
meeting have been updated. Section
900.5(h)(1) is added to require DOE and
the relevant Federal entities to discuss
the IIP Process and requirements with
the project proponent, the different
Federal authorization processes, and
arrangements for the project proponent
to contribute funds to DOE to cover
costs in the IIP Process (in accordance
with 42 U.S.C. 7278), establishment of
cost recovery agreements or procedures
in accordance with regulations of
relevant Federal entities, where
applicable, or the use of third-party
contractors under DOE’s supervision,
where applicable. DOE believes an early
discussion of the process and
requirements will ensure efficient
participation of the parties and early
identification of potential issues.
This final rule adds § 900.5(h)(2) to
require DOE to identify certain
applications that need to be submitted
to relevant Federal entities during the
IIP Process (for example, Standard Form
299, which a project proponent would
file to seek authorization for
transmission lines crossing Federal
property). The timing of the expected
Federal applications, including which
applications may be required during the
IIP Process and which should be
submitted following the conclusion of
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
the IIP Process, will be covered in the
initial meeting.
This final rule adds § 900.5(h)(3)
requiring DOE to establish all analysis
areas necessary for the completion of
resource reports required under § 900.6.
By requiring DOE to establish the
analysis areas at this early stage of the
IIP Process, this final rule enables and
encourages the project proponent to
begin assembling the resource reports
soon after the proposed project is
accepted into the CITAP Program.
As discussed in the previous section,
§ 900.4(j)(3)(i) through (iv) are
redesignated as § 900.4(a)(1) through (8)
to encourages the project proponent to
utilize the criteria in those paragraphs
when in identifying potential routes and
study corridors. Section 900.5(h)(5)
retains the requirement in § 900.4(j)(3)
for DOE and other agencies to identify
other criteria for adding or modifying
potential routes but adds that the
agencies should also identify criteria for
potential study corridors as well.
Section 900.5(h)(5) is further amended
to include a requirement that DOE and
the relevant Federal entities discuss
study corridors and potential routes
identified by the project proponent and
the criteria used to identify those
corridors and routes.
This final rule revises the requirement
that DOE produce a draft initial meeting
summary within 15 calendar days after
the meeting to 10 calendar days, and the
revises the time that participating
Federal entities and Non-Federal
entities, and the project proponent will
then have to provide corrections to the
draft summary from 15 calendar days to
10 calendar days. Additionally, this
final rule revises the requirement that
DOE produce a final initial meeting
summary within 30 days of receiving
corrections to the draft summary to 10
days. All three changes are intended to
expedite the IIP Process.
This final rule revises this section to
add the requirement in § 900.6 that
requires DOE to add the final initial
meeting summary to the consolidated
administrative docket. Finally, this final
rule removes portions of paragraph
(j)(3)(v) because the contents are
addressed elsewhere.
§ 900.6 Project Proponent Resource
Reports
This final rule adds a new § 900.6 to
add requirements for project proponents
to develop, in collaboration with
relevant Federal entities, thirteen
resource reports that will serve as
inputs, as appropriate, into the relevant
Federal entities’ own environmental
analysis and authorization processes.
This pre-application material will
PO 00000
Frm 00049
Fmt 4701
Sfmt 4700
35359
provide for earlier collection of critical
information to inform the future
application process relating to the
proposed transmission line and
facilities, including preliminary
information to support DOE’s and the
relevant Federal entities’ compliance
with section 106 of the NHPA, the ESA,
and NEPA. The thirteen resource reports
are: General project description; Water
use and quality; Fish, wildlife, and
vegetation; Cultural resources;
Socioeconomics; Geological resources
and hazards; Soil resources; Land use,
recreation, and aesthetics; Communities
of interest; Air quality and noise effects;
Alternatives; Reliability, resilience, and
safety; and Tribal interests. This final
rule renumbers the resource reports in
response to a comment, as discussed in
section VI.L of this document.
This final rule adds requirements for
project proponents to develop these
resource reports as part of the preapplication process instead of the
affected environmental resources and
impacts summary document required
from project proponents under the
existing rule at section 900.4(d). The
resource reports identify information
needed to complete NEPA and other
review and authorization requirements.
However, the topics identified and the
reports do not limit the information
relevant Federal entities may need,
require from project proponents, or
develop independently, as necessary to
satisfy each relevant Federal entity’s
applicable statutory and regulatory
obligations. To address possible
differences in information required for
onshore and offshore project
environments, the final rule allows the
Director to modify the requirements of
resource reports to ensure that the
reports adequately cover their intended
purpose. Each resource report will
comprehensively discuss the baseline
conditions and anticipated impacts to
resources relevant to DOE’s required
environmental review, namely under
NEPA, ESA, and section 106 of the
NHPA. NEPA requires Federal agencies
to analyze and assess potential
environmental effects of the proposed
Federal agency action, and these effects
can vary in significance and complexity.
DOE anticipates that these reports will
inform its work to meet its requirements
under the various environmental laws
referenced above. In addition, proper
assessment of the resources potentially
affected by the proposed action can also
help DOE identify resource conflicts,
missing information, and needs from
other agencies, and inform the projectspecific schedule. These conflicts and
needs can then be discussed and
E:\FR\FM\01MYR2.SGM
01MYR2
35360
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES2
addressed during the review meeting
and throughout the IIP Process.
These resource reports will be
developed by project proponents during
the IIP Process with input and feedback
from the Federal and non-Federal
entities involved in authorization
decisions. This procedure better
matches the IIP Process with the project
development and Federal review
timelines. Under these changes, a
project proponent may initiate the IIP
Process without detailed environmental
resources information, but the detailed
information required by this section
must be developed to complete the IIP
Process. The more detailed preapplication information, presented in
the resource reports, will allow project
proponents and the relevant Federal
entities to coordinate and identify issues
prior to submission of applications for
authorizations, inform project design,
and expedite relevant Federal entities’
environmental reviews by providing
environmental information that relevant
Federal entities can use after submission
of applications to inform their own
reviews and by ensuring those
applications are complete.
§ 900.7 Standard and Project-Specific
Schedules
This final rule adds a new § 900.7 to
amend how DOE will carry out its
obligation to ‘‘establish prompt and
binding intermediate milestones and
ultimate deadlines for the review of, and
Federal authorization decisions relating
to, the proposed facility’’ pursuant to
section 216(h). 16 U.S.C. 824p(h)(4)(A).
Specifically, this final rule adds a
description for the ‘‘standard schedule,’’
which DOE will publish as guidance
and update from time to time. The
standard schedule is not project
specific. Rather, it will describe, as a
general matter, the steps necessary to
review applications for Federal
authorizations, and the related
environmental reviews necessary to site
qualifying projects. This schedule will
contemplate that authorizations and
related environmental reviews be
completed within two years.
Paragraph (b) describes the projectspecific schedule. As discussed further
below, DOE will develop this schedule
with the NEPA joint lead agency and the
relevant Federal entities on a per-project
basis during the IIP Process. This
schedule would provide the ‘‘binding
intermediate milestones and ultimate
deadlines’’ required by section 216(h).
This provision is intended to specify the
considerations that DOE will
incorporate into its determination of the
appropriate project-specific schedule
including joint lead and other agency-
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
specific regulations and schedules.
Section 216(h)(4)(B) requires DOE to set
a project-specific schedule under which
all Federal authorizations may be
completed within one year of the filing
of a complete application unless other
requirements of Federal law require a
longer schedule. DOE intends to
determine the project-specific schedule
based on the considerations specified in
paragraph (b).
§ 900.8 IIP Process Review Meeting
This final rule amends the IIP Process
to ensure that DOE and the Federal and
non-Federal entities involved have
meaningful opportunities to identify
issues of concern prior to the project
proponent’s submission of applications
for authorizations. In addition to the
initial and close-out meetings included
in the current text of part 900, this final
rule establishes an IIP Process review
meeting, to be held at the request of the
project proponent following initial
submission of the requisite thirteen
resource reports. In addition, this final
rule adds a requirement for a project
proponent requesting the review
meeting to update DOE on the status of
the project’s public engagement and
provide updated environmental
information.
This final rule adds that the IIP
Process review meeting will ensure that
DOE and the relevant Federal and nonFederal entities involved have
meaningful opportunities to identify
issues of concern prior to the close of
the IIP Process and submission of
applications for Federal authorizations.
To this end, this final rule adds a
requirement in paragraph (f) that at the
review meeting the relevant Federal
entities should discuss any remaining
issues of concern, information gaps,
data needs, potential issues or conflicts,
statutory and regulatory standards, and
expectations for complete applications
for Federal authorizations. Additionally,
the meeting participants will provide
updates on the siting process, including
stakeholder outreach and input. To
facilitate these discussions, paragraph
(a) is added to state that a project
proponent should submit a request for
the review meeting containing helpful
documents and information such as a
summary table of changes made to the
project since the initial meeting, maps
of proposed routes within study
corridors, a conceptual plan for
implementation and monitoring of
mitigation measures, an updated public
engagement plan and timeline
information including dates on which
any applications were already filed,
estimated dates for filing remaining
applications with Federal and non-
PO 00000
Frm 00050
Fmt 4701
Sfmt 4700
Federal entities, and a proposed
duration for each Federal land use
authorization expected to be required
for the proposed project.
Additionally, the IIP Process review
meeting will provide an opportunity for
DOE and the relevant Federal and nonFederal entities to review the detailed
resource reports prepared pursuant to
§ 900.6. Therefore, the review meeting
will only be held after submission of the
reports. Section 900.8(f)(8) is added to
state that during the IIP Process review
meeting, DOE and the relevant Federal
and non-Federal entities will identify
any updates to the information included
in those reports that the project
proponent must make before the
conclusion of the IIP Process. Finally,
this final rule adds in § 900.8(k) the
requirement that the project proponent
revise resource reports based on
feedback received during the meeting.
DOE believes that identifying and
addressing issues in the reports during
the IIP Process instead of at the end of
that process would expedite DOE’s
preparation of a single environmental
review document and increase the
likelihood of readiness of the project
proponent’s application(s) for Federal
authorization(s).
Furthermore, the IIP Process review
meeting will integrate DOE’s statutory
schedule-setting function discussed in
the previous section into the IIP Process.
For this purpose, the review meeting
request under paragraph (a) should
include a schedule for completing
upcoming field resource surveys, if
known, and estimated dates that the
project proponent will file requests for
Federal and non-Federal authorizations
and consultations. These resources will
assist DOE in preparing the proposed
project-specific schedule, which DOE
would be required to present at the
review meeting under § 900.8(f)(9). At
the meeting, the relevant Federal
entities would discuss the process for,
and estimated time to complete,
required Federal authorizations. These
discussions, along with other matters
discussed at the review meeting would,
in turn, allow DOE to continue refining
the project-specific schedule.
This final rule adds a requirement in
paragraph (b) that within 10 days of
receiving the review meeting request,
DOE must provide relevant Federal
entities and relevant non-Federal
entities with materials included in the
request and the initial resource reports
submitted under § 900.6. In paragraph
(c), DOE believes a 60-day period is
necessary to review the request for
sufficiency and provide notice to the
proponent and relevant Federal and
non-Federal agencies and provides in
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES2
paragraph (d) that it will provide
reasons for any findings of insufficiency
and how the project proponent may
address them for reconsideration.
Furthermore, this final rule adds a
requirement in paragraph (e) that the
review meeting will convene within 15
days of providing notice that the request
has been accepted. These timelines will
ensure that the IIP Process is pursued
expeditiously while affording the
relevant Federal entities sufficient time
to review the relevant materials. The
requirement to share the review meeting
request and initial resources reports in
paragraph (b) will ensure that all
entities participating in the meeting
have access to the materials being
discussed at the meeting.
This final rule adds requirements in
paragraphs (g), (h), and (i) that the IIP
Process review meeting will conclude
with a draft and, subsequently, a final
review meeting summary, to be
prepared by DOE. This summary will be
included in the consolidated
administrative docket described by
§ 900.10. It will serve as a docket of the
issues identified by the parties to the
review meeting, and to ensure that the
project proponent, the relevant Federal
and non-Federal entities, and DOE, have
a shared understanding of the work
remaining to be done during the IIP
Process.
This final rule adds paragraph (j) to
include a mechanism by which it may
determine whether the project
proponent has developed the scope of
its proposed project and alternatives
sufficiently for DOE to determine that
there exists an undertaking with the
potential to affect historic properties for
purposes of section 106 of the NHPA. If
DOE so determines, DOE will initiate its
section 106 review of the undertaking
and authorize project proponents as
CITAP Program applicants to initiate
consultation with SHPOs, THPOs, and
others consistent with 36 CFR
800.2(c)(4). This provision is intended
to allow initiation of section 106
consultation during the IIP Process,
prior to submission of applications for
authorizations, but with sufficient
opportunity for the project proponent,
the relevant Federal entities, and DOE,
to determine the scope of the proposed
project.
§ 900.9 IIP Process Close-Out Meeting
This final rule amends the close-out
meeting provisions of the current rule at
§ 900.4(k) and (l). The IIP Process will
conclude with the close-out meeting.
This final rule adds the requirement of
submission of a close-out meeting
request to specify the modifications to
the project since the review meeting.
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
This final rule removes the requirement
in this section that states that the
request may be submitted no less than
45 days after the initial meeting. DOE
removes that requirement because
changes to the IIP Process in this final
rule no longer allow for a request to be
submitted within that timeframe.
This final rule removes paragraphs
(k)(3), (5), (8), and (9). The information
required under those paragraphs will be
submitted with the review meeting
request under § 900.8(a). Likewise, DOE
removed paragraphs (k)(4), (6), and (7)
because the information required under
those paragraphs would be submitted in
the resources reports under § 900.6.
Finally, paragraph (k)(1) is removed
because the submission of close-out
meeting request materials is presumed
to indicate that a close-out meeting is
being requested.
Paragraphs (a)(2) and (3) require a
description of all changes made to the
proposed project since the review
meeting and a final public engagement
plan. In paragraph (a)(4) DOE added a
requirement that the project proponent
provide the requests for Federal
authorizations for the proposed project.
These will be included in the close-out
meeting request to ensure that the
project proponent is ready to begin the
Federal authorization process.
This final rule revises the timelines
for requesting and convening a close-out
meeting. In current paragraphs (1), (2),
and (3), DOE has 30 days to respond to
a close-out meeting request and 60 days
from the date of providing a response to
convene the close-out meeting. DOE
provides in paragraph (b) that within 10
days of receiving the request, DOE must
provide relevant Federal entities and
relevant non-Federal entities with
materials included in the request and
any updated resource reports submitted
as required under § 900.8. Paragraph (c)
provides that DOE has 60 days to review
the request for sufficiency and notify the
project proponent and all relevant
Federal and non-Federal entities of
DOE’s decision. Under paragraph (d), if
DOE determines that the meeting
request or updated resource reports are
insufficient then DOE will provide
reasons and how deficiencies may be
addressed. Under paragraph (e), DOE
will convene the close-out meeting
within 15 days of notifying the project
proponent that the request and updated
resource reports have been accepted.
These new timelines will ensure that
the IIP Process is pursued expeditiously.
Furthermore, the requirement to share
the close-out meeting request materials
in paragraph (b) would ensure that all
entities participating in the meeting
PO 00000
Frm 00051
Fmt 4701
Sfmt 4700
35361
have access to the materials being
discussed at the meeting.
DOE removed the requirement that
the substance of the close-out meeting
include a description of remaining
issues of concern, information gaps,
data needs, and potential issues or
conflicts that could impact the time it
will take relevant Federal entities to
process applications for Federal
authorizations. This information is
covered at the review meeting under
§ 900.8(d). Likewise, DOE eliminated
paragraphs (l)(3)(ii), (iii), (iv), and (v)
because that information is now
required to be discussed at the review
meeting. DOE added in paragraph (e)
that DOE will present the final projectspecific schedule at the meeting, in
keeping with DOE’s statutory schedulesetting function discussed previously.
As previously explained, the projectspecific schedule will include the
intermediate milestones and final
deadlines for review of the project
proponent’s application and related
environmental reviews.
This final rule removes the portion of
paragraph (l) of the current regulation
which states that ‘‘The IIP Process
Close-Out Meeting will also result in the
identification of a potential NEPA Lead
Agency pursuant to § 900.6 described.’’
This final rule adds a provision to select
the NEPA joint lead agency earlier in
the IIP Process to allow for sufficient
coordination.
DOE removed paragraph (l)(3)(vi)
because the information covered by the
Final IIP Resources Report will be
covered by the thirteen resources
reports. Additionally, DOE removed
paragraph (l)(3)(vii), which encourages
agencies to use the Final IIP Resources
Report to inform the NEPA Process.
Instead, this final rule adds a new
requirement at § 900.12(f) to require all
relevant Federal entities to use the
single environmental review document
as the basis for Federal authorization
decisions. That requirement is
discussed in more detail as follows.
This final rule removes paragraph
(l)(3)(viii), which requires relevant
Federal entities to identify a preliminary
schedule for authorizations for the
proposed project, because now DOE will
set a project-specific schedule for all
relevant Federal entities in consultation
with such entities.
Paragraphs (g), (h), and (i) provide
that the IIP Process close-out meeting
will conclude with a draft and,
subsequently a final close-out meeting
summary, to be prepared by DOE. This
summary will be included in the
administrative docket. It would serve as
a summary of the issues identified by
the parties to the close-out meeting, and
E:\FR\FM\01MYR2.SGM
01MYR2
35362
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES2
ensure that the project proponent, the
relevant Federal and non-Federal
entities, and DOE, have a shared
understanding of the conclusion of the
IIP Process.
In paragraph (i)(4), in accordance with
the 2023 MOU, DOE will notify the
FPISC Executive Director that the
project should be included on the FPISC
Dashboard as a transparency project if
the project is not identified as a covered
project pursuant to § 900.5(e).
In paragraph (j), DOE and the NEPA
joint lead agency shall issue a notice of
intent to publish an environmental
review document within 90 days of the
later of the IIP Process close-out meeting
or the receipt of a complete application
for a Federal authorization for which
NEPA review will be required, as
consistent with the final project-specific
schedule to enable DOE to implement
its coordinating authority under FPA
section 216(h).
Finally, in paragraph (k), in
accordance with section 313(h)(8)(A)(i)
of the FPA, DOE shall issue, for each
Federal land use authorization for a
proposed electric transmission facility, a
preliminary duration determination
commensurate with the anticipated use
of the proposed facility.
§ 900.10 Consolidated Administrative
Docket
Current § 900.6 requires DOE to
maintain an IIP Process Administrative
File with all relevant documents and
communications between the project
proponent and the agencies and
encourages agencies to work with DOE
to create a single record. To better
integrate and coordinate Federal
authorizations, the new section
dispenses with the IIP Process
Administrative File and combines all
documents that were previously
included in that file along with all
information assembled by relevant
Federal entities for authorizations and
reviews after completion of the IIP
Process into a single, consolidated
administrative docket.
To this end, this final rule amends
and redesignates paragraph (b) as a new
paragraph (a) to articulate more clearly
the information that should be included
in the docket, including requests made
during the IIP Process, IIP Process
meeting summaries, resources reports,
and the final project-specific schedule.
The sentence in current paragraph (b)
regarding the Freedom of Information
Act is removed because that law applies
to requests for information from the
public on its own terms.
Current paragraph (b) also requires
DOE to share the IIP Process
Administrative File with the joint lead
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
NEPA agency. However, this final rule
adds in paragraph (c) the requirement
that DOE make the consolidated
administrative docket available to both
the NEPA joint lead agency and any
Federal or non-Federal entity that will
issue an authorization for the project.
This change ensures that other entities
are able to use the docket for their own
authorizations. Consequently, this final
rule removes paragraph (d), which says
that Federal entities are strongly
encouraged to maintain information
developed during the IIP Process.
This final rule adds a new paragraph
(d) providing notice that, as necessary
and appropriate, DOE may require a
project proponent to contract with a
qualified docket-management
consultant to assist DOE and the NEPA
joint lead agency in compiling and
maintaining the administrative docket.
Such a contractor may assist DOE and
the relevant Federal entities in
maintaining a comprehensive and
readily accessible docket. DOE is also
proposing that any such contractor shall
operate at the direction of DOE, and that
DOE shall retain responsibility and
authority over the content of the docket
to ensure the integrity and completeness
of the docket.
This final rule adds a new paragraph
(e) providing that upon request, any
member of the public may be provided
materials included in the docket,
excluding any materials protected as
CEII or as confidential under other
processes. This addition is to support
stakeholder engagement in the IIP
Process.
Finally, this final rule relocates
paragraph (a) of the current rule to
paragraph (b) for organizational
purposes.
§ 900.11 NEPA Lead Agency and
Selection of NEPA Joint Lead Agency
This section states that DOE serves in
the NEPA lead agency role
contemplated in section 216(h) except
where a joint lead is designated, in
which case DOE serves as a joint lead.
DOE coordinates the selection of a
NEPA lead agency in compliance with
NEPA, CEQ implementing regulations at
40 CFR part 1500, and each agency’s
respective NEPA implementing
regulations and procedures.
This final rule redesignates § 900.5 to
a new § 900.11 and amends this section
to reflect that DOE, in accordance with
section 216(h)(5)(A) and the 2023 MOU,
will serve as lead agency for purposes
of NEPA along with any NEPA joint
lead agency as designated pursuant to
the MOU and § 900.11 consistent with
its obligation as lead agency to
PO 00000
Frm 00052
Fmt 4701
Sfmt 4700
coordinate with relevant Federal
entities.
In the 2023 MOU, the MOU signatory
agencies agreed to a process by which
a NEPA joint lead agency could be
designated. Under that process, DOE
and the agency with the most significant
interest in the management of Federal
lands or waters that would be traversed
or affected by the proposed project
would serve as lead agencies jointly
responsible for preparing an EIS under
NEPA. Section 900.11(b) reflects that
agreed-upon process.
These amendments also provide that,
for projects that would traverse both
USDA and DOI lands, DOE will request
that USDA and DOI determine the
appropriate NEPA joint lead agency.
§ 900.12 Environmental Review
Consistent with DOE’s role as lead
agency, a new § 900.12 is added to
define DOE’s responsibilities as lead
agency for environmental reviews and
the NEPA process, including by
preparing a single environmental review
document designed to serve the needs of
all relevant Federal entities. In
paragraph (a) of this section, this final
rule clarifies that DOE will begin
preparing an environmental review
document following the conclusion of
the IIP Process and after receipt of a
relevant application. It also notes that
DOE will do so in conjunction with any
NEPA joint lead agency selected under
§ 900.11.
The other provisions of this section
specify details of DOE’s—and any NEPA
joint lead agency’s—role as lead NEPA
agency, including to arrange for
contractors, publish completed
documents, and identify the full scope
of alternatives for analysis. This final
rule provides that except where
inappropriate or inefficient to do so, the
Federal agencies shall issue a joint
record of decision, inclusive of all
relevant Federal authorizations
including the determination by the
Secretary of Energy of a duration for
each land use authorization issued
under section 216(h)(8)(A)(i). This jointdecision provision is added to be
consistent with NEPA regulations,
including the Fiscal Responsibility Act
of 2023, which codified processes to
streamline the environmental review
process and facilitate one Federal
decision, be consistent with the
Congressional intent of FPA 216(h), and
enhance DOE’s coordinating function.
Consistent with section 216(h)(5)(A),
which requires that DOE’s
environmental review document serve
as ‘‘the basis for all decisions on the
project under Federal law,’’ paragraph
(f) is added to establish that the relevant
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
Federal agencies will use the
environmental review document as the
basis for their respective decisions.
Finally, paragraph (g) is added to
specify that DOE will serve as lead
agency for purposes of consultation
under the ESA and compliance with the
NHPA unless the relevant Federal
entities designate otherwise. This
provision will allow DOE to meet its
obligation under section 216(h)(2) to
coordinate ‘‘all . . . related
environmental reviews of the facility.’’
§ 900.13 Severability
Section § 900.13 provides that the
provisions of this final rule are separate
and severable from one another, and
that if any provision is stayed or
determined to be invalid by a court of
competent jurisdiction, the remaining
provisions would still function sensibly
and shall continue in effect. This
severability clause is intended to clearly
express the Department’s intent that
should a provision be stayed or
invalidated the remaining provisions
shall continue in effect. The Department
has carefully considered the
requirements of this final rule, both
individually and in their totality,
including their potential costs and
benefits to project proponents. In the
event a court were to stay or invalidate
one or more provisions of this rule as
finalized, the Department would want
the remaining portions of the rule as
finalized to remain in full force and
legal effect.
VIII. Regulatory Review
A. Review Under Executive Orders
12866, 13563, and 14094
Executive Order (‘‘E.O.’’) 12866,
‘‘Regulatory Planning and Review,’’ 58
FR 51735 (Oct. 4, 1993), as
supplemented and reaffirmed by E.O.
13563, ‘‘Improving Regulation and
Regulatory Review,’’ 76 FR 3821 (Jan.
21, 2011) and amended by E.O. 14094,
‘‘Modernizing Regulatory Review,’’ 88
FR 21879 (April 11, 2023), requires
agencies, to the extent permitted by law,
to (1) propose or adopt a regulation only
upon a reasoned determination that its
benefits justify its costs (recognizing
that some benefits and costs are difficult
to quantify); (2) tailor regulations to
impose the least burden on society,
consistent with obtaining regulatory
objectives, taking into account, among
other things, and to the extent
practicable, the costs of cumulative
regulations; (3) select, in choosing
among alternative regulatory
approaches, those approaches that
maximize net benefits (including
potential economic, environmental,
public health and safety, and other
advantages; distributive impacts; and
equity); (4) to the extent feasible, specify
performance objectives, rather than
specifying the behavior or manner of
compliance that regulated entities must
adopt; and (5) identify and assess
available alternatives to direct
regulation, including providing
economic incentives to encourage the
desired behavior, such as user fees or
marketable permits, or providing
information upon which choices can be
made by the public. DOE emphasizes as
well that E.O. 13563 requires agencies to
use the best available techniques to
quantify anticipated present and future
benefits and costs as accurately as
possible. In its guidance, the Office of
Information and Regulatory Affairs
(OIRA) has emphasized that such
techniques may include identifying
35363
changing future compliance costs that
might result from technological
innovation or anticipated behavioral
changes. For the reasons stated in the
preamble, this regulatory action is
consistent with these principles.
Section 6(a) of E.O. 12866 requires
agencies to submit ‘‘significant
regulatory actions’’ to OIRA for review.
OIRA has determined that this
regulatory action constitutes a
‘‘significant regulatory action’’ within
the scope of E.O. 12866. Accordingly,
this action is subject to review under
E.O. 12866 by OIRA of the Office of
Management and Budget (OMB).
Section 6(a) of E.O. 12866 requires an
agency issuing a ‘‘significant regulatory
action’’ to provide an assessment of the
potential costs and benefits of the
regulatory action. To that end, DOE has
further assessed the qualitative and
quantitative costs and benefits of this
final rule.
The societal costs of the action are the
direct costs incurred by project
proponents during the IIP Process. DOE
discussed in the previous sections that
most of the information required to be
submitted during the IIP Process would
likely be required absent these
regulations and therefore the investment
of time and resources required by this
process are unlikely to be an additional
burden on respondents. However, the
full costs are considered in this analysis
for transparency. These costs of
$439,000 per year are detailed in the
Paperwork Reduction Act burden
analysis. The table below captures the
10-year and 20-year net present value of
those annual costs under two discount
rates (3% and 7%).
CITAP PROGRAM NPV COST ESTIMATES *
Discount rate
10-year NPV ................................................................................................................................................
20-year NPV ................................................................................................................................................
3%
7%
$3,745,000
6,531,000
$3,083,000
4,651,000
ddrumheller on DSK120RN23PROD with RULES2
* 10-year analysis is 2024–2033, 20-year analysis is 2024–2043. NPV estimates provided in 2024$.
The benefits of the CITAP Program,
designed to reduce the Federal
authorization timelines for interstate
electric transmission facilities and
enable more rapid deployment of
transmission infrastructure, include
direct benefits to the project proponents
in decreased time and expenditure on
authorizations and a series of indirect
social benefits.
Increasing the current pace of
transmission infrastructure deployment
will generate benefits to the public in
multiple ways that can be categorized
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
into grid operations, system planning,
and non-market benefits. Grid operation
benefits include a reduction in the
congestion costs for generating and
delivering energy; mitigation of weather
and variable generation uncertainty,
enhanced diversity of supply, which
increases market competition and
reduces the need for regional backup
power options; and increased market
liquidity and competition.15 From a
15 Millstein, A. et al. (2022) Empirical estimates
of transmission value using locational marginal
PO 00000
Frm 00053
Fmt 4701
Sfmt 4700
system planning standpoint, accelerated
transmission investments will allow the
development of new, low cost power
plants in areas of high congestion which
might not otherwise see investment due
to capacity constraints, and additional
grid hardening or resilience. Finally,
non-market benefits to the public
include reduced costs for meeting
prices, Empirical Estimates of Transmission Value
using Locational Marginal Prices | Electricity
Markets and Policy Group, 6. Available at: https://
emp.lbl.gov/publications/empirical-estimatestransmission.
E:\FR\FM\01MYR2.SGM
01MYR2
35364
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
public policy goals related to emissions
and equitable energy access, as well as
emissions reductions system wide.16
The DOE Grid Deployment Office
released the 2023 National
Transmission Needs Study (Needs
Study), which identified significant
need for the expansion of electric
transmission across the contiguous
United States.17 The Needs Study and
2022 interconnection queue analysis by
Berkeley Lab support DOE’s analysis
that the CITAP Program will provide
substantial benefits by reducing
authorization timelines for transmission
projects and increasing the speed of
transmission development and clean
energy integration.18
The quantitative benefits of the CITAP
Program will ultimately depend on the
projects that are designed and
developed by project proponents.
However, the quantifiable benefits of
transmission development can be
estimated generally. These quantifiable
benefits are the result of reductions in
transmission congestion costs and
avoided emissions from the increased
use of clean energy enabled by
additional transmission.
A 2023 analysis of transmission
congestion costs by a consulting group
found that congestion costs have risen
from an average of $7.1 billion between
2016 and 2021 to $20.8 billion in
2022.19 A 2022 study by Lawrence
Berkeley National Lab found that
between 2012 and 2021, a 1000 MW
interregional transmission line could
have provided $20 to $670 million
dollars per year in value by providing
congestion relief, which would have
lowered energy costs to consumers.20
Forward-looking projections for
transmission value along these
parameters are not available, and DOE is
reluctant to project the complex changes
to technical operations and market
dynamics given the wide range in
projected value. However, DOE notes
that it has estimated that the CITAP
Program will serve three projects a year
that are each roughly equivalent to a
1000 MW line, an increase in the
average number of these transmission
ddrumheller on DSK120RN23PROD with RULES2
16 Id.
17 DOE, National Transmission Needs Study (Oct.
2023), available at https://www.energy.gov/sites/
default/files/2023-12/National%20Transmission
%20Needs%20Study%20-%20Final_2023.12.1.pdf.
18 Berkeley Lab, Queued up: Characteristics of
power plants seeking transmission interconnection
(2023), Electricity Markets and Policy Group.
Available at: https://emp.lbl.gov/queues.
19 (2023) Transmission congestion costs rise again
in U.S. RTOS, 1. Available at: https://
gridstrategiesllc.com/wp-content/uploads/2023/07/
GS_Transmission-Congestion-Costs-in-the-U.S.RTOs1.pdf.
20 Millstein, et al., 2022, 15.
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
projects authorized by a Federal agency
in the past 17 years. With decreased
authorization times after the CITAP
Program is initialized, the additional
capacity enabled by this action would
likely provide substantial congestion
relief, consistent with the studies cited
previously.
A key driver of transmission
congestion costs is that the growth of
low-cost renewable energy projects is
outpacing the rate of transmission
expansion. Inadequate transmission
capacity can lead to curtailment of
available renewable energy in favor of
thermal generators, which increases
costs to consumers due to fuel prices
and increases emissions.21 A recent
projection found that transmission
capacity must expand by 2.3% annually
to realize the full benefits of the clean
energy investments in the IRA.
However, in the last decade,
transmission capacity has only
increased an average of 1% per year.22
The modeling projects that increasing
the rate of transmission capacity
expansion by even just 50% (1% to
1.5% annually) would significantly
reduce emissions by enabling more
clean energy on the grid, estimating
nearly 600 million tons of avoided
emissions (CO2 equivalent) in 2030
alone.23 An annual 1.5% increase in
transmission capacity is estimated to
add 7,000 MW to the grid in 2030 and
provide an estimated $53.4 billion in
societal benefits from avoided emissions
that year, using a $89/ton social cost of
carbon.24 DOE estimates that the CITAP
21 Howland, E. (2023) US grid congestion costs
jumped 56% to $20.8B in 2022: Report, Utility Dive.
Available at: https://www.utilitydive.com/news/
grid-congestion-costs-transmission-gets-gridstrategies-report/687309/#:∼:text=
Costs%20to%20consumers
%20from%20congestion%20on
%20the%20U.S.,report%20released
%20Thursday%20by%20consulting%20firm
%20Grid%20Strategies. and Nationwide
transmission congestion costs rise to $20.8 billion
in 2022 (2023). Advanced Power Alliance. Available
at: https://poweralliance.org/2023/07/13/
nationwide-transmission-congestion-costs-rise-to20-8-billion-in-2022/#:∼:text=By%20extrapolating
%20data%20from%20Independent%20Market
%20Monitor%20reports,congestion
%20costs%20reached%20%2420.8%20billion
%20nationwide%20last%20year.
22 Jenkins, J.D. et al. (2022) Electricity
transmission is key to unlock the full potential of
the Inflation Reduction Act, Zenodo. Available at:
https://zenodo.org/record/7106176#
:∼:text=Previously%2C%20REPEAT%20Project
%20estimated%20that%20IRA%20could
%20cut,from%20electric%20vehicles%2C%20heat
%20pumps%2C%20and
%20other%20electrification.
23 Id.
24 Technical support document: Social cost of
carbon, methane, (2021) whitehouse.gov, 5.
Available at: https://www.whitehouse.gov/wpcontent/uploads/2021/02/
PO 00000
Frm 00054
Fmt 4701
Sfmt 4700
Program will increase the number of
high-capacity projects seeking Federal
authorizations, providing a portion of
projected avoided emissions benefits
through increased transmission
capacity. These benefits would continue
to grow in the following years as
transmission capacity is increased.
While these estimates of quantitative
benefits are necessarily approximate,
the non-monetized benefits of the
CITAP Program to the public are
expected to far offset the monetized
costs to project proponents. By enabling
rapid development of enhanced
transmission capacity, the CITAP
Program will help increase access to a
diversity of generation sources, offset
transmission congestion and carbon
costs, and deliver reliable, affordable
power that future consumers will need
when and where they need it.
B. Review Under the Regulatory
Flexibility Act
The Regulatory Flexibility Act of 1980
(5 U.S.C. 601 et seq.) requires that an
agency prepare an initial regulatory
flexibility analysis for any regulation for
which a general notice of proposed
rulemaking is required, unless the
agency certifies that the rule, if
promulgated, will not have a significant
economic impact on a substantial
number of small entities (5 U.S.C.
605(b)). As required by E.O. 13272,
‘‘Proper Consideration of Small Entities
in Agency Rulemaking,’’ 67 FR 53461
(Aug. 16, 2002), DOE published
procedures and policies on February 19,
2003, to ensure that the potential
impacts of its rules on small entities are
properly considered during the
rulemaking process (see 68 FR 7990).
DOE has made its procedures and
policies available on the Office of the
General Counsel’s website
(www.energy.gov/gc/office-generalcounsel).
DOE reviewed this final rule under
the provisions of the Regulatory
Flexibility Act and the procedures and
policies published on February 19,
2003. DOE certifies that this final rule
will not have a significant economic
impact on a substantial number of small
entities. The factual basis for this
certification is set forth.
DOE expects that the amendments to
part 900 will not affect the substantive
interests of such project proponents,
including any project proponents that
are small entities. DOE expects actions
taken under the provisions to coordinate
information and agency communication
before applications for Federal
TechnicalSupportDocument_SocialCostof
CarbonMethaneNitrousOxide.pdf.
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
authorizations are submitted to Federal
agencies for review and consideration
would help reduce application review
and decision-making timelines.
Ensuring that all project proponents
avail themselves of the benefits of the
IIP Process will result in a clear, nonduplicative, process. Participation in the
CITAP Program is optional. Thus,
proposing to make the IIP Process a
condition of the Program does not
prevent project proponents from
submitting application outside of the
Program. DOE, however, encourages
project proponents to take advantage of
the Program based on the urgency and
a consensus among 2023 MOU
signatories of the anticipated benefits
the Program will provide.
Furthermore, these changes are
procedural and apply only to project
proponents that develop electric
transmission infrastructure. Historically,
entities that develop transmission
infrastructure are larger entities.
Therefore, these procedures are unlikely
to directly affect small businesses or
other small entities. For these reasons,
DOE certifies that this final rule will not
have a significant economic impact on
a substantial number of small entities.
Accordingly, DOE has not prepared a
regulatory flexibility analysis for this
rulemaking. DOE’s certification and
supporting statement of factual basis
will be provided to the Chief Counsel
for Advocacy of the Small Business
Administration for review under 5
U.S.C. 605(b).
C. Review Under the Paperwork
Reduction Act of 1995
This final rule contains information
collection requirements subject to
review and approval by OMB pursuant
to the Paperwork Reduction Act of 1995
(44 U.S.C. 3501 et seq.) (PRA) and the
procedures implementing that Act (5
CFR 1320.1 et seq.). The request to
approve and revise this collection
requirement has been submitted to OMB
for approval. The amendments are
intended to improve the pre-application
procedures and result in more efficient
processing of applications.
This final rule modifies certain
reporting and recordkeeping
requirements included in OMB Control
No. 1910–5185 which is an ongoing
collection. The revisions to DOE’s
regulations associated with the OMB
Control No. 1910–5185 information
collection are intended to ensure that
DOE may carry out its statutory
obligations under section 216(h) of the
FPA. Information supplied will be used
to support an initiation request
necessary to begin DOE’s IIP Process.
The revisions include requiring that a
35365
project proponent provide: (1)
additional maps and information for the
summary of proposed project; (2) a
project participation plan; and (3) a
statement regarding whether the project
is a FAST–41 covered project.
Additional information collection
required includes thirteen resource
reports describing the project and its
impacts to allow DOE to complete a
single environmental review document
as part of the IIP Process. Those reports
are: General project description; Water
use and quality; Fish, wildlife, and
vegetation; Cultural resources;
Socioeconomics; Geological resources
and hazards; Soil resources; Land use,
recreation, and aesthetics; Communities
of interest; Air quality and noise effects;
Alternatives; Reliability, resilience, and
safety; and Tribal interests.
Additionally, during the review and
close-out meetings, project proponents
will provide updates to project
documents and the project schedule.
The revisions represent an increase in
information collection requirements and
burden for OMB No. 1910–5185.
The estimated burden and cost for the
requirements contained in this final rule
follow. Each entry indicates the time
estimated for a meeting or the time
estimated for the respondent to prepare
the report or request.
ESTIMATE OF ANNUAL RESPONDENT REPORTING AND RECORDKEEPING BURDEN AND COST
Estimated
number of
total
responses *
Estimated
number of
respondents
Form number/title
(and/or other collection instrument name)
Estimated
number of
burden hours
per response
Estimated
burden hours
(total
responses ×
number of
hours per
response)
Estimated
reporting and
recordkeeping
cost burden **
Current Rule Estimate of Annual Respondent Reporting and Recordkeeping Burden and Cost
Section 900.2 .......................................................................
Section 900.4 .......................................................................
5
5
5
10
1
5
5
50
$283
2,830
Total ..............................................................................
........................
15
........................
55
3,113
90
24
330
375
600
600
480
480
288
480
600
676
660
480
300
3
12
3
5,855
1,561
21,467
24,394
39,030
39,030
31,224
31,224
18,734
31,224
39,030
43,714
42,933
31,224
19,515
195
781
195
ddrumheller on DSK120RN23PROD with RULES2
Final Rule Estimate of Annual Respondent Reporting and Recordkeeping Burden and Cost
Initiation Request .................................................................
Initial Meeting .......................................................................
Resource Report 1: General project description .................
Resource Report 2: Water use and quality .........................
Resource Report 3: Fish, wildlife, and vegetation ...............
Resource Report 4: Cultural resources ...............................
Resource Report 5: Socioeconomics ..................................
Resource Report 6: Tribal interests .....................................
Resource Report 7: Communities of interest ......................
Resource Report 8: Geological resources and hazards .....
Resource Report 9: Soil resources .....................................
Resource Report 10: Land use, recreation and aesthetics
Resource Report 11: Air quality and noise effects ..............
Resource Report 12: Alternatives ........................................
Resource Report 13: Reliability, resilience, and safety .......
Review Meeting Request .....................................................
Review Meeting ...................................................................
Close-Out Meeting Request ................................................
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
PO 00000
Frm 00055
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
Fmt 4701
Sfmt 4700
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
E:\FR\FM\01MYR2.SGM
30
8
110
125
200
200
160
160
96
160
200
224
220
160
100
1
4
1
01MYR2
35366
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ESTIMATE OF ANNUAL RESPONDENT REPORTING AND RECORDKEEPING BURDEN AND COST—Continued
Estimated
number of
total
responses *
Estimated
number of
respondents
Form number/title
(and/or other collection instrument name)
Estimated
number of
burden hours
per response
Estimated
burden hours
(total
responses ×
number of
hours per
response)
Estimated
reporting and
recordkeeping
cost burden **
Close-Out Meeting ...............................................................
3
3
2
6
390
Total ..............................................................................
3
3
2,134
6,402
421,720
* One response per respondent.
** estimated cost based on median hourly wage for a project manager from https://www.bls.gov/oes/current/oes131111.htm ($45.81/hr) and
fully burdened scaling factor from https://www.bls.gov/regions/southwest/news-release/employercostsforemployeecompensation_regions.htm.
Notwithstanding any other provision
of the law, no person is required to
respond to, nor shall any person be
subject to a penalty for failure to comply
with, a collection of information subject
to the requirements of the PRA, unless
that collection of information displays a
currently valid OMB Control Number.
D. Review Under the National
Environmental Policy Act of 1969
DOE has analyzed this final rule in
accordance with NEPA and DOE’s
NEPA implementing regulations (10
CFR part 1021). DOE has determined
that this final rule is covered under the
categorical exclusion located at 10 CFR
part 1021, subpart D, appendix A,
Categorical Exclusion A5 because this
final rule revises existing regulations at
10 CFR part 900. The changes would
affect the process for the consideration
of future proposals for electricity
transmission, and potential
environmental impacts associated with
any particular proposal would be
analyzed pursuant to NEPA and other
applicable requirements. DOE has
considered whether this action would
result in extraordinary circumstances
that would warrant preparation of an
Environmental Assessment or EIS and
has determined that no such
extraordinary circumstances exist.
Therefore, DOE has determined that this
rulemaking does not require an
Environmental Assessment or an EIS.
ddrumheller on DSK120RN23PROD with RULES2
E. Review Under Executive Order 12988
With respect to the review of existing
regulations and the promulgation of
new regulations, Section 3(a) of E.O.
12988, ‘‘Civil Justice Reform,’’ 61 FR
4729 (Feb. 7, 1996), imposes on Federal
agencies the general duty to adhere to
the following requirements: (1)
eliminate drafting errors and ambiguity;
(2) write regulations to minimize
litigation; (3) provide a clear legal
standard for affected conduct rather
than a general standard; and (4) promote
simplification and burden reduction.
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
Section 3(b) of E.O. 12988 specifically
requires that agencies make every
reasonable effort to ensure that the
regulation: (1) clearly specifies the
preemptive effect, if any; (2) clearly
specifies any effect on existing Federal
law or regulation; (3) provides a clear
legal standard for affected conduct
while promoting simplification and
burden reduction; (4) specifies the
retroactive effect, if any; (5) adequately
defines key terms; (6) specifies whether
administrative proceedings are to be
required before parties may file suit in
court and, if so, describes those
proceedings and requires the exhaustion
of administrative remedies; and (7)
addresses other important issues
affecting clarity and general
draftsmanship under any guidelines
issued by the Attorney General. Section
3(c) of E.O. 12988 requires agencies to
review regulations in light of applicable
standards in section 3(a) and section
3(b) to determine whether they are met,
or it is unreasonable to meet one or
more of them. DOE has completed the
required review and determined that, to
the extent permitted by law, this final
rule meets the relevant standards of E.O.
12988.
F. Review Under Executive Order 13132
E.O. 13132, ‘‘Federalism’’, 64 FR
43255 (Aug. 10, 1999), imposes certain
requirements on agencies formulating
and implementing policies or
regulations that preempt State law or
that have federalism implications.
Agencies are required to examine the
constitutional and statutory authority
supporting any action that would limit
the policymaking discretion of the
States and carefully assess the necessity
for such actions. E.O. 13132 also
requires agencies to have an accountable
process to ensure meaningful and timely
input by State and local officials in the
development of regulatory policies that
have federalism implications. On March
14, 2000, DOE published a statement of
policy describing the intergovernmental
PO 00000
Frm 00056
Fmt 4701
Sfmt 4700
consultation process it will follow in the
development of such regulations (see 65
FR 13735). DOE has examined this
notice and has determined that this final
rule will not preempt State law and will
not have a substantial direct effect on
the States, the relationship between the
national government and the States, or
the distribution of power and
responsibilities among the various
levels of government. No further action
is required by E.O. 13132.
G. Review Under Executive Order 13175
Under E.O. 13175, ‘‘Consultation and
Coordination with Indian Tribal
Governments,’’ 65 FR 67249 (Nov. 6,
2000), DOE may not issue a
discretionary rule that has Tribal
implications or that imposes substantial
direct compliance costs on Indian Tribal
governments unless DOE provides funds
necessary to pay the costs of the Tribal
governments or consults with Tribal
officials before promulgating the rule.
This final rule aims to improve the
coordination of Federal authorizations
for proposed interstate electric
transmission facilities pursuant to the
FPA. Specifically, the amendments are
intended to refine the pre-application
procedures and result in more efficient
processing of applications. As a result,
the amendments to part 900 do not have
substantial direct effects on one or more
Indian Tribes, will not impose
substantial direct compliance costs on
Indian Tribal governments, and will not
preempt Tribal laws. Accordingly, the
funding and consultation requirements
of E.O. 13175 do not apply, and a Tribal
summary impact statement is not
required.
H. Review Under the Unfunded
Mandates Reform Act of 1995
Title II of the Unfunded Mandates
Reform Act (UMRA) of 1995 (Pub. L.
104–4) requires each Federal agency to
assess the effects of a Federal regulatory
action on State, local, and Tribal
governments, and the private sector.
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
(Pub. L. 104–4, sec. 201 (codified at 2
U.S.C. 1531)). For a regulatory action
likely to result in a rule that may cause
the expenditure by State, local, and
Tribal governments, in the aggregate, or
by the private sector of $100 million or
more in any one year (adjusted annually
for inflation), section 202 of UMRA
requires a Federal agency to publish a
written statement that estimates the
resulting costs, benefits, and other
effects on the national economy (2
U.S.C. 1532(a), (b)). UMRA also requires
a Federal agency to develop an effective
process to permit timely input by
elected officers of State, local, and
Tribal governments on a proposed
‘‘significant Federal intergovernmental
mandate,’’ and requires an agency plan
for giving notice and opportunity for
timely input to potentially affected
small governments before establishing
any requirements that might
significantly or uniquely affect them. On
March 18, 1997, DOE published a
statement of policy on its process for
intergovernmental consultation under
UMRA (see 62 FR 12820) (This policy
is also available at: www.energy.gov/gc/
guidance-opinions). DOE examined this
final rule according to UMRA and its
statement of policy and has determined
that the rule contains neither an
intergovernmental mandate, nor a
mandate that may result in the
expenditure by State, local, and Tribal
governments, in the aggregate, or by the
private sector, of $100 million or more
in any year. Accordingly, no further
assessment or analysis is required under
UMRA.
ddrumheller on DSK120RN23PROD with RULES2
I. Review Under Executive Order 12630
DOE has determined, under E.O.
12630, ‘‘Governmental Actions and
Interference with Constitutionally
Protected Property Rights,’’ 53 FR 8859
(March 18, 1988), that this this final rule
would not result in any takings that
might require compensation under the
Fifth Amendment to the U.S.
Constitution.
J. Review Under Executive Order 13211
E.O. 13211, ‘‘Actions Concerning
Regulations That Significantly Affect
Energy Supply, Distribution, or Use,’’ 66
FR 28355 (May 22, 2001), requires
Federal agencies to prepare and submit
to the OMB a Statement of Energy
Effects for any proposed significant
energy action. A ‘‘significant energy
action’’ is defined as any action by an
agency that promulgated or is expected
to lead to promulgation of a final rule,
and that: (1)(i) is a significant regulatory
action under E.O. 12866, or any
successor order; and (ii) is likely to have
a significant adverse effect on the
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
supply, distribution, or use of energy, or
(2) is designated by the Administrator of
OIRA as a significant energy action. For
any proposed significant energy action,
the agency must give a detailed
statement of any adverse effects on
energy supply, distribution, or use
should the proposal be implemented,
and of reasonable alternatives to the
action and their expected benefits on
energy supply, distribution, and use.
This final rule is intended to improve
the pre-application procedures for
certain transmission projects, and
therefore result in the more efficient
processing of applications, and thus this
final rule will not have a significant
adverse effect on the supply,
distribution, or use of energy and is
therefore not a significant energy action.
Accordingly, DOE has not prepared a
Statement of Energy Effects.
K. Review Under the Treasury and
General Government Appropriations
Act, 1999
Section 654 of the Treasury and
General Government Appropriations
Act, 1999 (Pub. L. 105–277) requires
Federal agencies to issue a Family
Policymaking Assessment for any rule
that may affect family well-being. This
final rule would not have any impact on
the autonomy or integrity of the family
as an institution. Accordingly, DOE has
concluded that it is not necessary to
prepare a Family Policymaking
Assessment.
L. Review Under the Treasury and
General Government Appropriations
Act, 2001
The Treasury and General
Government Appropriations Act, 2001
(44 U.S.C. 3516 note) provides for
Federal agencies to review most
disseminations of information to the
public under guidelines established by
each agency pursuant to general
guidelines issued by OMB. OMB’s
guidelines were published at 67 FR
8452 (Feb. 22, 2002), and DOE’s
guidelines were published at 67 FR
62446 (Oct. 7, 2002).
DOE has reviewed this final rule
under the OMB and DOE guidelines and
has concluded that it is consistent with
applicable policies in those guidelines.
IX. Congressional Notification
As required by 5 U.S.C. 801, DOE will
report to Congress on the promulgation
of this rule before its effective date. The
report will state that the Office of
Information and Regulatory Affairs has
determined that the rule does not meet
the criteria set forth in 5 U.S.C. 804(2).
PO 00000
Frm 00057
Fmt 4701
Sfmt 4700
35367
X. Rehearing
This rule is a final order subject to
section 313 of the FPA (16 U.S.C. 825l).
Accordingly, any party seeking judicial
review of this rule must first seek
rehearing before the Department. A
request for rehearing must be submitted
in accordance with the FOR FURTHER
INFORMATION CONTACT portion of this
rule, within 30 days of the issuance of
this rule. A request must concisely state
the alleged errors in the final rule and
must list each issue in a separately
enumerated paragraph; any issue not so
listed will be deemed waived.
XI. Approval by the Office of the
Secretary of Energy
The Secretary of Energy has approved
publication of this final rule.
List of Subjects in 10 CFR Part 900
Electric power, Electric utilities,
Energy, Reporting and recordkeeping
requirements.
Signing Authority
This document of the DOE was signed
on April 11, 2024, by Maria D.
Robinson, Director, Grid Deployment
Office, pursuant to delegated authority
from the Secretary of Energy. That
document with the original signature
and date is maintained by DOE. For
administrative purposes only, and in
compliance with requirements of the
Office of the Federal Register, the
undersigned DOE Federal Register
Liaison Officer has been authorized to
sign and submit the document in
electronic format for publication, as an
official document of the Department of
Energy. This administrative process in
no way alters the legal effect of this
document upon publication in the
Federal Register.
Signed in Washington, DC, on April 12,
2024.
Treena V. Garrett,
Federal Register Liaison Officer, U.S.
Department of Energy.
For the reasons stated in the preamble,
the Department of Energy revises 10
CFR part 900 to read as follows:
■
PART 900—COORDINATION OF
FEDERAL AUTHORIZATIONS FOR
ELECTRIC TRANSMISSION FACILITIES
Sec.
900.1 Purpose and scope.
900.2 Definitions.
900.3 Applicability to other projects.
900.4 Purpose and scope of IIP Process.
900.5 Initiation of IIP Process.
900.6 Project proponent resource reports.
900.7 Standard and project-specific
schedules.
900.8 IIP Process review meeting.
E:\FR\FM\01MYR2.SGM
01MYR2
35368
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
900.9 IIP Process close-out meeting.
900.10 Consolidated administrative docket.
900.11 NEPA lead agency and selection of
NEPA joint lead agency.
900.12 Environmental review.
900.13 Severability.
Authority: 16 U.S.C. 824p(h).
ddrumheller on DSK120RN23PROD with RULES2
§ 900.1
Purpose and scope.
(a) Pursuant to section 216(h) of the
Federal Power Act (16 U.S.C. 824p(h)),
the Department of Energy (DOE)
establishes the Coordinated Interagency
Transmission Authorizations and
Permits Program (CITAP Program)
under this part to coordinate the review
and processes related to Federal
authorizations necessary to site a
proposed electric transmission facility.
Pursuant to section 216(h)(4)(A), this
part establishes the mechanism by
which DOE will set prompt and binding
intermediate milestones and ultimate
deadlines for the processes related to
deciding whether to issue such
authorizations. In addition, as the lead
agency and in collaboration with any
National Environmental Policy Act
(NEPA) joint lead agency and in
consultation with the relevant Federal
entities, as applicable, DOE will prepare
a single environmental review
document, which will be designed to
serve the needs of all relevant Federal
agencies and inform all Federal
authorization decisions on the proposed
electric transmission project.
(b) This part provides a process for
the timely submission of information
needed for Federal decisions related to
authorizations for siting proposed
electric transmission projects. This part
seeks to ensure that these projects are
developed consistent with the nation’s
environmental laws, including laws that
address endangered and threatened
species, critical habitats, and cultural
and historic properties. This part
provides a framework, called the
Integrated Interagency Pre-Application
(IIP) Process, by which DOE will
coordinate submission of materials
necessary for Federal authorizations and
related environmental reviews required
under Federal law to site proposed
electric transmission facilities, and
integrates the IIP Process into the CITAP
Program.
(c) This part describes the timing and
procedures for the IIP Process, which
should be initiated prior to a project
proponent’s submission of any
application for a required Federal
authorization. The IIP Process provides
for timely and focused pre-application
meetings with relevant Federal and nonFederal entities. In addition, the IIP
Process facilitates early identification of
potential siting constraints and
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
opportunities. The IIP Process promotes
thorough and consistent stakeholder
engagement by a project proponent. At
the close-out of each IIP Process, DOE
will establish the schedule for all
Federal reviews and authorizations
required to site a proposed electric
transmission facility, in coordination
with the relevant Federal entities.
(d) This part improves the Federal
permitting process by facilitating the
early submission, compilation, and
documentation of information needed
for coordinated review by relevant
Federal entities under the National
Environmental Policy Act (42 U.S.C.
4321 et seq.). This part also facilitates
expeditious action on necessary Federal
authorizations by ensuring that relevant
Federal entities coordinate their
consideration of those applications and
by providing non-Federal entities the
opportunity to coordinate their nonFederal permitting and environmental
reviews with the reviews of the relevant
Federal entities.
(e) This part facilitates improved and
earlier coordination of and consultation
between relevant Federal entities,
relevant non-Federal entities, and others
pursuant to section 106 of the National
Historic Preservation Act (54 U.S.C.
306108) (NHPA) and its implementing
regulations found at 36 CFR part 800.
Under this part, DOE may determine it
has an undertaking with the potential to
affect historic properties and may, at
that time, authorize a project proponent,
as a CITAP applicant, to initiate section
106 consultation for the undertaking
consistent with 36 CFR 800.2(c)(4). Prior
to that determination, this part requires
project proponents to gather initial
information and make recommendations
relevant to the section 106 process to
the extent possible. This part also
establishes DOE as lead for the section
106 process, consistent with DOE’s role
as lead or joint lead agency for purposes
of NEPA, in order to maximize
opportunities for coordination between
the NEPA and section 106 processes.
Federal entities remain responsible for
government-to-government consultation
with Indian Tribes (and government-tosovereign consultation in the context of
Native Hawaiian relations) and for any
findings and determinations required by
and reserved to Federal agencies in 36
CFR part 800.
(f) This part applies only to qualifying
projects as defined by § 900.2.
(g) Participation in the IIP Process
does not alter any requirements to
obtain necessary Federal authorizations
for proposed electric transmission
projects. Nor does this part alter any
responsibilities of the relevant Federal
PO 00000
Frm 00058
Fmt 4701
Sfmt 4700
entities for environmental review or
consultation under applicable law.
(h) The Director may waive any
requirement imposed on a project
proponent under this part if, in the
Director’s discretion, the Director
determines that the requirement is
unnecessary, duplicative, or
impracticable under the circumstances
relevant to the proposed electric
transmission project. Where the
principal project developer is itself a
Federal entity that would be otherwise
expected to prepare an environmental
review document for the project, the
Director shall consider modifications to
the requirements under this part as may
be necessary under the circumstances.
§ 900.2
Definitions.
As used in this part:
Analysis area means a geographical
area established for a resource report at
the IIP Process initial meeting and
modified at the IIP Process review
meeting, if applicable.
Authorization means any license,
permit, approval, finding,
determination, or other administrative
decision required under Federal, Tribal,
State, or local law to site a proposed
electric transmission facility, including
special use authorization, certifications,
opinions, or other approvals.
Communities of Interest means the
following communities that could be
affected by a proposed electric
transmission project: disadvantaged
communities; rural communities; Tribal
communities; indigenous communities;
geographically proximate communities;
communities with environmental justice
concerns; and energy communities.
Director means the Director of the
DOE Grid Deployment Office, that
person’s delegate, or another DOE
official designated to perform the
functions of this part by the Secretary of
Energy.
Federal authorization means any
authorization required under Federal
law.
Federal entity means any Federal
agency or department.
Indian Tribe has the same meaning as
provided by 25 U.S.C. 5304(e).
Mitigation approach means an
approach that applies a conceptual plan
to identify appropriate measures to
avoid, minimize, or compensate for
potential impacts to resources from a
proposed electric transmission project,
consistent with 40 CFR 1508.1(s) or any
successor regulation. A mitigation
approach identifies the needs and
baseline conditions of targeted
resources, potential impacts from the
proposed project, cumulative impacts of
past and reasonably foreseeable future
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
disturbances to those resources, and
future disturbance trends, then uses this
information to identify priorities for
measures across the relevant area. Such
an approach includes full consideration
of the conditions of additionality
(meaning that the benefits of a
compensatory mitigation measure
improve upon the baseline conditions in
a manner that is demonstrably new and
would not have occurred without the
mitigation measure) and durability
(meaning that the effectiveness of a
mitigation measure is sustained for the
duration of the associated direct and
indirect impacts).
MOU signatory agency means a
Federal entity that has entered into the
currently effective memorandum of
understanding (MOU) under section
216(h)(7)(B)(i) of the Federal Power Act,
such as the interagency MOU executed
in May 2023, titled ‘‘Memorandum of
Understanding among the U.S.
Department of Agriculture, Department
of Commerce, Department of Defense,
Department of Energy, the
Environmental Protection Agency, the
Council on Environmental Quality, the
Federal Permitting Improvement
Steering Council, Department of the
Interior, and the Office of Management
and Budget Regarding Facilitating
Federal Authorizations for Electric
Transmission Facilities.’’
NEPA joint lead agency means the
Federal entity designated under
§ 900.11.
Non-Federal entity means an Indian
Tribe, multi-State governmental entity,
State agency, or local government
agency.
Participating agencies means:
(1) The Department of Agriculture
(USDA);
(2) The Department of Commerce;
(3) The Department of Defense (DOD);
(4) The Department of Energy;
(5) The Environmental Protection
Agency (EPA);
(6) The Council on Environmental
Quality;
(7) The Office of Management and
Budget;
(8) The Department of the Interior
(DOI);
(9) The Federal Permitting
Improvement Steering Council (FPISC);
(10) Other agencies and offices as the
Secretary of Energy may from time to
time invite to participate; and
(11) The following independent
agencies, to the extent consistent with
their statutory authority and obligations,
and determined by the chair or
executive director of each agency, as
appropriate:
(i) The Federal Energy Regulatory
Commission (FERC); and
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
(ii) The Advisory Council on Historic
Preservation.
Potentially affected landowner means
an owner of a real property interest that
is potentially affected directly (e.g.,
crossed or used) or indirectly (e.g.,
changed in use) by a project right-ofway, potential route, or proposed
ancillary or access site, as identified in
§ 900.6.
Project area means the area located
between the two end points of the
proposed electric transmission facility
containing the study corridors selected
by the project proponent for in-depth
consideration for the proposed project
and the immediate surroundings of the
end points of the proposed facility. The
project area does not necessarily
coincide with ‘‘permit area,’’ ‘‘area of
potential effect,’’ ‘‘action area,’’ or other
terms specific to a certain type of
regulatory review.
Project proponent means a person or
entity who initiates the IIP Process in
anticipation of seeking a Federal
authorization for a proposed electric
transmission project.
Qualifying project means:
(1) A proposed electric transmission
line and its attendant facilities:
(i) That will either be a high-voltage
(230 kV or above) line or a regionally or
nationally significant line, as
determined by DOE based upon relevant
factors, including but not limited to,
reduction in congestion costs for
generating and delivering energy,
mitigation of weather and variable
generation uncertainty, and enhanced
diversity of supply;
(ii) Which is expected to be used, in
whole or in part, for the transmission of
electric energy in interstate or
international commerce for sale at
wholesale;
(iii) Which is expected to require
preparation of an environmental impact
statement (EIS) pursuant to NEPA to
inform an agency decision on a Federal
authorization;
(iv) Which is not proposed for
authorization under section 8(p) of the
Outer Continental Shelf Lands Act (43
U.S.C. 1337(p));
(v) Which is not seeking a
construction or modification permit
from FERC pursuant to section 216(b) of
the Federal Power Act (16 U.S.C.
824p(b)); and
(vi) Which will not be wholly located
within the Electric Reliability Council of
Texas interconnection; or
(2) Any other proposed electric
transmission facility that is approved by
the Director under the process set out in
§ 900.3.
Relevant Federal entity means a
Federal entity with jurisdictional
PO 00000
Frm 00059
Fmt 4701
Sfmt 4700
35369
interests that may have an effect on a
proposed electric transmission project,
that is responsible for issuing a Federal
authorization for the proposed project,
that has relevant expertise with respect
to environmental and other issues
pertinent to or potentially affected by
the proposed project, or that provides
funding for the proposed project. The
term includes participating agencies.
The term includes a Federal entity with
either permitting or non-permitting
authority; for example, those entities
with which consultation or review must
be completed before a project may
commence, such as DOD for an
examination of military test, training, or
operational impacts.
Relevant non-Federal entity means a
non-Federal entity with relevant
expertise or jurisdiction within the
project area, that is responsible for
issuing an authorization for the
proposed electric transmission project,
that has relevant expertise with respect
to environmental and other issues
pertinent to or potentially affected by
the proposed project, or that provides
funding for the proposed project. The
term includes an entity with either
permitting or non-permitting authority,
such as an Indian Tribe, Native
Hawaiian Organization, or State or
Tribal Historic Preservation Office with
whom consultation must be completed
in accordance with section 106 of the
NHPA prior to approval of a permit,
right-of-way, or other authorization
required for a Federal authorization.
Route means an area along a linear
path within which a proposed electric
transmission facility could be sited that
is:
(1) Wide enough to allow minor
adjustments in the alignment of the
proposed facility to avoid sensitive
features or to accommodate potential
engineering constraints; and
(2) Narrow enough to allow detailed
study.
Stakeholder means any relevant nonFederal entity, interested nongovernmental organization, potentially
affected landowner, or other interested
person or organization.
Study corridor means a contiguous
area (not to exceed one mile in width)
within the project area where potential
routes or route segments may be
considered for further study. A study
corridor does not necessarily coincide
with ‘‘permit area,’’ ‘‘area of potential
effect,’’ ‘‘action area,’’ or other defined
terms of art that are specific to types of
regulatory review.
§ 900.3
Applicability to other projects.
(a) Following the procedures set out
in this section, the Director may
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
35370
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
determine that a proposed electric
transmission facility that does not meet
the description of a qualifying project
under paragraph (1) of the definition in
§ 900.2 is a qualifying project under
paragraph (2) of the definition.
(b) A requestor seeking DOE
assistance under this part for a proposed
electric transmission facility that does
not meet the description of a qualifying
project under paragraph (1) of the
definition in § 900.2 must file a request
for coordination with the Director. The
request must contain:
(1) The legal name of the requester; its
principal place of business; and the
name, title, and mailing address of the
person or persons to whom
communications concerning the request
for coordination are to be addressed;
(2) A concise description of the
proposed facility sufficient to explain its
scope and purpose;
(3) A list of anticipated relevant
Federal entities involved in the
proposed facility; and
(4) A list of anticipated relevant nonFederal entities involved in the
proposed facility, including any agency
serial or docket numbers for pending
applications.
(c) Not later than 30 calendar days
after the date that the Director receives
a request under this section, the
Director, in consultation with the
relevant Federal entities, will determine
if the proposed electric transmission
facility is a qualifying project under this
part and will notify the project
proponent in writing of one of the
following:
(1) If accepted, that the proposed
facility is a qualifying project and the
project proponent must submit an
initiation request as set forth under
§ 900.5; or
(2) If not accepted, that the proposed
facility is not a qualifying project, a
justification of that determination, and
an indication that the project proponent
must follow the procedures of each
relevant Federal entity that has
jurisdiction over the proposed facility
without DOE performing a coordinating
function.
(d) In making the determination
whether a proposed electric
transmission facility is a qualifying
project, the Director may consider:
(1) Whether the proposed facility
would benefit from CITAP Program
coordination;
(2) Whether the proposed facility
would result in reduced congestion
costs for generating and delivering
energy;
(3) Whether the proposed facility
would result in mitigation of weather
and variable generation uncertainty;
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
(4) Whether the proposed facility
would result in an enhanced diversity of
supply; and
(5) Any other relevant factors, as
determined by the Director.
(e) For a proposed facility that is
seeking a construction or modification
permit pursuant to section 216(b) of the
Federal Power Act, DOE may only
consider a request for assistance under
this section if the request under
paragraph (b) of this section is
consistent with Delegation Order No.
S1–DEL–FERC–2006 or any similar,
subsequent delegation that the Secretary
may order.
(f) At the discretion of the MOU
signatory agencies, this section may be
applied to a proposed electric
transmission facility proposed for
authorization under section 8(p) of the
Outer Continental Shelf Lands Act, if
the proposed authorization is
independent of any generation project.
(g) This section does not apply to:
(1) A proposed electric transmission
facility proposed to be authorized under
section 8(p) of the Outer Continental
Shelf Lands Act in conjunction with a
generation project; or
(2) A proposed electric transmission
facility wholly located within the
Electric Reliability Council of Texas
interconnection.
§ 900.4
Purpose and scope of IIP Process.
(a) The Integrated Interagency PreApplication (IIP) Process is intended for
a project proponent who has identified
potential study corridors or potential
routes and the proposed locations of any
intermediate substations for a proposed
electric transmission project. To the
extent possible, the project proponent
should use the following criteria to
identify potential study corridors and
potential routes:
(1) Potential environmental, visual,
historic, cultural, economic, social, or
health effects or harm based on the
proposed project or proposed siting, and
anticipated constraints (for instance,
pole height and corridor width based on
line capacity to improve safety and
resiliency of the project);
(2) Potential cultural resources, sacred
sites, and historic properties that may be
eligible for or listed in the National
Register of Historic Places;
(3) Areas under (or potentially under)
special protection by State or Federal
statute and areas subject to a Federal
entity or non-Federal entity decision
that could potentially increase the time
needed for project evaluation and siting
a transmission line route. Such areas
may include, but are not limited to,
properties or sites that may be of
traditional religious or cultural
PO 00000
Frm 00060
Fmt 4701
Sfmt 4700
importance to Indian Tribes, National
Scenic and Historic Trails, National
Landscape Conservation System units
managed by the Bureau of Land
Management (BLM), Land and Water
Conservation Fund lands, National
Wildlife Refuges, national monuments,
National Historic Landmarks, units of
the National Park System, national
marine sanctuaries, and marine national
monuments;
(4) Opportunities to site potential
routes through designated corridors,
previously disturbed lands, and lands
with existing infrastructure as a means
of potentially reducing impacts and
known conflicts as well as the time
needed for affected Federal land
managers to evaluate an application for
a Federal authorization if the route is
sited through such areas (e.g., colocation
with existing infrastructure or location
on previously disturbed lands, in energy
corridors designated by the Department
of the Interior or the Department of
Agriculture under section 503 of the
Federal Land Policy and Management
Act (Pub. L. 94–579) or section 368 of
the Energy Policy Act of 2005 (Pub. L.
109–58), existing rights-of-way, National
Interest Electric Transmission Corridors
designated under Federal Power Act
section 216(a), or utility corridors
identified in a land management plan);
(5) Potential constraints caused by
impacts on military test, training, and
operational missions, including impacts
on installations, ranges, and airspace;
(6) Potential constraints caused by
impacts on the United States’ aviation
system;
(7) Potential constraints caused by
impacts to navigable waters of the
United States; and
(8) Potential avoidance, minimization,
offsetting, and compensatory (onsite and
offsite) measures, developed through a
mitigation approach to reduce or offset
the potential impact of the proposed
project to resources requiring
mitigation.
(b) Participation in the IIP Process is
a prerequisite for the coordination
provided by DOE between relevant
Federal entities, relevant non-Federal
entities, and the project proponent.
(c) The IIP Process ensures early
interaction between the project
proponents, relevant Federal entities,
and relevant non-Federal entities to
enhance early understanding by those
entities. Through the IIP Process, the
project proponent will provide relevant
Federal entities and relevant nonFederal entities with a clear description
of the proposed electric transmission
project, the project proponent’s siting
process, and the environmental and
community setting being considered by
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
the project proponent for siting the
proposed electric transmission facility;
and will coordinate with relevant
Federal entities to develop resource
reports that will serve as inputs, as
appropriate, into the relevant Federal
analyses and facilitate early
identification of project issues.
(d) The IIP Process is an iterative
process anchored by three meetings: the
initial meeting, review meeting, and
close-out meeting. These meetings,
defined in §§ 900.5, 900.8 and 900.9, are
milestones in the process and do not
preclude any additional meetings or
communications between the project
proponent and the relevant Federal
entities. The iterative nature of the
process is provided for in procedures for
evaluating the completeness of
submitted materials and the suitability
of materials for the relevant Federal
entities’ decision-making before each
milestone.
(e) DOE, in exercising its
responsibilities under this part, will
communicate regularly with FERC,
electric reliability organizations and
electric transmission organizations
approved by FERC, relevant Federal
entities, and project proponents. DOE
will use information technologies to
provide opportunities for relevant
Federal entities to participate remotely.
(f) DOE, in exercising its
responsibilities under this part, will to
the maximum extent practicable and
consistent with Federal law, coordinate
the IIP Process with any relevant nonFederal entities. DOE will use
information technologies to provide
opportunities and reduce burdens for
relevant non-Federal entities to
participate remotely.
(g) The Director may at any time
require the project proponent to provide
additional information necessary to
resolve issues raised by the IIP Process.
(h) Pursuant to 10 CFR 1004.11, any
person submitting information during
the IIP Process that the person believes
to be confidential and exempt by law
from public disclosure should submit
two well-marked copies, one marked
‘‘confidential’’ that includes all the
information believed to be confidential,
and one marked ‘‘non-confidential’’
with the information believed to be
confidential deleted or redacted. DOE
will make its own determination about
the confidential status of the
information and treat it according to its
determination, in accordance with
applicable law. The project proponent
must request confidential treatment for
all material filed with DOE containing
non-public location, character, and
ownership information about cultural
resources.
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
(i) Pursuant to 10 CFR 1004.13, any
person submitting information during
the IIP Process that the person believes
might contain Critical Electric
Infrastructure Information (CEII) should
submit a request for CEII designation of
information.
§ 900.5
Initiation of IIP Process.
(a) Initiation request. A project
proponent shall submit an initiation
request to DOE. The project proponent
may decide when to submit the
initiation request. The initiation request
must include, based on best available
information:
(1) A summary of the proposed
electric transmission project, as
described by paragraph (b) of this
section;
(2) Associated maps, geospatial
information, and studies (provided in
electronic format), as described by
paragraph (c) of this section;
(3) A project participation plan, as
described by paragraph (d) of this
section; and
(4) A statement regarding the
proposed project’s status pursuant to
Title 41 of the Fixing America’s Surface
Transportation Act (FAST–41) (42
U.S.C. 4370m–2(b)(2)), as described by
paragraph (e) of this section.
(b) Summary of the proposed project.
The summary of the proposed electric
transmission project may not exceed 10
single-spaced pages unless the project
proponent requests a waiver of the page
limit, including a rationale for the
waiver, and DOE grants the waiver. The
summary must include:
(1) The following information:
(i) The project proponent’s legal name
and principal place of business;
(ii) The project proponent’s contact
information and designated point(s) of
contact;
(iii) Whether the project proponent is
an individual, partnership, corporation,
or other entity and, if applicable, the
State laws under which the project
proponent is organized or authorized;
and
(iv) If the project proponent resides or
has its principal office outside the
United States, documentation related to
designation by irrevocable power of
attorney of an agent residing within the
United States;
(2) A statement of the project
proponent’s interests and objectives;
(3) To the extent available, copies of
or links to:
(i) Any regional electric transmission
planning documents, regional reliability
studies, regional congestion or other
related studies that relate to the
proposed project or the need for the
proposed project; and
PO 00000
Frm 00061
Fmt 4701
Sfmt 4700
35371
(ii) Any relevant interconnection
requests;
(4) A description of potential study
corridors and routes identified by the
project proponent and a brief
description of the evaluation criteria
and methods used by the project
proponent to identify and develop those
corridors and routes;
(5) A brief description of the proposed
project, including end points, voltage,
ownership, intermediate substations if
applicable, and, to the extent known,
any information about constraints or
flexibility with respect to the proposed
project;
(6) Identification of any
environmental and engineering firms
and sub-contractors under contract to
develop the proposed project;
(7) The project proponent’s proposed
schedule for filing necessary Federal
and State applications, construction
start date, and planned in-service date,
assuming receipt of all necessary
authorizations; and
(8) A list of anticipated relevant
Federal entities and relevant nonFederal entities, including contact
information for each Federal agency,
State agency, Indian Tribe, or multiState entity that is responsible for or has
a role in issuing an authorization or
environmental review for the proposed
project.
(c) Maps, geospatial information, and
studies. The initiation request must
include maps, geospatial information,
and studies in support of the
information provided in the summary of
the proposed project under paragraph
(b) of this section. Maps must be of
sufficient detail to identify the study
corridors and potential routes. Project
proponents must provide the maps,
information, and studies as electronic
data files that may be readily accessed
by relevant Federal entities and relevant
non-Federal entities. The maps,
information, and studies described in
this paragraph (c) must include:
(1) Location maps and plot plans to
scale showing all major components,
including a description of zoning and
site availability for any permanent
facilities; cultural resource location
information in these materials should be
submitted in accordance with
§ 900.4(h);
(2) A map of the project area showing
potential study corridors and potential
routes;
(3) Existing data or studies relevant to
the summary of the proposed project;
and
(4) Citations identifying sources, data,
and analyses used to develop the
summary of the proposed project.
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
35372
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
(d) Project participation plan. The
project participation plan, which may
not exceed 10, single-spaced pages,
summarizes the outreach that the
project proponent conducted prior to
submission of the initiation request, and
describes the project proponent’s
planned outreach to communities of
interest going forward. A supplemental
appendix may be submitted to provide
sufficient detail in addition to the
narrative elements. The project
participation plan must include:
(1) A summary of prior outreach to
communities of interest and
stakeholders including:
(i) A description of what work already
has been done, including stakeholder
and community outreach and public
engagement, as well as any entities and
organizations interested in the proposed
electric transmission project;
(ii) A list of environmental,
engineering, public affairs, other
contractors or consultants employed by
the proponent to facilitate public
outreach;
(iii) A description of any materials
provided to the public, such as
environmental surveys or studies;
(iv) A description of the communities
of interest identified and the process by
which they were identified;
(v) A general description of the real
property interests that would be
impacted by the proposed project and
the rights that the owners of those
property interests would have under
State law; and
(vi) A summary of comments received
during these previous engagement
activities, issues identified by
stakeholders, communities of interest
(including various resource issues,
differing project alternative study
corridors or routes, and revisions to
routes), and responses provided to
commenters, if applicable; and
(2) A public engagement plan, which
must:
(i) Describe the project proponent’s
outreach plan and status of those
activities, including planned future
activities corresponding to each of the
items or issues identified in paragraphs
(d)(1)(i) through (vi) of this section,
specifying the planned dates or
frequency;
(ii) Describe the manner in which the
project proponent will reach out to
communities of interest about potential
mitigation of concerns;
(iii) Describe planned outreach
activities during the permitting process,
including efforts to identify, and engage,
individuals with limited English
proficiency and linguistically isolated
communities, and provide
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
accommodations for individuals with
accessibility needs; and
(iv) Discuss the specific tools and
actions used by the project proponent to
facilitate public communications and
public information, including whether
the project proponent will have a
readily accessible, easily identifiable,
single point of contact.
(e) FAST–41 statement. The FAST–41
statement required under paragraph (a)
of this section must specify the status of
the proposed electric transmission
project pursuant to FAST–41 at the time
of submission of the initiation request.
The statement must either:
(1) State that the project proponent
has sought FAST–41 coverage pursuant
to 42 U.S.C. 4370m–2(a)(1); and state
whether the Executive Director of the
FPISC has created an entry on the
Permitting Dashboard for the project as
a covered project pursuant to 42 U.S.C.
4370m–2(b)(2)(A); or
(2) State that the project proponent
elected not to apply to be a FAST–41
covered project at this time.
(f) Initiation request determination.
Not later than 20 calendar days after the
date that DOE receives an initiation
request, DOE shall:
(1) Determine whether the initiation
request meets the requirements of this
section and, if not previously
determined under § 900.3, whether the
proposed electric transmission facility is
a qualifying project;
(2) Identify the relevant Federal
entities and relevant non-Federal
entities and provide each with an
electronic copy of the initiation request;
and
(3) Give notice to the project
proponent and relevant Federal and
non-Federal entities of DOE’s
determinations under paragraph (f)(1) of
this section.
(g) Deficiencies. If DOE determines
under paragraph (f)(1) of this section
that the initiation request does not meet
the requirements of this section, DOE
must provide the reasons for that
finding and a description of how the
project proponent may, if applicable,
address any deficiencies in the
initiation request so that DOE may
reconsider its determination. If DOE
determines under paragraph (f)(1) of this
section that the proposed electric
transmission facility is not a qualifying
project, DOE must provide a
justification for the determination and
the project proponent may file a request
for coordination with the Director as
provided in § 900.3. A project to site a
proposed electric transmission facility
that is not a qualifying project is not
eligible for participation in the IIP
Process.
PO 00000
Frm 00062
Fmt 4701
Sfmt 4700
(h) Initial meeting. If a project
proponent submits a valid initiation
request, DOE, in consultation with the
identified relevant Federal entities, shall
convene the IIP Process initial meeting
with the project proponent and all
relevant Federal entities notified by
DOE under paragraph (f) of this section
as soon as practicable and no later than
15 calendar days after the date that DOE
provides notice under paragraph (f) that
the initiation request meets the
requirements of this section. DOE shall
also invite relevant non-Federal entities
to participate in the initial meeting.
During the initial meeting:
(1) DOE and the relevant Federal
entities shall discuss with the project
proponent the IIP Process, Federal
authorization process, related
environmental reviews, any
arrangements for the project proponent
to contribute funds to DOE to cover
costs incurred by DOE and the relevant
Federal entities in the IIP Process (in
accordance with 42 U.S.C. 7278), any
requirements for entering into cost
recovery agreements, and paying for
third-party contractors under DOE’s
supervision, where applicable;
(2) DOE will identify any Federal
applications that must be submitted
during the IIP Process, to enable
relevant Federal entities to begin work
on the review process, and those
applications that will be submitted after
the IIP Process. All application
submittal timelines will be accounted
for in the project-specific schedule
described in § 900.7;
(3) DOE will establish all analysis
areas necessary for the completion of
resource reports required under § 900.6;
(4) The project proponent shall
describe the proposed electric
transmission project and the contents of
the initiation request;
(5) DOE and the relevant Federal
entities, along with any relevant nonFederal entities who choose to
participate, will review the information
provided by the project proponent and
publicly available information, discuss
the study corridors and potential routes
identified by the project proponent,
discuss the evaluation criteria and
methods used to identify those corridors
and routes and, to the extent possible
and based on agency expertise and
experience, identify any additional
criteria for adding or modifying
potential routes and study corridors;
(6) DOE and the relevant Federal
entities will discuss, based on available
information provided by the project
proponent, any surveys and studies that
may be required for potential routes and
completion of the resource reports,
including biological (including
E:\FR\FM\01MYR2.SGM
01MYR2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
threatened and endangered species or
avian, aquatic, and terrestrial species
and aquatic habitats of concern), visual,
cultural, economic, social, health, and
historic surveys and studies.
(i) Feedback to project proponent.
Feedback provided to the project
proponent under paragraph (h) of this
section does not constitute a
commitment by any relevant Federal
entity to approve or deny a Federal
authorization request, nor does the IIP
Process limit agency discretion
regarding NEPA review.
(j) Draft initial meeting summary. Not
later than 10 calendar days after the
initial meeting, DOE shall:
(1) Prepare a draft initial meeting
summary that includes a summary of
the meeting discussion, a description of
key issues and information gaps
identified during the meeting, and any
requests for more information from
relevant Federal entities and relevant
non-Federal entities; and
(2) Convey the draft summary to the
project proponent, relevant Federal
entities, and any relevant non-Federal
entities that participated in the meeting.
(k) Corrections. The project proponent
and entities that received the draft
initial meeting summary under
paragraph (j) of this section will have 10
calendar days following receipt of the
draft initial meeting summary to review
the draft and provide corrections to
DOE.
(l) Final summary. Not later than 10
calendar days following the close of the
10-day review period under paragraph
(k) of this section, DOE shall:
(1) Prepare a final initial meeting
summary by incorporating received
corrections, as appropriate;
(2) Add the final summary to the
consolidated administrative docket
described by § 900.10; and
(3) Provide an electronic copy of the
summary to all relevant Federal entities,
relevant non-Federal entities, and the
project proponent.
ddrumheller on DSK120RN23PROD with RULES2
§ 900.6 Project proponent resource
reports.
(a) Preparation and submission. The
project proponent shall prepare and
submit to DOE the 13 project proponent
resource reports described in this
section. The project proponent may
submit the resource reports at any time
before requesting a review meeting
under § 900.8 and shall, at the direction
of DOE, revise resource reports in
response to comments received from
relevant Federal entities and relevant
non-Federal entities during the
Integrated Interagency Pre-Application
(IIP) Process.
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
(b) Content. Each resource report must
include concise descriptions, based on
the best available scientific and
commercial information, of the known
existing environment and major site
conditions. The detail of each resource
report must be commensurate with the
complexity of the proposal and its
potential for environmental impacts.
Each topic in each resource report must
be addressed or its omission justified. If
any resource report topic is not
addressed at the time the applicable
resource report is filed or its omission
is not addressed, the report must
explain why the topic is missing. If
material required for one resource report
is provided in another resource report or
in another exhibit, it may be
incorporated by reference. If outside
material is reasonably available for
review and comment, a resource report
may incorporate that material by
reference by including a citation to the
material and a brief summary of the
material. Consistent with §§ 900.1(h)
and 900.4(g), the Director may modify
the requirements of this section to
reflect differences in onshore and
offshore environments and uses.
(c) Requirements for IIP Process
progression. Failure of the project
proponent to provide at least the
required initial or revised content will
prevent progress through the IIP Process
to the IIP Process review or close-out
meetings, unless the Director
determines that the project proponent
has provided an acceptable reason for
the item’s absence and an acceptable
timeline for filing it. Failure to file
within the accepted timeline will
prevent further progress in the IIP
Process.
(d) General requirements. As
appropriate, each resource report shall:
(1) Address conditions or resources
that might be directly or indirectly
affected by the proposed electric
transmission project;
(2) Identify environmental effects
expected to occur as a result of the
proposed project;
(3) Identify the potential effects of
construction, operation (including
maintenance and malfunctions), and
termination of the proposed project, as
well as potential cumulative effects
resulting from existing or reasonably
foreseeable projects;
(4) Identify measures proposed to
enhance the environment or to avoid,
minimize, or compensate for potential
adverse effects of the proposed project;
and
(5) Provide a list of publications,
reports, and other literature or
communications, including agency
PO 00000
Frm 00063
Fmt 4701
Sfmt 4700
35373
communications, that were cited or
relied upon to prepare each report.
(e) Federal responsibility. The
resource reports prepared by the project
proponent under this section do not
supplant the requirements under
existing environmental laws related to
the information required for Federal
authorization or consultation processes.
The relevant Federal entities shall
independently evaluate the information
submitted and shall be responsible for
the accuracy, scope, and contents of all
Federal authorization decision
documents and related environmental
reviews.
(f) Resource Report 1—General project
description. This report should describe
all expected facilities associated with
the project, special construction and
operation procedures, construction
timetables, future plans for related
construction, and permits,
authorizations, and consultations that
are expected to be required for proposed
project. Resource Report 1 must:
(1) Describe and provide location
maps of all facilities to be constructed,
modified, abandoned, replaced, or
removed, including facilities related to
construction and operational support
activities and areas such as maintenance
bases, staging areas, communications
towers, power lines, and new access
roads (roads to be built or modified), as
well as any existing infrastructure
proposed to be used for the project (e.g.,
connections to existing substations and
transmission, and existing access roads);
(2) Describe specific generation
resources that are known or reasonably
foreseen to be developed or
interconnected as a result of the
proposed electric transmission project,
if any;
(3) Identify facilities constructed by
other entities that are related to the
proposed project (e.g., fiber optic cables)
and where those facilities would be
located;
(4) Provide the following information
for each facility described under
paragraphs (f)(1) through (3) of this
section:
(i) A brief description of the facility,
including, as appropriate, ownership,
land requirements, megawatt size,
construction status, and an update of
the latest status of Federal, State, and
local permits and approvals; and
(ii) Current topographic maps
showing the location of the facility;
(5) Provide any communications with
the appropriate State Historic
Preservation Offices (SHPOs) and Tribal
Historic Preservation Offices (THPOs)
regarding cultural and historic resources
in the project area;
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
35374
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
(6) To the extent known, identify the
permits, authorizations, and
consultations that are expected to be
required for proposed project, including
consultation under section 106 of the
NHPA, consultation under section 7 of
the Endangered Species Act of 1973
(Pub. L. 93–205, as amended, 16 U.S.C.
1531 et seq.), consistency
determinations under the Coastal Zone
Management Act (CZMA), and permits
under the Clean Water Act (33 U.S.C.
1251 et seq.) (CWA);
(7) Describe any developments in
obtaining authorizations and permits or
completing required consultations for
the proposed project and identify
environmental mitigation requirements
specified in any permit or proposed in
any permit application to the extent not
specified elsewhere in this resource
report or another resource report;
(8) If the project includes
abandonment of certain facilities, rightsof-way, or easements, identify and
describe the following:
(i) facilities, rights-of-way, or
easements that the project proponent
plans to abandon;
(ii) how the facilities, rights-of-way, or
easements would be abandoned;
(iii) how the abandoned facilities,
rights-of-way, and easements would be
restored;
(iv) the owner of the facilities, rightsof-way, or easement after abandonment;
(v) the party responsible for the
abandoned facilities, rights-of-way, or
easement;
(vi) whether landowners were or are
expected to be given the opportunity to
request that the abandoned facilities on
their property, including foundations
and below ground components, be
removed; and
(vii) landowners whose preferences
regarding abandoned facility removal
the project proponent does not intend to
honor and reasons why the project
proponent does not intend to honor
those preferences;
(9) Provide construction timetables
and describe, by milepost, proposed
construction and restoration methods to
be used in areas of rugged topography,
residential areas, active croplands, sites
where the proposed project would be
located parallel to and under roads, and
sites where explosives may be used;
(10) Describe estimated workforce
requirements for the proposed project,
including the number of construction
spreads, average workforce
requirements for each construction
spread, estimated duration of
construction from initial clearing to
final restoration, and number of
personnel to be hired to operate the
proposed project;
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
(11) Describe reasonably foreseeable
plans for future expansion of facilities
related to the project, including
additional land requirements and the
compatibility of those plans with the
current proposal;
(12) Provide the names and mailing
addresses of all potentially affected
landowners identified by the project
proponent, identify which potentially
affected landowners have been notified
by the project proponent, and describe
the methodology used to identify
potentially affected landowners;
(13) Summarize the proposed
mitigation approach anticipated by the
project proponent to reduce the
potential impacts of the proposed
project to resources warranting or
requiring mitigation; and
(14) Describe how the proposed
project will reduce capacity constraints
and congestion on the transmission
system, meet unmet demand, or connect
generation resources (including the
expected type of generation, if known)
to load, as appropriate.
(g) Resource Report 2—Water use and
quality. This report should describe
water resources that may be impacted
by the proposed project, describe the
potential impacts on these resources,
and describe the measures taken to
avoid and minimize adverse effects to
such water resources, where
appropriate. Resource Report 2 must:
(1) Identify surface water resources,
including perennial waterbodies,
intermittent streams, ephemeral
waterbodies, municipal water supply or
watershed areas, specially designated
surface water protection areas and
sensitive waterbodies, floodplains, and
wetlands, that would be crossed by a
potential route;
(2) For each surface water resource
that would be crossed by a potential
route, identify the approximate width of
the crossing, State water quality
classifications, any known potential
pollutants present in the water or
sediments, and any downstream potable
water intake sources within the
applicable analysis area;
(3) Describe typical staging area
requirements at surface water resource
crossings and identify and describe each
potential surface water crossing where
staging areas are likely to be more
extensive and could require a mitigation
approach to address potential impacts to
the water resource;
(4) Provide two copies of floodplain
and National Wetland Inventory (NWI)
maps or, if not available, appropriate
State wetland maps clearly showing the
study corridors or potential routes and
mileposts;
PO 00000
Frm 00064
Fmt 4701
Sfmt 4700
(5) For each wetland crossing, identify
the milepost of the crossing, the wetland
classification specified by the USFWS,
and the length of the crossing, and
describe, by milepost, wetland crossings
as determined by field delineations
using the current Federal methodology;
(6) For each floodplain crossing,
identify the mileposts, acres of
floodplains affected, flood elevation,
and basis for determining that elevation;
(7) Describe and provide data
supporting the expected impact of the
proposed project on surface and
groundwater resources;
(8) Describe and provide data
supporting proposed avoidance and
minimization measures as well as
protection or enhancement measures
that would reduce the potential for
adverse impacts to surface and
groundwater resources, and discuss any
potential compensation expected to be
provided for remaining unavoidable
impacts to water resources due to the
proposed project;
(9) Identify the location of known
public and private groundwater supply
wells or springs within the applicable
analysis area;
(10) Identify locations of EPA or Statedesignated principal-source aquifers
and wellhead protection areas crossed
by a potential route;
(11) Discuss the results of any
coordination with relevant Federal
entities or non-Federal entities related
to CWA permitting and include any
written correspondence that resulted
from the coordination; and
(12) Indicate whether the project
proponent expects that a water quality
certification (under section 401 of the
CWA) will be required for any potential
routes.
(h) Resource Report 3—Fish, wildlife,
and vegetation. This report should
identify and describe potential impacts
to aquatic and terrestrial habitats,
wildlife, and plants from the proposed
project and discuss potential avoidance,
minimization, or compensation
measures, and enhancement or
protection measures to reduce adverse
impacts to these resources. Resource
Report 3 must:
(1) Describe aquatic habitats that
occur in the applicable analysis area,
including commercial and recreational
warmwater, coldwater, and saltwater
fisheries and associated significant
habitats such as spawning or rearing
areas, estuaries, and other essential fish
habitats;
(2) Describe terrestrial habitats that
occur in the project area, including
wetlands, typical wildlife habitats, and
rare, unique, or otherwise significant
habitats;
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
(3) Identify fish, wildlife, and plants
that may be affected by the proposed
project, including species that have
commercial, recreational, or aesthetic
value and that may be affected by the
proposed project;
(4) Describe and provide the acreage
of vegetation cover types that would be
affected by the proposed project,
including unique ecosystems or
communities such as remnant prairie or
old-growth forest, or significant
individual plants, such as old-growth
specimen trees;
(5) Describe the impact of the
proposed project on aquatic and
terrestrial habitats, including potential
loss and fragmentation;
(6) Describe the potential impact of
the proposed project on Federally listed,
candidate, or proposed endangered or
threatened species, State, Tribal, and
local species of concern, and those
species’ habitats, including the
possibility of a major alteration to
ecosystems or biodiversity;
(7) Describe the potential impact of
maintenance, clearing, and treatment of
the applicable analysis area on fish,
wildlife, and plant life;
(8) Identify all Federally listed,
candidate, or proposed endangered or
threatened species that may be affected
by the proposed project and proposed or
designated critical habitats that
potentially occur in the applicable
analysis area;
(9) Identify all State, Tribal, and local
species of concern that may be affected
by the proposed project;
(10) Identify all known and potential
bald and golden eagle nesting and
roosting sites, migratory bird flyways,
and any sites important to migratory
bird breeding, feeding, and sheltering
within the applicable analysis areas.
These identifications should coincide
with the USFWS’s most current range
and location maps at the time this
resource report is submitted;
(11) Discuss the results of any
discussions conducted by the proponent
to date with relevant Federal entities or
relevant non-Federal entities related to
fish, wildlife, and vegetation resources,
and include any written correspondence
that resulted from the discussions;
(12) Include the results of any
appropriate surveys that have already
been conducted, as well as plans and
protocols for future surveys. If
potentially suitable habitat is present,
species-specific surveys may be
required;
(13) If present, identify all Federally
designated essential fish habitat (EFH)
that occurs in the applicable analysis
area and provide:
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
(i) Information on all EFH, as
identified by the pertinent Federal
fishery management plans, which may
be adversely affected by potential
routes;
(ii) The results of discussions with
National Marine Fisheries Service; and
(iii) Any resulting EFH assessments
that were evaluated, and EFH
Conservation Recommendations that
were provided by the National Marine
Fisheries Service;
(14) Describe potential avoidance,
minimization, or compensation
measures, and enhancement or
protection measures to address adverse
effects described in paragraphs (h)(5),
(6), and (7) of this section;
(15) Describe anticipated site-specific
mitigation approaches for fisheries,
wildlife (including migration corridors
and seasonal areas of use), grazing, and
plant life;
(16) Describe proposed measures to
avoid and minimize incidental take of
Federally listed and candidate species
and species of concern, including eagles
and migratory birds; and
(17) Include copies of any
correspondence not otherwise provided
pursuant to this paragraph (h)
containing recommendations from
appropriate Federal, State, and local fish
and wildlife agencies to avoid or limit
impact on wildlife, fish, fisheries,
habitats, and plants, and the project
proponent’s response to those
recommendations.
(i) Resource Report 4—Cultural
resources. This report should describe
the location of known cultural and
historic resources, previous surveys and
listings of cultural and historic
resources, the potential effects that
construction, operation, and
maintenance of the proposed project
will have on those resources, and initial
recommendations for avoidance and
minimization measures to address
potential effects to those resources. The
information provided in Resource
Report 4 will contribute to the
satisfaction of DOE’s and relevant
Federal entities’ obligations under
section 106 of the NHPA.
(1) Resource Report 4 must contain:
(i) A summary of known cultural and
historic resources in the applicable
analysis area including but not limited
to those listed or eligible for listing on
the National Register of Historic Places,
such as properties of religious and
cultural significance to Indian Tribes,
and any material remains of past human
life or activities that are of an
archeological interest;
(ii) A description of potential effects
that construction, operation, and
maintenance of the proposed project
PO 00000
Frm 00065
Fmt 4701
Sfmt 4700
35375
will have on resources identified in
paragraph (i)(1)(i) of this section;
(iii) Documentation of the project
proponent’s initial communications and
engagement, including preliminary
outreach and coordination, with Indian
Tribes, indigenous peoples, THPOs,
SHPOs, communities of interest, and
other entities having knowledge of,
interest regarding, or an understanding
about the resources identified in
paragraph (i)(1)(i) of this section and
any written comments from SHPOs,
THPOs, other Tribal historic
preservation offices or governments, or
others, as appropriate and available;
(iv) Recommended avoidance and
minimization measures to address
potential effects of the proposed project;
(v) Any relevant existing surveys or
listings of cultural and historic
resources in the affected environment;
and
(vi) Recommendations for any
additional surveys needed; and
(vii) A description, by milepost, of
any area that has not been surveyed due
to a denial of access by landowners.
(2) The project proponent must
update this report with the results of
any additional surveys that the project
proponent chooses to undertake, as
identified in in paragraph (i)(1)(vi) of
this section, after the initial submission
of this report.
(3) The project proponent must
request confidential treatment for all
material filed with DOE containing nonpublic location, character, and
ownership information about cultural
resources in accordance with § 900.4(h).
(j) Resource Report 5—
Socioeconomics. This report should
identify and quantify the impacts of
constructing and operating the proposed
project on the demographics and
economics of communities in the
applicable analysis area, including
minority and underrepresented
communities. Resource Report 5 must:
(1) Describe the socioeconomic
resources that may be affected in the
applicable analysis area;
(2) Describe the positive and adverse
socioeconomic impacts of the proposed
project;
(3) Evaluate the impact of any
substantial migration of people into the
applicable analysis area on
governmental facilities and services and
describe plans to reduce the impact on
the local infrastructure;
(4) Describe on-site labor
requirements during construction and
operation, including projections of the
number of construction personnel who
currently reside within the applicable
analysis area, who would commute
daily to the site from outside the
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
35376
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
analysis area, or who would relocate
temporarily within the analysis area;
(5) Determine whether existing
affordable housing within the applicable
analysis area is sufficient to meet the
needs of the additional population; and
(6) Describe the number and types of
residences and businesses that would be
displaced by the proposed project,
procedures to be used to acquire these
properties, and types and amounts of
relocation assistance payments.
(k) Resource Report 6—Tribal
interests. This report must identify the
Indian Tribes and indigenous
communities that may be affected by the
construction, operation, and
maintenance of the project facilities,
including those Indian Tribes and
indigenous communities that may
attach religious and cultural
significance to cultural resources within
the project area. In developing this
report, the project proponent should
consider both Indian Tribes with
contemporary presence in the project
area and Indian Tribes with historic
connections to the area. To the extent
Indian Tribes and indigenous
communities are willing to
communicate and share resource
information, this report must discuss
the potential impacts of project
construction, operation, and
maintenance on Indian Tribes and
Tribal interests. This discussion must
include impacts to sacred sites and
Treaty rights, impacts related to
enumerated resources and areas
identified in the resource reports listed
in this section (for instance, water
rights, access to property, wildlife and
ecological resources, etc.), and set forth
available information on any additional,
relevant traditional cultural and
religious resources that could be
affected by the proposed electric
transmission project that are not already
addressed. This resource report should
acknowledge existing relationships
between adjacent and underlying
Federal land management agencies and
the Indian Tribes. In developing this
report, the project proponent should
engage the Federal land manager early
to leverage existing relationships.
Specific site or property locations, the
disclosure of which may create a risk of
harm, theft, or destruction of
archaeological or Native American
cultural resources and information
which would violate any Federal law,
including section 9 of the
Archaeological Resources Protection Act
of 1979 (Pub. L. 96–95, as amended) (16
U.S.C. 470hh) and section 304 of the
NHPA (54 U.S.C. 307103), should be
submitted consistent with § 900.4(h).
The project proponent must request
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
confidential treatment for all material
filed with DOE containing non-public
location, character, and ownership
information about Tribal resources in
accordance with § 900.4(h).
(l) Resource Report 7—Communities
of Interest. This report must summarize
best available information about the
presence of communities of interest.
The resource report must identify and
describe the potential impacts of
constructing, operating, and
maintaining the proposed electric
transmission project on communities of
interest; and describe any proposed
mitigation approaches for such impacts
or community concerns. The report
must include a discussion of any
disproportionate and/or adverse human
health or environmental impacts to
communities of interest.
(m) Resource Report 8—Geological
resources and hazards. This report
should describe geological resources
that might be directly or indirectly
affected by the proposed electric
transmission project and methods to
reduce those effects. The report should
also describe geological hazards that
could place project facilities at risk and
methods proposed to mitigate those
risks. Resource Report 8 must:
(1) Describe geological resources in
the applicable analysis area that are
currently or potentially exploitable, if
relevant;
(2) Identify, by milepost, existing and
potential geological hazards and areas of
nonroutine geotechnical concern in the
applicable analysis area, such as high
seismicity areas, active faults, and areas
susceptible to soil liquefaction; planned,
active, and abandoned mines; karst
terrain (including significant caves
protected under the Federal Cave
Resources Protection Act (Pub. L. 100–
691, as amended) (16 U.S.C. 4301 et
seq.)); and areas of potential ground
failure, such as subsidence, slumping,
and land sliding;
(3) Discuss the risks posed to the
proposed project from each hazard or
area of nonroutine geotechnical concern
identified in paragraph (m)(2) of this
section;
(4) Describe how the proposed project
would be located or designed to avoid
or minimize adverse effects to geological
resources and reduce risk to project
facilities, including geotechnical
investigations and monitoring that
would be conducted before, during, and
after construction;
(5) Discuss the potential for blasting
to affect structures and the measures to
be taken to remedy such effects; and
(6) Specify methods to be used to
prevent project-induced contamination
from mines or from mine tailings along
PO 00000
Frm 00066
Fmt 4701
Sfmt 4700
the right-of-way and discuss whether
the proposed project would hinder mine
reclamation or expansion efforts.
(n) Resource Report 9—Soil resources.
This report should describe the soils
that could be crossed by the proposed
electric transmission project, the
potential effect on those soils, and the
proposed mitigation approach for those
effects. Resource Report 9 must:
(1) List, by milepost, the soil
associations that would be crossed by
each potential route and describe the
erosion potential, fertility, and drainage
characteristics of each association;
(2) For the applicable analysis area:
(i) List the soil series within the area
and the percentage of the area
comprised of each series;
(ii) List the percentage of each series
which would be permanently disturbed;
(iii) Describe the characteristics of
each soil series; and
(iv) Indicate which soil units are
classified as prime or unique farmland
by the USDA, Natural Resources
Conservation Service;
(3) Identify potential impacts from:
soil erosion due to water, wind, or loss
of vegetation; soil compaction and
damage to soil structure resulting from
movement of construction vehicles; wet
soils and soils with poor drainage that
are especially prone to structural
damage; damage to drainage tile systems
due to movement of construction
vehicles and trenching activities; and
interference with the operation of
agricultural equipment due to the
probability of large stones or blasted
rock occurring on or near the surface as
a result of construction;
(4) Identify, by milepost, cropland
and residential areas where loss of soil
fertility due to trenching and backfilling
could occur; and
(5) Describe the proposed mitigation
approach to reduce the potential for
adverse impact to soils or agricultural
productivity.
(o) Resource Report 10—Land use,
recreation, and aesthetics. This report
should describe the existing uses of land
that may be impacted by the proposed
project, and changes to those land uses
and impacts to inhabitants and users
that would occur if the proposed
electric transmission project is
approved. Resource Report 10 must:
(1) Describe the width and acreage
requirements of all construction and
permanent rights-of-way required for
project construction, operation, and
maintenance;
(2) List existing rights-of-way that
would be co-located with or adjacent to
the proposed rights-of-way (including
temporary construction lines), and any
required utility coordination, permits,
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
and fees that would be associated as a
result;
(3) Identify, preferably by diagrams,
existing rights-of-way that are expected
to be used for any portion of the
construction or operational right-of-way,
the overlap, and how much additional
width is expected to be required;
(4) Identify the total amount of land
to be purchased or leased for each
project facility, the amount of land that
would be disturbed for construction,
operation, and maintenance of the
facility, and the use of the remaining
land not required for project operation
and maintenance, if any;
(5) Identify the size of typical staging
areas and expanded work areas, such as
those at railroad, road, and waterbody
crossings, and the size and location of
all construction materials storage yards
and access roads;
(6) Identify, by milepost, the existing
use of:
(i) Lands crossed by or adjacent to
each project facility; and
(ii) Lands on which a project facility
is expected to be located;
(7) Describe:
(i) Planned development within the
applicable analysis area that is either
included in a master plan or on file with
the local planning board or the county;
(ii) The time frame (if available) for
such development; and
(iii) Proposed coordination to
minimize impacts on land use due to
such development;
(8) Identify areas within applicable
analysis areas that:
(i) Are owned or controlled by
Federal, State or local agencies, or
private preservation groups;
(ii) Are directly affected by the
proposed project or any project facilities
or operational sites; and
(iii) Have special designations not
otherwise mentioned in other resource
reports.
(iv) Examples of such specially
designated areas under this provision
may include but are not limited to sugar
maple stands, orchards and nurseries,
landfills, hazardous waste sites, nature
preserves, conservation or agricultural
lands subject to conservation or
agricultural easements or restrictions,
game management areas, remnant
prairie, old-growth forest, national or
State forests, parks, designated natural,
recreational or scenic areas, registered
natural landmarks, and areas managed
by Federal entities under existing land
use plans as Visual Resource
Management Class I or Class II areas;
(9) Identify Indian Tribes and
indigenous communities that may be
affected by the proposed project;
(10) Describe Tribal and indigenous
community resources lands, interests,
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
and established treaty rights that may be
affected by the proposed project;
(11) Identify properties within the
project area which may hold cultural or
religious significance for Indian Tribes
and indigenous communities, regardless
of whether the property is on or off of
any Federally recognized Indian
reservation;
(12) Identify resources within the
applicable analysis area that are
included in, or are designated for study
for inclusion in, if available: the
National Wild and Scenic Rivers System
(16 U.S.C. 1271), the National Wildlife
Refuge System (16 U.S.C. 668dd), the
National Wilderness Preservation
System (16 U.S.C. 1131), the National
Trails System (16 U.S.C. 1241–1251),
the National Park System (54 U.S.C.
100101–120104), National Historic
Landmarks (NHLs), National Natural
Landmarks (NNLs), Land and Water
Conservation Fund (LWCF) acquired
Federal lands, LWCF State Assistance
Program sites and the Federal Lands to
Parks (FLP) program lands, or a
wilderness area designated under the
Wilderness Act (16 U.S.C. 1131–1136);
or the National Marine Sanctuary
System, including national marine
sanctuaries (16 U.S.C. 1431–1445c–1.)
and Marine National Monuments as
designated under authority by the
Antiquities Act (54 U.S.C. 320301–
320303) or by Congress; National
Forests and Grasslands (16 U.S.C. 1609
et seq); and lands in easement programs
managed by the Natural Resource
Conservation Service or the U.S. Forest
Service (16 U.S.C. 3865, et seq.);
(13) Indicate whether the project
proponent will need to submit a CZMA
Federal consistency certification to State
coastal management program(s) for the
project, as required by NOAA’s Federal
consistency regulations at 15 CFR part
930, subpart D;
(14) Describe the impacts the
proposed project will have on:
(i) Present uses of land in the
applicable analysis area, including
commercial uses, mineral resource uses,
and recreational uses,
(ii) Public health and safety;
(iii) Federal, State, and Tribal
scientific survey, research, and
observation activities;
(iv) Sensitive resources and critical
habitats;
(v) The aesthetic value of the land and
its features; and
(vi) Federal, State or Tribal access
limitations.
(15) Describe any temporary or
permanent restrictions on land use that
would result from the proposed project.
(16) Describe the proposed mitigation
approach intended to address impacts
PO 00000
Frm 00067
Fmt 4701
Sfmt 4700
35377
described in paragraphs (o)(12) and (13)
of this section, as well as protection and
enhancement of existing land use;
(17) Provide a proposed operations
and maintenance plan for vegetation
management, including management of
noxious and invasive species;
(18) Describe the visual characteristics
of the lands and waters affected by the
proposed project. Components of this
description include a description of
how permanent project facilities will
impact the visual character of proposed
project right-of-way and surrounding
vicinity, and measures proposed to
lessen these impacts. Project proponents
are encouraged to supplement the text
description with visual aids;
(19) Identify, by milepost, all
residences and buildings near the
proposed electric transmission facility
construction right-of-way, and identify
the distance of the residence or building
from the edge of the right-of-way and
provide survey drawings or alignment
sheets to illustrate the location of the
proposed facility in relation to the
buildings;
(20) List all dwellings and related
structures, commercial structures,
industrial structures, places of worship,
hospitals, nursing homes, schools, or
other structures normally inhabited by
humans or intended to be inhabited by
humans on a regular basis within the
applicable analysis area and provide a
general description of each habitable
structure and its distance from the
centerline of the proposed project. In
cities, towns, or rural subdivisions,
houses can be identified in groups, and
the report must provide the number of
habitable structures in each group and
list the distance from the centerline to
the closest habitable structure in the
group;
(21) List all known commercial AM
radio transmitters located within the
applicable analysis area and all known
FM radio transmitters, microwave relay
stations, or other similar electronic
installations located within the analysis
area; provide a general description of
each installation and its distance from
the centerline of the proposed project;
and locate all installations on a routing
map; and
(22) List all known private airstrips
within the applicable analysis area and
all airports registered with the Federal
Aviation Administration (FAA) with at
least one runway more than 3,200 feet
in length that are located within the
analysis area. Indicate whether any
transmission structures will exceed a
100:1 horizontal slope (one foot in
height for each 100 feet in distance)
from the closest point of the closest
runway. List all airports registered with
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
35378
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
the FAA having no runway more than
3,200 feet in length that are located
within the analysis area. Indicate
whether any transmission structures
will exceed a 50:1 horizontal slope from
the closest point of the closest runway.
List all heliports located within the
analysis area. Indicate whether any
transmission structures will exceed a
25:1 horizontal slope from the closest
point of the closest landing and takeoff
area of the heliport. Provide a general
description of each private airstrip,
registered airport, and registered
heliport, and state the distance of each
from the centerline of the proposed
transmission line. Locate all airstrips,
airports, and heliports on a routing map.
(23) Information made available under
paragraphs (o)(9), (10), and (11) must be
submitted consistent with § 900.4(h),
including information regarding specific
site or property locations, the disclosure
of which will create a risk of harm,
theft, or destruction of archaeological or
Native American cultural resources and
information which would violate any
Federal law, including section 9 of the
Archaeological Resources Protection Act
of 1979 (Pub. L. 96–95, as amended) (16
U.S.C. 470hh) and section 304 of the
NHPA (54 U.S.C. 307103).
(p) Resource Report 11—Air quality
and noise effects. This report should
identify the effects of the proposed
electric transmission project on the
existing air quality and noise
environment and describe proposed
measures to mitigate the effects.
Resource Report 11 must:
(1) Describe the existing air quality in
the applicable analysis area, indicate if
any project facilities are located within
a designated nonattainment or
maintenance area under the Clean Air
Act (42 U.S.C. 7401 et seq.), and provide
the distance from the project facilities to
any Class I area in the project area;
(2) Estimate emissions from the
proposed project and the corresponding
impacts on air quality and the
environment;
(i) Estimate the reasonably foreseeable
emissions, including greenhouse gas
emissions, from construction, operation,
and maintenance of the project facilities
(such as emissions from tailpipes,
equipment, fugitive dust, open burning,
and substations) expressed in tons per
year; include supporting calculations,
emissions factors, fuel consumption
rates, and annual hours of operation;
(ii) Estimate the reasonably
foreseeable change in greenhouse gas
emissions from the existing, proposed,
and reasonably foreseeable generation
resources identified in Resource Report
1 (see paragraph (f) of this section) that
may connect to the proposed project or
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
interconnect as a result of the proposed
project, if any, as well as any other
modeled air emissions impacts;
(iii) For each designated
nonattainment or maintenance area,
provide a comparison of the emissions
from construction, operation, and
maintenance of the proposed project
with the applicable General Conformity
thresholds (40 CFR part 93);
(iv) Identify the corresponding
impacts on communities and the
environment in the applicable analysis
area from the estimated emissions;
(v) Describe any proposed mitigation
measures to control emissions identified
under this section; and
(vi) Estimate the reasonably
foreseeable effect of the proposed
project on indirect emissions;
(3) Describe existing noise levels at
noise-sensitive areas in the applicable
analysis area, such as schools, hospitals,
residences, and any areas covered by
relevant State or local noise ordinances;
(i) Report existing noise levels as the
a-weighted decibel (dBA) Leq (day), Leq
(night), and Ldn (day-night sound level)
and include the basis for the data or
estimates;
(ii) Include a plot plan that identifies
the locations and duration of noise
measurements, the time of day, weather
conditions, wind speed and direction,
engine load, and other noise sources
present during each measurement; and
(iii) Identify any noise regulations that
may be applicable to the proposed
project;
(4) Estimate the impact of the
proposed project on the noise
environment;
(i) Provide a quantitative estimate of
the impact of transmission line
operation on noise levels at the edge of
the proposed right-of-way, including
corona, insulator, and Aeolian noise;
and provide a quantitative estimate of
the impact of operation of proposed
substations and appurtenant project
facilities on noise levels at nearby noisesensitive areas, including discrete tones;
(A) Include step-by-step supporting
calculations or identify the computer
program used to model the noise levels,
the input and raw output data and all
assumptions made when running the
model, far-field sound level data for
maximum facility operation (either from
the manufacturer or from far-field sound
level data measured from similar project
facilities in service elsewhere) and the
source of the data;
(B) Include sound pressure levels for
project facilities, dynamic insertion loss
for structures, and sound attenuation
from the project facilities to the edge of
the right-of-way or to nearby noisesensitive areas (as applicable);
PO 00000
Frm 00068
Fmt 4701
Sfmt 4700
(ii) Describe the impact of proposed
construction activities, including any
nighttime construction, on the noise
environment; estimate the impact of any
horizontal directional drilling, pile
driving, or blasting on noise levels at
nearby noise-sensitive areas and include
supporting assumptions and
calculations;
(5) Based on noise estimates, indicate
whether the proposed project will
comply with applicable noise
regulations and whether noise
attributable to any proposed substation
or appurtenant facility will exceed
permissible levels at any pre-existing
noise-sensitive area;
(6) Based on noise estimates,
determine whether any wildlife-specific
noise thresholds may have an impact on
the proposed project, such as those
thresholds specific to avian species that
may be relevant in significant wildlife
areas, if appropriate; and
(7) Describe measures, and
manufacturer’s specifications for
equipment, proposed to mitigate noise
effects and impacts to air quality,
including emission control systems,
installation of filters, mufflers, or
insulation of piping and buildings, and
orientation of equipment away from
noise-sensitive areas.
(q) Resource Report 12—Alternatives.
This report should describe the range of
study corridors that were considered as
alternatives during the planning,
identification, and design of the
proposed electric transmission project
and compare the environmental impacts
of such corridors and the routes
contained in those corridors. This
analysis may inform the relevant
Federal entities’ subsequent analysis of
their alternatives during the NEPA
process. Resource Report 12 must:
(1) Identify all study corridors and
routes contained within those corridors.
The report must identify the location of
the corridors on maps of sufficient scale
to depict their location and relationship
to the proposed project, and the
relationship of the proposed electric
transmission facility to existing rightsof-way;
(2) Discuss the ‘‘no action’’ alternative
and the potential for accomplishing the
proponent’s proposed objectives using
alternative means;
(3) Discuss design and construction
methods considered by the project
proponent;
(4) Identify all the alternative study
corridors and routes the project
proponent considered in the initial
screening for the proposed project but
did not recommend for further study
and the reasons why the proponent
chose not to examine such alternatives.
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
(5) For alternative study corridors and
routes recommended for more in-depth
consideration, the report must:
(i) Describe the potential impacts to
cultural and historic resources for each
alternative;
(ii) Describe the environmental
characteristics of each alternative,
provide comparative tables showing the
differences in environmental
characteristics for the alternatives, and
include an analysis of the potential
relative environmental impacts for each
alternative;
(iii) Provide an explanation of the
costs to construct, operate, and maintain
each alternative, the potential for each
alternative to meet project deadlines,
and technological and procedural
constraints in developing the
alternatives; and
(iv) Demonstrate whether and how
environmental benefits and costs were
weighed against economic benefits and
costs to the public.
(r) Resource Report 13—Reliability,
resilience, and safety. This report
should describe the impacts that would
result from a failure of the proposed
electric transmission facility, the
measures, procedures, and features that
would reduce the risk of failure, and
measures in place to reduce impacts and
protect the public if a failure did occur.
Resource Report 13 must:
(1) Discuss events that could result in
a failure of the proposed facility,
including accidents, intentional
destructive acts, and natural
catastrophes (accounting for the
likelihood of relevant natural
catastrophes resulting from climate
change);
(2) Describe the reasonably
foreseeable impacts that would result
from a failure of the proposed electric
transmission facility, including hazards
to the public, environmental impacts,
and service interruptions;
(3) Describe the operational measures,
procedures, and design features of the
proposed project that would reduce the
risk of facility failure;
(4) Describe measures proposed to
protect the public from failure of the
proposed facility (including
coordination with local agencies);
(5) Discuss contingency plans for
maintaining service or reducing
downtime;
(6) Describe measures used to exclude
the public from hazardous areas,
measures used to minimize problems
arising from malfunctions and accidents
(with estimates of probability of
occurrence), and identify standard
procedures for protecting services and
public safety during maintenance and
breakdowns; and
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
(7) Describe improvements to
reliability likely to result from the
proposed project.
§ 900.7 Standard and project-specific
schedules.
(a) DOE shall publish, and update
from time to time, a standard schedule
that identifies the steps generally
needed to complete decisions on all
Federal environmental reviews and
authorizations for a proposed electric
transmission project. The standard
schedule will include recommended
timing for each step so as to allow final
decisions on all Federal authorizations
within two years of the publication of a
notice of intent to prepare an
environmental review document under
§ 900.9 or as soon as practicable
thereafter, considering the requirements
of relevant Federal laws, and the need
for robust analysis of proposed project
impacts, early and meaningful
consultation with potentially affected
Indian Tribes and engagement with
stakeholders and communities of
interest.
(b) During the Integrated Interagency
Pre-Application (IIP) Process, DOE, in
coordination with any NEPA joint lead
agency and relevant Federal entities,
shall prepare a project-specific schedule
that is informed by the standard
schedule prepared under paragraph (a)
of this section and that establishes
prompt and binding intermediate
milestones and ultimate deadlines for
the review of, and Federal authorization
decisions relating to, a proposed electric
transmission project, accounting for
relevant statutory requirements, the
potential route, reasonable alternative
potential routes, if any, the need to
assess and address any impacts to
military testing, training, and
operations, and other factors particular
to the specific proposed project,
including the need for early and
meaningful consultation with
potentially affected Indian Tribes and
engagement with stakeholders and
communities of interest. DOE may
revise the project-specific schedule as
needed to satisfy applicable statutory
requirements, allow for engagement
with stakeholders and communities of
interest, and account for delays caused
by the actions or inactions of the project
proponent.
§ 900.8
IIP Process review meeting.
(a) An Integrated Interagency PreApplication (IIP) Process review
meeting is required for each proposed
electric transmission project utilizing
the IIP Process and may only be held
after the project proponent submits a
review meeting request to DOE. The
PO 00000
Frm 00069
Fmt 4701
Sfmt 4700
35379
project proponent may submit the
request at any time following
submission of the initial resource
reports required under § 900.6. The
review meeting request must include:
(1) A summary table of changes made
to the proposed project since the IIP
Process initial meeting, including
potential environmental and community
benefits from improved siting or design;
(2) Maps of potential routes and study
corridors, including the proposed line,
substations, and other infrastructure, as
applicable, with at least as much detail
as required for the initiation request
described by § 900.5 and as modified in
response to early stakeholder input and
outreach and feedback from relevant
Federal entities and relevant nonFederal entities;
(3) If known, a schedule for
completing any upcoming field resource
surveys, as appropriate;
(4) A conceptual plan for
implementation and monitoring of
proposed mitigation measures to avoid,
minimize, or compensate for effects of
the proposed project, consistent with 40
CFR 1508.1(s) or any successor
regulation. This may include
compensatory mitigation measures
(offsite and onsite);
(5) An updated public engagement
plan described in § 900.5(d)(2),
reflecting actions undertaken since the
project proponent submitted the
initiation request and input received
from relevant Federal entities and
relevant non-Federal entities;
(6) A listing of:
(i) The dates on which the project
proponent filed applications or requests
for Federal authorizations and the dates
on which the project proponent filed
revisions to previously filed
applications or requests; and
(ii) Estimated dates for filing
remaining applications or requests for
Federal authorization;
(7) Estimated dates that the project
proponent will file requests for
authorizations and consultations with
relevant non-Federal entities; and
(8) A proposed duration for each
Federal land use authorization expected
to be required for the proposed project,
commensurate with the anticipated use
of the proposed electric transmission
facility.
(b) Not later than 10 calendar days
after the date that DOE receives the
review meeting request, DOE shall
provide relevant Federal entities and
relevant non-Federal entities with
materials included in the request and
the initial resource reports submitted
under § 900.6 via electronic means.
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
35380
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
(c) Not later than 60 calendar days
after the date that DOE receives the
review meeting request, DOE shall:
(1) Determine whether the meeting
request meets the requirements of
paragraph (a) of this section and
whether the initial resource reports are
sufficiently detailed; and
(2) Give notice to the project
proponent and relevant Federal and
non-Federal entities of DOE’s
determinations under paragraph (c)(1) of
this section.
(d) If DOE determines under
paragraph (c)(1) of this section that the
meeting request does not meet the
requirements of paragraph (a) of this
section or that the initial resource
reports are not sufficiently detailed,
DOE must provide the reasons for that
finding and a description of how the
project proponent may address any
deficiencies in the meeting request or
resource reports so that DOE may
reconsider its determination.
(e) Not later than 15 calendar days
after the date that DOE provides notice
to the project proponent under
paragraph (c) of this section that the
review meeting request and initial
resource reports have been accepted,
DOE shall convene the review meeting
with the project proponent and the
relevant Federal entities. All relevant
non-Federal entities participating in the
IIP Process shall also be invited.
(f) During the IIP Process review
meeting:
(1) The relevant Federal entities shall
discuss, and modify if needed, the
analysis areas used in the initial
resource reports;
(2) Relevant Federal entities shall
identify any remaining issues of
concern, known information gaps or
data needs, and potential issues or
conflicts that could impact the time it
will take the relevant Federal entities to
process applications for Federal
authorizations for the proposed electric
transmission project;
(3) Relevant non-Federal entities may
identify remaining issues of concern,
information needs, and potential issues
or conflicts for the project;
(4) The participants shall discuss the
project proponent’s updates to the siting
process to date, including stakeholder
outreach activities, resultant stakeholder
input, and project proponent response
to stakeholder input;
(5) Led by DOE, all relevant Federal
entities shall discuss statutory and
regulatory standards that must be met to
make decisions for Federal
authorizations required for the proposed
project;
(6) Led by DOE, all relevant Federal
entities shall describe the process for,
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
and estimated time to complete,
required Federal authorizations and,
where possible, the anticipated cost
(e.g., processing and monitoring fees
and land use fees);
(7) Led by DOE, all relevant Federal
entities shall describe their expectations
for complete applications for Federal
authorizations for the proposed project;
(8) Led by DOE, all relevant Federal
entities shall identify necessary updates
to the initial resource reports that must
be made before conclusion of the IIP
Process, or, as necessary, following
conclusion of the IIP Process; and
(9) DOE shall present the proposed
project-specific schedule developed
under § 900.7.
(g) Not later than 10 calendar days
after the review meeting, DOE shall:
(1) Prepare a draft review meeting
summary that includes a summary of
the meeting discussion, a description of
key issues and information gaps
identified during the meeting, and any
requests for more information from
relevant Federal entities and relevant
non-Federal entities; and
(2) Convey the draft summary to the
project proponent, relevant Federal
entities, and any non-Federal entities
that participated in the meeting.
(h) The project proponent and entities
that received the draft review meeting
summary under paragraph (g) of this
section will have 10 calendar days
following receipt of the draft to review
the draft and provide corrections to
DOE.
(i) Not later than 10 calendar days
following the close of the 10-day review
period under paragraph (h) of this
section, DOE shall:
(1) Prepare a final review meeting
summary incorporating received
corrections, as appropriate;
(2) Add the final summary to the
consolidated administrative docket
described by § 900.10; and
(3) Provide an electronic copy of the
summary to the relevant Federal
entities, relevant non-Federal entities,
and the project proponent.
(j) Not later than 10 calendar days
following the close of the 10-day review
period under paragraph (h) of this
section, DOE shall:
(1) determine whether the project
proponent has developed the scope of
its proposed project and alternatives
sufficiently for DOE to determine that
there exists an undertaking for purposes
of section 106 of the NHPA; and
(2) if the scope is sufficiently
developed, initiate consultation with
SHPOs, THPOs, and others consistent
with 36 CFR 800.2(c)(4), which may
include authorizing a project proponent,
as a CITAP applicant, to initiate section
PO 00000
Frm 00070
Fmt 4701
Sfmt 4700
106 consultation and providing
appropriate notifications.
(k) After the review meeting and
before the IIP Process close-out meeting
described by § 900.9 the project
proponent shall revise resource reports
submitted under § 900.6 based on
feedback from relevant Federal entities
and relevant non-Federal entities
received during the review meeting and
based on any updated surveys
conducted since the initial meeting.
§ 900.9
IIP Process close-out meeting.
(a) An Integrated Interagency PreApplication (IIP) Process close-out
meeting concludes the IIP Process for a
proposed electric transmission project
and may only be held after the project
proponent submits a close-out meeting
request to DOE. The project proponent
may submit the request at any time
following the submission of the updated
resource reports as required under
§ 900.8. The close-out meeting request
shall include:
(1) A summary table of changes made
to the proposed project during the IIP
Process, including potential
environmental and community benefits
from improved siting or design;
(2) A description of all changes made
to the proposed project since the review
meeting, including a summary of
changes made to the updated resource
reports in response to the concerns
raised during the review meeting;
(3) A final public engagement plan, as
described in § 900.5(d)(2);
(4) Requests for Federal
authorizations for the proposed project;
and
(5) An updated estimated timeline of
filing requests for all other
authorizations and consultations with
non-Federal entities.
(b) Not later than 10 calendar days
after the date that DOE receives the
close-out meeting request, DOE shall
provide relevant Federal entities and
relevant non-Federal entities with
materials included in the request and
any updated resource reports submitted
under § 900.6 via electronic means.
(c) Not later than 60 calendar days
after the date that DOE receives the
close-out meeting request, DOE shall:
(1) Determine whether the meeting
request meets the requirements of
paragraph (a) of this section and
whether the updated resource reports
are sufficiently detailed; and
(2) Give notice to the project
proponent and relevant Federal and
non-Federal entities of DOE’s
determinations under paragraph (c)(1) of
this section.
(d) If DOE determines that the
meeting request does not meet the
E:\FR\FM\01MYR2.SGM
01MYR2
ddrumheller on DSK120RN23PROD with RULES2
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
requirements of paragraph (a) of this
section or that the updated resource
reports are not sufficiently detailed,
DOE must provide the reasons for that
finding and a description of how the
project proponent may address any
deficiencies in the meeting request or
resource reports so that DOE may
reconsider its determination.
(e) Not later than 15 calendar days
after the date that DOE provides notice
to the project proponent under
paragraph (c) of this section that the
close-out meeting request and updated
resource reports have been accepted,
DOE shall convene the close-out
meeting with the project proponent and
all relevant Federal entities. All relevant
non-Federal entities participating in the
IIP Process shall also be invited.
(f) The IIP Process close-out meeting
concludes the IIP Process. During the
close-out meeting:
(1) The participants shall discuss the
project proponent’s updates to the siting
process to date, including stakeholder
outreach activities, resultant stakeholder
input, and project proponent response
to stakeholder input; and
(2) DOE shall present the final projectspecific schedule.
(g) Not later than 10 calendar days
after the close-out meeting, DOE shall:
(1) Prepare a draft close-out meeting
summary; and
(2) Convey the draft summary to the
project proponent, relevant Federal
entities, and any non-Federal entities
that participated in the meeting.
(h) The project proponent and entities
that received the draft close-out meeting
summary under paragraph (g) of this
section will have 10 calendar days
following receipt of the draft to review
the draft and provide corrections to
DOE.
(i) Not later than 10 calendar days
following the close of the 10-day review
period under paragraph (h) of this
section, DOE shall:
(1) Prepare a final close-out meeting
summary by incorporating received
corrections, as appropriate;
(2) Add the final summary to the
consolidated administrative docket
described by § 900.10;
(3) Provide an electronic copy of the
summary to all relevant Federal entities,
relevant non-Federal entities, and the
project proponent; and
(4) In the event that the proposed
project is not identified as a covered
project pursuant to § 900.5(e), notify the
FPISC Executive Director that the
proposed project ought to be included
on the FPISC Dashboard as a
transparency project.
(j) DOE and any NEPA joint lead
agency shall issue a Notice of Intent to
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
prepare an environmental review
document for the proposed project
within 90 days of the later of the IIP
Process close-out meeting or the receipt
of a complete application for a Federal
authorization for which NEPA review
will be required, as consistent with the
final project-specific schedule.
(k) DOE shall issue, for each Federal
land use authorization for a proposed
electric transmission facility, a
preliminary duration determination
commensurate with the anticipated use
of the proposed facility.
§ 900.10
docket.
Consolidated administrative
(a) DOE shall maintain a consolidated
docket of:
(1) All information that DOE
distributes to or receives from the
project proponent, relevant Federal
entities, and relevant non-Federal
entities related to the Integrated
Interagency Pre-Application (IIP)
Process, including:
(i) The IIP initiation request, review
meeting request, and close-out meeting
request required by §§ 900.5, 900.8, and
900.9;
(ii) The IIP Process final meeting
summaries required by §§ 900.5, 900.8
and 900.9;
(iii) The IIP Process final resource
reports developed under § 900.6;
(iv) The final project-specific
schedule developed under §§ 900.7 and
900.8;
(v) Other documents submitted by the
project proponent as part of the IIP
Process or provided to the project
proponent as part of the IIP Process,
including but not limited to maps,
publicly available data, and other
supporting documentation; and
(vi) Communications between any
relevant Federal or non-Federal entity
and the project proponent regarding the
IIP Process; and
(2) All information assembled and
used by relevant Federal entities as the
basis for Federal authorizations and
related reviews following completion of
the IIP Process.
(b) Federal entities should include
DOE in all communications with the
project proponent related to the IIP
Process for the proposed electric
transmission project.
(c) DOE shall make the consolidated
docket available, as appropriate, to the
NEPA joint lead agency selected under
§ 900.11; any relevant Federal or nonFederal entity responsible for issuing an
authorization for the proposed project;
and any consulting parties per section
106 of the NHPA, consistent with 36
CFR part 800. DOE shall exclude or
redact privileged documents, as
appropriate.
PO 00000
Frm 00071
Fmt 4701
Sfmt 4700
35381
(d) Where necessary and appropriate,
DOE may require a project proponent to
contract with a qualified recordmanagement consultant to compile a
contemporaneous docket on behalf of all
participating agencies. Any such
contractor shall operate at the direction
of DOE, and DOE shall retain
responsibility and authority over the
content of the docket.
(e) Upon request, any member of the
public will be provided materials
included in the docket, excluding any
materials protected as CEII or otherwise
required or allowed to be withheld
under the Freedom of Information Act.
§ 900.11 NEPA lead agency and selection
of NEPA joint lead agency.
(a) For a proposed electric
transmission project that is accepted for
the Integrated Interagency PreApplication (IIP) Process under § 900.5,
DOE shall serve as the NEPA lead
agency to prepare an environmental
review document to serve the needs of
all relevant Federal entities. A NEPA
joint lead agency to prepare the
environmental review document may
also be designated pursuant to this
section, no later than by the IIP Process
review meeting.
(b) The NEPA joint lead agency, if
any, shall be the Federal entity with the
most significant interest in the
management of Federal lands or waters
that would be traversed or affected by
the proposed project. DOE shall make
this determination in consultation with
all Federal entities that manage Federal
lands or waters traversed or affected by
the proposed project. For a proposed
project that would traverse lands
managed by both the USDA and the
DOI, DOE will request that USDA and
DOI determine the appropriate NEPA
joint lead agency, if any.
§ 900.12
Environmental review.
(a) After the Integrated Interagency
Pre-Application (IIP) Process close-out
meeting, and after receipt of a relevant
application for a Federal authorization
or permit in accordance with the final
project-specific schedule, DOE and any
NEPA joint lead agency selected under
§ 900.11 shall prepare an environmental
review document for the proposed
electric transmission project designed to
serve the needs of all relevant Federal
entities.
(b) When preparing the environmental
review document, DOE and any NEPA
joint lead agency shall:
(1) Consider the materials developed
throughout the IIP Process; and
(2) Consult with relevant Federal
entities and relevant non-Federal
entities.
E:\FR\FM\01MYR2.SGM
01MYR2
35382
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES2
(c) DOE, in consultation with any
NEPA joint lead agency, is expected to
be responsible for:
(1) Identifying, contracting with,
directing, supervising, and arranging for
the payment of contractors, as
appropriate, to draft the environmental
review document; and
(2) Publishing the environmental
review document and any related
documents.
(d) Each Federal entity or non-Federal
entity that is responsible for issuing a
separate Federal authorization for the
proposed project shall:
(1) Identify all information and
analysis needed to make the
authorization decision; and
(2) Identify all alternatives that need
to be included, including a preferred
alternative, with respect to the
authorization.
VerDate Sep<11>2014
17:41 Apr 30, 2024
Jkt 262001
(e) DOE and any NEPA joint lead
agency, in consultation with relevant
Federal entities, shall identify the full
scope of alternatives for analysis,
including the no action alternative.
(f) To the maximum extent permitted
under law, relevant Federal entities
shall use the environmental review
document as the basis for all Federal
authorization decisions on the proposed
project. DOE and the relevant Federal
entities shall issue, except where
inappropriate or inefficient, a joint
decision document, which will include
the determination by the Secretary of a
duration for each land use authorization
issued on the proposed project.
(g) For all proposed projects, DOE
shall serve as lead agency for
consultation under the Endangered
Species Act (50 CFR 402.07) and section
PO 00000
Frm 00072
Fmt 4701
Sfmt 9990
106 of the NHPA (36 CFR 800.2(a)(2))
unless the relevant Federal entities
designate otherwise. DOE shall
coordinate these consultation processes
with the Federal agency with the most
significant interest in the management
of Federal lands or waters that would be
traversed or affected by the proposed
project or the designated lead agency.
§ 900.13
Severability.
The provisions of this part are
separate and severable from one
another. Should a court hold any
provision(s) to be stayed or invalid,
such action shall not affect any other
provision of this part and the remaining
provisions shall remain in effect.
[FR Doc. 2024–08157 Filed 4–30–24; 8:45 am]
BILLING CODE 6450–01–P
E:\FR\FM\01MYR2.SGM
01MYR2
Agencies
[Federal Register Volume 89, Number 85 (Wednesday, May 1, 2024)]
[Rules and Regulations]
[Pages 35312-35382]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-08157]
[[Page 35311]]
Vol. 89
Wednesday,
No. 85
May 1, 2024
Part II
Department of Energy
-----------------------------------------------------------------------
10 CFR Part 900
Coordination of Federal Authorizations for Electric Transmission
Facilities; Final Rule
Federal Register / Vol. 89 , No. 85 / Wednesday, May 1, 2024 / Rules
and Regulations
[[Page 35312]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
10 CFR Part 900
[DOE-HQ-2023-0050]
RIN 1901-AB62
Coordination of Federal Authorizations for Electric Transmission
Facilities
AGENCY: Grid Deployment Office, U.S. Department of Energy.
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: The Department of Energy (DOE) is amending its regulations for
the timely coordination of Federal authorizations for proposed
interstate electric transmission facilities pursuant to the Federal
Power Act (FPA). Specifically, DOE is establishing an integrated and
comprehensive Coordinated Interagency Transmission Authorizations and
Permits Program (CITAP Program); making participation in the Integrated
Interagency Pre-Application (IIP) Process a pre-condition for
assistance under the CITAP Program; re-establishing the IIP Process as
an iterative and collaborative process between the proponent of a
proposed electric transmission project and Federal and State agencies
to develop information needed for Federal authorizations; requiring the
project proponent to engage in robust engagement with the public,
communities of interest, and Indian Tribes during the IIP Process;
aligning and harmonizing the IIP Process and implementation of the FPA
with the Fixing America's Surface Transportation Act; and ensuring that
DOE may carry out its statutory obligation to prepare a single
environmental review document sufficient for the purposes of all
Federal authorizations necessary to site a proposed project.
DATES: This rule is effective May 31, 2024.
FOR FURTHER INFORMATION CONTACT: Liza Reed, U.S. Department of Energy,
Grid Deployment Office, 4H-065, 1000 Independence Avenue SW,
Washington, DC 20585. Telephone: (202) 586-2006. Email:
[email protected].
SUPPLEMENTARY INFORMATION:
I. Executive Summary
II. Background and Authority
III. Summary of the Final Rule
IV. Tribal Sovereignty
V. Terminology and Clarification Changes
VI. Discussion of Comments
A. General
B. Purpose and Scope
C. Qualifying Projects
D. Purpose and Scope of IIP Process
E. Public Participation in the IIP Process
F. Timing of IIP Process and NOI Issuance
G. IIP Process Initiation Request
H. Standard and Project-Specific Schedules
I. Selection of NEPA Lead and Joint Lead Agencies and
Environmental Review
J. Section 106 of the NHPA
K. Definitions
L. Resource Reports
M. Administrative Docket
N. Interaction With FPA 216(a) and FPA 216(b)
O. Miscellaneous
P. Out of Scope Comments
VII. Section-by-Section Analysis
VIII. Regulatory Review
A. Review Under Executive Orders 12866, 13563, and 14094
B. Review Under the Regulatory Flexibility Act
C. Review Under the Paperwork Reduction Act of 1995
D. Review Under the National Environmental Policy Act of 1969
E. Review Under Executive Order 12988
F. Review Under Executive Order 13132
G. Review Under Executive Order 13175
H. Review Under the Unfunded Mandates Reform Act of 1995
I. Review Under Executive Order 12630
J. Review Under Executive Order 13211
K. Review Under the Treasury and General Government
Appropriations Act, 1999
L. Review Under the Treasury and General Government
Appropriations Act, 2001
IX. Congressional Notification
X. Rehearing
XI. Approval by the Office of the Secretary of Energy
I. Executive Summary
In this final rule, the Department of Energy (DOE) is amending its
regulations under section 216(h) of the Federal Power Act (16 U.S.C.
824p(h)) (FPA) to establish a Coordinated Interagency Transmission
Authorizations and Permits Program (CITAP Program) under which DOE will
coordinate and expedite Federal authorizations and environmental
reviews required to site proposed electric transmission facilities,
which may include reviews pursuant to the National Environmental Policy
Act of 1969 (Pub. L. 91-190, as amended, 42 U.S.C. 4321 et seq.)
(NEPA), the National Historic Preservation Act (Pub. L. 89-665, as
amended, 54 U.S.C. 30010 et seq.) (NHPA), the Endangered Species Act of
1973 (Pub. L. 93-205, as amended, 16 U.S.C. 1531 et seq.) (ESA), and
evaluations necessary for authorizations under the Federal Land Policy
and Management Act (Pub. L. 94-579, as amended, 43 U.S.C. 1701 et
seq.). DOE coordination under this final rule will increase the
efficiency and effectiveness of the Federal authorization and review
process for proposed electric transmission facilities by establishing
pre-application procedures designed to collect the information needed
to perform efficient and timely Federal authorization and environmental
reviews, reducing duplication of effort through preparation of a single
environmental review document as the basis for all Federal decisions,
and setting binding schedules for the completion of all Federal
authorizations and environmental reviews. In doing so, this final rule
aims to reduce the time it takes to site and permit the electric
transmission infrastructure needed to ensure the delivery of reliable,
resilient and low-cost electricity to American homes and businesses.
Actions to enable more rapid deployment of electric transmission
are more important than ever. As DOE documented in its 2023 National
Transmission Needs Study, additional transmission capacity is needed in
nearly every region of the country to improve the reliability and
resilience of electric service, alleviate high costs caused by
transmission congestion and constraints that prevents low-cost energy
from reaching customers, and access new low-cost low carbon energy
supplies to serve increasing electricity demands.\1\ Over the past
decade additional transmission capacity has been added at half the rate
of the previous three decades, at a time when electricity demand is
increasing and new diverse sources of electricity generation are needed
to serve that demand and meet Federal, State, and consumer goals to
reduce greenhouse gas emissions from the electricity sector.\2\
Accelerating the current pace of transmission infrastructure investment
and deployment is needed to meet these objectives and will generate
multiple benefits to the public, including improved reliability and
resilience, lower electricity costs, additional economic activity, and
reduced greenhouse gas emissions. By enabling rapid development of
transmission capacity, the CITAP Program will help increase access to a
diversity of generation sources, reduce transmission congestion and
power-sector emissions, and deliver reliable, affordable power that
future consumers will need when and where they need it.
---------------------------------------------------------------------------
\1\ United States Department of Energy, National Transmission
Needs Study (Feb. 2023), available at: https://www.energy.gov/sites/default/files/2023-02/022423-DRAFTNeedsStudyforPublicComment.pdf.
\2\ Jenkins, J.D. et al. (2022) Electricity transmission is key
to unlock the full potential of the Inflation Reduction Act, Zenodo.
Available at: https://zenodo.org/record/
7106176#:~:text=Previously%2C%20REPEAT%20Project%20estimated%20that%2
0IRA%20could%20cut,from%20electric%20vehicles%2C%20heat%20pumps%2C%20
and%20other%20electrification.
---------------------------------------------------------------------------
On August 23, 2023, in accordance with section 216(h) of the FPA
and a
[[Page 35313]]
May 2023 Memorandum of Understanding (MOU) among nine Federal agencies
committing to expedite the siting, permitting, and construction of
electricity transmission infrastructure through more effective
implementation of section 216(h) of the FPA, DOE issued a notice of
proposed rulemaking (NOPR), to establish the CITAP Program. (88 FR
57011).\3\ Under the CITAP Program, the entity or individual heading
the project (``project proponent'') will work with DOE and other
Federal agencies to gather materials necessary to inform the completion
of authorizations and environmental reviews. These materials include
thirteen reports the project proponent will prepare that describe the
proposed project and its potential impacts on resources including land,
water, plant and animal life (``resource reports''); a summary of the
proposed project that will include details on which Federal
authorizations or permits may be necessary and the anticipated timeline
to completion of acquiring the described authorizations and permits;
and proposed project participation and public engagement plans, which
will outline opportunities for the public to participate in project
authorization decisions and ensure sufficient engagement with both
communities of interest and relevant stakeholders. This process of
collaborative information gathering is referred to as the ``Integrated
Interagency Pre-Application Process'' or ``IIP Process.''
---------------------------------------------------------------------------
\3\ The nine 2023 MOU signatory agencies are USDA, DOC, DOD,
DOE, DOI, EPA, Federal Permitting Steering Improvement Steering
Council (Permitting Council), CEQ, and the Office of Management and
Budget (OMB). The 2023 MOU is publicly available at https://www.whitehouse.gov/wp-content/uploads/2023/05/Final-Transmission-MOU-with-signatures-5-04-2023.pdf.
---------------------------------------------------------------------------
Under the CITAP Program, DOE will set intermediate milestones and
ultimate deadlines for the review of relevant authorizations and
environmental reviews that provide for their completion within two
years and establish DOE as the lead agency for the preparation of a
single environmental review document, in compliance with NEPA, that
supports the decisions of all relevant Federal entities.\4\ This final
rule confirms the CITAP Program and the restructured and improved IIP
Process as described in the NOPR and adopts revisions to the NOPR
proposals in response to comments regarding issues such as the Federal
evaluation timelines, approaches to environmental reviews, and levels
of details required for the Program.
---------------------------------------------------------------------------
\4\ Section 900.2 of the final rule defines ``Federal entity''
as any Federal agency or department. That section also defines
``relevant Federal entity'' as a Federal entity with jurisdictional
interests that may have an effect on a proposed electric
transmission project, that is responsible for issuing a Federal
authorization for the proposed project, that has relevant expertise
with respect to environmental and other issues pertinent to or
potentially affected by the proposed project, or that provides
funding for the proposed project. The term includes participating
agencies. The term includes a Federal entity with either permitting
or non-permitting authority; for example, those entities with which
consultation or review must be completed before a project may
commence, such as DOD for an examination of military test, training
or operational impacts.
---------------------------------------------------------------------------
The IIP Process is a project-proponent-driven process. Accordingly,
the time to complete the IIP Process and begin the time bound, two-year
Federal authorization and environmental review period depends on the
preparation and responsiveness of the project proponent. This final
rule establishes a series of checkpoints in the IIP Process (the three
anchor meetings described below) and requirements for the pre-
application materials that project proponents must develop to proceed
through the Process (principally, resource reports and public
participation and engagement plans, which are to be developed with
guidance from Federal entities). The timeline for completing the pre-
application process and proceeding through these checkpoints will
depend, in large part, on the readiness and responsiveness of project
proponents. As discussed further below, DOE has revised the NOPR
proposals in this final rule to reduce the time reserved for DOE to
review and respond to the requested information within the IIP Process
to just over six months. Coupled with the two-year timeline that DOE
and signatories to the 2023 Memorandum of Understanding Regarding
Facilitating Federal Authorizations for Electric Transmission
Facilities (2023 MOU) agreed to for review of applications and related
environmental review, DOE expects that the CITAP Program will
substantially reduce the time necessary for permitting of transmission
facilities.
In response to the NOPR, DOE received 50 comments during the public
comment period, as well as stakeholder input during the public webinar
and additional briefing provided by the Grid Deployment Office in DOE
that will be administering the CITAP Program. In this final rule, DOE
is making several changes to the regulatory text proposed in the NOPR
in response to public comments.
DOE received 27 comments in support of the CITAP Program, and
several specifically supporting the IIP Process, the Federal decision-
making timeline, and the requirement for the thirteen resource reports.
Commenters specifically lauded the resource reports for their early and
meaningful public engagement components, their effectiveness in
coordinating decision-making across different Federal agencies, and
their essential role in allowing the subsequent authorization and
environmental review processes to be completed within two years.
Commenters also affirmed the need for DOE to serve as the Lead Agency
for NEPA review, section 106 of the NHPA, and section 7 of the ESA for
projects in the CITAP Program to ensure that its objective of making
transmission permitting processing more effective and efficient is
realized.
The received comments were also instrumental in identifying
opportunities to streamline the IIP Process further to ensure that
these objectives are met. The IIP Process proposed in the NOPR would
have provided, at a maximum, 240 days for DOE evaluation and
determinations of completeness and readiness to move to the next steps
in the process. In response to comments requesting more efficiency, in
this final rule that timeline has been reduced by 55 days by
streamlining notification and convening timelines to now total 185 days
at a maximum. Additional reductions to documentation timelines, which
do not impact decision making, total 45 days, reducing all IIP Process
activity by 100 days. As noted previously, however, the total timeline
to complete the IIP Process will vary in each individual case based on
the project proponent's preparation and responsiveness and the
project's readiness to proceed to Federal authorization and
environmental reviews. Project proponents will move most quickly
through the IIP Process and Federal authorization and environment
review processes by ensuring their projects are ready to proceed and by
ensuring they are responsive to DOE and Federal agency requests for
information.
Section VI of this document discusses several other major issues
raised by commenters and provides DOE's responses.
II. Background and Authority
The electric transmission system is the backbone of the United
States' electricity system, connecting electricity generators to
distributors and customers across the nation. Electric transmission
facilities often traverse long distances and cross multiple
jurisdictions, including Federal, State, Tribal, and private lands. To
receive Federal financial support or build electric transmission
facilities on or through Federal lands and waters, project
[[Page 35314]]
developers often must secure authorizations from one or multiple
Federal agencies, which can take considerable time and result in costly
delays.
Recognizing the need for increased efficiency in the authorization
process for transmission facilities, the Energy Policy Act of 2005
(Pub. L. 109-58) (EPAct) established a national policy to enhance
coordination and communication among Federal agencies with authority to
site electric transmission facilities. Section 1221(a) of EPAct added a
new section 216 to Part II of the FPA, which sets forth provisions
relevant to the siting of interstate electric transmission facilities.
Section 216(h) of the FPA, ``Coordination of Federal Authorizations for
Transmission Facilities,'' requires DOE to coordinate all Federal
authorizations and related environmental reviews needed for siting
interstate electric transmission projects, including NEPA reviews,
permits, special use authorizations, certifications, opinions, or other
approvals required under Federal law.
Among other things, it authorizes DOE to act as the lead agency for
Federal coordination and reviews and requires the Secretary of Energy,
to the maximum extent practicable under Federal law, to coordinate the
Federal authorization and review process with any Indian Tribes, multi-
state entities, and State agencies that have their own separate
permitting and environmental reviews. 16 U.S.C. 824p(h)(2)-(3).
Relatedly, section 216(h) requires the Secretary to provide an
``expeditious'' pre-application mechanism for prospective project
proponents; directs the Secretary to establish prompt and binding
intermediate milestones and ultimate deadlines for the review of, and
Federal authorization decisions relating to, the proposed facility; and
provides a mechanism through which a project proponent or any State
where the facility would be located may appeal to the President for
review, if an agency fails to act within those deadlines or denies an
application. 16 U.S.C. 824p(h)(4), (h)(6). The statute also directs the
Secretary to prepare, in consultation with the affected agencies, a
single environmental review document to be used as the basis for all
decisions on the proposed project under Federal law, and to determine,
for each Federal land use authorization that must be issued, whether
the duration of such authorization is commensurate with the facility's
anticipated use. 16 U.S.C. 824p(h)(5)(A); (h)(8)(A).
As discussed in the proposed rule, in May 2023 DOE entered into an
implementing MOU with eight other agencies to unlock these benefits.
The 2023 MOU expanded upon prior efforts to ensure pre-construction
coordination and provides updated direction to Federal agencies in
expediting the siting, permitting, and construction of electric
transmission facilities. DOE subsequently published a NOPR in August
2023 to update and expand on its existing pre-application mechanism
provided in regulations at 10 CFR part 900. Through this rule, DOE
amends its section 216(h) implementing regulations to more effectively
implement this authority and better coordinate review of Federal
authorizations for proposed interstate electric transmission
facilities.
For the reasons explained in the following sections, in this final
rule, DOE adopts its proposal in the NOPR, with modifications discussed
below.
III. Summary of the Final Rule
This final rule is needed for DOE to update its regulations
implementing section 216(h) to establish the CITAP Program, improve the
IIP Process, and provide for the coordinated review of applications for
Federal authorizations necessary to site transmission facilities. DOE's
previous implementing regulations structured the IIP Process around two
anchor meetings: the Initial and Close-Out meetings. To inform Federal
agency coordination, project proponents were required to submit a
project summary, an affected environmental resources and impacts
summary, a summary of early identification of project issues, and data
including maps and geospatial information. Additionally, the
regulations included a process for identifying the NEPA lead agency and
for establishing a preliminary NEPA review schedule. These regulations
did not establish DOE as the lead agency for NEPA review, nor address
important environmental and resource reviews under NHPA or ESA.
Notably, these regulations did not establish a process through which
DOE would set binding milestones for environmental reviews and Federal
permitting and authorization decisions.
In this final rule, DOE first establishes a comprehensive and
integrated CITAP Program. The CITAP Program is the vehicle through
which DOE will implement its authority as defined in Section 216(h) of
the FPA, beginning with the IIP Process through the DOE-led
environmental review and including DOE's coordination of the schedule
for the Federal decisions on permits and authorizations.
Under the CITAP Program, DOE: (i) provides for an effective IIP
Process to facilitate timely submission of materials necessary to
inform Federal authorizations and related environmental reviews
required under Federal law; (ii) sets intermediate milestones and
ultimate deadlines for the review of such authorizations and
environmental reviews; and (iii) serves as the lead agency for the
preparation of a single environmental review document in compliance
with NEPA, designed to serve the needs of all relevant Federal entities
and effectively inform their corresponding Federal authorization
decisions. These elements of the CITAP Program are described in more
detail throughout this rule.
Second, pursuant to the FPA, DOE makes the IIP Process a mandatory
precondition for participation in the CITAP Program. A project
proponent's participation in the IIP Process is necessary for the
success of the other elements of the CITAP Program and for the
Secretary's satisfaction of the statutory obligations imposed by
section 216(h) and affords a unique opportunity for project proponents
to provide essential information and to coordinate with Federal
entities prior to submission of applications for Federal
authorizations. DOE has determined that it will not be able to fulfill
its role as lead agency under section 216(h)--including the
establishment of binding deadlines--for projects that do not complete
the IIP Process. DOE does not require the participation of any Federal
or non-Federal entity in the IIP Process; rather Federal entities have
agreed to participate through the 2023 MOU and non-Federal entities may
participate at their discretion. As discussed further below, DOE
concludes that the benefits of participating in the IIP Process, and
the resulting access to the CITAP Program, justify the costs to project
proponents. The CITAP Program will substantially accelerate the process
by which transmission projects are permitted and developed, and the
benefits of the expected reduction in permitting timelines are likely
to significantly exceed the cost of participating in the IIP Process.
Third, this final rule improves the IIP Process to ensure that it
provides project proponents and Federal entities an opportunity to
identify as early as possible potential environmental and community
impacts associated with a proposed project. The IIP Process is intended
to ensure that necessary information is provided to the relevant
Federal entities in a timely and coordinated fashion; it is also
intended to avoid the duplication of cost and effort that project
proponents and Federal entities face in navigating the
[[Page 35315]]
series of authorizations necessary to site a transmission line and to
allow both the project proponent and the Federal entities to avoid
time- and resource-consuming pitfalls that would otherwise appear
during the application process. Accordingly, DOE requires that project
proponents submit resource reports and public participation and
engagement plans, developed with guidance from Federal entities, and
participate in a series of iterative meetings to ensure that Federal
entities have ample opportunities to provide this guidance. The
resource reports are intended to develop data and materials that will
facilitate Federal entities' review of the project proponent's
applications under the applicable Federal statutes. The early
engagement facilitated by the submission of public participation and
engagement plans will inform a project proponent's development of a
proposed project. This early engagement begins before an application is
submitted to the Federal Government and provides opportunities for
Tribes and communities to express their views early in the process and
to share their concerns directly with project proponents. However, the
IIP Process does not relieve the relevant Federal entities of their
legal obligation to comply with applicable requirements to consult with
Tribes and engage with communities. This rule provides that the total
time for DOE reviews and responses in the IIP Process is 185 days.\5\
Based on that timeline for DOE decision-making, DOE expects that a
prepared and responsive project proponent could complete the IIP
Process within a year.
---------------------------------------------------------------------------
\5\ This excludes meeting information summaries, which DOE does
not categorize as review and response time that could impact a
project timeline, because preparation of required information for
subsequent IIP Process steps can happen in parallel.
---------------------------------------------------------------------------
Fourth, pursuant to Congress's express directive in section
216(h)(4), DOE introduces the standard schedule and project-specific
schedules, through which DOE will establish binding intermediate
milestones and ultimate deadlines for Federal authorizations and
related environmental reviews. The standard schedule identifies the
steps generally needed to complete decisions on all Federal
environmental reviews and authorizations for a proposed electric
transmission project, including recommended timing for each step so as
to allow final decisions on all Federal authorizations within two years
of the publication of a notice of intent (NOI) to prepare an
environmental review document. This document serves as a template for
the development of project-specific schedules. During the IIP Process,
DOE and relevant Federal entities will prepare a project-specific
schedule, informed by the standard schedule, that establishes prompt
and binding intermediate milestones and ultimate deadlines for the
review of, and Federal authorization decisions relating to, a proposed
electric transmission project, accounting for relevant factors
particular to the specific proposed project, including the need for
early and meaningful consultation with potentially affected Indian
Tribes and engagement with stakeholders.
Fifth, DOE simplifies the development of an administrative record
by incorporating the IIP Process administrative file into a single
docket that contains all the information assembled and utilized by the
relevant Federal entities as the basis for Federal authorizations and
related reviews. DOE will maintain that docket, which will be available
to the public upon request except as restricted due to confidentiality
or protected information processes. Access to, and restrictions of
access to, the docket will be addressed at the time of project-specific
implementation.
Sixth, DOE amends its regulations to provide that DOE will serve as
the lead NEPA agency and that, in collaboration with any NEPA joint
lead agency \6\ determined pursuant to procedures established by these
regulations and the 2023 MOU and in coordination with the relevant
Federal entities, DOE will prepare a single environmental review
document to serve as the NEPA document for all required Federal
authorizations. DOE will also serve as lead for consultation under
section 106 of the NHPA and section 7 of the ESA for projects in the
CITAP Program, unless the relevant Federal entities designate
otherwise. As additional projects utilize the CITAP Program, DOE
anticipates that it will be able to improve upon its NEPA processes,
ultimately leading to greater efficiencies for both project proponents
and Federal agencies. Relatedly, the rule provides that DOE and the
relevant Federal entities shall issue, except where inappropriate or
inefficient, a joint decision document.
---------------------------------------------------------------------------
\6\ As discussed in section V.D of this document, DOE is
replacing the term ``NEPA co-lead agency'' from the proposed
regulatory text with ``NEPA joint lead agency'' in this final rule.
The change is non-substantive. For clarity and readability, DOE uses
the term ``NEPA joint lead agency'' throughout the preamble in place
of ``NEPA co-lead agency'' even when discussing a comment or
document that originally referred to a ``NEPA co-lead agency.''
---------------------------------------------------------------------------
Finally, DOE provides that the primary scope of the CITAP Program
is on-shore high-voltage or regionally or nationally significant
transmission projects that are expected to require preparation of an
environmental impact statement (EIS) and establishes procedures through
which projects outside of that primary scope can seek a determination
of qualifying-project status from the Grid Deployment Office on a case-
by-case basis.
IV. Tribal Sovereignty
DOE affirms the sovereignty of Federally recognized Indian Tribes
and confirms that this final rule makes no changes to Federal agencies'
government-to-government responsibilities. Tribal sovereignty refers to
Federally recognized Indian Tribes' original, inherent authority to
govern themselves, their lands, and their resources. Because of their
unique status as sovereigns, Federally recognized Tribes have a direct,
government-to-government relationship with the Federal government. The
United States has a general, ongoing trust relationship with Indian
Tribes as well as with the Native Hawaiian Community. Neither section
216(h) nor this final rule in any way alters that relationship.
Tribal and Native Hawaiian consultation is a process for
communication between the Federal government and Indian Tribes and the
Native Hawaiian Community that is grounded in the government-to-
government or the government-to-sovereign relationship, respectively.
Tribal and Native Hawaiian consultation may be required as part of
compliance with section 106 of the NHPA, or may arise from other
Federal authorities such as Executive Order 13007 or the Presidential
Memorandum on Uniform Standards for Tribal Consultation (2022).
Agencies often consult with Indian Tribes and the Native Hawaiian
Community in conjunction with fulfilling their obligations under NEPA.
Consistent with these requirements and authorities, during
implementation of the CITAP Program, DOE commits to undertake Tribal
and Native Hawaiian consultation as appropriate. Also as appropriate,
DOE commits to designate Indian Tribes with special expertise regarding
a qualifying project, including knowledge about sacred sites that the
project could affect, that are eligible, to become cooperating agencies
under NEPA, and to consult with Indian Tribes and Native Hawaiian
Organizations as required by the NHPA in the Section 106 process.
Finally, DOE clarifies that the IIP Process, resource reports, and
other submissions are not
[[Page 35316]]
intended to, nor will they, satisfy DOE's or other Federal agencies'
legal obligations and responsibilities under the relevant statutes,
such as NEPA, NHPA, and ESA. The Federal agencies remain legally
responsible for their compliance with the applicable statutes.
V. Terminology and Clarification Changes
In this final rule, DOE has made a number of changes to ensure
consistent use of terminology across part 900.
A. ``Project Area'' v. ``Study Corridor'' v. ``Route''
The proposed rule used several terms related to areas. In this
final rule, DOE has ensured that the usage of these terms is
consistent. DOE clarifies here their meaning and use. For the area
containing the study corridors selected by the project proponent for
in-depth consideration and the immediate surroundings of the end points
of the proposed electric transmission facility, DOE uses the term
``project area.'' For a location within a project area where multiple
transmission line designs may be contemplated, DOE used the term
``study corridor''; within the project area, there may be multiple
study corridors. Within a given study corridor, DOE refers to
``potential routes'' or ``route segments''; within the study corridor,
there may be multiple potential routes or route segments.
Notably, DOE revises the definition of project area from what was
proposed by replacing ``containing all study corridors'' with
``containing the study corridors selected by the project proponent for
in-depth consideration'' to clarify the scope of this term.
Additionally, to clarify the role of study corridors, DOE added to the
study corridors definition that ``study corridor does not necessarily
coincide with `permit area,' `area of potential effect,' `action area,'
or other defined terms that are specific to types of regulatory
review.''
The proposed rule used multiple terms to refer to a route of an
electric transmission line that is considered during the IIP Process,
including ``proposed route'' and ``potential route.'' This final rule
replaces these synonymous terms with ``potential route.''
B. ``Potential Project'' v. ``Qualifying Project'' v. ``Transmission
Facility''
The proposed rule used several terms to refer to an electric
transmission facility that is proposed to be sited and constructed,
including ``transmission facility'' and ``electric transmission
facility.'' This final rule replaces these terms with ``proposed
electric transmission facility,'' which is shortened to ``proposed
facility'' when the identity of the facility is clear from the context.
Similarly, the proposed rule included a variety of phrases to refer
to an electric transmission project, including ``qualifying project,''
``electric transmission project,'' ``proposed qualifying project,''
``proposed undertaking'' and ``project.'' This final rule replaces
these terms with ``proposed electric transmission project,'' which is
shortened to ``proposed project'' when the identity of the project is
clear from the context. While the revision replaces the defined term
``qualifying project'' in a number of instances, the revision has no
substantive effect, because any proposed electric transmission project
that is accepted into the IIP Process must involve a proposed electric
transmission facility that is a qualifying project.
C. ``Plants'' v. ``Vegetation''
The proposed rule used several terms to describe plant life, such
as ``plant life,'' ``plants'' and ``vegetation.'' DOE has revised this
final rule to consistently use the term ``plants,'' except where the
rule uses an established term of art such as ``vegetation management''
or for consistency with Resource Report naming across agencies.
D. ``NEPA Co-Lead Agency'' vs ``NEPA Joint Lead Agency''
The proposed rule used the term ``NEPA co-lead agency'' to refer to
a Federal entity that may be designated under Sec. 900.11 to share the
responsibilities of DOE as lead agency in preparing an environmental
review document. DOE has revised the final rule to replace that term
with ``NEPA joint lead agency'' to better conform with the terminology
used in NEPA, as amended by Section 321 of the Fiscal Responsibility
Act of 2023 (Pub. L. 118-5). The change is non-substantive and only
reflects a difference in terminology.
VI. Discussion of Comments
A. General
In response to the NOPR, DOE received 50 sets of comments from the
following persons and groups:
Advanced Energy United (AEU), Alan Leiserson, American Clean Power
Association (ACP), American Council on Renewable Energy (ACORE),
American Electric Power Service Corporation (AEP), Americans for a
Clean Energy Grid (ACEG), Arizona Game and Fish Department (AZGFD),
Arizona State Historic Preservation Office (Arizona SHPO), California
Energy Commission and California Public Utilities Commission (CEC/
CPUC), Center for Biological Diversity (CBD), Clean Air Task Force
(CATF), Clean Energy Buyers Association (CEBA), ClearPath, Colorado
Governor's Office, Conrad Ko, Conservation and Renewable Energy
Coalition (CARE--comprised of the National Wildlife Federation, The
National Audubon Society, Environmental Law and Policy Center, and The
Nature Conservancy), Delaware Division of Historical and Cultural
Affairs (Delaware SHPO), EarthGrid PBC, Edison Electric Institute
(EEI), Environmental Defense Fund (EDF), Gallatin Power Partners, LLC
(Gallatin Power), Grid United LLC (Grid United), Idaho Governor's
Office of Energy and Mineral Resources, Idaho Power, James Birdwell,
Kentucky SHPO, Kris Pastoriza, Land Trust Alliance (LTA), Large Public
Power Council, Los Angeles Department of Water and Power (LADWP), mkron
mkron, National Association of Manufacturers, National Association of
Tribal Historic Preservation Officers (NATHPO), New Mexico Department
of Cultural Affairs Historic Preservation Division (NM SHPO), New York
Transmission Owners (NYTO), New York University School of Law Institute
for Policy Integrity (Policy Integrity), Niskanen Center, Oceti Sakowin
Power Authority (OSPA), Pew Charitable Trusts, PJM Interconnection, LLC
(PJM), Public Interest Organizations (PIOs, comprised of Earthjustice,
Natural Resources Defense Council, NW Energy Coalition, Southern
Environmental Law Center, Sustainable FERC Project, and WeACT for
Environmental Justice) (PIO), Santa Rosa Rancheria Tachi Yokut Tribe,
Scott Cooley, Solar Energy Industries Association (SEIA), State of
Colorado Governor's Office, State of Idaho Energy Office, Stoel Rives,
LLP, StopPATH WV, Todd Simmons, VEIR, Inc, and an anonymous commenter.
Of the 50 comments, 27 expressed general support for the proposed
rule and many supported specific aspects, including the IIP Process,
the Federal decision-making timelines, and the requirement for the
thirteen resource reports.\7\ Commenters specifically
[[Page 35317]]
lauded the resource reports for their early and meaningful public
engagement components, their effectiveness in coordinating decision-
making across different Federal agencies, and their essential role in
streamlining environmental permitting processes to two years.
---------------------------------------------------------------------------
\7\ Advanced Energy United; American Clean Power Association;
American Council on Renewable Energy; American Electric Power
Service Corporation; American Electric Power Service Corporation;
Americans for a Clean Energy Grid; Arizona Game and Fish Department;
California Energy Commission joint with California Public Utilities
Commission; Clean Air Task Force; Clean Energy Buyers Association;
Colorado Energy Office; Conrad Ko; Delaware State Historic
Preservation Office; Edison Electric Institute; Environmental
Defense Funds; Gallatin Power Partners, LLC; Grid United, LLC; New
York Transmission Owners; Niskanen Center; PJM Interconnection,
L.L.C.; Public Interest Organizations; Scott Cooley; Solar Energy
Industries Association; State of Idaho; Stoel Rives; The Pew
Charitable Trusts; and Todd Simmons.
---------------------------------------------------------------------------
Six commenters, NATHPO, Santa Rosa Rancheria Tachi Yokut Tribe,
StopPath WV, James Birdwell, ClearPath, and mkron mkron were not
supportive of the rulemaking.
The comments and DOE's responses are discussed in detail in the
subsequent subsections.
B. Purpose and Scope of Rule
DOE's Proposal
In the NOPR, DOE proposed to establish the CITAP Program; made the
IIP Process a mandatory precondition to participate in the CITAP
Program; described the procedures and timing of the IIP Process;
provided a process to set deadlines and milestones for projects;
designated DOE as the lead NEPA agency for the purposes of preparing a
single environmental impact statement; provided for earlier
coordination of and consultation between relevant Federal entities,
relevant non-Federal entities, and others pursuant to section 106 of
the NHPA; designated DOE as a co-lead agency for the section 106
process; and clarified applicability to qualifying projects. Finally,
DOE proposed to include a provision stating that participation in the
IIP Process does not alter any requirements to obtain necessary Federal
authorizations for electric transmission facilities nor does it alter
any responsibilities of the relevant Federal entities for environmental
review or consultation under applicable law.
Summary of Public Comments
DOE received several comments regarding DOE's authority to
establish the CITAP Program, the ability of the proposed CITAP Program
to meet the goals established by Congress in EPAct 2005, and the scope
of the proposed CITAP Program.
Regarding DOE's authority to establish the CITAP Program, EDF,
PIOs, and CATF observed that the CITAP Program is consistent with the
statutory language of section 216(h) of the FPA and with the 2023 MOU.
Pew Charitable Trusts expressed their support for several key elements
of the proposed rule, including the creation of a new framework for
coordinated Federal authorizations.
PIOs commented that DOE's proposed rule appropriately effectuates
the congressional intent underlying section 216(h) of the FPA, and that
DOE has sufficiently explained its proposed changes in the rule text by
demonstrating awareness of changing its policies and providing sound
reasons for doing so. PIOs also noted that although agencies do not
need to demonstrate that the reasons for the new policies are better
than the reasons for the old policies, they believed DOE has done so in
the proposed rule. On the other hand, NATHPO and the Santa Rosa
Rancheria Tachi Yokut Tribe requested that DOE withdraw the proposed
rule. NATHPO and the Santa Rosa Rancheria Tachi Yokut Tribe found the
proposed rule ``opaque'' and stated that they were unable to determine
if the rule represented a threat to Tribal Nations' cultural resources
and sacred places. Additionally, NATHPO and the Santa Rosa Rancheria
Tachi Yokut Tribe objected to the rule on the grounds that it contained
``numerous fundamental flaws,'' but only provided two examples, one
concerning the Communities of Interest report and one concerning the
Tribal Interests report. Specifically, regarding Communities of
Interest, the commenters expressed concern not with the proposed rule
text, but with a comment from DOE staff which the commenters believed
indicated this resource report would fulfill NHPA ``Section 106
responsibilities for determining the impact of projects on Tribal
Nations' cultural resources and sacred places.'' Regarding Resource
Report 13, the commenters expressed concerns with a comment from DOE
staff which the commenters believe indicated, contrary to the proposed
rule text, that this resource report would not include ``the effect of
projects on Tribal Nations' cultural resources.'' These concerns are
discussed in further detail and addressed in sections VI.J and
VI.L.xiii of this document. Finally, NATHPO and the Santa Rosa
Rancheria Tachi Yokut Tribe argued that DOE did not effectively engage
with Tribal Historic Preservation Officers (THPOs) while drafting the
proposed rule.
Regarding the ability of the proposed CITAP Program to meet the
stated goals of coordinating Federal authorizations and completing
environmental review within a 2-year schedule, PIOs stated they believe
the proposed rule will improve efficiency in Federal permitting for
transmission projects that are urgently needed to address the climate
crisis, improve reliability, and reduce congestion, and that the rule
will accelerate the development of infrastructure that will provide the
foundation for a clean and equitable energy grid. Pew Charitable Trusts
stated that it believes that the proposed rule offers an appropriately
streamlined approach to coordinating and facilitating transmission
project authorizations. Pew Charitable Trusts further noted that
previous studies of various types of infrastructure projects and
environmental reviews suggest that an open, transparent, and
comprehensive review process can work to the benefit of the public and
developers. Pew Charitable Trusts supported that the schedule can be
altered by DOE depending on the complexity of the review and other
factors. ACEG recommended adding ``prompt and binding'' to describe the
milestones and deadlines DOE will set in the schedule for Federal
decision-making. The State of Idaho agreed that Federal efforts to
reduce the time required for transmission project developers to receive
decisions on Federal authorizations are needed and agreed that such
actions should be encouraged. However, it also cautioned that those
efforts should be implemented in a way that avoids diminishing the
benefits of such reform by the addition of new permitting processes or
requirements. In contrast, StopPATH WV asked why the NOPR was written
in a way that presumes project approval, expressed concern that it was
not clear how this rulemaking would speed up timelines, and asserted
that if agencies could not change the project or deny it, then this
would be a bureaucratic waste of time. Kris Pastoriza requested
clarification on how the CITAP Program would change the jurisdiction of
the Federal Energy Regulatory Commission (FERC).
Regarding DOE's role as a lead agency for environmental review and
preparation of a single EIS, DOE received several comments in support
of the role and the consistency of this designation with existing
regulations and legislation. EDF commented that the rule is consistent
with Section 107 of the Fiscal Responsibility Act of 2023, which
amended NEPA to require the designation of a lead agency to coordinate
and schedule environmental review, as well as the related amendments to
NEPA implementing regulations proposed by the Council for Environmental
Quality. AEP, SEIA, Pew Charitable Trusts, EEI, and CEBA each
[[Page 35318]]
commented in support of DOE serving as the lead agency for developing a
single environmental review document. SEIA noted that currently a lack
of coordination among agencies causes unpredictability and inefficiency
in the environmental review process and effective coordination will
provide a more predictable and efficient process, a reduction in
unnecessary delays and costs, and heightened allowance for more robust
environmental reviews. ACEG recommended replacing the phrase
``environmental impact statement'' with ``NEPA document'' because that
phrasing more closely matches the statutory language in section
216(h)(5)(A) and because it accounts for the breadth of reviews
organized under the CITAP Program. EEI recommended that DOE must also
rely on the expertise of Federal agencies to ensure certainty and
minimize risk of post record decision litigation.
Regarding the authority of the Director of the Grid Deployment
Office to waive requirements, PIOs recommended establishing specific,
transparent criteria by which the Director of the Grid Deployment
Office can waive the review requirements for a proposed project that
are deemed unnecessary, duplicative, or impracticable and further
argued for the establishment of an appeal process for said waivers.
PIOs further provided that if DOE declines to implement criteria and an
appeals process that this final rule should eliminate the waiver
provision.
DOE Response
In this final rule, DOE retains the proposal in the NOPR to
establish the CITAP Program, which requires the IIP Process for CITAP
Program participation, sets binding schedules for Federal decision
making, and through which DOE will serve as lead agency for
environmental review and document preparation. In response to comments,
DOE makes minor changes to this final rule for clarification but
retains the full intent and scope of the proposed rule.
With respect to NATHPO's comment regarding outreach, DOE believes
that it engaged with appropriate entities regarding the rulemaking. DOE
met with the Advisory Council for Historic Preservation in developing
the language of the proposed rule and specifically with respect to
addressing potential impacts on cultural resources and consistency of
the CITAP Program with the requirements of the NHPA. Further, DOE
developed the NOPR with substantive engagement from other Federal
entities through the interagency review process. DOE then provided a
45-day public comment period during which DOE noticed and provided a
public webinar open to anyone to attend, and organized briefings with
interested groups to introduce the proposed rule and listen to
comments, to which NATHPO, THPOs, and State Historical Preservation
Officers (SHPOs) were invited. In this final rule, DOE has made changes
to provide additional clarity in the rule text and resolve ambiguity
when possible. In particular, DOE clarifies certain issues relating to
Tribal sovereignty, cultural resources, and the section 106 process in
response to specific concerns raised by NATHPO, Santa Rosa Rancheria
Tachi Yokut Tribe, and other commenters.
In response to the State of Idaho's concerns and Kris Pastoriza's
question regarding DOE implementing its coordinating authority, this
final rule neither establishes new permitting requirements nor alters
FERC's siting authority over transmission lines. Rather, DOE will be
coordinating agencies' exercise of their existing authorities. This
final rule maintains the NOPR provision that the IIP Process does not
alter any requirements to obtain necessary Federal or non-Federal
authorizations for electric transmission facilities. Similarly, DOE
disagrees with the assertion that the proposed rule presumes project
approval. The CITAP Program as described in the proposed rule and
confirmed in this final rule coordinates and sets a schedule for
Federal decision-making for qualified projects; it does not presume or
require the outcome of such Federal decisions. Regarding DOE's schedule
setting role in the CITAP Program, DOE agrees with ACEG's
recommendation to align the language of this final rule with the
authorizing statute and includes ``prompt and binding'' in the
description of milestones in this final rule.
Regarding DOE serving as lead agency for environmental review and
development of a single EIS designed to serve the needs of all relevant
Federal agencies and inform all Federal authorization decisions on the
proposed qualifying project, DOE acknowledges that it will rely on
other Federal agencies' expertise and believes the CITAP Program and
IIP Process confirmed in this final rule will ensure this occurs. DOE
agrees with ACEG's recommendation to align the language with the
authorizing statute and changes ``EIS'' to ``environmental review
document'' throughout this final rule.
DOE makes no changes to the proposal to allow the Director of the
Grid Deployment Office to waive requirements of the CITAP Program, nor
does DOE adopt specific criteria for such waivers. The purpose of the
CITAP Program and IIP Process is to allow DOE to perform a coordinating
function for electric transmission facilities seeking Federal
authorizations. Giving the Director the discretion to waive
requirements of the CITAP Program helps ensure that this coordination
function promotes efficiency and reduces duplication, as Congress
intended in FPA section 216(h). In addition, it is important to note
that a waiver granted by the Director under the CITAP Program would not
waive Federal requirements for authorizations or permits. For these
reasons, DOE is not persuaded that a lack of specific criteria for
waivers in this final rule will substantively harm any entity or party.
C. Qualifying Projects
DOE's Proposal
Section 216(h) of the FPA authorizes DOE to perform its
coordinating function for all transmission facilities seeking Federal
authorizations. In the NOPR, DOE proposed to prioritize the subset of
these facilities that benefit the most from DOE's coordinating role and
provide the most benefits to the American public from expeditious
environmental review.
In the NOPR, DOE proposed to define the subset of proposed electric
transmission facilities for which to perform its coordinating
function--called ``qualifying projects''--by defining two types of
qualification: qualification by attribute and qualification by request.
For qualification by attribute (set out in paragraph (1) of the
proposed definition of ``qualifying project''), DOE proposed in the
NOPR to categorize a proposed electric transmission facility as a
``qualifying project'' based on the presence of certain enumerated
attributes: it must be high-voltage (defined as 230 kV or above) or
``regionally or nationally significant''; it will be used for the
transmission of electric energy in interstate or international commerce
for sale at wholesale; it will need one or more Federal authorizations
expected to require preparation of an environmental impact statement
(EIS) pursuant to NEPA; it will not require authorization under section
8(p) of the Outer Continental Shelf Lands Act; the developer will not
require a construction or modification permit from FERC pursuant to
section 216(b) of the FPA; and the proposed transmission facility will
not be wholly located within the Electric Reliability Council of Texas
interconnection.
[[Page 35319]]
DOE proposed that, if a proposed electric transmission facility did
not qualify for the CITAP Program by attribute it could still qualify
by request, as provided by paragraph (2) of the proposed definition of
qualifying project and under the process set out in proposed Sec.
900.3 of the NOPR. Under that process, DOE proposed that the project
proponent file a request for coordination under the CITAP Program with
the Director of the Grid Deployment Office. Then, the Director of the
Grid Deployment Office, in consultation with the relevant Federal
entities, determine, within 30 calendar days of receipt of the request,
whether the proposed electric transmission facility is a ``qualifying
project.'' In the NOPR, DOE proposed that proposed electric
transmission facilities requiring a permit from FERC could be
qualifying projects if the request came from the FERC Chair. DOE also
proposed that projects proposed for authorization under section 8(p) of
the Outer Continental Shelf Lands Act (43 U.S.C. 1331 et seq.)
independent of any generation project may be qualifying projects at the
discretion of MOU signatory agencies.
DOE proposed to exclude from both types of qualification, and from
the CITAP Program altogether, any project proposed to be authorized
under section 8(p) of the Outer Continental Shelf Lands Act in
conjunction with a generation project and any project for which the
proposed transmission facility is wholly located within the Electric
Reliability Council of Texas interconnection.
Summary of Public Comments
DOE received several comments on the proposed definition of
``qualifying project.''
Starting with the qualification by attribute in paragraph (1) of
the definition, DOE received several comments on the specific proposed
attributes. Both AEP and Niskanen Center supported the proposed high-
voltage threshold of 230 kV or above. On the other hand, CEC/CPUC
opposed limiting eligibility based on a voltage threshold and instead
suggest expanding eligibility to proposed electric transmission
facilities at any voltage level.
With regard to DOE's proposal for qualification by attribute to
require that a proposed electric transmission facility that does not
satisfy the voltage threshold must be ``regionally or nationally
significant,'' both Niskanen Center and ClearPath asserted that this
alternative criterion is ambiguous. ClearPath recommended removing the
alternative criterion altogether and only allowing for high-voltage
transmission lines (i.e., those that satisfy the 230 kV or above
threshold) to be ``qualifying projects.'' Niskanen Center recommended
instead that DOE adopt factors that it will consider when determining
whether a proposed transmission facility is ``regionally or nationally
significant.'' Specifically, Niskanen Center suggested these factors:
``(i) a reduction in the congestion costs for generating and delivering
energy; (ii) a mitigation of weather and variable generation
uncertainty; (iii) an enhanced diversity of supply; (iv) any reduced or
avoided carbon emissions from the increased use of clean energy; and
(v) an increased market liquidity and competition.''
Moving to the other attributes, CEC/CPUC asked DOE to clarify how
it will determine whether all or part of a proposed electric
transmission facility will be ``used for the transmission of electric
energy in interstate or international commerce for sale at wholesale.''
Further, CEC/CPUC recommended that DOE expand the attribute list to
include a proposed electric transmission facility that will be used in
intrastate commerce because, according to CEC/CPUC, intrastate
transmission lines can traverse lands managed by several Federal
agencies, such that DOE coordination under the CITAP Program would
provide benefits to these projects as well. In the alternative, CEC/
CPUC asked that DOE clarify how a proposed intrastate transmission
facility, such as an onshore, intrastate transmission facility built to
support offshore wind development, that traverses Federal lands, could
be a ``qualifying project.''
On the proposed attribute that the proposed electric transmission
facility would need one or more Federal authorizations that require
preparation of an EIS pursuant to NEPA, AEP supported the proposal
whereas Niskanen Center and PIOs recommended expanding the proposal to
include proposed electric transmission facilities for which preparation
of either an environmental assessment (EA) or an EIS is anticipated.
PIOs also encouraged DOE to define which proposed electric transmission
facilities are ``expected'' to require preparation of an EIS and which
are expected to require preparation of an EA. In support of the
recommendation to expand eligibility to include proposed electric
transmission facilities for which preparation of an EA is expected (in
addition to those for which preparation of an EIS is expected), PIOs
argued that FERC regulations only require preparation of an EA for
proposed electric transmission facilities sited within an existing
right-of-way. If DOE adopts the proposal without PIOs' recommended
expansion, PIOs explained that such proposed electric transmission
facilities may be excluded from the CITAP Program, resulting in the
CITAP Program not providing its full purported benefits. Similar to
Niskanen Center and PIOs, CEC/CPUC recommended that DOE expand the
definition of ``qualifying project'' such that any proposed electric
transmission facility for which multiple Federal agency approvals will
be required are eligible, regardless of what type of document is
required under NEPA.
On qualification by request--i.e., when a project proponent seeks
qualifying-project status through a request to the Director of the Grid
Deployment Office--several commenters expressed concern about DOE's
level of discretion in the proposal. EEI requested examples of the
types of proposed electric transmission facilities that may be deemed
``qualifying projects'' by request. PIOs argued that the proposal
appears to be wholly discretionary, making it difficult for project
proponents, relevant regulators, and members of the public to
understand what proposed electric transmission facilities may be
eligible to participate in the CITAP Program. PIOs suggested that DOE
establish criteria for how DOE will evaluate requests, which would
assist project proponents in making well-grounded requests for
participation in the CITAP Program. According to PIOs, these criteria
should be: if the proposed electric transmission facility will benefit
from DOE's coordination in terms of expeditious authorizations; if
DOE's coordination will provide benefits that exceed the costs; and, if
Federal and non-Federal regulators have sufficient resources to
dedicate to the project's participation in the CITAP Program. PIOs also
suggested that DOE require project proponents to explain what portions
of their proposed electric transmission facility do not meet the
``qualifying project'' definition (i.e., the attributes) and how the
CITAP Program will facilitate Federal authorizations for the project or
be otherwise beneficial. Further, PIOs recommended that DOE adopt a
requirement that the Director of the Grid Deployment Office explain in
writing the determination of whether a project is deemed a ``qualifying
project'' by request. PIOs also recommended that if DOE rejects a
request to participate in the CITAP Program, project proponents should
be allowed to appeal the
[[Page 35320]]
decision to the Secretary of Energy. Similarly, ACP commented that the
proposed rule lacked clarity regarding what can qualify as an ``other
project'' and recommended that DOE provide further detail on the
aspects which it will consider when making this determination.
As proposed, qualification by request included a limitation in
Sec. 900.3(d): for a proposed electric transmission facility seeking a
permit from FERC pursuant to section 216(b) of the Federal Power Act,
DOE may only consider a request for coordination if the requestor is
FERC acting through its chair. ACORE recommended that DOE provide more
detailed guidance for this category of proposed electric transmission
facilities and for DOE to authorize relevant project proponents to
submit a petition requesting such a request from the FERC Chair.
Likewise, CEBA urged DOE to clarify the relationship between the
section 216(b) and section 216(h) processes and to explain how the FERC
Chair can request that a proposed electric transmission facility be
eligible to participate in the CITAP Program under section 216(h). Both
qualification by attribute and qualification by request included
limitations related to offshore transmission facilities. For
qualification by attribute, one listed attribute provided that the
proposed electric transmission facility would not require authorization
under section 8(p) of the Outer Continental Shelf Lands Act. Likewise,
for qualification by request, DOE proposed to exclude electric
transmission facilities proposed to be authorized under section 8(p) of
the Outer Continental Shelf Lands Act in conjunction with a generation
project. However, projects proposed to be authorized under section 8(p)
of the Outer Continental Shelf Lands Act could be allowed at the
discretion of the MOU signatory agencies (as defined in the proposed
rule) if the proposed offshore transmission facility is independent of
any generation project.
A number of commenters expressed concerns regarding DOE's treatment
of proposed offshore transmission facilities. Broadly, ACP, ACORE, and
PIOs contended that DOE must explain why the limitations on offshore
transmission facilities are included and how the CITAP Program will
apply to offshore transmission facilities in practice. ACP and ACORE
suggested that DOE establish a process to allow potential State-
proposed transmission facilities to participate in the CITAP Program
before a project developer is selected and include a process to enable
the Bureau of Ocean Energy Management or a State to engage or request
that a project participate in the CITAP Program.
More specific to DOE's proposal, NYTOs opposed the offshore
transmission facility-related attribute, asserting that its inclusion
prevents proposed offshore transmission facilities from benefiting from
the CITAP Program for project sections located closer to shore as well
as for project sections that fall under the scope of the Outer
Continental Shelf Lands Act. PIOs suggested removing the limitations in
qualification by request and instead allowing for proposed offshore
transmission facilities to take advantage of the CITAP Program without
the approval of the MOU signatories. At a minimum, PIOs suggested
removing the limitation that proposed offshore transmission facilities
tied to generation projects cannot participate in the CITAP Program.
Moreover, both PIOs and ACORE requested that DOE revise its proposal
from requiring agreement from all MOU signatories and instead only
requiring agreement from relevant MOU signatories participating in the
environmental review or authorization.
Finally, other commenters proposed revisions to DOE's proposed
definition of ``qualifying project'' based on advanced transmission
technologies and undergrounding. VEIR recommended that DOE include
superconductors in its definition of ``qualifying projects'' because,
according to VEIR, a superconductor can transfer more power at lower
voltages than qualifying high-voltage transmission lines. EarthGrid
asserted that underground transmission projects should be considered as
a distinct category. And CBD suggested that DOE require that a proposed
electric transmission facility be strictly necessary and that non-
transmission alternatives could not adequately address the issue
addressed by the proposed electric transmission facility before
allowing the project to participate in the CITAP Program.
DOE Response
In this final rule, DOE retains the proposal in the NOPR to provide
two types of qualification (qualification by attribute and
qualification by request) for proposed electric transmission facilities
to be ``qualifying projects.'' In response to commenters, DOE is making
the following revisions to the details of those two types of
qualification.
First, consistent with commenters' suggestions, DOE has adopted
factors that DOE may consider when determining that a proposed electric
transmission facility is a qualifying project. For qualification by
attribute, this final rule includes factors that DOE may consider when
assessing if a proposed electric transmission facility is regionally or
nationally significant. Similarly, for qualification by request, this
final rule includes factors that DOE may consider when assessing if a
proposed electric transmission facility is a qualifying project.
Second, this final rule removes the requirement that projects seeking a
permit from FERC under FPA section 216(b) may only be accepted into the
CITAP Program if requested by FERC acting through its chair and states
that the coordination between FERC and DOE on projects seeking permits
under FPA section 216(b) will be consistent with the relevant
delegation order governing DOE's coordination authority under FPA
section 216(h), which may change from time to time. Third, this final
rule also states that if DOE does not determine that a project is
qualifying project, DOE will provide the reasons for its finding in
writing.
DOE believes that the definition of ``qualifying project'' adopted
in this final rule appropriately balances the value of focusing DOE's
resources on those proposed electric transmission facilities for which
Federal coordination will be most impactful with the aims of the broad
grant of authority to DOE under FPA section 216(h). By initially
limiting the definition of ``qualifying project'' to those proposed
electric transmission facilities that qualify by attribute, i.e., those
that are high-voltage or regionally or nationally significant and that
possess the other listed attributes, DOE is targeting for Federal
coordination those complex proposed electric transmission facilities
that will reap the greatest benefits from the CITAP Program. DOE
believes that these proposed electric transmission facilities are also
likely to provide substantial benefits to consumers in the form of
congestion relief, emissions reductions, and increased reliability and
resilience, among other benefits, to ensure reliable, affordable power
can be delivered to consumers when and where they need it.
Qualification by request provides DOE with additional flexibility to
consider whether projects that do not meet the targeted attributes may
be appropriate for participation in the CITAP Program as well,
consistent with DOE's authority under section 216(h) to coordinate for
all transmission facilities seeking Federal authorizations.
As for specific aspects of the NOPR proposal, starting with
qualification by attribute and the voltage threshold therein (i.e.,
proposed electric transmission facilities must be 230 kV or above), DOE
declines to adopt the suggestion by CEC/CPUC to expand
[[Page 35321]]
eligibility to proposed transmission facilities at any voltage level.
Such an expansion, although permissible by the statute, would not be
the most effective use of DOE's authority because it would likely
result in DOE providing coordination for proposed transmission
facilities that would benefit less from the program. For example, DOE
could be obligated to provide coordination for less complex proposed
electric transmission facilities for which there is a low risk of
protracted Federal authorization and review timelines and thereby have
fewer resources to dedicate to those transmission facilities with more
complex permitting requirements and/or more Federal authorizations and
thus more risk of protracted review timelines in the absence of DOE
coordination. Nonetheless, DOE acknowledges that voltage alone does not
determine complexity nor whether the proposed transmission facility may
benefit from participation in the CITAP Program. That is why this final
rule provides multiple avenues for lower-voltage proposed transmission
facilities to be ``qualifying projects,'' whether because they are
``regionally or nationally significant'' or because they are determined
to be qualifying projects by request to the Director of the Grid
Deployment Office, on a case-by-case basis. In addition, satisfying the
high-voltage threshold alone does not make a proposed transmission
facility a ``qualifying project;'' it still must demonstrate the
attributes listed in this final rule.
As for the alternative criterion under qualification by attribute--
whether the proposed transmission facility is ``regionally or
nationally significant''--DOE declines to remove this criterion but
agrees that the proposal was ambiguous and therefore adopts clarifying
revisions in this final rule. DOE believes that this alternative to the
voltage threshold is important to ensure that lower-voltage
transmission facilities that may benefit from participation in the
CITAP Program have an avenue to be ``qualifying projects,'' as
explained in the prior paragraph. Nevertheless, DOE appreciates
commenters' requests for greater transparency and thus adopts factors
to guide DOE's determination whether a proposed transmission facility
is ``regionally or nationally significant.''
In particular, DOE adopts regulations in this final rule that
provide that, in determining whether a proposed transmission facility
is ``regionally or nationally significant,'' DOE will consider whether
a proposed transmission facility will reduce congestion costs, mitigate
uncertainty, and enhance supply diversity. These factors are consistent
with the overarching goals of focusing the CITAP Program on proposed
transmission facilities for which DOE's coordination will be most
impactful. The adopted regulations provide that DOE may consider other
factors as well. This discretion is important to ensure that DOE has
flexibility to best use its resources to provide Federal coordination
where consistent with the goals of the CITAP Program and available
resources. As explained in DOE's 2023 Needs Study, transmission
infrastructure improvements can benefit consumers by improving grid
reliability, resource adequacy, and resilience of the power system, as
well as reducing congestion and losses and enabling access to clean,
diverse energy supply. While transmission that addresses unnecessarily
high costs to consumers may be regionally or nationally significant, so
too may be transmission that reduces the vulnerability of the electric
system to disruptive events, which risk high costs and service
interruptions. The benefits of transmission also extend beyond the
power system--to increased employment, tax revenues, and other economic
development benefits. These benefits are all relevant to DOE's
determination of whether a transmission line is ``regionally or
nationally significant.''
Although Niskanen Center suggested two additional factors for DOE
to list as part of its determination as to whether a proposed electric
transmission facility is ``regionally or nationally significant''
beyond those adopted herein (specifically focused on reduced or avoided
carbon emissions and increased market liquidity and competition from
the proposed electric transmission facility), DOE declines to adopt
additional factors. For one, project proponents are unlikely to have
substantial information at the stage of development recommended for
initiation of the IIP Process for DOE to evaluate vis-[agrave]-vis
these recommended factors. If such information is available, though,
DOE may nevertheless consider it because, as explained above, DOE is
maintaining discretion to consider other factors as part of its
assessment of whether a proposed transmission facility is ``regionally
or national significant.''
As for the proposed attribute concerning whether all or part of a
proposed transmission facility will be ``used for the transmission of
electric energy in interstate or international commerce for sale at
wholesale,'' DOE declines to provide further clarification in this
final rule because this determination will be made based on the facts
and circumstances of the proposed electric transmission facility
seeking DOE coordination at the time of application. DOE expects that
this determination will be informed by relevant precedent interpreting
similar language in other provisions of the FPA, though DOE is not
bound by that precedent in interpreting its own regulatory language.
DOE declines to expand the listed attributes of a qualifying
proposed electric transmission facility to also include intrastate
transmission facilities. As previously explained, DOE's intent in
defining a subset of electric transmission facilities for which DOE
will conduct Federal coordination is to focus on where the CITAP
Program is likely to be most impactful. While intrastate transmission
facilities can have significant benefits, they are generally less
likely to be the types of facilities that DOE expects will reap the
greatest benefits from DOE's coordination or that would provide the
greatest benefits to consumers as a result of more efficient permitting
of critical transmission infrastructure. Nonetheless, DOE does not
prohibit proponents of intrastate transmission facilities (e.g., high-
voltage intrastate transmission facilities that may require multiple
Federal authorizations) from seeking qualification by request.
Regarding the proposed attribute that a proposed electric
transmission facility would need one or more Federal authorizations
that require preparation of an EIS pursuant to NEPA, DOE declines to
make the changes suggested by Niskanen Center, PIOs, and CEC/CPUC. As
explained above, DOE is aiming to identify as ``qualifying projects''
those proposed electric transmission facilities for which DOE
coordination under the CITAP Program is likely to be most impactful and
to yield the greatest benefits for consumers. DOE believes that
focusing on proposed electric transmission facilities for which
preparation of an EIS is expected is an appropriate factor for
narrowing the list of potential electric transmission facilities for
DOE coordination because an EIS is typically needed for more complex
projects. Preparation of an EIS is also a longer, more involved process
and one that poses a greater risk of delays absent interagency
coordination. Note that, although qualification by attribute is limited
to those for which an EIS is likely required, qualification by request
does not have this limitation, such that a project proponent is
permitted to request DOE coordination even if an EIS
[[Page 35322]]
is not expected and seek a determination from the Director of the Grid
Deployment Office on eligibility for the CITAP Program. As for the
request that DOE define which proposed transmission facilities are
expected to require an EIS, DOE declines to do so in this final rule.
DOE and its fellow agencies will apply NEPA and its implementing
regulations and will follow applicable regulations pursuant to NEPA, as
will other relevant Federal agencies, to determine whether an EIS needs
to be prepared, and those same regulations will inform any expectations
as to whether an EIS is likely to be required.
Regarding qualification by request, DOE agrees with commenters that
criteria regarding the types of proposed electric transmission
facilities that may be deemed ``qualifying projects'' under this
process would be beneficial to project proponents, and ultimately to
DOE in identifying the subset of projects that best suit the CITAP
Program's goals. Consequently, DOE adopts criteria in this final rule
that the Director of the Grid Deployment Office may consider when
evaluating a request to determine whether a proposed electric
transmission facility is a ``qualifying project.'' DOE will consider
whether a proposed electric transmission facility will benefit from
coordination under the CITAP program, reduce congestion costs, mitigate
uncertainty, and enhance supply diversity. These factors are consistent
with the overarching goals of focusing the CITAP Program on proposed
electric transmission facilities for which DOE's coordination will be
most impactful, to the ultimate benefit of consumers via reduced
congestion and enhanced reliability and resilience, among other
benefits. DOE believes the remaining discretion for DOE to determine
which proposed electric transmission facilities are ``qualifying
projects'' is consistent with the statutory framework that permits DOE
to coordinate the Federal authorizations necessary for any transmission
facility and the aim of the section 216(h) itself, notably the timely
permitting of transmission projects.
DOE agrees that it should explain its determinations of whether
qualification by request is granted in writing and consequently
establishes a requirement for such an explanation in this final rule.
DOE makes no revisions in response to the suggestion that an
appeals process be incorporated into the rule text for non-qualifying
projects. DOE notes that any project not accepted under qualification
by attribute may seek qualification by request of the Director of the
Grid Deployment Office, and that this final rule does not disallow
projects from resubmitting materials.
Turning to the proposed limitation to qualification by request for
a proposed electric transmission facility seeking a permit from FERC
pursuant to section 216(b) of the FPA, which stated that DOE may only
consider a request for coordination if the requestor is FERC acting
through its chair, DOE revises its proposal in this final rule to
clarify that the request for Federal coordination for proposed
transmission facilities seeking a permit from FERC under section 216(b)
must be consistent with Delegation Order No. 1-DEL-FERC-2006 or any
similar, subsequent delegation to FERC, which depend on the mutual and
continuing agreement of both agencies. With respect to CEBA and ACORE's
requests for more detail on the procedures for the FERC Chair to
request that a proposed electric transmission facility be eligible to
participate in the CITAP Program, such procedures will depend on the
state of any delegations of DOE's authority under FPA section 216(h);
therefore, DOE finds that clarifying these procedures is best done
through guidance outside the rulemaking process. Similarly, with
respect to ACORE's request to be able to submit a petition for the FERC
Chair to request DOE to consider a request for assistance under the
proposed section, the removal of that section in this final rule
obviates the need for such a process to be established by DOE and the
establishment of any processes at FERC are outside the scope of this
rulemaking.
With respect to the treatment of offshore transmission facilities,
commenters expressed concerns with the limitations related to offshore
transmission facilities and sought further explanation, at a minimum.
DOE adopts the proposal to exclude transmission facilities proposed to
be authorized under section 8(p) of the Outer Continental Shelf Lands
Act in conjunction with a generation project. DOE and the 2023 MOU
signatories determined that offshore transmission facilities connected
to generation projects should not be eligible for participation in the
CITAP Program because the authorizations of, and permits for, these
transmission facilities are typically included in the authorizations
and permits for the connected generation projects. Coordinating Federal
authorizations for generation projects, and reducing timelines for
joint transmission-generation projects with interdependent permitting
requirements, are beyond the scope of the 2023 MOU and the CITAP
Program. This limitation allows DOE to focus its resources on
addressing known challenges for transmission facility permitting.
With respect offshore transmission facilities whose Federal
authorizations and project development are independent of generation
development, DOE is finalizing an approach consistent with the 2023
MOU. For qualification by attribute, DOE declines to remove the
requirement that the proposed electric transmission facility will not
require authorization under section 8(p) of the Outer Continental Shelf
Lands Act. Excluding offshore transmission from the qualification by
attribute will facilitate a more efficient allocation of resources.
Shared offshore transmission is a nascent industry with unique and
unsettled permitting issues. Considering proposed offshore transmission
facilities as potentially eligible for the CITAP Program in
consultation with the MOU signatories, which is provided under
qualification by request, will allow DOE to adopt a more tailored and
responsive approach to this new industry.
In order for offshore transmission facilities to be eligible for
the CITAP Program via qualification by request, DOE proposed, and
adopts here, the requirement that the MOU signatories must agree to DOE
coordination for offshore transmission facilities for the reasons
explained in the prior paragraph. DOE declines to only require
agreement from those MOU signatories that are authorizing Federal
agencies. DOE is unpersuaded that a single, non-authorizing agency
would unilaterally hold up a proposed offshore transmission facility's
eligibility for the CITAP Program, such that those agencies should not
be allowed to participate in the eligibility decision making. Instead,
DOE believes that continuing the coordination demonstrated by the MOU
is consistent with the spirit of the CITAP Program and important for
keeping all relevant agencies involved in ongoing development of
offshore transmission permitting.
DOE also declines to establish a process to allow potential State-
awarded transmission facilities to participate and to enable the Bureau
of Ocean Energy Management or a State to request that a project
participate, as ACP and ACORE suggested. At this time, DOE is focusing
the CITAP Program on addressing well-documented and understood Federal
authorization issues via improved coordination for a subset of proposed
electric transmission facilities for which DOE coordination is likely
to be most impactful. DOE is not persuaded that
[[Page 35323]]
creating a process for entities other than the project proponent to
request participation for a proposed project in the CITAP Program is
necessary to provide the benefits of the program to a project. DOE may
consider revising its approach to offshore transmission facilities in
future rulemakings pursuant to FPA section 216(h).
Concerning commenters' proposed revisions to the definition of
``qualifying project'' based on advanced transmission technologies or
undergrounding, DOE declines to adopt such revisions. As explained
throughout this section, DOE's approach is targeted towards proposed
transmission facilities that are likely facing the types of permitting
challenges for which FPA section 216(h) and the CITAP Program were
created. Commenters provide no evidence to suggest that superconductor
permitting or undergrounding are unique as to warrant special
recognition within the definition of ``qualifying project.'' This is
not to say that a proponent of a transmission facility that contains
these features cannot also be a ``qualifying project'' under DOE's
adopted definition.
Finally, DOE declines to adopt CBD's suggestion that DOE impose a
necessity test for proposed electric transmission facilities compared
to non-transmission alternatives as a gateway to participation in the
CITAP Program. Congress directed DOE to coordinate the authorizations
necessary for the siting of transmission lines. DOE understands that to
mean that Congress believes transmission lines are necessary and that
Congress did not intend to supplant existing transmission planning
processes. Through the CITAP Program, DOE will coordinate
authorizations for transmission lines, which remain subject to the
statutes relevant to their authorization, including NEPA. Through these
statutes and their associated environmental review processes that DOE
will coordinate, reasonable alternatives will be considered by the
appropriate Federal agency as appropriate, which may or may not include
non-transmission alternatives.
D. Purpose and Scope of the IIP Process
DOE's Proposal
Under the proposed rule, the IIP Process is intended for qualifying
project proponents who have sufficiently advanced their project such
that they have identified potential study corridors and/or potential
routes and the proposed locations of any intermediate substations. DOE
proposed to establish the IIP Process as a mandatory prerequisite for
coordination under the CITAP Program and require the submission of
thirteen project proponent resource reports that will serve as inputs,
as appropriate, into the relevant Federal analyses and facilitate early
identification of project issues. Within these resource reports, DOE
proposed to require reasonably foreseeable information in three of
them: in the General Project Summary, DOE proposed to require
reasonably foreseeable plans for future expansion of facilities and
specific generation resources that are known or reasonably foreseen to
be developed or interconnected; in the air quality and noise effects
report, DOE proposed to require estimates on reasonably foreseeable
emissions construction, operation, and maintenance, and reasonably
foreseeable changes in greenhouse gas emissions and indirect emissions;
and in the Reliability, Resilience, and Safety report, DOE proposed to
require a description of the reasonably foreseeable impacts from a
failure of the proposed facility.
DOE also proposed to also establish the IIP Process as an iterative
process anchored by three meetings, which function as milestones in the
process: the initial meeting, review meeting, and close-out meeting.
DOE proposed in the NOPR to require the project proponent to submit an
initiation request containing certain information to DOE to initiate
the IIP Process, including a summary of the qualifying project not to
exceed 10 single-spaced pages and a project participation plan not to
exceed 10 single-spaced pages. DOE also proposed to require the
proponent to submit meeting review requests containing certain
information to DOE prior to each of the three meetings. DOE proposed
that the project proponent submit incomplete information so long as an
acceptable reason for the absence of the information and an acceptable
timeline for filing it is provided, and it provided the Director with
discretion to waive any requirement imposed on a project proponent if
the Director determines that that the requirement is unnecessary,
duplicative, or impracticable under the relevant circumstances.
The proposed rule explained that the IIP Process would ensure early
interaction between the project proponent, relevant Federal entities,
and relevant non-Federal entities, and that DOE would, to the maximum
extent practicable and consistent with Federal law, coordinate the IIP
Process with any relevant non-Federal entities. DOE also proposed in
the NOPR that the IIP Process did not preclude additional
communications between the project proponent and relevant Federal
entities outside the IIP Process meetings.
Additionally, the NOPR proposed to provide a process by which a
person may submit confidential information during the IIP Process or to
request designation of information containing Critical Electric
Infrastructure Information (CEII); these provisions established the
mechanisms through which the IIP Process complied with 10 CFR 1004.11
and 1004.13.
In the NOPR, DOE specifically sought comment on the page
limitations and on the resource report requirements to avoid, to the
maximum extent practicable, duplication in these requirements.
Summary of Public Comments
DOE received several comments that addressed the purpose and scope
of the IIP Process including comments on the IIP Process as a
prerequisite for DOE coordination; the level of detail required during
the IIP Process and in resource reports, including page limits and
reasonably foreseeable impacts; the role of the three anchor meetings;
participation of Federal and non-Federal entities; and protection of
confidential information and/or CEII. Comments to specific resource
report requirements are addressed in section VI.L of this document on
an individual report basis.
DOE received many comments in support of the proposed IIP Process.
Grid United, PIOs, State of Colorado Governor's Office, EEI, ACP,
ACORE, PJM, and CEBA expressed support for the revitalized IIP Process
proposed in the NOPR. PIOs stated that the IIP Process will help
Federal agencies coordinate information exchange that is necessary to
fulfill their individual statutory mandates, avoid duplication of cost
and effort for project proponents, and reduce the potential for
unexpected delays later in the permitting process. PIOs also agreed
with DOE that, by increasing the pace of transmission development
through the IIP Process, the proposed rule will confer significant
public benefits. The State of Colorado Governor's Office recognized
that the IIP Process would provide developers a uniform mechanism for
projects to identify siting constraints and opportunities, engage with
Indian Tribes, local communities, and other stakeholders, and to gather
information that would serve as inputs, as appropriate, into Federal
authorization decisions. EEI and ACP recognized the potential benefits
to be gained from the IIP Process and encouraged DOE to move swiftly to
both finalize the proposed approach and commit to
[[Page 35324]]
working closely with project proponents to ensure that the IIP Process
produces the promised results. EEI stated its belief that by
collaborating with electric companies, DOE can significantly increase
the efficiency of the process and reduce the time needed for NEPA
reviews while ensuring environmental integrity and project deployment.
ACP and ACORE both supported the mandatory nature of the IIP
Process as a prerequisite to participation in the CITAP Program,
provided that it serves its intended objective of enhancing
coordination, reducing permitting timelines, and minimizing
duplication. ACP and ACORE noted that the IIP Process's early
environmental review could conserve resources for public and private
participations. PJM noted that the requirement should help avoid the
current multi-agency piecemeal approach.
DOE also received comments generally in support of the
establishment of the resource reports. AEU and the CARE Coalition
expressed support for the thirteen resource reports proposed by DOE.
AEU commented that the resource reports provided a comprehensive and
wide-ranging analysis of the project. CARE Coalition commented that the
resource reports were sufficiently comprehensive and detailed to enable
Federal agencies, State and Tribal authorities, stakeholders, and the
public to adequately review the project. AZGFD explained that the
heightened consideration for resources through submitting 13 resource
reports early in the process enables coordination and prevents
implementation delays. It also stated that in some cases, adequate
assessment of resources could take multiple years and multiple
revisions before Federal environmental review is complete.
However, while commenters were broadly supportive, some commenters
suggested changes to the level of detail required during the IIP
Process and resource reports, indicating these would add flexibility
and avoid what they perceived as unnecessary or burdensome tasks. Pew
Charitable Trusts, in response to potential opposition to the level of
information required in the pre-application phase, cited previous
studies that conclude that a transparent and thorough siting process
can benefit both the public and developers. AEP emphasized that an IIP
Process should only be mandatory if it (1) informs the NEPA process and
(2) minimizes duplication by project proponents and Federal entities.
AEP noted that the IIP Process should also conserve the resources of
project developers by actively encouraging permitting authorities to
rely on the IIP Process's early environmental review. AEP also urged
DOE to coordinate with transmission developers to enhance efficiency
and protect environmental objectives. ACP cautioned against a
burdensome pre-application phase and encouraged DOE to demand a level
of information that is appropriate for NEPA scoping and consistent with
the project's development. ACEG agreed with these assertions, adding
that the level of information required in the IIP Process should be
appropriate to support the relevant Federal entities' reviews and
consultations, including under NEPA, ESA, and NHPA. ACEG emphasized the
importance of reasonable and flexible demands. Similarly, CEBA
cautioned against an IIP Process that was too complicated or time
consuming. ACORE noted that the timeline for the submission of
information in the IIP Process should align with when developers have
the needed information and recommended that DOE provide some
flexibility in those instances when the full scope of the information
required in the IIP reports is not yet available. The NYTOs also
suggested DOE should ensure that its data requests and sufficiency
determinations align with the reliable data and information standards
now set forth in sections 102(E) and 106(b)(3) of NEPA. These NEPA
standards emphasize the use of reliable data and explicitly provide in
NEPA section 106(b)(3)(B) that in making a determination regarding the
level of review under NEPA, an agency ``is not required to undertake
new scientific or technical research unless the new scientific or
technical research is essential to a reasoned choice among
alternatives, and the overall costs and time frame of obtaining it are
not unreasonable.'' Similarly, Grid United recommended that DOE should
consider section 106(b)(3) of NEPA in determining the level of
information that is sufficient for each IIP Process meeting. AEP
cautioned against a CITAP or IIP Process that duplicates or exceeds
State regulatory application requirements.
Several comments addressed the level of detail required in the
resource reports and the burden this would represent to the project
proponent. ACP expressed concerns with the level of time and effort
required for the development and submission of DOE's proposed resource
reports so early in the process, when their usefulness in NEPA's EIS
review process is uncertain, and urged DOE to consider that there may
be limited information available in the early stages of permitting. ACP
requested that the mandatory ``shall'' language be changed to
``should'' or ``to the extent practicable.'' ACEG, SEIA, and CEBA noted
that DOE needs to strike a balance between requiring enough information
to be helpful in streamlining the review but not making requirements so
strict that project proponents are discouraged. ACEG stated that
information required in the resource reports must be limited to the
information available at the time of submission, as this is a
preliminary stage and developers should not be discouraged from
applying if they do not yet have all the information. ACEG recommended
that the detail of each resource report must be commensurate with the
level of available information at the time of the submission.
Relatedly, DOE received several comments regarding the requirements
that project proponents account for reasonably foreseeable effects.
PIOs commented in support of the proposed rule's requirement to assess
climate impacts. PIOs explained that the proposed rule's requirements
that resource reports account for generation resources that are
reasonably foreseen to be developed or interconnected and for
reasonably foreseeable changes in emissions will ensure a rigorous
environmental analysis that properly accounts for the project's climate
impacts and are well-founded in NEPA's plain text and implementing
regulations, CEQ guidance, and judicial precedent. Policy Integrity
provided similar rationale and additionally indicated that providing
such data would be ``relatively easy'' for proponents. Policy Integrity
elaborated that FERC has historically required such estimates from
transmission developers, that developers have previously submitted
these data and analysis to both DOE and FERC, and that power system
emissions estimates are accessible through readily available modeling
software. Along similar lines, AEU commented that the resource reports
are comprehensive and require a wide-ranging analysis of the project,
and that the requirement to describe reasonably foreseeable generation
resources is especially beneficial because it illustrates the project's
value and benefits to the larger regional and interregional grid.
On the other hand, CATF suggested that instead of requiring project
proponents to describe reasonably foreseeable generation resources, DOE
should request this specific information only for generator
interconnections designed to connect specific generation resources to
the bulk power system.
[[Page 35325]]
CATF explained that it may be difficult for certain qualifying projects
to determine the scope of what generation resources are reasonably
foreseeable. Accordingly, CATF recommended that DOE not require project
proponents to determine associated generation resources where
burdensome, speculative, and of limited value to decision makers, and
revise the provision to include only ``specific'' generation resources.
CATF cited to judicial decisions to support the proposition that an
analysis of foreseeable generation is not required where the generation
would likely have occurred even absent the project. ClearPath offered
additional criticisms of the foreseeable generation requirement.
ClearPath urged DOE not to exceed its jurisdiction to conduct
environmental reviews by including additional requirements without
consulting CEQ, and stated that DOE's requirements to consider indirect
impacts of the project and identify effects from existing or reasonably
foreseeable projects are beyond DOE's statutory authority and are
contrary to CEQ Guidance. ClearPath recommended that DOE limit IIP
Process requirements, and subsequent review in an EIS, to only an
electric transmission line and its attendant facilities within Federal
jurisdiction. Finally, the NM SHPO inquired generally about foreseeable
generation, and whether foreseeable development will be considered in
the assessment of historic properties under NHPA section 106 and its
implementing regulations.
DOE also received comments on the iterative nature of the IIP
Process and the role and scope of the three anchor meetings. While ACP
approved of the general structure of anchor meetings, ACP emphasized
the importance of flexibility in order to accommodate proposed projects
that already have conducted significant Federal and State outreach or
have agency-specific reporting that may differ in approach and timing
to the IIP. ACP also suggested that DOE clarify how potential route
changes can be accommodated without restarting the process, and that
the final rule provide specific criteria that DOE and relevant Federal
entities would follow in their consideration of adding, deleting, or
modifying these routes.
ACEG suggested that DOE amend the proposed rule to strike or
significantly modify its ``sufficiency'' standard for scheduling
meetings, which DOE proposed to be required for scheduling each of the
three required anchor meeting requests. ACEG and NYTOs commented that
DOE should only find a meeting request insufficient when the
information provided in the meeting request is insufficient to support
a productive meeting, e.g., a review meeting request should only
require sufficient information to hold a productive discussion on the
initial resource reports. For an example, NYTOs stated that as an
``initial review meeting'' is intended to identify issues of concern,
information gaps or data needs--the existence of information gaps or
the need for additional data, itself, should not be an appropriate
basis for declining to proceed with a review meeting. ACEG expressed
concerns that the current approach could allow an application to be
indefinitely ``parked'' by unreasonable or overly burdensome demands
for more information for purposes of a sufficiency determination.
Similarly, Idaho Power asked, recognizing that review under the IIP
Process is iterative, what controls there are to avoid continued and
repeated refinement of analysis. Idaho Power also asked if the resource
report requirement change infers the project proponent will have
already identified potential resource concerns by consulting with
relevant, Federal land managers.
DOE requested comments on page limits for certain submission in the
NOPR and received seven responses. CBD and the CARE Coalition both
expressed a general concern with page limits on environmental reviews,
with CBD stating that arbitrary limits risk sacrificing detail,
undermining public participation, and causing delays. The Kentucky SHPO
stated that page limits may be applicable if resource reports will
serve only as background information, but page limits may not comply
with NHPA or applicable State statutes if documentation is intended to
be utilized by the project proponent or Federal agency for section 106
consultation materials. AZGFD noted that the NOPR only mentions page
limits in the documents Summary of the Qualifying Project and Project
Participation Plan, required by Sec. 900.5, and recommended that DOE
not include page limits for resource reports. ACP expressed concern
with imposing page limits on project summaries and participations plans
required by Sec. 900.5 and instead recommended that DOE allow for
flexibility and allow for page-limit carve outs for appendices where
appropriate. Gallatin Power stated that the page limits for the Summary
of the Qualifying Project and Project Participation Plan are reasonable
but noted that the scope of transmission projects will vary greatly and
suggested that DOE allow project proponents to request additional pages
if deemed necessary. The CEC/CPUC stated that the page limit for the
Summary of the Qualifying Project is appropriate but the limit for the
Project Participation Plan may be limiting. Similarly, EDF raised a
concern that the ten-page limitation for a Project Participation Plan
might constrain the level of detail needed to comprehensively and
holistically assess the project's impact and may signal to project
proponents that only a cursory assessment is needed.
DOE received one comment regarding the participation of relevant
Federal entities. EEI noted that transmission projects that
interconnect, parallel, or cross facilities owned or operated by
Federal power marketing administrations, such as Bonneville Power
Administration and the Western Area Power Administration, may also be
qualifying projects under the CITAP Program as proposed. EEI suggested
that in such cases, the Federal power marketing administrations must be
involved in some manner as relevant Federal entities, either as joint
lead agency with DOE or otherwise, and should remain actively involved
in the coordination process. EEI further noted that providing a
coordination role for Federal power marketing administrations is
consistent with section 216(h).
DOE received comments from ACEG, AEP, and PIOs that addressed
participation of relevant non-Federal entities. AEP urged DOE to be
mindful of the important and necessary roles State and local
decisionmakers play in the proposed transmission project approval
process. ACEG and PIOs generally supported the clear and increased role
for non-Federal entities, including Indian Tribes, SHPOs, and THPOs, in
the IIP Process but noted that the important role of these additional
entities in the process can also complicate reviews. ACEG recommended
that DOE ensure that these non-Federal entities not only have but also
use their seat at the IIP Process table and have necessary resources to
fully participate in the process. PIOs stated that such improved
coordination will be essential to ensure that resource reports provide
all the necessary analysis and information to enable project proponents
to receive all relevant authorizations. ACEG also noted that one way
DOE can facilitate this participation is by effectively implementing
its grant funding opportunities for transmission siting and permitting
participation.
Regarding confidential information and/or CEII, the CARE Coalition
recommended that DOE specifically
[[Page 35326]]
invite comments from Indian Tribes regarding best practices around
outreach by project proponents and prioritize Tribal recommendations.
The CARE Coalition also recommended that DOE create a list of best
practices; add free, prior, and informed consent (FPIC) to that list;
and add language stating agencies must apply FPIC to all interactions
between agencies and Tribal governments. The CARE Coalition believes
that these changes will ensure that agencies adhere to both the United
Nations Declaration on the Rights of Indigenous Peoples and the Federal
trust responsibility to Tribal governments. Relatedly, PIOs recommended
that DOE adopt language from the Washington State Attorney General's
Centennial Accord Plan, Indigenous Knowledge requirements, and
requirements from the 2022 Biden Memorandum on Uniform Consultation
Standards. The CARE Coalition recommended that DOE add a separate
provision requiring agencies to clearly articulate the levels of
confidentiality afforded to the public and governmental engagement for
the information shared therein. The CARE Coalition recommended that DOE
ensure that sacred sites, locations, and Indigenous Knowledge are
protected from public disclosure to the greatest extent practicable.
The NM SHPO added that agency officials should address concerns about
confidentiality with Tribes.
DOE received comments requesting clarification on how the proposed
rule would affect transmission projects that are already in the
permitting process from Stoel Rives LLP and Idaho Power and a comment
from Gallatin Power regarding the interaction of the IIP Process with
other permitting processes. Stoel Rives argued that these projects
should also be eligible for DOE's improved and expedited approval
process, under the CITAP Program or otherwise. Stoel Rives encouraged
DOE to consider these projects in this final rule and provide a roadmap
detailing how they can be integrated into the process. Gallatin Power
raised a concern that under the current provisions, a project proponent
will not be able to submit applications to relevant Federal agencies
for necessary Federal authorizations until after the completion of the
IIP Process. Gallatin Power contended that the submission of an
authorization application and supporting materials allows for the
developer to identify its interest in a right-of-way path impacting
Federal land and be designated the ``first-in-line'' for review.
Forcing the application submittal to later in the process could result
in multiple developers attempting to complete the IIP Process,
including the intensive resource reports, for the same lands at the
same time. This would create substantial inefficiencies for both the
project proponents and the agencies involved. Gallatin Power suggested
that to avoid this, DOE should either continue to allow developers to
submit applications to Federal agencies prior to initiating the IIP
Process or institute a similar ``first-in-line'' approach based on when
projects are proposed for the CITAP Program. Gallatin Power also
proposed that the transmission projects that have already submitted
applications for authorizations to relevant Federal agencies should not
be forced to redo their application process or have their applications
invalidated until the IIP Process is completed. They argued that doing
so would be highly disruptive to development efforts and
counterproductive to DOE's goals.
DOE also received comments regarding studies that may be undertaken
during the IIP Process. The CEC/CPUC encouraged early coordination and
review of a project proponent's supporting study methods for the IIP
Process because reviewing study methods and securing necessary
approvals for field review, before a proponent has conducted its
studies, could reduce later delays. Additionally, the CEC/CPUC
encouraged DOE to help other Federal agencies set schedules for timely
study authorizations and afford exemptions to allow project proponents
to initiate the IIP/CITAP Process if other Federal agency
authorizations are delayed. Idaho Power asked DOE to clarify if the
level of study is assumed to be desktop/GIS-informed or if there an
expectation that field surveys will be completed for all project
alternatives. Idaho Power also asked if DOE would be the final arbiter
of completeness for studies or if each relevant Federal land management
agency would have the authority to request additional information.
Gallatin Power commented that DOE should clarify when the project
proponent will receive authorization from Federal agencies to complete
field resource surveys. Gallatin Power further stated that a lack of
structure could allow for the permitting timelines to remain the same
since uncertainty would be shifted to before the start of the rule's
proposed two-year NEPA deadline.
Five commenters provided responses to DOE's request regarding the
duplicative aspects of the NOPR. ACP commented that project proponents
should be permitted to incorporate by reference existing data,
environmental reviews, and public engagement efforts to streamline the
process. ACEG recommended that the specific language regarding
incorporation by reference be clarified so that incorporation by
reference is permissible for all data, not just material in other
resource reports and provided some suggested edits to the provision.
CEC/CPUC stated that duplicative aspects of reports should be
eliminated to limit inconsistencies in review, providing as an example
that the Cultural Resources resource report, the Tribal Resources
resource report, the Communities of Interest resource report, and the
Socioeconomic resource report all overlap but may not be reviewed by
the same agency subject matter experts, which may result in
inconsistent evaluations.
ClearPath stated that the requirement for project proponents to
list and describe all dwellings and related structures or other
structures normally or intended to be inhabited by humans within a 0.5-
mile-wide corridor centered on the proposed transmission line was
duplicative of information regarding affected landowners required in
General Project Description resource report and should be omitted.
ACP recommended that DOE not require the public disclosure of names
of people project proponents spoke to in preparing the resource
reports, as this is overly onerous and lack of detail in this section
should not be a basis to legally challenge DOE's eventual
determination.
DOE Response
In this final rule, DOE retains the purpose and scope of the IIP
Process as proposed in the NOPR, including the three-anchor-meeting
structure and information requirements for progressing through the
process, with minor revisions. DOE revises this final rule for clarity
and to reduce burdensome and duplicative requirements in response to
comments, as described below. DOE revises the page limits in this final
rule to allow for project proponents to request a waiver. DOE makes no
other revisions in response to these comments but notes that revisions
to resource reports and IIP Process meetings in response to other,
specific comments received on those aspects are addressed in sections
VI.N and G of this document.
DOE declines to act on those comments urging greater flexibility in
the IIP Process and in the content of resource reports because it
believes such measures are unnecessary. This final rule confirms the
provisions in the NOPR that provide for sufficient
[[Page 35327]]
flexibility: the three anchor meetings, which provide structured
opportunities to discuss and establish expectations; the provision
permitting the project proponent to submit resource reports missing
discrete pieces of information so long as the project proponent
provides an acceptable reason for the omission and an acceptable
timeline for curing the omission; and the provision granting the
Director of the Grid Deployment Office with discretion to waive any
requirement imposed on a project proponent if the Director of the Grid
Deployment Office determines that that it is unnecessary, duplicative,
or impracticable under the relevant circumstances. DOE finds that
together these provisions provided the flexibility necessary to respond
to a wide variety of circumstances.
Regarding comments from ACP, ACEG, ACORE, SEIA, and CEBA on the
level of detail requested in resource reports and specifically the
availability of information based on project maturity and compliance
with NEPA regulations, DOE makes no revisions in response to these
comments. First, DOE believes the level of detail in the resource
reports is necessary for DOE to implement its authority under section
216(h), which includes both environmental review and the coordination
of decision making with relevant Federal entities. Second, this final
rule adopts the proposed provision that project proponents may address
and justify omissions or incomplete information. DOE believes this
provides sufficient flexibility to accommodate project differences
without further revision. Regarding ACP's request to modify language
from shall to ``should'' or ``to the extent practicable'', where DOE
intends to impose a mandatory obligation, it uses appropriate language,
including ``shall.''
Regarding the inclusion of reasonably foreseeable effects, DOE
declines to make changes to the requirements that project proponents
identify certain reasonably foreseeable effects. DOE's obligations
under NEPA, as well as corresponding obligations under section 106 of
the NHPA and the ESA, require the Department to consider the reasonably
foreseeable effects of major Federal actions affecting the quality of
the human environment, as noted in PIOs' comment. While the scope of
any NEPA review will be determined at the close of the IIP Process and
on a case-by-case basis, the information required for inclusion within
the resource reports discussed in this section is likely to be relevant
for preparation of environmental review documents necessary for
authorizations subject to this rule. In order to assist DOE in fully
considering this relevant information, DOE seeks input from project
proponents to identify reasonably foreseeable generation projects that
may be caused by a Federal authorization. Even when DOE determines a
particular generation resource to be outside the scope of review DOE
may still need to identify the resource and explain its conclusion. The
language of the rule tracks these statutory obligations, and is
consistent with the Secretary of Energy's authority under section
216(h) to require the submission of all data considered necessary.
Regarding the iterative nature and level of information requested
for the three anchor meetings, DOE makes minor changes in this final
rule regarding the discussion of and criteria for modifying study
corridors in response to comments. DOE restates that the IIP Process is
designed to allow for flexibility throughout the process while
maintaining sufficient review periods to ensure that the project
proponent is taking the steps necessary to complete the required
Federal authorization processes.
In response to ACP's concern on how route changes will be
accommodated without restarting the IIP Process, DOE believes the
iterative nature of the IIP Process provides mechanisms to account for
route changes, including: meetings, the use of analysis areas for
resource report assessments (discussed in section VI.K.ii of this
document in detail), study corridors that may contain multiple routes,
and the resubmission of resources reports, none of which require a
restart to the IIP Process. Accordingly, DOE makes no changes in
response. Regarding ACP's request for criteria on adding or deleting
routes, DOE revises the rule for clarity. First, DOE relocates the list
of criteria from the initial meeting to Sec. 900.4, Purpose and Scope
of the IIP Process, and clarifies in the text that these are the
initial list of criteria the project proponent should consider when
developing potential study corridors and potential routes for the IIP
Process. The change encourages the project proponent to utilize the
criteria in identifying routes and corridors throughout the IIP
Process, rather than just after the initial meeting. Second, DOE
removes ``deleting'' from the initial meeting discussion topic to
clarify that the IIP Process does not include a Federal entity deleting
any corridors or routes. This final rule retains the requirement for
DOE and other agencies to identify other criteria for adding or
modifying potential routes and includes that the agencies should also
identify criteria for potential study corridors as well. DOE makes no
further revisions as these changes sufficiently clarify the criteria
recommended and how they will be considered, and any additional
criteria will be discussed on a project-by-project basis.
DOE makes no changes to the final rule in response to comments from
ACEG and NYTO regarding establishing a standard for determining the
sufficiency of materials required for each IIP Process meeting. DOE
requests the information it deems necessary and sufficient for each
meeting as described in the rule and has chosen not to provide a
specific standard in order to maintain flexibility to evaluate
submitted materials depending on the specific needs and circumstances
of each project. As previously noted, IIP Process materials may be
submitted with omissions provided that the omission is noted, a reason
is given, and reasonable timeline for curing the omission is provided.
Additionally, the final rule confirms the proposed provisions through
which DOE will provide reasons for finding the submissions deficient
and how such deficiencies may be addressed by the project proponent.
DOE believes these provisions provide flexibility for a wide range of
project circumstances.
Regarding concerns from Idaho Power and ACEG that projects could be
``parked'' in the IIP Process, DOE makes no revisions to the final
rule. This final rule confirms the intended iterative nature of the IIP
Process and the interests of DOE in engaging in communications that are
not limited to the three anchor meetings. These provisions are intended
to prevent the situation described by the commenters where a request is
rejected due to information or knowledge gaps or continued study
refinement, by providing a communication mechanism through which such
gaps could be discussed in advance. Additionally, as previously
explained, DOE provides sufficient flexibility to the IIP Process to
accommodate unique circumstances.
Regarding Idaho Power's question as to whether project proponents
are expected to engage with agencies prior to the IIP Process, DOE
responds that project proponents may choose to consult with relevant
entities prior to IIP Process at their discretion, but are not required
or expected to do so.
Regarding page limits, DOE believes that the limitation on the
number of pages in the Summary of the Qualifying Project and the
Project Participation Plan is generally useful and appropriate, but
agrees with commenters that some complex projects may require
additional pages to address pertinent information for the project and
the project
[[Page 35328]]
proponent's outreach. Accordingly, DOE revises this final rule to allow
for project proponents to request waivers to the page limitations of
the Summary of the Qualifying Project and the Project Participation
Plan. As the proposed rule established no specific page limitations on
the environmental review document or resource reports, DOE makes no
additional revisions in response to comments on those documents but
acknowledges that relevant statutory page limits for environmental
review documents will be followed.
Regarding the participation of relevant Federal entities, DOE has
made no changes in response to EEI's suggestion to include Federal
power marketing administrations because DOE has determined that such a
scenario is already allowed by the regulatory text in the definition of
relevant Federal entity.
Regarding the participation of relevant non-Federal entities, DOE
agrees that not all relevant non-Federal entities will have the
resources available to participate in the IIP Process. DOE makes no
changes to this final rule, however, because provisions for cost-
recovery and contribution of funds, which may assist in those entities'
participation, are already included in the IIP Process. The
recommendation of coordination of grant funding is outside the scope of
this rulemaking, which is limited to implementation of DOE's
coordinating authority under section 216(h) of the FPA. DOE has made no
changes in response to this comment. DOE encourages non-Federal
entities with authority to make permitting decisions regarding proposed
electric transmission projects (e.g., State siting authorities) to
actively participate in the CITAP Program, and will continue to seek
ways to support such participation as the Program is implemented.
Regarding confidentiality of information and recommendations from
the CARE Coalition among others, DOE makes no changes to this final
rule. DOE finds that existing statutory provisions referenced in the
proposed rule and confirmed in this final rule provide a framework for
the protection of certain sensitive information from public disclosure.
DOE recognizes that Indian Tribes are entitled to decline to provide
information potentially at issue in the resource reports and IIP
Process, and notes that this final rule does not mandate that Indian
Tribes provide any material or information to project proponents. DOE
will work with Indian Tribes to access relevant material and
incorporate it into relevant decision-making while protecting the
confidential and sensitive nature of that information as necessary and
legally permitted. Additionally, as noted in section IV of this
document, DOE affirms the sovereignty of Federally recognized Indian
Tribes and confirms that the rule makes no changes to Federal agencies'
government-to-government responsibilities. DOE commits to undertake
Tribal consultation as appropriate, including as required by applicable
authorities such as Executive Order 13007 or the Presidential
Memorandum on Uniform Standards for Tribal Consultation, and commits to
designate Indian Tribes with special expertise regarding a qualifying
project, including knowledge about sacred sites that the project could
affect, that are eligible, to become cooperating agencies under NEPA.
DOE declines to include in the final rule best practices around
outreach by project proponents or to import existing requirements
related to Tribal engagement into this rule. The form and scope of
outreach may vary by project and DOE believes these issues are best
addressed on a project-by-project basis or in guidance outside of this
rule.
Regarding participation of projects already undergoing a permitting
process, DOE notes that nothing in the definition of qualifying project
excludes such projects from participation and that the flexibility
provided for in the IIP Process will allow DOE to determine
accommodations for such projects on a project-by-project basis. DOE
disagrees with Gallatin Power's interpretation that the CITAP Program
would disallow or invalidate permitting applications previously
submitted prior to initiation of the IIP Process or submitted during
the IIP Process. DOE acknowledges that some applications for
authorizations may already be submitted prior to initiation of the IIP
Process or may be submitted during the IIP Process and accommodates for
such scenarios in the rule. For example, this final rule confirms the
NOPR provisions that the initiation request and the review meeting
request require the project proponent to provide a list of anticipated
and completed dates of applications for authorizations or permits.
Further, the rule specifically provides in Sec. 900.5(h)(2) that at
the initial meeting DOE will identify any Federal applications that
must be submitted during the IIP Process to enable relevant Federal
entities to begin work on the review process. DOE finds that these
provisions sufficiently provide that this final rule will not impede
developers' strategies for seeking authorizations for their projects.
Nowhere in the rule does DOE indicate that these applications will be
invalidated or require resubmission, nor does DOE have authority to do
so.
Regarding study methods and approvals as raised by CEC/CPUC, Idaho
Power, and Gallatin Power, DOE revises this final rule to provide
clarity on the extent to which analysis of alternatives is expected
(discussed in more detail in section VI.L.xi of this document) and to
specify that required or recommended surveys or studies will be
discussed in the IIP Process during the initial and review meeting. DOE
makes no further revisions to this final rule in response to these
comments as study methods and authorization timelines are specific to
project circumstances and DOE will address these on a project-by-
project basis. DOE clarifies here that DOE leads the IIP Process and
will determine the completeness of documents and studies for the
purpose of progressing through the milestones, while relevant Federal
entities maintain statutory authority for determining the completeness
of information needed for their decision-making.
Regarding the duplicative nature of some resources reports, DOE
makes minor revisions in response to these comments. DOE agrees that
incorporation by reference should extend to publicly available sources,
such as existing data and environmental reviews, but only if they exist
in electronic form (to ensure relevant entities can reasonably access
the material), and revises this final rule to allow for such
references. In response to the request to combine resource reports to
assure consistent review, DOE makes no revisions in response to this
comment as DOE believes the division of resource reports will provide
specific information pertinent to that resource topic that is necessary
for DOE to implement its coordination authority. Further DOE believes
the coordination of reviews within the IIP Process with relevant
Federal entities will provide consistency of evaluation, and notes that
the review of project proponent resource reports does not replace or
supplant Federal entities' responsibilities to evaluate necessary
information for decision making on authorizations and permits under
their purview. Regarding the request to remove duplication in reporting
of affected landowners and dwellings proximate to the proposed route,
DOE makes no revisions in this final rule. DOE does not agree that
these are duplicative requests, as affected landowner describes a
person or entity and dwelling describes a building.
In response to ACP's concern about the burden of providing detailed
information on all persons contacted in
[[Page 35329]]
development of the resource reports, DOE agrees that this provision
represents an unnecessary burden on project proponents and removes it
from this final rule.
E. Public Participation in the IIP Process
DOE's Proposal
The proposed rule included several provisions addressing public
participation. In the NOPR, DOE proposed the project proponent submit,
as part of the initiation request, a project participation plan. The
proposed project participation plan included the project proponent's
history of engagement with communities of interest and stakeholders,
and a public engagement plan for the project proponent's future
engagement with communities of interest and with Indian Tribes that
would be affected by a proposed qualifying project. Before the review
and close-out meetings, DOE proposed that the project proponent provide
an updated public engagement plan to reflect any activities during the
IIP Process. Additionally, the proposed rule required the standard
schedule to take into consideration the need for early and meaningful
consultation with Indian Tribes and engagement with stakeholders and
communities of interest. Likewise, the project-specific schedule was
required to account for early and meaningful consultation with Indian
Tribes and engagement with stakeholders.
Summary of Public Comments
DOE received several comments addressing public participation
during the IIP Process, including the requirement of project proponents
to plan for and report on engagement with various groups, and
recommendations for modifications, clarifications, expansions, and
reductions of the proposed public engagement reporting requirements.
Many commenters supported DOE's requirement to have a project
proponent submit project participation and engagement plans. ACP, AEU,
ACEG, SEIA, Pew Charitable Trusts, CEBA, and PIOs all expressed support
for the requirement, expressing that such engagement would build trust
and allow prompt response to concerns. PIOs expressed that they believe
DOE is correct to require project proponents to furnish ``specific
information on the proponent's engagement with communities of interest
and with Indian Tribes'' and that requiring a public participation plan
is well-grounded in binding Federal authorities. Additionally, PIOs
expressed appreciation to DOE for noting that project proponent
outreach efforts are merely complementary and not substitutive for
Federal agencies' own engagement with communities and Indian Tribes nor
are they substitutive for formal requirements under NEPA or other laws
that provide formal avenues for community input. ACP supported DOE's
efforts to encourage early and consistent engagement by project
proponents with affected communities, as this represents a best
practice for identifying, mitigating, and avoiding risks of sometimes-
contentious transmission project development.
DOE received several comments recommending changes to the role of
public participation and the scope of participants. EDF stated that the
project participation plan is too narrowly focused, as public input
should be expansive and not limited to ``project engineering and route
planning.'' The CARE Coalition encouraged DOE to require that project
participation and public engagement plans include information about
engagement with advocates for the public interest, such as advocates
for wildlife protection, who may not be covered under the definition of
``communities of interest.'' The CARE Coalition argued that the
inclusion of these groups and individuals in the project participation
and public engagement plans would help develop resource reports, reduce
litigation risk, reduce delays, and reduce overall project costs. PIOs
recommended that DOE require separate engagement plans for Indian
Tribes and communities of interest.
Commenters requested more guidance on public engagement, including
parameters, minimum requirements, metrics, and best practices. EDF
commented that proposed rule does not require the project proponent to
strictly define communities of interest and recommended that the
communities considered should be based on CEQ's Climate and Economic
Justice Screening Tool or a comparable tool. EDF further recommended
refining the public engagement plan to include mandatory deadlines or
frequency of outreach requirements, to specify when communities of
interest will have an opportunity to raise concerns, and to list
additional tools that would facilitate communication in order to
improve the efficacy of the plan. EDF expressed concern that the
project participation plan did not require project proponents to engage
with communities before substantive plans were solidified or require
that input from communities of interest is taken into account in the
beginning stages of plan development. Similarly, Niskanen Center was
concerned that the proposed rule did not have sufficient notification
or consultation requirements regarding the proposed public engagement
plan, such that a project proponent would actually have to engage early
or meaningfully with impacted parties or communities of interest.
Niskanen Center accordingly recommended adopting notice requirements
with defined timing and linked to specific milestones such as the
notice of an initiation request. The CARE Coalition recommended that
DOE adopt a definition of ``early and meaningful engagement'' similar
to EPA's definition of ``meaningful involvement'' in its Environmental
Justice 2020 Glossary and stated that providing a definition will
ensure that engagement with communities does not simply consist of
``check-the-box'' exercises without meaningfully engaging with
communities that are disproportionately and adversely affected by
certain Federal activities. ACP suggested that DOE should provide
additional clarity as to what specific steps are required for
engagement, and what DOE considers as ``successful'' engagement, and
AEU echoed this comment. ACP, AEU and ACEG requested that DOE expressly
recognize that engagement with potentially affected parties does not
necessarily mean that all parties will reach a consensus on all issues.
The CARE Coalition suggested DOE require submission of an ``Applicant
Code of Conduct'' with additional information collection and sharing
requirements for engagement, which would bring the rule into better
alignment with FERC's proposed backstop permitting rule. Similarly,
PIOs suggested that DOE require project proponents to adhere to a
rigorous ethical code of conduct. Additionally, EDF suggested that the
proposed rule might benefit from the expertise of DOE's Office of
Economic Impact and Diversity.
The CARE Coalition, CBD, and CEBA suggested including best
practices for public engagement and providing guidelines for project
proponents as to what activities are considered engagement.
Commenters also expressed concern about the extent and approach to
public engagement. AEP cautioned against a CITAP Program or IIP Process
that duplicates or exceeds the RTO stakeholder process or required
State and local permitting functions that ensure robust community and
landowner engagement and outreach. ClearPath expressed opposition to
requirements in the project participation plan and public engagement
plan that
[[Page 35330]]
create duplicative engagement requirements and institute different
standards of engagement for different population segments. ClearPath
specifically took issue with the different standards for ``communities
of interest'' and ``stakeholders'' in the plans and suggested that the
distinction was counterproductive to development of transmission
projects and possibly unconstitutional. ClearPath also recommended
amending the requirement that a project participation plan must include
``[a] description of . . . any entities and organizations interested in
the proposed undertaking.'' ClearPath stated that it was impossible to
describe any interested entities and organizations because DOE did not
provide a threshold for what actions constitute a demonstration of
interest. ClearPath recommended reevaluating whether this requirement
was feasible and overly burdensome. StopPATH WV expressed its view that
the project participation plan described in the NOPR is one-sided given
that the developer and agencies have primary decision-making power and
suggested that the name should be changed.
DOE received three comments regarding the role of community
benefits plans. Alan Leiserson commented that the public engagement
plans should require that the project proponent propose a community
benefit plan and consider affected communities' suggestions for it. EDF
also proposed that CITAP project participation plans and public
engagement plans be required to include information on any potential
community benefits agreements and the process that would be used to
work with communities of interest in developing such agreements. EDF
reasoned that information about any community benefit agreement or plan
would support the CITAP review process and allow for coordinated review
of the compliance of those plans with any other legal requirements. ACP
supported DOE's efforts to encourage early and consistent engagement by
project sponsors with affected communities. ACP expressed that DOE
should consider environmental mitigation and community benefits
developed under this community engagement process as project mitigation
and/or design features in NEPA reviews.
PIOs, CARE Coalition, CBD, and Policy Integrity recommended that
DOE incorporate additional opportunities for public participation in
the IIP Process. PIOs stated that communities and organizations with
relevant expertise should be allowed to participate in the three
required meetings. CARE Coalition and PIOs suggested that DOE add an
opportunity for public comment on project proponents' compliance with
their participation plans and provide a mechanism for affected
communities to make concerns known if proponents interact with the
communities in a manner that is aggressive, coercive, dishonest, or
otherwise unethical or if stakeholders disagree with project proponents
over the scope or nature of a project's impacts. Similarly, CBD
suggested including junctures at which the public could provide input
into the resource reports and public participation plan. Policy
Integrity also recommended that DOE modify the proposed IIP Process to
allow for early public comments, arguing that early community feedback
and expert opinion could reveal pitfalls in a project in the pre-
application stage. Without this step, Policy Integrity expressed
concern that the public would have no voice until after the
participating agencies have deliberated and potentially come to a
consensus on certain issues in the pre-application stage. For example,
Policy Integrity noted that agencies may deem project proponents'
Alternatives Report as complete once they ratify it during the IIP
Process, without any consideration for public input. Additionally,
Policy Integrity argued that its proposed revision would bring the IIP
Process into closer alignment with the pre-filing process for natural
gas infrastructure at FERC, which accepts formal public comment, and
suggested the consolidated administrative docket be allowed to provide
public feedback.
DOE Response
In this final rule, DOE retains the proposals in the NOPR to
require a project participation plan and a public engagement plan, and
the provisions in the NOPR addressing engagement with communities of
interest, Indian Tribes, potentially affected landowners, and
stakeholders. In response to these comments, DOE makes minor changes to
this final rule to clarify the scope of topics on which project
proponents should seek public engagement, for the reasons discussed
below. Revisions to the definitions of communities of interest,
potentially affected landowners, stakeholders, and to the resource
reports are addressed in sections VI.J and VI.K of this document in
response to other comments.
Regarding the role of public participation and the scope of
participants, DOE makes minor changes in response to these comments.
DOE clarifies that the project participation plan may include--but is
not limited to--engagement related to project engineering and route
planning and strikes ``project engineering and route planning'' from
this final rule to reflect this. DOE makes no changes in response to
the request to require engagement with advocates for the public
interest because DOE believes further expanding the required engagement
creates an undue burden on project proponents without substantial
benefit to communities of interest. Furthermore, DOE understands that
these advocates may, and often do, act as representatives on behalf of
communities of interest and are therefore likely to be engaged through
those relationships. DOE is unpersuaded that two public engagement
plans, one for communities of interest and another for Tribal
engagement, are necessary and believes that the proposed resource
report requirements for communities of interest and Tribal interests
allow for sufficient differentiation on the topics for DOE's
consideration.
Regarding requests for minimum standards, deadlines, frequency,
specific steps, use of tools for identifying communities of interest,
and notice requirements, from CARE Coalition, CBD, CEBA, EDF, and
Niskanen Center, DOE makes no revisions in this final rule in response
to these comments. DOE believes the provisions for public engagement in
the proposed rule and confirmed here establish sufficiently clear
expectations for project proponent activities while maintaining
flexibility for the project proponent to shape engagement consistent
with the project circumstances and development. These provisions as
proposed and now finalized sufficiently support the goals of the CITAP
Program by encouraging engagement on the part of the project proponent
to identify concerns early and to allow for the project proponent to
consider adjustments in a timely and responsive manner. Additionally,
these provisions are complementary and additional to Federal agencies'
own engagement with communities and Indian Tribes and the requirements
under NEPA or other laws that provide formal avenues for public input
including notice and consultation requirements. DOE is not persuaded
that additional requirements are necessary or appropriate for the IIP
Process.
Regarding codes of conduct, DOE has determined that defining a
singular code within the regulatory text is unnecessary at this time.
In its role coordinating the IIP Process and the CITAP Program, DOE
will work closely with project proponents, relevant
[[Page 35331]]
Federal entities, communities, and other stakeholders. In that role,
DOE will endeavor to ensure that project proponents engage in good
faith with all participants. In contrast to FERC, DOE does not have
specific statutory authority regarding eminent domain and thus
alignment with all aspects of FERC's proposed rulemaking pursuant to
engagement practices is not appropriate but may be addressed on a
project-by-project basis where relevant. With experience, DOE may find
it appropriate to provide code-of-conduct or ethical guidance and may
rely on the resources provided by commenters. DOE also clarifies, in
response to EDF's concern, that offices across the agency, including
the Office of Energy Justice and Equity (formerly Economic Impact and
Diversity), were consulted in the development of the rule.
DOE declines to define ``successful,'' as requested by ACP, or
``early and meaningful'' engagement as requested by the CARE Coalition,
because DOE believes the required information on engagement (including
what groups and individuals were engaged, how they were identified,
topics that were raised, and the project proponent's responses)
provides sufficient clarity and additional definitions are unnecessary.
DOE declines to include the statement requested by ACP, AEU and ACEG
that engagement with potentially affected parties does not necessarily
mean that all parties will reach a consensus on all issues because DOE
is not persuaded that the proposed rule indicates that all parties will
reach a consensus on all issues and therefore finds such a statement
unnecessary.
DOE believes that best practices are best provided in guidance
rather than regulatory text to allow for flexibility and evolution of
such practices and makes no changes in this final rule in response to
the comments by CARE Coalition, CBD, and CEBA. In the future, DOE may
issue guidance for community-led engagement, measuring engagement,
identifying communities of interest, and ethical and meaningful
engagement, which may include or reference the sources provided by
commenters as necessary for implementation of the CITAP Program.
In response to ClearPath's concern about different standards of
engagement, DOE reiterates that the various requirements, including the
resource reports and public engagement plan, are tailored to fulfill
various, not mutually exclusive, purposes to facilitate transmission
authorizations pursuant to the CITAP Program, and are not intended to,
nor do they, establish a hierarchy of treatment and consideration of
impacts across population segments.
In response to StopPath WV's objection to the project participation
plan, DOE declines to change the name of the project participation plan
because DOE is not persuaded that the phrase implies any decision-
making authority.
Regarding the role of community benefits and community benefits
plans, DOE makes no changes to this final rule. DOE believes that the
public participation provisions proposed and confirmed here are
sufficient to allow project proponents to engage with communities in
the development of plans or agreements and for compliance to be
evaluated in the CITAP Program where relevant for Federal permitting or
authorization decisions. DOE does not agree that additional
requirements are needed, as the comments suggest that the situations
described are not universal but rather depend on the project, and
therefore are best addressed on a project-by-project basis.
Regarding recommendations for inclusion of expert groups in the IIP
Process meetings and providing avenues for public comments, DOE makes
no changes in this final rule in response to these comments. First, as
noted previously, DOE believes the provisions in the proposed rule and
confirmed here are sufficient to support the goals of the CITAP
Program. DOE has structured the three IIP Process meetings to serve as
milestones for coordination between the project proponent and the
relevant Federal and non-Federal entities to ensure DOE can meet its
obligations under FPA section 216(h) and DOE does not intend to use
these meetings to solicit feedback from communities of interest or
receive expert input from other organizations. The public participation
plan is designed with the intent to identify issues well ahead of the
IIP Process meetings for this reason, as the meetings themselves are
not intended to serve as avenues for broader input. Second, as noted by
DOE throughout the rule and supported by commenters, the CITAP Program
public participation requirements are complementary and additional to
Federal agencies' own engagement with communities and Indian Tribes and
the requirements under NEPA or other laws that provide formal avenues
for public input and public comment, including on project impacts.
DOE disagrees with Policy Integrity's interpretation that agencies
will make decisions on Federal authorizations during the IIP Process.
Federal agency decisions remain subject to distinct decision-making
processes with requirements under NEPA and other laws that provide
formal avenues for public input. Furthermore, with respect to Policy
Integrity's specific concern regarding project proponent's Alternatives
resource report, as discussed in further detail below, see section
VI.K.xi of this document, the project proponent's Alternatives resource
report must discuss alternatives identified and considered by the
project proponent. However, while a project proponent's study
corridors, potential routes, and range of potential routes are relevant
information, they do not displace the overall alternatives development
process that must take place in consultation with relevant Federal and
non-Federal entities, stakeholders, and the public. That process
remains subject to public comment pursuant to NEPA and other laws.
F. Timing of IIP Process and NOI Issuance
DOE's Proposal
The proposed rule included several provisions addressing the IIP
Process timeline. In the NOPR, DOE proposed to, within 15 calendar days
of receiving an IIP Process initiation request, notify relevant Federal
entities and relevant non-Federal entities of the initiation request
along with a determination that the recipient is either a relevant
Federal entity or a relevant non-Federal entity and whether the project
proponent should participate in the IIP Process. Also, DOE proposed to,
within 30 calendar days of receiving the request, notify the project
proponent and all relevant Federal entities and relevant non-Federal
entities whether the initiation request meets the applicable
requirements. If the request is found to meet the applicable
requirements, DOE proposed, in consultation with the identified
relevant Federal entities, to convene the IIP Process initial meeting
within 30 days of providing notice to the project proponent.
In the NOPR, DOE proposed to, within 15 calendar days after the
initial meeting with the project proponent and relevant entities,
prepare and deliver a draft initial meeting summary to the project
proponent, relevant federal entities, and any non-Federal entities that
participated in the meeting. The proposed rule provided a period of 15
calendar days after receipt of the draft initial meeting summary for
relevant entities to review and provide corrections to DOE.
In the NOPR, DOE proposed, within 15 calendar days of the close of
the 15-day review period, to prepare a final meeting summary that
incorporates
[[Page 35332]]
received corrections, as appropriate, and incorporate the final summary
into the consolidated administrative docket.
DOE proposed in the NOPR to, within 60 calendar days after
receiving a project proponent's review meeting request, notify the
project proponent and all relevant Federal entities and relevant non-
Federal entities that the review meeting request has been accepted. In
the NOPR, DOE proposed, within 30 calendar days after DOE provides
notice that the review meeting request has been accepted, to convene
the review meeting with the project proponent and relevant Federal
agencies.
DOE proposed in the NOPR to, within 15 calendar days after the
review meeting, prepare and deliver a draft review meeting summary to
the project proponent, relevant Federal entities, and any non-Federal
entities that participated in the meeting. In the NOPR, DOE proposed to
provide a period of 15 calendar days after receipt of the draft review
meeting summary for relevant entities to review and provide corrections
to DOE.
DOE proposed in the NOPR to, within 15 calendar days of the close
of the 15-day review period, prepare a final review meeting summary
that incorporates received corrections, as appropriate, and to
incorporate the final summary into the consolidated administrative
docket.
In the NOPR, DOE proposed to, within 60 calendar days after receipt
of the close-out meeting request, notify the project proponent and all
relevant Federal entities and relevant non-Federal entities that the
close-out meeting request has been accepted. DOE also proposed to,
within 30 calendar days of DOE notifying the project proponent that the
close-out meeting request has been accepted, convene the close-out
meeting with the project proponent and all relevant Federal entities.
DOE proposed in the NOPR to, within 15 calendar days after the
close-out meeting, prepare and deliver a draft close-out meeting
summary to the project proponent, relevant federal entities, and any
non-Federal entities that participated in the meeting. In the NOPR, DOE
provided a period of 15 calendar days after receipt of the draft close-
out meeting summary for relevant entities to review and provide
corrections to DOE.
In the NOPR, DOE proposed to, within 15 calendar days of the close
of the 15-day review period, prepare a final close-out meeting summary
that incorporates received corrections, as appropriate, and to
incorporate the final summary into the consolidated administrative
docket.
Summary of Public Comments
DOE received comments from PIOs, SEIA, ClearPath, and AEU that
expressed general support for DOE's proposed IIP Process timelines.
Several commenters suggested specific changes to the IIP Process
timelines proposed in the NOPR. Grid United and ACP recommended
reducing the time between receipt of an initiation request and the date
of the initial meeting to no more than 30 calendar days. NYTOs
recommended that DOE adopt a 60-day maximum period between receipt of a
review meeting request and the convening of the review meeting because
a significant amount of the information would have already been
reviewed as part of the initial meeting.
ACEG suggested that DOE reduce the 45-day summary and report
process after each of the three anchor meetings (initial meeting, the
review meeting, and the close-out meeting) and further suggested that
DOE require a real-time wrap-up at the end of each meeting during which
DOE would provide a meeting summary and participating entities would
immediately make any needed corrections. ACEG also recommended that DOE
reduce the number of days between the initiation request and initial
meeting to 15 days, and reduce the number of days between the close out
meeting request and that meeting to 30 days. Grid United also suggested
shortening the meeting summary process by emphasizing close-out and
action item discussions at the meeting and designating a 15-day period,
thereafter, for finalizing the meeting report.
Several commenters requested more information on the total timeline
for the IIP Process and the CITAP Program. ACP recommended that the IIP
Process include a general timetable to ensure that it does not add
unnecessary costs or delays. Similarly, ACEG and CEBA recommended that
the rule establish a presumptive one-year limit for completion of the
IIP Process. ACORE commented that it supports ACEG's recommendation
that DOE commit that any transmission project will be fully authorized
in under three years and not longer than five years (from initiation of
the pre-application process through issuance of all required Federal
authorizations, including any required notice to proceed). CEBA argued
that, ideally, the IIP Process and application process, including all
environmental review procedures, would be completed within three years.
CEBA added that DOE should work with the project developer on a joint
schedule that may better accommodate the unique nature of the proposed
project. Similarly, ClearPath suggested that the IIP Process timeline
in the rule could serve as a baseline and that DOE should allow a
project proponent to submit a proposed IIP Process schedule. EDF noted
that the IIP Process could take more than one year given the lack of
specific deadlines for specific IIP Process steps. EDF stated that
there are IIP Process requirements such as the project participation
plan that require significant effort and time to develop and that this
development time is not captured in the IIP Process schedule. EDF
recommended that DOE consider specifying a time period for when a
developer must resubmit its review meeting request and close-out
meeting request if either request does not meet the specified
requirements.
CEBA noted that the burden of completing the IIP Process in a
timely manner is highly dependent on the level of effort and resources
brought to bear by the project proponent and suggested that DOE should
anticipate and recognize a broad diversity of project proposals and
afford maximum flexibility for the developer. CEBA further encouraged
DOE to ensure that the IIP Process does not become too complicated and
time consuming, which could undermine the objective reflected in recent
law to shorten the Federal authorization process. Gallatin Power stated
that a lack of structure could allow for the permitting timelines to
remain the same because timeline uncertainty would be shifted to before
the start of the rule's proposed two-year NEPA deadline.
PJM noted that although the NOPR describes the CITAP Program
deadlines as ``binding,'' the May 2023 MOU contemplates a process to
modify the project-specific deadlines. PJM believes that due to this
and the fact that the extensive, mandatory IIP Process is not factored
into the two-year timeline, the actual review and approval process will
most likely take longer than two years. Hence, PJM requested that DOE
carefully reexamine that the proposed revisions will actually aid in
accelerating the current process in a way that will ensure that, at a
minimum, the CITAP Program is able, in all but the most unusual of
cases, to be completed within the two-year time frame or less.
Four commenters, NYTOs, Grid United, ACEG, and ClearPath, expressed
concern over the lack of a deadline for DOE to issue the NOI. Grid
United recommended that the presumptive deadline should be 90 days
after the
[[Page 35333]]
close-out meeting. The NYTOs recommended a presumptive deadline of 45
days after either the close-out meeting or the project proponent's
completion of applicable filing procedures for each involved Federal
agency. ACEG suggested that DOE require the NOI to be issued within 90
days of the project proponent filing all applications and resource
reports. ACP recommended that DOE ensure that as little time as
possible elapses between submittal of an application for an EIS Scoping
NOI, and the subsequent publication in the Federal Register.
DOE Response
This final rule makes several revisions to the DOE decision-making
timelines that reduce the total time for DOE reviews and responses in
the IIP Process by 55 days and the total time for all IIP Process steps
by 100 days. DOE also revises this final rule to establish a deadline
for DOE and any NEPA joint lead agency to issue an NOI to prepare an
environmental review document for the proposed project. That deadline
is established as within 90 days of the later of the IIP Process close-
out meeting or the receipt of a complete application for a Federal
authorization for which NEPA review will be required. DOE makes no
revisions to establish timelines for project proponents or to set a
timeline for the IIP Process or overall CITAP Program. DOE recognizes
that some of the IIP Process is within the government's control, and,
where reasonable, for those pieces of the process this final rule
adopts shorter timelines. For other pieces of the process, however, the
pace is dictated by the project proponent (or factors outside anyone's
control, like inclement weather). For those pieces, DOE has not set
timelines.
Regarding reducing time between meeting requests and meeting
convenings, DOE makes several revisions. DOE agrees that the deadlines
for determining the sufficiency of the initiation request and convening
the initial meeting can be moved forward to streamline evaluation and
coordination. To simplify the initiation request review and reduce the
timeline, in this final rule DOE is combining the deadline for
providing notice to Federal and non-Federal entities under Sec.
900.5(f) of the NOPR with the deadline for providing notice of the
sufficiency determination. Further, this final rule reduces the
timeline for making a sufficiency determination on the initiation
request from 30 calendar days after receiving the initiation request to
20 calendar days. Finally, DOE revises the timeline for convening the
initial meeting from 30 calendar days after providing notice of the
sufficiency determination to 15 calendar days. In sum, the revisions
reduce the maximum time period between receiving the initiation request
and the initial meeting from 60 calendar days to 35 calendar days.
DOE also agrees that the other IIP Process meetings can be convened
in less time. Accordingly, the final rule revises the timeline for
convening the review meeting and close-out meeting from within 30
calendar days of sufficiency determination to within 15 calendar days.
Regarding NYTO's comment that the time between a review meeting request
and the review meeting could be reduced, in this final rule DOE
shortens the period from 90 days to 75 days by convening the review
meeting within 15 days rather than 30 days. However, DOE maintains the
review period for the meeting request at a maximum of 60 days because
DOE and the relevant Federal and relevant non-Federal entities will be
reviewing both the meeting request and the draft submission of the 13
resource reports, which will be substantial and will benefit from
careful review. The review meeting timeline may be significantly
reduced if the project proponent chooses to submit resource reports in
advance, and communicates with DOE, as provided for in the IIP Process.
DOE declines to adopt an immediate meeting summary review process
as suggested by ACEG and Grid United because the content of each of the
meetings is likely to be substantial, with multiple subject matter
experts likely to attend from the relevant Federal entities and
relevant non-Federal entities. DOE does not agree that immediate
summaries will adequately capture an initial draft of the meeting
outcomes. DOE also wishes to clarify that the meeting summary timelines
do not add to the total time of the IIP Process because they are not
precursors to any subsequent milestones. That is, while DOE is
preparing summaries of each meeting, preparation or revisions to the
resource reports or other materials needed for subsequent IIP Process
steps can and should continue. Nonetheless, DOE does agree that these
timelines should be reduced. Consequently, this final rule changes the
deadline for DOE to deliver a meeting summary from 15 calendar days
after the meeting to 10 calendar days after the meeting, for all three
of the IIP Process meetings. Similarly, this final rule shortens the
deadline for a project proponent and other entities to review the
meeting summary from 15 calendar days after receiving the summary to 10
calendar days after receiving the summary. Finally, the deadline for
DOE to provide the final meeting summary is changed from 15 calendar
days after the period for corrections to 10 calendar days after the
period for corrections. DOE notes that since these deadlines are
expressed as calendar days, not work days, DOE is declining additional
reductions to ensure the expectations can be met. In sum, the revisions
reduce the maximum time period between the conclusion of an IIP Process
meeting and the finalization of the meeting summary from 45 calendar
days to 30 calendar days.
In response to comments requesting a general timetable or
presumptive timeline for the IIP Process or the CITAP Program, DOE
makes no changes in this final rule. In the proposed rule and confirmed
here, DOE provides decision-making timelines for DOE's responsibilities
in the IIP Process, leaving the timing of project proponent actions to
trigger the next milestone flexible to account for differences in
projects. When factoring the changes described above, the maximum total
time for DOE reviews and responses in the IIP Process in this final
rule is 185 days. Based on that timeline for DOE decision-making, DOE
expects that a prepared and responsive project proponent could readily
complete the IIP Process within a year.
DOE does not agree that this final rule should set a total time for
the IIP Process or CITAP Program. DOE has chosen to set expeditious
timelines for the actions it and its fellow agencies can control. But
the time required for each IIP process will ultimately depend on the
needs and capabilities of the project proponent. Some projects will be
able to move quickly and complete the process well within a year, while
others may need more time. Even the best-prepared project proponents
may need time to accommodate re-routing or design changes that result
from unforeseen developments in the land acquisition process, the
interconnection process, or other activities that they pursue in
parallel to the IIP Process and that are not entirely within their
control. DOE makes no revisions to establish timelines for project
proponents to resubmit materials in response to EDF's request to
accommodate project proponents with different capabilities. DOE is also
declining to make revisions in response to ClearPath's or CEBA's
recommendations to allow for individualized IIP Process schedules;
again, the overall schedule for the IIP Process will ultimately be
determined by the project proponent. Regarding PJM's comment that the
IIP Process is not accounted for in the two-year
[[Page 35334]]
schedule described in the 2023 MOU, DOE confirms that this is accurate
and reflects the agreement in the 2023 MOU. DOE clarifies that the two-
year timeline begins with the publication of an NOI to prepare an
environmental review document; the IIP Process is intended to precede
the publication of the NOI. As discussed in this section and section
VI.H addressing the standard schedule and project-specific schedules,
DOE has reviewed the timelines set out in this rule and modified
certain timelines in the IIP Process to further streamline where
appropriate.
In response to comments requesting a timeline for NOI issuance, DOE
revises this final rule to state that DOE will issue an NOI within 90
days of the later of the IIP Process close-out meeting or the receipt
of a complete application for a Federal authorization for which NEPA
review will be required. This 90-day timeline aligns with recommended
performance schedules established by the Federal Permitting Improvement
Steering Council (FPISC). DOE does not adopt the recommendation to time
the issuance of the NOI on the receipt of all applications, because
some applications may require more information or project development
before filing. For instance, both the FPISC-recommended performance
schedules \8\ and DOE's draft standard schedule indicate that
applications for Clean Water Act (33 U.S.C. 1251 et seq.) (CWA) or
Rivers and Harbors Act (33 U.S.C. 401 et seq.) permit applications may
be filed after the NOI is issued.\9\
---------------------------------------------------------------------------
\8\ ``Recommended Performance Schedules.'' Permitting Dashboard:
Federal Infrastructure Projects, FEDERAL PERMITTING IMPROVEMENT
STEERING COUNCIL, Nov. 2023, www.permits.performance.gov/sites/permits.dot.gov/files/2023-11/RPS_November%202023.pdf.
\9\ ``Draft Standard Schedule.'' Grid Deployment Office, United
States Department of Energy, Aug. 2023, www.energy.gov/sites/default/files/2023-08/CITAP-Standard-Schedule-Draft.pdf.
---------------------------------------------------------------------------
G. IIP Process Initiation Request
DOE's Proposal
To participate in the CITAP Program, DOE proposed to require a
project proponent to submit an IIP Process initiation request to DOE
that included a summary of the qualifying project; associated maps,
geospatial information, and studies (provided in electronic format); a
project participation plan; and a statement regarding the proposed
qualifying project's status pursuant to Title 41 of the Fixing
America's Surface Transportation Act (FAST-41) (42 U.S.C. 4370m-
2(b)(2)).
Summary of Public Comments
DOE received two comments on the contents of the initiation request
for the IIP Process. LTA recommended that DOE add sufficient and
satisfactory title work for the real property through which an electric
transmission facility will pass to the list of required materials for
an initiation request in order to identify conserved lands. ACEG stated
that additional clarity is needed on how the CITAP program will align
with FAST-41 and stated that a project proponent might not be able to
state whether the project is covered under FAST-41 in the IIP Process
initiation request. ACEG also stated it is unclear how DOE will
coordinate with FPISC if the project is covered under the CITAP Program
and FAST-41.
DOE Response
In this final rule DOE maintains the required initiation request
materials proposed in the NOPR with no revisions.
In response to the request to add title work to the requirements,
DOE does not make this revision because DOE believes this would be
overly burdensome on the project proponent at the initiation stage of
the IIP Process, when a project proponent may not have a finalized
route.
In response to the request for more information on alignment with
FAST-41, DOE first provides clarification on the provision in the
proposed rule. In the proposed rule, DOE would request the status of a
project under FAST-41 at the time of the initiation request. But this
provision would not ask the project proponent to speculate as to
whether the project may be covered in the future. DOE believes the
project proponent will be able to state if the project has applied for
coverage under FAST-41 and if a coverage determination has been made at
the time of the initiation request, and therefore DOE makes no changes
in this final rule. Additionally, DOE provides no revisions regarding
coordination with the Permitting Council because, as noted by the
commenter, a project's FAST-41 status may change during the CITAP
Program and therefore DOE expects that coordination between the
Permitting Council and DOE will vary on a project-by-project basis.
Examples of such coordination are described in the 2023 MOU, and DOE
designed the CITAP Program timelines to work in harmony with the
Permitting Council processes accordingly.
H. Standard and Project-Specific Schedules
DOE's Proposal
In the NOPR, DOE proposed to establish intermediate milestones and
ultimate deadlines for Federal authorizations and related environmental
reviews through the introduction of standard and project-specific
schedules in accordance with the terms of FPA section 216(h)(4) and of
the 2023 MOU. Specifically, DOE proposed to periodically publish a
standard schedule identifying the steps needed to complete decisions on
all Federal environmental reviews and authorizations for a qualifying
project along with the recommended timing for each step. In addition,
DOE proposed to establish project-specific schedules for each project
participating in the IIP Process, to set binding deadlines by which
Federal authorizations and related environmental reviews for a
particular project must be completed. DOE proposed to base the project-
specific schedule on the standard schedule, to develop it in
consultation with the project proponent and other Federal agencies, and
to finalize it at the conclusion of the IIP Process.
Summary of Public Comments
DOE received several comments regarding the standard schedule and
the development of project-specific schedules. Two commenters supported
these provisions. The State of Colorado Governor's Office stated its
belief that the standard schedule and the project-specific schedule
will provide added flexibility to each project and expressed hope that
doing so will minimize the time of the approval process. ClearPath
expressed its support for the development of the standard schedule to
serve as a baseline for developing project-specific schedules.
Three commenters raised concerns that the two-year timeline in the
standard schedule and presumed for the project-specific schedules was
too long, and a fourth commenter, PJM, commented in favor of the two-
year timeline, but expressed concerns that it may still not adequately
expedite the Federal permitting process. OSPA stated that the proposed
two-year EIS process is still too long. Alan Leiserson recommended that
the standard schedule deadline should be set at one year, or as soon
thereafter as practicable, to be consistent with section 216(h). AEP
recommended setting one-year timelines for environmental assessments
and two years for environmental impact statements. PJM proposed that
DOE clarify in the proposed revisions that
[[Page 35335]]
while developing the binding, project-specific milestones the relevant
agencies will endeavor to shorten the two-year timeline based on the
proposed project's scope and location in conjunction with the relevant
statutory requirements.
On the other hand, two commenters raised concerns that the two-year
timeline was too short. CBD cautioned against setting any timelines for
environmental reviews because it could cause agencies to cut corners
and result in increased opposition to proposed projects. Similarly,
AZGFD expressed concerns that expediting the approval process to
facilitate rapid transmission infrastructure development may have
unforeseen impacts on wildlife resources. AZGFD argued that although
establishing a standard schedule would help in streamlining the
process, some projects might require additional time for completion of
the NEPA analysis and identification of appropriate conservation
measures. AZGFD encouraged DOE to have provisions for independent
process-specific timeframes, rather than a standard schedule, to allow
adequate time for evaluation and assessment of potential impacts. AZGFD
requested DOE to provide clear guidelines on establishment of review
times for cooperating or participating agencies with statutory
authority or special expertise related to proposed actions. AZGFD
further mentioned that it is unclear whether the proposed two-year
timeframe applies to the IIP Process, the NEPA process, or the combined
process.
Three commenters suggested the project proponent provide more input
into the development of the project-specific schedule. ClearPath
recommended that DOE allow project proponents to propose a project-
specific schedule. Similarly, ACEG and Grid United proposed that the
project proponent have the opportunity to provide DOE and the relevant
entities with a draft project-specific schedule before the initial
meeting, which would be discussed at the initial meeting. Grid United
also suggested requiring ongoing consultation between the project
proponent, DOE, and the relevant agencies as part of finalizing the
project-specific schedule. PJM suggested that DOE include a provision
for revisiting the CITAP Program at least every two years to gauge
whether the process is meeting its intended goals.
DOE Response
In this final rule, DOE retains without revision the proposal in
the NOPR to publish a standard schedule for completing environmental
review and decision making for Federal authorizations for qualifying
projects within two-years and to develop a proposed schedule with the
NEPA joint lead agency and the relevant Federal entities on a project-
specific basis during the IIP Process.
Regarding requests to reduce the two-year time frame to complete
environmental reviews, DOE makes no changes to this final rule because
DOE maintains its conviction that, as a general matter, for
transmission projects of the type that meet the qualifying project
definition, a two-year timeframe is the shortest practicable length of
time necessary to consider applications for authorizations under
relevant Federal laws and complete the necessary environmental reviews.
Accordingly, DOE concludes that a two-year timeline is likely to be
consistent with DOE's statutory obligations under FPA section 216(h).
However, DOE notes that the rule does not preclude DOE, in consultation
with relevant agencies, from setting project-specific timelines that
are shorter than the two-year timeline, should such a timeline be
practicable.
Regarding concerns that the two-year timeframe is too short and
could reduce the quality of environmental review or impact wildlife
resources, DOE makes no changes to final rule because the CITAP Program
does not alter any Federal environmental review standards or
responsibilities towards wildlife resources. Additionally, this two-
year timeline is consistent with the timelines established by the
Fiscal Responsibility Act of 2023. Further, DOE notes that the standard
schedule is a general framework for environmental review and
authorizations, but that the proposed and now this final rule require
that DOE develop a schedule specific to each project that addresses the
unique permitting and review requirements for that project. In
addition, as explained in the proposed rule, DOE anticipates that the
IIP Process will inform the environmental review process, such that a
two-year timeline is reasonable. DOE believes this structure
sufficiently addresses AZGFD's concerns.
Regarding the request to establish a standard schedule for EAs, DOE
makes no changes to this final rule because the CITAP Program focuses
DOE resources on projects expecting to complete an EIS, and
adjustments, including to schedules, for any project requiring an EA
will be addressed on a project-specific basis. Accordingly, DOE finds
it unnecessary to establish a timeline for EAs in the text of this
final rule but notes that the rule does not prevent DOE from publishing
a standard schedule for EAs if the agency finds it necessary.
Regarding the suggestions that DOE allow the project proponent to
propose a project-specific schedule or provide additional opportunities
for the project proponent to discuss the project-specific schedule with
DOE and the relevant Federal entities, DOE notes that nothing in the
rule prevents the project proponent from proposing a schedule but DOE
maintains the statutory authority to set and maintain the schedule.
Additionally, as proposed and finalized here, DOE requires the project
proponent to submit information on the intended or desired timelines
for various Federal applications as part of each meeting request during
the IIP Process. DOE is required to present a proposed project-specific
schedule at the review meeting and a final project-specific schedule at
the close-out meeting. Project proponents are encouraged to communicate
with DOE and relevant entities throughout the IIP Process. Project
proponents are welcome to submit any information they believe will help
DOE create the project-specific schedule, including a draft schedule,
through any of these mechanisms. DOE believes these requirements
provide sufficient opportunity for the project proponent to give input
on the schedule and therefore makes no changes to the rule in response
to these comments.
In response to PJM's suggestion that DOE revisit the CITAP Program
every two years, DOE makes no revisions in this final rule. DOE will
evaluate the CITAP Program as appropriate, which may be based on time,
the number of projects DOE has coordinated in the process, or other
relevant factors.
I. Selection of NEPA Lead and Joint Lead Agencies and Environmental
Review
DOE's Proposal
Section 216(h)(2) of the FPA authorizes DOE to act as the lead
agency to coordinate Federal authorizations and related environmental
reviews required to site an interstate electric transmission facility.
DOE proposed in the NOPR that DOE serve as the NEPA lead agency to
prepare an EIS to serve the needs of all relevant entities. In the
NOPR, DOE proposed that a NEPA joint lead agency may be designated no
later than the IIP Process review meeting. The NEPA joint lead agency,
if any, would be the Federal entity with the most significant interest
in the management of the Federal lands or waters that would be
traversed or affected by the qualifying project, and DOE would make
this determination in consultation with all Federal entities that
manage Federal
[[Page 35336]]
lands or waters affected. The proposed rule also provided that for all
qualifying projects, DOE and the relevant Federal entity or entities
would serve as co-lead agencies for consultation under the ESA and for
compliance with section 106 of the NHPA.
After the IIP Process close-out meeting and once an application has
been received in accordance with the project-specific schedule, the
proposed rule would require DOE and the NEPA joint lead agency to
prepare an EIS for the qualifying project, which is meant to serve the
needs of all relevant Federal entities. The proposed rule would also
require DOE and the NEPA joint lead agency to consider the materials
developed throughout the IIP Process; consult with relevant Federal
entities and relevant non-Federal entities; draft the EIS, working with
contractors, as appropriate; publish all completed environmental review
documents; and identify the full scope of alternatives for analysis in
consultation with the relevant Federal entities.
Finally, the proposed rule would also require the Federal entities
or non-Federal entities that are responsible for issuing a Federal
authorization for the qualifying project to identify all information
and analysis needed to make the authorization decision, identify all
alternatives that need to be included, and to use the EIS as the basis
for their Federal authorization decision on the qualifying project to
the extent permitted by law.
Summary of Public Comments
DOE received several comments addressing NEPA lead and joint lead
designation and the environmental review DOE will undertake following
the IIP Process.
Regarding the proposal to establish DOE as the NEPA lead agency,
PJM and the State of Colorado Governor's Office expressed support. The
State of Colorado Governor's Office noted that DOE as the lead NEPA
agency could effectively lead an iterative, interagency process to
ensure applications for Federal authorizations are ready for review and
can meet the specified timelines. It also noted that having one agency
leading the NEPA process reduces duplication of work and improves
efficiency.
DOE received comments from CBD, PIOs, and Gallatin Power regarding
the process for designation of a joint lead agency. CBD expressed
concern that DOE would not have the expertise to evaluate impacts of
transmission projects on ecosystems, species, and the environment, and
recommended that the rules should require the designation of a land use
agency as the NEPA joint lead agency. Gallatin Power commented that DOE
should designate a joint lead agency that has experience permitting
transmission projects during the promulgation of the rule and should
implement a practice of identifying a joint lead agency prior to an IIP
Initial Meeting instead of after the completion of the IIP Process.
Gallatin Power argues that these joint lead agency designations will
allow DOE to rely on Federal agencies with substantial experience in
permitting and enable DOE to expedite approvals through the adoption of
invaluable insights and best practices. PIOs challenged the proposed
rule's assumption that only one agency can serve as a joint lead agency
on the basis that the assumption is a departure from the statute and
CEQ regulations both of which allow multiple agencies to serve as
``joint lead agencies.'' PIOs encouraged DOE to consider whether
allowing multiple joint lead agencies could better comport with NEPA
and CEQ regulations and better realize the proposed rule's goal of
improving efficiency in Federal analysis and decision-making.
Three commenters suggested that the CITAP Program issue a joint
record of decision for projects. CATF, PIOs, and SEIA recommended that
DOE should ensure that the CITAP Program is in alignment with the
congressional direction and best practices for NEPA. They recommended
that DOE provide that, where feasible, agency decisions should be
issued together in a joint record of decision, or provide greater
clarity as to why DOE declines to require a joint record of decision.
These commenters noted that requiring a joint record of decision aligns
with recent revisions to NEPA and CEQ's NEPA regulations and promotes
efficiency and coordination. They also suggested that a joint record of
decision effectuates Congressional direction that the basis for all
decisions under Federal law use DOE's environmental review and reduces
confusion about how to seek judicial review.
Multiple commenters submitted comments on the scope of
environmental reviews and considerations. AEP agreed that DOE should
carry out its statutory obligation to prepare a single EIS sufficient
for the purposes of all Federal authorizations necessary to site a
qualifying project. AEP further added that, to the extent practicable,
the EIS should also include any relevant information to satisfy state
permitting requirements to avoid duplication of reporting requirements.
PIOs noted that the rule's inclusion of a requirement to assess climate
impacts is well-founded in NEPA's plain text, its implementing
regulations, authoritative guidance, and judicial precedent. PIOs
further stated that DOE has both the authority and the responsibility
to require assessments of climate related impacts, as NEPA's plain text
explicitly includes ``reasonable foreseeable environment effects.''
However, PIOs also stated that DOE should use existing regulatory and
scientific tools that CEQ makes available to assist other Federal
agencies with their legally required analysis, and that the resulting
analysis of climate impacts need not be perfect. AZGFD noted that when
completing the IIP Process and developing the EIS, it is important to
ensure that adequate consideration is given to wildlife and wildlife
habitat resources along the project route, that effects to those
resources and areas are not generalized for the full project route, and
that, as necessary, suitable conservation measures are identified for
specific areas and resources. AZGFD stated that it is also important to
consider the varying purposes, management plans, and land use goals or
mandates for lands managed by different Federal agencies. Hence, AZGFD
requested further information on how the proposed rule and development
of a single EIS by DOE will ensure that wildlife and wildlife habitat
resources are considered and accommodated through the IIP Process. ACP
mentioned that CEQ is simultaneously conducting revisions to its
regulations implementing NEPA and suggested that DOE should ensure that
the CITAP Program and any potential DOE rulemaking aligns with CEQ's
NEPA rulemaking.
DOE received multiple recommendations for streamlining
environmental review. OSPA asserted that a Programmatic Environmental
Impact Statement (PEIS) would dramatically speed the deployment of
transmission in chronically underserved areas of the Upper Great
Plains. Similarly, ACP suggested that DOE develop resource-specific
programmatic NEPA reviews to reduce the administrative burden and legal
risk of project-specific reviews. AEP recommended allowing for greater
use of programmatic reviews and categorical exclusions. Alan Leiserson
said DOE should use more categorical exclusions for clean energy
projects. AEP recommended modifying thresholds for Federal agencies
when determining what requires development of an environmental
document. OSPA additionally recommended that DOE should expressly make
EIS underlying
[[Page 35337]]
data available to Federal and non-Federal permitting entities for
purposes of developing a PEIS. OSPA recommended that THPOs explicitly
have access to this data as well as well as any consultants hired by
THPOs.
Three commenters suggested DOE include statements about what
information or resources could be used in the environmental review. ACP
argued that the resource reports are useful beyond the IIP Process and
so this final rule should require that materials and findings in
resource reports be used in the NEPA EIS process. ACP further noted
that ideally this authority for consideration of the resource reports
would be DOE's alone rather than DOE and the joint lead agency. AEP
recommended stating that Federal agencies can use existing data and
studies in determining when to develop an environmental document. AEP
also recommended allowing for greater project proponent involvement in
preparing environmental documents. DOE received the following
additional comments:
CBD recommended that DOE prioritize development on already degraded
lands, existing rights of way, and other areas where communities will
not object to new infrastructure. ACORE noted that there may be
projects that do not participate in the CITAP Program, but that will
still have DOE as the lead agency. Accordingly, ACORE recommended that
DOE clarify which of CEQ's NEPA provisions, including timing
requirements, would apply to these types of projects.
DOE Response
In this final rule, DOE confirms its role as NEPA lead agency, the
process for selecting a joint lead agency, and the responsibilities DOE
will undertake for environmental review, with minor revisions in
response to these comments. DOE revises this final rule to state that
DOE and relevant Federal entities shall issue, except where
inappropriate or inefficient, a joint decision document.
Regarding the joint lead agency selection process, DOE makes no
revisions in response to these comments. As proposed and confirmed
here, the designation of a joint lead agency will be determined by DOE
and Federal entities that manage Federal lands or waters by no later
than the IIP Process review meeting. DOE believes the process for
designating a joint lead, if any, is consistent with NEPA implementing
regulations and provides flexibility to identify the relevant expertise
among the relevant entities. Further, since the rule requires DOE to
engage Federal land- and water-management agencies in the process, DOE
is not persuaded that including a joint lead requirement is necessary,
as suggested by CBD and Gallatin Power, and instead believes it is best
to leave that determination up to the Federal entities on a project-
specific basis. Regarding the timing of the designation, DOE notes that
this final rule confirms the same timing as the proposed rule,
requiring the designation by the review meeting, not the completion of
the IIP Process as indicated by the commenter. DOE does not agree that
a designation requirement is appropriate before the initial meeting
because DOE believes the initial meeting provides important project
information that could inform any joint lead designation. In response
to the PIO's comment about multiple joint leads, DOE maintains the
presumption in the rule that no more than one joint lead agency will be
designated to ensure efficiency and effectiveness, which will enable
DOE to meet its coordination and scheduling obligations under FPA
section 216(h).
In response to the recommendation that the CITAP Program issue
joint records of decision, DOE agrees with the commenters that this
would be consistent with NEPA as amended by the Fiscal Responsibility
Act of 2023. DOE also agrees that a policy in favor of joint records of
decision would be consistent with the purpose of FPA section 216(h) and
would enhance DOE's coordinating function. Accordingly, DOE revises
this final rule to provide that, except where inappropriate or
inefficient, the Federal agencies shall issue a joint record of
decision that includes all relevant Federal authorizations and, to
ensure consistency with the requirements of section 216(h), includes,
if applicable, the determination by the Secretary of Energy of a
duration for each land use authorization issued under section
216(h)(8)(A)(i).
Regarding the scope of environmental reviews, DOE makes no changes
to this final rule because the rule as proposed did not change any of
DOE or other Federal entities' responsibilities to comply with existing
NEPA regulations and environmental review laws. DOE will endeavor to
incorporate State requirements in the environmental review and makes no
revisions to address this because DOE believes this will be
accomplished through the inclusion of relevant non-Federal entities in
the IIP Process. Similarly, DOE will endeavor to follow NEPA best
practices and use available tools and does not find that these comments
require any revisions to the rule.
Regarding ACP's request to require the use of resource reports in
the preparation of the environmental review document, AEP's request
that DOE include a provision that existing data can be used, and AEP's
recommendation that DOE allow for greater project proponent involvement
in preparing environmental documents, DOE makes no changes in this
final rule. Data requirements for environmental reviews are outside of
scope of this rulemaking, which concerns only the implementation of
DOE's coordinating authority under FPA section 216(h) and does not
address the substance of NEPA compliance by DOE or its fellow agencies.
But DOE reiterates that the purpose of the resource reports is to
inform environmental review (and agency authorizations), and affirms
its commitment to adhering to best practices for leveraging existing
data sources. Comments suggesting revised environmental review
thresholds, the use of categorical exclusions, and PEISs, are likewise
outside the scope of this rulemaking.
In response to CBD's request that DOE prioritize development on
already degraded lands, DOE makes no changes to this final rule as this
is beyond the scope of DOE's coordinating authority. While DOE and its
fellow agencies may encourage development on degraded lands, DOE lacks
authority to impose any requirement to that effect in the final rule.
In response to ACORE's request for more information on how DOE will
serve as lead agency for projects that are not in the CITAP Program,
DOE makes no changes to this final rule as this is beyond the scope of
the rulemaking, which is the implementation of DOE's coordinating
authority under FPA section 216(h).
J. Section 106 of the NHPA
DOE's Proposal
In the NOPR, DOE explained that the project proponent resource
reports are intended to develop data and materials that will facilitate
Federal entities' review of the project proponent's applications under
a number of Federal statutes, including section 106 of the NHPA. DOE
also explained that this initial information-gathering phase precedes
the formal consultation process under section 106. DOE proposed to
authorize project proponents, as applicants to the CITAP Program, to
begin section 106 consultation during the IIP Process, but only at such
time as a project is sufficiently well developed to allow formal
consultation to begin. DOE proposed to make this determination
[[Page 35338]]
within 45 days of the IIP Process review meeting. Finally, DOE affirmed
that DOE would remain legally responsible for all findings and
determinations charged to the agency under section 106.
Summary of Public Comments
DOE received multiple comments related to section 106 of the NHPA.
First, multiple commenters requested clarification regarding whether,
and the extent to which, the resource reports would fulfill agencies'
and project proponents' section 106 obligations. For instance, the
Kentucky SHPO sought clarification of whether the resource reports will
serve as only background information, or if they are intended to be
utilized by the project proponent or agencies for section 106
consultation materials, as their purpose would affect DOE's ability to
impose page limits. It also stated that it is unclear whether DOE
proposes to frontload NPS National Historic Landmarks (NHL) review
under section 106, and that doing so is not feasible from a regulatory
standpoint. The NM SHPO commented that it is not clear, as proposed,
whether the rule authorizes the project proponent to initiate
consultation with the SHPO and elicit comments on the resource reports,
and noted that it may not be possible to account for all of the section
106 impacts of a project at the initiation stage. The NM SHPO suggested
that this may need to be stipulated in a Programmatic Agreement and
asked how other agency reviews will be conducted. Relatedly, the
Arizona SHPO stated that DOE intends to authorize all project
proponents to act on its behalf and with procedures that deviate from
the standard 36 CFR 800 Subpart B compliance process, and hence it
advised that DOE consult with the National Conference of State Historic
Preservation Officers (NCSHPO), NATHPO, and ACHP to develop a CITAP
Program Alternative in accordance with 36 CFR 800.14. DOE also received
comments from the Delaware SHPO and NM SHPO suggesting that DOE consult
with ACHP and other entities regarding NHPA compliance.
DOE also received comments on the resource reports as they relate
to section 106. The Delaware SHPO recommended that the requirements of
the proposed ``Resource Report 4: Cultural Resources'' be explicitly
defined as cultural resources identification and evaluation level
surveys, determined necessary through consultation with consulting
parties, that meet the relevant Secretary of the Interior Standards and
applicable State and Tribal guidelines. The Delaware SHPO expressed
concern that the provision in its current form might lead to a scenario
wherein the project proponent could be required to redo cultural
resource reports if initiation occurs after the submission and review
of resource reports, which would cause duplication of effort, leading
to unnecessary delays and frustration for all parties. Conversely,
NATHPO and the Santa Rosa Rancheria Tachi Yokut Tribe expressed concern
regarding a comment by Department of Energy staff because they believed
it indicated that the Communities of Interest resource report would
satisfy section 106 conditions for examining the impacts of projects on
Tribal Nations' cultural resources and sacred places. The commenters
also stated that the proposed resource reports are not a Program
Alternative approved by the ACHP under 36 CFR 800 and cannot be used to
satisfy DOE requirements under NHPA section 106.
DOE received comments on the timing of the section 106 process in
relation to the CITAP Program process. The Delaware SHPO noted that the
current CITAP Program's schedule would cause the project to experience
significant delays when complying with section 106 of NHPA. The
Delaware SHPO explained that, as proposed, project proponents would be
required to complete resource reports to allow DOE to determine whether
there is an undertaking. But, the Delaware SHPO argued, the presence of
historic properties is not a determining factor to establish an
undertaking. Rather, the Delaware SHPO noted that, per 36 CFR 800.3(a)
and 800.16(y), an undertaking is an action with a Federal nexus, which
is the type of activity with the potential to cause an effect on
historic property. The Delaware SHPO stated that all above-ground
transmission lines eligible for the CITAP Program would be undertakings
and the initiation of consultation should occur concurrently with or
immediately after the first CITAP Program meeting for a project. This
process would set up the project proponent, DOE, and all consulting
parties to begin consultation on the level of survey needed to identify
historic properties early in the process. The Delaware SHPO noted that
earlier consultation will allow the project to meet CITAP and NEPA
deadlines and further noted that, with larger transmission projects,
multiple SHPOs and numerous consulting parties will be involved and
that property access would need to be arranged for surveys and longer
reports, all of which may require longer review times. In addition, if
a memorandum of agreement is needed due to any adverse effects to
historic properties, negotiating and executing such an agreement could
be time-consuming.
DOE received comments from the Arizona SHPO and the Kentucky SHPO
indicating that only one agency could be selected as lead agency for
section 106 consultations as the process did not allow for co-lead
agencies.
Finally, DOE received comments regarding SHPOs' resource
constraints. The Arizona SHPO expressed concerns that due to staffing
and budgeting constraints it would not have adequate resources to
conduct preliminary review of NHPA section 106 for project proponents
prior to the establishment of a Federal undertaking by Federal agency.
DOE Response
In this final rule, DOE maintains the structure and purpose of the
resource reports. DOE revises this final rule as discussed below to
adjust the timeline for DOE to make a determination of an undertaking
pursuant to section 106 and to designate DOE as the lead agency for
section 106.
DOE clarifies that the resource reports are not intended to fulfill
the agencies' section 106 responsibilities. Instead, the information
provided in the Cultural Resources resource report, and the other
resource reports as applicable, will contribute to the satisfaction of
DOE's and relevant Federal entities' obligations under section 106. As
the lead agency for section 106, DOE remains legally responsible for
all findings and determinations charged to the agency under section
106. The function of the resource reports is to gather information to
contribute to DOE's subsequent section 106 compliance. DOE appreciates
that project proponents may not have access to all information required
for DOE's section 106 compliance at the time the proponents submit
their resource reports. This final rule adopts, as proposed, that a
project proponent may file incomplete information but must address the
reason for the omission. The final rule also provides the Director of
the Grid Deployment Office the discretion to allow the project to
proceed to the next milestone and provides that the Director of the
Grid Deployment Office may waive requirements as appropriate, providing
flexibility to the IIP Process to accommodate unique circumstances.
Regarding the comments on particular resource reports, DOE declines
to revise the definition of cultural resources in the Cultural
Resources resource report
[[Page 35339]]
in this final rule. That resource report is intended to inform not only
DOE's section 106 compliance but also the environmental review
document. Given that the timing of consultation under section 106 may
vary based on the project and that this resource report is intended to
fulfill multiple purposes, DOE necessarily retains its broader scope.
Additionally, as previously noted, neither the Communities of Interest
resource report nor any other resource report is intended to fulfill
DOE's or relevant Federal entities' obligations under section 106.
As for the comments related to program alternatives, DOE submitted
the proposed and final rules for interagency review under E.O. 12866
and intends to work collaboratively with ACHP and other relevant
entities to develop mechanisms for efficient and effective
implementation of section 106, which may include program alternatives.
DOE, however, does not modify this final rule to provide for a
particular program alternative under the section 106 implementing
regulations \10\ nor does DOE intend for the resource reports to serve
as a program alternative; DOE wishes to inform its approach through
initial implementation and further collaboration with relevant
entities. DOE believes this part provides sufficient flexibility to
allow for an appropriate alternative without specifying one at this
time.
---------------------------------------------------------------------------
\10\ See 36 CFR 800.14.
---------------------------------------------------------------------------
DOE agrees that initiating the NHPA section 106 consultation
process earlier than DOE had proposed may be feasible and beneficial
for certain project proposals that are sufficiently mature for DOE to
determine there is an undertaking pursuant to the regulations
implementing section 106.\11\ DOE has accordingly revised this final
rule to remove the requirement that DOE make the undertaking
determination only after the IIP Process review meeting. As revised,
the final rule allows DOE to make the determination at any point in the
IIP Process, but no later than 10 calendar days following the close of
the 10-day review period.
---------------------------------------------------------------------------
\11\ See 36 CFR 800.3(a) and 800.16(y).
---------------------------------------------------------------------------
Regarding resource constraint concerns, DOE understands the
staffing and budgeting constraints that SHPOs and THPOs may face. DOE
does not intend for the IIP Process to create additional or preliminary
review requirements for SHPOs and THPOs, and has designed the IIP
Process with the intention of avoiding doing so. Rather, the intent of
the IIP Process is to align the NHPA section 106 review with other
Federal permitting and authorization processes. DOE notes that SHPOs
and THPOs may consult with DOE and other relevant Federal agencies as
to the range of possible assistance and resources that may be
available.
Finally, DOE modifies this final rule to indicate that DOE intends
to serve as lead agency for section 106 of the NHPA as section 106 does
not provide for a co-lead agency. The modification aligns this final
rule and regulatory path with section 106's statutory language and
procedures.
K. Definitions
i. Affected Landowner
DOE's Proposal
In the NOPR, DOE proposed to define ``affected landowner'' as an
owner of real property interests who is usually referenced in the most
recent county or city tax records, and whose real property (1) is
located within either 0.25 miles of a proposed study corridor or route
of a qualifying project or at a minimum distance specified by State
law, whichever is greater; or (2) contains a residence within 3,000
feet of a proposed construction work area for a qualifying project.
Summary of Public Comments
Commenters made multiple suggestions for revisions to the
definition.
ACP recommended that DOE use the term ``potentially impacted
landowner'' instead of ``affected landowner,'' given that ``affected
landowner'' might carry some implication of an obligation for
compensation.
ClearPath recommended that DOE adopt the definition of ``affected
landowner'' used in FERC's natural gas pipeline permitting regulations
and FERC's proposed rule for implementing section 216(b) of the FPA.
ClearPath suggested that the effective use of ``affected landowner'' in
FERC's natural gas pipeline permitting demonstrates that definition's
legal durability and thereby bolsters the legal durability and
predictability of this final rule.
Some commenters recommended that DOE revise the distances included
in the proposed definition of affected landowner. To that end, SEIA,
for instance, expressed support for a rule that considers the proposed
project scale, geographic considerations, and resource usage of
landowners to determine if a landowner falls under an ``affected
landowner.'' Niskanen Center described the definition of ``affected
landowner'' as nebulous and thus impracticable and overly burdensome,
and recommended proximity qualifiers and a measure of immediate impact
to the definition. LTA recommended that the rule should move away from
a one-size-fits-all distance for the definition of landowner, and
instead require project proponents to engage with communities of
interest to assist in identifying potential impacts to landowners and
the distance within which notifications to landowners would be
appropriate. LTA specifically proposed that DOE expand the definition
of ``affected landowner'' to include areas that a community of interest
has identified as having one or more resources likely to be impacted by
a proposed project. Grid United commented that the specific distances
expressed in the definition of ``analysis area'' were not standard for
high voltage transmission lines and could result in unnecessary data
collection, burdens, and complexity for the project. Grid United
suggested lowering the distances in the definition to 500 feet and
likewise recommended establishing 500 feet as a presumptive radius for
identification of affected resources unless existing practices dictated
otherwise. ACP commented that the 0.25-mile distance provided is both
too broad and too rigid and proposed that DOE remove references to a
particular distance from the definition and instead base the required
distance on the physical characteristics of the project and resource
evaluated in each report.
Commenters also recommended that DOE include or omit certain
considerations from the definition. LTA recommended that DOE remove the
reference to county and city tax records because many owners of real
property interests are not listed in these records. LTA also suggested
that DOE explicitly include in the definition of ``affected landowner''
conservation easement holders and landowners whose viewshed or other
ecosystem services may be impacted by the transmission facility. ACP
requested that DOE explicitly exclude landowners affected through
owning mineral estate property interests, given the possibility of a
project involving broad areas of potentially unoccupied land, and
exclude additional areas of potential construction work, including
roads and ancillary facilities, that may be preliminary prior to
completion of a NEPA review.
Finally, PIOs recommended that DOE require project proponents to
provide a landowner bill of rights in transmission permitting processes
to ensure affected landowners are informed of their rights in dealings
with the proponent and attached a draft landowner bill of rights they
submitted for FERC's proposed backstop permitting rule for reference.
PIOs outlined that the landowner bill of
[[Page 35340]]
rights should include any information on requirements to obtain party
status prior to appeal, how to obtain such status, and if and how a
party can participate in the presidential appeal process.
DOE Response
In this final rule, DOE revises the definition of affected
landowner, for the reasons described below, to the following:
Potentially affected landowner means an owner of a real property
interest that is potentially affected directly (e.g., crossed or used)
or indirectly (e.g., changed in use) by a project right-of-way,
potential route, or proposed ancillary or access site, as identified in
Sec. 900.6.
At the outset, DOE clarifies that the project proponent is
responsible for identifying potentially affected landowners based on
the definition provided in this final rule. Nevertheless, as provided
in this final rule, the project proponent must provide, as part of the
IIP Process, the methodology by which potentially affected landowners
were identified, which will allow DOE to evaluate the completeness of
the process. Additionally, while the project proponent makes this
determination, this final rule provides avenues for communities of
interest and stakeholders to comment on the proposed project and engage
with the project proponent; this definition does not limit those
avenues.
DOE has also made edits to this definition in response to comments.
First, DOE agrees with ACP that, at this stage, landowners are not
necessarily affected, but are only ``potentially'' affected.
Accordingly, DOE changes the defined term from ``affected landowner''
to ``potentially affected landowner'' and includes a reference to
``potential indirect and direct effects'' in the new definition.
Second, in response to ClearPath's comment, DOE has also revised
the definition in this final rule to broaden how real property
interests can be potentially impacted by the proposed project, which
aligns more closely with FERC's definition of ``affected landowner.''
DOE declines to adopt the exact same definition as FERC, reflecting
that FERC's permitting and siting rules do not have an identical
purpose to this final rule, which is to coordinate Federal
authorizations for transmission facilities.
Relatedly, DOE agrees with the commenters that suggested DOE revise
the distance referenced in the affected landowner definition. DOE
agrees that in certain instances the distances in the proposed rule
will be overinclusive and overly burdensome, but also that a one-size-
fits-all distance will not adequately capture all landowners that are
potentially affected by the transmission project. Because a single
distance does not provide sufficient flexibility to account for
differences in projects, DOE declines to adopt the 500-foot presumptive
distance proposed by Grid United. Instead, DOE has removed distances
from the definition of ``potentially affected landowner,'' and provides
that a potentially affected landowner is one whose real property
interest is either potentially affected directly or indirectly by the
proposed project. In addition, this final rule requires the project
proponent to describe the methodology used to identify potentially
affected landowners. This definition allows project proponents to more
precisely identify landowners who are most likely to be potentially
affected by the project, because those real property interests may not
always align with the distances included in the proposed rule and any
prescribed distances may be under or overinclusive depending on the
particulars of a project.
Additionally, DOE agrees with LTA's comment that the reference to
county and city tax records should be removed. As LTA noted, tax
records may not, depending on the circumstances, accurately include the
potentially affected real property interests. Accordingly, DOE has
revised this final rule to remove the requirement that the owner of the
real property interests is one who is usually referenced in the most
recent county or city tax records. However, this final rule does not
preclude the project proponent from referencing recent tax records. DOE
declines to require the involvement of communities of interest in the
identification of potentially affected landowners because this is an
unnecessary step for identifying real property interests. The term
``potentially affected landowners'' is not intended to refer to all
potential impacts; therefore, additional engagement on impacts of a
proposed project is not needed to satisfy this definition. Stakeholders
and communities of interest are among the terms that capture a broader
scope of potential impacts. This final rule also does not preclude
project proponents from involving communities of interest in this
process.
DOE also declines LTA's suggestion to include conservation easement
holders and landowners whose viewshed or other ecosystem services may
be impacted by the proposed electric transmission facility. DOE defines
potentially affected landowners in the context of real property
interests. In some cases, conservation easements may be considered a
real property interest and certain landowners whose viewshed or other
ecosystem services may be affected may fall within the definition of a
potentially affected landowner, but DOE declines to require that
project proponents always include these landowners since these
landowners may not always be owners of real property interests that are
potentially affected. Additionally, DOE has not adopted ACP's
suggestion to explicitly exclude mineral interest holders from the
definition, as notice to such parties is still important for
understanding reasonably foreseeable effects related to mineral entry
and exploration. Nor has DOE adopted ACP's recommendation to exclude
additional areas of potential construction work, because these areas
are potentially relevant for environmental review and these landowners
could be affected by the project.
Finally, DOE declines to require project proponents to provide a
landowner bill of rights. DOE disagrees with PIOs that a landowner bill
of rights is needed or useful for this process, because DOE's exercise
of its authority under section 216(h) does not confer eminent domain
authority. Although DOE declines to require the provision of a
landowner bill of rights, in response to PIOs' request that such a bill
of rights include information on the rehearing and review process and
the presidential appeals process, DOE notes that these topics are
discussed in Sections VI.O.i and ii of this document, respectively.
However, in response to both PIOs and LTA, DOE encourages all
interested parties to proactively engage transparently and in good
faith with appropriate stakeholders, including potentially affected
landowners, and may issue best practices on engagement as discussed in
section VI.E of this document.
ii. Analysis Area
DOE's Proposal
The NOPR did not provide a definition for ``analysis area'' nor did
it use this specific term. However, DOE sought comment from the public
on whether distances included in the proposed rule were appropriate,
which informed the definition of this term and are discussed below.
Summary of Public Comments
DOE requested specific comment on whether distances included in the
[[Page 35341]]
proposed rule were appropriate and received numerous recommendations on
changes to distances in this final rule.
ACEG commented that the 0.25-mile distance is too narrow in some
contexts or overly broad in others (e.g., affected landowners), and
that the distance should be determined by the impacts of the project.
Pew Charitable Trusts recommended that DOE allow greater flexibility,
stating that while the proposed distance comports with the distance
FERC would use for project notification requirements in the context of
National Interest Electric Transmission Corridors (NIETCs), some cases
warrant a wider area of review, including in areas that include
National Wildlife Refuges, designated wilderness areas, cultural
resources, or indigenous sacred sites. Pew Charitable Trusts suggested
that the distance proposal could be managed like the standard template
schedule, which is open to change depending on the project.
DOE received three comments specifically on the Land Use,
Recreation, and Aesthetics resource report. LTA supported the use of a
0.25-mile distance, but because the distance will vary based on the
specifics of each project and site, proposed that project proponents
also consider an area that a community of interest, including experts
from local conservation organizations, has identified as having one or
more resources likely to be impacted by a proposed project.
PIOs submitted that whether 0.25 miles is a sufficient distance is
largely dependent on the nature of the impacts that DOE is attempting
to identify. PIOs stated that wilderness areas are particularly
vulnerable to visual impacts and proposed that DOE use distances of 5-
10 miles for when considering visual impacts of proposed projects.
Relatedly, PIOs noted that certain areas preserved for wildlife habitat
may be vulnerable to adverse impacts from transmission projects at
distances greater than 0.25 miles, and accordingly, recommended that
areas with valuable habitat for migratory birds, such as National
Wildlife Refuges, should generally be identified no less than 10 miles
from the proposed transmission project, and that DOE should consult
with the relevant agencies and organizations to identify appropriate
distances.
The CARE Coalition stated that the 0.25-mile distance in the Land
Use, Recreation, and Aesthetics resource report is arbitrary and
unsuitable for several of the resources listed in that section,
including visual resources and wildlife habitat. Referencing research
at Argonne National Laboratory, the CARE Coalition suggested that a
minimum distance of 10 miles for 500 kV or greater lines and at least
five miles for 230-500 kV lines be used to identify sensitive visual
resources. Additionally, citing concerns over project impacts to bird
species, the CARE Coalition recommended DOE require proponents to
identify key habitats for migratory birds and mammals, such as National
Parks and National Wildlife Refuges, within 10 miles of proposed
projects or consult with the U.S. Fish and Wildlife Service (USFWS) to
identify adequate distances for critical migratory bird nesting and
stopover habitats, as well as for large mammal migration corridors.
The CEC/CPUC also stated that a 0.25-mile distance is often too
narrow and may not capture all indirect impacts, including visual
impacts on National Historical Landmarks. CEC/CPUC recommended that
distances should be developed with consideration to the scale and scope
of the proposed project and the specific resources evaluated.
The Arizona SHPO and CEC/CPUC proposed that DOE align distance
requirements with the Area of Potential Effect (APE) under section 106
of the NHPA. The Arizona SHPO recommended that DOE provide guidance to
project proponents to develop study areas that conform to the NEPA
definition of affected environment as applicable to resource type, and
for cultural resource assessments, includes the definition of an APE.
Relatedly, the Kentucky SHPO further noted that an APE of 0.25 miles
may be acceptable, depending on the type of transmission activities
proposed, whether it is new construction or a rebuild, the applicable
SHPO's guidance/standards, and any known resources near the proposed
project area. On the other hand, the NM SHPO stated that the 0.25-mile
distance is not adequate to address effects to cultural resources and
landscapes, National Historic Trails, and National Monuments,
especially in western states where the viewshed is expansive.
DOE Response
In this final rule, DOE removes the distances proposed, and adds a
defined term, ``analysis area.'' This approach allows the participants
in the IIP Process to determine the appropriate analysis area based on
project-specific factors.
DOE agrees with the many commenters who indicated the distances
should allow for more flexibility. Accordingly, DOE has determined that
specific distances should be removed from the final rule, as the
appropriate distances for various analyses depend on the relevant
physical characteristics and needs of the given project and resource at
issue. Instead, as discussed in the revisions to Sec. Sec. 900.5 and
900.8, DOE and the project proponent must, at the initial meeting,
establish initial analysis areas for each resource as determined by
project-specific factors like ecology, land use and ownership, and
other physical characteristics of the landscape. The proposed analysis
areas for each resource may then be refined and finalized during the
IIP Process review meeting. DOE confirms that establishment of such
analysis areas for wildlife, fish, and plant life will involve not only
the project proponent but the appropriate Federal and non-Federal
entities, like the USFWS and relevant State and local agencies, to
ensure analysis areas are adequate and consistent with those agencies'
requirements and appropriate guidance. Relatedly, DOE declines to align
the distance requirements with the APE under section 106 of the NHPA or
to add any other method of identifying distances, including relying on
distances identified by communities of interest, in favor of providing
greater flexibility for the reasons stated above. DOE notes that where
a legal standard exists for defining the area of analysis for a
particular resource, as in the case of the APE for historic properties,
the determination of the analysis area for that resource will take into
account that legal standard.
DOE is adding the defined term ``analysis area'' to account for the
removal of the distances, and provide a consistent use of terminology
throughout the final rule that accounts for the project's
characteristics and needs and the resources at issue. DOE defines
analysis area to mean an area established for a resource report at the
IIP Process initial meeting and modified at the IIP Process review
meeting, as applicable. Discussion of specific uses of this term is
included in section VII of this document.
iii. Communities of Interest
DOE's Proposal
In the NOPR, DOE proposed to add a definition for ``communities of
interest'' to ensure broad coverage of potentially impacted populations
during the public engagement process and establishment of the public
engagement plan. In the NOPR, DOE also proposed to define communities
of interest to include disadvantaged, fossil energy, rural, Tribal,
indigenous, geographically proximate, or communities with environmental
justice concerns that
[[Page 35342]]
could be affected by the qualifying project.
Summary of Public Comments
DOE received multiple comments suggesting amendments or
clarifications to the definition of ``communities of interest'' in the
proposed rule.
ClearPath opposed DOE's definition of communities of interest,
commenting that the definition is ambiguous and lacks ``legal
durability.'' ClearPath pointed specifically to the phrase
``geographically proximate'' as ambiguous and commented that the
phrase, ``communities with environmental justice concerns'' provides no
methodology for project proponents to adequately identify these
communities. Niskanen Center proposed that further guidance on the term
might include precise parameters such as defining it as being within
0.25 miles of a study corridor or potential route. Niskanen Center also
indicated that the precise meaning of the terms ``disadvantaged,''
``fossil energy,'' ``rural,'' ``geographically proximate,'' or
``communities with environmental justice concerns'' is unclear,
potentially leading to confusion and litigation in the IIP Process and
CITAP Program.
EDF stated that the broad proposed definition of ``communities of
interest'' could potentially overlook key differences among and within
the identified communities. Referencing several White House commitments
and executive orders concerning impacts on communities with
environmental justice concerns, EDF advised DOE to ensure it carefully
addresses the concerns of those communities in the proposed rule.
PIOs lauded the proposed rule's definition of communities of
interest for broadly including Indigenous communities. Similar to EDF's
comments, PIOs maintained that DOE revise its definition of
``communities of interest'' to better reflect environmental justice
issues. PIOs recommended that DOE remove the term ``disadvantaged,''
specifically include ``communities of Color'' and ``low-income or low-
wealth communities'' in the definition, and capitalize the terms
``Color'' and ``Indigenous.''
PIOs also suggested that DOE clarify and ``equitably describe'' the
definition of ``fossil energy'' and align the definition of
``overburdened'' with the U.S. Environmental Protection Agency (EPA) EJ
2020 Glossary. PIOs then urged DOE to specifically require project
proponents to describe how they will reach out to communities of
interest about mitigation and require the resource report to describe
proposed measures or community concerns. PIOs also recommended that DOE
require project proponents to solicit community comments regarding
their preferred form of mitigation and to respond to those comments.
Policy Integrity suggested that for project proponents to identify
communities of interest more accurately--especially given that DOE does
not define ``disadvantaged,'' ``fossil energy,'' ``rural,'' or
``communities with ``environmental justice concerns''--DOE should
provide administrable criteria, such as project proponents locating
``disadvantaged'' communities via the Climate and Economic Justice
Screening Tool. Policy Integrity also recommended that DOE consider
allowing communities to self-identify, which would ensure that
communities are not excluded because of limitations of existing
identification tools or methods. The commenter also indicated it would
be more appropriate for DOE to adjudicate whether a community should be
considered as having environmental justice concerns based on evidence
submitted rather than allowing the project proponent to make this
determination.
LTA suggested that the definition of communities of interest should
include local nonprofit conservation organizations to ensure that the
conservation and working lands community is included early in the IIP
Process.
Finally, NATHPO and the Santa Rosa Rancheria Tachi Yokut Tribe
commented that categorizing Tribal Nations as ``Communities of
Interest'' fails to recognize the sovereignty of Tribal Nations. By
doing so, NATHPO and the Santa Rosa Rancheria Tachi Yokut Tribe argued
that the proposed rule neglects distinct nation-to-nation
responsibilities.
DOE Response
In this final rule DOE has revised the definition of ``communities
of interest'' to improve readability and ensure consistency with the
Inflation Reduction Act (Pub. L. 117-169) (IRA) but has retained the
communities identified in the proposed rule, as discussed below. DOE
notes that the project proponent is responsible for identifying
communities of interest and taking the required actions with respect to
these communities for purposes of complying with the proponent's
responsibilities under these regulations, but through the IIP Process,
DOE and the relevant Federal entities and relevant non-Federal entities
will have the opportunity to assess the processes by which proponents
identify and engage with communities of interest.
To improve the readability of the definition, DOE has revised the
structure of the definition to provide a list of the types of
communities that are communities of interest. To that end, to clarify
that the communities listed in the definition is the exclusive set of
communities to which this definition applies, this final rule edits the
definition to note that communities of interest ``means'' rather than
``includes'' the listed communities. Finally, DOE has changed the
reference to ``fossil energy'' communities to ``energy communities'' to
align the terminology with that used throughout the IRA's programs.
DOE appreciates the comments regarding the scope of ``communities
of interest'' and the communities included in the definition. DOE
declines to revise the communities included within the definition
beyond the revision to ``fossil energy'' communities discussed above.
DOE declines to prescribe a particular distance for ``geographically
proximate'' communities for reasons similar to those explained above in
connection with ``analysis area.'' For any given project or community,
a set 0.25-mile distance could be over- or under-inclusive. Instead,
the current definition provides flexibility and broad coverage for the
project proponent to identify the communities that could be affected by
a given project.
DOE also declines to provide definitions for the terms used in the
definition of communities of interest, or to otherwise narrow the
definition. As written, the definition of communities of interest
provides broad coverage of various communities and flexibility to
consider relevant groups that may fall within such communities. Because
the ways in which a project may affect certain communities varies, DOE
believes that the definition in this final rule appropriately provides
flexibility to encompass the potentially varied affected communities of
interest. Relatedly, DOE declines to provide particular criteria that a
project proponent must consider in identifying communities of interest,
to permit communities to self-identify or to require that proponents
engage further with community members, or to administer in the first
instance whether a particular community qualifies, in favor of
providing flexibility to the project proponent and the ability of DOE
and the relevant Federal entities and relevant non-Federal entities to
assess and refine the identification as needed throughout the IIP
Process.
DOE declines to remove or replace the term ``disadvantaged'' and
declines to include ``communities of Color'' and
[[Page 35343]]
``low-income or low-wealth communities.'' The term provides flexibility
for the project proponent to consider a broad range of disadvantaged
communities that could be affected by the proposed project. Consistent
with its usage throughout this rule, as well as in rules promulgated by
other agencies such as FERC, DOE declines to capitalize the term
``indigenous.'' Whether or not the term is capitalized, project
proponents have the same responsibilities to these communities.
Additionally, DOE declines to include nonprofit groups, as
requested by LTA, as the definition is focused on communities, not
organizations or entities. Nevertheless, this final rule does not
preclude an organization from representing a community during IIP
Process engagement, and additionally provides a definition of
stakeholder that could include the type of organization LTA describes.
Lastly, DOE affirms the sovereignty of Indian Tribes. DOE clarifies
that the inclusion of Tribal communities in the definition of
communities of interest is not intended to, nor does it, neglect the
nation-to-nation responsibilities of Federal agencies when engaging
with Indian Tribes, which are distinct from the project proponent's
responsibilities under the CITAP Program. The CITAP Program and final
rule make no changes to Federal agencies' nation-to-nation
responsibilities. DOE's intent in including Tribal communities in the
definition is to establish an expectation that project proponents
engage with and consider the impacts of proposed projects on Tribal
communities.
iv. Other Definition Changes
1. Mitigation Approach and Mitigation Strategies or Plans
DOE's Proposal
The NOPR included definitions for two terms, ``landscape mitigation
approach'' and ``landscape mitigation strategies or plans.'' In the
NOPR, DOE proposed to define landscape mitigation approach to mean an
approach that applies the mitigation hierarchy to develop mitigation
measures for impacts to resources from a qualifying project at the
relevant scale, however narrow or broad, that is necessary to sustain
those resources, or otherwise achieve established resources. Among
other things, the definition explained that the mitigation hierarchy
refers to an approach that first seeks to avoid, then minimize impacts,
and then, when necessary, compensate for residual impacts; while a
landscape mitigation approach identifies the needs and baseline
conditions of targeted resources, potential impacts from the qualifying
project, cumulative impacts of past and likely projected disturbances
to those resources, and future disturbance trends, then uses this
information to identify priorities for mitigation measures across the
relevant area to provide the maximum benefit to the impacted resources.
In the NOPR, DOE proposed to define landscape mitigation strategies
or plans as documents developed through, or external to, the NEPA
process that apply a landscape mitigation approach to identify
appropriate mitigation measures in advance of potential impacts to
resources from qualifying projects.
Summary of Public Comments
ACP recommended that DOE cabin the definition of landscape
mitigation approach. Specifically, ACP suggested that the definition
include a materiality threshold for all references to impacts to limit
overreach and include language regarding the practicability of such an
approach. ACP elaborated that the definition should also permit
mitigation efforts to be conducted following stakeholder engagement,
allow for a deferral of such approach to mitigation in lieu of agency-
driven mitigation approaches, and, where stakeholder engagement efforts
are ongoing, allow for those processes to fully inform the selected
mitigation measures.
DOE Response
In this final rule, DOE has revised ``landscape mitigation
approach'' to a more general term ``mitigation approach'' and removed
the defined term ``landscape mitigation strategies or plans.''
DOE revised the definition for ``landscape mitigation approach''
because limiting mitigation approaches to only landscape-level
approaches and strategies may not be sufficiently flexible to account
for the variety of needs implicated by this rule. Rather than prescribe
a single approach, DOE believes that this final rule should create an
opportunity for consideration and discussion of multiple types of
proposed mitigation for a given proposed project. In addition, DOE has
revised this definition for clarity and to more closely align with
existing NEPA regulations regarding mitigation.
DOE declines to implement ACP's suggestion to include a materiality
threshold and a discussion of the practicability of any proposed
mitigation approaches to limit overreach, because no decisions are
being made on mitigation during the IIP Process. Instead, as part of
the IIP Process, the project proponent is expected to bring to DOE and
any relevant Federal entities and relevant non-Federal entities a
proposed mitigation approach, which will facilitate the development of
a shared understanding of project needs and expectations.
DOE also disagrees with ACP's suggestion to include stakeholder
engagement in development of proposed mitigation approaches both
ongoing and future. This final rule encourages stakeholder engagement
by the project proponent throughout the IIP Process and the rule does
not preclude the engagement described in ACP's comment. DOE avoids
codifying a particular mitigation approach process in regulatory text,
as this process may inaccurately indicate a preference or priority for
the approach.
Because the revisions to mitigation approach rendered ``landscape
mitigation strategies or plans'' redundant, DOE has removed this
defined term from this final rule.
2. MOU Signatory Agency
DOE's Proposal
In the NOPR, DOE proposed to define ``MOU Signatory Agency'' to
mean a signatory of the interagency Memorandum of Understanding
executed in May 2023, titled ``Memorandum of Understanding among the
U.S. Department of Agriculture, Department of Commerce, Department of
Defense, Department of Energy, the Environmental Protection Agency, the
Council on Environmental Quality, the Federal Permitting Improvement
Steering Council, Department of the Interior, and the Office of
Management and Budget Regarding Facilitating Federal Authorizations for
Electric Transmission Facilities.''
Summary of Public Comments
ACP submitted that, in addition to the nine agencies that signed
the 2023 MOU, the definition should include any signatories to similar
or subsequent MOUs entered into in the future.
DOE Response
DOE agrees with ACP's comment that MOU Signatory Agency should be
sufficiently broad to cover not only those signatories to the MOU
executed in May 2023, but also to cover signatories to potential
similar or subsequent MOUs entered into pursuant to section
216(h)(7)(B)(i) of the FPA later in time. This final rule revises this
definition to provide this flexibility, such that if a future MOU
includes additional or different agencies, the
[[Page 35344]]
definition in this final rule will not need to be revised accordingly.
3. Relevant Non-Federal Entity
DOE's Proposal
In the NOPR, DOE proposed to define ``non-Federal entity'' as an
Indian Tribe, multi-State governmental entity, State agency, or local
government agency, and to define ``relevant non-Federal entity'' as a
non-Federal entity with relevant expertise or jurisdiction within the
project area, that is responsible for issuing an authorization for the
qualifying project, that has special expertise with respect to
environmental and other issues pertinent to or potentially affected by
the qualifying project, or that provides funding for the qualifying
project. The NOPR also proposed to provide that term includes an entity
with either permitting or non-permitting authority, such as an Indian
Tribe, Native Hawaiian Organization, or State or Tribal Historic
Preservation Offices, with whom consultation must be completed in
accordance with section 106 of the NHPA prior to approval of a permit,
right-of-way, or other authorization required for a Federal
authorization.
Summary of Public Comments
DOE received two comments on the definition of relevant non-Federal
entity. AZGFD recommended that DOE include State wildlife agencies as
standard non-Federal entities engaged in the IIP Process. AZGFD noted
that State wildlife agencies can provide project-specific special
expertise on wildlife species occurrence and distributions, areas of
potential concern, wildlife connectivity, and more, as well as advise
on potential conservation measures to avoid, minimize, or offset
potential impacts. PIOs commented that DOE should expand the definition
to allow certain members of the public to participate in the IIP
Process. PIOs noted that, as drafted, the definition excludes community
groups or public interest organizations because they are not
regulators, even if they have special expertise with respect to
environmental and other issues pertinent to or potentially affected by
the qualifying project. Instead, the proposed rule would consider these
entities as stakeholders, who, as PIOs argued, have significantly less
access to the IIP Process compared with relevant non-Federal entities.
PIOs believe that allowing community and public interest groups with
special expertise to participate in the IIP Process would further the
rule's aim to create an opportunity to identify as early as possible
potential environmental and community impacts associated with a
proposed project. Relatedly, PIOs recommended that DOE define the term
``special expertise'' to help project proponents, affected communities,
and public interest organizations in better understanding what groups
may meet this definition and allow community or public interest groups
to request that they be permitted to participate in the IIP/CITAP
Process by explaining what special expertise they possess.
DOE Response
DOE revises the definition of relevant non-Federal entity to
replace ``special expertise'' with ``relevant expertise'' to avoid
confusion with the NEPA-defined term ``special expertise.'' DOE
declines any further revisions to the definition of relevant non-
Federal entity that would expand its scope in this final rule.
First, DOE notes that because State wildlife agencies are likely to
have relevant expertise or jurisdiction within the proposed project
area, may be responsible for issuing an authorization for the
qualifying project, may have relevant expertise with respect to
environmental and other issues pertinent to or potentially affected by
the qualifying project, or may provide funding for the qualifying
project, such agencies may meet the definition of a relevant non-
Federal entity. The list of non-Federal entities included in the
definition merely provides examples and is not a comprehensive list.
Next, DOE appreciates the expertise of community groups and public
interest organizations. Rather than expand the definition of relevant
non-Federal entity, DOE believes that the IIP Process, coupled with
existing avenues for public comment, will best integrate the expertise
and input of community groups and public interest organizations. The
IIP Process provides for timely and focused pre-application meetings
with relevant Federal entities and relevant non-Federal entities, as
well as for early identification of potential siting constraints and
opportunities, and seeks to promote thorough and consistent stakeholder
engagement by a project proponent. The IIP process is not, however,
intended to supplant existing public comment processes afforded by
relevant statutes, such as NEPA. DOE believes that it has appropriately
defined relevant non-Federal entity to provide the necessary
information to fulfill its obligations under section 216(h) and
facilitate the pre-application process, while still providing
sufficient avenues for others to participate as stakeholders and
through those existing public-comment processes. DOE declines to
provide a definition for special expertise because the term has been
removed from the rule. DOE does not expand the definition of non-
Federal entity to explicitly include non-regulating or non-permitting
entities as the current definition may already include those entities
as long as they meet additional criteria.
4. Stakeholder
DOE's Proposal
In the NOPR, DOE proposed to define the term ``stakeholder'' to
mean any relevant non-Federal entity, any non-governmental
organization, affected landowner, or other person potentially affected
by a proposed qualifying project.
Summary of Public Comments
ACP commented that the proposed definition of ``stakeholder'' is
overly broad, including its reference to anyone ``potentially affected
by the proposed qualifying project.'' ACP suggested that DOE narrow the
definition to a party able to show some cognizable interest potentially
being affected by the project.
DOE Response
In this final rule, DOE revises the definition of ``stakeholder''
to provide that the term means any relevant non-Federal entity,
interested non-governmental organization, potentially affected
landowner, or other interested person or organization.
In part, DOE has revised this definition to reflect the revision to
terminology used in this final rule, i.e., replacing ``affected
landowner'' with ``potentially affected landowner,'' for the reasons
explained above. DOE has also revised the definition to provide more
precise parameters for who is a stakeholder for purposes of this final
rule, in some instances narrowing the definition and in others,
broadening it. Specifically, the definition clarifies that only
``interested,'' rather than ``all,'' non-governmental organizations are
stakeholders, which appropriately limits coverage to only those non-
governmental organizations that have interest in the proposed project.
Additionally, DOE revises the definition to provide that any other
stakeholders must be ``interested'' and provides that stakeholders may
be interested persons or organizations. This revision broadens the
scope of other stakeholders beyond only persons, allowing those
organizations that do not fall within the scope of relevant non-Federal
entity, non-governmental organization, or potentially affected
landowner to be considered stakeholders. DOE believes
[[Page 35345]]
this revision is appropriate given the diversity of entities that may
be affected by or interested in a proposed project. Additionally, the
revision broadens the definition beyond those who are potentially
affected to those who are interested. Again, DOE believes this
expansion is appropriate in light of various entities that may have
equities in a proposed project. For instance, LTA raised in its comment
that local conservation organizations may have relevant expertise and
views on a proposed project.
DOE disagrees with ACP's proposal to narrow the definition to only
those parties able to show some cognizable interest potentially being
affected by the project. First, DOE does not discern a practical
difference in requiring that an interest be ``cognizable,'' and
believes that DOE's definition is consistent with ACP's intent to
ensure stakeholders have an interest in or are potentially affected by
a proposed project. Second, DOE believes ACP's proposal is
unnecessarily narrow and may potentially exclude relevant persons,
organizations, or entities from the CITAP Program, including relevant
non-Federal entities. Finally, DOE clarifies that this definition does
not determine who is a party or has standing to challenge a relevant
authorization or related environmental review document issued under
section 216(h).
5. Study Corridor
DOE's Proposal
DOE proposed to define study corridor as a contiguous area (not to
exceed one mile in width) within the project area where alternative
routes or route segments may be considered for further study.
Summary of Public Comments
DOE received two comments on the definition of the term study
corridor. ACP recommended that the definition regarding consideration
of NEPA alternative routes should be restricted to only those within
the study corridor. ACP also recommended that the definition of study
corridor be limited to alternative routes already within consideration
of the study corridors, because, as ACP argued, this would cabin the
scope of review and is necessary to avoid potential litigation risk if
the rule were to require proponents to consider all potential
alternative routes. OSPA requested that this final rule allow for study
corridors wider than one mile to consider more alternative transmission
paths. OSPA described that the one-mile width restriction is
inconsistent with the broad definition of ``project area,'' which may
limit the evaluation of potential transmission sites. OSPA therefore
urged DOE to either change the definition or allow proponents to
request exemptions from the one-mile restriction.
DOE Response
In this final rule, DOE revises the definition of study corridor to
clarify the role of study corridors and the relationship between this
term and other NEPA-related terms, as provided in section IV of this
document.
DOE declines to revise the definition as ACP recommended. First,
DOE clarifies that the project area may contain multiple study
corridors and that those study corridors may include multiple potential
routes. Additionally, DOE notes that study corridors are proposed by
the project proponent, and the number of such study corridors will be
driven by the project proponent, depending on the level of development
of the project design at the time of IIP Process initiation. While
these study corridors are developed by the project proponent, nothing
in this rule commits DOE to limiting NEPA alternatives to these study
corridors. The definition suffices to allow DOE and the relevant
Federal entities to evaluate the study corridor and potential NEPA
alternatives through the IIP Process.
DOE declines to implement OSPA's recommendation that the definition
allow for study corridors wider than one mile. DOE assesses that the
one-mile distance suffices to provide DOE and the relevant Federal
entities with the information necessary to make the relevant
determinations and issue the relevant authorizations, while avoiding
overburdening the project proponent.
6. Resilience
DOE's Proposal
As noted, DOE proposed to require the submission of 13 resource
reports, one of which would be titled Reliability, Resilience, and
Safety.
Summary of Public Comments
One anonymous commenter noted that DOE did not provide a definition
of the term ``resilience'' and requested that DOE define the term.
DOE Response
DOE declines in the final rule to provide a definition for the term
``resilience.'' This term does not appear outside of the Reliability,
Resilience, and Safety resource report and its meaning is evident from
the substance of that report.
7. Proposed Facility
DOE's Proposal
In the NOPR, DOE used the term ``proposed facility'' to delineate
the scope of certain information project proponents would be required
to submit. For instance, the NOPR proposed in Sec. 900.3(b) to require
the project proponent to provide a concise description of the proposed
facility and a list of anticipated relevant Federal and non-Federal
entities involved in the proposed facility.
Summary of Public Comments
CARE Coalition requested that DOE provide a definition of the term
``proposed facility.''
DOE Response
DOE declines in the final rule to provide a definition for proposed
facility. DOE believes that the meaning of this term is sufficiently
clear from the context and notes that through the IIP Process, project
proponents will be able to refine the scope of the proposed facility as
needed.
L. Resource Reports
The PIOs noted that DOE's resource reports are similar to the
resource reports required under FERC's proposed rule regarding FERC's
siting authority in NIETCs, per FPA section 216(b). The PIOs
recommended that DOE align the numbering of resource reports with the
numbering in FERC's proposed rule. DOE agrees with the suggested
numbering change and has renumbered the reports accordingly. The
following table catalogs the renumbering.
------------------------------------------------------------------------
Proposed rule Final rule
Resource report name numbering numbering
------------------------------------------------------------------------
General Project Description..... Resource Report 1. Resource Report 1.
Water Use and Quality........... Resource Report 2. Resource Report 2.
Fish, Wildlife, and Vegetation.. Resource Report 3. Resource Report 3.
Cultural Resources.............. Resource Report 4. Resource Report 4.
Socioeconomics.................. Resource Report 5. Resource Report 5.
Geological Resources............ Resource Report 6. Resource Report 8.
[[Page 35346]]
Soil Resources.................. Resource Report 7. Resource Report 9.
Land Use, Recreation, and Resource Report 8. Resource Report
Aesthetics. 10.
Communities of interest......... Resource Report 9. Resource Report 7.
Air Quality and Noise Effects... Resource Report 10 Resource Report
11.
Alternatives.................... Resource Report 11 Resource Report
12.
Reliability, Resilience, and Resource Report 12 Resource Report
Safety. 13.
Tribal Interests................ Resource Report 13 Resource Report 6.
------------------------------------------------------------------------
In this final rule, DOE also makes non-substantive edits to the
proposed rule text of the resource reports to clarify the intent of the
reports and clearly state the information that must be included in the
reports. Across the resource reports, DOE reorganizes the proposed
paragraphs to state the purpose of the resource report in the
introductory paragraph (e.g., paragraph (j)) and list all requirements
for the resource report in subparagraphs (e.g., paragraphs (j)(1), (2),
etc.).
DOE's responses to comments on the resource report requirements as
well as additional changes to the resource report requirements are
discussed as follows. The ordering of the discussion follows the
ordering of the resource reports in the NOPR.
i. General Project Description Resource Report
DOE's Proposal
In the NOPR, DOE proposed to require the submission of a resource
report containing a general project description. The NOPR proposed that
this report describe facilities associated with the project, special
construction and operation procedures, construction timetables, future
plans for related construction, compliance with regulations and codes,
and permits that must be obtained.
In the NOPR, DOE proposed 12 topics that would be required as part
of the report. The NOPR required that the project proponent: describe
and provide location maps of all relevant facilities, access roads, and
infrastructure; describe specific generation resources that are known
or reasonably foreseen to be developed or interconnected; identify
other companies that may construct facilities related to the project
and where those facilities would be located; provide certain
information regarding the facilities identified; provide certain
information if the project is considering abandonment of certain
resources; describe proposed construction and restoration methods;
describe estimated workforce requirements; describe reasonably
foreseeable plans for future expansion of facilities; describe all
authorizations required and identify environmental mitigation
requirements; provide the names and mailing addresses of all affected
landowners; summarize any relevant potential avoidance, minimization,
and conservation measures; and describe how the project will reduce
capacity constraints and congestion on the transmission system, meet
unmet demand, or connect generation resources to load, as appropriate.
Summary of Public Comments
DOE received one comment addressing the General Project Description
resource report that is not already addressed in other sections of the
discussion. ClearPath opposed the requirement that project proponents
``describe how the project will reduce capacity constraints and
congestion on the transmission system, meet unmet demand, or connect
generation resources (including the expected type of generation, if
known) to load, as appropriate,'' arguing that this information is
outside the scope of Federal jurisdiction under FPA 216(h).
That comment and others addressing reasonable and foreseeable
generation are discussed in section VI.D of this document.
DOE Response and Summary of Other Changes
In this final rule, DOE retains the scope and purpose of this
resource report with no revisions in response to ClearPath's comment
because information may be helpful for understanding the project
proponent's purpose and need and the potential scope of the
environmental review, consistent with DOE's coordinating obligations
under FPA section 216(h).
Additionally, DOE is eliminating a requirement from the NOPR for
this report to include correspondence with the USFWS and National
Marine Fisheries Service regarding potential impacts of the proposed
facility on federally listed threatened and endangered species and
their designated critical habitats because that correspondence is
already required in Resource Report 3: Fish, Wildlife, and Vegetation,
thereby reducing duplication of requirements.
ii. Water Use and Quality Resource Report
DOE's Proposal
In the NOPR, DOE proposed requiring project proponents to submit a
report on existing water resources that may be impacted by the proposed
project, the impacts of the proposed project on those resources, and
proposed mitigation, enhancement, or protective measures to address
those impacts.
Summary of Changes
DOE did not receive any comments on the Water Use and Quality
Report that have not been addressed in another section of this final
rule. However, DOE has made several changes to the requirements for the
resource report between the NOPR and this final rule.
In keeping with the discussion in section VI.K.ii of this document,
DOE is replacing two distances included in the proposed rule with ``in
the applicable analysis area'' to give DOE, the project proponent, and
appropriate Federal and non-Federal entities flexibility to set these
distances based on the physical characteristics and needs of the
project. A project proponent must now identify the location of known
public and private groundwater supply wells or springs within the
applicable analysis area rather than within ``150 feet of proposed
construction areas.'' A project proponent must now identify any
downstream potable water intake sources within the applicable analysis
area, rather than ``three miles downstream'' of a surface water
crossing.
DOE is making several terminology changes to clarify the scope of
the analyses required by the report. The report now requires the
project proponent to identify surface water resources crossed by a
``potential route'' rather than ``the project.'' The report also
requires wetland maps showing ``study corridors and potential routes''
rather than just a ``proposed route.'' Finally, the report requires
identification of aquifers and wellhead protection area crossed by a
``potential route,'' rather than ``proposed facilities.''
[[Page 35347]]
Lastly, DOE is relocating a requirement to indicate whether a water
quality certification under section 401 of the CWA will be required for
any potential routes. This requirement was proposed for the General
Project Description resource report but has been moved into the
requirements for this report because it deals directly with water
resources.
iii. Fish, Wildlife, and Vegetation Resource Report
DOE's Proposal
In the NOPR, DOE proposed to require the submission of a resource
report on fish, wildlife, and vegetation. As proposed, DOE required
this report to include a description of aquatic life, wildlife, and
vegetation in the proposed project area; expected impacts on these
resources including potential effects on biodiversity; and proposed
mitigation, enhancement, avoidance, or protection measures. DOE also
proposed that this resource report may require species surveys to
determine significant habitats or communities of species of special
concern to Federal, Tribe, State or local agencies, or field surveys to
determine the presence of suitable habitat. Finally, DOE proposed
requiring the project proponent to provide a description of the
proposed measures to avoid and minimize incidental take of Federally
protected species, including eagles and migratory birds as part of this
resource report.
Summary of Public Comments
DOE received two comments on the Fish, Wildlife, and Vegetation
resource report, from AZGFD and the CARE Coalition.
AZGFD encouraged DOE to include State wildlife sensitive species,
especially those classified as of Greatest Conservation Need in
individual State Wildlife Action Plans. AZGFD also recommended that
potential impacts from habitat loss and fragmentation, including
potential impacts on wildlife connectivity, identified habitat linkages
or wildlife corridors, be analyzed in the report, considering that
transmission infrastructure affects wildlife movements and habitat use.
It suggested that DOE provide guidance in the rule regarding
coordination with State wildlife agencies on conservation measures
necessary for adequate wildlife connectivity.
The CARE Coalition suggested that the report should describe known
migratory corridors for large mammals within three kilometers of the
proposed line. The CARE Coalition also suggested that project
proponents should consult with USFWS to determine a distance at which
the project proponent should identify Federally listed or proposed
endangered or threatened species and critical habitats in the report.
DOE Response and Summary of Other Changes
DOE makes minor revisions in response to these comments. In
response to AZGFD's request to include classifications like ``Greatest
Conservation Need,'' DOE revises this final rule to request relevant
information on ``State, Tribal, and local species of concern and those
species' habitats'' because DOE believes this broader terminology
addresses the concern raised by the commenter and additionally extends
to consider species, habitats, or communities of species of concern to
Federal, Tribal, State, or local agencies. DOE also agrees that habitat
fragmentation impacts are relevant to the resource report and revises
this final rule to include information on the potential effects of the
proposed project on habitats, including effects related to habitat loss
and fragmentation. Regarding AZGFD's request for guidance on
coordination with State wildlife agencies, DOE makes no changes to this
final rule as such coordination will depend on project specific
circumstances, for example if a wildlife agency in the State
participates as a relevant non-Federal entity in the IIP Process.
In response to CARE Coalition's request to include mammalian
migratory corridors, DOE makes no revisions to this final rule. DOE
believes the detail requested in the resource report is sufficient to
provide such information if it is relevant to the project.
DOE is also making changes to the proposed rule text that are not
in response to a specific comment. DOE is making several changes to
clarify the scope of the analyses required in the report. The rule now
requires the project proponent to identify aquatic habitats in the
``applicable analysis area'' rather than in the ``affected area'' and
cabins the requirement to identify terrestrial habitats to only those
terrestrial habitats in the project area. The rule also requires
information on essential fish habitat which may be adversely affected
by ``potential routes,'' rather than ``the project.''
In keeping with the discussion in section VI.K.ii of this document,
DOE is replacing four distances and areas included in the proposed rule
with ``in the applicable analysis area'' to give DOE, the project
proponent, and appropriate Federal and non-Federal entities flexibility
to set these distances based on the physical characteristics and needs
of the project. DOE is now requiring a project proponent to identify
aquatic habitats that occur in the ``applicable analysis area'' rather
than in the ``affected area.'' Additionally, DOE is requiring the
project proponent to identify proposed or designated critical habitats
that potentially occur in the ``applicable analysis area'' rather than
the ``project area.'' DOE is also now requiring a project proponent to
identify the location of potential bald and golden eagle nesting and
roosting sites, migratory bird flyways, and any sites important to
migratory bird breeding, feeding, and sheltering within the
``applicable analysis areas,'' rather than within ``10 miles of the
proposed project area.'' While 10 miles is currently the USFWS
standard, DOE opts to leave establishment of these boundaries flexible
for future project needs as well as any future updates to USFWS
requirements. Likewise, DOE is requiring the project proponent to
identify all Federally designated essential fish habitat that occurs in
the ``applicable analysis area'' whereas in the proposed text, the
scope of that identification was undefined.
Lastly, the rule clarifies the role of surveys in the resource
report. The rule provides that the project proponent must include the
results of any appropriate surveys that have already been conducted and
provide protocols for future surveys. The rule maintains the provision
that if potentially suitable habitat is present, species-specific
surveys may be required.
iv. Cultural Resources Resource Report
DOE's Proposal
In the NOPR, DOE proposed to require the submission of a resource
report on cultural resources, which would contribute to the
satisfaction of DOE's and other relevant Federal entities' obligations
under section 106 of the NHPA. The NOPR required the resource report to
describe known cultural and historic resources in the affected
environment, including those listed or eligible for listing on the
National Register of Historic Places (NRHP), potential adverse effects
to those resources, and recommended avoidance and minimization measures
to address those potential effects. It also required the resource
report to document the project proponent's initial communications and
engagement with and comments from Indian Tribes, indigenous peoples,
THPOs, SHPOs, communities of interest, and other relevant entities, and
provide details
[[Page 35348]]
regarding surveys. Finally, the NOPR required that the project
proponent request confidential treatment for all materials filed with
DOE containing location, character, and ownership information about
cultural resources.
Summary of Public Comments
DOE received one comment on the Cultural Resources Resource Report
from NM SHPO that is not otherwise addressed in section VI.J of this
document.
NM SHPO appreciated DOE's requirement for project proponents to
consider treatments to avoid, minimize, or mitigate harmful impacts to
the landscape, but encouraged DOE to also require project proponents to
consider these treatments for individual historic properties eligible
for or listed in the NRHP. This inclusion would require that resource
reports begin with historic contexts for landscape-level evaluations
and that other Federal agencies examine landscape-level eligibility and
effects during the review of resource reports. The NM SHPO noted that
in New Mexico, consultants are required to meet State documentation
guidelines before accessing cultural resource records to produce a
cultural resources report, and subsequently questioned whether DOE's
regulation will acknowledge or supersede State statutes, regulations,
or guidelines.
DOE Response and Summary of Other Changes
DOE makes no revisions in response to NM SHPO's comment. DOE
clarifies that while the CITAP Program is intended to facilitate
coordination with relevant State statutes, regulations, and guidelines,
the rule does not supersede State statutes, regulations, or guidelines.
Regarding the NM SHPO's request that the rule should consider
treatments to mitigate harmful impacts on certain individual
properties, DOE notes that the rule does not preclude this sort of
action, but makes no revisions to mandate a particular approach to
mitigation because DOE believes these approaches are more appropriate
to discuss in the context of project-specific circumstances. The
updated definition of mitigation approach in this final rule is
intended to create an opportunity for consideration and discussion of
multiple types of mitigation strategies for a proposed project. DOE
also notes that no decisions are made on mitigation during the IIP
Process; rather, the IIP Process facilitates the development of a
shared understanding of project needs and expectations.
DOE is also making several changes to the proposed rule text that
are not in response to a specific comment. In keeping with the
discussion in section VI.K.ii of this document, DOE is now requiring a
summary of known cultural and historic resources in the ``applicable
analysis area'' rather than in the ``affected environment.''
Furthermore, in the requirement to provide a summary of known
cultural and historic resources, DOE is adding as an example of those
resources, properties of religious and cultural significance to Indian
Tribes, and any material remains of past human life or activities that
are of an archeological interest. This change was made to broaden and
clarify the definition of cultural resources included in the rule.
v. Socioeconomics Resource Report
DOE's Proposal
In the NOPR, DOE proposed to require the submission of a resource
report on socioeconomics. DOE proposed to require in this resource
report the identification and quantification of the impacts of
constructing and operating the proposed project on the demographics and
economics of communities in the project area, including minority and
underrepresented communities.
Summary of Public Comments
DOE received one comment addressing the required elements of the
Socioeconomics resource report. ClearPath recommended that DOE exclude
the requirement for project proponents to ``evaluate the impact of any
substantial migration of people into the proposed project area on
governmental facilities and services and describe plans to reduce the
impact on the local infrastructure'' because it is ambiguous and beyond
DOE's statutory authority. Furthermore, ClearPath noted the project
proponent is not responsible for minimizing the impact on local
infrastructure from the significant migration of people.
DOE Response
DOE makes no revisions in response to this comment because DOE
finds this information is commonly requested for evaluating the impacts
of infrastructure permitting.\12\
---------------------------------------------------------------------------
\12\ See, for example, 10 CFR 380.16(g).
---------------------------------------------------------------------------
DOE is making several changes to the proposed rule text that are
not in response to a specific comment. In keeping with the discussion
in section VI.K.ii of this document, DOE is replacing multiple areas of
study included in the proposed rule with ``in the applicable analysis
area'' to give DOE, the project proponent, and appropriate Federal and
non-Federal entities flexibility to set these distances based on the
physical characteristics and needs of the project. The rule now
requires the project proponent to describe the socioeconomic resources
that may be affected in the ``applicable analysis area'' rather than in
the ``project area.'' Likewise, the rule requires the project proponent
to evaluate the impact of any substantial migration of people into the
``applicable analysis area'' rather than the ``proposed project area.''
Finally, the rule replaces ``impact area'' with ``applicable analysis
area'' in several instances because ``impact area'' is not defined in
the rule.
vi. Geological Resources and Hazards Resource Report
DOE's Proposal
The NOPR proposed requiring project proponents to submit a resource
report on geological resources that might be affected by the proposed
project and geological hazards that might put the proposed project at
risk. As written, the NOPR required the resource report to include a
description of methods to reduce the effects on geological resources
and reduce the risks posed by the hazards.
Summary of Changes
DOE did not receive any comments on the Geological Resources
resource report that have not been addressed in another section of this
final rule. However, DOE has made minor changes to the requirements and
description for the resource report between the NOPR and this final
rule.
The title of this resource report has been updated to ``Geological
Resources and Hazards'' to better reflect the scope of the report.
Additionally, in keeping with the discussion in section VI.K.ii of this
document, DOE is clarifying that the project proponent only needs to
describe geological resources and hazards ``in the applicable analysis
area.'' The proposed rule did not provide a definite boundary for these
identifications.
vii. Soil Resources Resource Report
DOE's Proposal
The NOPR proposed requiring project proponents to submit a resource
report on soil resources that might be affected by the proposed
project, the effect on those soils, and measures proposed to avoid,
minimize, or mitigate impact.
Summary of Changes
DOE did not receive any comments on the Soil Resources resource
report that have not been addressed in another
[[Page 35349]]
section of this final rule. However, DOE has made one substantive
change to the requirements for the resource report between the NOPR and
this final rule.
The NOPR proposed that a project proponent would need to list and
describe soil series for any ``site larger than five acres.'' However,
because almost all projects in the CITAP Program would cover more than
five acres, this distinction would not set an effective boundary on the
area of the requirement. Therefore, this final rule requires
identification and description of soil series within ``the applicable
analysis area'' to allow DOE, the project proponent, and relevant
Federal and non-Federal entities to determine the scope of the analysis
needed.
viii. Land Use, Recreation, and Aesthetics Resource Report
DOE's Proposal
DOE proposed to require the submission of a resource report on land
use, recreation, and aesthetics. DOE also proposed to require in this
resource report a description of the existing uses of land on, and
within various distances, the proposed project and changes to those
land uses and impacts to inhabitants and users that would occur if the
project were approved. The NOPR also required the report to describe
proposed mitigation measures, including protection and enhancement of
existing land use.
DOE sought comment on whether further revisions were needed to
proposed Sec. 900.6(m)(8), which proposed that the project proponent
identify, by milepost and length of crossing, the area of direct effect
of each proposed facility and operational site on lands owned or
controlled by Federal or State agencies with special designations not
otherwise mentioned in other resource reports, as well as lands
controlled by private preservation groups (examples include sugar maple
stands, orchards and nurseries, landfills, hazardous waste sites,
nature preserves, game management areas, remnant prairie, old-growth
forest, national or State forests, parks, designated natural,
recreational or scenic areas, registered natural landmarks, or areas
managed by Federal entities under existing land use plans as Visual
Resource Management Class I or Class II areas), and identify if any of
those areas are located within 0.25 mile of any proposed facility.
Summary of Public Comments
DOE received several comments on required elements of the Land Use,
Recreation, and Aesthetics Resource Report. LTA expressed support for
the inclusion of this resource report and commented specifically in
support of retaining multiple provisions of this report.
DOE received responses on whether revisions were needed to
paragraph (m)(8) from LTA and CEC/CPUC. The CEC/CPUC advised DOE to
divide Sec. 900.6(m)(8) into two sections: one about conservation
lands and another about lands with protective covenants due to distinct
management practices. LTA recommended adding ``conservation or
agricultural lands subject to state statutorily enabled conservation or
agricultural easements or restrictions'' to the list of examples. CEC/
CPUC recommended DOE include lands conserved and held by local focus on
land use restrictions, and include more specific provisions that
agricultural conservation lands described should only include those
with formal designations.
LTA recommended requiring the project proponent to describe ``an
area a Community of Interest has identified as having one or more
resources likely to be impacted by a proposed project'' in addition to
the specifically listed areas under the list of Federal designations in
paragraph (10). LTA also recommended adding to the specifically listed
areas ``National Forests and Grasslands'' and ``lands in easement
programs managed by the Natural Resource Conservation Service or the
U.S. Forest Service'' to this paragraph.
LTA recommended DOE revise its request for a detailed operations
and maintenance plan for vegetation management to include, ``that
utilizes native species to the maximum extent practical.''
ACP stated that the requirement that proponents identify all
residences and buildings within 200 feet of the edge of the proposed
transmission line construction right-of-way was ``excessively onerous''
and impractical. ACP suggested that the transmission right-of-way is a
more appropriate boundary than the construction right-of-way.
AZGFD recommended that this resource report identify potential
impacts to access for State wildlife agencies to carry out their
responsibilities, outdoor recreation, and recreational access. AZGFD
urged DOE to coordinate with State wildlife agencies to ensure actions
do not prevent State agencies from conducting their responsibilities.
DOE Response and Summary of Other Changes
DOE retains the scope and purpose of the Land Use, Recreation, and
Aesthetics Resource Report with minor revisions in response to these
comments.
In response to the comments on revisions to paragraph (8), which
includes a list of example specially designated areas, DOE has made
overall changes to the structure and language of the paragraph to
improve the clarity and readability of the requested information, to
reduce emphasis on the specific types of land ownership or use, and to
clarify that the resource report provides details regarding lands with
explicit status through Federal, state, or local formal designation, as
well as lands owned or controlled by Federal, State or local agencies
or private preservation groups. DOE has also added that the proposed
list is not exhaustive of the types of lands that should be identified
in this section, but rather identifies examples of the types of lands
that may meet the criteria now more clearly listed. DOE disagrees with
CEC/CPUC that this resource report should only include lands with a
formal agricultural conservation designations because the intent of
this provision and its list of examples is to capture lands with
special status not typically contemplated by Federal or State law but
agrees with LTA that ``conservation or agricultural lands subject to
State statutorily enabled conservation or agricultural easements or
restrictions'' is a helpful additional example and includes this in
this final rule.
In response to comments on the list of Federal statutory
designations in paragraph (10), DOE makes minor revisions to include
forests and grasslands. DOE agrees that specifically listed areas
should include Forest and Grasslands and lands in easement programs
managed by the Natural Resource Conservation Service or the U.S. Forest
Service and includes those in this final rule. DOE does not include
areas identified by communities of interest because the intent of this
resource report requirement is to identify areas that fall under
specific Federal statutes and regulations to assist DOE in implementing
its environmental review and coordination authority. In response to
LTA's request that the vegetation management provision include a
prioritization of the use of native species, DOE makes no revisions in
this final rule because DOE believes specific prescriptions for project
management practices should be addressed on a project-specific basis.
In response to ACP's comment on the appropriate area for building
identification DOE revises the proposed distance-based requirement but
maintains construction right-of-way
[[Page 35350]]
because the effects of construction on buildings is information that
DOE believes is necessary to inform DOE's environmental review.
In response to AZGFD's request that this final rule consider
impacts to State wildlife agencies, DOE makes no revisions because the
agency believes that the text is sufficiently clear on the need for
project proponents to provide such information in the resource report.
Further, DOE believes that the coordination with non-Federal entities
in the IIP Process sufficiently addresses the concern of coordination
with State wildlife agencies and makes no further revisions.
DOE is also making several changes to the proposed rule text that
are not in response to a specific comment. DOE significantly
reorganizes portions of the resource report requirements for clarity
but does not make any substantive changes through the reorganization.
In keeping with the discussion in section VI.K.ii of this document,
DOE is replacing multiple distances included in the proposed rule with
``in the applicable analysis area'' to give DOE, the project proponent,
and appropriate Federal and non-Federal entities flexibility to set
these distances based on the physical characteristics and needs of the
project. A project proponent must now identify certain planned
development within ``the applicable analysis area'' rather than within
``0.25 mile of proposed facilities.'' Likewise, the requirement for a
project proponent to identify directly affected areas that are owned or
controlled by a governmental entity or private preservation group
within ``0.25 miles of any proposed facility'' has been changed to
within ``applicable analysis areas.'' The final rule also requires the
project proponent to identify resources within ``the applicable
analysis area'' that are included in or designated for study for
inclusion in certain Federal land and water management statutes. The
proposed rule asked for the project proponent to identify the same
types of resources ``crossed by or within 0.25 mile of the proposed
transmission project facilities.''
ix. Communities of Interest Resource Report
DOE's Proposal
DOE proposed to require the submission of a resource report on
communities of interest. DOE proposed to require in this resource
report a summary of known information about the presence of communities
of interest that could be affected by the qualifying project;
identification and description of the potential impacts of
constructing, operating, and maintaining the project on communities of
interest; a description of any proposed measures intended to avoid,
minimize, or mitigate such impacts or community concerns; and a
discussion of any disproportionate and/or adverse human health or
environmental impacts to communities of interest.
Summary of Public Comments
DOE received three comments on the Communities of Interest Resource
Report that are not already addressed in the discussion regarding the
definition of communities of interest in section VI.K.iii of this
document.
LTA expressed support for retaining this resource report. ClearPath
opposed the addition of this resource report because ``by proposing
separate requirements for Communities of Interest in Project
Participation plans and outreach plans, the DOE is conceding that
stakeholder engagement requirements are deficient.'' ClearPath claims
that the proposal represents duplicative requirements and paperwork for
project proponents and establishes a hierarchy of treatment and
consideration of project impacts across population segments that could
have concerns regarding equal treatment and discrimination.
Regarding the requirement that the project proponent ``[s]ummarize
known information about the presence of communities of interest that
could be affected by the qualifying project,'' EDF noted that the
phrase ``known information'' may present a loophole, and instead the
project proponent should be required to investigate, observe, and
understand the concerns of communities of interest. EDF also indicated
that regulations should specify that there is a responsibility to
avoid, minimize, or mitigate any health or environmental impacts
identified.
DOE Response
DOE retains the Communities of Interest resource report with minor
revisions in response to these comments. DOE does not agree that this
resource report is duplicative with the public engagement plan and
clarifies that this resource report is aimed at identifying negative
impacts to communities of interest and mitigation measures while the
public participation plan is aimed at ensuring sufficient engagement.
ClearPath's concerns about the disparate treatment in the public
engagement plan are discussed in further detail in section VI.E of this
document.
DOE agrees with EDF that ``known'' is not consistent with the
intent of the information request and revises this final rule to
require ``best available information on'' rather than EDF's proposed
cure because this is consistent with the standard of information
gathering for environmental reviews.
x. Air Quality and Noise Effects Resource Report
DOE's Proposal
DOE proposed to require the submission of a resource report on air
quality and noise effects. DOE proposed to require in this resource
report the identification of the effects of the project on the existing
air quality and noise environment and describe proposed measures to
mitigate the effects.
Summary of Public Comments
DOE received three comments in response to the Air Quality and
Noise Effects resource report proposal.
Policy Integrity stated that the NOPR is unclear regarding local
air pollutants and non-power-sector emissions and advised DOE to
require project proponents to comprehensively estimate the associated
changes to GHG emissions and local air pollution from their
transmission project and alternatives, such as indirect upstream GHG
emissions from methane leakage. Additionally, the commenter suggested
that the need to estimate and describe impacts from changes to criteria
pollutants should not depend on whether they remain below the Clean Air
Act's National Ambient Air Quality Standards (NAAQS), stating that the
EPA has recognized that there is no safe level of exposure. In
contrast, ClearPath strongly opposed Air Quality and Noise Effects
resource report's proposed requirement that project proponents estimate
direct, indirect, and ``reasonably foreseeable'' generation resource-
related project emissions. ClearPath described the proposed
requirements as vague and as lacking a robust process for proponents to
follow, such that proponents are unlikely to understand and comply.
AZGFD recommended that DOE require the identification of air and
noise related potential impacts on all wildlife resources, in addition
to the Federally-listed species or sensitive wildlife habitats
currently identified.
DOE Response and Summary of Other Changes
DOE retains the Air Quality and Noise Effects resource report in
full in this final rule with no changes in response to these comments.
[[Page 35351]]
Regarding local air pollutants and emissions, DOE makes no changes
in response to the comment. DOE believes the rule makes clear that it
requires information regarding non-GHG emissions and non-power-sector
emissions. In this resource report, project proponents must identify
reasonably foreseeable emissions caused by the project, regardless of
whether those emissions occur in NAAQS non-attainment areas. DOE
believes that requirement provides adequate guidance to project
proponents.
Regarding the impacts on wildlife resources, DOE believes the
impacts to wildlife are sufficiently addressed in the Fish, Wildlife,
and Vegetation resources report and makes no revisions to this report.
DOE is making several changes to the proposed rule text that are
not in response to a specific comment. DOE significantly reorganizes
portions of the resource report requirements for clarity but does not
make any substantive changes through the reorganization.
In keeping with the discussion in section VI.K.ii of this document,
DOE is replacing multiple areas of study included in the proposed rule
with ``in the applicable analysis area'' to give DOE, the project
proponent, and appropriate Federal and non-Federal entities flexibility
to set these distances based on the physical characteristics and needs
of the project. A project proponent is now required to describe
existing air quality in ``the applicable analysis area'' rather than in
the ``project area.'' Likewise, a project proponent is required to
identify air quality impacts on communities and the environment in the
``applicable analysis area,'' rather than the ``project area.''
Finally, the proposed rule clarifies that a project proponent is
required to describe existing noise levels at noise-sensitive areas in
the ``applicable analysis area,'' instead of leaving the study area
undefined.
xi. Alternatives Resource Report
DOE's Proposal
DOE proposed to require the submission of a resource report on
alternatives. DOE proposed to require this resource report to include a
description of alternatives identified by the project proponent during
its initial analysis, which may inform the relevant Federal entities'
subsequent analysis of alternatives, address alternative routes and
alternative design methods, and compare the potential environmental
impacts and potential impacts to cultural and historic resources of
such alternatives to those of the proposed project. DOE also proposed
that the project proponent include all of the alternatives identified
by the project proponent, including those the proponent chose not to
examine or not examine in greater detail, and an explanation for the
project proponent's choices regarding the identification and
examination of alternatives. The NOPR proposed to require that project
proponents demonstrate whether and how environmental benefits and costs
were weighed against economic benefits and costs to the public, and
technological and procedural constraints in developing the
alternatives, as well as explain the costs to construct, operate, and
maintain each alternative, the potential for each alternative to meet
project deadlines, and the potential environmental impacts of each
alternative.
Summary of Public Comments
DOE received three comments addressing the Alternatives Resource
Report that are not already addressed in other sections.
Niskanen Center noted that the alternatives report would benefit
from clarifying language and revisions to avoid ambiguity regarding the
definition of alternatives and the extent to which they should be
included in the resource report and provided recommendations. Niskanen
Center also requested clarifying language if the Alternatives resource
report is the only report that is required to include an alternatives
analysis, and that if not, DOE should clearly state its request for
such analysis in each report.
ACP expressed concerns regarding the NOPR not reflecting the
intersections between state, Tribal, and Federal siting authorities,
specifically noting the overlapping timetables that can be difficult to
predict. ACP provided as an example that if State siting precedes
Federal siting, only a single route might be approved which would
materially limit the required NEPA alternative and potentially increase
overall legal risk if opponents claim that the failure to adequately
consider proposed alternatives violates NEPA or the Administrative
Procedure Act. ACP recommended that DOE explicitly address these
limited alternatives that may be established through a State siting
process, as well as ensure that Federal reviews account for the
potential scope of State siting determinations and not require
consideration of alternatives that are impossible or implausible.
The CARE Coalition urged DOE to specifically require the
consideration of alternative transmission technologies (ATTs), such as
dynamic line ratings, power flow controllers, advanced conductors, and
battery storage, in the report. The commenter explained that failure to
consider ATTs excludes a potentially low-cost alternative that may
prevent or reduce environmental harm.
DOE Response
DOE maintains the Alternatives resource report but makes
substantial revisions in response to these comments to reduce ambiguity
on the scope and purpose.
In response to Niskanen Center's comment, DOE confirms that this
resource report is the only resource report that requires an
alternatives analysis. Other resource reports are intended to address
the potential study corridors or routes along which the project
proponent is considering siting the electric transmission facility.
Those resource reports do not need to address alternative study
corridors or alternative routes that the project proponent has
eliminated from consideration.
The Alternatives resource report is intended to provide an overview
of the study corridors and routes that were initially considered for
the proposed project, but that ultimately were not chosen for further
study by the project proponent. In keeping with this intent, in this
final rule, DOE is requiring a project proponent to identify all study
corridors that were considered as part of the proposed project, as well
as all routes contained within those study corridors. Within that broad
group of study corridors and routes, DOE requires the project proponent
to identify those alternative study corridors and routes that the
project proponent eliminated from further study under an initial
screening, and the reasons why those corridors and routes were
eliminated.
For the remaining alternative study corridors and routes, DOE
requires analyses of certain impacts of siting the electric facility in
the corridor or along the route. Likewise, DOE requires a discussion of
the costs, timelines, and technological and procedural constraints of
siting the electric facility in the corridor or along the route.
Finally, DOE requires the project proponent to demonstrate whether and
how environmental benefits and costs were weighed against economic
benefits and costs to the public for the route or corridor.
In response to ACP's concern about overlapping timetables and
limitations to alternatives, DOE makes no additional revisions because,
as clarified above, the Alternatives resource report addresses the
project proponent's
[[Page 35352]]
approach to Alternatives which may inform, but does not supplant, DOE's
consideration of appropriate alternatives for its environmental review.
In response to CARE Coalition's request that DOE include ATTs, DOE
declines to specify the consideration of specific evolving technologies
in its regulatory test.
xii. Reliability, Resilience, and Safety Resource Report
DOE's Proposal
DOE proposed to require the submission of a resource report on
potential hazards to the public from failures of the proposed electric
transmission facility due to accidents, intentional destructive acts,
and natural catastrophes. DOE also proposed requiring the report to
describe how these events would affect reliability, benefits to
reliability from the project, and what procedures and design features
could be used to reduce risks to the facility and the public.
Summary of Changes
DOE did not receive any comments on the Reliability, Resilience,
and Safety resource report that have not been addressed in another
section of this final rule. However, in this final rule DOE
significantly reorganizes portions of the proposed resource report
requirements for clarity but does not make any substantive changes
through the reorganization.
xiii. Tribal Interests Resource Report
DOE's Proposal
DOE proposed to require the submission of a resource report on
Tribal interests. DOE proposed to require in this resource report the
identification of the Indian Tribes, indigenous communities, and their
respective interests that may be affected by the proposed transmission
facilities, including those Indian Tribes and indigenous communities
that may attach religious and cultural significance to historic
properties within the right-of-way or in the project area as well as
any underlying Federal land management agencies. DOE also proposed to
require in this resource report a discussion of potential impacts on
Indian Tribes and Tribal interests and of traditional cultural and
religious resources that could be affected by the proposed project, to
the extent Indian Tribes are willing to share this information.
Additionally, DOE proposed that certain specific site or location
information that may create a risk of harm, theft, or destruction, or
otherwise violate Federal law should be submitted separately, and that
the project proponent must request confidential treatment for all
material filed with DOE containing location, character, and ownership
information about Tribal resources.
Summary of Public Comments
DOE received four comments regarding the Tribal Interests Resource
Report that are not already addressed in previous discussions. Most
comments are addressed in section VI.J of this document in response to
the approach to compliance with section 106 of the NHPA.
LTA expressed support for this resource report and urged DOE to
collaborate with Indian Tribes to ensure that the language used in the
report adequately protects their interests. The Santa Rosa Rancheria
Tachi Yokut Tribe and NATHPO expressed concern with a comment by DOE
staff, which the commenters believe indicated, contrary to the proposed
rule text, that the Tribal Interests resource report would not contain
cultural resources, examples of Tribal resources provided in the
proposed rule (e.g., water rights, access to property, wildlife and
ecological resources) are Tribal cultural resources. The commenters
stated that this comment reflects a fundamental lack of understanding
about what is a Tribal cultural resource. Relatedly, the NM SHPO noted
that resources identified in other resource reports, such as the Water
Use and Quality resource report and the Fish, Wildlife, and Vegetation
resource report, may also be of traditional and cultural significance
and eligible for the NRHP.
DOE Response
In this final rule DOE retains the Tribal Interests resource report
with minor revisions for clarity in response to comments. First, DOE
did not intend to indicate that the Tribal Interests resource report
would not contain cultural resources. Second, DOE sought comment from
Indian Tribes and will coordinate with Indian Tribes in accordance with
the Federal Government's nation-to-nation responsibilities, pursuant to
DOE's authority under FPA 216(h).
In response to the concern raised by Santa Rosa Rancheria Tachi
Yokut Tribe and NATHPO that the resource report requirements reflect a
misunderstanding about tribal cultural resources, DOE revises the
report for clarity. DOE acknowledges that the Tribal Interests and
Cultural Resources resource reports may contain some resources that
overlap in part but clarifies that they are intended to support
different purposes and request different details. DOE expects that
certain cultural resources may be described in both resource reports
and revises the Cultural Resources resource report to clarify that
cultural and historic resources include, among other things, properties
of religious and cultural significance to Indian Tribes.
M. Administrative Docket
DOE's Proposal
To better coordinate Federal authorizations, DOE proposed to
maintain a consolidated administrative docket containing meeting
requests, meeting summaries, resource reports, other information
assembled during the IIP Process, and all information assembled by
relevant Federal entities for authorizations and reviews after
completion of the IIP Process.
Summary of Public Comments
Commenters, such as EEI, PJM, and the CARE Coalition, expressed
support for a consolidated administrative docket. PJM believes that a
consolidated administrative docket will ensure all Federal entities are
working from a single, complete record for reviews and decisions. One
commenter, Niskanen Center, proposed that the administrative docket be
public, while the CARE Coalition proposed the rule provide more details
to clarify access to the administrative docket to ensure stakeholder
participation. Another commenter, StopPATH WV, proposed DOE make the
administrative docket information available to landowners that may be
impacted by the proposed project.
DOE Response
DOE maintains the features and purpose of the administrative docket
in this final rule with minor revisions. DOE agrees that the public
should have access to the administrative docket for the proposed
project and revises this final rule to provide that ``Upon request, any
member of the public may be provided materials included in the docket,
excluding any materials protected as CEII or as confidential under
other processes (e.g., confidential business information and
information developed during consultation with Tribes).''
N. Interaction With FPA 216(a) and FPA 216(b)
Summary of Public Comments
Seven commenters provided comments on the interaction of the
proposed rule with DOE's process for designating NIETCs, per FPA
section
[[Page 35353]]
216(a), and FERC's pending regulations regarding its siting authority
in NIETCs, per FPA section 216(b), referred to by some commenters as
``backstop siting.''
PIOs praised DOE's proposed rule for its alignment with FERC's
proposed backstop permitting rule. PIOs anticipated that this
coordination would support a consistent, predictable, and rigorous
Federal review and permitting process and offer certainty to project
proponents, as they seek necessary authorizations. Additionally, PIOs
anticipated that alignment would ensure project proponents could easily
engage in both processes if necessary, citing potential scenarios in
which a project seeking a FERC permit needs multiple Federal
authorizations and could benefit from the IIP Process or a project
undergoing the IIP Process decides it needs a FERC permit. PIOs argued
that in these cases, alignment across processes would allow project
proponents to effectively engage in both processes, while reducing
duplication. PIOs identified several similarities between proposed
requirements under DOE's CITAP Program and FERC's proposed rule. PIOs
stated that DOE's proposed IIP Process plays a similar role to FERC's
pre-filing process. Additionally, PIOs noted that DOE's resource
reports are similar to those required under FERC's rule and recommended
that DOE align the numbering of resource reports with the numbering in
FERC's proposed rule.
Several commenters supported alignment of the CITAP Program's
requirements with FPA sections 216(a) and 216(b) regulations. ACEG,
CEBA and the CARE Coalition urged DOE to align the CITAP Program with
NIETC designation and FERC's backstop siting authority. CEBA suggested
this would avoid duplication and ensure processes are clear and remain
streamlined across relevant Federal agencies. ACEG stated it would
ensure effective and efficient implementation; the CARE Coalition
argued that this coordination would provide certainty and transparency
for stakeholders, predictability for project proponents, and a
reduction in associated project permitting costs. LADWP recommended
that DOE align the information required by the resource reports during
the IIP Process with the information required by the resource reports
under FERC's proposed backstop permitting rule. LADWP suggested that
alignment of this information would result in a more efficient
permitting process. Similarly, ACORE recommended that DOE provide a
mechanism for any information submitted under the NIETC program to be
incorporated into the IIP Process.
ACP commented that since proposed electric transmission projects
seeking Federal ``backstop'' siting authority under section 216(b) of
the FPA would not be eligible for the CITAP Program, DOE should ensure,
in conjunction with FERC, that any subsequent NEPA rulemakings will
allow for each agency to use an EIS prepared by the other agency as
this would help to minimize the potential for duplicative reviews.
Similarly, EDF recommended that in the event a transmission facility
requires a construction or modification permit from FERC pursuant to
section 216(b) of the FPA, DOE should conduct a single coordinated
environmental review with FERC. EDF explained that the benefits of such
a coordinated review have already been recognized by DOE in its
``Building a Better Grid Initiative to Upgrade and Expand the Nation's
Electric Transmission Grid To Support Resilience, Reliability, and
Decarbonization'' NOI, wherein DOE states that ``DOE and FERC intend to
work together, as appropriate, to establish coordinated procedures that
facilitate efficient information gathering related to the scope of
activities under review pursuant to these authorities.'' EDF believes
that by coordinating, to the greatest extent practicable, pre-filing
and application processes, DOE and FERC can work with project
proponents to identify and resolve issues as quickly as possible, share
information in a timely fashion, and expedite reviews conducted
pursuant to these authorities, NEPA, and other requirements. ACEG added
that to avoid fragmentation in the review process, and to comply with
section 216(h) of the FPA, DOE must prepare a single document for the
project's NEPA review, which will serve as the basis for decision-
making under both NIETC and CITAP.
Two comments requested more information. ACEG and CEBA requested
clarification on how a project proponent can initiate the CITAP Program
while seeking project-specific NIETC designation and how a CITAP
Program project can apply for backstop siting. ACEG explained that a
project in a NIETC could need to transition to backstop siting years
into the CITAP Program review process, and CEC/CPUC similarly requested
clarification on what will happen to a CITAP Program application once a
project becomes eligible for backstop siting. CEBA offered its
interpretation of the NOPR, understanding that projects could
participate in the section 216(h) process if the project has not
triggered or received section 216(b) FERC backstop authority. ACEG
explained that project proponents are likely to seek NIETC designation
to unlock funding opportunities available to projects in designated
corridors. ACEG encouraged DOE to streamline the processes by allowing
project proponents to submit a single application to initiate both
processes.
Conrad Ko suggested the routes of any applicant for a transmission
line construction permit to be automatically designated as a NIETC and
for the entire United States should be designated a NIETC.
DOE Response
DOE makes no revisions to the rule in response to these comments,
except to renumber the resource reports to align with the numbering in
FERC's proposed rule. DOE intends to coordinate interagency efforts to
the greatest extent possible, pursuant to its authority under FPA
section 216(h). The responsibility for coordinating Federal
authorization under section 216(h) for projects seeking a permit under
FPA section 216(b) has been delegated to FERC, pursuant to Delegation
Order No. S1-DEL-FERC-2006. DOE's current approach to the environmental
analysis for designation of NIETCs under section 216(a) may be found in
the Guidance on Implementing Section 216(a) of the Federal Power Act to
Designate National Interest Electric Transmission Corridors issued in
December 2023.\13\
---------------------------------------------------------------------------
\13\ ``U.S. Department of Energy Grid Deployment Office Guidance
on Implementing Section 216(a) of the Federal Power Act to Designate
National Interest Electric Transmission Corridors.'' National
Interest Electric Transmission Corridor Designation Process, United
States Department of Energy, 19 Dec. 2023, www.energy.gov/sites/default/files/2023-12/2023-12-15GDONIETCFinalGuidanceDocument.pdf.
---------------------------------------------------------------------------
DOE does not find that any provisions in this rule would preclude
the use of an EIS prepared by another agency, including FERC, should
such a circumstance arise. DOE agrees with commenters that projects
within a NIETC may qualify for the CITAP Program; however, if a project
within a NIETC seeks a permit from FERC under FPA section 216(b), FPA
section 216(h) coordination will proceed consistent with Delegation
Order No. S1-DEL-FERC-2006. DOE has endeavored to align the
environmental review procedures for NIETC designation and the CITAP
Program to the greatest extent possible, and additionally align with
FERC's proposed procedures for implementing section 216(b), as observed
by PIOs, to minimize the chance that such transitions create
duplicative work or unnecessary delay. Deviations among the
regulations,
[[Page 35354]]
particularly the specific contents of the thirteen resource reports,
reflect the differences in authorizations and permits DOE expects to
coordinate and provide for in its single environmental review under FPA
section 216(h).
This final rule maintains the provision that the Director of the
Grid Deployment Office may waive requirements of the CITAP Program,
which provides flexibility for transitioning between processes without
requiring duplicative work. Nothing in this final rule precludes the
reuse or concurrent submission of resource reports or other project
materials for a proposed project in a NIETC, whether under
consideration for designation or already designated, seeking CITAP
Program participation. DOE declines to further specify the coordination
between NIETCs and the CITAP Program because it is outside the scope of
the rulemaking. DOE has sufficiently established the requirements and
restrictions on qualifying project designation and further details on
interactions with other DOE programs are implementation issues that
will be determined as needed. DOE may provide additional guidance
outside of this rule regarding the interactions of various DOE and FERC
authorities in section 216 of the FPA.
O. Miscellaneous
i. Presidential Appeal
Summary of Public Comments
DOE received comments regarding the presidential appeals process
and review. PIOs commented that the language in the proposed rule was
consistent with the FPA but requested clarification on the process to
inform project proponents and members of the public. PIOs requested
that DOE clarify how the appeal to the President might work, and
whether and how a project proponent might appeal the President's
decision. AEU explained that the FPA section 216(h) allows for an
appeal to the President of the United States which appears to be an
extreme step in a process that should be handled through a judicial or
administrative hearing. The association emphasized that transmission
developers should have the ability to appeal if the approval process is
not proceeding according to the schedule set by DOE through no fault of
their own and the proposed rule should either describe how an appeal to
the President would proceed or lay out a specific appeal process for a
project developer. AEU also expressed concerns regarding recourse if
the timeframe from NOI through issuance of the EIS is not met. AEP
similarly recommended enabling project proponents to petition the court
if Federal agencies fail to comply with applicable deadlines.
DOE Response
Section 216(h) of the FPA authorizes the President to hear and
consider appeals under that section. The 2023 MOU describes the
procedures for Presidential appeals. The Presidential appeals provision
of section 216 of the FPA and the procedures described in the MOU,
including any process by which such a decision may be appealed, are
outside the scope of DOE's authority and thus outside the scope of this
rulemaking.
In response to AEP's request that DOE enable project proponents to
petition a court if Federal agencies fail to comply with applicable
deadlines, DOE notes that it does not, through this rule, have the
authority to authorize, or prohibit, project proponents from filing
court petitions regarding of Federal agency adherence to applicable
deadlines.
ii. Rehearing and Judicial Review
Summary of Public Comments
PIOs urged DOE to explain the implications of section 313 of the
FPA, including (1) the FPA's judicial review provision, in which
challenges are first brought to the agency, and then litigated in a
court of appeals under shorter timelines than most Federal agency
decisions, which are subject to review in district courts within six
years, and (2) the exhaustion requirements of the FPA, under which
courts only recognize claims raised in a rehearing application. PIOs
also asked DOE to explain whether the FPA's judicial review provisions
require a potential challenger to intervene before DOE, to raise any
substantive concerns during the DOE process even if DOE lacks
substantive expertise with the challenger's concerns, to seek rehearing
within thirty days, and to seek judicial review in a court of appeals
within sixty days of a rehearing decision. PIOs also recommended that
DOE (1) encourage parties, in both pre- and post-application outreach,
to provide comment on transmission applications, (2) provide language
for doing so, and (3) grant party status to any party that submits a
timely comment.
DOE Response
Section 313 of the FPA contains rehearing and judicial review
provisions applicable to orders issued by DOE under the FPA, including
any order issued under section 216(h). 16 U.S.C. 825l.\14\ Section
313(a) provides that any person aggrieved by an order must first apply
for rehearing within 30 days of the issuance of such order. Upon
receiving the application, section 313 authorizes DOE to grant or deny
rehearing or to abrogate or modify its order without a further hearing.
DOE has 30 days to act upon the application for rehearing or the
application is deemed to have been denied. Under section 313(b), a
party may then proceed to seek judicial review in the courts of
appeals, by filing a petition for review in such a court within 60 days
of the order on the application for rehearing.
---------------------------------------------------------------------------
\14\ Section 313 refers to ``an order issued by the [Federal
Power] Commission.'' 16 U.S.C. 825l(a)-(b). In 1977, Congress
dissolved the Federal Power Commission and transferred its
authorities to DOE and FERC. See Department of Energy Organization
Act, Public Law 95-91, 91 Stat. 565 (Aug. 4, 1977). The rehearing
and judicial review provisions of section 313 apply to DOE as a
successor to the Federal Power Commission. See Ctr. for Biological
Diversity v. Dep't of Energy, No. CV 08-168AHM(MANX), 2008 WL
4602721, at *5-6 (C.D. Cal. Oct. 16, 2008); Pa. Pub. Util. Comm'n v.
Bodman, No. CIV. 1:CV-07-2002, 2008 WL 3925840, at *3-5 (M.D. Pa.
Aug. 21, 2008).
---------------------------------------------------------------------------
Thus, any party that wishes to ensure the availability of judicial
review of any relevant authorization or related environmental review
document issued under section 216(h) should raise in rehearing before
DOE all challenges to such authorization or document, including those
actions undertaken by DOE in its role as the lead agency for purposes
of environmental review. Subject to any further process, DOE intends to
treat as a party any person or entity that comments on any relevant
authorization or related environmental review document. Because these
topics relate to procedures outside the scope of this rule and may
depend on specific factual circumstances, DOE declines at this time to
establish model language regarding rehearing and review. Nevertheless,
DOE supports interested parties making comments on transmission
applications in the CITAP Program, including pursuant to NEPA and other
review processes that afford opportunities for comment and
participation. Because of the various avenues for comment and
participation and because the CITAP Program does not limit the public
comments that can be made through the existing avenues for public
input, DOE finds it is unnecessary to provide standardized language for
providing comments as suggested by commenters.
iii. Role of States
Summary of Public Comments
DOE received two comments related to the roles of states in siting
[[Page 35355]]
transmission lines. AEP emphasized the importance of respecting the
roles and responsibilities of states and localities in transmission
project approval. CEC/CPUC encouraged the coordination of Federal and
State permitting processes, explaining that most major transmission
facilities in California will require both Federal and State
environmental review and approval. To align these processes and inform
coordination, CEC/CPUC recommended that DOE support project-specific
MOUs between State and Federal permitting authorities.
DOE Response
DOE agrees with the commenters on the importance of states in the
siting of transmission lines. Accordingly, and consistent with section
216(h), the IIP Process is designed to encourage and facilitate states'
participation. Moreover, nothing in the IIP Process supersedes any
State siting or permitting authority. DOE may develop project-specific
MOUs as appropriate and necessary; such individual decisions are
outside the scope of this rulemaking.
iv. Effective Date
Summary of Public Comments
Idaho Power requested clarification on when the CITAP Program
outlined in the proposed rule would go into effect.
DOE Response
DOE intends for the CITAP Program to take effect on the day this
final rule takes effect: 30 days after publication of the rule in the
Federal Register.
v. Costs and Benefits of Conservation
Summary of Public Comment
AZGFD requested additional information about DOE's assessment of
potential costs and benefits of the CITAP program. AZGFD stated that it
was unclear whether DOE has assessed and evaluated the costs associated
with implementation of conservation measures for offsetting potential
impacts to resources. If DOE did not include this analysis, AZGFD
recommends that DOE account for the cost of conservation measures.
DOE Response
DOE makes no changes in this final rule in response to this
comment. DOE believes that the CITAP Program, as finalized in this
rulemaking, is designed to enhance coordination of decision-making
efforts for the purposes of improved speed and efficiency of Federal
permitting and authorizations overall, but will not materially impact
the outcomes of specific decisions, which would include any
conservation measures required to be undertaken. DOE's assessment of
the final rule's anticipated costs and benefits is presented in section
VIII of this document.
vi. Burden Estimates Under the Paperwork Reduction Act of 1995
Summary of Public Comment
Gallatin Power expressed concern that the cost burden estimated in
the NOPR seemed ``significantly lower than current market rates.''
Gallatin Power acknowledged that the median hourly rate was used to
calculate the cost burden, but explained that, in its experience,
``these hourly wages are significantly more when contracting with a
subject matter expert, at an industry-accepted firm.'' Gallatin Power
also expressed concern that the cost and time estimates did not
identify a size for the transmission project given that ``these costs
and time estimates would vary greatly among project lengths and
locations.''
DOE Response
DOE makes no changes in this final rule in response to this
comment. Although Gallatin Power expressed concern about the burden
analysis, it did not challenge DOE's approach as unreasonable nor did
it provide an alternative approach for DOE to consider. As Gallatin
Power acknowledges, costs and time estimates can vary widely among
projects. Given that estimates can vary widely by project, DOE believes
it was reasonable to use the most recently available median hourly wage
for management analysts according to the Bureau of Labor Statistics,
for the proposed rulemaking and in this final rule, consistent with
DOE's previous burden analysis for this collection. Though this revised
collection changes the volution and subject matter of the information
collection, including requesting analysis from a range of experts, many
of the median wages reported by BLS for environmental and scientific
consultants are below the management analysis median wage proposed by
DOE, further supporting DOE's use of this occupation as a basis for
estimation. Regarding the size of transmission project, DOE estimated
an average burden for a qualifying project under CITAP, which
represents a wide range of length and size, based on the special
expertise in environmental evaluation of transmission projects within
DOE. DOE's assessment of the final rule's estimated burden is in
section VIII of this document.
P. Out of Scope Comments
Summary of Public Comments
DOE received six additional comments not addressed above. NAM noted
it supports a diverse approach to powering communities and operations,
and urged DOE to follow its findings in the draft National Transmission
Needs Study released in February 2023.
The State of Colorado Governor's Office stated that the proposed
rule does not consider the need to minimize the potential of the
challenges from private citizens and groups alleging deficiencies in
project review under NEPA and other statutes nor DOE's ability to
facilitate interstate transmission development in the face of
opposition from certain states or organizations.
EEI suggested DOE consider how its implementation of section 216(h)
can support electric companies working to meet State timelines for
reducing emissions in the electric grid through its implementation of
section 216(h) and for DOE and other agencies to consider IRA funds to
increase the training of personnel or to provide grants to other
agencies.
Kris Pastoriza requested clarification on a statement on FERC's
website, a definition for or list of ``interstate transmission lines.''
Gallatin Power asked DOE to clarify whether designated DOE staff
would be assigned to qualifying projects who could help move the
permitting process along and would facilitate knowledge retention.
EDF recommended DOE consider co-location of transmission projects
within abandoned rights-of-way. In addition, EDF recommended DOE
develop a record of right-of-way locations and to consider publishing
this information on an interactive map for ease of use by the public.
EDF believes the CITAP Program presents the perfect opportunity to
develop this information. EDF believes this proposal would be
consistent with the objective to ensure NEPA reviews are not
duplicative because the information about rights-of-way would be more
readily available for transmission projects.
DOE Response
DOE finds these comments to be out of scope of the rulemaking,
which addresses the implementation of DOE's authority to coordinate
Federal environmental review and decision-making on transmission
project authorizations and permits. The findings of the Needs Study are
outside the scope of this rulemaking, as are the potential of
challenges alleging deficiencies in NEPA review, as well as
[[Page 35356]]
any interpretations of FERC's authority. Regarding EEI's request that
DOE consider State emissions reductions statutes in its implementation
of section 216(h), DOE's authority is limited to coordination of
environmental reviews and decision-making; project proponents remain
responsible for meeting or complying with any State emissions
reductions statutes. Additionally, regarding Gallatin Power's request
that DOE clarify which DOE staff will be assigned to qualifying
projects, whether there will be certain designated staff assigned to
these projects will depend on the particular project and is best
addressed on a project-by-project basis. Regarding EDF's recommendation
for DOE to consider co-location within abandoned rights-of-way, project
proponents remain responsible for proposed routes, and they may
consider co-location as appropriate. Regarding EDF's recommendation for
DOE to use the CITAP Program as an opportunity to develop a database of
rights-of-way, DOE finds it unnecessary to adopt any regulatory text to
address this recommendation but may, through implementation of the
program, develop various tools to inform the public.
VII. Section-by-Section Analysis
Sec. 900.1 Purpose and Scope
Section 900.1 provides a process for the timely and coordinated
submission of information necessary for decision-making for Federal
authorizations for siting of proposed electric transmission facilities
pursuant to section 216(h) of FPA. This final rule revises Sec. 900.1
to update the purpose of part 900, reference the establishment of the
CITAP Program, and improve readability. These changes reflect DOE's
understanding that Congress intended DOE to make the process to obtain
multiple Federal authorizations more efficient and reduce
administrative delays, which requires clear authority, process, and
timelines. The changes in this section reflect DOE's intent to carry
out the full scope of the authority that Congress provided. Paragraph
(a) is added to establish the overarching CITAP Program and provide a
roadmap to authorities and processes throughout part 900. This
paragraph states that DOE will act as a lead agency for preparing an
environmental review document for any qualifying project. Paragraph
(a), as well as revised paragraph (d), identify DOE's role in
establishing and monitoring adherence to intermediate milestones and
final deadlines, as required by section 216(h).
This final rule revises the current regulatory text of Sec. 900.1
by dividing it into paragraphs (b) through (d). Portions of the text
dealing with the IIP Process have been updated to clarify that the
process will require submission of materials necessary for Federal
authorizations and that the IIP Process should be initiated prior to
the submission of any application for a Federal authorization. The
changes also clarify that the IIP Process is integrated into the CITAP
Program.
In this final rule, DOE is adding paragraph (e) to clarify the
intended relationship between the early coordination envisioned by the
IIP Process and the duties prescribed by section 106 of the NHPA and
the implementing regulations at 36 CFR part 800. In particular, this
section clarifies that nothing in the IIP Process is intended to
abrogate the obligations of Federal agencies under 36 CFR part 800.
Additionally, this section authorizes a project proponent as an
applicant to the CITAP Program to initiate section 106 consultation
during that proponent's involvement in the IIP Process.
DOE redesignates paragraphs (a) and (e) of current Sec. 900.2 as
new paragraphs (f) and (g) of this section because the paragraphs
contain general propositions regarding part 900 and are better suited
to the general ``Purpose and Scope'' section. This final rule adds a
new paragraph (f) to establish that DOE and the relevant Federal
entities shall issue a joint decision document except where
inappropriate or inefficient. This revision is to be consistent with
NEPA regulations, including the Fiscal Responsibility Act of 2023,
which codified processes to streamline the environmental review process
and facilitate one Federal decision, be consistent with the
Congressional intent of FPA 216(h), and enhance DOE's coordinating
function. This final rule revises new paragraph (g) to clarify that DOE
will serve as lead agency for consultation under section 7 of the ESA
and section 106 of the NHPA unless the relevant Federal entities
designate otherwise. This revision aligns the lead agency designation
with the authorizing statutes.
This final rule also adds paragraph (h) to afford the Director of
DOE's Grid Deployment Office, or that person's delegate, flexibility
necessary to ensure that part 900 does not result in unnecessary,
duplicative, or impracticable requirements. DOE added this paragraph to
authorize the Director to waive any such requirements. Further, this
paragraph specifically contemplates a scenario in which a Federal
entity is the principal project developer. Under such circumstances,
DOE has added language to indicate that the Director will consider
modifications to the requirements under this part as may be necessary
under the circumstances.
Sec. 900.2 Definitions
DOE redesignated Sec. 900.3 as Sec. 900.2 for the purpose of
providing the definitions of terms before those terms occur in the body
of the regulation. Section 900.2 provides definitions for various terms
used throughout part 900. This final rule amends or adds the following
definitions:
Revises the term ``affected landowner'' to ``potentially
affected landowner'' and revises the substance of that definition to
include any owner of a real property interest whose interest is
potentially affected by a project right-of-way, potential route, or
proposed ancillary or access site. Adds a definition of ``analysis
area'' to serve as a reference in locating the points in the IIP
Process that analysis areas are established and modified.
Adds a definition for ``authorization'' to provide clarity
in several places where that term occurs. Amends the definition for
``Federal authorization'' to account for the new definition of
``authorization.''
Adds a definition for ``communities of interest'' to
ensure broad coverage of potentially impacted populations during the
public engagement process and establishment of the public engagement
plan. Adds a definition for ``participating agencies'' to serve as
shorthand for the group of agencies that will serve various roles under
the amendments to the coordination of Federal authorizations.
Adds a definition of ``NEPA joint lead agency'' to
identify where information about the designation of a NEPA joint lead
agency occurs in the rule.
Removes the term ``OE-1,'' meaning the Assistant Secretary
for DOE's Office of Electricity Delivery and Energy Reliability, and
replaces it with the definition for ``Director,'' meaning the Director
of DOE's Grid Deployment Office or that person's delegate. Under
section 1.14(D) of Delegation Order No. S1-DEL-S3-2023 and section
1.9(D) of Redelegation Order No. S3-DEL-GD1-2023 the Secretary of
Energy delegated authority to exercise authority under section 216(h)
to the Grid Deployment Office. That authority had previously been
delegated to DOE's Office of Electricity Delivery and Energy
Reliability. The same substitution is made throughout part 900 to
reflect that delegation change.
[[Page 35357]]
Revises the reference to the definition of ``Indian
Tribe'' in the United States Code to the correct reference following
the 2016 editorial reclassification. This change does not amend the
definition. Adds the definitions for ``relevant Federal entity'' and
``relevant non-Federal entity'' using the substance of the definitions
from ``Federal entity'' and ``non-Federal entity,'' respectively. These
changes are intended to show that the terms only mean Federal or non-
Federal entities with some relation to a particular qualifying project.
These changes are updated throughout part 900.
Revises the definition for ``regional mitigation
approach'' to a more general term of ``mitigation approach.'' DOE
revised this term because regional-level approaches and strategies may
be too limiting for the needs at hand; instead, DOE wants to create the
opportunity for discussion of all types of proposed mitigation for a
given proposed project. In addition, DOE has revised the substance of
this definition to clarify the meaning and more closely align with
existing NEPA regulations regarding mitigation. Because the revisions
to mitigation approach rendered ``regional mitigation strategies or
plans'' redundant, DOE has removed that definition.
Revises the definition for ``MOU signatory agency'' to
mean any Federal entity that has entered into the currently effective
MOU under section 216(h)(7)(B)(i) of the FPA. This change decouples the
term from any particular MOU and keeps the rule current without
requiring changes to the regulatory text. The term references the 2023
MOU as an example.
Revises the definition for ``qualifying project'' in a
number of ways. First, the revised definition removes the qualifier
``non-marine'' before high voltage transmission line and electric
transmission line to match potential scope of the Program with that
agreed to in the MOU. Second, the revised definition includes several
factors for determining if a transmission line is regionally or
nationally significant. Third, the revised definition limits the term
to projects that are expected to require preparation of an EIS because
the Federal coordination will be most impactful for such projects due
to their complexity. Fourth, in accordance with the 2023 MOU, this
final rule revises the definition to state that the term does not
include any transmission facility authorized under section 8(p) of the
Outer Continental Shelf Lands Act (43 U.S.C. 1337(p)). The exception to
that restriction included in the 2023 MOU is provided for in the
changes to Sec. 900.3 and discussed further in that section. Fifth, in
accordance with the 2023 MOU, the term excludes a transmission facility
that are seeking a construction or modification permit from FERC
pursuant to section 216(b) of the FPA. Sixth, the revised definition
excludes projects located wholly within the Electric Reliability
Council of Texas interconnection, as required by section 216(k) (16
U.S.C. 824p(k)). This exclusion is also located in Sec. 900.2(c) of
the current rule, but it is not replicated it in this definition for
clarity. Seventh, the revision provides a mechanism under Sec. 900.3
by which a project that does not meet the definition of a qualifying
project under the first paragraph of the term may still participate in
the Program. This change is discussed in more detail in the following
section.
Revises the definition for ``project area'' to clarify the
scope of this term.
Removes the definitions of ``DOE'' and ``NEPA'' because
those terms are acronyms best addressed in the regulatory text rather
than as definitions.
Removes the definition of ``FPA'' because that term no
longer occurs in the regulatory text.
Removes the definitions for ``early identification of
project issues,'' ``IIP resources report,'' ``IIP process
administrative file,'' ``lead 216(h) agency,'' ``MOU principals,'' and
``other projects'' because those terms no longer occur in part 900.
Removes the definition for ``NEPA Lead Agency'' because
that term is self-explanatory in the context in which it occurs.
Revises the term ``stakeholder'' for clarity and
readability and includes ``organization'' in the definition to clarify
that stakeholders are not just individuals.
Revises the term ``study corridor'' to clarify that the
term does not coincide with ``permit area,'' ``area of potential
effect,'' ``action area,'' or other terms specific to certain types of
regulatory review.
Sec. 900.3 Applicability to Other Projects
Section 900.2 of the current rule, titled ``Applicability,''
provides an application process by which a project proponent may seek
DOE assistance under part 900 for an ``other project.'' This final rule
redesignates Sec. 900.2 as Sec. 900.3 and retains a mechanism by
which projects that do not otherwise qualify as ``qualifying projects''
may be treated.
Section 900.2(b) is revised and redesignated as Sec. 900.3(a)-(c)
to more clearly communicate the process by which a project proponent
may request that a facility be approved as a qualifying project. In
particular, this final rule removes the definition of the term ``other
project'' and instead includes the substance of that term in paragraph
(a) of the revised section.
Paragraphs (a) and (e) of current Sec. 900.2 are redesignated as
paragraphs Sec. 900.1(f) and (g), respectively, because those
paragraphs contain general propositions regarding part 900 and are
better suited to the general ``Purpose and Scope'' section. This final
rule removes the first sentence of current Sec. 900.2(e) as it is
unnecessary because part 900 does not purport to affect other Federal
law requirements except in specific, articulated instances.
Current paragraphs Sec. 900.2 (g) and (h) are relocated to Sec.
900.4 as paragraphs (e) and (f), respectively, because Sec. 900.4
provides a general background to the IIP Process, and the substance of
those paragraphs is more relevant to the IIP Process than the rest of
part 900. Current Sec. 900.2(d) is redesignated as paragraph (e) and a
new paragraph (d) is added. New paragraph (d) provides factors that the
Director of GDO may consider when determining if a proposed electric
transmission facility should be considered a qualifying project and
accepted into the CITAP Program.
Redesignated paragraph (e) is further amended. Whereas the current
version of that paragraph provides that the section does not apply to a
transmission facility that will require a construction or modification
permit from FERC, this final rule amends the paragraph to allow such
projects to take advantage of part 900, provided that the request to be
included in the CITAP Program is submitted by a person with relevant
authority under Delegation Order No. S1-DEL-FERC-2006 or any
subsequent, similar delegation.
In addition, this final rule removes paragraph (f), which describes
the IIP process as a complementary process that does not supplant
existing pre-application processes, because this final rule establishes
the IIP Process as the mandatory precondition for coordination under
section 216(h).
This final rule adds new paragraphs (f) and (g)(1) that allow a
project proposed to be authorized under Section 8(p) of the Outer
Continental Shelf Lands Act to receive coordination assistance under
part 900, provided that the project is not to be authorized in
connection to a generation project and that all 2023 MOU signatories
agree to the project's inclusion in the CITAP Program. These additions
reflect the terms of the 2023 MOU.
[[Page 35358]]
Finally, current paragraph (c) is moved to paragraph (g)(2) to
improve the readability of the section.
Sec. 900.4 Purpose and Scope of IIP Process
Section 900.4 of the current rule states the purpose and structure
of the IIP Process. This final rule divides this section into
Sec. Sec. 900.4, 900.5, 900.8, and 900.9 to improve readability.
Section 900.4(a) of the current rule remains in Sec. 900.4 but is
further divided into paragraphs (a), (b), and (c) to improve
readability.
Sections 900.4(j)(3)(i) through (iv) are redesignated as Sec.
900.4(a)(1) through (8) and amended to reflect a new purpose. Current
Sec. 900.4(j)(3) requires the Federal entities at the initial meeting
to identify reasonable criteria for adding, deleting, or modifying
preliminary routes within the study corridors and lists nine criteria
that should be included in the criteria that Federal entities identify.
In contrast, new Sec. 900.4(a) provides that those criteria should
instead be used by the project proponent when identifying potential
study corridors and potential routes. The change encourages the project
proponent to utilize the criteria in identifying routes and corridors
throughout the IIP Process, rather than just after the initial meeting.
This final rule retains the requirement for DOE and other agencies to
identify other criteria for adding or modifying potential routes and
includes that the agencies should also identify criteria for potential
study corridors as well.
Additionally, Sec. 900.4(b) establishes the IIP Process as a
prerequisite for coordination, consistent with the statutory language
and the revisions to the purpose of part 900 in Sec. 900.1. This final
rule adds a new paragraph (d) to clarify that the IIP Process does not
preclude additional communications between the project proponent and
relevant Federal entities outside of the meetings envisioned by the IIP
Process. The paragraph further emphasizes that DOE intends for the IIP
Process to be an iterative process and that each milestone in the
process is designed to improve upon the materials that Federal entities
have available for authorization and environmental review decisions.
This rule redesignates Sec. 900.2(g) and (h) as Sec. 900.4(e) and
(f), respectively, because Sec. 900.4 provides a general background to
the IIP Process, and the substance of those paragraphs is more relevant
to the IIP Process than the rest of part 900. Section Sec. 900.4 gives
new authority to the Director to request additional information from a
project proponent during the IIP Process to ensure that DOE can collect
the information needed to adequately complete the IIP Process.
Finally, this final rule adds new paragraphs (h) and (i), which
provide processes by which a person may submit confidential information
during the IIP Process or to request designation of information
containing Critical Electric Infrastructure Information (CEII). These
provisions establish the mechanisms through which the IIP Process
complies with 10 CFR 1004.11 and 1004.13.
Sec. 900.5 Initiation of IIP Process
Section 900.5 is composed of current Sec. 900.4(b), (c), (e), (g),
(h), (i), and (j). This final rule revises these provisions to
enumerate the documents and information required to initiate the IIP
Process, expedite that process, ensure that community impacts from the
project are identified early, and improve the overall readability and
clarity of the provisions.
Currently, an initiation request to begin the IIP Process must
include a summary of the qualifying project; a summary of affected
environmental resources and impacts, including associated maps,
geospatial information, and studies; and a summary of early
identification of project issues. This final rule revises the contents
of the request. First, this final rule updates the contents required in
the summary of the qualifying project in paragraph (b) to include
project proponent details; identification of any environmental and
engineering firms and subcontractors under contract to develop the
qualifying project; and a list of anticipated relevant Federal and non-
Federal entities to ensure sufficient information is provided for DOE
to review and to include all necessary agencies in the process. This
final rule also adds new requirements for additional maps as part of
the initiation request, as detailed in paragraph (c). DOE believes the
additional information in paragraphs (b) and (c) is necessary to
properly identify the relevant agencies for efficient coordination.
Additional requirements are added in this final rule to require
submission of a project participation plan as part of the initiation
request. This plan is in place of the summary of early identification
of project issues currently required under the current regulation. The
project participation plan, as detailed in paragraph (d), will include
the project proponent's history of engagement and a public engagement
plan for the project proponent's future engagement with communities of
interest and with Indian Tribes that would be affected by a proposed
qualifying project. The plan would include specific information on the
proponent's engagement with communities of interest and with Indian
Tribes that would be affected by a proposed qualifying project. An
updated public engagement plan would be required at the end of the IIP
Process to reflect any activities during that process. The addition of
a public engagement plan that includes communities of interest and
Indian Tribes that could be affected by a proposed qualifying project,
would ensure that the project proponent follows best practices around
outreach. Moreover, by including this plan in the IIP Process, the
regulation will provide relevant Federal entities an opportunity to
provide input into the project proponent's engagement efforts, and to
ensure that the project proponent engages with all communities of
interest and Indian Tribes that could be affected by the proposed
qualifying project. The engagement complements Tribal consultation and
public engagement undertaken by the relevant Federal entities and would
not substitute for Federal agencies engaging in Nation-to-Nation
consultation with Indian Tribes and public engagement with stakeholders
and communities of interest.
This final rule adds a new paragraph (e), to require submission of
a statement regarding the project's status under Title 41 of the Fixing
America's Surface Transportation Act (FAST-41) (42 U.S.C. 4370m et
seq.) as part of the initiation request. This statement is intended to
facilitate coordination between the IIP Process and the FAST-41
Process. This final rule adds requirements for project proponents to
indicate whether their proposed project currently is a FAST-41
``covered project.''
This final rule adds paragraph (f), which gives DOE 20 days from
the receipt of the initiation request to determine whether the
initiation request is sufficient and whether the proposed electric
transmission facility is a qualifying project. In that same timeframe,
paragraph (f) requires DOE to provide relevant Federal entities and
relevant non-Federal entities with a copy of the initiation request and
notify the project proponent and all relevant Federal entities and
relevant non-Federal entities whether the initiation request is
sufficient and whether the proposed facility is a qualifying project.
This final rule adds a new paragraph (g), to provide clarity to the
process that DOE and the project proponent must follow if DOE
determines that the initiation request is insufficient or that the
proposed facility is not a qualifying
[[Page 35359]]
project. Paragraph (g) dictates that DOE must give the project
proponent the rationales for the determinations. It also provides that
the project proponent may file a request for coordination with the
Director of the GDO as provided in Sec. 900.3, if DOE determines that
the proposed facility is not a qualifying project.
This final rule removes the requirement to submit an affected
environmental resources and impacts summary as part of the initiation
request. As discussed in more detail in the next section, that summary
is replaced by thirteen resource reports submitted after the IIP
Process initial meeting.
Section 900.5(j) is redesignated as Sec. 900.5(h), and the content
of that section is amended to reflect a new timeline for convening the
IIP Process initial meeting and updates to the discussions that must
occur at the meeting. The timeline for convening the initial meeting
has been reduced from within 45 days of providing notice to the project
proponent and the relevant Federal and non-Federal entities that it has
received an IIP Process initiation request to within 15 days of
providing notice under paragraph (f) that the initiation request meets
the requirements of the section.
Likewise, the contents of the initial meeting have been updated.
Section 900.5(h)(1) is added to require DOE and the relevant Federal
entities to discuss the IIP Process and requirements with the project
proponent, the different Federal authorization processes, and
arrangements for the project proponent to contribute funds to DOE to
cover costs in the IIP Process (in accordance with 42 U.S.C. 7278),
establishment of cost recovery agreements or procedures in accordance
with regulations of relevant Federal entities, where applicable, or the
use of third-party contractors under DOE's supervision, where
applicable. DOE believes an early discussion of the process and
requirements will ensure efficient participation of the parties and
early identification of potential issues.
This final rule adds Sec. 900.5(h)(2) to require DOE to identify
certain applications that need to be submitted to relevant Federal
entities during the IIP Process (for example, Standard Form 299, which
a project proponent would file to seek authorization for transmission
lines crossing Federal property). The timing of the expected Federal
applications, including which applications may be required during the
IIP Process and which should be submitted following the conclusion of
the IIP Process, will be covered in the initial meeting.
This final rule adds Sec. 900.5(h)(3) requiring DOE to establish
all analysis areas necessary for the completion of resource reports
required under Sec. 900.6. By requiring DOE to establish the analysis
areas at this early stage of the IIP Process, this final rule enables
and encourages the project proponent to begin assembling the resource
reports soon after the proposed project is accepted into the CITAP
Program.
As discussed in the previous section, Sec. 900.4(j)(3)(i) through
(iv) are redesignated as Sec. 900.4(a)(1) through (8) to encourages
the project proponent to utilize the criteria in those paragraphs when
in identifying potential routes and study corridors. Section
900.5(h)(5) retains the requirement in Sec. 900.4(j)(3) for DOE and
other agencies to identify other criteria for adding or modifying
potential routes but adds that the agencies should also identify
criteria for potential study corridors as well. Section 900.5(h)(5) is
further amended to include a requirement that DOE and the relevant
Federal entities discuss study corridors and potential routes
identified by the project proponent and the criteria used to identify
those corridors and routes.
This final rule revises the requirement that DOE produce a draft
initial meeting summary within 15 calendar days after the meeting to 10
calendar days, and the revises the time that participating Federal
entities and Non-Federal entities, and the project proponent will then
have to provide corrections to the draft summary from 15 calendar days
to 10 calendar days. Additionally, this final rule revises the
requirement that DOE produce a final initial meeting summary within 30
days of receiving corrections to the draft summary to 10 days. All
three changes are intended to expedite the IIP Process.
This final rule revises this section to add the requirement in
Sec. 900.6 that requires DOE to add the final initial meeting summary
to the consolidated administrative docket. Finally, this final rule
removes portions of paragraph (j)(3)(v) because the contents are
addressed elsewhere.
Sec. 900.6 Project Proponent Resource Reports
This final rule adds a new Sec. 900.6 to add requirements for
project proponents to develop, in collaboration with relevant Federal
entities, thirteen resource reports that will serve as inputs, as
appropriate, into the relevant Federal entities' own environmental
analysis and authorization processes. This pre-application material
will provide for earlier collection of critical information to inform
the future application process relating to the proposed transmission
line and facilities, including preliminary information to support DOE's
and the relevant Federal entities' compliance with section 106 of the
NHPA, the ESA, and NEPA. The thirteen resource reports are: General
project description; Water use and quality; Fish, wildlife, and
vegetation; Cultural resources; Socioeconomics; Geological resources
and hazards; Soil resources; Land use, recreation, and aesthetics;
Communities of interest; Air quality and noise effects; Alternatives;
Reliability, resilience, and safety; and Tribal interests. This final
rule renumbers the resource reports in response to a comment, as
discussed in section VI.L of this document.
This final rule adds requirements for project proponents to develop
these resource reports as part of the pre-application process instead
of the affected environmental resources and impacts summary document
required from project proponents under the existing rule at section
900.4(d). The resource reports identify information needed to complete
NEPA and other review and authorization requirements. However, the
topics identified and the reports do not limit the information relevant
Federal entities may need, require from project proponents, or develop
independently, as necessary to satisfy each relevant Federal entity's
applicable statutory and regulatory obligations. To address possible
differences in information required for onshore and offshore project
environments, the final rule allows the Director to modify the
requirements of resource reports to ensure that the reports adequately
cover their intended purpose. Each resource report will comprehensively
discuss the baseline conditions and anticipated impacts to resources
relevant to DOE's required environmental review, namely under NEPA,
ESA, and section 106 of the NHPA. NEPA requires Federal agencies to
analyze and assess potential environmental effects of the proposed
Federal agency action, and these effects can vary in significance and
complexity. DOE anticipates that these reports will inform its work to
meet its requirements under the various environmental laws referenced
above. In addition, proper assessment of the resources potentially
affected by the proposed action can also help DOE identify resource
conflicts, missing information, and needs from other agencies, and
inform the project-specific schedule. These conflicts and needs can
then be discussed and
[[Page 35360]]
addressed during the review meeting and throughout the IIP Process.
These resource reports will be developed by project proponents
during the IIP Process with input and feedback from the Federal and
non-Federal entities involved in authorization decisions. This
procedure better matches the IIP Process with the project development
and Federal review timelines. Under these changes, a project proponent
may initiate the IIP Process without detailed environmental resources
information, but the detailed information required by this section must
be developed to complete the IIP Process. The more detailed pre-
application information, presented in the resource reports, will allow
project proponents and the relevant Federal entities to coordinate and
identify issues prior to submission of applications for authorizations,
inform project design, and expedite relevant Federal entities'
environmental reviews by providing environmental information that
relevant Federal entities can use after submission of applications to
inform their own reviews and by ensuring those applications are
complete.
Sec. 900.7 Standard and Project-Specific Schedules
This final rule adds a new Sec. 900.7 to amend how DOE will carry
out its obligation to ``establish prompt and binding intermediate
milestones and ultimate deadlines for the review of, and Federal
authorization decisions relating to, the proposed facility'' pursuant
to section 216(h). 16 U.S.C. 824p(h)(4)(A). Specifically, this final
rule adds a description for the ``standard schedule,'' which DOE will
publish as guidance and update from time to time. The standard schedule
is not project specific. Rather, it will describe, as a general matter,
the steps necessary to review applications for Federal authorizations,
and the related environmental reviews necessary to site qualifying
projects. This schedule will contemplate that authorizations and
related environmental reviews be completed within two years.
Paragraph (b) describes the project-specific schedule. As discussed
further below, DOE will develop this schedule with the NEPA joint lead
agency and the relevant Federal entities on a per-project basis during
the IIP Process. This schedule would provide the ``binding intermediate
milestones and ultimate deadlines'' required by section 216(h). This
provision is intended to specify the considerations that DOE will
incorporate into its determination of the appropriate project-specific
schedule including joint lead and other agency-specific regulations and
schedules. Section 216(h)(4)(B) requires DOE to set a project-specific
schedule under which all Federal authorizations may be completed within
one year of the filing of a complete application unless other
requirements of Federal law require a longer schedule. DOE intends to
determine the project-specific schedule based on the considerations
specified in paragraph (b).
Sec. 900.8 IIP Process Review Meeting
This final rule amends the IIP Process to ensure that DOE and the
Federal and non-Federal entities involved have meaningful opportunities
to identify issues of concern prior to the project proponent's
submission of applications for authorizations. In addition to the
initial and close-out meetings included in the current text of part
900, this final rule establishes an IIP Process review meeting, to be
held at the request of the project proponent following initial
submission of the requisite thirteen resource reports. In addition,
this final rule adds a requirement for a project proponent requesting
the review meeting to update DOE on the status of the project's public
engagement and provide updated environmental information.
This final rule adds that the IIP Process review meeting will
ensure that DOE and the relevant Federal and non-Federal entities
involved have meaningful opportunities to identify issues of concern
prior to the close of the IIP Process and submission of applications
for Federal authorizations. To this end, this final rule adds a
requirement in paragraph (f) that at the review meeting the relevant
Federal entities should discuss any remaining issues of concern,
information gaps, data needs, potential issues or conflicts, statutory
and regulatory standards, and expectations for complete applications
for Federal authorizations. Additionally, the meeting participants will
provide updates on the siting process, including stakeholder outreach
and input. To facilitate these discussions, paragraph (a) is added to
state that a project proponent should submit a request for the review
meeting containing helpful documents and information such as a summary
table of changes made to the project since the initial meeting, maps of
proposed routes within study corridors, a conceptual plan for
implementation and monitoring of mitigation measures, an updated public
engagement plan and timeline information including dates on which any
applications were already filed, estimated dates for filing remaining
applications with Federal and non-Federal entities, and a proposed
duration for each Federal land use authorization expected to be
required for the proposed project.
Additionally, the IIP Process review meeting will provide an
opportunity for DOE and the relevant Federal and non-Federal entities
to review the detailed resource reports prepared pursuant to Sec.
900.6. Therefore, the review meeting will only be held after submission
of the reports. Section 900.8(f)(8) is added to state that during the
IIP Process review meeting, DOE and the relevant Federal and non-
Federal entities will identify any updates to the information included
in those reports that the project proponent must make before the
conclusion of the IIP Process. Finally, this final rule adds in Sec.
900.8(k) the requirement that the project proponent revise resource
reports based on feedback received during the meeting. DOE believes
that identifying and addressing issues in the reports during the IIP
Process instead of at the end of that process would expedite DOE's
preparation of a single environmental review document and increase the
likelihood of readiness of the project proponent's application(s) for
Federal authorization(s).
Furthermore, the IIP Process review meeting will integrate DOE's
statutory schedule-setting function discussed in the previous section
into the IIP Process. For this purpose, the review meeting request
under paragraph (a) should include a schedule for completing upcoming
field resource surveys, if known, and estimated dates that the project
proponent will file requests for Federal and non-Federal authorizations
and consultations. These resources will assist DOE in preparing the
proposed project-specific schedule, which DOE would be required to
present at the review meeting under Sec. 900.8(f)(9). At the meeting,
the relevant Federal entities would discuss the process for, and
estimated time to complete, required Federal authorizations. These
discussions, along with other matters discussed at the review meeting
would, in turn, allow DOE to continue refining the project-specific
schedule.
This final rule adds a requirement in paragraph (b) that within 10
days of receiving the review meeting request, DOE must provide relevant
Federal entities and relevant non-Federal entities with materials
included in the request and the initial resource reports submitted
under Sec. 900.6. In paragraph (c), DOE believes a 60-day period is
necessary to review the request for sufficiency and provide notice to
the proponent and relevant Federal and non-Federal agencies and
provides in
[[Page 35361]]
paragraph (d) that it will provide reasons for any findings of
insufficiency and how the project proponent may address them for
reconsideration. Furthermore, this final rule adds a requirement in
paragraph (e) that the review meeting will convene within 15 days of
providing notice that the request has been accepted. These timelines
will ensure that the IIP Process is pursued expeditiously while
affording the relevant Federal entities sufficient time to review the
relevant materials. The requirement to share the review meeting request
and initial resources reports in paragraph (b) will ensure that all
entities participating in the meeting have access to the materials
being discussed at the meeting.
This final rule adds requirements in paragraphs (g), (h), and (i)
that the IIP Process review meeting will conclude with a draft and,
subsequently, a final review meeting summary, to be prepared by DOE.
This summary will be included in the consolidated administrative docket
described by Sec. 900.10. It will serve as a docket of the issues
identified by the parties to the review meeting, and to ensure that the
project proponent, the relevant Federal and non-Federal entities, and
DOE, have a shared understanding of the work remaining to be done
during the IIP Process.
This final rule adds paragraph (j) to include a mechanism by which
it may determine whether the project proponent has developed the scope
of its proposed project and alternatives sufficiently for DOE to
determine that there exists an undertaking with the potential to affect
historic properties for purposes of section 106 of the NHPA. If DOE so
determines, DOE will initiate its section 106 review of the undertaking
and authorize project proponents as CITAP Program applicants to
initiate consultation with SHPOs, THPOs, and others consistent with 36
CFR 800.2(c)(4). This provision is intended to allow initiation of
section 106 consultation during the IIP Process, prior to submission of
applications for authorizations, but with sufficient opportunity for
the project proponent, the relevant Federal entities, and DOE, to
determine the scope of the proposed project.
Sec. 900.9 IIP Process Close-Out Meeting
This final rule amends the close-out meeting provisions of the
current rule at Sec. 900.4(k) and (l). The IIP Process will conclude
with the close-out meeting. This final rule adds the requirement of
submission of a close-out meeting request to specify the modifications
to the project since the review meeting. This final rule removes the
requirement in this section that states that the request may be
submitted no less than 45 days after the initial meeting. DOE removes
that requirement because changes to the IIP Process in this final rule
no longer allow for a request to be submitted within that timeframe.
This final rule removes paragraphs (k)(3), (5), (8), and (9). The
information required under those paragraphs will be submitted with the
review meeting request under Sec. 900.8(a). Likewise, DOE removed
paragraphs (k)(4), (6), and (7) because the information required under
those paragraphs would be submitted in the resources reports under
Sec. 900.6. Finally, paragraph (k)(1) is removed because the
submission of close-out meeting request materials is presumed to
indicate that a close-out meeting is being requested.
Paragraphs (a)(2) and (3) require a description of all changes made
to the proposed project since the review meeting and a final public
engagement plan. In paragraph (a)(4) DOE added a requirement that the
project proponent provide the requests for Federal authorizations for
the proposed project. These will be included in the close-out meeting
request to ensure that the project proponent is ready to begin the
Federal authorization process.
This final rule revises the timelines for requesting and convening
a close-out meeting. In current paragraphs (1), (2), and (3), DOE has
30 days to respond to a close-out meeting request and 60 days from the
date of providing a response to convene the close-out meeting. DOE
provides in paragraph (b) that within 10 days of receiving the request,
DOE must provide relevant Federal entities and relevant non-Federal
entities with materials included in the request and any updated
resource reports submitted as required under Sec. 900.8. Paragraph (c)
provides that DOE has 60 days to review the request for sufficiency and
notify the project proponent and all relevant Federal and non-Federal
entities of DOE's decision. Under paragraph (d), if DOE determines that
the meeting request or updated resource reports are insufficient then
DOE will provide reasons and how deficiencies may be addressed. Under
paragraph (e), DOE will convene the close-out meeting within 15 days of
notifying the project proponent that the request and updated resource
reports have been accepted. These new timelines will ensure that the
IIP Process is pursued expeditiously. Furthermore, the requirement to
share the close-out meeting request materials in paragraph (b) would
ensure that all entities participating in the meeting have access to
the materials being discussed at the meeting.
DOE removed the requirement that the substance of the close-out
meeting include a description of remaining issues of concern,
information gaps, data needs, and potential issues or conflicts that
could impact the time it will take relevant Federal entities to process
applications for Federal authorizations. This information is covered at
the review meeting under Sec. 900.8(d). Likewise, DOE eliminated
paragraphs (l)(3)(ii), (iii), (iv), and (v) because that information is
now required to be discussed at the review meeting. DOE added in
paragraph (e) that DOE will present the final project-specific schedule
at the meeting, in keeping with DOE's statutory schedule-setting
function discussed previously. As previously explained, the project-
specific schedule will include the intermediate milestones and final
deadlines for review of the project proponent's application and related
environmental reviews.
This final rule removes the portion of paragraph (l) of the current
regulation which states that ``The IIP Process Close-Out Meeting will
also result in the identification of a potential NEPA Lead Agency
pursuant to Sec. 900.6 described.'' This final rule adds a provision
to select the NEPA joint lead agency earlier in the IIP Process to
allow for sufficient coordination.
DOE removed paragraph (l)(3)(vi) because the information covered by
the Final IIP Resources Report will be covered by the thirteen
resources reports. Additionally, DOE removed paragraph (l)(3)(vii),
which encourages agencies to use the Final IIP Resources Report to
inform the NEPA Process. Instead, this final rule adds a new
requirement at Sec. 900.12(f) to require all relevant Federal entities
to use the single environmental review document as the basis for
Federal authorization decisions. That requirement is discussed in more
detail as follows.
This final rule removes paragraph (l)(3)(viii), which requires
relevant Federal entities to identify a preliminary schedule for
authorizations for the proposed project, because now DOE will set a
project-specific schedule for all relevant Federal entities in
consultation with such entities.
Paragraphs (g), (h), and (i) provide that the IIP Process close-out
meeting will conclude with a draft and, subsequently a final close-out
meeting summary, to be prepared by DOE. This summary will be included
in the administrative docket. It would serve as a summary of the issues
identified by the parties to the close-out meeting, and
[[Page 35362]]
ensure that the project proponent, the relevant Federal and non-Federal
entities, and DOE, have a shared understanding of the conclusion of the
IIP Process.
In paragraph (i)(4), in accordance with the 2023 MOU, DOE will
notify the FPISC Executive Director that the project should be included
on the FPISC Dashboard as a transparency project if the project is not
identified as a covered project pursuant to Sec. 900.5(e).
In paragraph (j), DOE and the NEPA joint lead agency shall issue a
notice of intent to publish an environmental review document within 90
days of the later of the IIP Process close-out meeting or the receipt
of a complete application for a Federal authorization for which NEPA
review will be required, as consistent with the final project-specific
schedule to enable DOE to implement its coordinating authority under
FPA section 216(h).
Finally, in paragraph (k), in accordance with section
313(h)(8)(A)(i) of the FPA, DOE shall issue, for each Federal land use
authorization for a proposed electric transmission facility, a
preliminary duration determination commensurate with the anticipated
use of the proposed facility.
Sec. 900.10 Consolidated Administrative Docket
Current Sec. 900.6 requires DOE to maintain an IIP Process
Administrative File with all relevant documents and communications
between the project proponent and the agencies and encourages agencies
to work with DOE to create a single record. To better integrate and
coordinate Federal authorizations, the new section dispenses with the
IIP Process Administrative File and combines all documents that were
previously included in that file along with all information assembled
by relevant Federal entities for authorizations and reviews after
completion of the IIP Process into a single, consolidated
administrative docket.
To this end, this final rule amends and redesignates paragraph (b)
as a new paragraph (a) to articulate more clearly the information that
should be included in the docket, including requests made during the
IIP Process, IIP Process meeting summaries, resources reports, and the
final project-specific schedule. The sentence in current paragraph (b)
regarding the Freedom of Information Act is removed because that law
applies to requests for information from the public on its own terms.
Current paragraph (b) also requires DOE to share the IIP Process
Administrative File with the joint lead NEPA agency. However, this
final rule adds in paragraph (c) the requirement that DOE make the
consolidated administrative docket available to both the NEPA joint
lead agency and any Federal or non-Federal entity that will issue an
authorization for the project. This change ensures that other entities
are able to use the docket for their own authorizations. Consequently,
this final rule removes paragraph (d), which says that Federal entities
are strongly encouraged to maintain information developed during the
IIP Process.
This final rule adds a new paragraph (d) providing notice that, as
necessary and appropriate, DOE may require a project proponent to
contract with a qualified docket-management consultant to assist DOE
and the NEPA joint lead agency in compiling and maintaining the
administrative docket. Such a contractor may assist DOE and the
relevant Federal entities in maintaining a comprehensive and readily
accessible docket. DOE is also proposing that any such contractor shall
operate at the direction of DOE, and that DOE shall retain
responsibility and authority over the content of the docket to ensure
the integrity and completeness of the docket.
This final rule adds a new paragraph (e) providing that upon
request, any member of the public may be provided materials included in
the docket, excluding any materials protected as CEII or as
confidential under other processes. This addition is to support
stakeholder engagement in the IIP Process.
Finally, this final rule relocates paragraph (a) of the current
rule to paragraph (b) for organizational purposes.
Sec. 900.11 NEPA Lead Agency and Selection of NEPA Joint Lead Agency
This section states that DOE serves in the NEPA lead agency role
contemplated in section 216(h) except where a joint lead is designated,
in which case DOE serves as a joint lead. DOE coordinates the selection
of a NEPA lead agency in compliance with NEPA, CEQ implementing
regulations at 40 CFR part 1500, and each agency's respective NEPA
implementing regulations and procedures.
This final rule redesignates Sec. 900.5 to a new Sec. 900.11 and
amends this section to reflect that DOE, in accordance with section
216(h)(5)(A) and the 2023 MOU, will serve as lead agency for purposes
of NEPA along with any NEPA joint lead agency as designated pursuant to
the MOU and Sec. 900.11 consistent with its obligation as lead agency
to coordinate with relevant Federal entities.
In the 2023 MOU, the MOU signatory agencies agreed to a process by
which a NEPA joint lead agency could be designated. Under that process,
DOE and the agency with the most significant interest in the management
of Federal lands or waters that would be traversed or affected by the
proposed project would serve as lead agencies jointly responsible for
preparing an EIS under NEPA. Section 900.11(b) reflects that agreed-
upon process.
These amendments also provide that, for projects that would
traverse both USDA and DOI lands, DOE will request that USDA and DOI
determine the appropriate NEPA joint lead agency.
Sec. 900.12 Environmental Review
Consistent with DOE's role as lead agency, a new Sec. 900.12 is
added to define DOE's responsibilities as lead agency for environmental
reviews and the NEPA process, including by preparing a single
environmental review document designed to serve the needs of all
relevant Federal entities. In paragraph (a) of this section, this final
rule clarifies that DOE will begin preparing an environmental review
document following the conclusion of the IIP Process and after receipt
of a relevant application. It also notes that DOE will do so in
conjunction with any NEPA joint lead agency selected under Sec.
900.11.
The other provisions of this section specify details of DOE's--and
any NEPA joint lead agency's--role as lead NEPA agency, including to
arrange for contractors, publish completed documents, and identify the
full scope of alternatives for analysis. This final rule provides that
except where inappropriate or inefficient to do so, the Federal
agencies shall issue a joint record of decision, inclusive of all
relevant Federal authorizations including the determination by the
Secretary of Energy of a duration for each land use authorization
issued under section 216(h)(8)(A)(i). This joint-decision provision is
added to be consistent with NEPA regulations, including the Fiscal
Responsibility Act of 2023, which codified processes to streamline the
environmental review process and facilitate one Federal decision, be
consistent with the Congressional intent of FPA 216(h), and enhance
DOE's coordinating function.
Consistent with section 216(h)(5)(A), which requires that DOE's
environmental review document serve as ``the basis for all decisions on
the project under Federal law,'' paragraph (f) is added to establish
that the relevant
[[Page 35363]]
Federal agencies will use the environmental review document as the
basis for their respective decisions.
Finally, paragraph (g) is added to specify that DOE will serve as
lead agency for purposes of consultation under the ESA and compliance
with the NHPA unless the relevant Federal entities designate otherwise.
This provision will allow DOE to meet its obligation under section
216(h)(2) to coordinate ``all . . . related environmental reviews of
the facility.''
Sec. 900.13 Severability
Section Sec. 900.13 provides that the provisions of this final
rule are separate and severable from one another, and that if any
provision is stayed or determined to be invalid by a court of competent
jurisdiction, the remaining provisions would still function sensibly
and shall continue in effect. This severability clause is intended to
clearly express the Department's intent that should a provision be
stayed or invalidated the remaining provisions shall continue in
effect. The Department has carefully considered the requirements of
this final rule, both individually and in their totality, including
their potential costs and benefits to project proponents. In the event
a court were to stay or invalidate one or more provisions of this rule
as finalized, the Department would want the remaining portions of the
rule as finalized to remain in full force and legal effect.
VIII. Regulatory Review
A. Review Under Executive Orders 12866, 13563, and 14094
Executive Order (``E.O.'') 12866, ``Regulatory Planning and
Review,'' 58 FR 51735 (Oct. 4, 1993), as supplemented and reaffirmed by
E.O. 13563, ``Improving Regulation and Regulatory Review,'' 76 FR 3821
(Jan. 21, 2011) and amended by E.O. 14094, ``Modernizing Regulatory
Review,'' 88 FR 21879 (April 11, 2023), requires agencies, to the
extent permitted by law, to (1) propose or adopt a regulation only upon
a reasoned determination that its benefits justify its costs
(recognizing that some benefits and costs are difficult to quantify);
(2) tailor regulations to impose the least burden on society,
consistent with obtaining regulatory objectives, taking into account,
among other things, and to the extent practicable, the costs of
cumulative regulations; (3) select, in choosing among alternative
regulatory approaches, those approaches that maximize net benefits
(including potential economic, environmental, public health and safety,
and other advantages; distributive impacts; and equity); (4) to the
extent feasible, specify performance objectives, rather than specifying
the behavior or manner of compliance that regulated entities must
adopt; and (5) identify and assess available alternatives to direct
regulation, including providing economic incentives to encourage the
desired behavior, such as user fees or marketable permits, or providing
information upon which choices can be made by the public. DOE
emphasizes as well that E.O. 13563 requires agencies to use the best
available techniques to quantify anticipated present and future
benefits and costs as accurately as possible. In its guidance, the
Office of Information and Regulatory Affairs (OIRA) has emphasized that
such techniques may include identifying changing future compliance
costs that might result from technological innovation or anticipated
behavioral changes. For the reasons stated in the preamble, this
regulatory action is consistent with these principles.
Section 6(a) of E.O. 12866 requires agencies to submit
``significant regulatory actions'' to OIRA for review. OIRA has
determined that this regulatory action constitutes a ``significant
regulatory action'' within the scope of E.O. 12866. Accordingly, this
action is subject to review under E.O. 12866 by OIRA of the Office of
Management and Budget (OMB).
Section 6(a) of E.O. 12866 requires an agency issuing a
``significant regulatory action'' to provide an assessment of the
potential costs and benefits of the regulatory action. To that end, DOE
has further assessed the qualitative and quantitative costs and
benefits of this final rule.
The societal costs of the action are the direct costs incurred by
project proponents during the IIP Process. DOE discussed in the
previous sections that most of the information required to be submitted
during the IIP Process would likely be required absent these
regulations and therefore the investment of time and resources required
by this process are unlikely to be an additional burden on respondents.
However, the full costs are considered in this analysis for
transparency. These costs of $439,000 per year are detailed in the
Paperwork Reduction Act burden analysis. The table below captures the
10-year and 20-year net present value of those annual costs under two
discount rates (3% and 7%).
CITAP Program NPV Cost Estimates *
------------------------------------------------------------------------
Discount rate 3% 7%
------------------------------------------------------------------------
10-year NPV....................... $3,745,000 $3,083,000
20-year NPV....................... 6,531,000 4,651,000
------------------------------------------------------------------------
* 10-year analysis is 2024-2033, 20-year analysis is 2024-2043. NPV
estimates provided in 2024$.
The benefits of the CITAP Program, designed to reduce the Federal
authorization timelines for interstate electric transmission facilities
and enable more rapid deployment of transmission infrastructure,
include direct benefits to the project proponents in decreased time and
expenditure on authorizations and a series of indirect social benefits.
Increasing the current pace of transmission infrastructure
deployment will generate benefits to the public in multiple ways that
can be categorized into grid operations, system planning, and non-
market benefits. Grid operation benefits include a reduction in the
congestion costs for generating and delivering energy; mitigation of
weather and variable generation uncertainty, enhanced diversity of
supply, which increases market competition and reduces the need for
regional backup power options; and increased market liquidity and
competition.\15\ From a system planning standpoint, accelerated
transmission investments will allow the development of new, low cost
power plants in areas of high congestion which might not otherwise see
investment due to capacity constraints, and additional grid hardening
or resilience. Finally, non-market benefits to the public include
reduced costs for meeting
[[Page 35364]]
public policy goals related to emissions and equitable energy access,
as well as emissions reductions system wide.\16\
---------------------------------------------------------------------------
\15\ Millstein, A. et al. (2022) Empirical estimates of
transmission value using locational marginal prices, Empirical
Estimates of Transmission Value using Locational Marginal Prices
[verbar] Electricity Markets and Policy Group, 6. Available at:
https://emp.lbl.gov/publications/empirical-estimates-transmission.
\16\ Id.
---------------------------------------------------------------------------
The DOE Grid Deployment Office released the 2023 National
Transmission Needs Study (Needs Study), which identified significant
need for the expansion of electric transmission across the contiguous
United States.\17\ The Needs Study and 2022 interconnection queue
analysis by Berkeley Lab support DOE's analysis that the CITAP Program
will provide substantial benefits by reducing authorization timelines
for transmission projects and increasing the speed of transmission
development and clean energy integration.\18\
---------------------------------------------------------------------------
\17\ DOE, National Transmission Needs Study (Oct. 2023),
available at https://www.energy.gov/sites/default/files/2023-12/National%20Transmission%20Needs%20Study%20-%20Final_2023.12.1.pdf.
\18\ Berkeley Lab, Queued up: Characteristics of power plants
seeking transmission interconnection (2023), Electricity Markets and
Policy Group. Available at: https://emp.lbl.gov/queues.
---------------------------------------------------------------------------
The quantitative benefits of the CITAP Program will ultimately
depend on the projects that are designed and developed by project
proponents. However, the quantifiable benefits of transmission
development can be estimated generally. These quantifiable benefits are
the result of reductions in transmission congestion costs and avoided
emissions from the increased use of clean energy enabled by additional
transmission.
A 2023 analysis of transmission congestion costs by a consulting
group found that congestion costs have risen from an average of $7.1
billion between 2016 and 2021 to $20.8 billion in 2022.\19\ A 2022
study by Lawrence Berkeley National Lab found that between 2012 and
2021, a 1000 MW interregional transmission line could have provided $20
to $670 million dollars per year in value by providing congestion
relief, which would have lowered energy costs to consumers.\20\
Forward-looking projections for transmission value along these
parameters are not available, and DOE is reluctant to project the
complex changes to technical operations and market dynamics given the
wide range in projected value. However, DOE notes that it has estimated
that the CITAP Program will serve three projects a year that are each
roughly equivalent to a 1000 MW line, an increase in the average number
of these transmission projects authorized by a Federal agency in the
past 17 years. With decreased authorization times after the CITAP
Program is initialized, the additional capacity enabled by this action
would likely provide substantial congestion relief, consistent with the
studies cited previously.
---------------------------------------------------------------------------
\19\ (2023) Transmission congestion costs rise again in U.S.
RTOS, 1. Available at: https://gridstrategiesllc.com/wp-content/uploads/2023/07/GS_Transmission-Congestion-Costs-in-the-U.S.-RTOs1.pdf.
\20\ Millstein, et al., 2022, 15.
---------------------------------------------------------------------------
A key driver of transmission congestion costs is that the growth of
low-cost renewable energy projects is outpacing the rate of
transmission expansion. Inadequate transmission capacity can lead to
curtailment of available renewable energy in favor of thermal
generators, which increases costs to consumers due to fuel prices and
increases emissions.\21\ A recent projection found that transmission
capacity must expand by 2.3% annually to realize the full benefits of
the clean energy investments in the IRA. However, in the last decade,
transmission capacity has only increased an average of 1% per year.\22\
The modeling projects that increasing the rate of transmission capacity
expansion by even just 50% (1% to 1.5% annually) would significantly
reduce emissions by enabling more clean energy on the grid, estimating
nearly 600 million tons of avoided emissions (CO2
equivalent) in 2030 alone.\23\ An annual 1.5% increase in transmission
capacity is estimated to add 7,000 MW to the grid in 2030 and provide
an estimated $53.4 billion in societal benefits from avoided emissions
that year, using a $89/ton social cost of carbon.\24\ DOE estimates
that the CITAP Program will increase the number of high-capacity
projects seeking Federal authorizations, providing a portion of
projected avoided emissions benefits through increased transmission
capacity. These benefits would continue to grow in the following years
as transmission capacity is increased.
---------------------------------------------------------------------------
\21\ Howland, E. (2023) US grid congestion costs jumped 56% to
$20.8B in 2022: Report, Utility Dive. Available at: https://
www.utilitydive.com/news/grid-congestion-costs-transmission-gets-
grid-strategies-report/687309/
#:~:text=Costs%20to%20consumers%20from%20congestion%20on%20the%20U.S.
,report%20released%20Thursday%20by%20consulting%20firm%20Grid%20Strat
egies. and Nationwide transmission congestion costs rise to $20.8
billion in 2022 (2023). Advanced Power Alliance. Available at:
https://poweralliance.org/2023/07/13/nationwide-transmission-
congestion-costs-rise-to-20-8-billion-in-2022/
#:~:text=By%20extrapolating%20data%20from%20Independent%20Market%20Mo
nitor%20reports,congestion%20costs%20reached%20%2420.8%20billion%20na
tionwide%20last%20year.
\22\ Jenkins, J.D. et al. (2022) Electricity transmission is key
to unlock the full potential of the Inflation Reduction Act, Zenodo.
Available at: https://zenodo.org/record/
7106176#:~:text=Previously%2C%20REPEAT%20Project%20estimated%20that%2
0IRA%20could%20cut,from%20electric%20vehicles%2C%20heat%20pumps%2C%20
and%20other%20electrification.
\23\ Id.
\24\ Technical support document: Social cost of carbon, methane,
(2021) whitehouse.gov, 5. Available at: https://www.whitehouse.gov/wp-content/uploads/2021/02/TechnicalSupportDocument_SocialCostofCarbonMethaneNitrousOxide.pdf.
---------------------------------------------------------------------------
While these estimates of quantitative benefits are necessarily
approximate, the non-monetized benefits of the CITAP Program to the
public are expected to far offset the monetized costs to project
proponents. By enabling rapid development of enhanced transmission
capacity, the CITAP Program will help increase access to a diversity of
generation sources, offset transmission congestion and carbon costs,
and deliver reliable, affordable power that future consumers will need
when and where they need it.
B. Review Under the Regulatory Flexibility Act
The Regulatory Flexibility Act of 1980 (5 U.S.C. 601 et seq.)
requires that an agency prepare an initial regulatory flexibility
analysis for any regulation for which a general notice of proposed
rulemaking is required, unless the agency certifies that the rule, if
promulgated, will not have a significant economic impact on a
substantial number of small entities (5 U.S.C. 605(b)). As required by
E.O. 13272, ``Proper Consideration of Small Entities in Agency
Rulemaking,'' 67 FR 53461 (Aug. 16, 2002), DOE published procedures and
policies on February 19, 2003, to ensure that the potential impacts of
its rules on small entities are properly considered during the
rulemaking process (see 68 FR 7990). DOE has made its procedures and
policies available on the Office of the General Counsel's website
(www.energy.gov/gc/office-general-counsel).
DOE reviewed this final rule under the provisions of the Regulatory
Flexibility Act and the procedures and policies published on February
19, 2003. DOE certifies that this final rule will not have a
significant economic impact on a substantial number of small entities.
The factual basis for this certification is set forth.
DOE expects that the amendments to part 900 will not affect the
substantive interests of such project proponents, including any project
proponents that are small entities. DOE expects actions taken under the
provisions to coordinate information and agency communication before
applications for Federal
[[Page 35365]]
authorizations are submitted to Federal agencies for review and
consideration would help reduce application review and decision-making
timelines. Ensuring that all project proponents avail themselves of the
benefits of the IIP Process will result in a clear, non-duplicative,
process. Participation in the CITAP Program is optional. Thus,
proposing to make the IIP Process a condition of the Program does not
prevent project proponents from submitting application outside of the
Program. DOE, however, encourages project proponents to take advantage
of the Program based on the urgency and a consensus among 2023 MOU
signatories of the anticipated benefits the Program will provide.
Furthermore, these changes are procedural and apply only to project
proponents that develop electric transmission infrastructure.
Historically, entities that develop transmission infrastructure are
larger entities. Therefore, these procedures are unlikely to directly
affect small businesses or other small entities. For these reasons, DOE
certifies that this final rule will not have a significant economic
impact on a substantial number of small entities. Accordingly, DOE has
not prepared a regulatory flexibility analysis for this rulemaking.
DOE's certification and supporting statement of factual basis will be
provided to the Chief Counsel for Advocacy of the Small Business
Administration for review under 5 U.S.C. 605(b).
C. Review Under the Paperwork Reduction Act of 1995
This final rule contains information collection requirements
subject to review and approval by OMB pursuant to the Paperwork
Reduction Act of 1995 (44 U.S.C. 3501 et seq.) (PRA) and the procedures
implementing that Act (5 CFR 1320.1 et seq.). The request to approve
and revise this collection requirement has been submitted to OMB for
approval. The amendments are intended to improve the pre-application
procedures and result in more efficient processing of applications.
This final rule modifies certain reporting and recordkeeping
requirements included in OMB Control No. 1910-5185 which is an ongoing
collection. The revisions to DOE's regulations associated with the OMB
Control No. 1910-5185 information collection are intended to ensure
that DOE may carry out its statutory obligations under section 216(h)
of the FPA. Information supplied will be used to support an initiation
request necessary to begin DOE's IIP Process. The revisions include
requiring that a project proponent provide: (1) additional maps and
information for the summary of proposed project; (2) a project
participation plan; and (3) a statement regarding whether the project
is a FAST-41 covered project. Additional information collection
required includes thirteen resource reports describing the project and
its impacts to allow DOE to complete a single environmental review
document as part of the IIP Process. Those reports are: General project
description; Water use and quality; Fish, wildlife, and vegetation;
Cultural resources; Socioeconomics; Geological resources and hazards;
Soil resources; Land use, recreation, and aesthetics; Communities of
interest; Air quality and noise effects; Alternatives; Reliability,
resilience, and safety; and Tribal interests. Additionally, during the
review and close-out meetings, project proponents will provide updates
to project documents and the project schedule. The revisions represent
an increase in information collection requirements and burden for OMB
No. 1910-5185.
The estimated burden and cost for the requirements contained in
this final rule follow. Each entry indicates the time estimated for a
meeting or the time estimated for the respondent to prepare the report
or request.
Estimate of Annual Respondent Reporting and Recordkeeping Burden and Cost
----------------------------------------------------------------------------------------------------------------
Estimated
burden hours
Estimated Estimated Estimated (total Estimated
Form number/title (and/or other number of number of number of responses x reporting and
collection instrument name) respondents total burden hours number of recordkeeping
responses * per response hours per cost burden **
response)
----------------------------------------------------------------------------------------------------------------
Current Rule Estimate of Annual Respondent Reporting and Recordkeeping Burden and Cost
----------------------------------------------------------------------------------------------------------------
Section 900.2................... 5 5 1 5 $283
Section 900.4................... 5 10 5 50 2,830
-------------------------------------------------------------------------------
Total....................... .............. 15 .............. 55 3,113
----------------------------------------------------------------------------------------------------------------
Final Rule Estimate of Annual Respondent Reporting and Recordkeeping Burden and Cost
----------------------------------------------------------------------------------------------------------------
Initiation Request.............. 3 3 30 90 5,855
Initial Meeting................. 3 3 8 24 1,561
Resource Report 1: General 3 3 110 330 21,467
project description............
Resource Report 2: Water use and 3 3 125 375 24,394
quality........................
Resource Report 3: Fish, 3 3 200 600 39,030
wildlife, and vegetation.......
Resource Report 4: Cultural 3 3 200 600 39,030
resources......................
Resource Report 5: 3 3 160 480 31,224
Socioeconomics.................
Resource Report 6: Tribal 3 3 160 480 31,224
interests......................
Resource Report 7: Communities 3 3 96 288 18,734
of interest....................
Resource Report 8: Geological 3 3 160 480 31,224
resources and hazards..........
Resource Report 9: Soil 3 3 200 600 39,030
resources......................
Resource Report 10: Land use, 3 3 224 676 43,714
recreation and aesthetics......
Resource Report 11: Air quality 3 3 220 660 42,933
and noise effects..............
Resource Report 12: Alternatives 3 3 160 480 31,224
Resource Report 13: Reliability, 3 3 100 300 19,515
resilience, and safety.........
Review Meeting Request.......... 3 3 1 3 195
Review Meeting.................. 3 3 4 12 781
Close-Out Meeting Request....... 3 3 1 3 195
[[Page 35366]]
Close-Out Meeting............... 3 3 2 6 390
-------------------------------------------------------------------------------
Total....................... 3 3 2,134 6,402 421,720
----------------------------------------------------------------------------------------------------------------
* One response per respondent.
** estimated cost based on median hourly wage for a project manager from https://www.bls.gov/oes/current/oes131111.htm ($45.81/hr) and fully burdened scaling factor from https://www.bls.gov/regions/southwest/news-release/employercostsforemployeecompensation_regions.htm.
Notwithstanding any other provision of the law, no person is
required to respond to, nor shall any person be subject to a penalty
for failure to comply with, a collection of information subject to the
requirements of the PRA, unless that collection of information displays
a currently valid OMB Control Number.
D. Review Under the National Environmental Policy Act of 1969
DOE has analyzed this final rule in accordance with NEPA and DOE's
NEPA implementing regulations (10 CFR part 1021). DOE has determined
that this final rule is covered under the categorical exclusion located
at 10 CFR part 1021, subpart D, appendix A, Categorical Exclusion A5
because this final rule revises existing regulations at 10 CFR part
900. The changes would affect the process for the consideration of
future proposals for electricity transmission, and potential
environmental impacts associated with any particular proposal would be
analyzed pursuant to NEPA and other applicable requirements. DOE has
considered whether this action would result in extraordinary
circumstances that would warrant preparation of an Environmental
Assessment or EIS and has determined that no such extraordinary
circumstances exist. Therefore, DOE has determined that this rulemaking
does not require an Environmental Assessment or an EIS.
E. Review Under Executive Order 12988
With respect to the review of existing regulations and the
promulgation of new regulations, Section 3(a) of E.O. 12988, ``Civil
Justice Reform,'' 61 FR 4729 (Feb. 7, 1996), imposes on Federal
agencies the general duty to adhere to the following requirements: (1)
eliminate drafting errors and ambiguity; (2) write regulations to
minimize litigation; (3) provide a clear legal standard for affected
conduct rather than a general standard; and (4) promote simplification
and burden reduction. Section 3(b) of E.O. 12988 specifically requires
that agencies make every reasonable effort to ensure that the
regulation: (1) clearly specifies the preemptive effect, if any; (2)
clearly specifies any effect on existing Federal law or regulation; (3)
provides a clear legal standard for affected conduct while promoting
simplification and burden reduction; (4) specifies the retroactive
effect, if any; (5) adequately defines key terms; (6) specifies whether
administrative proceedings are to be required before parties may file
suit in court and, if so, describes those proceedings and requires the
exhaustion of administrative remedies; and (7) addresses other
important issues affecting clarity and general draftsmanship under any
guidelines issued by the Attorney General. Section 3(c) of E.O. 12988
requires agencies to review regulations in light of applicable
standards in section 3(a) and section 3(b) to determine whether they
are met, or it is unreasonable to meet one or more of them. DOE has
completed the required review and determined that, to the extent
permitted by law, this final rule meets the relevant standards of E.O.
12988.
F. Review Under Executive Order 13132
E.O. 13132, ``Federalism'', 64 FR 43255 (Aug. 10, 1999), imposes
certain requirements on agencies formulating and implementing policies
or regulations that preempt State law or that have federalism
implications. Agencies are required to examine the constitutional and
statutory authority supporting any action that would limit the
policymaking discretion of the States and carefully assess the
necessity for such actions. E.O. 13132 also requires agencies to have
an accountable process to ensure meaningful and timely input by State
and local officials in the development of regulatory policies that have
federalism implications. On March 14, 2000, DOE published a statement
of policy describing the intergovernmental consultation process it will
follow in the development of such regulations (see 65 FR 13735). DOE
has examined this notice and has determined that this final rule will
not preempt State law and will not have a substantial direct effect on
the States, the relationship between the national government and the
States, or the distribution of power and responsibilities among the
various levels of government. No further action is required by E.O.
13132.
G. Review Under Executive Order 13175
Under E.O. 13175, ``Consultation and Coordination with Indian
Tribal Governments,'' 65 FR 67249 (Nov. 6, 2000), DOE may not issue a
discretionary rule that has Tribal implications or that imposes
substantial direct compliance costs on Indian Tribal governments unless
DOE provides funds necessary to pay the costs of the Tribal governments
or consults with Tribal officials before promulgating the rule. This
final rule aims to improve the coordination of Federal authorizations
for proposed interstate electric transmission facilities pursuant to
the FPA. Specifically, the amendments are intended to refine the pre-
application procedures and result in more efficient processing of
applications. As a result, the amendments to part 900 do not have
substantial direct effects on one or more Indian Tribes, will not
impose substantial direct compliance costs on Indian Tribal
governments, and will not preempt Tribal laws. Accordingly, the funding
and consultation requirements of E.O. 13175 do not apply, and a Tribal
summary impact statement is not required.
H. Review Under the Unfunded Mandates Reform Act of 1995
Title II of the Unfunded Mandates Reform Act (UMRA) of 1995 (Pub.
L. 104-4) requires each Federal agency to assess the effects of a
Federal regulatory action on State, local, and Tribal governments, and
the private sector.
[[Page 35367]]
(Pub. L. 104-4, sec. 201 (codified at 2 U.S.C. 1531)). For a regulatory
action likely to result in a rule that may cause the expenditure by
State, local, and Tribal governments, in the aggregate, or by the
private sector of $100 million or more in any one year (adjusted
annually for inflation), section 202 of UMRA requires a Federal agency
to publish a written statement that estimates the resulting costs,
benefits, and other effects on the national economy (2 U.S.C. 1532(a),
(b)). UMRA also requires a Federal agency to develop an effective
process to permit timely input by elected officers of State, local, and
Tribal governments on a proposed ``significant Federal
intergovernmental mandate,'' and requires an agency plan for giving
notice and opportunity for timely input to potentially affected small
governments before establishing any requirements that might
significantly or uniquely affect them. On March 18, 1997, DOE published
a statement of policy on its process for intergovernmental consultation
under UMRA (see 62 FR 12820) (This policy is also available at:
www.energy.gov/gc/guidance-opinions). DOE examined this final rule
according to UMRA and its statement of policy and has determined that
the rule contains neither an intergovernmental mandate, nor a mandate
that may result in the expenditure by State, local, and Tribal
governments, in the aggregate, or by the private sector, of $100
million or more in any year. Accordingly, no further assessment or
analysis is required under UMRA.
I. Review Under Executive Order 12630
DOE has determined, under E.O. 12630, ``Governmental Actions and
Interference with Constitutionally Protected Property Rights,'' 53 FR
8859 (March 18, 1988), that this this final rule would not result in
any takings that might require compensation under the Fifth Amendment
to the U.S. Constitution.
J. Review Under Executive Order 13211
E.O. 13211, ``Actions Concerning Regulations That Significantly
Affect Energy Supply, Distribution, or Use,'' 66 FR 28355 (May 22,
2001), requires Federal agencies to prepare and submit to the OMB a
Statement of Energy Effects for any proposed significant energy action.
A ``significant energy action'' is defined as any action by an agency
that promulgated or is expected to lead to promulgation of a final
rule, and that: (1)(i) is a significant regulatory action under E.O.
12866, or any successor order; and (ii) is likely to have a significant
adverse effect on the supply, distribution, or use of energy, or (2) is
designated by the Administrator of OIRA as a significant energy action.
For any proposed significant energy action, the agency must give a
detailed statement of any adverse effects on energy supply,
distribution, or use should the proposal be implemented, and of
reasonable alternatives to the action and their expected benefits on
energy supply, distribution, and use. This final rule is intended to
improve the pre-application procedures for certain transmission
projects, and therefore result in the more efficient processing of
applications, and thus this final rule will not have a significant
adverse effect on the supply, distribution, or use of energy and is
therefore not a significant energy action. Accordingly, DOE has not
prepared a Statement of Energy Effects.
K. Review Under the Treasury and General Government Appropriations Act,
1999
Section 654 of the Treasury and General Government Appropriations
Act, 1999 (Pub. L. 105-277) requires Federal agencies to issue a Family
Policymaking Assessment for any rule that may affect family well-being.
This final rule would not have any impact on the autonomy or integrity
of the family as an institution. Accordingly, DOE has concluded that it
is not necessary to prepare a Family Policymaking Assessment.
L. Review Under the Treasury and General Government Appropriations Act,
2001
The Treasury and General Government Appropriations Act, 2001 (44
U.S.C. 3516 note) provides for Federal agencies to review most
disseminations of information to the public under guidelines
established by each agency pursuant to general guidelines issued by
OMB. OMB's guidelines were published at 67 FR 8452 (Feb. 22, 2002), and
DOE's guidelines were published at 67 FR 62446 (Oct. 7, 2002).
DOE has reviewed this final rule under the OMB and DOE guidelines
and has concluded that it is consistent with applicable policies in
those guidelines.
IX. Congressional Notification
As required by 5 U.S.C. 801, DOE will report to Congress on the
promulgation of this rule before its effective date. The report will
state that the Office of Information and Regulatory Affairs has
determined that the rule does not meet the criteria set forth in 5
U.S.C. 804(2).
X. Rehearing
This rule is a final order subject to section 313 of the FPA (16
U.S.C. 825l). Accordingly, any party seeking judicial review of this
rule must first seek rehearing before the Department. A request for
rehearing must be submitted in accordance with the FOR FURTHER
INFORMATION CONTACT portion of this rule, within 30 days of the
issuance of this rule. A request must concisely state the alleged
errors in the final rule and must list each issue in a separately
enumerated paragraph; any issue not so listed will be deemed waived.
XI. Approval by the Office of the Secretary of Energy
The Secretary of Energy has approved publication of this final
rule.
List of Subjects in 10 CFR Part 900
Electric power, Electric utilities, Energy, Reporting and
recordkeeping requirements.
Signing Authority
This document of the DOE was signed on April 11, 2024, by Maria D.
Robinson, Director, Grid Deployment Office, pursuant to delegated
authority from the Secretary of Energy. That document with the original
signature and date is maintained by DOE. For administrative purposes
only, and in compliance with requirements of the Office of the Federal
Register, the undersigned DOE Federal Register Liaison Officer has been
authorized to sign and submit the document in electronic format for
publication, as an official document of the Department of Energy. This
administrative process in no way alters the legal effect of this
document upon publication in the Federal Register.
Signed in Washington, DC, on April 12, 2024.
Treena V. Garrett,
Federal Register Liaison Officer, U.S. Department of Energy.
0
For the reasons stated in the preamble, the Department of Energy
revises 10 CFR part 900 to read as follows:
PART 900--COORDINATION OF FEDERAL AUTHORIZATIONS FOR ELECTRIC
TRANSMISSION FACILITIES
Sec.
900.1 Purpose and scope.
900.2 Definitions.
900.3 Applicability to other projects.
900.4 Purpose and scope of IIP Process.
900.5 Initiation of IIP Process.
900.6 Project proponent resource reports.
900.7 Standard and project-specific schedules.
900.8 IIP Process review meeting.
[[Page 35368]]
900.9 IIP Process close-out meeting.
900.10 Consolidated administrative docket.
900.11 NEPA lead agency and selection of NEPA joint lead agency.
900.12 Environmental review.
900.13 Severability.
Authority: 16 U.S.C. 824p(h).
Sec. 900.1 Purpose and scope.
(a) Pursuant to section 216(h) of the Federal Power Act (16 U.S.C.
824p(h)), the Department of Energy (DOE) establishes the Coordinated
Interagency Transmission Authorizations and Permits Program (CITAP
Program) under this part to coordinate the review and processes related
to Federal authorizations necessary to site a proposed electric
transmission facility. Pursuant to section 216(h)(4)(A), this part
establishes the mechanism by which DOE will set prompt and binding
intermediate milestones and ultimate deadlines for the processes
related to deciding whether to issue such authorizations. In addition,
as the lead agency and in collaboration with any National Environmental
Policy Act (NEPA) joint lead agency and in consultation with the
relevant Federal entities, as applicable, DOE will prepare a single
environmental review document, which will be designed to serve the
needs of all relevant Federal agencies and inform all Federal
authorization decisions on the proposed electric transmission project.
(b) This part provides a process for the timely submission of
information needed for Federal decisions related to authorizations for
siting proposed electric transmission projects. This part seeks to
ensure that these projects are developed consistent with the nation's
environmental laws, including laws that address endangered and
threatened species, critical habitats, and cultural and historic
properties. This part provides a framework, called the Integrated
Interagency Pre-Application (IIP) Process, by which DOE will coordinate
submission of materials necessary for Federal authorizations and
related environmental reviews required under Federal law to site
proposed electric transmission facilities, and integrates the IIP
Process into the CITAP Program.
(c) This part describes the timing and procedures for the IIP
Process, which should be initiated prior to a project proponent's
submission of any application for a required Federal authorization. The
IIP Process provides for timely and focused pre-application meetings
with relevant Federal and non-Federal entities. In addition, the IIP
Process facilitates early identification of potential siting
constraints and opportunities. The IIP Process promotes thorough and
consistent stakeholder engagement by a project proponent. At the close-
out of each IIP Process, DOE will establish the schedule for all
Federal reviews and authorizations required to site a proposed electric
transmission facility, in coordination with the relevant Federal
entities.
(d) This part improves the Federal permitting process by
facilitating the early submission, compilation, and documentation of
information needed for coordinated review by relevant Federal entities
under the National Environmental Policy Act (42 U.S.C. 4321 et seq.).
This part also facilitates expeditious action on necessary Federal
authorizations by ensuring that relevant Federal entities coordinate
their consideration of those applications and by providing non-Federal
entities the opportunity to coordinate their non-Federal permitting and
environmental reviews with the reviews of the relevant Federal
entities.
(e) This part facilitates improved and earlier coordination of and
consultation between relevant Federal entities, relevant non-Federal
entities, and others pursuant to section 106 of the National Historic
Preservation Act (54 U.S.C. 306108) (NHPA) and its implementing
regulations found at 36 CFR part 800. Under this part, DOE may
determine it has an undertaking with the potential to affect historic
properties and may, at that time, authorize a project proponent, as a
CITAP applicant, to initiate section 106 consultation for the
undertaking consistent with 36 CFR 800.2(c)(4). Prior to that
determination, this part requires project proponents to gather initial
information and make recommendations relevant to the section 106
process to the extent possible. This part also establishes DOE as lead
for the section 106 process, consistent with DOE's role as lead or
joint lead agency for purposes of NEPA, in order to maximize
opportunities for coordination between the NEPA and section 106
processes. Federal entities remain responsible for government-to-
government consultation with Indian Tribes (and government-to-sovereign
consultation in the context of Native Hawaiian relations) and for any
findings and determinations required by and reserved to Federal
agencies in 36 CFR part 800.
(f) This part applies only to qualifying projects as defined by
Sec. 900.2.
(g) Participation in the IIP Process does not alter any
requirements to obtain necessary Federal authorizations for proposed
electric transmission projects. Nor does this part alter any
responsibilities of the relevant Federal entities for environmental
review or consultation under applicable law.
(h) The Director may waive any requirement imposed on a project
proponent under this part if, in the Director's discretion, the
Director determines that the requirement is unnecessary, duplicative,
or impracticable under the circumstances relevant to the proposed
electric transmission project. Where the principal project developer is
itself a Federal entity that would be otherwise expected to prepare an
environmental review document for the project, the Director shall
consider modifications to the requirements under this part as may be
necessary under the circumstances.
Sec. 900.2 Definitions.
As used in this part:
Analysis area means a geographical area established for a resource
report at the IIP Process initial meeting and modified at the IIP
Process review meeting, if applicable.
Authorization means any license, permit, approval, finding,
determination, or other administrative decision required under Federal,
Tribal, State, or local law to site a proposed electric transmission
facility, including special use authorization, certifications,
opinions, or other approvals.
Communities of Interest means the following communities that could
be affected by a proposed electric transmission project: disadvantaged
communities; rural communities; Tribal communities; indigenous
communities; geographically proximate communities; communities with
environmental justice concerns; and energy communities.
Director means the Director of the DOE Grid Deployment Office, that
person's delegate, or another DOE official designated to perform the
functions of this part by the Secretary of Energy.
Federal authorization means any authorization required under
Federal law.
Federal entity means any Federal agency or department.
Indian Tribe has the same meaning as provided by 25 U.S.C. 5304(e).
Mitigation approach means an approach that applies a conceptual
plan to identify appropriate measures to avoid, minimize, or compensate
for potential impacts to resources from a proposed electric
transmission project, consistent with 40 CFR 1508.1(s) or any successor
regulation. A mitigation approach identifies the needs and baseline
conditions of targeted resources, potential impacts from the proposed
project, cumulative impacts of past and reasonably foreseeable future
[[Page 35369]]
disturbances to those resources, and future disturbance trends, then
uses this information to identify priorities for measures across the
relevant area. Such an approach includes full consideration of the
conditions of additionality (meaning that the benefits of a
compensatory mitigation measure improve upon the baseline conditions in
a manner that is demonstrably new and would not have occurred without
the mitigation measure) and durability (meaning that the effectiveness
of a mitigation measure is sustained for the duration of the associated
direct and indirect impacts).
MOU signatory agency means a Federal entity that has entered into
the currently effective memorandum of understanding (MOU) under section
216(h)(7)(B)(i) of the Federal Power Act, such as the interagency MOU
executed in May 2023, titled ``Memorandum of Understanding among the
U.S. Department of Agriculture, Department of Commerce, Department of
Defense, Department of Energy, the Environmental Protection Agency, the
Council on Environmental Quality, the Federal Permitting Improvement
Steering Council, Department of the Interior, and the Office of
Management and Budget Regarding Facilitating Federal Authorizations for
Electric Transmission Facilities.''
NEPA joint lead agency means the Federal entity designated under
Sec. 900.11.
Non-Federal entity means an Indian Tribe, multi-State governmental
entity, State agency, or local government agency.
Participating agencies means:
(1) The Department of Agriculture (USDA);
(2) The Department of Commerce;
(3) The Department of Defense (DOD);
(4) The Department of Energy;
(5) The Environmental Protection Agency (EPA);
(6) The Council on Environmental Quality;
(7) The Office of Management and Budget;
(8) The Department of the Interior (DOI);
(9) The Federal Permitting Improvement Steering Council (FPISC);
(10) Other agencies and offices as the Secretary of Energy may from
time to time invite to participate; and
(11) The following independent agencies, to the extent consistent
with their statutory authority and obligations, and determined by the
chair or executive director of each agency, as appropriate:
(i) The Federal Energy Regulatory Commission (FERC); and
(ii) The Advisory Council on Historic Preservation.
Potentially affected landowner means an owner of a real property
interest that is potentially affected directly (e.g., crossed or used)
or indirectly (e.g., changed in use) by a project right-of-way,
potential route, or proposed ancillary or access site, as identified in
Sec. 900.6.
Project area means the area located between the two end points of
the proposed electric transmission facility containing the study
corridors selected by the project proponent for in-depth consideration
for the proposed project and the immediate surroundings of the end
points of the proposed facility. The project area does not necessarily
coincide with ``permit area,'' ``area of potential effect,'' ``action
area,'' or other terms specific to a certain type of regulatory review.
Project proponent means a person or entity who initiates the IIP
Process in anticipation of seeking a Federal authorization for a
proposed electric transmission project.
Qualifying project means:
(1) A proposed electric transmission line and its attendant
facilities:
(i) That will either be a high-voltage (230 kV or above) line or a
regionally or nationally significant line, as determined by DOE based
upon relevant factors, including but not limited to, reduction in
congestion costs for generating and delivering energy, mitigation of
weather and variable generation uncertainty, and enhanced diversity of
supply;
(ii) Which is expected to be used, in whole or in part, for the
transmission of electric energy in interstate or international commerce
for sale at wholesale;
(iii) Which is expected to require preparation of an environmental
impact statement (EIS) pursuant to NEPA to inform an agency decision on
a Federal authorization;
(iv) Which is not proposed for authorization under section 8(p) of
the Outer Continental Shelf Lands Act (43 U.S.C. 1337(p));
(v) Which is not seeking a construction or modification permit from
FERC pursuant to section 216(b) of the Federal Power Act (16 U.S.C.
824p(b)); and
(vi) Which will not be wholly located within the Electric
Reliability Council of Texas interconnection; or
(2) Any other proposed electric transmission facility that is
approved by the Director under the process set out in Sec. 900.3.
Relevant Federal entity means a Federal entity with jurisdictional
interests that may have an effect on a proposed electric transmission
project, that is responsible for issuing a Federal authorization for
the proposed project, that has relevant expertise with respect to
environmental and other issues pertinent to or potentially affected by
the proposed project, or that provides funding for the proposed
project. The term includes participating agencies. The term includes a
Federal entity with either permitting or non-permitting authority; for
example, those entities with which consultation or review must be
completed before a project may commence, such as DOD for an examination
of military test, training, or operational impacts.
Relevant non-Federal entity means a non-Federal entity with
relevant expertise or jurisdiction within the project area, that is
responsible for issuing an authorization for the proposed electric
transmission project, that has relevant expertise with respect to
environmental and other issues pertinent to or potentially affected by
the proposed project, or that provides funding for the proposed
project. The term includes an entity with either permitting or non-
permitting authority, such as an Indian Tribe, Native Hawaiian
Organization, or State or Tribal Historic Preservation Office with whom
consultation must be completed in accordance with section 106 of the
NHPA prior to approval of a permit, right-of-way, or other
authorization required for a Federal authorization.
Route means an area along a linear path within which a proposed
electric transmission facility could be sited that is:
(1) Wide enough to allow minor adjustments in the alignment of the
proposed facility to avoid sensitive features or to accommodate
potential engineering constraints; and
(2) Narrow enough to allow detailed study.
Stakeholder means any relevant non-Federal entity, interested non-
governmental organization, potentially affected landowner, or other
interested person or organization.
Study corridor means a contiguous area (not to exceed one mile in
width) within the project area where potential routes or route segments
may be considered for further study. A study corridor does not
necessarily coincide with ``permit area,'' ``area of potential
effect,'' ``action area,'' or other defined terms of art that are
specific to types of regulatory review.
Sec. 900.3 Applicability to other projects.
(a) Following the procedures set out in this section, the Director
may
[[Page 35370]]
determine that a proposed electric transmission facility that does not
meet the description of a qualifying project under paragraph (1) of the
definition in Sec. 900.2 is a qualifying project under paragraph (2)
of the definition.
(b) A requestor seeking DOE assistance under this part for a
proposed electric transmission facility that does not meet the
description of a qualifying project under paragraph (1) of the
definition in Sec. 900.2 must file a request for coordination with the
Director. The request must contain:
(1) The legal name of the requester; its principal place of
business; and the name, title, and mailing address of the person or
persons to whom communications concerning the request for coordination
are to be addressed;
(2) A concise description of the proposed facility sufficient to
explain its scope and purpose;
(3) A list of anticipated relevant Federal entities involved in the
proposed facility; and
(4) A list of anticipated relevant non-Federal entities involved in
the proposed facility, including any agency serial or docket numbers
for pending applications.
(c) Not later than 30 calendar days after the date that the
Director receives a request under this section, the Director, in
consultation with the relevant Federal entities, will determine if the
proposed electric transmission facility is a qualifying project under
this part and will notify the project proponent in writing of one of
the following:
(1) If accepted, that the proposed facility is a qualifying project
and the project proponent must submit an initiation request as set
forth under Sec. 900.5; or
(2) If not accepted, that the proposed facility is not a qualifying
project, a justification of that determination, and an indication that
the project proponent must follow the procedures of each relevant
Federal entity that has jurisdiction over the proposed facility without
DOE performing a coordinating function.
(d) In making the determination whether a proposed electric
transmission facility is a qualifying project, the Director may
consider:
(1) Whether the proposed facility would benefit from CITAP Program
coordination;
(2) Whether the proposed facility would result in reduced
congestion costs for generating and delivering energy;
(3) Whether the proposed facility would result in mitigation of
weather and variable generation uncertainty;
(4) Whether the proposed facility would result in an enhanced
diversity of supply; and
(5) Any other relevant factors, as determined by the Director.
(e) For a proposed facility that is seeking a construction or
modification permit pursuant to section 216(b) of the Federal Power
Act, DOE may only consider a request for assistance under this section
if the request under paragraph (b) of this section is consistent with
Delegation Order No. S1-DEL-FERC-2006 or any similar, subsequent
delegation that the Secretary may order.
(f) At the discretion of the MOU signatory agencies, this section
may be applied to a proposed electric transmission facility proposed
for authorization under section 8(p) of the Outer Continental Shelf
Lands Act, if the proposed authorization is independent of any
generation project.
(g) This section does not apply to:
(1) A proposed electric transmission facility proposed to be
authorized under section 8(p) of the Outer Continental Shelf Lands Act
in conjunction with a generation project; or
(2) A proposed electric transmission facility wholly located within
the Electric Reliability Council of Texas interconnection.
Sec. 900.4 Purpose and scope of IIP Process.
(a) The Integrated Interagency Pre-Application (IIP) Process is
intended for a project proponent who has identified potential study
corridors or potential routes and the proposed locations of any
intermediate substations for a proposed electric transmission project.
To the extent possible, the project proponent should use the following
criteria to identify potential study corridors and potential routes:
(1) Potential environmental, visual, historic, cultural, economic,
social, or health effects or harm based on the proposed project or
proposed siting, and anticipated constraints (for instance, pole height
and corridor width based on line capacity to improve safety and
resiliency of the project);
(2) Potential cultural resources, sacred sites, and historic
properties that may be eligible for or listed in the National Register
of Historic Places;
(3) Areas under (or potentially under) special protection by State
or Federal statute and areas subject to a Federal entity or non-Federal
entity decision that could potentially increase the time needed for
project evaluation and siting a transmission line route. Such areas may
include, but are not limited to, properties or sites that may be of
traditional religious or cultural importance to Indian Tribes, National
Scenic and Historic Trails, National Landscape Conservation System
units managed by the Bureau of Land Management (BLM), Land and Water
Conservation Fund lands, National Wildlife Refuges, national monuments,
National Historic Landmarks, units of the National Park System,
national marine sanctuaries, and marine national monuments;
(4) Opportunities to site potential routes through designated
corridors, previously disturbed lands, and lands with existing
infrastructure as a means of potentially reducing impacts and known
conflicts as well as the time needed for affected Federal land managers
to evaluate an application for a Federal authorization if the route is
sited through such areas (e.g., colocation with existing infrastructure
or location on previously disturbed lands, in energy corridors
designated by the Department of the Interior or the Department of
Agriculture under section 503 of the Federal Land Policy and Management
Act (Pub. L. 94-579) or section 368 of the Energy Policy Act of 2005
(Pub. L. 109-58), existing rights-of-way, National Interest Electric
Transmission Corridors designated under Federal Power Act section
216(a), or utility corridors identified in a land management plan);
(5) Potential constraints caused by impacts on military test,
training, and operational missions, including impacts on installations,
ranges, and airspace;
(6) Potential constraints caused by impacts on the United States'
aviation system;
(7) Potential constraints caused by impacts to navigable waters of
the United States; and
(8) Potential avoidance, minimization, offsetting, and compensatory
(onsite and offsite) measures, developed through a mitigation approach
to reduce or offset the potential impact of the proposed project to
resources requiring mitigation.
(b) Participation in the IIP Process is a prerequisite for the
coordination provided by DOE between relevant Federal entities,
relevant non-Federal entities, and the project proponent.
(c) The IIP Process ensures early interaction between the project
proponents, relevant Federal entities, and relevant non-Federal
entities to enhance early understanding by those entities. Through the
IIP Process, the project proponent will provide relevant Federal
entities and relevant non-Federal entities with a clear description of
the proposed electric transmission project, the project proponent's
siting process, and the environmental and community setting being
considered by
[[Page 35371]]
the project proponent for siting the proposed electric transmission
facility; and will coordinate with relevant Federal entities to develop
resource reports that will serve as inputs, as appropriate, into the
relevant Federal analyses and facilitate early identification of
project issues.
(d) The IIP Process is an iterative process anchored by three
meetings: the initial meeting, review meeting, and close-out meeting.
These meetings, defined in Sec. Sec. 900.5, 900.8 and 900.9, are
milestones in the process and do not preclude any additional meetings
or communications between the project proponent and the relevant
Federal entities. The iterative nature of the process is provided for
in procedures for evaluating the completeness of submitted materials
and the suitability of materials for the relevant Federal entities'
decision-making before each milestone.
(e) DOE, in exercising its responsibilities under this part, will
communicate regularly with FERC, electric reliability organizations and
electric transmission organizations approved by FERC, relevant Federal
entities, and project proponents. DOE will use information technologies
to provide opportunities for relevant Federal entities to participate
remotely.
(f) DOE, in exercising its responsibilities under this part, will
to the maximum extent practicable and consistent with Federal law,
coordinate the IIP Process with any relevant non-Federal entities. DOE
will use information technologies to provide opportunities and reduce
burdens for relevant non-Federal entities to participate remotely.
(g) The Director may at any time require the project proponent to
provide additional information necessary to resolve issues raised by
the IIP Process.
(h) Pursuant to 10 CFR 1004.11, any person submitting information
during the IIP Process that the person believes to be confidential and
exempt by law from public disclosure should submit two well-marked
copies, one marked ``confidential'' that includes all the information
believed to be confidential, and one marked ``non-confidential'' with
the information believed to be confidential deleted or redacted. DOE
will make its own determination about the confidential status of the
information and treat it according to its determination, in accordance
with applicable law. The project proponent must request confidential
treatment for all material filed with DOE containing non-public
location, character, and ownership information about cultural
resources.
(i) Pursuant to 10 CFR 1004.13, any person submitting information
during the IIP Process that the person believes might contain Critical
Electric Infrastructure Information (CEII) should submit a request for
CEII designation of information.
Sec. 900.5 Initiation of IIP Process.
(a) Initiation request. A project proponent shall submit an
initiation request to DOE. The project proponent may decide when to
submit the initiation request. The initiation request must include,
based on best available information:
(1) A summary of the proposed electric transmission project, as
described by paragraph (b) of this section;
(2) Associated maps, geospatial information, and studies (provided
in electronic format), as described by paragraph (c) of this section;
(3) A project participation plan, as described by paragraph (d) of
this section; and
(4) A statement regarding the proposed project's status pursuant to
Title 41 of the Fixing America's Surface Transportation Act (FAST-41)
(42 U.S.C. 4370m-2(b)(2)), as described by paragraph (e) of this
section.
(b) Summary of the proposed project. The summary of the proposed
electric transmission project may not exceed 10 single-spaced pages
unless the project proponent requests a waiver of the page limit,
including a rationale for the waiver, and DOE grants the waiver. The
summary must include:
(1) The following information:
(i) The project proponent's legal name and principal place of
business;
(ii) The project proponent's contact information and designated
point(s) of contact;
(iii) Whether the project proponent is an individual, partnership,
corporation, or other entity and, if applicable, the State laws under
which the project proponent is organized or authorized; and
(iv) If the project proponent resides or has its principal office
outside the United States, documentation related to designation by
irrevocable power of attorney of an agent residing within the United
States;
(2) A statement of the project proponent's interests and
objectives;
(3) To the extent available, copies of or links to:
(i) Any regional electric transmission planning documents, regional
reliability studies, regional congestion or other related studies that
relate to the proposed project or the need for the proposed project;
and
(ii) Any relevant interconnection requests;
(4) A description of potential study corridors and routes
identified by the project proponent and a brief description of the
evaluation criteria and methods used by the project proponent to
identify and develop those corridors and routes;
(5) A brief description of the proposed project, including end
points, voltage, ownership, intermediate substations if applicable,
and, to the extent known, any information about constraints or
flexibility with respect to the proposed project;
(6) Identification of any environmental and engineering firms and
sub-contractors under contract to develop the proposed project;
(7) The project proponent's proposed schedule for filing necessary
Federal and State applications, construction start date, and planned
in-service date, assuming receipt of all necessary authorizations; and
(8) A list of anticipated relevant Federal entities and relevant
non-Federal entities, including contact information for each Federal
agency, State agency, Indian Tribe, or multi-State entity that is
responsible for or has a role in issuing an authorization or
environmental review for the proposed project.
(c) Maps, geospatial information, and studies. The initiation
request must include maps, geospatial information, and studies in
support of the information provided in the summary of the proposed
project under paragraph (b) of this section. Maps must be of sufficient
detail to identify the study corridors and potential routes. Project
proponents must provide the maps, information, and studies as
electronic data files that may be readily accessed by relevant Federal
entities and relevant non-Federal entities. The maps, information, and
studies described in this paragraph (c) must include:
(1) Location maps and plot plans to scale showing all major
components, including a description of zoning and site availability for
any permanent facilities; cultural resource location information in
these materials should be submitted in accordance with Sec. 900.4(h);
(2) A map of the project area showing potential study corridors and
potential routes;
(3) Existing data or studies relevant to the summary of the
proposed project; and
(4) Citations identifying sources, data, and analyses used to
develop the summary of the proposed project.
[[Page 35372]]
(d) Project participation plan. The project participation plan,
which may not exceed 10, single-spaced pages, summarizes the outreach
that the project proponent conducted prior to submission of the
initiation request, and describes the project proponent's planned
outreach to communities of interest going forward. A supplemental
appendix may be submitted to provide sufficient detail in addition to
the narrative elements. The project participation plan must include:
(1) A summary of prior outreach to communities of interest and
stakeholders including:
(i) A description of what work already has been done, including
stakeholder and community outreach and public engagement, as well as
any entities and organizations interested in the proposed electric
transmission project;
(ii) A list of environmental, engineering, public affairs, other
contractors or consultants employed by the proponent to facilitate
public outreach;
(iii) A description of any materials provided to the public, such
as environmental surveys or studies;
(iv) A description of the communities of interest identified and
the process by which they were identified;
(v) A general description of the real property interests that would
be impacted by the proposed project and the rights that the owners of
those property interests would have under State law; and
(vi) A summary of comments received during these previous
engagement activities, issues identified by stakeholders, communities
of interest (including various resource issues, differing project
alternative study corridors or routes, and revisions to routes), and
responses provided to commenters, if applicable; and
(2) A public engagement plan, which must:
(i) Describe the project proponent's outreach plan and status of
those activities, including planned future activities corresponding to
each of the items or issues identified in paragraphs (d)(1)(i) through
(vi) of this section, specifying the planned dates or frequency;
(ii) Describe the manner in which the project proponent will reach
out to communities of interest about potential mitigation of concerns;
(iii) Describe planned outreach activities during the permitting
process, including efforts to identify, and engage, individuals with
limited English proficiency and linguistically isolated communities,
and provide accommodations for individuals with accessibility needs;
and
(iv) Discuss the specific tools and actions used by the project
proponent to facilitate public communications and public information,
including whether the project proponent will have a readily accessible,
easily identifiable, single point of contact.
(e) FAST-41 statement. The FAST-41 statement required under
paragraph (a) of this section must specify the status of the proposed
electric transmission project pursuant to FAST-41 at the time of
submission of the initiation request. The statement must either:
(1) State that the project proponent has sought FAST-41 coverage
pursuant to 42 U.S.C. 4370m-2(a)(1); and state whether the Executive
Director of the FPISC has created an entry on the Permitting Dashboard
for the project as a covered project pursuant to 42 U.S.C. 4370m-
2(b)(2)(A); or
(2) State that the project proponent elected not to apply to be a
FAST-41 covered project at this time.
(f) Initiation request determination. Not later than 20 calendar
days after the date that DOE receives an initiation request, DOE shall:
(1) Determine whether the initiation request meets the requirements
of this section and, if not previously determined under Sec. 900.3,
whether the proposed electric transmission facility is a qualifying
project;
(2) Identify the relevant Federal entities and relevant non-Federal
entities and provide each with an electronic copy of the initiation
request; and
(3) Give notice to the project proponent and relevant Federal and
non-Federal entities of DOE's determinations under paragraph (f)(1) of
this section.
(g) Deficiencies. If DOE determines under paragraph (f)(1) of this
section that the initiation request does not meet the requirements of
this section, DOE must provide the reasons for that finding and a
description of how the project proponent may, if applicable, address
any deficiencies in the initiation request so that DOE may reconsider
its determination. If DOE determines under paragraph (f)(1) of this
section that the proposed electric transmission facility is not a
qualifying project, DOE must provide a justification for the
determination and the project proponent may file a request for
coordination with the Director as provided in Sec. 900.3. A project to
site a proposed electric transmission facility that is not a qualifying
project is not eligible for participation in the IIP Process.
(h) Initial meeting. If a project proponent submits a valid
initiation request, DOE, in consultation with the identified relevant
Federal entities, shall convene the IIP Process initial meeting with
the project proponent and all relevant Federal entities notified by DOE
under paragraph (f) of this section as soon as practicable and no later
than 15 calendar days after the date that DOE provides notice under
paragraph (f) that the initiation request meets the requirements of
this section. DOE shall also invite relevant non-Federal entities to
participate in the initial meeting. During the initial meeting:
(1) DOE and the relevant Federal entities shall discuss with the
project proponent the IIP Process, Federal authorization process,
related environmental reviews, any arrangements for the project
proponent to contribute funds to DOE to cover costs incurred by DOE and
the relevant Federal entities in the IIP Process (in accordance with 42
U.S.C. 7278), any requirements for entering into cost recovery
agreements, and paying for third-party contractors under DOE's
supervision, where applicable;
(2) DOE will identify any Federal applications that must be
submitted during the IIP Process, to enable relevant Federal entities
to begin work on the review process, and those applications that will
be submitted after the IIP Process. All application submittal timelines
will be accounted for in the project-specific schedule described in
Sec. 900.7;
(3) DOE will establish all analysis areas necessary for the
completion of resource reports required under Sec. 900.6;
(4) The project proponent shall describe the proposed electric
transmission project and the contents of the initiation request;
(5) DOE and the relevant Federal entities, along with any relevant
non-Federal entities who choose to participate, will review the
information provided by the project proponent and publicly available
information, discuss the study corridors and potential routes
identified by the project proponent, discuss the evaluation criteria
and methods used to identify those corridors and routes and, to the
extent possible and based on agency expertise and experience, identify
any additional criteria for adding or modifying potential routes and
study corridors;
(6) DOE and the relevant Federal entities will discuss, based on
available information provided by the project proponent, any surveys
and studies that may be required for potential routes and completion of
the resource reports, including biological (including
[[Page 35373]]
threatened and endangered species or avian, aquatic, and terrestrial
species and aquatic habitats of concern), visual, cultural, economic,
social, health, and historic surveys and studies.
(i) Feedback to project proponent. Feedback provided to the project
proponent under paragraph (h) of this section does not constitute a
commitment by any relevant Federal entity to approve or deny a Federal
authorization request, nor does the IIP Process limit agency discretion
regarding NEPA review.
(j) Draft initial meeting summary. Not later than 10 calendar days
after the initial meeting, DOE shall:
(1) Prepare a draft initial meeting summary that includes a summary
of the meeting discussion, a description of key issues and information
gaps identified during the meeting, and any requests for more
information from relevant Federal entities and relevant non-Federal
entities; and
(2) Convey the draft summary to the project proponent, relevant
Federal entities, and any relevant non-Federal entities that
participated in the meeting.
(k) Corrections. The project proponent and entities that received
the draft initial meeting summary under paragraph (j) of this section
will have 10 calendar days following receipt of the draft initial
meeting summary to review the draft and provide corrections to DOE.
(l) Final summary. Not later than 10 calendar days following the
close of the 10-day review period under paragraph (k) of this section,
DOE shall:
(1) Prepare a final initial meeting summary by incorporating
received corrections, as appropriate;
(2) Add the final summary to the consolidated administrative docket
described by Sec. 900.10; and
(3) Provide an electronic copy of the summary to all relevant
Federal entities, relevant non-Federal entities, and the project
proponent.
Sec. 900.6 Project proponent resource reports.
(a) Preparation and submission. The project proponent shall prepare
and submit to DOE the 13 project proponent resource reports described
in this section. The project proponent may submit the resource reports
at any time before requesting a review meeting under Sec. 900.8 and
shall, at the direction of DOE, revise resource reports in response to
comments received from relevant Federal entities and relevant non-
Federal entities during the Integrated Interagency Pre-Application
(IIP) Process.
(b) Content. Each resource report must include concise
descriptions, based on the best available scientific and commercial
information, of the known existing environment and major site
conditions. The detail of each resource report must be commensurate
with the complexity of the proposal and its potential for environmental
impacts. Each topic in each resource report must be addressed or its
omission justified. If any resource report topic is not addressed at
the time the applicable resource report is filed or its omission is not
addressed, the report must explain why the topic is missing. If
material required for one resource report is provided in another
resource report or in another exhibit, it may be incorporated by
reference. If outside material is reasonably available for review and
comment, a resource report may incorporate that material by reference
by including a citation to the material and a brief summary of the
material. Consistent with Sec. Sec. 900.1(h) and 900.4(g), the
Director may modify the requirements of this section to reflect
differences in onshore and offshore environments and uses.
(c) Requirements for IIP Process progression. Failure of the
project proponent to provide at least the required initial or revised
content will prevent progress through the IIP Process to the IIP
Process review or close-out meetings, unless the Director determines
that the project proponent has provided an acceptable reason for the
item's absence and an acceptable timeline for filing it. Failure to
file within the accepted timeline will prevent further progress in the
IIP Process.
(d) General requirements. As appropriate, each resource report
shall:
(1) Address conditions or resources that might be directly or
indirectly affected by the proposed electric transmission project;
(2) Identify environmental effects expected to occur as a result of
the proposed project;
(3) Identify the potential effects of construction, operation
(including maintenance and malfunctions), and termination of the
proposed project, as well as potential cumulative effects resulting
from existing or reasonably foreseeable projects;
(4) Identify measures proposed to enhance the environment or to
avoid, minimize, or compensate for potential adverse effects of the
proposed project; and
(5) Provide a list of publications, reports, and other literature
or communications, including agency communications, that were cited or
relied upon to prepare each report.
(e) Federal responsibility. The resource reports prepared by the
project proponent under this section do not supplant the requirements
under existing environmental laws related to the information required
for Federal authorization or consultation processes. The relevant
Federal entities shall independently evaluate the information submitted
and shall be responsible for the accuracy, scope, and contents of all
Federal authorization decision documents and related environmental
reviews.
(f) Resource Report 1--General project description. This report
should describe all expected facilities associated with the project,
special construction and operation procedures, construction timetables,
future plans for related construction, and permits, authorizations, and
consultations that are expected to be required for proposed project.
Resource Report 1 must:
(1) Describe and provide location maps of all facilities to be
constructed, modified, abandoned, replaced, or removed, including
facilities related to construction and operational support activities
and areas such as maintenance bases, staging areas, communications
towers, power lines, and new access roads (roads to be built or
modified), as well as any existing infrastructure proposed to be used
for the project (e.g., connections to existing substations and
transmission, and existing access roads);
(2) Describe specific generation resources that are known or
reasonably foreseen to be developed or interconnected as a result of
the proposed electric transmission project, if any;
(3) Identify facilities constructed by other entities that are
related to the proposed project (e.g., fiber optic cables) and where
those facilities would be located;
(4) Provide the following information for each facility described
under paragraphs (f)(1) through (3) of this section:
(i) A brief description of the facility, including, as appropriate,
ownership, land requirements, megawatt size, construction status, and
an update of the latest status of Federal, State, and local permits and
approvals; and
(ii) Current topographic maps showing the location of the facility;
(5) Provide any communications with the appropriate State Historic
Preservation Offices (SHPOs) and Tribal Historic Preservation Offices
(THPOs) regarding cultural and historic resources in the project area;
[[Page 35374]]
(6) To the extent known, identify the permits, authorizations, and
consultations that are expected to be required for proposed project,
including consultation under section 106 of the NHPA, consultation
under section 7 of the Endangered Species Act of 1973 (Pub. L. 93-205,
as amended, 16 U.S.C. 1531 et seq.), consistency determinations under
the Coastal Zone Management Act (CZMA), and permits under the Clean
Water Act (33 U.S.C. 1251 et seq.) (CWA);
(7) Describe any developments in obtaining authorizations and
permits or completing required consultations for the proposed project
and identify environmental mitigation requirements specified in any
permit or proposed in any permit application to the extent not
specified elsewhere in this resource report or another resource report;
(8) If the project includes abandonment of certain facilities,
rights-of-way, or easements, identify and describe the following:
(i) facilities, rights-of-way, or easements that the project
proponent plans to abandon;
(ii) how the facilities, rights-of-way, or easements would be
abandoned;
(iii) how the abandoned facilities, rights-of-way, and easements
would be restored;
(iv) the owner of the facilities, rights-of-way, or easement after
abandonment;
(v) the party responsible for the abandoned facilities, rights-of-
way, or easement;
(vi) whether landowners were or are expected to be given the
opportunity to request that the abandoned facilities on their property,
including foundations and below ground components, be removed; and
(vii) landowners whose preferences regarding abandoned facility
removal the project proponent does not intend to honor and reasons why
the project proponent does not intend to honor those preferences;
(9) Provide construction timetables and describe, by milepost,
proposed construction and restoration methods to be used in areas of
rugged topography, residential areas, active croplands, sites where the
proposed project would be located parallel to and under roads, and
sites where explosives may be used;
(10) Describe estimated workforce requirements for the proposed
project, including the number of construction spreads, average
workforce requirements for each construction spread, estimated duration
of construction from initial clearing to final restoration, and number
of personnel to be hired to operate the proposed project;
(11) Describe reasonably foreseeable plans for future expansion of
facilities related to the project, including additional land
requirements and the compatibility of those plans with the current
proposal;
(12) Provide the names and mailing addresses of all potentially
affected landowners identified by the project proponent, identify which
potentially affected landowners have been notified by the project
proponent, and describe the methodology used to identify potentially
affected landowners;
(13) Summarize the proposed mitigation approach anticipated by the
project proponent to reduce the potential impacts of the proposed
project to resources warranting or requiring mitigation; and
(14) Describe how the proposed project will reduce capacity
constraints and congestion on the transmission system, meet unmet
demand, or connect generation resources (including the expected type of
generation, if known) to load, as appropriate.
(g) Resource Report 2--Water use and quality. This report should
describe water resources that may be impacted by the proposed project,
describe the potential impacts on these resources, and describe the
measures taken to avoid and minimize adverse effects to such water
resources, where appropriate. Resource Report 2 must:
(1) Identify surface water resources, including perennial
waterbodies, intermittent streams, ephemeral waterbodies, municipal
water supply or watershed areas, specially designated surface water
protection areas and sensitive waterbodies, floodplains, and wetlands,
that would be crossed by a potential route;
(2) For each surface water resource that would be crossed by a
potential route, identify the approximate width of the crossing, State
water quality classifications, any known potential pollutants present
in the water or sediments, and any downstream potable water intake
sources within the applicable analysis area;
(3) Describe typical staging area requirements at surface water
resource crossings and identify and describe each potential surface
water crossing where staging areas are likely to be more extensive and
could require a mitigation approach to address potential impacts to the
water resource;
(4) Provide two copies of floodplain and National Wetland Inventory
(NWI) maps or, if not available, appropriate State wetland maps clearly
showing the study corridors or potential routes and mileposts;
(5) For each wetland crossing, identify the milepost of the
crossing, the wetland classification specified by the USFWS, and the
length of the crossing, and describe, by milepost, wetland crossings as
determined by field delineations using the current Federal methodology;
(6) For each floodplain crossing, identify the mileposts, acres of
floodplains affected, flood elevation, and basis for determining that
elevation;
(7) Describe and provide data supporting the expected impact of the
proposed project on surface and groundwater resources;
(8) Describe and provide data supporting proposed avoidance and
minimization measures as well as protection or enhancement measures
that would reduce the potential for adverse impacts to surface and
groundwater resources, and discuss any potential compensation expected
to be provided for remaining unavoidable impacts to water resources due
to the proposed project;
(9) Identify the location of known public and private groundwater
supply wells or springs within the applicable analysis area;
(10) Identify locations of EPA or State-designated principal-source
aquifers and wellhead protection areas crossed by a potential route;
(11) Discuss the results of any coordination with relevant Federal
entities or non-Federal entities related to CWA permitting and include
any written correspondence that resulted from the coordination; and
(12) Indicate whether the project proponent expects that a water
quality certification (under section 401 of the CWA) will be required
for any potential routes.
(h) Resource Report 3--Fish, wildlife, and vegetation. This report
should identify and describe potential impacts to aquatic and
terrestrial habitats, wildlife, and plants from the proposed project
and discuss potential avoidance, minimization, or compensation
measures, and enhancement or protection measures to reduce adverse
impacts to these resources. Resource Report 3 must:
(1) Describe aquatic habitats that occur in the applicable analysis
area, including commercial and recreational warmwater, coldwater, and
saltwater fisheries and associated significant habitats such as
spawning or rearing areas, estuaries, and other essential fish
habitats;
(2) Describe terrestrial habitats that occur in the project area,
including wetlands, typical wildlife habitats, and rare, unique, or
otherwise significant habitats;
[[Page 35375]]
(3) Identify fish, wildlife, and plants that may be affected by the
proposed project, including species that have commercial, recreational,
or aesthetic value and that may be affected by the proposed project;
(4) Describe and provide the acreage of vegetation cover types that
would be affected by the proposed project, including unique ecosystems
or communities such as remnant prairie or old-growth forest, or
significant individual plants, such as old-growth specimen trees;
(5) Describe the impact of the proposed project on aquatic and
terrestrial habitats, including potential loss and fragmentation;
(6) Describe the potential impact of the proposed project on
Federally listed, candidate, or proposed endangered or threatened
species, State, Tribal, and local species of concern, and those
species' habitats, including the possibility of a major alteration to
ecosystems or biodiversity;
(7) Describe the potential impact of maintenance, clearing, and
treatment of the applicable analysis area on fish, wildlife, and plant
life;
(8) Identify all Federally listed, candidate, or proposed
endangered or threatened species that may be affected by the proposed
project and proposed or designated critical habitats that potentially
occur in the applicable analysis area;
(9) Identify all State, Tribal, and local species of concern that
may be affected by the proposed project;
(10) Identify all known and potential bald and golden eagle nesting
and roosting sites, migratory bird flyways, and any sites important to
migratory bird breeding, feeding, and sheltering within the applicable
analysis areas. These identifications should coincide with the USFWS's
most current range and location maps at the time this resource report
is submitted;
(11) Discuss the results of any discussions conducted by the
proponent to date with relevant Federal entities or relevant non-
Federal entities related to fish, wildlife, and vegetation resources,
and include any written correspondence that resulted from the
discussions;
(12) Include the results of any appropriate surveys that have
already been conducted, as well as plans and protocols for future
surveys. If potentially suitable habitat is present, species-specific
surveys may be required;
(13) If present, identify all Federally designated essential fish
habitat (EFH) that occurs in the applicable analysis area and provide:
(i) Information on all EFH, as identified by the pertinent Federal
fishery management plans, which may be adversely affected by potential
routes;
(ii) The results of discussions with National Marine Fisheries
Service; and
(iii) Any resulting EFH assessments that were evaluated, and EFH
Conservation Recommendations that were provided by the National Marine
Fisheries Service;
(14) Describe potential avoidance, minimization, or compensation
measures, and enhancement or protection measures to address adverse
effects described in paragraphs (h)(5), (6), and (7) of this section;
(15) Describe anticipated site-specific mitigation approaches for
fisheries, wildlife (including migration corridors and seasonal areas
of use), grazing, and plant life;
(16) Describe proposed measures to avoid and minimize incidental
take of Federally listed and candidate species and species of concern,
including eagles and migratory birds; and
(17) Include copies of any correspondence not otherwise provided
pursuant to this paragraph (h) containing recommendations from
appropriate Federal, State, and local fish and wildlife agencies to
avoid or limit impact on wildlife, fish, fisheries, habitats, and
plants, and the project proponent's response to those recommendations.
(i) Resource Report 4--Cultural resources. This report should
describe the location of known cultural and historic resources,
previous surveys and listings of cultural and historic resources, the
potential effects that construction, operation, and maintenance of the
proposed project will have on those resources, and initial
recommendations for avoidance and minimization measures to address
potential effects to those resources. The information provided in
Resource Report 4 will contribute to the satisfaction of DOE's and
relevant Federal entities' obligations under section 106 of the NHPA.
(1) Resource Report 4 must contain:
(i) A summary of known cultural and historic resources in the
applicable analysis area including but not limited to those listed or
eligible for listing on the National Register of Historic Places, such
as properties of religious and cultural significance to Indian Tribes,
and any material remains of past human life or activities that are of
an archeological interest;
(ii) A description of potential effects that construction,
operation, and maintenance of the proposed project will have on
resources identified in paragraph (i)(1)(i) of this section;
(iii) Documentation of the project proponent's initial
communications and engagement, including preliminary outreach and
coordination, with Indian Tribes, indigenous peoples, THPOs, SHPOs,
communities of interest, and other entities having knowledge of,
interest regarding, or an understanding about the resources identified
in paragraph (i)(1)(i) of this section and any written comments from
SHPOs, THPOs, other Tribal historic preservation offices or
governments, or others, as appropriate and available;
(iv) Recommended avoidance and minimization measures to address
potential effects of the proposed project;
(v) Any relevant existing surveys or listings of cultural and
historic resources in the affected environment; and
(vi) Recommendations for any additional surveys needed; and
(vii) A description, by milepost, of any area that has not been
surveyed due to a denial of access by landowners.
(2) The project proponent must update this report with the results
of any additional surveys that the project proponent chooses to
undertake, as identified in in paragraph (i)(1)(vi) of this section,
after the initial submission of this report.
(3) The project proponent must request confidential treatment for
all material filed with DOE containing non-public location, character,
and ownership information about cultural resources in accordance with
Sec. 900.4(h).
(j) Resource Report 5--Socioeconomics. This report should identify
and quantify the impacts of constructing and operating the proposed
project on the demographics and economics of communities in the
applicable analysis area, including minority and underrepresented
communities. Resource Report 5 must:
(1) Describe the socioeconomic resources that may be affected in
the applicable analysis area;
(2) Describe the positive and adverse socioeconomic impacts of the
proposed project;
(3) Evaluate the impact of any substantial migration of people into
the applicable analysis area on governmental facilities and services
and describe plans to reduce the impact on the local infrastructure;
(4) Describe on-site labor requirements during construction and
operation, including projections of the number of construction
personnel who currently reside within the applicable analysis area, who
would commute daily to the site from outside the
[[Page 35376]]
analysis area, or who would relocate temporarily within the analysis
area;
(5) Determine whether existing affordable housing within the
applicable analysis area is sufficient to meet the needs of the
additional population; and
(6) Describe the number and types of residences and businesses that
would be displaced by the proposed project, procedures to be used to
acquire these properties, and types and amounts of relocation
assistance payments.
(k) Resource Report 6--Tribal interests. This report must identify
the Indian Tribes and indigenous communities that may be affected by
the construction, operation, and maintenance of the project facilities,
including those Indian Tribes and indigenous communities that may
attach religious and cultural significance to cultural resources within
the project area. In developing this report, the project proponent
should consider both Indian Tribes with contemporary presence in the
project area and Indian Tribes with historic connections to the area.
To the extent Indian Tribes and indigenous communities are willing to
communicate and share resource information, this report must discuss
the potential impacts of project construction, operation, and
maintenance on Indian Tribes and Tribal interests. This discussion must
include impacts to sacred sites and Treaty rights, impacts related to
enumerated resources and areas identified in the resource reports
listed in this section (for instance, water rights, access to property,
wildlife and ecological resources, etc.), and set forth available
information on any additional, relevant traditional cultural and
religious resources that could be affected by the proposed electric
transmission project that are not already addressed. This resource
report should acknowledge existing relationships between adjacent and
underlying Federal land management agencies and the Indian Tribes. In
developing this report, the project proponent should engage the Federal
land manager early to leverage existing relationships. Specific site or
property locations, the disclosure of which may create a risk of harm,
theft, or destruction of archaeological or Native American cultural
resources and information which would violate any Federal law,
including section 9 of the Archaeological Resources Protection Act of
1979 (Pub. L. 96-95, as amended) (16 U.S.C. 470hh) and section 304 of
the NHPA (54 U.S.C. 307103), should be submitted consistent with Sec.
900.4(h). The project proponent must request confidential treatment for
all material filed with DOE containing non-public location, character,
and ownership information about Tribal resources in accordance with
Sec. 900.4(h).
(l) Resource Report 7--Communities of Interest. This report must
summarize best available information about the presence of communities
of interest. The resource report must identify and describe the
potential impacts of constructing, operating, and maintaining the
proposed electric transmission project on communities of interest; and
describe any proposed mitigation approaches for such impacts or
community concerns. The report must include a discussion of any
disproportionate and/or adverse human health or environmental impacts
to communities of interest.
(m) Resource Report 8--Geological resources and hazards. This
report should describe geological resources that might be directly or
indirectly affected by the proposed electric transmission project and
methods to reduce those effects. The report should also describe
geological hazards that could place project facilities at risk and
methods proposed to mitigate those risks. Resource Report 8 must:
(1) Describe geological resources in the applicable analysis area
that are currently or potentially exploitable, if relevant;
(2) Identify, by milepost, existing and potential geological
hazards and areas of nonroutine geotechnical concern in the applicable
analysis area, such as high seismicity areas, active faults, and areas
susceptible to soil liquefaction; planned, active, and abandoned mines;
karst terrain (including significant caves protected under the Federal
Cave Resources Protection Act (Pub. L. 100-691, as amended) (16 U.S.C.
4301 et seq.)); and areas of potential ground failure, such as
subsidence, slumping, and land sliding;
(3) Discuss the risks posed to the proposed project from each
hazard or area of nonroutine geotechnical concern identified in
paragraph (m)(2) of this section;
(4) Describe how the proposed project would be located or designed
to avoid or minimize adverse effects to geological resources and reduce
risk to project facilities, including geotechnical investigations and
monitoring that would be conducted before, during, and after
construction;
(5) Discuss the potential for blasting to affect structures and the
measures to be taken to remedy such effects; and
(6) Specify methods to be used to prevent project-induced
contamination from mines or from mine tailings along the right-of-way
and discuss whether the proposed project would hinder mine reclamation
or expansion efforts.
(n) Resource Report 9--Soil resources. This report should describe
the soils that could be crossed by the proposed electric transmission
project, the potential effect on those soils, and the proposed
mitigation approach for those effects. Resource Report 9 must:
(1) List, by milepost, the soil associations that would be crossed
by each potential route and describe the erosion potential, fertility,
and drainage characteristics of each association;
(2) For the applicable analysis area:
(i) List the soil series within the area and the percentage of the
area comprised of each series;
(ii) List the percentage of each series which would be permanently
disturbed;
(iii) Describe the characteristics of each soil series; and
(iv) Indicate which soil units are classified as prime or unique
farmland by the USDA, Natural Resources Conservation Service;
(3) Identify potential impacts from: soil erosion due to water,
wind, or loss of vegetation; soil compaction and damage to soil
structure resulting from movement of construction vehicles; wet soils
and soils with poor drainage that are especially prone to structural
damage; damage to drainage tile systems due to movement of construction
vehicles and trenching activities; and interference with the operation
of agricultural equipment due to the probability of large stones or
blasted rock occurring on or near the surface as a result of
construction;
(4) Identify, by milepost, cropland and residential areas where
loss of soil fertility due to trenching and backfilling could occur;
and
(5) Describe the proposed mitigation approach to reduce the
potential for adverse impact to soils or agricultural productivity.
(o) Resource Report 10--Land use, recreation, and aesthetics. This
report should describe the existing uses of land that may be impacted
by the proposed project, and changes to those land uses and impacts to
inhabitants and users that would occur if the proposed electric
transmission project is approved. Resource Report 10 must:
(1) Describe the width and acreage requirements of all construction
and permanent rights-of-way required for project construction,
operation, and maintenance;
(2) List existing rights-of-way that would be co-located with or
adjacent to the proposed rights-of-way (including temporary
construction lines), and any required utility coordination, permits,
[[Page 35377]]
and fees that would be associated as a result;
(3) Identify, preferably by diagrams, existing rights-of-way that
are expected to be used for any portion of the construction or
operational right-of-way, the overlap, and how much additional width is
expected to be required;
(4) Identify the total amount of land to be purchased or leased for
each project facility, the amount of land that would be disturbed for
construction, operation, and maintenance of the facility, and the use
of the remaining land not required for project operation and
maintenance, if any;
(5) Identify the size of typical staging areas and expanded work
areas, such as those at railroad, road, and waterbody crossings, and
the size and location of all construction materials storage yards and
access roads;
(6) Identify, by milepost, the existing use of:
(i) Lands crossed by or adjacent to each project facility; and
(ii) Lands on which a project facility is expected to be located;
(7) Describe:
(i) Planned development within the applicable analysis area that is
either included in a master plan or on file with the local planning
board or the county;
(ii) The time frame (if available) for such development; and
(iii) Proposed coordination to minimize impacts on land use due to
such development;
(8) Identify areas within applicable analysis areas that:
(i) Are owned or controlled by Federal, State or local agencies, or
private preservation groups;
(ii) Are directly affected by the proposed project or any project
facilities or operational sites; and
(iii) Have special designations not otherwise mentioned in other
resource reports.
(iv) Examples of such specially designated areas under this
provision may include but are not limited to sugar maple stands,
orchards and nurseries, landfills, hazardous waste sites, nature
preserves, conservation or agricultural lands subject to conservation
or agricultural easements or restrictions, game management areas,
remnant prairie, old-growth forest, national or State forests, parks,
designated natural, recreational or scenic areas, registered natural
landmarks, and areas managed by Federal entities under existing land
use plans as Visual Resource Management Class I or Class II areas;
(9) Identify Indian Tribes and indigenous communities that may be
affected by the proposed project;
(10) Describe Tribal and indigenous community resources lands,
interests, and established treaty rights that may be affected by the
proposed project;
(11) Identify properties within the project area which may hold
cultural or religious significance for Indian Tribes and indigenous
communities, regardless of whether the property is on or off of any
Federally recognized Indian reservation;
(12) Identify resources within the applicable analysis area that
are included in, or are designated for study for inclusion in, if
available: the National Wild and Scenic Rivers System (16 U.S.C. 1271),
the National Wildlife Refuge System (16 U.S.C. 668dd), the National
Wilderness Preservation System (16 U.S.C. 1131), the National Trails
System (16 U.S.C. 1241-1251), the National Park System (54 U.S.C.
100101-120104), National Historic Landmarks (NHLs), National Natural
Landmarks (NNLs), Land and Water Conservation Fund (LWCF) acquired
Federal lands, LWCF State Assistance Program sites and the Federal
Lands to Parks (FLP) program lands, or a wilderness area designated
under the Wilderness Act (16 U.S.C. 1131-1136); or the National Marine
Sanctuary System, including national marine sanctuaries (16 U.S.C.
1431-1445c-1.) and Marine National Monuments as designated under
authority by the Antiquities Act (54 U.S.C. 320301-320303) or by
Congress; National Forests and Grasslands (16 U.S.C. 1609 et seq); and
lands in easement programs managed by the Natural Resource Conservation
Service or the U.S. Forest Service (16 U.S.C. 3865, et seq.);
(13) Indicate whether the project proponent will need to submit a
CZMA Federal consistency certification to State coastal management
program(s) for the project, as required by NOAA's Federal consistency
regulations at 15 CFR part 930, subpart D;
(14) Describe the impacts the proposed project will have on:
(i) Present uses of land in the applicable analysis area, including
commercial uses, mineral resource uses, and recreational uses,
(ii) Public health and safety;
(iii) Federal, State, and Tribal scientific survey, research, and
observation activities;
(iv) Sensitive resources and critical habitats;
(v) The aesthetic value of the land and its features; and
(vi) Federal, State or Tribal access limitations.
(15) Describe any temporary or permanent restrictions on land use
that would result from the proposed project.
(16) Describe the proposed mitigation approach intended to address
impacts described in paragraphs (o)(12) and (13) of this section, as
well as protection and enhancement of existing land use;
(17) Provide a proposed operations and maintenance plan for
vegetation management, including management of noxious and invasive
species;
(18) Describe the visual characteristics of the lands and waters
affected by the proposed project. Components of this description
include a description of how permanent project facilities will impact
the visual character of proposed project right-of-way and surrounding
vicinity, and measures proposed to lessen these impacts. Project
proponents are encouraged to supplement the text description with
visual aids;
(19) Identify, by milepost, all residences and buildings near the
proposed electric transmission facility construction right-of-way, and
identify the distance of the residence or building from the edge of the
right-of-way and provide survey drawings or alignment sheets to
illustrate the location of the proposed facility in relation to the
buildings;
(20) List all dwellings and related structures, commercial
structures, industrial structures, places of worship, hospitals,
nursing homes, schools, or other structures normally inhabited by
humans or intended to be inhabited by humans on a regular basis within
the applicable analysis area and provide a general description of each
habitable structure and its distance from the centerline of the
proposed project. In cities, towns, or rural subdivisions, houses can
be identified in groups, and the report must provide the number of
habitable structures in each group and list the distance from the
centerline to the closest habitable structure in the group;
(21) List all known commercial AM radio transmitters located within
the applicable analysis area and all known FM radio transmitters,
microwave relay stations, or other similar electronic installations
located within the analysis area; provide a general description of each
installation and its distance from the centerline of the proposed
project; and locate all installations on a routing map; and
(22) List all known private airstrips within the applicable
analysis area and all airports registered with the Federal Aviation
Administration (FAA) with at least one runway more than 3,200 feet in
length that are located within the analysis area. Indicate whether any
transmission structures will exceed a 100:1 horizontal slope (one foot
in height for each 100 feet in distance) from the closest point of the
closest runway. List all airports registered with
[[Page 35378]]
the FAA having no runway more than 3,200 feet in length that are
located within the analysis area. Indicate whether any transmission
structures will exceed a 50:1 horizontal slope from the closest point
of the closest runway. List all heliports located within the analysis
area. Indicate whether any transmission structures will exceed a 25:1
horizontal slope from the closest point of the closest landing and
takeoff area of the heliport. Provide a general description of each
private airstrip, registered airport, and registered heliport, and
state the distance of each from the centerline of the proposed
transmission line. Locate all airstrips, airports, and heliports on a
routing map.
(23) Information made available under paragraphs (o)(9), (10), and
(11) must be submitted consistent with Sec. 900.4(h), including
information regarding specific site or property locations, the
disclosure of which will create a risk of harm, theft, or destruction
of archaeological or Native American cultural resources and information
which would violate any Federal law, including section 9 of the
Archaeological Resources Protection Act of 1979 (Pub. L. 96-95, as
amended) (16 U.S.C. 470hh) and section 304 of the NHPA (54 U.S.C.
307103).
(p) Resource Report 11--Air quality and noise effects. This report
should identify the effects of the proposed electric transmission
project on the existing air quality and noise environment and describe
proposed measures to mitigate the effects. Resource Report 11 must:
(1) Describe the existing air quality in the applicable analysis
area, indicate if any project facilities are located within a
designated nonattainment or maintenance area under the Clean Air Act
(42 U.S.C. 7401 et seq.), and provide the distance from the project
facilities to any Class I area in the project area;
(2) Estimate emissions from the proposed project and the
corresponding impacts on air quality and the environment;
(i) Estimate the reasonably foreseeable emissions, including
greenhouse gas emissions, from construction, operation, and maintenance
of the project facilities (such as emissions from tailpipes, equipment,
fugitive dust, open burning, and substations) expressed in tons per
year; include supporting calculations, emissions factors, fuel
consumption rates, and annual hours of operation;
(ii) Estimate the reasonably foreseeable change in greenhouse gas
emissions from the existing, proposed, and reasonably foreseeable
generation resources identified in Resource Report 1 (see paragraph (f)
of this section) that may connect to the proposed project or
interconnect as a result of the proposed project, if any, as well as
any other modeled air emissions impacts;
(iii) For each designated nonattainment or maintenance area,
provide a comparison of the emissions from construction, operation, and
maintenance of the proposed project with the applicable General
Conformity thresholds (40 CFR part 93);
(iv) Identify the corresponding impacts on communities and the
environment in the applicable analysis area from the estimated
emissions;
(v) Describe any proposed mitigation measures to control emissions
identified under this section; and
(vi) Estimate the reasonably foreseeable effect of the proposed
project on indirect emissions;
(3) Describe existing noise levels at noise-sensitive areas in the
applicable analysis area, such as schools, hospitals, residences, and
any areas covered by relevant State or local noise ordinances;
(i) Report existing noise levels as the a-weighted decibel (dBA)
Leq (day), Leq (night), and Ldn (day-night sound level) and include the
basis for the data or estimates;
(ii) Include a plot plan that identifies the locations and duration
of noise measurements, the time of day, weather conditions, wind speed
and direction, engine load, and other noise sources present during each
measurement; and
(iii) Identify any noise regulations that may be applicable to the
proposed project;
(4) Estimate the impact of the proposed project on the noise
environment;
(i) Provide a quantitative estimate of the impact of transmission
line operation on noise levels at the edge of the proposed right-of-
way, including corona, insulator, and Aeolian noise; and provide a
quantitative estimate of the impact of operation of proposed
substations and appurtenant project facilities on noise levels at
nearby noise-sensitive areas, including discrete tones;
(A) Include step-by-step supporting calculations or identify the
computer program used to model the noise levels, the input and raw
output data and all assumptions made when running the model, far-field
sound level data for maximum facility operation (either from the
manufacturer or from far-field sound level data measured from similar
project facilities in service elsewhere) and the source of the data;
(B) Include sound pressure levels for project facilities, dynamic
insertion loss for structures, and sound attenuation from the project
facilities to the edge of the right-of-way or to nearby noise-sensitive
areas (as applicable);
(ii) Describe the impact of proposed construction activities,
including any nighttime construction, on the noise environment;
estimate the impact of any horizontal directional drilling, pile
driving, or blasting on noise levels at nearby noise-sensitive areas
and include supporting assumptions and calculations;
(5) Based on noise estimates, indicate whether the proposed project
will comply with applicable noise regulations and whether noise
attributable to any proposed substation or appurtenant facility will
exceed permissible levels at any pre-existing noise-sensitive area;
(6) Based on noise estimates, determine whether any wildlife-
specific noise thresholds may have an impact on the proposed project,
such as those thresholds specific to avian species that may be relevant
in significant wildlife areas, if appropriate; and
(7) Describe measures, and manufacturer's specifications for
equipment, proposed to mitigate noise effects and impacts to air
quality, including emission control systems, installation of filters,
mufflers, or insulation of piping and buildings, and orientation of
equipment away from noise-sensitive areas.
(q) Resource Report 12--Alternatives. This report should describe
the range of study corridors that were considered as alternatives
during the planning, identification, and design of the proposed
electric transmission project and compare the environmental impacts of
such corridors and the routes contained in those corridors. This
analysis may inform the relevant Federal entities' subsequent analysis
of their alternatives during the NEPA process. Resource Report 12 must:
(1) Identify all study corridors and routes contained within those
corridors. The report must identify the location of the corridors on
maps of sufficient scale to depict their location and relationship to
the proposed project, and the relationship of the proposed electric
transmission facility to existing rights-of-way;
(2) Discuss the ``no action'' alternative and the potential for
accomplishing the proponent's proposed objectives using alternative
means;
(3) Discuss design and construction methods considered by the
project proponent;
(4) Identify all the alternative study corridors and routes the
project proponent considered in the initial screening for the proposed
project but did not recommend for further study and the reasons why the
proponent chose not to examine such alternatives.
[[Page 35379]]
(5) For alternative study corridors and routes recommended for more
in-depth consideration, the report must:
(i) Describe the potential impacts to cultural and historic
resources for each alternative;
(ii) Describe the environmental characteristics of each
alternative, provide comparative tables showing the differences in
environmental characteristics for the alternatives, and include an
analysis of the potential relative environmental impacts for each
alternative;
(iii) Provide an explanation of the costs to construct, operate,
and maintain each alternative, the potential for each alternative to
meet project deadlines, and technological and procedural constraints in
developing the alternatives; and
(iv) Demonstrate whether and how environmental benefits and costs
were weighed against economic benefits and costs to the public.
(r) Resource Report 13--Reliability, resilience, and safety. This
report should describe the impacts that would result from a failure of
the proposed electric transmission facility, the measures, procedures,
and features that would reduce the risk of failure, and measures in
place to reduce impacts and protect the public if a failure did occur.
Resource Report 13 must:
(1) Discuss events that could result in a failure of the proposed
facility, including accidents, intentional destructive acts, and
natural catastrophes (accounting for the likelihood of relevant natural
catastrophes resulting from climate change);
(2) Describe the reasonably foreseeable impacts that would result
from a failure of the proposed electric transmission facility,
including hazards to the public, environmental impacts, and service
interruptions;
(3) Describe the operational measures, procedures, and design
features of the proposed project that would reduce the risk of facility
failure;
(4) Describe measures proposed to protect the public from failure
of the proposed facility (including coordination with local agencies);
(5) Discuss contingency plans for maintaining service or reducing
downtime;
(6) Describe measures used to exclude the public from hazardous
areas, measures used to minimize problems arising from malfunctions and
accidents (with estimates of probability of occurrence), and identify
standard procedures for protecting services and public safety during
maintenance and breakdowns; and
(7) Describe improvements to reliability likely to result from the
proposed project.
Sec. 900.7 Standard and project-specific schedules.
(a) DOE shall publish, and update from time to time, a standard
schedule that identifies the steps generally needed to complete
decisions on all Federal environmental reviews and authorizations for a
proposed electric transmission project. The standard schedule will
include recommended timing for each step so as to allow final decisions
on all Federal authorizations within two years of the publication of a
notice of intent to prepare an environmental review document under
Sec. 900.9 or as soon as practicable thereafter, considering the
requirements of relevant Federal laws, and the need for robust analysis
of proposed project impacts, early and meaningful consultation with
potentially affected Indian Tribes and engagement with stakeholders and
communities of interest.
(b) During the Integrated Interagency Pre-Application (IIP)
Process, DOE, in coordination with any NEPA joint lead agency and
relevant Federal entities, shall prepare a project-specific schedule
that is informed by the standard schedule prepared under paragraph (a)
of this section and that establishes prompt and binding intermediate
milestones and ultimate deadlines for the review of, and Federal
authorization decisions relating to, a proposed electric transmission
project, accounting for relevant statutory requirements, the potential
route, reasonable alternative potential routes, if any, the need to
assess and address any impacts to military testing, training, and
operations, and other factors particular to the specific proposed
project, including the need for early and meaningful consultation with
potentially affected Indian Tribes and engagement with stakeholders and
communities of interest. DOE may revise the project-specific schedule
as needed to satisfy applicable statutory requirements, allow for
engagement with stakeholders and communities of interest, and account
for delays caused by the actions or inactions of the project proponent.
Sec. 900.8 IIP Process review meeting.
(a) An Integrated Interagency Pre-Application (IIP) Process review
meeting is required for each proposed electric transmission project
utilizing the IIP Process and may only be held after the project
proponent submits a review meeting request to DOE. The project
proponent may submit the request at any time following submission of
the initial resource reports required under Sec. 900.6. The review
meeting request must include:
(1) A summary table of changes made to the proposed project since
the IIP Process initial meeting, including potential environmental and
community benefits from improved siting or design;
(2) Maps of potential routes and study corridors, including the
proposed line, substations, and other infrastructure, as applicable,
with at least as much detail as required for the initiation request
described by Sec. 900.5 and as modified in response to early
stakeholder input and outreach and feedback from relevant Federal
entities and relevant non-Federal entities;
(3) If known, a schedule for completing any upcoming field resource
surveys, as appropriate;
(4) A conceptual plan for implementation and monitoring of proposed
mitigation measures to avoid, minimize, or compensate for effects of
the proposed project, consistent with 40 CFR 1508.1(s) or any successor
regulation. This may include compensatory mitigation measures (offsite
and onsite);
(5) An updated public engagement plan described in Sec.
900.5(d)(2), reflecting actions undertaken since the project proponent
submitted the initiation request and input received from relevant
Federal entities and relevant non-Federal entities;
(6) A listing of:
(i) The dates on which the project proponent filed applications or
requests for Federal authorizations and the dates on which the project
proponent filed revisions to previously filed applications or requests;
and
(ii) Estimated dates for filing remaining applications or requests
for Federal authorization;
(7) Estimated dates that the project proponent will file requests
for authorizations and consultations with relevant non-Federal
entities; and
(8) A proposed duration for each Federal land use authorization
expected to be required for the proposed project, commensurate with the
anticipated use of the proposed electric transmission facility.
(b) Not later than 10 calendar days after the date that DOE
receives the review meeting request, DOE shall provide relevant Federal
entities and relevant non-Federal entities with materials included in
the request and the initial resource reports submitted under Sec.
900.6 via electronic means.
[[Page 35380]]
(c) Not later than 60 calendar days after the date that DOE
receives the review meeting request, DOE shall:
(1) Determine whether the meeting request meets the requirements of
paragraph (a) of this section and whether the initial resource reports
are sufficiently detailed; and
(2) Give notice to the project proponent and relevant Federal and
non-Federal entities of DOE's determinations under paragraph (c)(1) of
this section.
(d) If DOE determines under paragraph (c)(1) of this section that
the meeting request does not meet the requirements of paragraph (a) of
this section or that the initial resource reports are not sufficiently
detailed, DOE must provide the reasons for that finding and a
description of how the project proponent may address any deficiencies
in the meeting request or resource reports so that DOE may reconsider
its determination.
(e) Not later than 15 calendar days after the date that DOE
provides notice to the project proponent under paragraph (c) of this
section that the review meeting request and initial resource reports
have been accepted, DOE shall convene the review meeting with the
project proponent and the relevant Federal entities. All relevant non-
Federal entities participating in the IIP Process shall also be
invited.
(f) During the IIP Process review meeting:
(1) The relevant Federal entities shall discuss, and modify if
needed, the analysis areas used in the initial resource reports;
(2) Relevant Federal entities shall identify any remaining issues
of concern, known information gaps or data needs, and potential issues
or conflicts that could impact the time it will take the relevant
Federal entities to process applications for Federal authorizations for
the proposed electric transmission project;
(3) Relevant non-Federal entities may identify remaining issues of
concern, information needs, and potential issues or conflicts for the
project;
(4) The participants shall discuss the project proponent's updates
to the siting process to date, including stakeholder outreach
activities, resultant stakeholder input, and project proponent response
to stakeholder input;
(5) Led by DOE, all relevant Federal entities shall discuss
statutory and regulatory standards that must be met to make decisions
for Federal authorizations required for the proposed project;
(6) Led by DOE, all relevant Federal entities shall describe the
process for, and estimated time to complete, required Federal
authorizations and, where possible, the anticipated cost (e.g.,
processing and monitoring fees and land use fees);
(7) Led by DOE, all relevant Federal entities shall describe their
expectations for complete applications for Federal authorizations for
the proposed project;
(8) Led by DOE, all relevant Federal entities shall identify
necessary updates to the initial resource reports that must be made
before conclusion of the IIP Process, or, as necessary, following
conclusion of the IIP Process; and
(9) DOE shall present the proposed project-specific schedule
developed under Sec. 900.7.
(g) Not later than 10 calendar days after the review meeting, DOE
shall:
(1) Prepare a draft review meeting summary that includes a summary
of the meeting discussion, a description of key issues and information
gaps identified during the meeting, and any requests for more
information from relevant Federal entities and relevant non-Federal
entities; and
(2) Convey the draft summary to the project proponent, relevant
Federal entities, and any non-Federal entities that participated in the
meeting.
(h) The project proponent and entities that received the draft
review meeting summary under paragraph (g) of this section will have 10
calendar days following receipt of the draft to review the draft and
provide corrections to DOE.
(i) Not later than 10 calendar days following the close of the 10-
day review period under paragraph (h) of this section, DOE shall:
(1) Prepare a final review meeting summary incorporating received
corrections, as appropriate;
(2) Add the final summary to the consolidated administrative docket
described by Sec. 900.10; and
(3) Provide an electronic copy of the summary to the relevant
Federal entities, relevant non-Federal entities, and the project
proponent.
(j) Not later than 10 calendar days following the close of the 10-
day review period under paragraph (h) of this section, DOE shall:
(1) determine whether the project proponent has developed the scope
of its proposed project and alternatives sufficiently for DOE to
determine that there exists an undertaking for purposes of section 106
of the NHPA; and
(2) if the scope is sufficiently developed, initiate consultation
with SHPOs, THPOs, and others consistent with 36 CFR 800.2(c)(4), which
may include authorizing a project proponent, as a CITAP applicant, to
initiate section 106 consultation and providing appropriate
notifications.
(k) After the review meeting and before the IIP Process close-out
meeting described by Sec. 900.9 the project proponent shall revise
resource reports submitted under Sec. 900.6 based on feedback from
relevant Federal entities and relevant non-Federal entities received
during the review meeting and based on any updated surveys conducted
since the initial meeting.
Sec. 900.9 IIP Process close-out meeting.
(a) An Integrated Interagency Pre-Application (IIP) Process close-
out meeting concludes the IIP Process for a proposed electric
transmission project and may only be held after the project proponent
submits a close-out meeting request to DOE. The project proponent may
submit the request at any time following the submission of the updated
resource reports as required under Sec. 900.8. The close-out meeting
request shall include:
(1) A summary table of changes made to the proposed project during
the IIP Process, including potential environmental and community
benefits from improved siting or design;
(2) A description of all changes made to the proposed project since
the review meeting, including a summary of changes made to the updated
resource reports in response to the concerns raised during the review
meeting;
(3) A final public engagement plan, as described in Sec.
900.5(d)(2);
(4) Requests for Federal authorizations for the proposed project;
and
(5) An updated estimated timeline of filing requests for all other
authorizations and consultations with non-Federal entities.
(b) Not later than 10 calendar days after the date that DOE
receives the close-out meeting request, DOE shall provide relevant
Federal entities and relevant non-Federal entities with materials
included in the request and any updated resource reports submitted
under Sec. 900.6 via electronic means.
(c) Not later than 60 calendar days after the date that DOE
receives the close-out meeting request, DOE shall:
(1) Determine whether the meeting request meets the requirements of
paragraph (a) of this section and whether the updated resource reports
are sufficiently detailed; and
(2) Give notice to the project proponent and relevant Federal and
non-Federal entities of DOE's determinations under paragraph (c)(1) of
this section.
(d) If DOE determines that the meeting request does not meet the
[[Page 35381]]
requirements of paragraph (a) of this section or that the updated
resource reports are not sufficiently detailed, DOE must provide the
reasons for that finding and a description of how the project proponent
may address any deficiencies in the meeting request or resource reports
so that DOE may reconsider its determination.
(e) Not later than 15 calendar days after the date that DOE
provides notice to the project proponent under paragraph (c) of this
section that the close-out meeting request and updated resource reports
have been accepted, DOE shall convene the close-out meeting with the
project proponent and all relevant Federal entities. All relevant non-
Federal entities participating in the IIP Process shall also be
invited.
(f) The IIP Process close-out meeting concludes the IIP Process.
During the close-out meeting:
(1) The participants shall discuss the project proponent's updates
to the siting process to date, including stakeholder outreach
activities, resultant stakeholder input, and project proponent response
to stakeholder input; and
(2) DOE shall present the final project-specific schedule.
(g) Not later than 10 calendar days after the close-out meeting,
DOE shall:
(1) Prepare a draft close-out meeting summary; and
(2) Convey the draft summary to the project proponent, relevant
Federal entities, and any non-Federal entities that participated in the
meeting.
(h) The project proponent and entities that received the draft
close-out meeting summary under paragraph (g) of this section will have
10 calendar days following receipt of the draft to review the draft and
provide corrections to DOE.
(i) Not later than 10 calendar days following the close of the 10-
day review period under paragraph (h) of this section, DOE shall:
(1) Prepare a final close-out meeting summary by incorporating
received corrections, as appropriate;
(2) Add the final summary to the consolidated administrative docket
described by Sec. 900.10;
(3) Provide an electronic copy of the summary to all relevant
Federal entities, relevant non-Federal entities, and the project
proponent; and
(4) In the event that the proposed project is not identified as a
covered project pursuant to Sec. 900.5(e), notify the FPISC Executive
Director that the proposed project ought to be included on the FPISC
Dashboard as a transparency project.
(j) DOE and any NEPA joint lead agency shall issue a Notice of
Intent to prepare an environmental review document for the proposed
project within 90 days of the later of the IIP Process close-out
meeting or the receipt of a complete application for a Federal
authorization for which NEPA review will be required, as consistent
with the final project-specific schedule.
(k) DOE shall issue, for each Federal land use authorization for a
proposed electric transmission facility, a preliminary duration
determination commensurate with the anticipated use of the proposed
facility.
Sec. 900.10 Consolidated administrative docket.
(a) DOE shall maintain a consolidated docket of:
(1) All information that DOE distributes to or receives from the
project proponent, relevant Federal entities, and relevant non-Federal
entities related to the Integrated Interagency Pre-Application (IIP)
Process, including:
(i) The IIP initiation request, review meeting request, and close-
out meeting request required by Sec. Sec. 900.5, 900.8, and 900.9;
(ii) The IIP Process final meeting summaries required by Sec. Sec.
900.5, 900.8 and 900.9;
(iii) The IIP Process final resource reports developed under Sec.
900.6;
(iv) The final project-specific schedule developed under Sec. Sec.
900.7 and 900.8;
(v) Other documents submitted by the project proponent as part of
the IIP Process or provided to the project proponent as part of the IIP
Process, including but not limited to maps, publicly available data,
and other supporting documentation; and
(vi) Communications between any relevant Federal or non-Federal
entity and the project proponent regarding the IIP Process; and
(2) All information assembled and used by relevant Federal entities
as the basis for Federal authorizations and related reviews following
completion of the IIP Process.
(b) Federal entities should include DOE in all communications with
the project proponent related to the IIP Process for the proposed
electric transmission project.
(c) DOE shall make the consolidated docket available, as
appropriate, to the NEPA joint lead agency selected under Sec. 900.11;
any relevant Federal or non-Federal entity responsible for issuing an
authorization for the proposed project; and any consulting parties per
section 106 of the NHPA, consistent with 36 CFR part 800. DOE shall
exclude or redact privileged documents, as appropriate.
(d) Where necessary and appropriate, DOE may require a project
proponent to contract with a qualified record-management consultant to
compile a contemporaneous docket on behalf of all participating
agencies. Any such contractor shall operate at the direction of DOE,
and DOE shall retain responsibility and authority over the content of
the docket.
(e) Upon request, any member of the public will be provided
materials included in the docket, excluding any materials protected as
CEII or otherwise required or allowed to be withheld under the Freedom
of Information Act.
Sec. 900.11 NEPA lead agency and selection of NEPA joint lead agency.
(a) For a proposed electric transmission project that is accepted
for the Integrated Interagency Pre-Application (IIP) Process under
Sec. 900.5, DOE shall serve as the NEPA lead agency to prepare an
environmental review document to serve the needs of all relevant
Federal entities. A NEPA joint lead agency to prepare the environmental
review document may also be designated pursuant to this section, no
later than by the IIP Process review meeting.
(b) The NEPA joint lead agency, if any, shall be the Federal entity
with the most significant interest in the management of Federal lands
or waters that would be traversed or affected by the proposed project.
DOE shall make this determination in consultation with all Federal
entities that manage Federal lands or waters traversed or affected by
the proposed project. For a proposed project that would traverse lands
managed by both the USDA and the DOI, DOE will request that USDA and
DOI determine the appropriate NEPA joint lead agency, if any.
Sec. 900.12 Environmental review.
(a) After the Integrated Interagency Pre-Application (IIP) Process
close-out meeting, and after receipt of a relevant application for a
Federal authorization or permit in accordance with the final project-
specific schedule, DOE and any NEPA joint lead agency selected under
Sec. 900.11 shall prepare an environmental review document for the
proposed electric transmission project designed to serve the needs of
all relevant Federal entities.
(b) When preparing the environmental review document, DOE and any
NEPA joint lead agency shall:
(1) Consider the materials developed throughout the IIP Process;
and
(2) Consult with relevant Federal entities and relevant non-Federal
entities.
[[Page 35382]]
(c) DOE, in consultation with any NEPA joint lead agency, is
expected to be responsible for:
(1) Identifying, contracting with, directing, supervising, and
arranging for the payment of contractors, as appropriate, to draft the
environmental review document; and
(2) Publishing the environmental review document and any related
documents.
(d) Each Federal entity or non-Federal entity that is responsible
for issuing a separate Federal authorization for the proposed project
shall:
(1) Identify all information and analysis needed to make the
authorization decision; and
(2) Identify all alternatives that need to be included, including a
preferred alternative, with respect to the authorization.
(e) DOE and any NEPA joint lead agency, in consultation with
relevant Federal entities, shall identify the full scope of
alternatives for analysis, including the no action alternative.
(f) To the maximum extent permitted under law, relevant Federal
entities shall use the environmental review document as the basis for
all Federal authorization decisions on the proposed project. DOE and
the relevant Federal entities shall issue, except where inappropriate
or inefficient, a joint decision document, which will include the
determination by the Secretary of a duration for each land use
authorization issued on the proposed project.
(g) For all proposed projects, DOE shall serve as lead agency for
consultation under the Endangered Species Act (50 CFR 402.07) and
section 106 of the NHPA (36 CFR 800.2(a)(2)) unless the relevant
Federal entities designate otherwise. DOE shall coordinate these
consultation processes with the Federal agency with the most
significant interest in the management of Federal lands or waters that
would be traversed or affected by the proposed project or the
designated lead agency.
Sec. 900.13 Severability.
The provisions of this part are separate and severable from one
another. Should a court hold any provision(s) to be stayed or invalid,
such action shall not affect any other provision of this part and the
remaining provisions shall remain in effect.
[FR Doc. 2024-08157 Filed 4-30-24; 8:45 am]
BILLING CODE 6450-01-P