Rights-of-Way, Leasing, and Operations for Renewable Energy, 35634-35684 [2024-08099]
Download as PDF
35634
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
V. Procedural Matters
DEPARTMENT OF THE INTERIOR
I. Executive Summary
Bureau of Land Management
43 CFR Part 2800
[BLM_HQ_FRN_MO# 4500177145]
RIN 1004–AE78
Rights-of-Way, Leasing, and
Operations for Renewable Energy
Bureau of Land Management,
Interior.
ACTION: Final rule.
AGENCY:
This final rule updates
procedures governing the BLM’s
renewable energy and right-of-way
programs, focusing on two main topics.
The first topic is solar and wind energy
generation rents and fees, implementing
new authority from the Energy Act of
2020 to ‘‘reduce acreage rental rates and
capacity fees, or both, for existing and
new wind and solar authorizations’’ and
making certain findings required by the
statute. The second topic is expanding
agency discretion to process
applications for solar and wind energy
generation rights-of-way inside
designated leasing areas (DLAs). In
addition to these two main topics, this
final rule makes technical changes,
corrections, and clarifications to the
regulations. This final rule will update
the BLM’s procedures governing the
BLM’s administration of rights-of-way
issued under Title V of the Federal Land
Policy and Management Act (FLPMA),
including for solar and wind energy
applications and development
authorizations.
DATES: This rule is effective July 1,
2024.
FOR FURTHER INFORMATION CONTACT:
Jayme Lopez, Interagency Coordination
Liaison, by phone at (520) 235–4581, or
by email at energy@blm.gov for
information relating to the BLM
Renewable Energy programs and
information about the final rule. Please
use ‘‘RIN 1004–AE78’’ in the subject
line. Individuals in the United States
who are deaf, deafblind, hard of hearing,
or have a speech disability may dial 711
(TTY, TDD, or TeleBraille) to access
telecommunications relay services.
Individuals outside the United States
should use the relay services offered
within their country to make
international calls to the point-ofcontact in the United States.
SUPPLEMENTARY INFORMATION:
ddrumheller on DSK120RN23PROD with RULES6
SUMMARY:
I. Executive Summary
II. Background
III. Discussion of Public Comments on the
Proposed Rule
IV. Section-by-Section Discussion
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
In 2021, the Bureau of Land
Management (BLM) initiated
preliminary activities related to
rulemaking through listening sessions
seeking public comment on the BLM’s
potential use of the Energy Act of 2020
(43 U.S.C. 3003) authority to ‘‘reduce
acreage rental rates and capacity fees’’ to
‘‘promote the greatest use of wind and
solar energy resources.’’ In May 2022,
the BLM published BLM Manual section
2806.60 as interim guidance to
implement that authority from the
Energy Act of 2020 pending completion
of this final rule. On June 16, 2023, the
BLM published a proposed rule (88 FR
39726 1) in the Federal Register, that,
among other things, proposed updates
to the BLM’s methodology for
determining acreage rents and capacity
fees for solar and wind energy
development projects, including
providing opportunities for reductions
to rents and fees under the authority of
the Energy Act of 2020. The BLM also
proposed more flexibility in how the
BLM processes applications for solar
and wind energy development inside
DLAs, and updates to how to prioritize
solar and wind energy applications. The
proposed rule also suggested technical
changes, corrections, and clarifications
to the existing right-of-way regulations.
After considering comments on the
proposed rule and other factors, the
BLM prepared this final rule.
II. Background
The BLM’s governing regulations for
rights-of-way, including for solar and
wind energy generation, are found at
Title 43 CFR part 2800. These
regulations were last comprehensively
updated by a final rule published in the
Federal Register on December 19, 2016,
‘‘Competitive Processes, Terms, and
Conditions for Leasing Public Lands for
Solar and Wind Energy Development
and Technical Changes and
Corrections’’ (81 FR 92122). That final
rule built upon existing rights-of-way
regulations and policies to expand
BLM’s ability to responsibly facilitate
solar and wind energy development.
Most recently, the BLM amended
components of 43 CFR part 2800 under
its final rule, ‘‘Update of the
Communications Uses Program, Cost
Recovery Fee Schedules, and Section
512 of FLPMA for Rights-of-Way,’’ (89
FR 25922) on April 12, 2024. That final
rule updated BLM regulations to
1 https://www.federalregister.gov/documents/
2023/06/16/2023-12178/rights-of-way-leasing-andoperations-for-renewable-energy.
PO 00000
Frm 00002
Fmt 4701
Sfmt 4700
enhance the communications uses
program, update its cost recovery fee
schedules, and add provisions
governing the development and
approval of operations, maintenance,
and fire prevention plans and
agreements for rights-of-way for electric
transmission and distribution facilities
(i.e., powerlines). That final rule also
included technical changes to certain
sections that this renewable energy rule
proposed to make changes to, as will be
discussed further in the section-bysection discussion of this final rule.
Solar and Wind Energy Rents and Fees
Title V of FLPMA (43 U.S.C. 1761–
1772) generally requires grant holders,
leaseholders, or both (holders) to ‘‘pay
in advance the fair market value’’ for
use of the public lands, subject to
certain exceptions. The Energy Act of
2020, 43 U.S.C. 3003, introduced a new
exception to FLPMA’s fair market value
requirement, authorizing the Secretary
to ‘‘reduce acreage rental rates and
capacity fees, or both, for existing and
new wind and solar authorizations’’ if
the agency makes certain findings.
These findings can include that the
existing rates ‘‘exceed fair market
value,’’ ‘‘impose economic hardships’’
or ‘‘limit commercial interest in a
competitive lease sale or right-of-way
grant,’’ or ‘‘that a reduced rental rate or
capacity fee is necessary to promote the
greatest use of wind and solar energy
resources.’’ 43 U.S.C. 3003(b)(1)(A)–(C)
and 3003(b)(2).
As reflected in this final rule, the
BLM determined that the changes to the
acreage rents and capacity fees for solar
and wind energy right-of-way
authorizations are needed to ‘‘promote
the greatest use of wind and solar
energy resources’’ and maximize
‘‘commercial interest’’ in lease sales and
right-of-way grants. Reducing the
acreage rent and capacity fee in this
final rule will encourage solar and wind
energy development with a goal of
increasing the share of clean energy that
is part of the United States’ domestic
power infrastructure as authorized by
the Energy Act of 2020 and directed by
Executive Orders 14008 and 14057. This
will be done by decreasing the costs for
developers to construct and operate
solar and wind energy development,
allowing them to increase investments
in new facilities and thus promote
additional development. These changes
will result in the most additional
deployment of solar and wind energy
development (see Regulatory Impact
Analysis 3.1.D). The BLM’s
determination is supported by a
regulatory impact analysis of economic
impacts, public comments received on
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
the proposed rule, and the BLM’s
experience with solar and wind energy
development on public lands.
Reductions in costs will also benefit
smaller-scale projects or projects that
are on the margins of being
economically profitable. Additionally,
the BLM expects that the rule will not
only increase interest among renewable
energy developers to use BLMadministered public lands, but it will
decrease the cost for developers such
that they may be able to invest in
additional wind and solar projects on
Tribal, State, or private lands. Further,
the decrease in cost to developers is
expected to translate, over time, to a
reduction in the average cost per MW of
solar and wind energy, which will make
solar- and wind-generated energy more
competitive with other energy sources
and will stabilize or even reduce the
cost of energy to consumers, even as the
cost of other energy sources may
experience increased volatility.
The BLM also determined that the
authority provided under the Energy
Act of 2020, 43 U.S.C. 3003, supports
two other reductions to the capacity fees
under two potentially qualifying
circumstances: (1) a Domestic Content
reduction when a grant holder or lease
holder demonstrates the use of
American-made iron, steel, construction
materials, or manufactured products in
the construction of the project
consistent with the requirements set
forth in this final rule; and (2) a
reduction for Project Labor Agreements
(PLAs), i.e., when the holder uses PLAs
to hire labor for the development and
construction of a solar or wind
development. The additional, voluntary
reductions offered in this final rule
advance the Energy Act of 2020 goal of
promoting the greatest use of solar and
wind energy resources. First, a Domestic
Content reduction will provide an
incentive to use components made or
manufactured in the United States in
the construction of the solar or wind
energy development project by
offsetting those costs, which, if broadly
adopted, could increase demand for
domestically produced renewable
energy parts and materials and, over the
long term, lead to decreased costs for
parts and materials, decreased reliance
on potentially volatile foreign-sourced
parts and materials, and ultimately
increased economic certainty for and
promotion of wind and solar energy
resources on public lands. Second, the
PLA reduction will incentivize good
labor practices and in turn lead to
responsible and productive
construction, minimize the potential
duration, and improve construction
standards, thereby promoting the
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
greatest use of wind and solar resources.
These reductions will also incentivize
project proponents to advance other
Congressional and Administration goals
that strengthen the use of American
products and manufacturing and the
associated labor markets.
Therefore, reductions in the final rule
that rely upon authority from the Energy
Act of 2020 include an 80 percent
reduction to the MWh rate when setting
the capacity fee and the two additional
reductions to the capacity fee for which
right-of-way holders may qualify: a 20
percent Domestic Content reduction and
a 20 percent PLA reduction. The MWh
rate reduction applies to projects when
they are permitted (or grants or rightsof-way are re-issued under 2806.51(c))
and continues for the life of the grant.
The MWh rate reduction will be 80
percent through 2035, 60 percent for
new authorizations in 2036, 40 percent
for new authorizations in 2037, and 20
percent for new authorizations in 2038
and beyond. Additional information on
the MWh rate is found under the
discussions of §§ 2801.5 and 2806.52(b)
of this preamble, as well as more
broadly under part 2806 of this
preamble.
This final rule also codifies a new
rate-setting methodology for solar and
wind energy development projects.
Under this rule, the BLM will collect
from right-of-way holders the greater of
either an acreage rent or a capacity fee.
The BLM will assess acreage rent by
applying the rate schedule, based on a
survey of values for pastureland from
the National Agricultural Statistics
Service (NASS) Cash Rents Survey, to
the number of acres that the right-ofway authorizes for use. Capacity fees
reflect the value of generating electricity
from solar and wind energy resources,
which are quantified by the number of
megawatt hours (MWh) of electricity
produced from public lands. In this
rule, the BLM has changed the
definition of capacity to move away
from the maximum capacity that a solar
facility could produce and towards
ensuring that the capacity fee reflects
the actual capacity for solar or wind
energy generation of a site covered by a
given right-of-way grant or lease, taking
into consideration environmental or
other factors that may impact generation
capacity of the site, including weather,
servicing, and Acts of God. As provided
in the final rule, the BLM will
determine the capacity fee by
considering the wholesale prices for
major trading hubs serving 11 western
States, and documentation concerning
the price received by the right-of-way
holder under a Power Purchase
Agreement.
PO 00000
Frm 00003
Fmt 4701
Sfmt 4700
35635
The final rule provides that, when
issuing a grant or lease for solar or wind
energy development, or a renewal of
such grant or lease, the BLM will set the
per-acre rate and the MWh rate
(including applicable reductions). The
acreage rent and capacity fee will be
adjusted annually, however, using an
annual adjustment factor set at the
beginning of the grant or lease term.
Upon renewal of a right-of-way, the peracre rate and the MWh rate and
reductions would be updated based on
the then-current rates, as well as any
applicable reductions for which the
right-of-way holder qualifies at that
time.
Existing right-of-way holders may
elect to continue using their current rate
setting methodology, which may be
updated periodically for changes in the
market, or change to the new rate setting
methodology in this final rule.
Otherwise, the new rate setting
methodology would only apply to new
or renewed rights-of-way. If an existing
right-of-way holder elects to change to
the new rate setting methodology, that
methodology will apply until the end of
the right-of-way term.
This final rule bases the capacity fee
for solar and wind energy generation
facilities on actual energy generation at
each facility rather than on nameplate
capacity. The BLM believes this change
more accurately reflects the actual
capacity for energy production of an
individual project based on a
developer’s selection of technology,
project design, and the solar or wind
resource available at a particular site.
This change to the capacity fee indexes
the required payment to the projects’
energy generation, being greater when
the project generates more energy and
less when it generates less.
This rule improves payment
predictability for grant and leaseholders
by revising the key data used for
determining the acreage rent and the
capacity fee—the state-wide pastureland
rent values and the wholesale price of
electricity—at the time the right-of-way
is issued. In doing so, the per-acre and
MWh rates are set for the term of the
right-of-way and only adjusted by the
annual adjustment factor and, in the
case of the capacity fee, by the holder’s
actual annual energy production. See
preamble §§ 2806.50 and 2805.52 for a
more detailed discussion of the BLM’s
proposed methodology for determining
the acreage rent and capacity fee.
Solar and Wind Energy Applications
Inside Designated Leasing Areas
In this final rule, the BLM clarifies
that it will review and process
applications, including on a non-
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
35636
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
competitive basis, for proposed solar
and energy generation rights-of-way
inside DLAs, which are defined at 43
CFR 2801.5(b). The BLM retains
discretion to conduct competitive
processes, either inside or outside of
DLAs, where the authorized officer
decides to do so. In the proposed rule,
the BLM used the terms ‘‘competitive
offer’’ and ‘‘competitive process’’
interchangeably. To provide clarity and
minimize confusion, the final rule uses
only the term ‘‘competitive process’’ to
describe the method by with the BLM
will offer parcels in a competitive
bidding process. To learn more about
BLM’s DLAs, see the 2012 Western
Solar Plan (https://blmsolar.anl.gov/
documents/solar-peis/), which
identified approximately 285,000 acres
of agency preferred development
locations (i.e., DLAs) with high
potential for solar energy production
and low conflicts with other resources
and uses. Subsequently, the BLM
designated approximately 388,000 acres
of preferred development locations for
solar energy in California through the
2016 Desert Renewable Energy
Conservation Plan (https://
blmsolar.anl.gov/documents/drecp/)
and over 192,000 acres of preferred
development locations for solar, wind,
and geothermal energy in Arizona
through the 2017 Restoration Design
Energy Project. Currently, the BLM is in
the process of updating its 2012 Western
Solar Plan to, among other things, make
programmatic planning decisions for
solar development on BLMadministered lands in 11 western states,
including Arizona, California (exclusive
of the area covered by the Desert
Renewable Energy Conservation Plan),
Colorado, Idaho, Montana, Nevada, New
Mexico, Utah, Oregon, Washington, and
Wyoming (See https://
eplanning.blm.gov/eplanning-ui/
project/2022371/510).
Under this final rule, if no
competitive interest exists for a
particular parcel, the BLM may issue
leases without a competitive process.
This change to the rule provides the
BLM with increased flexibility and
discretion to issue grants and leases
through either competitive or noncompetitive processes across all public
lands inside and outside of DLAs,
which is expected to maximize interest
in renewable energy leasing and
accelerate the deployment of solar and
wind energy on the public lands. See
subpart 2809 for a discussion of the
competitive process for solar and wind
energy.
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
Need for the Rule
FLPMA provides the BLM with
comprehensive authority for the
administration and protection of the
public lands and their resources and
directs that the public lands be managed
‘‘on the basis of multiple use and
sustained yield’’ unless otherwise
provided by law (43 U.S.C. 1732(a)).
Further, FLPMA authorizes the BLM to
issue rights-of-way on the public lands
for electric generation systems,
including solar and wind energy
generation systems, and mandates that
the United States receive fair market
value for the use of the public lands and
their resources unless otherwise
provided for by statute (43 U.S.C.
1764(g)).
On December 27, 2020, the Energy
Act of 2020 was enacted, establishing a
minimum goal of ‘‘authoriz[ing]
production of not less than 25 gigawatts
of electricity from wind, solar, and
geothermal energy projects by not later
than 2025’’ on Federal lands. 43 U.S.C.
3004. Current information regarding the
BLM’s approved energy development
projects and number of gigawatts is
available on its website.2 The Energy
Act of 2020 also provides the BLM with
new authority to reduce rates below fair
market value based on specific findings,
including ‘‘that a reduced rental rate or
capacity fee is necessary to promote the
greatest use of wind and solar energy
resources’’ 43 U.S.C. 3003(b)(2). The
BLM has determined that reduced rates
and fees are necessary to promote the
greatest use of wind and solar energy
resources, and this rule seeks to
implement such reductions consistent
with the direction in the Energy Act of
2020.
On January 27, 2021, President Biden
issued Executive Order (E.O.) 14008,
‘‘Tackling the Climate Crisis at Home
and Abroad.’’ Section 207 of E.O. 14008,
titled ‘‘Renewable Energy on Public
Lands and in Offshore Waters,’’
instructs DOI ‘‘to increase renewable
energy production on (public) lands.’’
The changes in this rulemaking will
provide clearer direction for the BLM in
processing proposed renewable energy
right-of-way applications on public
lands while also supporting the goals of
the Energy Act of 2020 and E.O. 14008.
Statutory Authority
Section 310 of FLPMA (43 U.S.C.
1740) authorizes the Secretary to
promulgate regulations to carry out the
purposes of FLPMA and other laws
applicable to public lands. Section 302
2 https://www.blm.gov/programs/energy-andminerals/renewable-energy/active-renewableprojects.
PO 00000
Frm 00004
Fmt 4701
Sfmt 4700
of FLPMA (43 U.S.C. 1732) also
provides comprehensive authority for
the administration and protection of the
public lands and their resources and
directs that the public lands be managed
‘‘under principles of multiple use and
sustained yield,’’ unless otherwise
provided by law (43 U.S.C. 1732(a)).
Sections 501, 504, and 505 of FLPMA
authorize the Secretary to grant rightsof-way on public lands; to issue
regulations governing such rights-ofway and charge rent for such rights-ofway; and to impose terms and
conditions on rights-of-way grants,
respectively (43 U.S.C. 1761, 1764, and
1765). Sections 304 and 504 of FLPMA
(43 U.S.C. 1734(b) and 1764(g)) also
authorize the BLM to collect funds from
right-of-way applicants or holders to
reimburse the agency for its costs
incurred while working on a proposed
or authorized right-of-way. As defined
by FLPMA, the term ‘‘right-of-way’’
includes an easement, lease, permit, or
license to occupy, use, or traverse
public lands (43 U.S.C. 1702(f)). See
Title V of FLPMA (43 U.S.C. 1761–
1772).
The Energy Act of 2020 authorizes the
Secretary to reduce acreage rental rates
and capacity fees if the Secretary makes
certain findings, which can include that
the existing rates ‘‘impose economic
hardships’’ or ‘‘limit commercial
interest in a competitive lease sale or
right-of-way grant,’’ or ‘‘that a reduced
rental rate or capacity fee is necessary
to promote the greatest use of wind and
solar energy resources’’ (43 U.S.C.
3003).
III. Discussion of Public Comments on
the Proposed Rule
This section of the preamble briefly
summarizes broad and general
comments on the proposed rule and the
BLM’s responses. Comment responses
within this section of the preamble have
been grouped and summarized by
category that would apply to one or
more sections of this final rule. You will
find additional comments that are more
specific to sections of this final rule, and
their responses, in Section IV (Sectionby-Section Discussion) of this preamble.
Solar and Wind Energy Rents and
Fees—Part 2806
Summary of Comments: While several
commenters supported the proposal for
reduced rents and fees, other
commenters questioned the need for
reduced rents and fees and requested
more research and discussion to
determine if current costs exceed fair
market value, impose economic
hardships, limit commercial interest, are
not competitively priced, or
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
disincentivize the greatest use of wind
and solar energy resources.
Response: Under the Energy Act of
2020 (43 U.S.C. 3003(b)), Congress
recognized the need to promote wind
and solar energy projects on Federal
lands, giving the Secretary the authority
to reduce acreage rental rates, capacity
fees, or both if she determines that ‘‘the
existing rates (A) exceed fair market
value; (B) impose economic hardships;
(C) limit commercial interest in a
competitive lease sale or right-of-way
grant; or (D) are not competitively
priced compared to other available
land;’’ or that a reduction is ‘‘necessary
to promote the greatest use of wind and
solar energy resources.’’ 43 U.S.C.
3003(b)(1)–(2). The BLM considered
whether capacity fee reductions are
necessary to promote the greatest use of
wind and solar energy resources and has
determined reductions are necessary.
This final rule describes how the
capacity fee reductions will increase
interest in and incentivize wind and
solar energy development on public
lands and thereby accelerate
deployment of renewable energy
resources in the United States. This
final rule also includes changes to the
BLM’s rate-setting methodology that
improve future rate predictability (see
Regulatory Impact Analysis) and reduce
potential for economic hardships.
Summary of Comments: Commenters
suggested that the BLM should not
speculate on the economic impacts of
the proposed rule or requested
additional analysis and use of
additional sources to back up statements
made.
Response: The BLM prepared an
economic analysis for the proposed rule
and then completed a Regulatory Impact
Analysis for this final rule that provides
a transparent analysis of the anticipated
economic consequences for this
rulemaking. This analysis informs the
agency decision, including whether this
rulemaking would accomplish its goals.
For further information on the economic
impacts of this rule, please see the
Regulatory Impact Analysis that is
available with a search at
regulations.gov of this Regulatory
Identifying Number ‘‘1004–AE78.’’
Summary of Comments: Commenters
suggested rents and fees should be
increased rather than decreased due to
the environmental impacts of solar and
wind energy development, as well as
their incompatibility with other uses.
Some further suggested that reducing
fees on projects that are on the margins
of being profitable creates the risk of
projects failing and not being properly
removed and rehabilitated.
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
Response: The BLM disagrees with
the commenters’ suggestion that rents
and fees should be increased rather than
decreased. As explained in more detail
in the previous section on Solar and
Wind Energy Rents and Fees, the Energy
Act of 2020 (43 U.S.C. 3003) provides
the BLM with authority to reduce
acreage rents and capacity fees,
including for the purpose of promoting
the greatest use of wind and solar
resources. The BLM has determined that
reductions in acreage rents and capacity
fees will promote wind and solar
resources and is within the BLM’s
discretion under the Energy Act of 2020.
Further, the BLM has carefully
considered its final rule and concluded
that decreasing rents and fees is
necessary to accomplish the goals set
forth by Congress in the Energy Act of
2020, by the President in E.O. 14008,
and by the Secretary in Secretary’s
Order 3399. Congress set a national goal
for renewable energy production on
Federal land, directing the Secretary to
seek to issue permits authorizing
production of not less than 25 gigawatts
of electricity from wind, solar, and
geothermal energy projects on Federal
land by not later than 2025. 43 U.S.C.
3004. Congress further provided the
Secretary with discretion to reduce the
acreage rental rates and capacity fees,
including where necessary to promote
the greatest use of solar and wind
energy resources on BLM-administered
public lands, which would advance the
goals set by the Energy Act of 2020, as
well as those in E.O. 13990, ‘‘Protecting
Public Health and the Environment and
Restoring Science to Tackle the Climate
Crisis,’’ 86 FR 7037; E.O. 14008,
‘‘Tackling the Climate Crisis at Home
and Abroad,’’ 86 FR 7619; and
Secretary’s Order 3399, ‘‘DepartmentWide Approach to the Climate Crisis
and Restoring Transparency and
Integrity to the Decision-Making
Process.’’ The use of public lands for
energy generation systems is specifically
contemplated in the FLPMA and the
Energy Act of 2020. The BLM considers
the potential environmental effects of
solar or wind energy development when
conducting land use planning and
evaluating project applications, not
when identifying appropriate rental
rates and fees for development projects.
The BLM considers and analyzes
environmental impacts of proposed
energy development, including
appropriate mitigation measures, before
authorizing any such project.
Additionally, the BLM does not believe
there is any correlation between
reductions in capacity fees and the
ability of project proponents to properly
PO 00000
Frm 00005
Fmt 4701
Sfmt 4700
35637
remove and remediate facilities. Any
applicable fee reductions contemplated
in this rule would not alter a project
proponent’s obligations to provide for
adequate bonding associated with
construction and remediation associated
with terminated or abandoned facilities,
as required by 43 CFR 2805.12(b),
2805.20, and 2809.18(e).
Summary of Comments: Commenters
noted that reducing rents and fees for
renewable energy projects on public
lands would economically impact the
developers of similar projects on private
or Tribal lands and could impact
property values.
Response: This final rule changes the
BLM’s administrative processes and
rates for solar and wind energy
development projects on public lands.
While the final rule is intended to
encourage solar and wind energy
development on the public lands, it
would be speculative for the BLM to
attempt to analyze whether and to what
extent there may be secondary impacts
to solar and wind energy development
on private or Tribal property. This is
particularly the case due to the wide
variety of factors that influence
developers’ decisions about whether
and where to pursue solar and wind
energy projects, including, but not
limited to, state, Tribal, and local
permitting requirements, the ability to
enter into power purchase or offtake
agreements, the availability of existing
or proposed transmission, and projectspecific financing considerations.
Notwithstanding these different factors,
the final rule will generally decrease
costs for developers on public lands,
which may permit them to pursue
additional opportunities for
development on Tribal, state, and
private lands and thereby further
promote the greatest use of solar and
wind energy.
Summary of Comments: Some
comments asked about rate changes that
would occur after 2036. Commenters
raised four specific issues that the 2036
rate change causes. First, some
commenters asserted that rates after
2036 would run higher than fair market
value and are therefore a violation of
FLPMA’s requirement that the BLM
charge no more than fair market value.
Second, some commenters asserted that
the Secretary’s authority to reduce rates
under the Energy Act extends beyond
2035, and America’s need for renewable
energy, set by Congressional and
Presidential goals, would require
incentives beyond 2036. Third, some
commenters asserted that the 2036 rate
increase would discourage right-of-way
renewals after that year. Last, some
commenters asserted that the BLM has
E:\FR\FM\01MYR6.SGM
01MYR6
35638
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES6
not adequately explained why it is
choosing to phase out the final rule’s
rate reductions in 2036.
Response: This final rule helps lead
the way to accomplishing the national
goal of a carbon pollution-free
electricity sector by 2035, as highlighted
in Executive Orders 14008 and 14057.
Based on its review of comments, the
BLM has modified the sunset provision
in the final rule. Instead of immediately
transitioning the capacity fee reduction
from 80 percent to 20 percent, the final
rule will lower the reduction by 20
percentage points per year over a period
of three years starting in 2036.
Instituting a phased sunset period to the
80 percent reduction in the capacity fee
is appropriate as the renewable energy
industry may no longer need this
reduction to achieve the greatest use of
wind and solar on public lands, and
progress toward our national goal of a
carbon-pollution free electricity sector
may indicate that a reduction is no
longer warranted. After the sunset
period ends, this final rule will continue
to provide a 20 percent reduction for
solar and wind energy development
projects. The BLM will evaluate
progress towards reaching national goals
and the benefit of the reduction before
2036 and could reinitiate rulemaking to
adjust incentives, including extending
them beyond 2036.
The BLM believes that knowing
beforehand what the rates are for a
facility and the increased predictability
of those rates in the future will improve
the economic certainty for project
development and support a developer’s
or operator’s decisions in power
purchasing, financing, and other
agreements that are necessary for a
successful renewable energy project.
This would be the same for existing
authorization holders who choose to
change to this new rate setting
methodology, as well as for
authorization renewals. Lastly, the BLM
believes that the economics for
renewable energy will continue to
improve over time, and that the
magnitude of such a reduction in 2036
is uncertain.
Lands Available for Solar and Wind
Energy Applications
Summary of Comments: Some
commenters recommended that the
BLM further restrict renewable energy
development outside of solar energy
zones and prohibit such development
close to sensitive habitats or recreation
areas. Commenters stated that
competitive offers should not be
allowed outside of designated zones.
Response: Through the National
Environmental Policy Act (NEPA)
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
process, the BLM considers the
environmental impacts of proposed uses
on the public lands, including solar and
wind energy development, to inform the
BLM decisions to deny, approve, or
approve with modification the proposed
use. The BLM will include terms and
conditions as appropriate to address
resource and environmental impacts of
the project. The BLM also performs
broader analysis to inform whether
certain lands may be made available for
that use through the land use planning
process required by FLPMA, 43 U.S.C.
1712. As described further below, the
BLM’s ongoing planning process to
update to its 2012 Western Solar Plan 3
will amend BLM land use plans in 11
Western States (Arizona, California,
Colorado, Idaho, Montana, Nevada, New
Mexico, Oregon, Utah, Washington, and
Wyoming), or portions thereof, to
identify new priority areas for solar
energy development, variance areas, and
public lands that are excluded from
solar energy development, and to
update requirements that holders must
comply with, including for sensitive
resources and uses that the BLM has
previously authorized. This rulemaking
does not make land use planning
decisions—including determining
whether areas should be excluded from
solar and wind energy development
because they would impact sensitive
habitats or recreation areas—which are
completed under a separate BLM
process. This rulemaking does not
change the competitive process outside
of designated zones, but rather aligns
the competitive process for solar and
wind applications across all areas
within and outside of designated areas.
The BLM believes that where
competitive interest exists—for
example, in the form of multiple
overlapping applications or a high level
of interest in a general area—
competitive processes should be used,
regardless of whether the lands are in a
DLA, to advance the projects that are
most likely to proceed to development.
Summary of Comments: Commenters
noted that the BLM references solar
energy zones from the 2012 Western
Solar Plan in the proposed rule without
discussing that the 2012 Plan is now
under revision and will include an
additional 5 states (Idaho, Montana,
Oregon, Washington, and Wyoming).
Commenters requested that the BLM
coordinate the rulemaking process with
the land use planning effort
accompanying the Western Solar
3 https://www.federalregister.gov/documents/
2022/12/08/2022-26659/notice-of-intent-to-preparea-programmatic-environmental-impact-statementto-evaluate-utility-scale.
PO 00000
Frm 00006
Fmt 4701
Sfmt 4700
Programmatic Environmental Impact
Statement (Western Solar PEIS),
recognizing the various alternatives
being considered and the impacts that
each (Western Solar PEIS vs. proposed
rule) have on the other. Commenters
believed many of the changes in this
rule that refer to decisions or processes
that occur prior to project approval are
currently being considered as part of the
Western Solar PEIS plan amendment
process and may be better suited for the
PEIS.
Response: This rulemaking effort and
the Western Solar PEIS are two separate
actions that complement one another,
but they have different goals, are subject
to different authorities, and will address
different aspects of the ROW
authorization process. This final rule
sets out how the BLM will process
applications and calculate rents, in
order to implement new authorities and
meet National goals established in the
Energy Act and directed by Executive
Order 14008 for both wind and solar
energy development. This rulemaking
does not make land use planning
decisions. In contrast, the plan
amendment process associated with the
Western Solar PEIS focuses exclusively
on solar development on public lands
through a separate process governed by
Section 202 of FLPMA (43 U.S.C. 1712)
and the BLM resource management
planning regulations at 43 CFR 1610, et
seq. to update the BLM’s Western Solar
Plan. That programmatic land use
planning process will consider updating
the BLM’s Western Solar Plan, with a
primary focus on identifying the best
locations for utility-scale solar energy
development, as well as restrictions and
mitigation applicable to such
development, on BLM-managed public
lands in 11 Western States. The BLM’s
land use planning decisions, including
any amendments to plans, will comply
with applicable laws and regulations.
Comment Summary: The BLM
understands from comments it has
received that some believe that the
proposed rule has insufficient analysis
under E.O. 12866. These comments
suggest that the BLM must coordinate
more closely with local governments to
collect economic data.
Response: The BLM appreciates the
interest and engagement from partners
across the multiple landscapes in the
United States, however the BLM
disagrees with comments that additional
coordination must be performed with
local governments for this rulemaking.
This rule governs the BLM’s
administration of applications and
authorizations for solar and wind energy
development projects on public lands.
While the rule does have some financial
E:\FR\FM\01MYR6.SGM
01MYR6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES6
implications with adjustments to the
BLM’s rates, these are transfer payments
as explained more fully in the
Regulatory Impact Analysis
accompanying this final rule and would
not materially affect the resources
available to the American economy. The
BLM will continue to engage with the
public it serves, and its many partners
through BLM’s public processes,
including project-specific analysis and
programmatic and land use planning
analysis through NEPA. No change
made based on these comments.
Need for the Rule
Summary of Comments: Commenters
requested the BLM include a more
meaningful explanation of the necessity
of this rulemaking, including technical
data that supports a need for increased
preferences and favorable treatment for
lease terms. Commenters stated that
solar development is not in line with
FLPMA and does not allow for multiple
use on public lands.
Response: The BLM received new
authority and guidance from Congress
(Energy Act of 2020) and direction from
the President (Executive Order 14008,
among others) to promote renewable
energy generation on public lands. This
rule implements the new authority and
direction for management of the public
lands. The BLM disagrees with the
comments suggesting that solar energy
development is inconsistent with
FLPMA’s multiple use mandate. In
managing the public lands, the BLM is
not required to make every parcel of
land available for all purposes.
Consistent with FLPMA’s multiple use
mandate, the BLM has discretion
through land use planning to identify
areas that are available for, or excluded
from, solar or wind energy development
and to evaluate each proposed solar or
wind energy development through a
site-specific environmental analysis,
including the need for environmental
mitigation, as part of the decisionmaking process prior to issuing a grant
or lease.
Summary of Comments: Other
commenters stated that they believe the
BLM must improve its approach to
facilitating renewable energy
development to meet congressional
goals. Other commenters expressed a
belief that the free market would
provide better solutions to greenhouse
gas emissions and the climate crisis
without authorizing projects on public
land or providing additional incentives
to site projects on public land.
Response: The BLM does not agree
that the free market alone would
provide better solutions to greenhouse
gas emissions and the climate crisis.
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
Additionally, the approach suggested by
commenters would be inconsistent with
direction from Congress and the
President to promote renewable energy
generation on public lands. Particularly,
the Energy Act of 2020, which is aimed
at facilitating and promoting further
development of wind and solar energy
on Federal lands, specifically directs the
BLM to ‘‘issue permits that, in total,
authorize production of not less than 25
gigawatts of electricity from wind, solar,
and geothermal energy projects by not
later than 2025, through management of
public lands and administration of
Federal laws,’’ 43 U.S.C. 3004(b)
(emphasis added). Additionally, as
described above, on January 27, 2021,
President Biden issued E.O. 14008,
‘‘Tackling the Climate Crisis at Home
and Abroad.’’ Section 207 of E.O. 14008,
titled ‘‘Renewable Energy on Public
Lands and in Offshore Waters,’’
instructs DOI ‘‘to increase renewable
energy production on [public] lands.’’
This final rule updates and improves
the BLM’s approach to facilitating
renewable energy development on
public lands based on lessons learned
from implementation of the 2016 rule as
well as changes in National renewable
energy goals and the maturation of
energy market over the past eight years.
This update to the BLM’s rules
improves the BLM’s orderly
administration of public lands and
helps reach the goals set by Congress
and at the direction of the President.
The BLM expects to continue working
with the public to provide better
solutions to resource concerns, such as
greenhouse gas emissions and climate
change, to best manage the public lands
and its resources. Addressing such
resource solutions are not part of this
rulemaking.
Summary of Comments: Commenters
stated that the current market
conditions, state and Federal mandates
and regulations, and demand for green
energy makes reducing fees unnecessary
and that the BLM has failed to explain
why the reductions are necessary.
Response: The changes in this rule
clarify how the BLM will process
renewable energy right-of-way
applications on public lands while
supporting the goals of the Energy Act
of 2020 and direction from the President
(E.O. 14008 and 14057). Through the
BLM’s experience administering solar
and wind energy development rights-ofway, the BLM understands the
importance of stable and predictable
rates for the term of an authorization.
The BLM expects that the rule will help
to meet national renewable goals more
expeditiously. The BLM expects that the
rule will not only increase interest
PO 00000
Frm 00007
Fmt 4701
Sfmt 4700
35639
among renewable energy developers to
use BLM-administered public lands, but
will decrease the cost for developers
such that they may be able to invest in
additional wind and solar projects on
Tribal, State, or private lands. The BLM
explains more fully the need for the rule
and its reductions in the section-bysection discussion portion of this rule
under subpart 2806.
Summary of Comments: A commenter
stated that section 3003(b) of the Energy
Act does not explicitly authorize the
Secretary of the Interior to reduce rightof-way rents and fees below fair market
value and that Congress did not
explicitly repeal, amend, or supersede
FLPMA’s unequivocal fair market value
requirement. They questioned if the
Energy Act supersedes FLPMA’s fair
market value requirement for rights-ofway.
Response: The BLM disagrees with
the comments suggesting that the
Energy Act of 2020 does not authorize
the Secretary to reduce right-of-way
rents and fees below fair market value.
First, a plain reading of the Energy Act
authorizes the Secretary to reduce rental
rates and capacity fees below fair market
value. Specifically, it authorizes the
Secretary to reduce ‘‘acreage rental
rates, capacity fees, and other recurring
annual fees in total’’ for solar and wind
energy generation projects on BLMmanaged public lands under a broad set
of circumstances. Additionally,
Congress presumably understood the
fair market value requirement in
FLPMA, and the discretion in the
Energy Act to reduce rental rates and
capacity fees is as a modification of that
existing requirement. The reductions
authorized in Section 3003 of the
Energy Act would be meaningless if
Congress intended the reductions to be
limited by FLPMA’s general
requirement to collect fair market value
for rights-of-way.
Statutory Authority
Summary of Comments: One
commenter expressed concern that this
proposed rule will set precedent for a
similar issue DOI is trying to address
under the Fluid Mineral Leases and
Leasing process.
Response: This final rule modifies
procedures that are specific to
identifying rental rates and capacity fees
for wind and solar authorizations; it
does not apply to or set a precedent for
other BLM authorizations or processes,
including those under the Mineral
Leasing Act (MLA).
Summary of Comments: Another
commenter requested information about
how this final rule interacts with other
BLM rules and administration
E:\FR\FM\01MYR6.SGM
01MYR6
35640
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES6
directives, including the Conservation
and Landscape Health Rule, Secretary’s
Order 3362, Improving Habitat Quality
in Western Big-Game Winter Range and
Migration Corridors (Feb. 9, 2018), and
BLM Instruction Memorandum 2023–
005 Change 1, Habitat Connectivity on
Public Lands (Nov. 18, 2022).
Response: This final rule updates the
processes used in the BLM’s orderly
administration of the public lands. Any
decisions made in connection with
right-of-way grants following the
procedures laid out in this rule will also
be subject to all other applicable legal
requirements and administrative
directives, including the Conservation
and Landscape Health Rule, Secretary’s
Order 3362, and BLM policies and
guidance.
National Environmental Policy Act
(NEPA)
Comment Summary: Commenters
requested the BLM prepare a NEPA
analysis to evaluate the environmental
effects of the final rule, including
because extraordinary circumstances (43
CFR 46.215) apply and therefore
reliance on a Categorical Exclusion is
not appropriate.
Response: The BLM disagrees with
comments that an environmental
assessment or environmental impact
statement analysis under NEPA is
required, or that extraordinary
circumstances apply to this rulemaking.
The BLM has determined that the
categorical exclusion at 43 CFR
46.210(i), which excludes, ‘‘regulations
. . . that are of an administrative,
financial, legal, technical, or procedural
nature; or whose environmental effects
are too broad, speculative, or conjectural
to lend themselves to meaningful
analysis and will later be subject to the
NEPA process, either collectively or
case-by-case,’’ applies to this final rule.
The BLM has reviewed the
extraordinary circumstances listed in 43
CFR 46.215 and determined that none
applies. This categorical exclusion
documentation is provided on the
BLM’s ePlanning web page at the
following URL: https://
eplanning.blm.gov/eplanning-ui/
project/2016102/510. As such, the final
rule fits within the categorical exclusion
for rules, regulations, or policies to
establish bureau-wide administrative
procedures, program processes, or
instructions. This final rule does not
authorize any project or other on-theground activity and therefore would
have no significant individual or
cumulative effect on the quality of the
human environment. At such time that
specific solar or wind energy
development projects are proposed, the
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
BLM will consider those proposed
actions in compliance with NEPA.
Comment Summary: Some
commenters suggested that there should
not be a requirement of a published
environmental assessment (EA) or
environmental impact statement (EIS)
before foreclosing the opportunity to
hold a competitive offer. Some
commenters believed the BLM should
require analysis of a competitive offer
through an EIS to identify and disclose
the impacts of such an action.
Response: The BLM is not required to
perform environmental analyses on
whether to hold a competitive process;
nonetheless, in § 2809.12(b) the BLM
reserves the right to complete a NEPA
analysis before holding a competitive
process. The BLM does not typically
complete a NEPA analysis for a
competitive leasing process, but at least
one NEPA analysis will be completed
before authorizing solar or wind energy
development. Determining that there
may be competitive interest and
utilizing a competitive process is
administrative and procedural only,
does not trigger the need to prepare an
environmental analysis under NEPA or
have any significant effect on the human
environment, and is simply based on
whether there is adequate interest from
more than one applicant. The BLM
would complete a land use planning
and NEPA analysis were it to change
allocations in a current land use plan to
allocate areas of public lands to either
allow or exclude solar or wind energy
development—a process the BLM is
currently undertaking regarding solar
energy for 11 western states by updating
the 2012 Western Solar Plan through a
PEIS.
For example, in the case of solar or
wind energy development leasing, the
BLM must first identify public lands as
a designated leasing area for solar or
wind energy development through a
land use planning process with an
associated NEPA analysis. If the BLM
receives competitive interest in those
lands, the BLM would hold a
competitive process to determine the
presumptive leaseholder. Alternatively,
the BLM may determine that the NEPA
analysis for a designated leasing area
should be updated to reflect new or
changing circumstances and in turn may
offer such lands competitively to
determine a preferred applicant. Upon
determining the presumptive
leaseholder or preferred applicant, the
BLM would then complete a NEPA
analysis before determining whether to
authorize the wind or solar energy
generation project proposed. For either
the presumptive leaseholder or
preferred applicant, even if the BLM
PO 00000
Frm 00008
Fmt 4701
Sfmt 4700
does not complete a NEPA analysis to
consider whether to hold a competitive
process, the resulting project will be
subject to multiple NEPA analyses
before it is approved.
Additional comments: Additional
comments and their responses are found
in Section IV (Section-by-Section
Discussion) of this preamble.
The BLM is a multiple-use agency,
and solar and wind energy development
is one of the many uses for which the
BLM manages the public lands. While
all comments that the BLM received are
important, this final rule does not
respond to those that are out of scope
for the action the BLM is taking.
Comments that are out of scope for this
rulemaking include those regarding
project-specific considerations, state
laws and authorities, national energy
policies and priorities that do not affect
solar and wind energy or the public
lands, engaging in specific partnerships,
general statements of support or
opposition to the rule which do not
require a detailed response, and
availability and distribution of financial
resources, among others that are not
specific to the BLM’s administration of
solar and wind energy development
applications and rights-of-way and ratesetting.
The BLM will continue to engage with
the public and Tribal, Federal, State,
and local government partners on the
BLM’s management of its public lands,
as appropriate. Subsequent actions that
the BLM may take will be subject to the
policies, laws, and regulations in place
at that time, including those for
consultation, environmental review, and
entering into agreements or partnerships
with others.
IV. Section-by-Section Discussion
43 CFR Part 2800 Rights-of-Way
Authorized Under FLPMA
Part 2800 of the CFR describes
requirements for rights-of-way issued
under Title V of FLPMA. This final rule
revises the per acre rent and per MWh
capacity fee schedules for solar and
wind energy development rights-of-way.
It updates the application process for
public lands and focuses the BLM’s
competitive processes to places where
there is competitive interest. This final
rule also includes the principles for
prioritizing solar and wind energy
applications, establishing criteria for a
‘‘complete application,’’ and corrects or
clarifies existing regulations.
The BLM conducted extensive public
and Tribal outreach on this rule both
prior to its publication as a proposed
rule and during the public comment
period on the proposed rule. Prior to the
E:\FR\FM\01MYR6.SGM
01MYR6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES6
publication of the proposed rule, the
BLM notified Tribes in August 2021 of
its upcoming rule and requested any
comments and concerns that Tribes may
have on such a rule. The BLM then held
three public listening sessions in
September 2021 on its potential use of
the Energy Act of 2020 authority. The
BLM also requested and received
feedback from the public on preferred
alternatives to use of the Energy Act of
2020 authority in its Manual 2806.60,
‘‘Rent,’’ which was later published in
May 2022 after three public listening
sessions and public review and
comment on the draft Manual. The BLM
published its proposed rule in June
2023, receiving nearly 900 comments
after holding three virtual public
meetings. The BLM also sent Tribes
another notice about the rulemaking in
July 2023, requesting Tribal input and
whether there was any interest to
consult on the rule. No Tribes
responded with interest to consult on
the BLM’s rulemaking.
Section 2801.5 What acronyms and
terms are used in the regulations in this
part?
The existing § 2801.5 contains the
acronyms and defines the terms used in
this part of the regulations. The BLM
proposed to remove, revise, and add
acronyms and terms to this section.
Section 2801.5 of this final rule has
some revisions in response to comments
that are discussed further in this section
for each respective revision.
Under this section, several
commenters recommended the BLM
engage relevant stakeholders and
industry experts to ensure definitions
accurately reflect industry practices and
standards. The BLM regularly engages,
and will continue to engage with,
industry; Tribal, Federal, State and local
authorities; and resource experts to
supplement its knowledge about
renewable energy and market
advancements. The BLM sought public
comment on the proposed rule and will
seek public comment on any changes to
its acronyms and terms in future
rulemakings.
The BLM received comments
requesting the BLM consider the full life
cycle of materials, energy inputs and
technology types, and resource and land
use footprints, and suggesting that
labeling all wind and solar energy as
renewable energy is misleading. The
BLM agrees that it should analyze land
use footprints and resource impacts of
proposed projects on public lands.
However, analyzing the full life cycle of
materials, energy inputs, and technology
types are addressed by other parts of the
Federal government where such
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
analysis is within their expertise. The
BLM also believes that for purposes of
this final rule, all solar and wind energy
generation projects are renewable
energy development projects insofar as
they use a natural resource on public
lands that is not depleted to produce
power.
One comment suggested that the BLM
should include a definition for ‘‘current
land use plan’’ to mean ‘‘a document
developed through a formal planning
process to guide the management of
activities and uses of public lands that
has been approved, amended, or
recertified within the past ten years.’’
The BLM has separate rules governing
its land use planning processes found at
43 CFR Chapter V, Subchapter A, that
provides definitions related to the
BLM’s land use planning. Accordingly,
the BLM did not make changes in
response to that comment since they are
out of scope for this rule under 43 CFR
part 2800.
Commenters suggested that the term
‘‘economic hardship’’ under 43 U.S.C.
3003 should be defined in this final rule
and that the BLM should require proof
of economic hardship for rent and fee
reductions. The BLM does not define
economic hardship in this rule as
suggested. Each instance of hardship is
unique to a holder and their
circumstances and will be assessed on
a case-by-case basis. The BLM does not
intend to define hardship
(economically, financially, or otherwise)
so as not to unintentionally preclude
reasonable requests to consider
hardship.
Commenters stated that the proposed
rule uses unclear language and is
inconsistent with underlying resource
management plans, agency guidance,
and regulatory frameworks, and
requested the BLM use more specific
language such as pastureland,
rangeland, habitat, or other terminology
to denote the uses of the landscape. The
BLM disagrees with the commenters’
suggestion that the proposed rule uses
unclear language and that the rule
should include other definitions in this
final rule. The BLM’s use of
‘‘pastureland rents’’ comes from the
name of the survey data used as the
basis in determining the acreage rent in
this final rule: The NASS Survey of
Pastureland Rents. This is a newer
source of data from NASS that was not
available in the original 2012 Western
Solar Plan or when the BLM
promulgated its 2016 rule for solar and
wind energy and has not yet carried
through to other guidance materials
from the BLM. It is appropriate for the
BLM to use this terminology in
describing the data used and its source
PO 00000
Frm 00009
Fmt 4701
Sfmt 4700
35641
in the regulations. Future BLM guidance
and actions would include this
terminology as appropriate.
Commenters requested the BLM settle
on one standard term (‘‘preferred
renewable energy development areas’’)
for the preferred renewable energy
project locations to avoid conflicts with
other resources and uses. Commenters
also suggested that the definitions for
‘‘variance areas’’ and ‘‘exclusion areas’’
should be added to the rule. The BLM
understands the interest in defining
such terms and has already done so in
its land use planning efforts, such as the
ongoing Solar Energy PEIS effort to
update the 2012 Western Solar Plan.
The BLM believes these terms are best
identified and defined as part of the
land use planning process and is not
making any changes to this rule due to
comments.
Paragraph (a) of this final rule
provides for the acronyms and
paragraph (b) provides for the terms
used in this part. The final rule would
remove, revise, and add certain terms to
the BLM’s acronyms and definitions
found in part 2800.
This final rule adds the acronym
‘‘FLPMA’’ to paragraph (a) meaning the
Federal Land Policy and Management
Act of 1976, as amended (43 U.S.C. 1701
et seq.). This acronym replaces the term
‘‘Act’’ from paragraph (b), providing
clarity as to which act the BLM is
referencing.
The BLM received no substantive
comments on replacing the term ‘‘Act’’
with ‘‘FLPMA,’’ and therefore this final
rule makes no changes to the proposed
rule.
This final rule removes definitions of
‘‘Megawatt (MW) capacity fee,’’ ‘‘Net
capacity factor,’’ ‘‘Megawatt hour
(MWh) price,’’ ‘‘Rate of return,’’ and
‘‘Hours per year.’’ The BLM no longer
charges a megawatt capacity fee based
on solar and wind energy generation
facility nameplate capacity; definitions
related to the nameplate capacity fee are
removed. The BLM did not make
changes to the definitions in the final
rule.
Some commenters noted
inconsistencies related to the terms
‘‘Rate of Return’’ and ‘‘Hours per year.’’
Commenters pointed out that the
proposed rule stated that these terms
would be removed from § 2801.5(b),
noting the paragraph numbering for the
Federal Register instructions were
confusing whether the terms were
removed or not. The BLM agrees with
commenters and has revised the Federal
Register instructions, removing the
proposed instruction number vi,
‘‘removing paragraphs (1) and (2) in the
term ‘‘Megawatt rate’’ and redesignating
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
35642
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
paragraphs (3) and (4) as paragraphs (1)
and (2). There are no paragraphs for the
revised term, and removing the
instructions is consistent with the
proposed definition. The BLM did not
make any other changes to this
definition in the final rule.
This final rule adds the term
‘‘Capacity fee’’ to mean the fee based on
the amount of electricity produced from
solar or wind energy resources on the
public lands. This is consistent with the
BLM’s change implementing a capacity
fee that is based on electricity
production. There were no substantive
comments on the term, and the BLM did
not make changes to this definition in
the final rule.
The BLM includes in this final rule a
new term ‘‘Domestic Content reduction’’
to define the circumstances in which a
holder meets the domestic content
criteria and thus qualifies for a fee
reduction. This final rule includes
changes to the term for ‘‘domestic
content’’ to mean an item or product
that qualifies for the Buy America
preference as set forth in Section 70914
of the Build America, Buy American
(BABA) Act, Public Law 117–58, 135
Stat. 429, §§ 70901–70927 (Nov. 15,
2021), and implementing guidance at 2
CFR part 184. The final rule modifies
the definition for ‘‘domestic content’’
from the definition of ‘‘domestic end
product,’’ as that term is used in Section
52.225–1 of the Federal Acquisition
Regulations (FAR) (48 CFR 52.225–1) in
the proposed rule, to the criteria for
‘‘domestic content preference’’ provided
in the BABA Act and 2 CFR part 184.
As described below, the qualifying
definition in this final rule offers clarity
and consistency among Federal
programs regarding what constitutes
domestic content and therefore is
appropriate to apply to determine when
a holder may obtain a fee reduction as
identified under § 2806.52(b).
The BLM has determined that offering
a Domestic Content reduction will
further promote the greatest use of solar
and wind resources because it will
support the development of secure,
reliable domestic supply chains while
also reducing economic hardships for
developers. As discussed in the
preamble to the proposed rule,
uncertainty in global supply chain
dynamics, as seen in recent years, can
delay deployment of solar and wind
energy development projects on public
lands (88 FR 39726, 39740–39742). By
offsetting some of the costs of
domestically sourced parts and
materials, the Domestic Content
reduction will insulate developers from
global supply chain shocks of all kinds
by reducing the economic dependence
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
of developers on global supply chains
and will also support the efforts of
domestic suppliers. In this way, the
proposed Domestic Content reduction
supports the transition to more reliable
domestic supply chains that will, in
turn, increase interest in developing
solar and wind energy projects
throughout the country, including on
public lands (43 U.S.C. 3003(b)(1)(C)),
and thereby would promote the
development of solar and wind energy
resources on public lands (43 U.S.C.
3003(b)(2)).
Similar to the BLM’s use in the
proposed rule of a definition for Buy
American based on section 52.225–1(b)
of the FAR, this final rule’s use of the
term ‘‘domestic content,’’ following the
BABA Act and 2 CFR part 184,
identifies the components of projects
through categories—iron or steel
products, manufactured products, or
construction material—that must be
produced or manufactured in the United
States in order to qualify for the
Domestic Content reduction. The BABA
Act applies to Federal financial
assistance funds for ‘‘infrastructure
projects,’’ which require the use of
material produced in the United States.
The Office of Management and Budget
(OMB) published its final guidance
implementing the BABA Act on August
23, 2023, under 2 CFR part 184.
Generally, under 2 CFR 184.4(e), a
‘‘domestic content’’ preference would
apply to three separate product
categories: (i) iron or steel products; (ii)
manufactured products; and (iii)
construction materials. The OMB’s
guidance defines each of these
categories and makes clear how a
proponent satisfies the categorical
requirements to demonstrate that the
components of an infrastructure project
meet the domestic content standards.
This final rule uses the term ‘‘domestic
content’’ as a catch-all term to refer to
items for which the holder might satisfy
the Domestic Content reduction based
on the definitions established 2 CFR
part 184.
Some commenters suggested that the
proposed Buy American definition
should be revised to reflect eligibility
for the reduction to mimic the guidance
published by the Treasury Department
and Internal Revenue Service for the
domestic content bonus credit from
section 13701 of the Inflation Reduction
Act (IRA), 117 Public Law 169, 136 Stat.
1818 (Aug. 16, 2022). Other commenters
requested the BLM utilize a domestic
content definition that incentivizes the
use of domestically manufactured core
solar components, as laid out in Section
13502 of the Inflation Reduction Act.
Commenters also urged the BLM to
PO 00000
Frm 00010
Fmt 4701
Sfmt 4700
refine its approach and apply more
robust origin standards to its domestic
content proposal.
The BLM has considered the various
comments suggesting different
definitions for what constitutes
American-made products for the
purposes of this reduction. In response
to this public input, the BLM has
changed from the FAR definition to the
BABA Act (and implementing guidance
at 2 CFR part 184) definition for the
domestic content preference. The BLM
is aware that the Treasury Department
and Internal Revenue Service have
issued guidance about the domestic
content bonus under the Inflation
Reduction Act for clean energy projects
and facilities that meet American
manufacturing and sourcing
requirements. However, that guidance
describes an intent to propose
regulations that have not yet been
finalized. This final rule’s definition for
domestic content aligns with definitions
in other Federal programs with
oversight over domestic products and
content. This approach will promote
consistency among these Federal
programs, reducing the potential for
unintended consequences resulting
from conflicting definitions. As noted
above, the BABA Act definition focuses
on construction materials and
components for infrastructure projects
and is closely aligned with the type of
projects covered in this final rule.
The final rule revises the term ‘‘grant’’
to reflect that solar or wind energy
leases are not covered under the
definition. The change provides clarity
for where the BLM will issue a solar or
wind energy grant and where a solar or
wind energy lease will be issued.
Commenters suggested the term
‘‘lease’’ is unnecessary and to use
‘‘grants’’ instead, as the difference
between a lease and a grant under the
proposed rule is the location of a rightof-way either inside or outside a DLA.
As identified in the BLM’s 2012
Western Solar Plan, leases will be
issued in areas designated for leasing
under the relevant land use plan. The
BLM disagrees with these comments
and retains the distinction between
solar and wind energy grants and leases
in this final rule based on location of
their issuance. The BLM did not make
any change to this definition in the final
rule.
This final rule adds the term
‘‘Capacity fee’’ to mean the fee based on
the amount of electricity produced from
solar or wind energy resources on the
public lands. This is consistent with the
BLM’s change implementing a capacity
fee that is based on electricity
production. There were no substantive
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
comments on the term, and the BLM did
not make changes to this definition in
the final rule.
The final rule revises the definition of
the term ‘‘Megawatt hour (MWh) rate’’
to mean the five-calendar-year average
of the annual weighted average
wholesale prices per MWh for major
trading hubs serving the 11 western
states of the continental United States.
This revision is consistent with the
BLM’s change to implement a capacity
fee for solar and wind energy
development projects.
Some commenters were unclear
whether the BLM had revised the
definition of ‘‘Megawatt hour (MWh)
rate’’ in the existing regulations, as
§ 2801.5(b) currently does not define
that term. Commenters presumed that
the BLM proposes to revise the existing
definition of ‘‘Megawatt rate.’’ The BLM
understands the confusion raised by
these comments. The BLM revises the
term ‘‘Megawatt rate’’ to ‘‘Megawatt
hour (MWh) rate’’ in this final rule,
consistent with the change to
implement a capacity fee for solar and
wind energy development projects. The
BLM did not make any other changes to
this definition in the final rule.
This final rule revises the term
‘‘Reasonable costs’’ to be consistent with
the rule change replacing the words
‘‘the Act’’ with the acronym ‘‘FLPMA.’’
There were no substantive comments on
the term, and the BLM did not make
changes to this definition in the final
rule.
‘‘Renewable Energy Coordination
Office (RECO)’’ is added in this final
rule to mean one of the National, State,
district, or field offices established by
the Secretary under 43 U.S.C. 3002(a)
that is responsible for implementing a
program to improve Federal permitting
coordination with respect to eligible
projects on covered land and such other
activities as the Secretary determines
necessary. There were no substantive
comments on the term, and the BLM did
not make changes to this definition in
the final rule.
This final rule includes the new term
‘‘solar or wind energy development’’ to
mean the use of public lands to generate
electricity from solar or wind energy
resources on public lands. This
definition clarifies that the term ‘‘energy
development’’ refers to uses of public
lands that directly involve the
generation of electricity on public lands.
This definition clarifies which right-ofway grants and leases are subject to the
conditions in Section 50265(b)(1) of the
IRA, which apply to ‘‘a right-of-way for
wind or solar energy development on
Federal land.’’
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
Commenters suggested revising the
definition of ‘‘solar or wind energy
development’’ to include language from
the BLM’s recent Instruction
Memorandum 2023–036, Inflation
Reduction Act Conditions for Issuing
Rights-of-Way for Solar or Wind Energy
Development (April 23, 2023), according
to which solar or wind energy
development ‘‘does not include sitetesting, communication sites,
transmission lines, gen-tie lines,
pipelines, roads, installation of batteries
and other energy storage systems, or
other uses that might indirectly support
energy production or transmission.’’
The BLM does not agree that adding
additional language to the definition is
necessary for this final rule. This rule
and the BLM’s policies were written to
complement each other in how the BLM
administers applications and rights-ofway for such projects. The BLM did not
make a change to this definition in the
final rule.
This final rule adds ‘‘Solar and wind
energy lease’’ to mean any right-of-way
issued under Title V of FLPMA within
an area identified in a BLM land use
plan as a DLA. Any right-of-way not
issued within an area identified as a
DLA would be a grant. The BLM
received comments on this term, which
are discussed with regard to the
definition of ‘‘grant’’ in this final rule.
The BLM did not make changes to this
definition in the final rule.
Section 2801.6 Scope
Section 2801.6 describes the scope of
43 CFR part 2800’s applicability.
Paragraph (a)(1) of this final rule
includes the additional language ‘‘or
leases’’ describing that this part applies
to both authorization types: grants and
leases.
A comment requested the following
language be added to § 2801.6 Scope:
‘‘Applications for transportation or
utility right-of-way crossing
conservation system units, national
recreation areas, or national
conservation areas in Alaska are subject
to the provisions of Title XI of the
Alaska National Interest Lands
Conservation Act and 43 CFR part 36.’’
This rule focuses on the BLM’s
generally applicable process for
administering applications and rightsof-way for solar and wind energy
development projects on the public
lands. It does not modify or amend
other applicable statutory or regulatory
requirements, and the BLM would
comply with all such requirements
during the process set forth in this rule.
The BLM made no changes to this
section in the final rule based upon
public comments.
PO 00000
Frm 00011
Fmt 4701
Sfmt 4700
35643
Section 2801.9 When do I need a grant
or lease?
Section 2801.9 explains when a grant
or lease is required for systems or
facilities located on public lands.
Paragraph (d) of this final rule extends
the term for solar or wind energy
development authorizations up to 50
years, and authorizations for other uses
that support solar or wind energy
development, to up to 50 years, and
make other technical changes.
Paragraph (d)(3) provides that solar or
wind energy development facilities
authorized with a grant or lease may be
issued for up to 50 years (plus initial
partial year of issuance). Paragraph
(d)(4) provides that energy storage
facilities that are authorized separate
from an energy generation facility are
authorized with a right-of-way grant for
up to 50 years. Paragraph (d)(6) provides
that electric transmission lines with a
capacity of 100 kV or more are
authorized with a right-of-way grant for
up to 50 years. The BLM did not make
a change to this section of the final rule.
Commenters raised concerns with a
50-year authorization term for large
development projects because, they
suggested, the longer the public lands
are occupied by a wind or solar project
the longer it will likely take for those
lands to fully recover after removing the
project. Commenters also suggested that
the longer-term authorization may
unreasonably occupy the public lands
with a solar or wind energy
development when preferable or newer
energy technology could be deployed
there.
The BLM disagrees with comments
that assert the increase of the maximum
term of an authorization from 30 years
to 50 years is inappropriate because
preferable technology may be desired at
that location in the future. The BLM
acknowledges that recovery of impacts
might be greater for a 50-year right-ofway term. However, the BLM will
analyze the environmental impacts of
each proposed project, including the
end of project life activities such as
reclamation and restoration of public
lands, under NEPA, and will consider
the appropriate term for each proposed
right-of-way, before deciding whether to
approve for deny a proposed right-ofway for energy development.
Additionally, BLM notes that most of
the ground-disturbing impacts of solar
or wind development come during the
construction phase, so the
environmental effects of a 50-year
authorization are therefore likely to be
similar to the effects of a 30-year
authorization with respect to recovery.
Any such impacts, however, will be
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
35644
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
considered on a case-by-case basis, in
compliance with NEPA, when the BLM
evaluates each proposed project.
Through this process, the BLM will
consider the reasonably foreseeable use
of public lands, including the
technology proposed by an applicant
and the environmental consequences of
that use, when deciding whether and for
what duration to authorize solar or wind
energy development on the public
lands.
Some commenters argued against
increasing the maximum term length for
a right-of-way and expressed concerns
about the economic and environmental
impacts and the lifespan of energy
generation equipment. Commenters
suggested that a longer term to an
authorization may not be appropriate
due to the shorter lifespans of solar
panels and wind turbines (30 years for
solar and 20–25 years for wind), and
that a shorter initial term, like the
current 30-year term, instead of 50 years
may be more suitable.
The BLM understands the concerns
raised by commenters regarding the
proposal to increase the maximum term
length for solar and wind energy
development authorizations. In the
BLM’s experience, the lifespan of solar
and wind energy projects has been
increasing over time as the technologies
advance. When the BLM last updated its
rules for solar and wind energy in 2016,
the lifespan of a solar or wind project
was approximately 20 years. The 30year term was appropriate for such a
length, considering the amount of time
necessary to construct a project and
then the expected time to decommission
and reclaim and restore the public lands
during the authorization term. With
increasing lifespans of solar and wind
equipment, a longer-term right-of-way is
appropriate. See recent Berkeley
National Laboratory, Results from a
Survey of U.S. Wind Industry
Professionals,4 and the Department of
Energy’s, Photovoltaics End-of-Life
Action Plan,5 for a discussion of wind
and solar energy project lifespans.
However, the BLM has made changes
to other parts of the rule to address the
commenters’ concerns about dedicating
public lands for up to 50 years to certain
projects or uses that, over time, may
become less efficient, see a significant
decrease in production, or become
entirely inactive. These changes also
address concerns about public lands
being used unlawfully for purposes
4 https://emp.lbl.gov/publications/benchmarkinganticipated-wind-project.
5 https://www.energy.gov/sites/default/files/202203/Solar-Energy-Technologies-Office-PV-End-ofLife-Action-Plan_0.pdf.
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
other than those identified in the ROW
grant (e.g., a former solar or wind
generating site being used for equipment
storage). In particular, the changes
impose conditions aimed at ensuring
diligent operations on the public lands,
see § 2805.12(c)(8). These are in
addition to the BLM’s existing diligent
development requirements under
§ 2805.12(c)(7).
Commenters suggested that the BLM
evaluate changes to the environment or
technology during the term of an
authorization after it has been approved.
The BLM did not adopt this suggestion.
Once the BLM issues a final decision,
the BLM would only re-address
technological changes or environmental
impacts during the term of an
authorization if the BLM undertakes a
new decision-making process, such as
in response to a ROW holder’s proposed
change in technology. The BLM’s
original analysis for a proposed facility
considers the environmental effects of
the facility and technology proposed by
the applicant for the term of the
proposed authorization, informing the
BLM’s decision to deny, approve, or
approve with modification the proposed
project. Any subsequent changes in
equipment used at the site that would
result in changes to environmental
impacts that may occur after the BLM
issues its decision, would be analyzed at
the time the BLM considers issuing a
new decision, based on the relevant
information available at that time. The
BLM may complete a new decisionmaking process to adjust the terms and
conditions of the authorization under
existing § 2805.15(e) under certain
circumstances, such as a change to
legislation or regulations, when
necessary to protect public safety, an
environmental change (e.g., new
threatened or endangered species
listing), or if proposed changes to
technology may result in additional or
different environmental impacts.
One comment requested clarification
on how § 2801.9 may be modified based
on outcomes of the ongoing update to
the Western Solar Plan. The analysis of
environmental impacts of energy
development and decisions made in
updating the Western Solar Plan do not
affect this final rule, which that
provides BLM procedures and
requirements when administering
applications and authorizations for solar
and wind energy development projects.
Some comments suggested that
proposed energy storage facilities and
proposed energy generation facilities
should be reviewed in separate NEPA
documents due to differences in fire risk
and toxicity concerns. While it is
beyond the scope of this rulemaking to
PO 00000
Frm 00012
Fmt 4701
Sfmt 4700
speculate as to how the BLM will
comply with NEPA when evaluating
individual projects, the BLM agrees that
energy storage facilities may have
environmental impacts that are distinct
from those posed by energy generation
facilities. Nevertheless, the BLM can
prepare a single NEPA document to
evaluate impacts from energy generation
facilities and energy storage facilities
and may find it appropriate to do so in
certain circumstances.
Subpart 2802—Lands Available for
FLPMA Grants or Leases
The BLM proposed to revise the title
of subpart 2802 to include ‘‘or leases’’
to clarify for readers that public lands
are available for both grants and leases,
consistent with other revisions in this
rule regarding leases. No comments
were received on this, and the BLM did
not make changes to the final rule.
Section 2802.11 How does the BLM
designate right-of-way corridors and
DLAs?
Section 2802.11 explains how the
BLM designates right-of-way corridors
and DLAs through its land use planning
process. This section includes a nonexhaustive list of factors the BLM could
consider when designating such areas
under its land use planning process
described in 43 CFR part 1600. Other
technical changes in § 2802.11(b)
improve readability and consistency
between the BLM’s regulatory authority
under part 2800 and its statutory
authority under FLPMA. The BLM did
make changes to this section of the final
rule.
Paragraph (b)(1) is unchanged from
the proposed rule and includes Tribal
land use plans that BLM reviews for
consistency when it is developing,
amending, or revising a land use plan in
accordance with Section 202(c)(9) of
FLPMA (43 U.S.C. 1712(c)(9)).
Paragraphs (b)(10) and (b)(11) add
criteria that the BLM may consider
when designating new leasing areas for
solar and wind energy. Paragraph (b)(10)
adds ‘‘access to electric transmission,’’
and paragraph (b)(11) provides for
consideration of relatively large areas
where energy development is feasible
and there is a low potential for conflict
due to environmental, cultural, and
other relevant criteria, including
assessing the demand for new or
expanded areas; applying
environmental, cultural, and other
screening criteria; and analyzing
proposed areas through the land use
planning process described in part 1600.
The BLM received comments about
whether the BLM’s proposal to carry
forward three of the four criteria from
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
the 2012 Western Solar Plan is
consistent with other BLM planning
actions. The BLM carried these three
criteria forward from the 2012 Western
Solar Plan, which is consistent with
other BLM plans identifying solar and
wind energy development areas.
Some commenters suggested that the
BLM redesignate proposed paragraph
(b)(11) as paragraph (b) and redesignate
existing paragraphs (b)–(d) as newly
designated paragraphs (c)–(e). The BLM
did not change the rule due to this
comment. Reorganizing the paragraphs
as suggested would be confusing to a
reader as considerations for solar energy
would no longer be located together in
one subparagraph. The BLM did revise
paragraph (b)(11) to clarify that the
factors BLM considers include ‘‘whether
there are areas’’ consistent with
revisions under paragraph (b).
One comment requested that wording
be amended to ‘‘clarify that BLM may
require sharing a gen-tie right of way
subject to reasonable terms.’’ The term
‘‘gen-tie’’ refers to a generation
interconnect transmission line that
connects the original source electric
generation (for the purposes of this rule,
a wind or solar energy development) to
the transmission system. These gen-tie
lines are typically less than 5 miles long
and require a right-of-way grant if they
cross public lands. The BLM retains
authority under 43 CFR 2805.15(b) to
allow or not allow such common use of
the right-of-way.
Commenters suggested that the BLM
alter the language of proposed
§ 2802.11(b), which identifies factors or
criteria that the BLM may consider
when designating an area of public land
as a right-of-way corridor or a DLA.
Some commenters recommended
replacing the proposed term ‘‘may’’ with
‘‘must.’’ Other commenters suggested
expressly incorporating all of the
considerations listed in 43 U.S.C.
1712(c), which governs criteria for
consideration by BLM when it prepares
land use plans, to this section. Other
commenters suggested that the BLM add
transmission and electric infrastructure
to the list of criteria or factors. Finally,
some commenters agreed with the
language in the proposed rule, which
provides a non-exclusive list of factors
or criteria that the BLM may consider
when designating a corridor or a DLA.
After considering comments on this
section, the BLM did make some
changes to this paragraph in the final
rule. While § 2802.11(b) provides
examples of criteria that the BLM may
consider, some of the listed criteria
might not be relevant in all cases, and
the BLM may consider additional
factors or criteria as appropriate.
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
Further, the BLM’s land use planning
regulations, 43 CFR 1600, provide
additional direction for complying with
the requirements of Section 202 of
FLPMA, 43 U.S.C. 1712. The BLM did
not add transmission and electric
infrastructure to the list of criteria or
factors because the proposed rule
already included ‘‘access to electric
transmission,’’ which is retained as a
criterion or factor in the final rule.
However, the BLM revised paragraph (b)
to replace ‘‘factors the BLM may
consider include, but are not limited to,
the following’’ to read as ‘‘the BLM may
consider various factors, including’’ to
clarify what the BLM considers when
designating such areas.
Commenters suggested that adding
three criteria to a list of other criteria for
the BLM to consider may create
confusion. Some commenters supported
the BLM adding paragraphs (b)(10) and
(b)(11) to provide more detail of what
and how the BLM considers when
designating new leasing areas. Other
commenters requested the BLM evaluate
criteria for designating exclusion areas
in addition to the criteria for designating
DLAs and right-of-way corridors. The
BLM believes that adding the three
additional criteria for consideration
when designated corridors and leasing
areas is appropriate and provides for
transparency when the BLM begins its
land use planning processes to
designate leasing areas. The BLM does
not agree that exclusion criteria are
appropriate when identifying DLAs.
However, paragraph (d) of the existing
regulations provides broad discretion
for the BLM to identify areas where the
BLM will not allow rights-of-way,
which may include criteria to identify
exclusion areas during the land use
planning process. During the land use
planning process, the BLM engages
Federal, Tribal, State, and local
government partners and the public to
inform and clarify the factors analyzed
when considering whether to designate
exclusion areas. Including these criteria
in the final rule will minimize the
confusion that may arise in the future.
Some comments requested that the
final rule include additional criteria for
designating exclusion and avoidance or
variance areas. Commenters suggested
that including these criteria would
encourage the appropriate designation
of such areas and thus focus on
processing right-of-way applications
only in areas where development is best
suited. The BLM disagrees with
commenters that additional criteria for
designating exclusion and avoidance or
variance areas should be included in the
final rule. Such criteria do not need to
be included in the final rule and are
PO 00000
Frm 00013
Fmt 4701
Sfmt 4700
35645
better suited for policy (e.g., instruction
memoranda), which can be
implemented consistent with this rule
and other applicable regulatory
authority and environmental analysis,
while also providing appropriate
flexibility in the process. Further,
exclusion criteria are based on the
environmental impacts of a program on
the public lands, which are identified
through a NEPA analysis, such as the
ongoing Western Solar PEIS that is
updating the 2012 Western Solar Plan.
Lastly, this final rule updates its
prioritization principles under 2804.35,
which were not in place in 2012 with
the Western Solar Plan. The BLM
believes that with the robust public
engagement, prioritization principles,
and other preliminary application
review meetings, holding a variance
process is not necessary in
administering applications for solar and
wind energy development.
Section 2803.10 Who may hold a grant
or lease?
Section 2803.10 provides the criteria
for who may hold a grant or lease. In
this final rule, the BLM clarifies that a
holder who is of legal age and
authorized to do business in one State
must also meet this requirement in each
other State in which the right-of-way
grant they seek is located. No comments
were received on this section, and the
BLM did not make changes to this
section of the final rule.
Section 2803.12 What happens to my
grant if I die?
In the notice of proposed rulemaking
for this rule, the BLM proposed to add
new paragraph (a) and redesignate
existing paragraphs (a) and (b) as
paragraphs (b) and (c). This final rule
does not carry forward those proposed
revisions because another final rule
included revisions that addressed those
concerns. The BLM’s final rule ‘‘Update
of the Communications Uses Program,
Cost Recovery Fee Schedules, and
Section 512 of FLPMA for Rights-ofWay,’’ (89 FR 25922) [April 12, 2024]
updated § 2803.12 to remove reference
to applications in the section title and
paragraph (a).
This final rule retitles this section and
revises paragraphs (a) and (b) to include
‘‘or lease’’ clarifying that this section
applies to both grants and leases.
Paragraph (b) of this final rule
replaces the word ‘‘distributee’’ with
‘‘receiver’’ to improve clarity to readers
that when the BLM distributes a grant
or lease, the instrument would be
received by the holder. This final rule
also includes the provision that
unqualified receivers of a right-of-way
E:\FR\FM\01MYR6.SGM
01MYR6
35646
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES6
must comply with all terms, conditions,
and stipulations.
One comment suggested that the BLM
clarify paragraph (b) to state that
distribution will take place under state
law in the state where the grant or lease
is located. Including this suggested
change could be inaccurate and
potentially unenforceable. The BLM’s
rules should not dictate distribution of
a lease as an inheritable interest in all
instances.
Section 2804.12 What must I do when
submitting my application?
Section 2804.12 explains what an
applicant must do when submitting a
right-of-way application. The BLM
proposed changes to paragraphs (c) and
proposed to add paragraphs (f) and (j).
The BLM did make a change to this
section of the final rule.
Paragraph (c) provides for additional
requirements for solar and wind energy
development or short-term rights-ofway. Paragraph (c)(1) requires payment
of an application filing fee for solar and
wind energy development and shortterm applications as an initial payment
toward cost recovery payments. The
BLM will refund the balance of the
application filing fee if it exceeds the
processing costs. Paragraph (c)(1) is
revised for readability and now reads
‘‘payment toward cost recovery’’ instead
of ‘‘payment towards cost recovery.’’
Paragraph (c)(2) requires payment of
additional reasonable costs in addition
to application filing fees. See existing
§ 2804.14 of this part for further
information on reasonable costs in
processing an application. Payment of
category 6 cost recovery fees—which are
based on full costs and are collected if
the BLM has determined that processing
efforts will take more than 64 hours to
complete—may be reduced by the
application filing fee that is paid when
submitting an application.
Some comments requested lower fees
for application submittal. Another
comment suggested that the BLM keep
the application fee until all ‘‘reasonable
costs’’ are paid before any refund is
given. Under the existing regulations,
application filing fees are a payment of
reasonable costs for the United States to
process an application and are intended
to discourage applicants from
unnecessarily applying for more land
than is reasonable for a solar or wind
energy development. As updated by this
final rule, these application filing fees
continue to be a payment of reasonable
costs and may now clearly be applied to
the processing fees, such as through a
cost recovery agreement. Any
overpayment of these costs may be
reimbursed to the applicant or carried to
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
cover the inspection and monitoring of
the right-of-way, if authorized. Entering
into a cost recovery agreement requires
action by the BLM and applicant to
complete, including the prioritization of
an application under § 2804.35 by the
BLM and payment of reasonable costs
identified by the BLM in a cost recovery
agreement.
Multiple comments suggested the
BLM issue a cost recovery agreement
within a certain timeframe, such as 30
days of receiving the required
information. The BLM agrees that it is
important for the BLM to be responsive
to applicants who have provided the
required information under this section.
The proposed rule added paragraph (j)
providing that an application is
complete when an applicant submits the
required information under this section.
Upon receiving a complete application,
the BLM would determine what cost
recovery amounts would be necessary,
and whether that should be under a cost
recovery agreement. See § 2804.14 for
further information. The BLM would
notify an applicant within 30 days
pursuant to § 2804.25(d) whether
processing their application will take
longer than 60 calendar days and what
the expected processing timeframe is for
the application. Section 2804.19 of the
BLM’s right-of-way regulations provides
that the BLM and applicant work
together to establish and issue the cost
recovery agreement; the length of that
process can vary widely based on a
number of variables including project
complexity, analysis of the needs from
a cost recovery agreement, and needed
inputs from the developer. As noted
under the previous comment response,
entering into a cost recovery agreement
requires action by the BLM and
applicant to complete, including
prioritization under § 2804.35 by the
BLM and payment of reasonable costs
identified by the BLM in a cost recovery
agreement.
Section 2804.12(f) of this final rule
clarifies that the BLM may require
additional information at any time
while processing an application.
Additional information may be
necessary, such as environmental
resource data. The BLM will issue a
deficiency notice pursuant to existing
§ 2804.25(c) to inform applicants of
additional information requirements.
Comments requested that the BLM
provide clear application requirements
and limit the BLM’s ability to request
additional information beyond those
requirements. The BLM believes that the
existing rules clearly state what is
required for applications under 2804.10,
What Should I do before I file my
application?; in § 2804.11, Where do I
PO 00000
Frm 00014
Fmt 4701
Sfmt 4700
file my grant application?; and as
updated by this final rule, § 2804.12,
What must I do when submitting my
application? Paragraph (f) of this final
rule provides that BLM may request
additional information while processing
an application. Additional information
may be requested under 2804.25(c) after
an application is determined to be
complete pursuant to added paragraph
(j) of this final rule.
Paragraph (j) describes that a
complete application meets or addresses
the requirements of § 2804.12, as
appropriate for the application
submitted. Some comments asked the
BLM to clarify the definition of
‘‘complete application’’ in paragraph (j).
The BLM believes that new paragraph (j)
clearly describes what a complete
application is. Upon satisfying the
requirements of this section, the BLM
will provide the applicant notice in
writing that the application is complete.
Some commenters suggested that the
BLM provide a determination of
application completeness within
specified timeframes to promote a
timelier application process. The BLM
agrees that it is important to remain
diligent in processing an application.
However, the BLM did not propose to
implement any timeframes for
determining an application is complete
as this section of the rules applies to
applications for all rights-of-way, not
just solar or wind energy applications.
Reasonable expectations for timely and
diligent application requirements will
vary depending on the complexity of
processing a certain type of system or
use on the public lands.
Section 2804.14 What is the processing
fee for a grant application?
The BLM recently published its final
rule ‘‘Update of the Communications
Uses Program, Cost Recovery Fee
Schedules, and Section 512 of FLPMA
for Rights-of-Way’’ (89 FR 25922) [April
12, 2024]. In that final rule, the BLM
updated its address within this section.
The proposed updates that the BLM
included in this rulemaking are no
longer necessary. No comments were
received, and the BLM did not make a
change to this section in this final rule.
Section 2804.22 How will the
availability of funds affect the timing of
the BLM’s processing?
Section 2804.22 of this final rule
clarifies how the availability of funds
may affect the BLM’s schedule for
processing an application. Paragraph (a)
clarifies that when the BLM is
processing an application, it will not
continue to process the application until
funds become available or the applicant
E:\FR\FM\01MYR6.SGM
01MYR6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES6
elects to pay full actual costs under
§ 2804.14(f). Paragraph (b) provides that
the BLM may deny an application after
90 days if it has requested reasonable
costs for processing an application and
the proponent has failed to provide
funds for reimbursement. The BLM did
not change this section of the final rule.
One commenter supported denying
applications for which fees had not been
paid. Such a procedure, the commenter
suggested, would disincentivize
applicants from submitting applications
that they do not intend to diligently
process. While the BLM will not deny
an application without cause, as
described in more detail under
§ 2804.26, the BLM agrees that failure to
diligently pursue an application,
including unfunded application cost
recovery agreements, and incomplete
applications, among other reasons are
good cause for denying an application.
Denying applications for these reasons
would deter applicants from submitting
applications for projects that they do not
intend to diligently pursue. Paragraph
(c) of this final rule provides that funds
paid towards the cost recovery
agreement for a project may not be
refundable. Such funds would be those
identified in the cost recovery
agreement for hiring additional staff or
contractors and agreed to by the
applicant or right-of-way holder.
Some comments supported the idea of
cost recovery agreements that would
allow the BLM to hire additional staff or
contractors to aid in application
processing and reduce processing times.
This requirement helps ensure that
there is available funding to the United
States for reasonable costs of the
government, including those BLM
hiring and contracting decisions made
to support processing applications.
Section 2804.23 What costs am I
responsible for when the BLM decides to
use a competitive process for my
application?
Section 2804.23 of the final rule
describes what costs an applicant is
responsible for when the BLM decides
to use a competitive process. Paragraph
(b) requires, for cost recovery processing
categories one through four, payment of
cost recovery processing fees as if the
other applications had not been filed.
Paragraph (c) clarifies who is
responsible for processing costs within
processing category six.
The BLM did not make a change to
this section of the final rule.
One comment suggested the language
be changed to read, ‘‘What costs am I
responsible for if the BLM decides to
use a competitive process for my
application?’’ The BLM considered this
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
change in title to the section and
believes that the proposed naming of
this section is clear with respect to what
costs the applicant will be responsible
for when the BLM determines it will use
a competitive process.
Section 2804.25 How will the BLM
process my application?
In the final rule, the BLM revised
§ 2804.25(c) to add that, if an applicant
fails to comply with a deficiency notice
under this section, the BLM may deny
the application. To ensure that
developers proceed diligently after
entering into a cost recovery agreement,
§ 2804.25(c)(1) requires applicants to
‘‘commence any required resource
surveys or inventories within one year
of the request date, unless otherwise
specified by the BLM.’’ If the applicant
fails to comply with a deficiency notice
under that provision, the BLM may
deny the application. See
§ 2804.26(a)(9). To clarify that the BLM
retains the discretion to deny an
application where the applicant does
not proceed diligently, the final rule
adds to § 2804.25(c): ‘‘Failure to meet
requirements under this section may
result in the BLM denying your
application pursuant to § 2804.26.’’
This added provision clarifies that the
BLM retains the discretion to deny an
application where the applicant does
not proceed diligently. This change is
consistent with changes made to
§ 2809.10(e) regarding when the BLM
will no longer hold a competitive
process. Together these amendments
give the industry the certainty it needs
to proceed with projects while retaining
the BLM’s discretion to deny an
application or offer lands competitively
if the applicant does not proceed
diligently. In that way, these
amendments balance the BLM’s
obligations to incentivize renewable
energy development on public lands
and to recover a fair return for U.S.
taxpayers.
In this section, the BLM proposed
removing a mandatory public meeting
that is unique to solar and wind energy
rights-of-way applications and is in
addition to other public participation
that would occur as part of the BLM’s
environmental review process.
Paragraph (e)(2) describes public
meeting requirements for solar or wind
energy right-of-way applications. In the
final rule, paragraph (e)(2) provides that
the BLM may hold a local public
meeting if there is no other public
meeting or opportunity for early
engagement. In other words, the final
rule would require the BLM to hold a
public meeting, offering the public
opportunity to engage early, though the
PO 00000
Frm 00015
Fmt 4701
Sfmt 4700
35647
BLM could satisfy this requirement by
holding a public scoping meeting or
other public meeting that facilitates
early engagement by the public.
Commenters suggested that the BLM
provide a website of applications and
authorizations for interested parties so
that they could receive up-to-date
information on the applications and
authorized projects. The BLM agrees
with comments about maintaining a site
that is accessible to the public on
existing and proposed (i.e., applications
for) projects on public lands. The BLM
currently maintains an active web page
at https://www.blm.gov/programs/
energy-and-minerals/renewable-energy/
active-renewable-projects where the
public may access the most recent
information on applications for solar,
wind, and geothermal development
projects, gen-tie-lines, upcoming lease
sales, and other relevant application and
development information about these
sites.
Some comments supported the
removal of the requirement that BLM
hold pre-processing public meetings,
noting that solar and wind energy
technologies are better known now than
they have been previously and that
these meetings are unnecessary. The
BLM also received comments that did
not support removing that requirement.
These comments expressed concerns
that by removing this public meeting the
BLM would be excluding the public and
should instead increase outreach to the
public in the area affected by these
proposed development projects. To
address these concerns, the BLM has
changed the regulatory text in paragraph
(e)(2)(i) to ensure that a public meeting
is held if there is no other opportunity
for the public’s early engagement. The
BLM also would retain discretion to
hold additional public meetings under
§ 2804.25(e).
Paragraph (e)(4) is updated to replace
‘‘the National Environmental Policy Act
(NEPA)’’ with ‘‘NEPA,’’ consistent with
the changes in paragraph (e)(2) of this
section. The BLM updates the reference
in this final rule, consistent with
changes that CEQ has made to its
regulations, such that 40 CFR parts 1501
through 1508 are now referred to as 40
CFR Chapter V, Subchapter A.
Paragraph (e)(5) provides that the
BLM will determine whether the
proposed use complies with applicable
Federal laws.
Paragraph (f) addresses the
segregation of lands within a right-ofway application. Paragraph (f)(3) now
provides that a segregation may be
extended when an application is
complete and cost recovery has been
received.
E:\FR\FM\01MYR6.SGM
01MYR6
35648
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES6
Some comments suggested that the 2year segregation limit is appropriate,
that the BLM should begin NEPA within
2 years of segregating the lands, and that
such limitations should be consistent
with the NEPA timeline requirements
within the Fiscal Responsibility Act.
The BLM agrees that the agency should
be diligent in processing applications,
including initiating NEPA. Because
separate legal authority and policy
guidance applies to NEPA compliance
procedures, including applicable
timelines to complete the NEPA
process, the BLM did not make a change
to this paragraph of the final rule in
response to these comments.
Some comments suggested additional
language should be added to establish
timelines and deadlines supporting
quick action in processing applications.
Section 2804.25(c) in the existing
regulations provides specific due
diligence requirements for applications.
Unless another timeline is specified by
the BLM, applicants have one year to
complete certain actions, and the BLM
may deny an application for failure to
comply with the one-year requirement
or other specified timeframe for
submitting necessary information to the
BLM. The BLM believes this timeline is
generally adequate to promote the
timely processing of applications and
permitting of solar and wind
development projects and to ensure that
developers cannot hold public lands by
submitting, but not diligently pursuing,
an application, thus precluding other
uses of such lands. The BLM did not
change the final rule in response to
these comments.
The BLM received requests to revise
the rule to require automatic segregation
once an applicant has filed a complete
application and has paid the required
application fees and grant extensions
past the four-year mark. Changing the
method to segregate lands and the
timeframes of those segregations is
outside the scope of this rule. The BLM
did not propose to change the method
and timing of segregation, but only to
make this paragraph consistent with
new provisions in the final rule for
complete applications and cost
recovery.
Section 2804.26 Under what
circumstances may the BLM deny my
application?
Section 2804.26 of this final rule
explains the circumstances under which
the BLM may deny an application.
Paragraph (a)(4), consistent with this
final rule replacing the term ‘‘the Act’’
with ‘‘FLPMA’’ discussed under
§ 2801.5, provides that the BLM may
deny your application if issuing the
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
grant would be inconsistent with
applicable law or regulation.
The BLM did not carry forward
paragraph (a)(9) of the proposed rule
because the BLM’s final rule, ‘‘Update of
the Communications Uses Program, Cost
Recovery Fee Schedules, and Section
512 of FLPMA for Rights-of-Way,’’ 89
FR 25922 (April 12, 2024) revised the
BLM regulations at § 2804.26(a) to add
the same provision allowing the BLM to
deny applications that fail to comply
with a deficiency notice . Thus, the
revision in the proposed rule that would
have added this provision is no longer
necessary.
Paragraph (10) incorporate
requirements of this final rule that are
discussed elsewhere. Paragraph (a)(10)
provides that an application may be
denied for failing to pay costs, as noted
in § 2804.22(b).
As proposed, paragraph (c) is
removed in this final rule. Any request
for an alternative requirement received
after an application has been denied is
not a timely request. Requests for an
alternative requirement must be timely.
See § 2804.40(c) for further information
on timely requests.
The BLM received a comment
recommending that the BLM add
another provision following section
(a)(4), suggesting that this new provision
address protection of special
conservation areas managed by the BLM
or other federal or state agencies. The
BLM believes that including the
suggested change to this section is
unnecessary. The BLM’s process to deny
an application under this section is
addressed in the existing regulations at
§ 2804.26. The BLM’s management of
special conservation and other sensitive
areas is generally determined through
the BLM’s resource management
planning and NEPA processes. The BLM
retains broad authority to deny an
application on the basis that it would
not be in the public interest, which may
also address this concern to deny
certain applications.
Section 2804.30
Reserved]
[Removed and
Section 2804.30 is removed and
reserved in this final rule. No comments
were received on this section and the
BLM did not make any changes to this
section in the final rule. Prior § 2804.30
addressed competitive leasing inside of
designated areas. The content of the
prior § 2804.30 is now duplicative of
this final rule in §§ 2809.13, 2809.14,
and 2809.17.
PO 00000
Frm 00016
Fmt 4701
Sfmt 4700
Section 2804.31
Reserved]
[Removed and
Section 2804.31 is removed and
reserved in this final rule. Prior
§ 2804.31 addressed competitive process
for site testing. This portion of the rule
was not used since first put in place in
2016 and is removed. The BLM may still
hold competitive processes for site
testing if there is a competitive interest
or other reasons as identified in
§ 2809.10 of this final rule.
Some comments supported the
removal of competitive processes for
site testing grants, and other
commenters suggested that the section
may be useful in local field office
decision making in the future. The BLM
agrees that retaining requirements for
competitive processes related to solar
and wind energy is important. Subpart
2809 of this final rule provides the
requirements for solar and wind energy
competitive processes, which includes
the requirements of this section.
Section 2804.35 Application
Prioritization for Solar and Wind Energy
Development Rights-of-Way
Section 2804.35 is retitled to
‘‘Application prioritization for solar and
wind energy development rights-ofway.’’ This section provides for the
relative importance of different criteria
that vary from location to location,
giving weight to local resource issues
and circumstances that are not equally
relevant for every application.
Additionally, there are practical
concerns for the BLM when processing
solar and wind energy applications.
This section provides that the relevant
criteria are to be applied holistically to
prioritize applications in a manner that
would facilitate environmentally
responsible projects and ensure that
agency workloads are allocated
appropriately. The revised section
would also explicitly recognize that the
BLM may identify additional criteria in
guidance, which may be national in
scope or specific to an area.
Paragraph (a) clarifies that the
purpose of prioritizing applications is to
allocate agency resources to processing
applications that have the greatest
potential for approval and
implementation. The BLM revised this
section from the proposed rule to clarify
that the BLM’s prioritization of an
application is not a decision and is not
subject to appeal under 43 CFR part 4.
One commenter asked whether the
BLM’s prioritization process might
hinder development of renewable
energy and potentially conflict with
national priorities for renewable energy
deployment. The BLM is endeavoring to
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
increase the responsible deployment of
renewable energy on the public lands
consistent with congressional and
presidential direction. In addition, the
BLM must continue to manage public
lands under the principles of multiple
use and sustained yield unless
otherwise provided by law (43 U.S.C.
1732(a)). The prioritization criteria
support national renewable energy goals
by helping the BLM to consider
applications for the projects that are
most likely to succeed and ensure the
BLM’s continued stewardship of the
public lands.
Paragraph (b) identifies criteria that
the BLM may consider when
prioritizing applications. This section
provides discretion to the BLM as to
how best to apply the criteria to
prioritize processing solar or wind
energy generation applications.
Some comments suggested
prioritizing applications for projects
inside DLAs. Other comments suggested
other criteria that should be considered
when prioritizing applications, such as
the presence of existing leasing
agreements and rights-of-way, whether
the application complies with all state
and federal regulations, the size or
location of the project, project features,
proximity to transmission, and
protection of natural resources.
The BLM believes that these
considerations are important, but no
changes to the regulatory text are
warranted since these considerations
were already included in the proposed
rule. The six listed criteria in the rule
provide flexibility in how the BLM may
apply the criteria for applications in the
BLM’s varied landscapes on which a
resource may have different sensitivities
in one location as compared to another
location. Prioritizing projects based on
siting in designated or preferred areas is
addressed in paragraph (b)(1). The BLM
addressed comments concerning
existing leasing agreements or rights-ofway in the BLM’s application
processing steps in subpart 2804 of
these rules. Paragraph (b)(4) addresses
commenter suggestions regarding
prioritizing applications based on
compliance with federal regulation.
Paragraphs (b)(2) and (b)(5) address the
size or location, project features,
proximity to electric transmission, and
the protection of natural resources.
Several comments requested clarity
on the application of the prioritization
criteria, including a description of the
relative importance of each criterion.
Other commenters also suggested that
they believe the BLM should be
prohibited from prioritizing
applications based on additional criteria
that are not expressly listed in this
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
section of the rule. In the BLM’s
experience, the relative importance of
different criteria may vary from location
to location due to resource
considerations. Likewise, not all
prioritization criteria are equally
relevant for every application. The BLM
has intentionally not set specific
preferences or weights for the criteria it
will apply when prioritizing
applications. This final rule confirms
that the BLM will consider the
prioritization criteria holistically when
considering applications, and that the
BLM may establish additional criteria
through local or national policy
guidance.
In the final rule, the BLM changed
paragraph (b) to refer to ‘‘criteria’’
instead of ‘‘factors’’ as proposed. This
change is consistent with the BLM’s use
of the term ‘‘criteria’’ in paragraph
(b)(6).
The first criterion is whether the
proposed project is located within an
area preferred for such development,
such as a DLA. The BLM may
reasonably presume that development
projects proposed within these areas are
more likely to proceed to approval as
they pose less severe resource conflicts
than other lands.
Some comments suggested that wind
energy is disadvantaged since there are
no wind energy designated leasing areas
or equivalents. The BLM disagrees with
these comments. First, the 2016 Desert
Renewable Energy Conservation Plan
(https://blmsolar.anl.gov/documents/
drecp/) designated more than 192,000
acres of preferred development
locations for solar, wind, and
geothermal energy. Additionally, the
criteria are not given specific
preferences or weights when compared
with one another, and, as such, the BLM
would take into account the lack of
wind DLAs when prioritizing wind
energy development applications.
The second criterion is whether the
proposed development avoids adverse
impacts to or conflicts with known
resources or uses on or adjacent to
public lands and includes specific
measures designed to further mitigate
impacts or conflicts. When submitting
an application to the BLM, the applicant
must address known potential adverse
resource conflicts, including those for
sensitive resources and values that are
the basis for special designations and
protections, as well as potential
conflicts with existing uses on or
adjacent to the proposed energy
generation facility. Under section
2804.12(b)(2), the applicant must also
include specific measures to mitigate
impacts or conflicts with resources and
uses. Including this information is
PO 00000
Frm 00017
Fmt 4701
Sfmt 4700
35649
necessary for the BLM to determine that
an application is complete. While
subsequent consultation, public
comment, and environmental review
processes may reveal unknown resource
or use conflicts, based on previous
experience permitting wind and solar
projects on public land, the BLM
understands that projects with fewer
known conflicts are more likely to
proceed to approval and successful
implementation.
The third criterion is whether the
proposed project is in conformance with
the governing BLM land use plans.
Applications identify whether the
proposed project is in conformance with
the governing land use plan or would
require an amendment or revision to the
plan. The BLM may, in its discretion,
consider applications for solar or wind
energy generation facilities that would
require an amendment or a revision to
the governing land use plan under part
1600 of these regulations. However,
such application could require greater
resources to process and could present
resource conflicts, which would result
in a lower priority.
The fourth criterion is whether the
proposed project is consistent with
relevant State, local, and Tribal
government laws, plans, or priorities.
The purpose of this determination is not
to enforce these State, local, or Tribal
laws, plans, or priorities, but rather to
promote comity and identify projects
that are more likely to be successfully
approved. In addition, applying this
principle helps to ensure that the BLM
takes into account the existing resource
knowledge and expertise that may be
available through State, local, and Tribal
plans and priorities. To carry out this
prioritization, the BLM may enter into
or rely on existing agreements with
State, local, or Tribal governments.
Some comments suggested that
prioritization of an application should
be subject to Tribal consultation. The
BLM engages Federally recognized
Tribes early in the application process
under § 2804.12(b)(4), which allows
Tribes to participate in preliminary
application review meetings with the
BLM and provide early information to
the BLM about an application.
Additionally, under paragraph (b)(4),
the BLM will consider ‘‘whether the
proposed project is consistent with
relevant State, Tribal, and local
government laws, plans, or priorities,’’
which may also include consultation
with Tribes. Finally, the BLM
acknowledges that E.O. 13175 sets forth
criteria for when the BLM is required to
consult with Tribes, and the BLM is
committed to consulting with Tribes
whenever such consultation is required
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
35650
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
under the E.O., without regard to
whether that requirement is specifically
articulated in this rule.
The fifth criterion is whether the
proposed project incorporates the best
management practices set forth in the
applicable BLM land use plans and
other BLM plans and policies. This
principle ensures that the BLM takes
into account the knowledge and
expertise that has gone into formulating
these existing plans and policies.
Should an application require amending
a BLM land use or other plan, it is likely
to require more time and effort to
process.
The sixth criterion considers any
other circumstances or prioritization
criteria identified by the BLM in
subsequent policy guidance or land use
planning for an area.
Paragraph (c) provides that the BLM
will prioritize applications, once
complete (as described in § 2804.12(j) of
this part). The BLM’s prioritization may
use any available information provided
in the application or its Plan of
Development, applicant responses to
deficiency notices, and information
provided to the BLM in public meetings
or by other Federal agencies and State,
local, or Tribal governments.
Paragraph (d) clarifies the BLM
discretion to re-categorize an
application’s priority at any time. Recategorizing an application may be
based on new information that the BLM
has received or on changes the applicant
has made to the application. Recategorizing an application may also be
based on the BLM’s need to adjust its
workload, if circumstances warrant such
re-prioritization.
Some comments expressed concern
that denying or de-prioritizing an
application prior to any final land use
designation, such as those which may
be made in the ongoing update to the
2012 Western Solar Plan, is
inappropriate or pre-decisional.
Comments further expressed that
pending applications should not be
denied before land use designations are
made. The BLM is not constrained by
ongoing or potential future land use
planning processes, but it must manage
public lands in conformance with the
land use plans currently in effect.
Accordingly, the BLM generally will not
deny or deprioritize an application
based on non-conformance with a future
or ongoing land use planning effort. The
criteria in the rule refer to consideration
of governing land use plans. The BLM
would deny or de-prioritize an
application pursuant to its broad
discretion in considering right-of-way
applications based on existing
information and existing land use plans.
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
At the same time, the BLM retains
authority to deny an application based
on appropriate information even if the
project would conform to the applicable
land use plan, including, for example,
where an application conflicts with
current management policies that have
not yet been incorporated into a land
use plan.
Some comments suggested that the
BLM should adopt a first-come, firstserved system when processing
applications or self-prioritization by an
applicant for multiple applications
within a single BLM field office. While
in practice the BLM often processes
applications on a first-come, first-served
basis, it retains discretion to prioritize
applications according to other
considerations including input from an
applicant about their applications. In
practice, the BLM has observed that the
prioritization of projects, particularly in
Field and District Offices with high
workloads, provides a number of
benefits for the BLM and applicants. In
coordinating with applicants, the BLM
discusses workload capacities and will
receive input from developers on the
priority of their applications and
whether there is a specific preferred
order. Due to the many factors the BLM
considers in this decision, however, the
BLM’s determination on a project’s
priority for processing may be different
than that requested by a particular
developer. Targeting workloads for BLM
staff and management facilitates
accelerated decision-making for those
solar and wind energy development
proposals with the greatest technical
and financial feasibility and the least
anticipated natural and cultural
resource conflicts and increases
consistency in processing project
applications for the BLM and applicant.
As detailed in the discussion of subpart
2809 in this rule, the BLM may also
determine that there is a competitive
interest for a right-of-way or system and
hold a competitive process.
Section 2804.40
Requirements
Alternative
Section 2804.40 of this final rule
provides for situations when an
applicant requests alternative
requirements from the BLM if the
requestor is unable to meet the
requirements of this subpart. The final
rule clarifies that this section applies
specifically to the BLM’s consideration
of alternatives to the application
requirements set forth in subpart 2804.
Other requirements related to rights-ofway, such as the requirement to pay rent
as set forth in subpart 2806, cannot be
adjusted under this section. The BLM
PO 00000
Frm 00018
Fmt 4701
Sfmt 4700
did not make a change to this section of
the final rule.
Some commenters suggested that state
and local governments should be
brought into the decision-making
process if an applicant is unable to meet
the application requirements and they
request an alternative to one or more
application requirements. It is the
BLM’s responsibility to determine
whether an alternative requirement for
the application process should be
allowed. Through agreements, including
with cooperating agencies, the BLM
engages with Tribal, Federal, State, and
local government offices when it
considers solar and wind energy
development projects. The BLM would
inform such partners of any changes to
its requirements. Additionally, the BLM
will consider under this section only
requests for alternatives to modify the
alternative requirements found in part
2804—Applying for FLPMA Grants.
Requests to modify other requirements,
including those identified in a decision
authorizing a right-of-way, such as
terms and conditions, cannot be
approved under this section. This
would include requests for alternative
access.
Section 2805.10 How will I know
whether the BLM has approved or
denied my application or if my bid for
a solar or wind energy development
grant or lease is successful or
unsuccessful?
Section 2805.10 of this final rule
clarifies that agency decisions about
whether to approve rights-of-way are
generally administratively appealable
while the issuance of a right-of-way
grant or lease itself is not an opportunity
for appeal.
Paragraph (c) of this final rule clarifies
that ‘‘The BLM will issue the right-ofway by signing the grant or lease and
transmitting it to you.’’ The BLM’s act
of returning the signed instrument to the
holder constitutes the ‘‘issuance’’ of the
right-of-way. Identifying the point in
time at which the right-of-way is
‘‘issued’’ is important for calculating
when the term of a right-of-way begins
to run (see § 2805.11) and when the
holder’s obligation to pay rent begins
(see § 2806.12). Identifying the point at
which the right-of-way is ‘‘issued’’ is
also important for clarifying which
actions are subject to the conditions in
Section 50265(b)(1) of the IRA, which
imposes conditions on when the
Secretary may ‘‘issue a right-of-way for
wind or solar energy development on
Federal land.’’ The BLM did not make
a change to this section of the final rule.
E:\FR\FM\01MYR6.SGM
01MYR6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES6
Section 2805.11
lease contain?
What does a grant or
Section 2805.11 of this final rule
revises the right-of-way authorization
term length for certain facilities, and the
final rule includes minor updates to the
proposed rule to improve technical
clarity. No change was made in this
section of the final rule due to public
comment.
The BLM’s final rule ‘‘Update of the
Communications Uses Program, Cost
Recovery Fee Schedules, and Section
512 of FLPMA for Rights-of-Way,’’ 89
FR 25922 (April 12, 2024), updated
§ 2805.11 to redesignate paragraph (b) to
paragraph (c). Proposed revisions from
this rule under § 2805.11(b) are now
finalized under 2805.11(c) consistent
with the redesignation of this paragraph.
Redesignated § 2805.11(c) addresses
the duration of rights-of-way. Section
2805.11(c)(2) provides specific terms for
solar and wind energy grants and leases.
Paragraphs (c)(2)(iv), (c)(2)(v), and (c)(4)
now show the maximum terms for solar
and wind energy generation facilities,
energy storage facilities that are separate
from energy generation facilities, and
electric transmission lines with a
capacity of 100 kV or more. The term for
a grant or lease for these types of
authorizations may be up to 50 years.
Revisions under this section are
consistent with those made under
§ 2801.9(d).
Paragraph (c)(2)(iv) is updated for the
maximum term for both grants and
leases, for up to 50 years (plus initial
partial year of issuance).
Paragraph (c)(2)(v) is updated for the
maximum term for rights-of-way for
energy storage facilities that are separate
from energy generation facilities.
Although the BLM generally treats
energy storage facilities as linear rightsof-way, rather than solar or wind energy
development rights-of-way, for purposes
such as rent calculation, the BLM
believes that the longer term of ‘‘up to
50 years,’’ commensurate with the
maximum term for solar or wind energy
development rights-of-way, will
facilitate the transition to cleaner
sources of energy in the United States.
Paragraph (c)(4) would be added to
update the term for electric transmission
lines with a capacity of 100 kV or more,
for up to 50 years, commensurate with
the term for solar and wind energy
development projects and energy
storage facilities that are separate from
energy generation facilities.
Some comments sought clarification
on whether a presumptive leaseholder’s
(which is defined at § 2809.15(b)(1))
control of the property would preclude
other uses, such as grazing or recreation,
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
or during any period when use is not
immediately initiated. Prior to the
competitive process, a prospective
bidder would be informed as to whether
they were bidding on a location with
existing authorized uses, such as
recreation or grazing or other known
casual uses. The BLM’s identification of
a presumptive leaseholder or issuance
of a lease would not automatically
exclude authorized uses. Rather, the
BLM must follow its existing processes
prior to ending existing uses; for
example, in the context of livestock
grazing, notice and cancellation is
provided, subject to any required public
comment periods.
The BLM understands from comments
it has received that there is some
confusion whether solar and wind
energy developments may also be
projects. In the final rule, the BLM
revised paragraph (b)(2) to add
‘‘projects’’ to clarify that solar and wind
energy developments may be projects.
Section 2805.12 What terms and
conditions must I comply with?
Section 2805.12 of this final rule lists
certain terms and conditions that apply
to all right-of-way grants and leases. The
BLM revised this section to address
public comments regarding the term
length authorized for certain facilities.
The BLM also included revisions to
prevent a holder’s non-use of the public
lands for the authorized energy
generation facilities.
Paragraph (c)(8) is added to this final
rule addressing concerns raised in
relation to § 2801.9(d) regarding the
longer term for grants and leases. This
rule provides diligent operation
requirements wherein the holder of a
solar or wind energy development grant
or lease must maintain at least 75
percent of energy generation capacity
for the authorized facility for the grant
or lease term. A failure to meet this
operational capacity for two consecutive
years may support the suspension or
termination of the grant or lease under
§§ 2807.17 through 2807.19. The BLM
would send notice to the grant or
leaseholder with a reasonable
opportunity to correct any
noncompliance with the diligent
operation requirement, including
resuming use of the right-of-way.
The BLM believes it is reasonable to
establish a requirement that solar and
wind energy generation developments
must operate within 75 percent of their
generation capacity, allowing a 25
percent operational change for each
year. 6 This allows a solar or wind
6 As demonstrated in a 2018 NREL study, forecast
modeling for solar photovoltaic and wind energy
PO 00000
Frm 00019
Fmt 4701
Sfmt 4700
35651
operator to safely accommodate
operational changes related to
unforeseen circumstances and maximize
their energy production without the
need to coordinate with the BLM for
normal operations. A sustained
reduction in output, such as for
anomalous storm years or changes to a
development’s technology, that reduce
the energy generation below 75 percent
of the project’s capacity would require
coordination with the BLM to update
project information. The energy
generation capacity is first established
by the right-of-way holder under section
2806.52(b)(5) in the first annual certified
statement, and then informed by
subsequent years’ operational capacities
in the annual statement. Since the BLM
bills in advance for a calendar year (see
part 2806 for further information on
solar and wind energy capacity fee), the
BLM believes that this operational
standard is appropriate for the orderly
administration of the public lands and
to ensure appropriate use of its
resources.
In response to the BLM’s notice, a
holder must provide reasonable
justification for the reductions in energy
generation, such as delays in equipment
delivery, legal challenges, or Acts of
God. Holders must also provide the
anticipated date when energy generation
will resume and a request for extension
under paragraph (e) for an extension of
operations period to satisfy the two-year
diligent operation requirements of
paragraph (c)(8). The BLM may deny a
request for extension for failure to
comply with this section.
The BLM will use the annual certified
statement required under § 2806.52(b)(5)
to determine whether a holder has been
meeting the minimum energy generation
capacity for the diligent operation
requirement. Under paragraph
2806.52(b)(5)(vi), the holder must notify
the BLM if they will reduce the amount
of energy generated by 25 percent or
more for that year. Two consecutive
years with reduced energy generation
would support the BLM’s notice to the
grant or leaseholder of noncompliance
with the diligent operation requirement.
Paragraph (e)(2) of this final rule
clarifies that the option of requesting
alternative stipulations, terms, or
conditions does not apply to terms or
conditions related to rents or fees. As
with requests for alternative application
requirements under § 2804.40, requests
developments is generally within 10 percent of
expected capacities over a one-year period. https://
www.nrel.gov/docs/fy23osti/79498.pdf, Solar PV,
Wind Generation, and Load Forecasting Dataset for
ERCOT 2018: Performance-Based Energy Resource
Feedback, Optimization, and Risk Management
(P.E.R.F.O.R.M.)
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
35652
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
for alternative stipulations, terms, or
conditions under § 2805.12 are limited
to technical obligations of the applicant
or holder and not to the holder’s
obligation to compensate the United
States for the use of the public lands
and their resources. Requests for
exemptions or deviations from the
general rent provisions of subpart 2806
should be made under provisions of that
subpart that specifically address such
exemptions or deviations, such as
existing § 2806.15(c) (not revised in this
rulemaking), which sets forth a
procedure for asking the BLM State
Director to waive or reduce a holder’s
rent payment, or § 2806.52(b)(1)(i),
which describes certain circumstances
under which the BLM may calculate the
capacity fee based on an alternative
MWh rate.
A comment suggested that the fees
could be based on third-party
evaluations, such as an appraisal. The
BLM considered whether an appraisal
specific to each authorization would be
appropriate and determined that using
such a process would be costly and add
considerable time to the processing of
an application. The BLM chose not to
use an appraisal, except when it
determines under § 2806.70 that its rent
schedules do not apply to the
underlying right-of-way use. For
example, if the BLM receives a right-ofway application requesting a permit for
a long-term landscape art installation,
the schedules for transmission, solar or
wind energy development, or
communications sites would not apply,
and the BLM may elect to use an
appraisal to determine the appropriate
rent. This final rule also provides for a
specific alternative MWh rate for
determining the capacity fee under
§ 2805.62(b)(1)(i) for development
projects that use a Power Purchase
Agreement (PPA). Such agreements
must be provided to the BLM for review.
If the BLM determines the lower rate is
appropriate, it will use such agreements
in place of the calculated MWh rate.
The BLM did not make a change in
response to this comment.
A comment requested that the BLM
require applicants to include PLAs and
add union labor protections as a term
and condition of solar and wind energy
rights-of-way. In this final rule, the BLM
has elected to provide an opportunity
for holders to receive capacity fee
reductions under certain conditions,
including where the holder can show it
is using PLAs for the construction of the
planned facility (see § 2806.52(b)),
consistent with the reduction authority
under the Energy Act of 2020. However,
in administering the public lands, the
BLM is making such compliance
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
voluntary, offering the capacity fee
reduction to incentivize the use of PLAs
for solar and wind energy development
projects instead of mandating
compliance with such a term. The BLM
believes this voluntary option provides
opportunities to a wide variety of
potential holders and recognizes the
effort of those who qualify for such
reductions consistent with criteria in
§ 2806.52(b). No change was made in
the final rule due to this comment.
Section 2805.13 When is a grant or
lease effective?
Section 2805.13 of this final rule
includes a minor technical clarification
to the title and section, adding ‘‘or
lease,’’ to build consistency for
authorization term lengths inside and
outside of DLAs.
The BLM received comments
opposing this section regarding term
length of authorizations. One comment
recommended the BLM extend the
maximum term from 30 years to 50
years only for leases inside DLAs.
Another comment opposed extending
the maximum term to 50 years for any
authorization. The BLM addressed this
and other similar comments under
§ 2801.9 of this preamble.
Section 2805.14 What rights does a
right-of-way grant or lease convey?
Section 2805.14 of this final rule
clarifies that the term ‘‘right-of-way’’ is
the category of authorizations that
generally are issued as a grant or a lease
under Title V of FLPMA. This clarity
has become increasingly important for
the internal and external understanding
of right-of-way authorizations with the
passage of new legislation. The BLM did
not receive comments on this section.
The title is revised to ‘‘What rights
does a right-of-way grant or lease
convey?’’ The title clarifies that this
section applies to both grants and
leases.
Paragraph (g) removes the text ‘‘solar
or wind energy development’’ and adds
‘‘right-of-way’’ to now read as ‘‘right-ofway grant or lease.’’ This section
provides for when an applicant applies
to renew any right-of-way grant or lease
under § 2807.22.
Section 2805.16 If I hold a grant or
lease, what monitoring fees must I pay?
The BLM’s final rule ‘‘Update of the
Communications Uses Program, Cost
Recovery Fee Schedules, and Section
512 of FLPMA for Rights-of-Way’’ 89 FR
25922 (April 12, 2024) updated the BLM
Headquarters address in § 2805.16.
Thus, the proposed rule’s update to the
BLM Headquarters address is no longer
necessary. The BLM did not receive
PO 00000
Frm 00020
Fmt 4701
Sfmt 4700
comments on this section and did not
include it in the final rule.
Subpart 2806 Annual Rents and
Payments
Subpart 2806 of this final rule
clarifies that the term ‘‘right-of-way’’ is
the category of authorizations that are
generally issued as a grant or a lease
under Title V of FLPMA. This clarity
has become increasingly important for
the internal and external understanding
of right-of-way authorizations with the
passage of new legislation.
In subpart 2806, the BLM sets the
acreage rent and capacity fee calculation
methodologies for solar and wind
energy development rights-of-way.
Section 504(g) of FLPMA, 43 U.S.C.
1764(g), requires right-of-way holders,
subject to several narrow exceptions, ‘‘to
pay in advance the fair market value’’
for the use of the public lands. Section
102(a) of FLPMA, 43 U.S.C. 1701(a),
clarifies that ‘‘it is the policy of the
United States that . . . the United States
receive fair market value of the use of
the public lands and their resources
unless otherwise provided for by
statute.’’ The BLM has consistently
taken the position that this statutory
mandate includes the authority to
charge acreage rent and capacity fees
that reflect the fair market value of the
public lands and their resources. For
example, the preamble to the BLM’s
2016 Final Rule, Competitive Processes,
Terms, and Conditions for Leasing
Public Lands for Solar and Wind Energy
Development and Technical Changes
and Corrections, explained that ‘‘(t)he
BLM has determined that the most
appropriate way to obtain fair market
value is through the collection of
multicomponent fee [sic] that comprises
an acreage rent, a MW capacity fee, and,
where applicable, a minimum and a
bonus bid for lands offered
competitively . . . . [T]he collection of
this multicomponent fee will ensure
that the BLM obtains fair market value
for the BLM authorized uses of the
public lands, including for solar and
wind energy generation.’’ 81 FR 92122,
92134 (Dec. 19, 2016). In that final rule,
the BLM further explained that the use
of a multicomponent rent and fee
structure that comprises an acreage rent,
a MW capacity fee, and in some cases
also a minimum and a bonus bid assists
the BLM in achieving important
objectives, including identifying and
capturing fair market value for the use
of public land, providing a consistent
approach with other categories of public
land uses, encouraging efficient use of
the public lands by reducing relative
costs for comparable projects using
fewer acres, and employing an approach
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
consistent with existing policies and
regulations governing the BLM’s
renewable energy program. See id. The
multicomponent fee of this final rule
will continue to advance important
objectives that serve the public interest,
including allowing the BLM to capture
fair market value for use of the land
(subject to reductions pursuant to
Energy Act of 2020 authority).
In the Energy Act of 2020, 43 U.S.C.
3003, Congress amended the fair market
value requirement of Section 504(g) of
FLPMA by providing the Secretary with
discretion to ‘‘consider acreage rental
rates, capacity fees, and other recurring
annual fees in total when evaluating
existing rates paid for the use of Federal
land’’ for solar and wind energy projects
and reduce acreage rental rates and
capacity fees if the Secretary makes
certain findings, including ‘‘that a
reduced rental rate or capacity fee is
necessary to promote the greatest use of
wind and solar energy resources.’’
Consistent with FLPMA and the Energy
Act of 2020, the BLM will continue to
charge solar and wind energy rights-ofway acreage rent and capacity fees. The
final rule implements a methodology
that bases rent and fee rates on local
land values and wholesale energy
market prices. This methodology also
supports the direction in the Energy Act
of 2020, 43 U.S.C. 3004, of meeting
national clean energy objectives,
including the congressional goal of
permitting 25 GW of renewable energy
by 2025 on Federal lands through
reductions in rental rates and capacity
fees. As described in the section-bysection discussion for subpart 2806, this
final rule is utilizing the authority in 43
U.S.C. 3003 to adjust the fair market
value requirement through reductions in
rental rates and capacity fees for solar
and wind energy projects on public
lands.
Under the final rule, acreage rent rates
for solar and wind energy rights-of-way
are determined using the NASS Cash
Rents Survey, which reflects a nominal
value of the land at the time the rightof-way is issued and prior to
commercial use. This per-acre land
rental value will be multiplied by an
encumbrance factor (which
differentiates between solar and wind
energy facilities) and an annual
adjustment factor that accounts for
changes in the value of the land over the
lifetime of the right-of-way due to
inflation and similar factors. Because
the NASS Cash Rents Survey used for
solar and wind acreage rents reflects a
valuation of annual rent, no rate of
return is applied when determining
solar and wind energy acreage rents.
The acreage rent rate reflects a nominal
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
value of the land to continue to
maintain site control after the right-ofway is issued.
Once a solar or wind energy
generation facility is utilizing the solar
or wind resources on public land to
produce electricity, the BLM may charge
the capacity fee for the right-of-way
unless the acreage rent remains higher
than the fee. The capacity fee is
determined in part using the annual
MWh production multiplied by either
wholesale power pricing information or
pricing figures specific to a project’s
PPA to determine the market value of
the electricity generated from the
project. The wholesale power pricing
information or other pricing basis
variables in the BLM’s calculation, like
the pastureland rental value based on
the NASS Cash Rents Survey used for
calculating acreage rents, will be fixed
at the time the right-of-way is issued
and will be updated using a fixed
annual adjustment factor. This market
value of the electricity generated will
then be multiplied by a rate of return
based on a percentage of wholesale
pricing and by certain qualifying fee
reductions to arrive at a capacity fee for
the authorized project.
Some comments suggested that fees
should be compared with the fees
associated with other energy sources
instead of being based on the per-acre
values for pastureland. Other comments
expressed support for the BLM using the
NASS Cash Rents Survey to calculate
acreage rent rates. The BLM manages
different energy sources, e.g., oil and gas
and geothermal, consistent with the
applicable laws for each. As such, rent
and fee values promulgated in
regulations consider differences under
law. Solar and wind energy generation
facilities on public lands are authorized
under Title V of the FLPMA (43 U.S.C.
1761–1771) and its implementing
regulations at 43 CFR part 2800. Section
504(g) of FLPMA generally sets the
requirements for how the BLM will
collect rents and fees for use of the
public lands and their resources through
a right-of-way. These requirements
differ from those in the MLA (30 U.S.C.
181 et seq.) and the Geothermal Steam
Act (30 U.S.C. 1001 et seq.), and thus a
comparison of fees for production of
these different energy sources on public
lands would be inappropriate and
irrelevant. In this final rule, the BLM
updates rents and fees for solar and
wind energy development rights-of-way
under the authority provided by FLPMA
to reflect the fair market value for use
of the public lands and their resources
by using acreage rental rates that reflect
local land values prior to commercial
electricity production through using
PO 00000
Frm 00021
Fmt 4701
Sfmt 4700
35653
pastureland cash rent survey values by
NASS. The BLM then applies its
authority under the Energy Act of 2020
to provide reductions that are necessary
to promote the greatest use of wind and
solar energy resources.
One comment suggested that the
proposed rule should not offer acreage
rent and capacity fee reductions to
projects outside DLAs and instead
should implement project-specific
reductions and other incentives to
promote responsible development
inside DLAs. DLAs are locations on
public lands that the BLM has
designated through the land use
planning process as priority areas for
solar and/or wind energy development.
Limiting acreage rent and capacity fee
reductions to DLAs would not, however,
meet the Energy Act of 2020’s direction
to promote the greatest use of wind and
solar resources. To date, the BLM has
only allocated DLAs for solar facilities
on public lands within six southwestern
states for locations that are
predominately favorable for thermal
solar projects (i.e., concentrated solar).
The BLM currently has no DLAs
allocated for solar in other states.
Furthermore, the BLM has no DLAs
allocated for wind energy development
on public lands in any state. The BLM
determined that limiting rent and fee
reductions to only DLAs would be suboptimal in supporting clean energy
goals. As such, the final rule will
provide for rent and fee reductions on
public lands both inside and outside
DLAs, which will serve the BLM’s
purpose of promoting the greatest use of
wind and solar energy resources on
public lands.
One comment suggested that subpart
2806 should not eliminate fair market
value for rental and leases on public
lands or the competitive bid process.
The commenter did not support
incentivizing renewable development
for a specific project by eliminating the
competitive leasing process. Contrary to
the commenter’s suggestion, this final
rule does not eliminate the BLM’s
ability to utilize a competitive bid
process for solar and wind energy
development. The final rule adjusts the
competitive process requirements for
wind and solar energy development
proposals within DLAs by aligning it to
be consistent with agency discretion for
utilizing a competitive process outside
DLAs when the BLM’s authorized
officer decides to use a competitive
process.
Some comments suggested that this
rule should generally raise fees for
developers and require more upfront
mitigation money to address long term
environmental issues. Related
E:\FR\FM\01MYR6.SGM
01MYR6
35654
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
comments suggested that the BLM
should establish an environmental
mitigation fund in addition to rents and
fees to accommodate the high
probability of direct and cumulative
impacts. The BLM considered these
comments and is not making these
suggested changes. The BLM believes
such changes are unnecessary because
the final rule does not limit the BLM’s
existing authority and ability to
appropriately impose mitigation
requirements as a component of the
terms, conditions, and stipulations for a
solar or wind energy development. The
BLM will continue to require
appropriate mitigation and conditions of
approval to address environmental
impacts for right-of-way grants and
leases without further requirements
promulgated under this final rule.
Other commenters stated that the
BLM should implement a minimum
efficiency criterion to ensure that
consumers receive the necessary
amount of power to keep up with
demand. The BLM disagrees with
comments suggesting that the BLM
should regulate how efficiently a project
must operate. Developing a project is a
complex process that depends on
several factors, including the
availability and cost of appropriate
technology. The BLM has included a
provision in this final rule that sets an
operational standard requiring a
development project to annually
maintain at least 75 percent of its energy
generation capacity. See § 2805.12(c)(8)
for further information on the
operational standards for solar and wind
energy development projects on public
lands.
ddrumheller on DSK120RN23PROD with RULES6
Section 2806.10 What rent must I pay
for my grant or lease?
Section 2806.10 of this final rule
provides a minor technical clarification
described below. The BLM did not
receive comments on this section and
has made no changes to it in the final
rule.
Section 2806.10 provides rent
requirements that apply to all grants and
leases, requiring payment in advance,
consistent with Section 504(g) of
FLPMA, as amended. New § 2806.10(c)
would clarify to a reader that the per
acre rent schedule for linear right-ofway grants must be used unless a
separate rent schedule is established for
your use—such as with communication
sites under § 2806.30 or solar and wind
energy development facilities per
§ 2806.50—or the BLM determines
under § 2806.70 that its rent schedules
do not apply to the underlying right-ofway use.
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
Section 2806.12
pay rent?
When and where do I
Section 2806.12 of this final rule
provides a minor technical clarification
as described below. The BLM did not
receive comments on this section and
has made no changes to it in the final
rule.
Paragraphs 2806.12(a) and (b)
describe the proration of rent for the
first year of a grant and the schedule for
payment of rents. Paragraphs 2806.12(a)
and (b) would be revised by deleting the
term ‘‘non-linear,’’ which is not defined
in the regulations, to clarify that these
provisions apply to all right-of-way
grants or leases.
Section 2806.20 What is the rent for a
linear right-of-way grant?
Section 2806.20 of this final rule
clarifies the BLM’s mailing address.
Section 2806.20(c) addresses how to
obtain a current rent schedule for linear
rights-of-way. This paragraph provides
the BLM’s mailing address of record by
reference to § 2804.14(c).
Solar and Wind Energy Development
Rights-of-Way
The existing regulations contain two
undesignated center headings to
organize and differentiate sections
pertaining to solar (see existing
§§ 2806.50 through 58) and wind (see
existing §§ 2806.60 through 68) energy
rights-of-way. The final rule revises
those sections and undesignated
headings to provide a single set of
provisions for all solar and wind energy
development rights-of-way. The rent,
fee, and payment requirements under
the final rule are discussed in the
following sections and are identical for
solar and wind except for the difference
in the encumbrance factor used in
calculating the acreage rent that is
discussed under § 2806.52(a). Sections
2806.50 through 2806.58 address solar
and wind energy rents and capacity
fees.
The final rule updates the acreage rent
and capacity fee calculation methods to
improve predictability of rates for solar
and wind energy development projects
on public land. The combined rent and
fee calculation methodologies have the
flexibility to meet FLPMA’s fair market
value requirement while also applying
calculation factors to reduce rates to
promote the greatest use of wind and
solar energy resources on the public
lands consistent with the Energy Act of
2020.
The final rule retains flexibility to
utilize different data sources for
electricity market values over time.
Developers of solar and wind energy on
PO 00000
Frm 00022
Fmt 4701
Sfmt 4700
public lands will have improved rate
predictability over the term of an
authorization. This is accomplished by
establishing an acreage rate and capacity
fee rate at the beginning of a grant or
lease term with upfront built-in rate
adjustments and by indexing the
capacity fee to the annual energy
production.
The BLM’s acreage rent is the average
of the state-wide pastureland rent from
the NASS Cash Rent Survey. The
acreage rent is the minimum payment
made to the BLM each year by the
developer. See § 2806.52(a) for further
information on the acreage rent.
The capacity fee, based on wholesale
power prices, serves to compensate the
United States for long-term site control
and the production value of the
electricity generated by solar and wind
energy projects on public lands. The
capacity fee will be collected annually,
but only when the capacity fee exceeds
the acreage rent for the year. See
§ 2806.52(b) for further information on
the capacity fee.
The final rule includes certain
reductions that may be applied under
the authority granted to the Secretary in
the Energy Act of 2020, which provides
that annual acreage rent and capacity
fees may be reduced if the Secretary
determines that a reduced rental rate or
capacity fee is necessary to promote the
greatest use of wind and solar energy
resources, among other reasons.
Adjustments to the capacity fee from the
MWh rate reduction, The Domestic
Content reduction, and PLA reduction
are discussed in greater detail in
§ 2806.52(b)(1)(ii) through (iv). The BLM
has determined that the rate reductions
in this final rule would help to promote
the greatest use of wind and solar
energy resources on public lands.
Section 2806.50 Rents and Fees for
Solar and Wind Energy Development
Section 2806.50 of the final rule
requires the holder of a solar or wind
energy right-of-way to pay in advance
the greater of either an annual acreage
rent or a capacity fee, consistent with
Section 504(g) of FLPMA (43 U.S.C.
1764(g)). There are no provisions in this
rule for a phased-in rent or fee.
The acreage rent or capacity fee, as
applicable, is calculated based on the
requirements found in §§ 2806.11 and
2806.12. The acreage rent is calculated
according to the formula set forth in
§ 2806.52(a), while the capacity fee is
calculated according to the formula set
forth in § 2806.52(b).
Some comments expressed concern
that this rule creates negative market
incentives by keeping acreage rents and
capacity fees artificially low. These
E:\FR\FM\01MYR6.SGM
01MYR6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES6
commenters suggest that the BLM
should implement a consistent yearly
increase in acreage rent and capacity
fees based on initial rates, with
reductions provided only for projects in
specific circumstances, such as siting
within solar zones or on disturbed
lands, and with strong commitments to
domestic content. The BLM is cognizant
that the rent and fee rate structure is
important for promoting the greatest use
of wind and solar energy resources and
is a critical component to providing
short- to medium-term stability for
emerging energy markets. There is a
strong public interest in maintaining
rate predictability for electricity
generating entities that are subject to
long-term interconnect and PPAs. This
final rule sets rates that are also
increased annually, through the annual
adjustment factor (see § 2806.52(b)(2)).
The annual adjustment continues
through the term of the authorization.
Additionally, this final rule provides an
opportunity for rate reductions for all
solar and wind energy development
projects that further the goals of the
Energy Act of 2020, which is to
authorize 25 gigawatts of renewable
energy on Federal lands by 2025 and
further national clean energy priorities.
The BLM did not make a change to this
section of the final rule.
Section 2806.51 Grant and Lease Rate
Adjustments
Section 2806.51’s title is changed
from the proposed rule to clarify that
this section applies to all grants and
leases. This section provides for rightof-way grant and leaseholders to
transition to the new rate making under
this final rule through an affirmative
request to the BLM. Absent a request,
they would retain the rate setting
method in effect prior to this final rule.
Paragraph (c) informs holders of
existing solar or wind energy
development rights-of-way that they
may request the new rate methodology
in this final rule be applied to their
existing grant or lease. Existing holders
have two years from the date this final
rule becomes effective to request a
change to the new rate making method.
The BLM will continue to apply the
grant holder’s or lessee’s current rate
methodology if a timely request is not
received.
The BLM received a comment that
does not support any rate reduction
based on an estimation of energy
generated because all rates should be
assessed on actual production. The BLM
has the administrative flexibility to
collect payment in advance based on
estimated energy. The amount the BLM
may collect for the right-of-way may
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
change once the BLM determines the
actual energy production on the right-ofway. The BLM will reconcile any
difference in the amount due and credit
any overpayment, and right-of-way
grant holders and lessees are liable for
any underpayment. See § 2806.52(b)(5)
of this rule for the BLM’s annual
certified statement that provides more
information about the estimated and
actual energy generation. The BLM did
not change this section of the final rule
in response to this comment.
Some comments recommended that
the final rule cap the total amount of
reduction in acreage rents and capacity
fees that an individual leaseholder can
claim for a right-of-way. The final rule
does not cap the number or level of
reductions an applicant or holder may
qualify for; however, the final rule does
require that the BLM collect no less than
the acreage rent for the right-of-way
each year, notwithstanding the number
of reductions that apply to the grant per
§ 2806.52(b). The BLM did not change
this section of the final rule in response
to this comment.
Some comments suggested that rate
reductions may be achieved without any
changes to where the BLM sources its
market pricing data. In the final rule, the
BLM preserves its discretion to change
the source of market data. In the BLM’s
experience, access to such information
may change over time. For this final
rule, the BLM is using the Energy
Information Administration pricing data
that may be found at https://
www.eia.gov/electricity/wholesale/.
Energy Information Administration data
is free and open to the public,
increasing transparency into the BLM’s
rate schedule. The BLM did not change
to this section of the final rule in
response to this comment.
Some comments recommended that
the BLM seek to increase domestically
sourced products and materials and that
the BLM should use this rule to
mandate robust domestic content
thresholds for projects permitted on
Federal land. The BLM agrees with
these commenters’ interest in increased
use of domestic content for solar and
wind energy development projects. This
final rule includes a financial incentive
in the form of a ‘‘Domestic Content
reduction’’ under § 2806.52(b)(1)(iii) to
encourage holders to use components
made or manufactured in the United
States in the construction of the solar or
wind energy project. This capacity fee
reduction is intended to offset costs
associated with using only iron, steel,
manufactured products, and
construction materials incorporated into
the project that are produced in the
United States consistent with the
PO 00000
Frm 00023
Fmt 4701
Sfmt 4700
35655
direction in the Energy Act of 2020. The
BLM anticipates that this proposed
capacity fee reduction would increase
economic certainty for renewable energy
projects on BLM-managed public lands.
By incentivizing the use of domestically
made parts and materials in exchange
for a reduced capacity fee, the BLM
expects to reduce costs for developers
that choose to incorporate domestically
produced materials into their projects.
The BLM believes that this reduction
will help increase demand for
domestically produced renewable
energy parts and materials. These
intended outcomes would serve to
promote the greatest use of wind and
solar energy resources on public lands.
Currently, wind and solar energy
developers face a choice between
relying on foreign-sourced parts and
materials or paying higher prices for
domestically sourced parts and
materials, if available. (See for example
the Department of Energy’s Solar
Photovoltaics—Supply Chain Deep Dive
Assessment, available at https://
www.energy.gov/sites/default/files/
2022-02/Solar%20Energy%20Supply
%20Chain%20Report%20%20Final.pdf). As seen in recent years,
uncertainty in global supply chain
dynamics has the potential to delay
deployment of solar and wind energy
development projects on public lands.
Using incentives to create demand for
American-made renewable energy parts
and materials will help develop
domestic supply chains and reduce
impacts on renewable energy
deployment on public lands from
potential supply chain delays. The BLM
believes that incentivizing the use of
parts and materials that qualify for the
Domestic Content reduction will
increase the responsible deployment of
renewable energy and will increase
commercial interest in the use of public
lands, promoting the development of
solar and wind energy resources on
public lands. This final rule changes the
definition used for domestic content to
align with the BABA Act and
implementing guidance at 2 CFR 184.
See § 2806.52(b) for further information
on the domestic content reduction.
Some comments suggested that a
broad approach to rate reductions may
have revenue implications and fail to
guarantee that taxpayers obtain a fair
return for the utilization of our public
lands. Consistent with congressional
and presidential direction, the BLM is
endeavoring to increase the responsible
deployment of renewable energy on the
public lands and as part of that
direction has been authorized to reduce
rents and fees to promote the greatest
E:\FR\FM\01MYR6.SGM
01MYR6
35656
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES6
use of wind and solar resources on
public lands. As part of this rulemaking
process, the BLM carefully deliberated
on how to implement the directives and
new authorities while maintaining a
reasonable return for the use of the
public lands and their resources.
Following the BLM’s implementation of
previous rate reductions in calendar
year 2022 for solar and wind energy
development projects, the agency
received feedback which generally
indicated that overall costs for
permitting, development, and
operations on Federal public lands were
still perceived as a barrier to entry and
a disincentive to the BLM’s ability to
promote solar and wind deployment on
public lands. The BLM believes the fee
reductions will assist in removing
barriers inhibiting deployment of solar
and wind development on public lands.
Section 2806.52 Annual Rents and
Fees for Solar and Wind Energy
Development
Section 2806.52 of this final rule
describes the BLM’s methodology to
determine the acreage rent and capacity
fee for solar and wind development
rights-of-way. Payment is required of
the greater of either an acreage rent,
which is calculated in advance of
authorization, or a capacity fee, which
is calculated upon the start of energy
generation. This section was revised
based on public comments.
Section 2806.52(a) provides that
acreage rent would be determined by
multiplying the number of acres
authorized for a project (rounded up to
the nearest tenth) by the state-specific
per-acre rate from the solar and wind
energy acreage rent schedule in effect at
the time a grant or lease is issued. The
acreage rent would be the minimum
yearly payment for a grant or lease and
would not be required if the capacity fee
under paragraph (b) of this section
exceeds the acreage rent.
Paragraph (a)(1) explains that the peracre rate is calculated by multiplying
the state-specific per-acre value by the
encumbrance factor and a factor that
reflects the compound annual
adjustment since the start of the grant or
lease term, according to the formula A
× B × ((1 + C) ∧ D)).
Paragraph (a)(1)(i) identifies ‘‘A’’ as
the per-acre rate, using the state-specific
per-acre value from the solar or wind
energy acreage rent schedule for the
state where a project is located for the
year when the grant or lease is issued.
The average per acre value will be
determined using the NASS pastureland
rents reported within the previous 5year period. The BLM will update the
acreage rent schedule and its per-acre
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
rate every 5 years consistent with the
timing of rent adjustments under
§ 2806.22 for the linear rents schedule.
Based on the pastureland rent value in
the NASS Cash Rents Survey through
2021, the most recent 5-year average
ranges from $2.10 per acre in Arizona to
$12.60 per acre in California with a
median value of $6.62 per acre in the
Western States. The next year the BLM
will update its rent schedule will be for
calendar year 2026.
Using Nevada as an example for how
the BLM will average NASS pastureland
rents, assume that NASS reported
values of $10.00, $13.00, and $10.00 per
acre respectively for 2019, 2020, and
2021. NASS reported values during the
5-year period only for those 3 years and
did not report values for 2017 and 2018.
In that case, the BLM would average the
reported values using three years for
that 5-year period, which would equate
to $11.00 per acre.
The per-acre rate charged to the rightof-way holder for a grant or lease will
not change once calculated and the
authorization is issued. Rates for an
existing authorization will not change
with updates to the acreage rent
schedule; instead, the acreage rent will
be adjusted by the annual adjustment
factor, ‘‘C’’ in the formula above, under
2806.52(a)(1)(iii).
Paragraph (a)(1)(ii) identifies ‘‘B’’ in
the formula above as the encumbrance
factor. The encumbrance factor is
applied to account for the intensity of
the solar or wind development’s surface
use of the public lands. In the final rule,
solar energy generation facilities are
subject to a 100 percent encumbrance
factor and wind energy generation
facilities are subject to a five percent
encumbrance factor. The 100 percent
encumbrance factor for solar facilities
reflects a greater intensity of
development on the surface of public
lands and a virtual exclusion of other
uses on the right-of-way. The five
percent encumbrance factor for wind
facilities recognizes that a wind energy
facility only partially encumbers the
land, allowing other uses to co-exist.
Some comments suggest that a lower
encumbrance value for solar is
appropriate, noting that facilities may
incorporate design elements or
construction methods that reduce
impacts to resources, such as raised
fences for wildlife passage or vegetation
disturbance caps. The BLM appreciates
that projects incorporating such
improvements may cause fewer impacts
to public land resources. However, the
BLM disagrees that such improvements
reduce the encumbrance factor, which is
based on the occupancy of the land and
impact to other uses of the land. Solar
PO 00000
Frm 00024
Fmt 4701
Sfmt 4700
energy developments have a greater
occupancy of the land and impact to
other uses because they preclude the
majority and sometimes all other uses.
This encumbrance factor for solar
energy developments is appropriate for
public lands, and the BLM retains its
100 percent encumbrance factor for this
rule.
One comment asserted that the
proposed encumbrance value of five
percent for wind energy is too low and
should be set around 50 percent and
that if the BLM decreases the
encumbrance factor from 10 percent, the
BLM should a explain its rationale in
this rule. Others believed the
encumbrance factor should be lower,
asserting that a mid-point encumbrance
factor of 3 percent is appropriate based
on the Department of Energy’s Wind
Vision analysis. The BLM considered
the intensity of the surface use and
exclusion of other uses when setting the
encumbrance factor in this final rule.
While the commenters that advocated
for a 50 percent encumbrance factor did
not provide data supporting that figure,
the National Renewable Energy
Laboratory has found that generally
‘‘only a small fraction of that area
(<1%–4%) is estimated to be directly
impacted or permanently occupied by
physical wind energy infrastructure.’’ 7
In practice, the BLM has found that,
based on geography or project design,
and effect on other uses, the
encumbrance may be more or less than
that reported by NREL occupied land
percentages and therefore set a five
percent encumbrance factor for wind
energy.
Paragraph (a)(1)(iii) clarifies that ‘‘C’’
in the formula above is the annual
adjustment factor, which is three
percent, and Paragraph (a)(1)(iv)
clarifies that ‘‘D’’ is the year of the grant
or lease term, where the first year
(whether partial or a full year) would be
0 (that is, there is no inflation for the
first year of the term). Under the final
rule, the annual adjustment factor
would be fixed at three percent and
compounded annually for the term of
the authorization.
Paragraph (a)(2) describes where you
may obtain a copy of the current peracre rates for the solar and wind energy
rent schedule.
Paragraph (b) describes that the
capacity fee is calculated by multiplying
the MWh rate or the alternative MWh
rate (which is described below), the
MWh rate reduction, the Domestic
Content reduction, PLA reduction, the
7 https://www.nrel.gov/news/program/2022/nrelexplores-the-dynamic-nature-of-wind-deploymentand-land-use.html.
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
rate of return, and the annual power
generated on public lands for the grant
or lease in question (measured in MWh)
by a factor that reflects the compound
annual adjustment. The capacity fee is
required to be paid annually beginning
in the first year that generation begins
for the energy generation facility. There
will be no capacity fee levied for the
first year or any other year if the acreage
rent exceeds the capacity fee. The
formula for calculating the annual
capacity fee is A × B × C × D × [(1 +
E) ∧F] × G × H.
Paragraph (b)(1)(i) describes that ‘‘A’’
is either the MWh rate, an amount
determined based on the average of the
annual weighted average wholesale
price per MWh for the major trading
hubs serving the 11 Western States of
the continental United States, or the
alternative MWh rate. The MWh rate is
calculated based on the wholesale
prices from the full five calendar-year
period preceding the most recent MWh
rate adjustment before the right-of-way
was issued, rounded to the nearest
dollar. There is no MWh rate phase-in
for energy generation facilities except
for existing holders that elect to
continue paying under their current rate
adjustment method per § 2806.51(c).
The BLM may use an alternative
MWh rate when a grant or leaseholder
enters into a PPA with a utility for a
price per MWh that is lower than the
average of the annual weighted average
wholesale price. In those instances, the
BLM will determine if the rate in the
PPA is appropriate to use instead of the
MWh rate. For example, an alternative
MWh rate may not be appropriate if a
utility issues itself a PPA for its solar or
wind energy development. If the rate in
the PPA is appropriate, then the BLM
would set an alternative MWh rate for
the grant or lease at the rate in the PPA.
The BLM received a request to remove
the BLM’s discretion to use an
alternative MWh rate rather than a MWh
rate calculated on the average wholesale
pricing as described under
§ 2806.52(b)(1)(i). The BLM provides an
opportunity for an alternative MWh rate
in this rule in the event that there is a
difference between wholesale pricing
(energy pricing at market) compared to
the negotiated pricing that may be
achieved in a PPA. The BLM
understands from a recent report from
Lawrence Berkeley National Lab
(available at https://emp.lbl.gov/utilityscale-solar/) that PPA pricing may be
less than wholesale market pricing. The
BLM does not want to disincentivize
reasonable development on public lands
or more favorable power purchase rates,
which would be contrary to national
goals set by law and directed by
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
executive order, by disincentivizing
such actions. However, the BLM also
wishes to ensure it retains the discretion
necessary to ensure that an alternative
MWh rate is appropriate. The BLM did
not make changes in the final rule due
to these comments.
In paragraph (b)(1)(ii), ‘‘B’’ is the
MWh rate reduction. The final rule sets
the capacity fee at 20 percent of the
wholesale price per MWh or alternative
MWh rate through calendar year 2035.
This reduction is consistent with the
authority provided in the Energy Act of
2020 allowing the Secretary to reduce
acreage rental rates and capacity fees if,
among other things, the Secretary
determines ‘‘that a reduced rental rate or
capacity fee is necessary to promote the
greatest use of wind and solar energy
resources.’’ Further, this reduction
would help BLM meet the goal under
the Energy Act of 2020 of ‘‘authoriz[ing]
production of not less than 25 gigawatts
of electricity from wind, solar, and
geothermal projects by not later than
2025.’’ Implementing this reduction is
necessary to promote the greatest use of
wind and solar energy resources and
maximize commercial interest in lease
sales by lowering the entry cost of
prospective energy generating facilities.
Additionally, implementing this
reduction puts the rates the BLM
charges closer to what the BLM charged
developers in 2007 and 2008 when
interest in solar and wind energy
development on public lands began to
increase. The reduced rates and new
rate setting methodology lower the
potential that existing right-of-way
holders who agreed to terms and
conditions for using public lands that
were later updated based on market
changes will experience economic
hardship as a result of those
adjustments. This final rule uses
predetermined adjustments instead.
For example, the MWh rate reduction
for a newly authorized solar or wind
energy grant or lease in 2035 will be set
at 20 percent of the wholesale price per
MWh or alternative MWh rate. This will
yield a continued 80 percent reduction
through the end of that authorization’s
term consistent with the Energy Act of
2020 authority.
Starting in 2036, the BLM will begin
to transition the MWh rate reduction to
20 percent by 2038. The MWh rate
reduction will be reduced to 60 percent
for new projects authorized in 2036, 40
percent for new projects authorized in
2037, and 20 percent for new projects
authorized in 2038 and beyond. The
rates for existing authorizations will not
change with this transition to a 20
percent reduction. For example, an
authorization for solar or wind energy
PO 00000
Frm 00025
Fmt 4701
Sfmt 4700
35657
development in 2037 would receive a 40
percent reduction through the end of the
authorization’s term. The BLM would
similarly apply this reduction to
authorizations it issues based on the
year of issuance.
Some comments suggested the
transition from an 80 percent MWh rate
reduction to a 20 percent MWh rate
reduction appears arbitrary and without
grounding in economic analysis of
market conditions and suggested instead
allowing the 80 percent reduction to
continue until a future rulemaking. The
BLM understands the concerns raised
by the commenters regarding the change
to the reduction in the proposed rule.
However, the BLM disagrees that the 80
percent MWh rate reduction should
continue until a future rulemaking.
Instituting a phased sunset period to the
80 percent reduction in the capacity fee
is appropriate as the renewable energy
industry may no longer need this
reduction to achieve the greatest use of
wind and solar on public lands, and
progress toward our national goal of a
carbon-pollution free electricity sector
may indicate that a reduction is no
longer warranted. In this final rule, the
BLM is revising the transition from
MWh rate reduction from 80 percent to
20 percent over several years. This
transition would lessen the year-overyear rate change until 2038, when the
MWh rate reduction would remain at 20
percent. The BLM will evaluate progress
towards reaching national goals before
2036 and could reinitiate rulemaking to
adjust incentives, including extending
them beyond 2036, if appropriate under
the authority in the Energy Act of 2020
or other applicable authority.
In paragraph (b)(1)(iii), ‘‘C’’ is the
Domestic Content reduction. This
paragraph is revised consistent with the
changes discussed under § 2801.5. As
explained previously, the BLM is
promoting the development of solar and
wind energy resources on public lands
by offsetting some of the costs of using
items and materials produced in the
United States in the construction of
solar and wind energy development
facilities. The BABA Act, Public Law
117–58, 135 Stat. 429, §§ 70901 through
70927 (Nov. 15, 2021) and the
implementing regulations at 2 CFR part
184, describe certain categories of items
or products that are eligible for the
domestic content preference. As noted
in § 2801.5, the BLM adopts the term
‘‘domestic content’’ to refer to the items
and materials associated with the
construction of a solar or wind energy
facility on public lands that are eligible
for the domestic content preference.
Paragraph (b)(1)(iii) of § 2806.52 of the
BLM’s regulation would reduce the
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
35658
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
capacity fee for solar or wind energy
generation facilities if the holder can
demonstrate that the construction of the
facilities for the right-of-way—excluding
labor costs—qualify as produced in the
United States as described in 2 CFR
184.4. The Domestic Content reduction
is 20 percent for facilities qualifying for
the domestic content preference defined
in 2 CFR part 184. To qualify for this
capacity fee reduction, the percent of
the energy generation facility’s total cost
that consists of items qualifying for the
domestic content preference would have
to meet or exceed the ‘‘Produced in the
United States’’ requirements in 2 CFR
184.3. Generally, this would mean that:
(1) all manufacturing processes for iron
or steel products used as a component
of the project occurred in the United
States; (2) manufactured products (a)
were manufactured in the United States,
and (b) the cost of the components of
the manufactured product that are
mined, produced, or manufactured in
the United States is greater than 55
percent of the total cost of the
manufactured product, as determined in
2 CFR 184.5; and (3) all manufacturing
processes for construction materials
occurred in the United States, as
defined in 2 CFR 184.6. The holder
would have to provide sufficient
documentation (e.g., purchase orders for
end products, materials, and supplies of
the facility; as-built or construction
plans) to demonstrate that the products
used in the energy generation facility
meet the thresholds identified in 2 CFR
part 184.
Once an energy generation facility
qualifies for a Domestic Content
reduction, the facility will continue to
benefit from the reduction for the term
of the grant or lease. The BLM will only
revisit the reduction at the time of an
assignment, amendment, or renewal of
an energy generation facility grant or
lease to determine what reduction, if
any, it may qualify for. The BLM will
apply the criteria defining the domestic
content preference and the components
of construction for the version of 2 CFR
part 184 in effect at the time the rightof-way is issued unless OMB amends
that guidance in the future in such a
way that the current definition
contemplated in this final rule no longer
provides a clear meaning. In that
circumstance, the BLM will apply the
most recent version of 2 CFR part 184
that provides a workable definition until
such time as the BLM is able to amend
its rules.
In addition to changing the definition
to qualify for a domestic content
reduction from a FAR to a BABA-based
definition, this final rule only provides
for a single 20 percent reduction that
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
interested parties qualify for if they
meet the requirements of 2 CFR part 184
instead of the incremental reduction
that the BLM had proposed. Under the
BABA definition described above,
projects qualify for the domestic content
preference by meeting or exceeding
specific materials requirements. As this
is a binary qualification, an incremental
reduction would be untenable. Further,
using a single reduction based on the
BABA threshold will provide for
simpler implementation of the
regulation and more clarity to
applicants.
One comment suggested that the BLM
use the Electronic Product
Environmental Assessment Tool
(EPEAT) product registry for
photovoltaic module use in
development projects and any Domestic
Content reduction. EPEAT is a global
label managed by the Global Electronics
Council that identifies environmentally
sustainable electronic products.
Currently, however, EPEAT only covers
a narrow set of products and
construction material related to solar
development facilities (specifically,
photovoltaic modules and inverters) and
does not cover any materials related to
wind energy generation facilities. As a
result, requiring applicants to use
EPEAT-registered products for
renewable energy facilities on public
lands could frustrate the goals of the
Domestic Content reduction. Further,
such a requirement would not serve the
purposes Energy Act of 2020 or relevant
direction in Executive Orders because it
would limit the technology that could
be deployed on public lands. The BLM
may, however, consider such criteria for
the Domestic Content reduction in the
future once the EPEAT covers a broader
range of solar and wind energy
materials. The BLM made no changes to
the final rule due to this comment.
Some comments suggested that the
BLM should require proof of
compliance with the domestic content
incentive prior to reducing rates. The
BLM agrees with these comments and
will require confirmation that the holder
seeking to obtain this reduction satisfies
the qualifying definitions the BLM is
utilizing: the standard in 2 CFR part
184. See § 2806.52(b)(5) regarding
conditional approvals where the BLM
makes it clear that approval will be
granted by the BLM once it has been
demonstrated to the satisfaction of the
BLM that the facility qualifies for the
reduction.
Some comments suggested that rate
reductions in the final rule should be
consistent with the IRA. The BLM
considered a reduction based on the
domestic content bonus tax credits in
PO 00000
Frm 00026
Fmt 4701
Sfmt 4700
the IRA and its definition of Buy
America bonus tax credits. The BLM is
aware that the Treasury Department has
issued guidance about the domestic
content bonus under the IRA for clean
energy projects and facilities that meet
American manufacturing and sourcing
requirements. However, that guidance
describes an intent to propose
regulations that have not yet been
finalized, and this final rule’s definition
for domestic content aligns with
definitions in other Federal programs
with oversight over domestic products
and content. No changes were made due
to these comments.
Paragraph (b)(1)(iv) is ‘‘D’’, the Project
Labor Agreement reduction. The BLM is
promoting the development of solar and
wind energy resources on public lands
by offsetting some of the costs when
using a PLA during construction of solar
and wind energy development projects
consistent with authority under the
Energy Act of 2020. The BLM’s
approach also is consistent with the
policy direction in Executive Order
14063 directing Federal agencies to use
PLAs in connection with large-scale
construction projects to promote
economy and efficiency in the context
of Federal procurement. A PLA is a prehire collective bargaining agreement
negotiated between one or more
construction unions and one or more
construction employers that establishes
the terms and conditions of employment
for a specific construction project,
consistent with 29 U.S.C. 158(f).
The 20 percent reduction of the
capacity fee offered in this final rule to
incentivize the use of a PLA is necessary
to promote the greatest use of solar and
wind energy resources on public land,
as authorized by the Energy Act of 2020
(43 U.S.C. 3003(b)(2). In particular,
PLAs lead to better and more efficient
outcomes in the construction of solar
and wind energy projects in the
following ways, which in turn leads to
the greatest use of solar and wind
resources. First, PLAs provide better
access to and retention of skilled
laborers, especially in a limited labor
market.8 Studies and reports
demonstrate that skilled labor provided
through PLAs offer a higher quality of
work, increased labor standards, more
timely construction, and fewer
8 Greg Lacurci, CNBC: Workers till Quitting At
High Rates—And Getting a Big Bump In Pay (Jan.
4, 2023); Jo Constantz, Bloomberg: The Great
Resignation Worked: Most Job-Swappers Got a
Raise (July 29, 2022); Frank Manzo IV, Larissa
Petrucci, & Robert Bruno, Ill. Econ. Policy Inst.: The
Union Advantage During the Construction Labor
Shortage 5 (2022).
E:\FR\FM\01MYR6.SGM
01MYR6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES6
deviations from construction plans.9
Second, PLAs improve workplace safety
by offering more apprentice-trained
journey workers, which studies have
shown lead to fewer injuries.10 Third,
PLAs can ensure construction
administration is streamlined, which
minimizes undue costs, delays, and
inefficiencies in construction projects,
particularly complex projects such as
wind or solar energy generation
facilities.11 Finally, PLAs contain nostrike, no-lockout clauses that can
prevent project construction delays
associated with labor disputes.12
The benefits associated with PLAs, in
turn, would have positive impacts for
renewable energy projects on public
lands, including ensuring responsible
and productive construction, and
minimizing the potential duration.
These improved construction standards
will better meet resource management
objectives and ensure authorized uses
on public lands are meeting the goal of
the Energy Act of 2020 to promote the
greatest use of solar and wind energy
resources. These improved construction
standards also are consistent with the
BLM’s authority under FLPMA to
incorporate right-of-way terms and
conditions that, among other things,
‘‘protect Federal property and economic
interests,’’ ‘‘manage efficiently the lands
. . . subject to the right-of-way,’’ and
‘‘protect lives and property.’’ (43 U.S.C.
1765(b)). Further, as demonstrated by
the reports and studies cited above, the
use of PLAs leads to higher and more
stable wages for workers. These
reductions to the rates will further
incentivize the use of PLAs by
developers and will help to offset higher
wages for workers, which, in turn, may
help to reduce or eliminate economic
hardships for workers who would
9 McFadden, Sai Santosh, and Ronit Shetty:
Quantifying the Value of Union Labor in
Construction Projects, Independent Project
Analysis, 2 and 8–9 (December 2022): https://
acrobat.adobe.com/link/review?uri=urn%3Aaaid%
3Ascds%3AUS%3Ad9e7f15b-9bf9-313f-b4ebde7a1dc11d9f; and Fred B. Kotler: Project Labor
Agreements in New York State II: In the Public
Interest and of Proven Value, Cornell University
ILR School, 10, 19 and 36 (May 1, 2011), https://
ecommons.cornell.edu/bitstream/handle/1813/
74333/LaborAgreementsinNYS_II.pdf?sequence=1.
10 Emma Waitzman & Peter Philips, UC Berkeley
Labor Ctr: Project Labor Agreements and Bidding
Outcomes: The Case of Community College
Construction in California 10, 16 (2017); Bureau of
Labor Statistics, National Census of Occupational
Injuries in 2021, USDL–22–2309 (2022)
(construction work is second highest for
occupational deaths).
11 Dep’t of Labor, Implementation of Project Labor
Agreements in Federal Construction Projects: An
Evaluation 20 (2011).
12 Dep’t of Labor, Implementation of Project Labor
Agreements in Federal Construction Projects: An
Evaluation 30 (2011).
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
otherwise not benefit from the higher
standards and protections in PLAs.
Some comments argued against the
use of the labor union incentives
included in the proposed rule and
questioned the BLM’s authority to offer
these incentives. Other comments
requested additional provisions be
added to ensure responsible use of
labor. As described above, the BLM has
concluded that, under the authority
provided in the Energy Act of 2020 and
FLPMA, it has discretion to include
reductions for the use of PLAs. These
reductions will incentivize the use of
PLAs, providing for increased
assurances of timely, efficient
construction; improved worker safety;
and higher and more stable wages for
workers. The BLM expects to publish
additional policy guidance, such as
through instruction memoranda, to
clarify how qualifying PLAs will be
identified, among other things. In
providing this reduction in the final
rule, the BLM is promoting responsible
use of labor and the greatest use of solar
and wind energy resources, as
authorized by the Energy Act of 2020,
by encouraging solar and wind energy
development on public lands.
Some comments suggested that the
rule should apply a tiered incentive for
developers based on the percentage of
local labor they commit to hire, which
could be implemented by certified
payroll reports that include employee
permanent addresses and in
consultation with local officials. Several
comments supported the inclusion of a
reduction for Union Labor or PLAs. In
the proposed rule, the BLM described
the potential of adding a 20 percent
capacity fee reduction for a holder’s use
of Union Labor or on the contingency of
a PLA. In this final rule, the BLM has
decided to include a reduction for
holders who have entered into, or
expect to enter into, a PLA for the
construction of a project, based on
comments and additional support for
the benefits of using PLAs to advance
infrastructure projects such as
renewable energy projects. This
additional reduction parallels the
domestic content reduction in this rule
in how it is applied in the calculation.
This reduction is based on the use of a
PLA in project construction and would
offset some developer costs. The BLM
does not include in this final rule the
suggested local labor reduction, but the
BLM believes the reduction for a PLA
may also support the use of local labor.
Paragraph (b)(1)(v) explains how the
BLM applies the alternative MWh rate
and the Domestic Content and PLA
reductions from paragraphs (b)(1)(ii),
(iii), and (iv) of this section. By default,
PO 00000
Frm 00027
Fmt 4701
Sfmt 4700
35659
the BLM will apply the ordinary MWh
rate under paragraph (b)(1)(i) and the
MWh rate reduction under paragraph
(b)(1)(ii). A developer who wished to
benefit from the alternative MWh rate,
the domestic content reduction, or the
PLA reduction will need to submit a
request for conditional approval prior to
the issuance of a grant or lease, along
with sufficient documentation to
demonstrate that the development
qualifies or may later qualify for these
rate reductions. In some cases, the BLM
will not be able to determine
definitively in advance whether the
proponent qualifies for these reductions.
The BLM may then conditionally
approve the requested reductions, but
the reductions will not go into effect
until the proponent adequately
demonstrates that the facility qualifies
for the relevant reduction. If energy
generation begins before the holder has
demonstrated that the facility qualifies,
the BLM will charge the holder the
capacity fee absent the reduction. The
capacity fee could be updated for
subsequent calendar years after the
holder demonstrates that the facility
qualifies, but the BLM will not refund
past payments made before the holder
demonstrates that they qualify and rate
reductions go into effect.
For example, an applicant or
presumptive leaseholder (see §§ 2809.13
and 2809.15, below) might request
conditional approval of an alternative
MWh rate. In that situation, a request for
conditional approval for an energy
generation facility may be granted if the
presumptive leaseholder has entered
into or intends to enter into a PPA (see
(b)(1)(i) of this section) that has a lower
rate than the MWh rate. Documentation
submitted to the BLM when requesting
conditional approval may include draft
or interim PPAs or confirmation in
writing from the purchasing party that
the parties have entered into
negotiations. While the BLM may then
conditionally approve the request for an
alternative MWh rate, the alternative
rate would not go into effect and be
used when calculating the payment
obligations until the PPA is finalized
and the BLM determines, in writing,
that the facility qualifies for the
alternative rate. The holder’s MWh rate
would then be updated for the next
year’s billing. Payments for past years
would not be adjusted retroactively.
In another example of a request for
conditional approval, an applicant or
presumptive leaseholder might request
conditional approval of a Domestic
Content reduction. In this example, a
request for conditional approval may be
granted if the proponent demonstrates
that it has firm plans to use items
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
35660
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
qualifying for the preference.
Documentation submitted to the BLM
when requesting conditional approval
may include procurement contracts or
design documents showing that the
facility would qualify for this reduction.
While the BLM may then conditionally
approve the request for a Domestic
Content reduction, the reduction would
not go into effect and be used to
calculate the proponent’s payment
obligations until the proponent submits
documentation of actual costs
associated with the construction of the
facility, such as fulfilled purchase
orders and as-built design documents
demonstrating installation of the
qualifying domestic content items in
that facility and the BLM determines, in
writing, that the facility actually
qualifies for the reduction. The holder’s
MWh rate then would be updated for
the next year’s billing. Payments for past
years would not be adjusted
retroactively.
Paragraph (b)(2) clarifies that ‘‘E’’ is
the annual adjustment factor, which is
set at three percent. This is the same
adjustment factor used for the annual
acreage rent under § 2806.52(a)(1)(iii).
See § 2806.52(a) of this preamble for
further discussion on the annual
adjustment factor.
The BLM understands that generally
when a solar or wind energy operator
begins generating electricity, it has
entered into an agreement with a utility
or other party to sell its power. It is
customary that such agreements include
an escalation clause that increases the
purchase price of power each year of the
agreement. These annual escalations
vary by agreement; however, in general,
the annual increase is approximately
one percent to five percent each year for
the contract term to account for gradual
decreases in system operational
efficiency, operating and maintenance
costs, and increases in the retail rate of
electricity. There may be some higher
annual escalation rates, but that is not
common. The BLM determined that a
three percent annual adjustment factor
is a reasonable escalation for the MWh
rate based on a review of the average
inflation rate over the previous fifteen
years. The BLM considered both an
adjustment for inflation that is
predictable and an adjustment that
changes more precisely with inflation
over time. The BLM determined that a
set inflationary adjustment that would
alter the starting electricity price per
MWh by a fixed factor each year was
preferrable, because it would increase
the predictability of future annual
payments. While it is possible that the
market price of electricity will deviate
from this fixed rate over time, the
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
benefit of rate predictability is
important to renewable energy
deployment on public lands. Future
inflation may be higher than the
historically low inflation of the decade
or more prior to 2019. To accommodate
the more recent inflationary trends, the
BLM relied on the IDP–GDP average
annual change for the most recent fiveyear period, 2018–2022 (estimating 2022
with data for three available quarters),
which was 3.36 percent, while taking
into account that for the ten-year period
preceding 2018, the rate was 1.52
percent. The BLM derived the 3 percent
rate in the final rule by rounding to the
nearest whole percent of the recent
inflationary trends.
Some comments requested that the
BLM remove the annual adjustment
factor or reduce it, possibly using the
prior year’s IPD–GDP calculation as an
adjustment factor. These comments
noted that the BLM should be
promoting the greatest use of solar and
wind energy resources and maximize
commercial interest in development on
public lands. Other commenters
suggested a higher annual adjustment
factor, noting that recent inflation
amounts are higher than the three
percent proposed.
The BLM considered a range of
annual adjustment factors, including
those based on IPD–GDP calculations.
The BLM’s use of three percent aims to
capture a reasonable annual adjustment
based on changes over time. This rule
promotes the greatest use of solar and
wind energy resources by applying and
offering reductions to the capacity fee
for qualifying developments.
Additionally, the BLM’s methodology
focuses on rate predictability; making a
recurring calculation using the IPD–GDP
is a disincentive for solar or wind
development because future rates
change by uncertain amounts making
the BLM rates unpredictable. This final
rule does not change the annual
adjustment factor due to these
comments.
The regular adjustment factor also
provides improved predictability of
rates over time for renewable energy
developers compared to the BLM’s
previous periodic adjustments of the
MWh fee, which were based on a
combination of the annual weighted
average wholesale price per MWh and
the adjusted rate of return for certain
U.S. Treasury Bonds, both of which are
variable.
Paragraph (b)(3) clarifies that ‘‘F’’ is
the year of the grant or lease term,
which is the same number used for the
annual acreage rent under
§ 2806.52(a)(1)(iv). See § 2806.52(a) of
PO 00000
Frm 00028
Fmt 4701
Sfmt 4700
this preamble for further discussion on
the year of the grant or lease term.
Paragraph (b)(4) clarifies that ‘‘G’’ is
the rate of return, which is set at seven
percent. By setting the rate of return in
this rule, the BLM increases the rate
predictability of its capacity fee. This
rate of return will not adjust during the
term of the authorization. In this final
rule, the rate of return is the
relationship of income to the total value
for a granted use of the public land
resource. The rate of return accounts for
the value of the authorization each year
for use of the resource on public lands
that is provided to the BLM through an
annual payment.
A comment recommended that the
BLM recalculate the rate of return using
a 30-year average rate of return for 10year Treasury Bond rates. The BLM
appreciates the suggested recalculation
of the rate of return over a 30-year
period. The BLM selected the 50-year
average of the 10-year Treasury Bond as
the reasonable rate to set its rate of
return for this rule. See the BLM’s
Regulatory Impact Analysis
accompanying this final rule for further
information on how the BLM calculated
the rate of return. No changes were
made in this final rule due to this
comment.
The 50-year simple (i.e., arithmetic)
average of the real annual return on 10year Treasury Bonds is approximately
seven percent. This 50-year period
includes times when the United States
went through periods of stagflation,
high inflation, economic boom, and
relatively calm market conditions. The
BLM’s use of the average of the 10-year
Treasury Bond rates is a reasonable
reflection of a modest return to the
government reflective of relatively low
risk to the public. The proposed seven
percent rate of return is also supported
by the Council of Economic Advisors,
which estimates a real return to U.S.
capital of around seven percent from
1960 to 2014 using data from the
National Income Product Accounts and
other sources.13 By setting the rate of
return in this final rule, it would not be
adjusted in the future, except by further
rulemaking.
One comment suggested that the rate
of return stay at two percent as currently
provided in BLM Manual 2806.60. The
comment further suggested that the
proposed increase from two to seven
percent does not appear to be reasonable
and is inconsistent with the Energy Act
of 2020. The updated rate setting
13 Council of Economic Advisers Issue Brief,
‘‘Discounting for Public Policy: Theory and Recent
Evidence on the Merits of Updating the Discount
Rate’’ (January 2017).
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
methodology in this final rule includes
an increased rate of return, consistent
with the BLM’s authority under FLPMA
to collect fair market value. The change
in the rate of return is commensurate
with other sectors of the energy market
that base their return on a percentage of
the commodity or energy generation
value. It is appropriate that the rate of
return change when transitioning from a
capacity fee based on nameplate
capacities to one based on the value of
energy generation at market. The former
rate setting methodology (see BLM
Manual 2806.60) implemented the
authority of the Energy Act of 2020 by
reducing the rate of return to two
percent. In this final rule, the BLM is
applying the authority of the Energy Act
of 2020 to the MWh Rate as reductions
under § 2806.52(b) instead of reducing
the rate of return. In this final rule, the
BLM has determined that reductions
under § 2806.52(b) for solar and wind
energy are more meaningful than the
reductions in the Manual 2806.60 and
are necessary to promote the greatest
use of solar and wind energy resources
on the public lands. The BLM did not
change this section of the final rule in
response to this comment.
Paragraph (b)(5) clarifies that ‘‘H’’ is
the annual energy generated on public
lands for the right-of-way in question.
The BLM will issue a bill to coincide
with the calendar year based on the
annual certified statement provided to
the BLM that gives either the amount of
estimated or actual electricity generated
by the development. The payment for
the first year of energy generation will
be based on an estimate of energy
generation, and then the BLM will
determine final payment for that first
year based on actual energy generation.
The following years of payments made
in advance, pursuant to 504(g) of
FLPMA, will be based on the most
recent calendar year’s actual energy
generation reported on the certified
statement. Exception to using actual
energy generation is provided for, in
certain circumstances, under paragraph
(b)(5)(vi) of this section. Paragraph (vii)
addresses late payments specific to
underestimating energy generation in
certain circumstances.
Paragraph (b)(5) has changed from the
proposed rule due to public comments.
The BLM proposed to require
developers to provide an estimate for
each year of energy generation of a
development project to calculate the
payment in advance. Those estimated
energy generation amounts would be
updated after that calendar year using
actual energy generation amounts and
any over or underpayment would be
determined at that time. Revisions to
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
this paragraph now provide in the
following subparagraphs that:
(i) The holder must submit an annual
certified statement to the BLM before
the first year of energy generation begins
or is scheduled to begin. Thereafter,
annual certified statements must be
submitted by the end of October.
(ii) Prior to the start of energy
generation, the holder must submit the
annual certified statement containing an
estimate of energy generation on the
right-of-way (estimate of first year’s
energy generation).
(iii) Once energy generation has
begun, the holder must submit to the
BLM an annual certified statement of
the most recent calendar year’s actual
energy generation on the right-of-way.
(iv) The BLM’s calculation for
payment of the capacity fee will be
based on the certified annual statement.
Calculation for payment of the capacity
fee for development projects that
contain both public and non-public
lands will be prorated by multiplying
the total energy generated by the
percentage of the total development area
made up of the right-of-way footprint on
public lands.
(v) If the year’s actual energy
generation exceeds or is less than the
amount of energy generation used to bill
for the payment in advance, the holder
will be billed, credited, or refunded for
the underpayment or overpayments
pursuant to §§ 2806.13(e) and 2806.16.
In no event will the total payment
required be less than the annual acreage
rent.
(vi) The BLM may approve a request
by a holder to provide a new estimate
of energy generation in certain
circumstances. Circumstances would
including those when energy generation
is expected to be interrupted, such as
with planned maintenance activities,
where the amount of energy generated is
expected to interrupt energy generation
by 25 percent or more, or where the
right-of-way holder is aware that the
energy generation in the subsequent
year will exceed the actual energy
generation for the previous year by 25
percent or more such that the BLM’s use
of the actual generation from the
previous year as the basis for a bill
would result in an underestimate of
more than 25 percent.
(vii) The BLM may assess a late
payment fee of 10 percent of actual
energy generation for the year in which
the underestimation occurs. The holder
will pay a late payment fee for each year
of underestimation if the right-of-way
holder underestimates energy
generation by 25 percent or more of the
actual energy generation or does not
provide the BLM with a new estimate
PO 00000
Frm 00029
Fmt 4701
Sfmt 4700
35661
when energy production will exceed the
previous year’s actual production by
more than 25 percent. The BLM may
decide not to assess the late payment if
the right-of-way holder provides an
adequate justification that the
underestimation was reasonably
unforeseeable prior to payment of the
annual bill, consistent with § 2805.12(e).
Some comments asserted that
penalties for underestimating generation
are inappropriate as factors outside of a
developer’s control, such as weather or
grid related interruptions, may cause
unexpected generation shortfalls.
Additionally, comments noted that
developers have every incentive to
maximize production, which may itself
cause a developer to underestimate
generation. The BLM has revised the
rule to reduce the potential that a holder
would be subject to a penalty while
minimizing the potential for
underestimation. Consistent with other
comments related to the term length
under 2801.9, the BLM has made
revisions to § 2806.52(b)(5) that are
consistent with revisions made under
§§ 2805.12(c)(8) and 2807.17(c). The
BLM revised paragraph (vi) and added
paragraph (vii) to this final rule due to
comments.
Pursuant to § 2805.12(c)(8), a holder
may receive a notice from the BLM of
their noncompliance with the right-ofway and that they are subject to rightof-way termination. Additionally, the
BLM may address a holder’s chronic
underestimation through existing
§ 2807.17(a), resulting in suspension or
termination of the authorization. The
BLM may make such a determination
after collecting relevant information,
including information provided
pursuant to § 2805.12(a)(15).
Some comments requested that the
rule preserve sensitive competitive
information amongst operators of solar
and wind energy development projects.
These comments suggested that the
BLM could allow developers to submit
generation data based on Form 923,
which is provided to the Energy
Information Administration. The final
rule does not carry forward the
suggested use of Form 923. The BLM
disagrees with waiting the additional
time to collect actual energy generation
and update or validate prior year bill
and payments with rights-of-way
holders. As suggested by commenters,
using Form 923 would delay billing for
actual energy generation amount by an
additional year, which is not acceptable
for the BLM’s responsible stewardship
of the public lands. No changes were
made due to this comment.
Section 2805.12(c)(8) sets the diligent
operation standards for solar and wind
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
35662
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
energy development projects and
provides steps to follow when a holder
expects to fail in meeting diligent
operation requirements. Holders may
follow the steps outlined in this section
to ensure compliance with this final
rule.
Paragraph (b)(6) of this section
describes where you may obtain a copy
of the current MWh rate schedule for
solar and wind energy generation.
Paragraph (b)(7) of this section
provides for periodic adjustments to the
MWh rate. This paragraph applies
unless you are an existing holder and
elect to continue paying under your
current rate adjustment method per
§ 2806.51(c).
Paragraph (b)(7)(i) of this section
clarifies that the rate from the MWh rate
schedule for the first year of energy
generation will not change once your
grant or lease is authorized. The annual
adjustment factor under
§ 2806.52(b)(1)(i) applies to the MWh
rate during the term of the grant or
lease. Any subsequent MWh rate
schedule updates will apply to new
grants and leases.
Paragraph (b)(7)(ii) of this section
provides that the MWh rate schedule
will be updated once every five years
consistent with the timing of acreage
rent adjustments. The MWh rate
schedule will include the annual
adjustment factor for the five-year
period it covers.
Paragraph (b)(8) of this section
provides that the general payment
provisions for rents under
§ 2806.14(a)(4) also apply to the
capacity fee.
Paragraph (c) applies unless you are
an existing grant or leaseholder and
elect to continue with your current MW
capacity fee adjustment method. The fee
is set at the time of authorization or reissuance and not adjusted further except
by the annual adjustment factor from
§ 2806.52(b)(2).
Some comments suggested that the
BLM should retain discretion under
§ 2805.12(e) to adjust rent and fee
values, including at the request of a
right-of-way applicant or holder. While
section 2805.12(e)(2) of this final rule
does not include a mechanism for
applicants or holders to request
alternative rent or fee rates in general,
the BLM has revised § 2806.52(b)(1)(i) to
identify circumstances where the BLM
would have discretion to select an
alternative MWh rate.
Some comments suggested a wide
range of potential fee structures to
address environmental and economic
factors. Some comments also requested
that the BLM clarify how the rents and
fee numbers were developed. The
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
BLM’s development of the acreage rent
and capacity fee was an iterative process
that included consideration of the
BLM’s legal authority; taxpayer
concerns for the collection of reasonable
rent for the use of public lands and
resources; the BLM’s prior policies for
rents and fees and their impact to solar
and wind deployment on public lands;
and the national renewable energy goals
on public lands set in section 3004 of
the Energy Act of 2020. The BLM
initially solicited comments in
September 2021 after which the BLM
published interim guidance in Manual
section 2806.60—Rent.
Some comments requested a
publication or annual report from the
BLM on the payments it has received
from solar and wind energy
development projects. This information
can be found in the BLM’s annual
publication of Public Land Statistics,
which enumerates annual revenues
from energy resources including wind
and solar rents and fees.
Some comments requested that the
BLM provide fee reductions for projects
that are sited on previously disturbed
lands or outside of sensitive wildlife
habitats. The BLM contemplated various
methods and models by which to
potentially apply rate reductions in this
final rule. Additional information on the
alternatives considered may be seen in
the proposed rule’s preamble discussion
under subpart 2806. The BLM
determined that an across-the-board
reduction best meets national energy
goals. This methodology provides
flexibility and financial incentives
without regard to where projects may be
sited. Having reduced rent and fee rates
that are independent of location
complements the BLM’s ability to
update land use planning, which
defines where project applications may
be proposed and where projects will not
become obsolete if or when technology
advances and siting needs shift for
economic or environmental reasons.
One comment suggested that a holder
should be able to select whether they
wish to pay an acreage rent or capacity
fee. The BLM disagrees with this
comment. This final rule clearly
provides for both an acreage rent or a
capacity fee for solar and wind energy
development projects. Generally, the
acreage rent is required for the intensity
of use and the occupancy, including site
control, of the surface of the public
lands. The capacity fee reflects the value
of the energy generated from the solar or
wind energy resource located on public
lands. The BLM will collect the greater
of either the acreage rent or the capacity
fee for a solar or wind energy
development.
PO 00000
Frm 00030
Fmt 4701
Sfmt 4700
One comment suggested rate
reductions be made available for
existing right-of-way holders who enter
into new PPAs for a project during the
term of an authorization, such as when
they repower. This final rule provides
for greatly increased rate predictability
for solar and wind energy development
rights-of-way. Under § 2806.52(b)(v), the
BLM provides an opportunity for
conditionally approving a reduction if it
receives a request with sufficient
documentation demonstrating that the
holder may qualify for the reduction
before the BLM issues the right-of-way.
No other opportunity for later qualifying
for a reduction is made available in this
rule as the reductions to its rates are
available prior to the BLM issuing the
ROW. The BLM believes that the
adjustments to improve rate
predictability, including allowing for a
longer term (see § 2801.9) for certain
rights-of-way, will provide for the
longer economical life of a particular
project. An operator or a holder of an
existing authorization may elect to keep
their current rate methodology,
including future adjustments that may
be made, if they do not wish to change
to the rate-setting methodology of this
final rule.
Some comments suggested that the 80
percent reduction of capacity fees
without any qualifying stipulations will
adversely distort the energy market and
land uses. The BLM does not expect this
final rule to alter the solar or wind
energy markets or uses of public lands
adversely. This final rule implements
the authority of the Energy Act of 2020
and direction of Executive Order 14008,
among others, that set goals to promote
the greatest use of solar and wind
energy resources on public lands. The
rule is intended to incentivize
development of wind and solar energy
projects on BLM-managed lands. The
BLM sees any resulting change that
benefits solar or wind in energy markets
as a positive development. See
Reductions and Discounts under 5.1 of
the Regulatory Impact Analysis for
further information on the 80 percent
reduction and the economic impacts of
the rule.
Some comments suggested that the
BLM should collect fair market value for
the use of federal lands under the BLM’s
rule. While FLPMA generally requires
the BLM to collect the fair market value
for the use of the public lands, the
Energy Act of 2020 provides the
Secretary of the Interior with additional
authority to reduce acreage rents and
capacity fees, including to less than fair
market value in certain circumstances.
The BLM is implementing this authority
to reduce the financial burden to solar
E:\FR\FM\01MYR6.SGM
01MYR6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
and wind energy developers to promote
the national interest of developing a
clean energy economy.
Section 2806.54 Energy Storage
Facilities That are Not Part of a Solar
or Wind Energy Development
Section 2806.54 clarifies that the rent
the BLM determines for an energy
storage facility that is not part of a solar
or wind energy development facility is
based on the linear rent schedule.
Energy storage facilities may be
authorized separately from a solar or
wind energy development facility. In
these instances, the BLM will apply the
linear rent schedule unless the BLM
determines that the linear rent schedule
does not apply to the underlying rightof-way use under § 2806.70, such as
when the BLM may determine that a
small site rent schedule applies to an
energy storage facility.
The BLM will not charge the rent or
fee of a solar or wind energy
development right-of-way for an energy
storage facility that is separate and
independent from a right-of-way for an
energy generation facility. Charging a
capacity fee would be inappropriate as
no energy generation from the facility
would be occurring from the use of
public lands. Using the pastureland
rents for energy storage would also be
inappropriate, as use of those acreage
rates is intended to be coupled with the
capacity fee to determine solar and
wind energy generation payments for
use of public lands.
Sections 2806.60 through 2806.68 are
removed from the final rule. Information
formerly contained in these sections is
now found in sections 2806.50 through
2806.58.
Subpart 2807—Grant Administration
and Operation
ddrumheller on DSK120RN23PROD with RULES6
Section 2807.17 Under what
conditions may BLM suspend or
terminate my grant?
Section 2807.17 of this final rule is
updated based upon comments on
§ 2801.9 regarding term length and
updates to § 2805.12 regarding new
diligent operation requirements for solar
and wind energy development. See the
respective sections of this preamble for
further information on the term length
and the terms and conditions of grants
and leases for solar and wind energy.
Section 2807.17(c) provides that the
BLM may suspend or terminate a rightof-way upon abandonment. The BLM
presumes that a right-of-way holder has
abandoned its right-of-way by failing to
use it for a continuous 5-year period,
except for solar and wind energy. Solar
and wind energy rights-of-way are
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
presumed to be abandoned after two
continuous years of insufficient
productivity or upon abandonment.
This section is updated consistent with
the new provision in § 2805.12(c)(8),
which provides for a holder to receive
notice of the BLM’s presumption and
gives a reasonable time to cure the
noncompliance with the diligent
operations requirement.
Section 2807.20 When must I amend
my application, seek an amendment of
my grant or lease, or obtain a new grant
or lease?
Section 2807.20 describes when a
right-of-way applicant must seek to
amend its application, grant, or lease.
Paragraph (b) clarifies that ‘‘except for
qualifying energy development grants
and leases per § 2806.51(c),’’ the
requirements for amending an
application or grant are the same as
processing a new application, including
payment of processing and monitoring
cost recovery fees. Section 2806.51(c)
provides a unique exception for existing
solar and wind energy rights-of-way
authorized before this final rule that
may convert to the rent adjustment
methodology of this final rule. See
§ 2806.51(c) of this preamble for further
information on qualifying
authorizations.
Paragraph (f) describes how the BLM
would administer an approved solar and
wind energy grant or lease if the holder
requests to change the rent adjustment
methodology. Any request would have
to be received within 2 years of the date
this rule becomes effective and would
be processed as an amendment by
which the BLM would re-issue the grant
or lease and update the terms and
conditions under § 2805.12 and rent
provisions under §§ 2806.50 through
2806.52. The BLM would be able to
collect or use processing and monitoring
costs under §§ 2804.14 and 2805.16 for
handling the request. See § 2806.51(c)
for further discussion regarding requests
to use the rent adjustment methodology
of this rule.
One comment suggested that State
and local governments should have a
shared decision-making role with the
BLM when the BLM considers reissuing a grant or lease to convert the
right-of-way over to the new rate
adjustment methodology. The BLM does
not agree with the suggestion that State
or local government offices should share
in a decision-making role when the
BLM decides whether to authorize a
change to the rent adjustment
methodology. Re-issuing an
authorization under this final rule is an
administrative action that will convert
existing authorized projects to the new
PO 00000
Frm 00031
Fmt 4701
Sfmt 4700
35663
rate setting methodology for the use of
BLM-administered public lands and
resources. The BLM will continue to
engage with the public, and Tribal,
Federal, State and local government
partners on the BLM’s management of
its public lands, as appropriate. The
BLM did not change this section of the
final rule.
Section 2807.21 May I assign or make
other changes to my grant or lease?
Section 2807.21 describes the
requirements for a holder seeking to
assign or make other changes to a grant
or lease.
Paragraph (e) clarifies that when the
BLM assigns a right-of-way from one
holder to another, it may modify a grant
or lease, such as by adding additional
terms and conditions. The paragraph
exempts solar and wind energy leases
from that provision unless
modifications are warranted under
§ 2805.15(e), which provides for
changes to terms and conditions as a
result of changes in legislation,
regulation, or as otherwise necessary to
protect the public health or safety or the
environment. This final rule removes
provisions that distinguished between
inside and outside DLAs for solar and
wind energy development. The BLM
may assign leases inside of DLAs
without competition.
One comment suggested that the BLM
should retain the authority to impose
additional requirements on solar and
wind projects. The commenter
expressed concern that the BLM may be
constrained when it comes to regulating
a bad operator especially with regards to
excepting a bond requirement and that
bond requirements should be mandatory
on solar and wind projects, so the BLM
does not have to clean up sites after
company closure or refusal to perform
reclamation. The BLM requires a bond
for all solar and wind energy grants and
leases. The BLM requires this bonding
upfront to cover reclamation costs and
to enforce the terms and conditions,
such as those for rent and capacity fees.
Paragraph (e) provides that the BLM,
when assigning a grant or lease to a new
holder, may modify the right-of-way and
add bonding and other requirements,
including additional terms and
conditions, except for wind and solar
leases which the BLM can only modify
when warranted as a result of changes
in legislation, regulation, or as
otherwise necessary to protect public
health or safety or the environment as
reflected in § 2805.15(e). The BLM also
has diligent development and operation
requirements, among other terms and
conditions, in § 2805.12 that further
ensure a holders’ compliance with the
E:\FR\FM\01MYR6.SGM
01MYR6
35664
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
right-of-way authorization and all its
requirements. The BLM did not change
this section of the final rule.
ddrumheller on DSK120RN23PROD with RULES6
Subpart 2809—Competitive Process for
Solar and Wind Energy Development
Applications or Leases
Subpart 2809, ‘‘Competitive Process
for Leasing Lands for Solar and Wind
Energy Development Inside Designated
Leasing Areas’’ is dedicated to
competitive solar and wind energy
processes. In the final rule, Subpart
2809 generally applies the same
competitive process both within and
outside DLAs.
Section 2809.10 Competitive Process
for Energy Development Grants and
Leases
Section 2809.10, ‘‘Competitive
process for energy development grants
and leases,’’ applies to public lands
located both inside and outside of
DLAs. Paragraphs (a) through (d)
explain that the BLM may conduct a
competitive process to consider solar or
wind energy development applications
or leases: (1) on its own initiative; (2)
based on responses to a call for
nominations; (3) based on a request
submitted by a member of the public in
writing; or (4) when it receives two or
more competing applications. These
provisions incorporate the BLM’s broad
discretion under FLPMA to determine
under what circumstances it may utilize
a competitive process. This section is
revised to replace ‘‘offer’’ with
‘‘process’’ to remain consistent with this
section’s requirements for solar and
wind energy development grant and
leases competitive process.
The BLM has determined that it will
implement its discretion under FLPMA
to potentially utilize a competitive
process for lands both inside and
outside of DLAs and thus standardize a
competitive process where competitive
interest exists. More specifically, the
BLM will use the most appropriate
process given the circumstances of a
particular location, spurring more
competition for the most desirable areas,
while continuing to increase solar and
wind energy deployment consistent
with the statutory direction in the
Energy Act of 2020.
As proposed, prior paragraph (d) is
removed consistent with changes made
under § 2804.35(b) and elsewhere in
subpart 2809. The BLM has discretion to
process applications inside DLAs
without going through a competitive
process. Accepting applications inside
DLAs reduces timelines and costs and
removes barriers for considering
development projects where there is no
competitive interest.
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
Proposed § 2809.10(e) would have
precluded the BLM from holding a
competitive process when the BLM has
accepted a complete application,
received a Plan of Development, entered
into a cost recovery agreement, and
published an EA or Draft EIS. Industry
comments suggested that the BLM
commit to not holding a competitive
process earlier than in the proposed
rule. In response to those comments, the
final rule establishes that the BLM will
not initiate a competitive process for
those lands where the BLM has
accepted a completed application,
received a Plan of Development, and
entered into a cost recovery agreement,
while removing the requirement that the
BLM must have published an EA or a
draft EIS.
The final rule also adds to
§ 2809.10(e) an exception referencing
§ 2804.25(c). Even where the BLM has
accepted a complete application,
received a Plan of Development, and
entered into a cost recovery agreement,
it may nonetheless offer lands in a
competitive process if the applicant has
not proceeded diligently as required by
§ 2804.25(c). These amendments give
the industry the certainty it needs to
proceed with projects while retaining
the BLM’s discretion to deny an
application or offer lands competitively
if the applicant does not proceed
diligently. In that way, these
amendments balance the BLM’s
obligations to incentivize renewable
energy development on public lands
and to recover a fair return for U.S.
taxpayers.
Some comments suggested that
requiring a competitive leasing process
in designated leasing areas has helped
ensure that only well-thought-out
projects are proposed. These
commenters raised concerns that
eliminating a required competitive
process will cause a rush of poorly
planned projects and will decrease use
of the designated leasing areas. Several
comments argued in favor of requiring
a competitive process in designated
areas, emphasizing that it shifts the
burden from taxpayers to those who
stand to profit, validates demand,
increases financial return for use of
public lands, drives innovation, and
ensures transparency and fairness in the
process. These comments expressed
concerns that non-competitive leasing
may discourage investment and lead to
inefficiencies.
In this final rule, the BLM’s change in
the use of competitive processes is
intended to provide flexibility in
addressing interest in the use of public
lands for solar and wind energy and will
not allow for or authorize poorly
PO 00000
Frm 00032
Fmt 4701
Sfmt 4700
planned projects. The BLM retains its
discretion to authorize or deny solar or
wind energy development projects. As
explained in the preamble to the
proposed rule, the requirement to
undertake competitive processes for all
applications in DLA’s extends the
timeline and increases costs, creating a
barrier for authorizing projects in areas
where there is no competitive interest.
The BLM has broad discretion under
FLPMA to determine under what
circumstances it may utilize a
competitive process for lands both
inside and outside of DLAs and to use
competitive processes only where
competitive interest exists. The BLM
anticipates that accepting applications
in DLAs without the prerequisite of
holding a competitive process will
likely generate more applications in the
most desirable locations. The final rule
also provides the BLM with the
flexibility to utilize a competitive
process where there are multiple
competing applications. The purpose of
these changes is to ensure that the BLM
can use the most appropriate process
given the circumstances of a particular
location, which the BLM believes will
spur more competition for the most
desirable areas, while continuing to
increase solar and wind energy
deployment consistent with the
statutory direction in the Energy Act of
2020.
For the same reasons, the BLM
disagrees with the comments that
focusing the BLM’s competitive process
and resources to where there is
competitive interest on public lands is
a negative impact to taxpayers, demand,
financial return, innovation, and
transparency. This final rule improves
transparency over all processes of the
BLM’s administration of applications
and right-of-way authorizations and
achieves the goals set by the Energy Act
of 2020 and direction of Executive
Order 14008. Moreover, although DLAs
represent areas specifically designated
for renewable energy development, they
are not the only areas where such
development may be appropriate, nor
are they the only areas where use of a
competitive process may be appropriate.
These projects are complex and require
many different steps and actions to
occur to be successful. The BLM
believes offering areas outside of DLAs
for a competitive process is appropriate
and would help to meet the goals of the
Energy Act of 2020 and direction of
Executive Order 14008.
Some comments suggested leasing
should not be competitive, or at least
only be considered in specific
circumstances, such as when multiple
applications for the same area are
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
submitted or when certain conditions
are met, such as when labor agreements
are not used. This section of the final
rule clarifies when the BLM may
conduct a competitive process,
including for competing applications
under paragraph (d). The BLM disagrees
that attaining an agreement to use
certain labor should determine whether
the BLM holds a competitive process or
not. The BLM’s discretion to hold a
competitive process includes when
there is competitive interest for that
system or land or upon the BLM’s own
initiative, among other reasons
identified in this section of the rule.
Some comments highlighted the
interest in a clear and standardized
process and suggested that the potential
for competition should be limited to
avoid deterring investment. In this final
rule, the BLM has provided a clear
process that the BLM will follow for
solar and wind energy development
projects when a competitive process is
held. However, the BLM does not agree
with comments to limit competition.
The BLM will generally hold a
competitive process where there is a
competitive interest, whether it is inside
or outside of designated leasing areas, or
on its own initiative.
Other comments recommended
adding steps to ensure no competition
exists before processing applications
without a competitive process.
Suggestions given to the BLM include
filing a notice in the local newspaper,
online, or in the Federal Register
whenever the BLM receives an
application requesting any other
applications to be submitted. This final
rule does not include provisions to
require solicitation of public interest
with every application submitted to the
BLM for a solar or wind energy
development. The Energy Act of 2020
and direction of Executive Order 14008
are clear in seeking expedited
deployment of renewable energy
projects on public lands. Adding
provisions in the BLM’s rules that
require additional steps to solicit
competitive interest where there may
not be any may slow the deployment of
renewable energy. Historically, the
majority of solar and wind rights-of-way
authorized on BLM-administered public
lands have been authorized after an
application process without a
competitive process, and there are only
six existing competitively issued leases,
which is only approximately six percent
of authorized development projects on
public lands. You may find information
on the BLM’s authorized and pending
solar and wind energy projects on its
website at: https://www.blm.gov/
programs/energy-and-minerals/
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
renewable-energy/active-renewableprojects. More specifically, since the
BLM began using competitive processes
for permitting solar leases on BLM
public lands, the agency has held five
competitive processes for 16 parcels.
These have resulted in multiple bids for
nine parcels, a single bid for three
parcels, and no bids for four parcels. In
the circumstances that BLM held a
competitive process and received no
bids, the BLM had previously received
several expressions of interest and
applications for those public lands. The
BLM then held a competitive auction
resulting in no bids for three parcels.
The BLM did not change this section of
the final rule.
A comment requested that the final
rule clarify when the BLM will not
require an auction. The BLM does not
believe additional clarification is
necessary, as § 2809.10(e) provides that
the BLM would not offer lands through
a competitive process when the BLM
has accepted a completed application,
received a Plan of Development, and
entered into a cost recovery agreement.
One comment suggested that the final
rule clarify that the BLM should be
precluded from using a competitive
process to award a solar or wind energy
development lease or grant on an area
of public lands once an applicant has
either submitted a right-of-way
application for solar or wind energy
development or made substantial
investments in potentially developing
that area of the public lands. While the
proposed rule provided that BLM would
not offer lands in a competitive process
if four criteria were met, this final rule
removes the fourth proposed criterion in
section (e): ‘‘on publication of an
Environmental Assessment or Draft
Environmental Statement.’’ The final
rule retains the first three, such that the
BLM would not offer lands in a
competitive process for which it has
accepted a complete application (see
§ 2804.12(j)), received a Plan of
Development (see § 2804.12(b)), and
entered into a cost recovery agreement
(see § 2804.14). This change requires
fewer milestones to close the window
for holding a competitive process than
the proposed rule and improves
certainty for interested developers to
proceed with applications but it does
not move the threshold for prohibiting
competitive processes earlier than in the
existing regulations as the commenter
suggested.
In addition to the changes under
2809.10(e), the BLM revised § 2804.25(c)
to clarify that the BLM retains discretion
to deny an application where the
applicant does not proceed diligently.
An applicant’s failure to remain diligent
PO 00000
Frm 00033
Fmt 4701
Sfmt 4700
35665
in processing an application may result
in the BLM denying the application and
offering the lands competitively. These
amendments balance the BLM’s
obligations to incentivize renewable
energy development on public lands
and to recover a fair return for U.S.
taxpayers.
A comment suggested that the BLM
should not require a competitive
process where an applicant’s facilities
are located on both private and federal
lands and the applicant has secured
agreements with the adjacent
landowners. This final rule governs the
BLM’s administration of applications
and authorizations, including
competitive processes. The BLM will
consider all relevant and available
information when determining whether
a competitive process is appropriate,
including whether separate agreements
had already been met for adjacent lands.
However, this rule does not preclude
the BLM from holding a competitive
process when agreements are held for
adjacent lands, which would allow
developers and adjacent landholders to
effectively monopolize the use of the
public lands without first obtaining
authorization from the BLM. In
instances where the BLM believes it is
appropriate, it may determine to hold a
competitive process.
Other commenters suggested that the
BLM should only have the discretion to
move to a competitive process in the
initiation phase of a project and not
after an application is complete and the
cost recovery is funded. This final rule
maintains the BLM’s discretion to
determine whether there is a
competitive interest in the public lands.
In the BLM’s experience, some
applications progress more slowly than
others once the existing requirements of
the BLM rules are met. By requiring a
complete application pursuant to
§ 2804.12(j), a Plan of Development
pursuant to § 2804.12(b), and a cost
recovery agreement pursuant to
§ 2804.14, the BLM will help ensure that
applicants remain diligent in pursuing
their use of the public lands, while
preserving discretion to utilize a
competitive process. Even after that
point, § 2804.25(c) of the final rule
clarifies that the BLM retains discretion
to deny an application where the
applicant does not proceed diligently.
These additional conditions will not
unreasonably burden diligent applicants
and will help identify those applicants
who are not working with the BLM to
process applications diligently.
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
35666
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
Section 2809.11 How will the BLM call
for nominations?
Section 2809.11 is retitled to improve
consistency with this section of the final
rule. No changes were made to this
section due to comments. Consistent
with the change in terminology of
§ 2809.10, the BLM changed ‘‘offer’’
with ‘‘process’’ throughout this section.
Paragraph (a) provides that the BLM
may publish a notice in the Federal
Register calling for nominations of
lands to be offered through a
competitive process for solar and wind
energy development. Other notification
methods may also be used, such as a
newspaper of general circulation in the
affected area or the internet. The section
allows for the BLM’s discretionary use
of a competitive process discussed in
§ 2809.10. The paragraph would also
specify information that will be
included in a call for nominations as
follows:
(1) The date, time, and location by
which nominations must be submitted;
(2) The date by which nominators will
be notified of the BLM’s decision on
timely submissions;
(3) The area or areas for which
nominations are being requested; and
(4) The qualification for a nominator,
which must include at a minimum the
requirements for an applicant, see
§ 2803.10.
Paragraph (b) provides the
requirements for nominating a parcel of
land for a competitive process.
Paragraph (b)(1) requires payment of $5
per acre for nominated parcels. The
nomination fee is collected by the BLM
under its cost recovery authority under
Sections 304(b) and 504(g) of FLPMA,
and the portion not spent in processing
the nomination and preparing for a
competitive process may be refunded to
the nominator if not successful in the
competitive process. These fees
reimburse the BLM for the expense of
preparing and holding a competitive
process.
Paragraph (b)(2) requires the
nomination to include the nominator’s
name and address of record. This
information is necessary for the BLM to
communicate with the nominator about
a future competitive process for the
parcel.
Paragraph (b)(3) requires that a
nomination be accompanied by a legal
land description and a map of the parcel
of land. This information helps identify
nominated parcels for the competitive
process.
Paragraph (c) provides that the BLM
will not accept nomination submissions
that do not comply with this section or
from submitters who are not qualified
per § 2803.10 to hold a grant or lease.
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
Paragraph (d) provides that a
nomination cannot be withdrawn except
by the BLM for cause, in which case the
nomination fee would be refunded.
Paragraph (e) provides that the
decision whether to hold a competitive
process in response to a nomination lies
in the BLM’s discretion.
Some comments requested that the
BLM make the nomination fee nonrefundable. One comment further
suggested that the BLM require ‘‘skin in
the game’’ from project proponents and
that the BLM should keep the fee to
cover at least any reasonable costs it
incurred in pursuing the nomination.
The BLM agrees with comments
suggesting that the fee should be used
in recovering its reasonable costs in
processing the nomination and
preparing for a competitive process. The
BLM’s authority under Sections 304(b)
and 504(g) of FLPMA allows for the use
of these funds in processing
applications. Per existing rules, the BLM
may refund the balance, if any, of
collected cost recovery funds when they
are no longer needed. Please see existing
subpart 2804, starting with § 2804.14,
for more information on the BLM’s
administration of cost recovery fees.
Section 2809.12 How will the BLM
select and prepare parcels?
Section 2809.12 describes how the
BLM identifies parcels suitable for
competitive processes. The BLM did not
make changes to this section of the final
rule in response to comments received,
except that, consistent with the change
in terminology of prior sections, the
BLM changed ‘‘offer’’ to ‘‘process’’
throughout this section. The BLM also
removed ‘‘on existing’’ when describing
land use designations to avoid
confusion and clarify that only existing
land use designations may be
considered.
Paragraph (a) clarifies that the BLM
may rely on any information it deems
relevant in identifying parcels for
competitive processes, but also
describes more precisely the most
common sources of information, which
include public nominations and existing
land use designations. The BLM is not
constrained to consider only these listed
sources of information when deciding
whether to conduct competitive
processes for certain parcels.
Paragraph (b) clarifies that the BLM
may conduct necessary studies and site
evaluation work, including applicable
environmental reviews and public
meetings, either before or after offering
lands for a competitive process. The
BLM has sometimes found that the
necessary studies and site evaluation
work cannot be completed until the
PO 00000
Frm 00034
Fmt 4701
Sfmt 4700
competitive process is held and the
successful bidder has submitted an
application or Plan of Development. The
BLM must complete site-specific NEPA
analysis even when the BLM has
identified a successful bidder as the
presumptive leaseholder. The BLM
retains discretion to approve, approve
with modification, or deny a proposed
energy development.
The BLM revised the language of
proposed paragraph (c) to clarify that it
is the BLM’s choice whether to use a
competitive process or not and that such
choices do not constitute a decision to
approve or deny a grant or lease and are
not subject to appeal under 43 CFR part
4.
A comment suggested that under
paragraph (c), the final rule should
allow for administrative appeals, as it
relates to BLM procedures used to make
decisions. Paragraph (c) of the final rule
clarifies that the BLM’s choice about
whether to use a competitive process is
not a decision to grant or deny a rightof-way or otherwise final agency action;
instead it represents only an
intermediate step that may or may not
lead to a decision. The public’s ability
to administratively appeal an agency
decision to grant or deny a right-of-way
is unaffected by this provision. The
BLM will continue to provide ample
opportunities to the public for
engagement throughout both the
competitive and non-competitive
permitting processes. An appeal may be
considered when the BLM issues a
decision under 43 CFR part 2800.
A comment suggested that allowing
for an administrative appeal process to
challenge a BLM choice to use a noncompetitive process would assist the
BLM in identifying whether there is any
competitive interest in the public land,
getting a better return for the public.
The BLM disagrees with this comment.
Administrative appeals may be
submitted only for agency decisions (see
existing § 2801.10). Additionally,
allowing for administrative appeals over
interim choices by the BLM about
which procedures to follow to reach a
decision would likely delay its decisionmaking process substantially.
Section 2809.13 How will the BLM
conduct competitive processes?
Section 2809.13 is retitled from the
proposed rule consistent with other
changes to replace ‘‘offer’’ with
‘‘process.’’ The change from the
proposed rule to read ‘‘process’’ when
describing the BLM’s competitive
process is made throughout this section
when appropriate.
This section describes how the BLM
conducts competitive processes.
E:\FR\FM\01MYR6.SGM
01MYR6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES6
Paragraph (b) provides that the BLM
publishes a notice of competitive
process in the Federal Register and
through other notification methods,
such as a newspaper of general
circulation in the area affected or the
internet. Paragraph (b)(7) clarifies that
the notice of competitive process would
state whether a successful bidder would
become a preferred applicant or a
presumptive leaseholder. Preferred
applicants are required to meet
application submission requirements
under § 2804.12, and presumptive
leaseholders are required to submit a
Plan of Development per § 2809.18. The
preferred applicants and presumptive
leaseholders are discussed further in
§ 2809.15.
Under paragraph (c) of this final rule,
the BLM will notify nominators of its
decision to conduct a competitive
process at least 30 days in advance of
the bidding for the lands that were
nominated if the nominator has paid the
nomination fees and demonstrated
qualifications to hold a grant or lease.
Some comments suggested that under
paragraph (b)(7) the BLM should
continue to require a successful bidder
to submit a Plan of Development. The
BLM agrees with these comments. A
Plan of Development is required in this
final rule by a presumptive leaseholder
under paragraph 2809.15(a)(ii) and by a
preferred applicant who would follow
the application process for solar and
wind energy applications, including the
submission of a Plan of Development
required under § 2804.25(c).
Section 2809.15 How will the BLM
select the successful bidder?
Section 2809.15 explains how the
successful bidder is selected. In this
final rule, the distinction between
preferred applicants and presumptive
leaseholders reflects the fact that the
BLM may conduct competitive
processes in a variety of circumstances
with different outcomes. The distinction
between presumptive leaseholder and
preferred applicant is intended to
ensure that the BLM can expedite
approval of proposed projects in areas
where the environmental impacts of
solar and wind energy development
have been previously analyzed and
disclosed through a land use planning
process. This will help ensure that the
BLM does not commit public land
resources before completing the
necessary analyses. This section is also
revised, consistent with other changes
in this rule, to refer to ‘‘process’’ where
appropriate when describing the BLM’s
competitive process.
Paragraph (a) of this final rule
provides that the highest bidder, prior to
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
any variable offsets, is the successful
bidder. Successful bidders may become
either the presumptive leaseholder or
the preferred applicant.
The term ‘‘presumptive leaseholder’’
describes situations in which at least
one round of environmental review for
solar or wind energy development has
been conducted before the competitive
process is held, so that the
environmental impacts of potential
development are relatively well
understood before the competitive
process is held and the successful
bidder has a high likelihood of being
able to obtain an authorization to
develop its proposed project. As set
forth in paragraph (b)(1)(i), a successful
bidder would only be designated as a
presumptive leaseholder if the lands for
which the competitive process is held
are located within a DLA and the BLM
has indicated in advance that the
successful bidder would become a
presumptive leaseholder (see also
§ 2809.13(b)(7)). These requirements
would limit the use of the term
‘‘presumptive leaseholder’’ to situations
in which the BLM has previously
completed an environmental analysis
for solar or wind energy development in
the area through the land use planning
process and has specified in advance
(through the notice of competitive
process) many of the terms, conditions,
and mitigation measures that would
need to be incorporated into an
approved authorization. A presumptive
leaseholder does not have to complete
the initial application review stage,
which is designed to ensure that the site
is generally appropriate for solar or
wind energy development. A
presumptive leaseholder has site control
for a solar or wind energy development,
precluding other competing solar or
wind energy development projects from
siting on that land, unless allowed by
the presumptive leaseholder. The BLM
would also not process other
applications for use of that land unless
allowed by the presumptive leaseholder.
This final rule also recognizes that
even with a presumptive leaseholder, an
additional site-specific environmental
analysis may be required before the
BLM irretrievably commits to allowing
a facility to be developed. The BLM
retains its full discretion in considering
whether to approve a presumptive
leaseholder’s proposal based on sitespecific environmental analysis, which
would typically be tiered to the areawide environmental analysis
accompanying the identification of the
area as a DLA. Paragraph (b)(1)(ii)
therefore notes that the presumptive
leaseholder’s right to develop a project
on the site is contingent upon the BLM’s
PO 00000
Frm 00035
Fmt 4701
Sfmt 4700
35667
approval of the presumptive
leaseholder’s Plan of Development.
Once the BLM approves the proposed
Plan of Development, following a sitespecific environmental analysis, a lease
could be awarded, conferring a right to
develop a project on the site, and the
presumptive leaseholder would become
a leaseholder.
In other cases, the BLM could conduct
a competitive process without having
completed an initial environmental
analysis for solar or wind energy
development for that area. In such cases,
as set forth in paragraph (b)(2), the
successful bidder would become the
‘‘preferred applicant’’ and would obtain
only the exclusive right to submit an
application for solar or wind energy
development on that site without
further competition from other
applicants for solar or wind energy
development. Such an application
would be processed under subpart 2804
in the same manner as other, noncompetitive applications. The BLM
would conduct a full environmental
analysis before the preferred applicant
may obtain a grant and the right to
develop a project on the site. A
preferred applicant that fails to meet the
requirements of subpart 2804 may lose
their status as the preferred applicant,
and the BLM may deny their application
consistent with § 2804.26.
Paragraph (b) provides that a
successful bidder becomes a
presumptive leaseholder or preferred
applicant only after making payments
required in paragraph (d) of this section
and satisfying the requirements for
holding a grant or lease under § 2803.10.
The BLM could move on to the next
highest bidder or re-offer the lands
under § 2809.17 if the successful bidder
does not satisfy these requirements.
Paragraph (b)(1) describes the
requirements to become a presumptive
leaseholder, which are that the public
lands successfully bid upon are located
within a DLA and that the notice of
competitive process indicated
successful bidders would become
presumptive leaseholders. This
paragraph also provides that the BLM
would only award a presumptive
leaseholder a lease if the BLM approves
the Plan of Development that is
submitted in accordance with
§ 2804.25(c).
Paragraph (b)(2) describes the
requirements for a preferred applicant.
A successful bidder who does not
become a presumptive leaseholder in
accordance with paragraph (b)(1) would
become a preferred applicant. The BLM
would process applications for a grant
or lease under § 2809.12. As with
presumptive leaseholders, approval of a
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
35668
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
preferred applicant’s application is not
guaranteed. However, the BLM would
not process other applications for solar
and wind energy development on lands
where a preferred applicant has been
identified, unless allowed by the
preferred applicant.
The BLM may consider issuing
authorizations for other uses, such as
roadways, testing facilities, recreation
permits, or even rights-of-way under
MLA authority on the lands for which
there is a preferred applicant.
Processing authorizations for other uses
under Title V of FLPMA would be
performed under subpart 2804.
Recreation permits and rights-of-way
under MLA authority would be
processed under parts 2920 and 2880,
respectively. In some instances, such as
with applications for incompatible uses,
the BLM may determine that the
proposed uses would be incompatible,
and therefore that processing these other
applications must wait until it issues a
decision on a preferred applicant’s
application for solar or wind energy
development.
Previous paragraphs (b) and (c) are
redesignated as (c) and (d) respectively.
Redesignated paragraph (c) is not
revised; it provides that the BLM will
determine variable offsets for the
successful bidder in accordance with
§ 2809.16.
Redesignated paragraph (d) provides
for bidder payment terms. Paragraph
(d)(1) provides for certain payment
methods, such as personal check,
cashier’s check, certified check, bank
draft, or money order, as well as other
methods deemed acceptable by the
BLM, should be paid to the Department
of the Interior—Bureau of Land
Management.
Paragraph (d)(2) requires payment of
20 percent of the bonus bid and the
minimum bid amount by the close of
official business hours on the day on
which the BLM conducts the
competitive process or other time the
BLM has specified in its notice.
Paragraph (d)(3) requires payment of
the balance of the bonus bid within 15
days after the day on which the BLM
conducts the competitive process.
Variable offsets are applied under
paragraph (c) of this section. Such
payments are made to the BLM office
conducting the competitive process.
Paragraph (d)(4) requires payment
within 15 days after the day on which
the BLM conducts the competitive
process to pay: for preferred applicants,
the application filing fee under
§ 2804.12(c) less any application fee
already paid under § 2809.11(c)(1); or
for presumptive leaseholders, the
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
acreage rent for the first full year of the
lease as provided in subpart 2806.
Paragraph (d)(5) clarifies that the BLM
may require successful bidders to pay
reasonable costs in addition to the
application filing fee when processing
an application. Additional reasonable
costs may include a Category 6 cost
recovery for the BLM to complete
processing the application. If a Category
6 cost recovery fee is required, it will be
reduced by the amount of the
application filing fee already paid. See
§ 2804.19 of existing regulations for
further information on Category 6 cost
recovery.
Paragraph (e) explains that the
successful bidder will not become a
preferred applicant or a presumptive
leaseholder and the BLM will keep all
money that has been submitted with the
competitive process if the successful
bidder does not satisfy the payment
terms under paragraph (d) of this
section. In such a case, the BLM could
proceed to the next highest bidder or reoffer the lands through a competitive
process under § 2809.17.
A comment questioned the rationale
behind determining the highest bidder
as the presumptive leaseholder instead
of the BLM making an offer to the
highest bidder. The commenter
suggested that the BLM would then offer
the lease to subsequent bidders if the
preceding highest bidder declines. The
BLM’s competitive process in this final
rule informs prospective bidders what
they would be bidding for in advance of
a competitive process. The BLM’s
required process under this final rule
provides important information to
prospective bidders up front, reducing
uncertainty on what they may bid on.
Prospective bidders will be able to bid
more confidently with that information.
This will also likely result in more and
higher bids than would be received if
the BLM provided such information
after a competitive process and will
reduce the need for the BLM to engage
the second highest bidder should the
highest bidder decline.
The BLM understands from a
comment that there may have been
some confusion on how the rule
distinguishes between holding a
competitive process and selecting a
presumptive leaseholder or preferred
applicant. In this final rule, § 2809.15(b)
makes clear that both of the following
criteria must be met to be a presumptive
leaseholder: first, lands offered must be
located within a DLA, and second, the
notice of competitive process must
indicate that bidders are bidding to
become a presumptive leaseholder. The
requirement that the lands be within a
DLA is important because DLAs, by
PO 00000
Frm 00036
Fmt 4701
Sfmt 4700
definition, have been subject to prior
environmental analysis and a land use
plan decision to designate the area for
solar or wind energy leasing. The
environmental analysis would have
identified potential conflicts and
assessed the environmental impacts of
siting a solar or wind energy generation
facility, and through the land use
planning process the BLM would have
determined any necessary mitigation
measures prior to the BLM offering the
site for leasing. The requirement that the
notice of competitive process must
indicate that bidders are bidding to
become a presumptive leaseholder,
meanwhile, is important because it
ensures that the terms and
consequences of the competitive process
are clear to all parties before the bidding
occurs, and because it retains the BLM’s
discretion to conduct a competitive
process for a preferred applicant, rather
than a presumptive leaseholder, even
within a DLA.
Some comments expressed concern
that the BLM continues to determine
that processing of applications for
‘‘incompatible’’ uses must wait until it
issues a decision for a first-in-line solar
or wind energy development and
believe this violates the intent of
FLPMA. Commenters believed the
language of the rule is unclear about
whether these other applications are
from other applicants for a similar rightof-way or whether it would apply to
applications for other land uses. These
commenters assert that either scenario is
inconsistent with FLPMA’s multiple-use
mandate.
In this portion of the rule, the BLM’s
presumption is that the BLM has
already identified a ‘‘preferred
applicant’’ or that the lands have
already been identified in the BLM’s
land use planning process as a DLA.
The FLPMA gives BLM discretion as to
how it will process applications,
including competing ones for the same
parcel. This does not violate FLPMA’s
multiple-use mandate.
Section 2809.16 When do variable
offsets apply?
Section 2809.16 provides that a
successful bidder may be eligible for a
variable offset of bonus bids. This
section is also revised, consistent with
other changes in this rule, to read as
‘‘process’’ where appropriate when
describing the BLM’s competitive
process.
Paragraph (c) in this final rule
clarifies to readers that the offsets are
not limited explicitly to what is listed
and that the BLM may use other factors,
including progressive steps towards the
listed factors.
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
Paragraph (c)(10) is unchanged except
for formatting to account for new
paragraphs (c)(11) and (12).
Paragraph (c)(11) provides an
incentive for use of items that qualify
for the Domestic Content preference in
solar and wind energy generation
facilities on public lands, to
complement the fee reduction described
in § 2806.52(b)(1)(iii). To qualify for the
Domestic Content variable offset,
prospective bidders must demonstrate
how they will meet the thresholds to
qualify for the variable offset. Similar to
the Domestic Content reduction for the
capacity fee described in
2806.52(b)(1)(iii), the thresholds
identified in the notice of competitive
process are consistent with the
requirements for the domestic content
preference in 2 CFR part 184. A
prospective bidder is required to
provide sufficient documentation to the
BLM prior to the competitive process to
show how the bidder qualifies or will
qualify for this variable offset. This may
be documentation in an initial Plan of
Development provided to the BLM or
other methods discussed in
§ 2806.52(b)(1)(v) of this preamble. As
discussed below, the BLM may hold in
suspense the amounts corresponding to
the variable offset until construction of
the facility is substantially complete or
the successful bidder otherwise
demonstrates to the BLM that the
project has met the domestic content
thresholds.
Some comments suggested that
including a requirement for a domestic
content preference as a variable offset
would raise the cost to taxpayers. The
BLM disagrees with commenters that
this rule will increase costs to taxpayers.
This final rule does not require bidders
or holders to qualify for the Domestic
Content preference as a variable offset or
other reductions and variable offsets. As
the comments were based on an
incorrect assumption that the rule
requires buying domestic equipment, no
change was made in response to
comments.
Paragraph (c)(12) provides an
incentive for use of qualifying PLAs,
such as during the construction of a
solar or wind energy generation facility
on public lands, to complement the fee
reduction described in
§ 2806.52(b)(1)(iv). To receive the PLA
variable offset, prospective bidders must
demonstrate how they qualify in the
notice of competitive process. A
prospective bidder is required to
provide sufficient documentation to the
BLM to show how they qualify, such as
in an initial Plan of Development or
other methods discussed in
§ 2806.52(b)(1)(v) of this final rule. The
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
BLM may hold in suspense the amounts
corresponding to the variable offset
until construction of the facility is
substantially complete or the successful
bidder can otherwise demonstrate to the
BLM that the PLA has been executed for
the facility.
Some comments supported the use of
a PLA as a basis for offering a variable
offset. These comments requested that
the BLM hold a second competitive
process if the BLM does not receive
bidders qualifying for a PLA variable
offset. This second competitive process
would allow for other potential bidders
to qualify. The final rule does not limit
the number of competitive processes
that the BLM may hold. However, the
BLM has included PLAs as an optional
variable offset.
Some comments noted that union
labor laws vary from State to State,
suggesting that oversight should be by
the State. This final rule provides a
variable offset for interested bidders
when using a qualifying PLA for
competitive processes for solar or wind
energy. The BLM’s offer of a PLA
variable offset does not rely on or
necessarily preclude applicable State
laws as they may apply to project labor.
The BLM may not approve a variable
offset from a bidder if it does not
comply with applicable laws.
Some commenters disagreed with the
BLM offering variable offsets, such as
for domestic content and the use of
union labor, because developers may
also receive reduced payments under
§ 2806.52. This final rule offers a bidder
potential benefits from both a variable
offset and a capacity fee reduction. The
BLM believes these variable offsets will
incentivize prospective bidders to
initiate projects with known benefits
and approaches that will further benefit
the public. Moreover, as described
above, reductions to the capacity fee
under § 2806.52(b) will promote the
greatest use of solar and wind energy
resources on public lands consistent
with 43 U.S.C. 3003.
Paragraph (c)(13) provides that the
BLM may use other factors when
determining whether additional types of
variable offsets for a competitive process
are appropriate.
Some comments requested additional
variable offsets to promote responsible
wind and solar development, using
efficient technology, agreements with
local authorities that benefit
communities, redevelopment of
disturbed sites, and combining or
collocating energy infrastructure. The
final rule continues to provide an
opportunity for additional variable
offsets in a competitive process under
§ 2809.16(c)(13). The BLM will describe
PO 00000
Frm 00037
Fmt 4701
Sfmt 4700
35669
the additional variable offsets, including
how you may qualify for such
additional variable offsets, in the notice
of competitive process.
Paragraph (e) provides for bidders to
qualify for a variable offset after the
BLM holds a competitive process. This
final rule recognizes that a bidder may
not be able to demonstrate the
qualifications for some variable offsets
to the BLM’s satisfaction until after the
BLM holds the competitive process,
such as with new provisions in
§§ 2809.16(c)(11) or 2809.16(c)(12) for
energy development facilities that
would contain items qualifying for the
Domestic Content preference or use of a
PLA. A bidder may conditionally
qualify for a variable offset before the
competitive process and then later
demonstrate their qualification to the
BLM and perfect their qualification. The
BLM will describe in the notice of
competitive process the way a bidder
may conditionally qualify for the
variable offset and could include
methods such as a written statement to
the BLM that they intend to qualify for
the variable offset. The bidder, if
successful, must later demonstrate to
the BLM that they have qualified for the
variable offset. The BLM may set a
deadline in the notice for bidders to
demonstrate that the proposed facility
qualifies for the variable offset. If the
bidder does not qualify for the variable
offset in the time provided or the bidder
is not able to adequately demonstrate
they qualify for the variable offset, the
U.S. Government will retain the bid
money as the balance of the bonus bid.
A comment stated that if the BLM sets
a deadline to qualify for a variable offset
in the notice of competitive process,
there should be a reasonable deadline
given to demonstrate qualifications. The
BLM agrees with this comment and
provides a deadline, including the
timeframe to qualify for the variable
offset, in its notice of competitive
process. See § 2809.16(e) of this part.
Section 2809.17 Will the BLM ever
reject bids or re-conduct a competitive
process?
Section 2809.17 identifies situations
when the BLM may reject a bid, offer a
lease to another bidder, or re-offer a
parcel. This section is retitled from the
proposed rule, consistent with other
changes in the final rule to read
‘‘process’’ when describing the BLM’s
competitive process.
Paragraph (b) provides that the BLM
may make the next highest bidder the
successful bidder if the named
successful bidder does not satisfy the
successful bidder requirements
identified under § 2809.15, does not
E:\FR\FM\01MYR6.SGM
01MYR6
35670
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES6
execute the lease, or is for any reason
disqualified from holding the lease.
As proposed, paragraph (d) is
removed from this section as it is
unnecessary with other revisions made
in this final rule to make public lands
inside of DLAs available to application
without a competitive process.
Section 2809.18 What terms and
conditions apply to a solar or wind
energy development lease?
Section 2809.18 lists the terms and
conditions of solar and wind energy
leases, which are issued inside of areas
classified or allocated for solar or wind
energy (e.g., DLAs).
Paragraph (a) clarifies that a lease
awarded from a competitive process
provides site control to a lessee.
However, the presumptive leaseholder
may not construct any facilities on the
right-of-way until the BLM issues a
subsequent notice to proceed, see
paragraph 2809.15(b)(1)(ii) of this final
rule. The term of a lease is consistent
with § 2805.11(c) of this final rule,
which provides for a reasonable term up
to 50 years, considering the cost of the
facility, its useful life, and the public
purpose it serves.
Paragraph (b) provides for rent terms
for solar and wind energy leases as
specified in § 2806.52.
Paragraph (f) provides that lease
assignments are applied for under
§ 2807.21. The BLM will not make any
changes to the lease terms or conditions,
as provided in § 2807.21(e), except for
modifications required under
§ 2805.15(e). Changes to right-of-way
terms or conditions would involve an
amendment action by the BLM in
addition to the assignment action.
One comment recommended that the
BLM adjust the terms and conditions
with an assignment to provide for land
access, lease length, processes,
collaboration with other agencies, and
decommissioning. This final rule
maintains the BLM’s process for
assigning leases. Generally, a solar or
wind energy lease assignment is an
administrative action transferring the
lease from a holder to a prospective
holder. The BLM’s analysis to approve
or approve with modification the
development lease includes analyzing
the access, lease term length,
participation from public and partners,
and the end-of-life decommissioning
and restoration of the public lands. The
BLM does not need to revisit these
considerations before assigning a lease
unless there are substantial changes that
may justify a change to the lease. For
example, the BLM may modify a lease
under § 2805.15(e), which reserve the
BLM’s right to change the terms and
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
conditions as a result in changes in
legislation, regulation, or as otherwise
necessary to protect public health or
safety or the environment.
Section 2809.19 Applications in
Designated Leasing Areas or on Lands
That Later Become Designated Leasing
Areas
As proposed, Section 2809.19 is
removed from the BLM’s rules in its
entirety. In this former section, the BLM
explained how it would evaluate
applications for public lands that later
become a DLA. The former section is
inconsistent with the changes in this
rule that allow for applications in DLAs
without first holding a competitive
process. Because designation of a DLA
does not preclude non-competitive
leasing, there is no need for the BLM to
automatically suspend a noncompetitive leasing application because
the lands at issue are being considered
for designation. At the same time, the
BLM may in its discretion deny an
application or assign the application a
low priority under § 2804.35.
Some commenters supported the BLM
making public lands inside DLAs
available for non-competitive leasing by
application. These commenters
continued to suggest that the BLM
should provide public notice regarding
how the BLM will handle noncompetitive lease applications. The
notice should provide for at least a 30day cutoff date for any expressions of
interest regarding a competitive interest
for offering lands within the DLA. The
BLM agrees with comments that notice
to the public is appropriate regarding
how the BLM will administer solar and
wind energy applications in an area
affected by a land use plan amendment.
However, each planning action or
programmatic analysis is unique, and
the BLM will respond to the unique
conditions for solar and wind energy
applications specific to that plan
amendment or programmatic analysis.
This may or may not include a period
of time in which the BLM would
continue to accept applications.
Severability
Existing § 2801.8 provides: ‘‘If a court
holds any provisions of the regulations
in this part or their applicability to any
person or circumstances invalid, the
remainder of these rules and their
applicability to other people or
circumstances will not be affected.’’ If
any portion of this final rule were to be
stayed or invalidated by a reviewing
court, the remaining elements would
continue to provide BLM with
important and independently effective
tools relating to the administration of its
PO 00000
Frm 00038
Fmt 4701
Sfmt 4700
right-of-way and renewable energy
programs. Hence, if a court prevents any
provision of one part of this rule from
taking effect, that should not affect the
other parts of the rule. The remaining
provisions would remain in force
because they could still operate
sensibly.
For example, the provisions that
reduce rents and fees to implement the
Energy Act of 2020 may function
independently of the rest of the rule.
Indeed, each particular change in rents
and fees may function independently.
Thus, if a court were to invalidate the
Domestic Content reduction or Project
Labor Agreement reduction, the other
rent and fee provisions should remain
undisturbed. Similarly, the provisions
that reduce rents and fees may function
independently of the provisions that
allow the BLM to choose whether to
conduct competitive processes inside
and outside DLAs.
V. Procedural Matters
Regulatory Planning and Review
(Executive Orders 12866 and 13563)
and Modernizing Regulatory Review
(Executive Order 14094)
Executive Order (E.O.) 12866 provides
that the Office of Information and
Regulatory Affairs (OIRA) in the Office
of Management and Budget will review
all significant rules. E.O. 14094 updates
the significance criteria in section 3(f) of
E.O. 12866.
OIRA has determined that this final
rule is a ‘‘significant regulatory action’’
within the scope of E.O. 12866, as
amended by E.O. 14094.
The BLM’s Regulatory Impact
Analysis concluded that the rule may
have an annual effect on the economy
of $200 million or more. These effects
are associated with construction of
projects induced by this rule.
Additionally, the BLM estimated that
the rule would have distributional
impacts in the form of transfer payments
from right-of-way applicants and
holders to the BLM. Transfer payments
are monetary payments from one group
to another that do not affect total
resources available to society. While
disclosing the estimated transfers are
important for describing the
distributional effects of the rule, these
payments should not be included in the
estimated costs and benefits per OMB
Circular A–4.
For more detailed information, see the
Regulatory Impact Analysis for
Revisions to 43 CFR 2800 (Regulatory
Impact Analysis) prepared for this rule.
This Regulatory Impact Analysis has
been posted in the docket for the rule on
the Federal eRulemaking Portal: https://
E:\FR\FM\01MYR6.SGM
01MYR6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES6
www.regulations.gov. In the Searchbox,
enter ‘‘RIN 1004–AE78,’’ click the
‘‘Search’’ button, open the Docket
Folder, and look under Supporting
Documents.
E.O. 13563 reaffirms the principles of
E.O. 12866 while calling for
improvements in the Nation’s regulatory
system to promote predictability, reduce
uncertainty, and use the best, most
innovative, and least burdensome tools
for achieving regulatory ends. The E.O.
directs agencies to consider regulatory
approaches that reduce burdens and
maintain flexibility and freedom of
choice for the public where these
approaches are relevant, feasible, and
consistent with regulatory objectives.
E.O. 13563 emphasizes further that
regulations must be based on the best
available science and that the rule
making process must allow for public
participation and an open exchange of
ideas. The BLM has developed this rule
in a manner consistent with these
requirements.
Regulatory Flexibility Act
This rule will not likely have a
significant economic effect on a
substantial number of small entities
under the Regulatory Flexibility Act
(RFA) (5 U.S.C. 601 et seq.). The RFA
generally requires that Federal agencies
prepare a regulatory flexibility analysis
for rules subject to the ‘‘notice-andcomment’’ rulemaking requirements
found in the Administrative Procedure
Act (5 U.S.C. 500 et seq.), if the rule
would have a significant economic
impact, whether detrimental or
beneficial, on a substantial number of
small entities. See 5 U.S.C. 601–612.
Congress enacted the RFA to ensure that
government regulations do not
unnecessarily or disproportionately
burden small entities. Small entities
include small businesses, small
governmental jurisdictions, and small
not-for-profit enterprises.
The BLM reviewed the Small
Business Size standards for the affected
industries. We determined that a small
share of the entities in the affected
industries are small businesses as
defined by the Small Business Act
(SBA). However, the BLM believes that
the impact on the small entities is not
significant. Although the rule could
potentially affect a substantial number
of small entities, the BLM does not
believe that these effects would be
economically significant.
The rule would benefit small
businesses by streamlining the BLM’s
processes and reducing annual rent and
capacity fee payments. These reductions
may motivate investment in additional
generation capacity and facilities by
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
freeing up money that would have
otherwise been paid to the BLM as rents
or fees. The rule also modifies
provisions that allow for an entity to
request a waiver or reduction to annual
rent and capacity fee payments.
For the purpose of conducting its
review pursuant to the RFA, the BLM
believes that the rule would not likely
have a ‘‘significant economic impact on
a substantial number of small entities,’’
as that phrase is used in 5 U.S.C. 605.
Therefore, the BLM has not prepared a
final regulatory flexibility analysis.
Some comments noted that they
believe there has been insufficient
analysis on this rule and request the
BLM perform an initial and final
regulatory flexibility analysis, as it is
required by Sections 603 and 604 of the
Regulatory Flexibility Act for rules that
may have a significant economic impact
on a substantial number of small
business and governmental entities.
Some commenters also believe the BLM
has broken down connected and
interrelated rule-making processes to
avoid significance and therefore has
failed to conduct the necessary impacts
analysis under the Regulatory
Flexibility Act, NEPA, E.O. 12866 and
other applicable authorities as required
under the Administrative Procedure
Act.
The BLM determines that solar and
wind projects with generating capacities
of less than 100 MW have average
annual receipts of $5.2 million (solar)
and $4.1 million (wind), which falls
within the range of receipts identified
for small businesses in the SBA size
standards. The average size of projects
currently under review by the BLM is
500MW. Also, projects smaller than
100MW may still fail to be small
businesses if they are owned by larger
corporations or governmental entities.
While it is reasonable to expect that
some small businesses will be affected,
it is not expected to be a substantial
number. Further, the principal effect
will be a reduction in rents and capacity
fees for the small businesses—a benefit.
In general, the share of rents and
capacity fees is small relative to project
revenues. Therefore, the benefits are not
a significant economic impact on the
small businesses.
Congressional Review Act
This action is subject to the CRA, and
BLM will submit a rule report to each
chamber of Congress and to the
Comptroller General of the United
States. This action meets the criteria in
5 U.S.C. 804(2).
Comment Summary: In response to
the proposed rule, a commenter
requested that the BLM explain
PO 00000
Frm 00039
Fmt 4701
Sfmt 4700
35671
contradictory conclusions of regulatory
impact in accordance with the
Congressional Review Act and E.O
12866, and coordinate with local
governments and businesses to collect
inclusive and broad economic data to
make an informed determination.
Response: The commenter’s concern
has been overtaken because DOI will
report to Congress on the promulgation
of this rule prior to its effective date.
The report will state that the Office of
Information and Regulatory Affairs has
determined that this rule meets the
criteria set forth in 5 U.S.C. 804(2).’’
Unfunded Mandates Reform Act
This rule does not impose an
unfunded mandate on State, local, or
Tribal governments, or the private sector
of more than $100 million per year. The
rule does not have a significant or
unique effect on State, local, or Tribal
governments, or the private sector.
Under the Unfunded Mandates Reform
Act (UMRA) (2 U.S.C. 1531 et seq.),
agencies must prepare a written
statement about benefits and costs, prior
to issuing a proposed or final rule that
may result in aggregate expenditure by
State, local, and Tribal governments, or
the private sector, of $100 million or
more in any 1 year.
This rule is not subject to the
requirements under the UMRA. The rule
does not contain a Federal mandate that
may result in expenditures of $100
million or more for State, local, and
Tribal governments, in the aggregate, or
to the private sector in any one year.
The rule would not significantly or
uniquely affect small governments. A
statement containing the information
required by the UMRA is not required.
One comment requested that the BLM
submit documentation that is complete,
transparent, and factual for this
rulemaking and that is informed by
economic data obtained through
coordination with local governments
and a diverse range of private sector
industries, such as grazing, mining and
recreation. The resubmitted
documentation should support the
claim that this rule does not impose an
unfunded mandate under the UMRA. If
a finding shows that the rule does
impose an unfunded mandate, then the
BLM must complete a cost and benefit
analysis as required by the UMRA. The
BLM disagrees that this rule requires
resubmitting documentation supporting
the BLM’s unfunded mandate
determination. This final rule, including
its Regulatory Impact Analysis, clearly,
transparently, and factually discusses
the impacts of the rule, which governs
the BLM’s administration of
applications and right-of-way grants and
E:\FR\FM\01MYR6.SGM
01MYR6
35672
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
leases for solar and wind energy. This
rule does not result in Tribal, State, or
local governments having to expend
funds. Therefore, this rule does not
impose an unfunded federal mandate
and does not require a cost and benefit
analysis. In any event, this rule and the
accompanying Regulatory Impact
Analysis provide all the information the
UMRA requires.
Governmental Actions and Interference
With Constitutionally Protected Property
Right—Takings (E.O. 12630)
This rule does not affect a taking of
private property or otherwise have
taking implications under E.O. 12630.
Section 2(a) of E.O. 12630 identifies
policies that do not have takings
implications, such as those that abolish
regulations, discontinue governmental
programs, or modify regulations in a
manner that lessens interference with
the use of private property. The rule
would not interfere with private
property. A takings implication
assessment is not required.
Some comments noted that access
across federal, state, or county managed
lands should not entail encumbrances
or restrictions on private property. This
final rule does not restrict access across
any lands. Through separate
environmental review, such as through
land use planning, the BLM may
consider actions that affect access.
Tribal, Federal, State, and local
government offices, as well as
communities and private citizens will
have opportunity to engage in those
environmental processes.
Federalism (E.O. 13132)
Under the criteria in Section 1 of E.O.
13132, this rule does not have sufficient
federalism implications to warrant the
preparation of a federalism summary
impact statement. It does not have
substantial direct effects on the States,
on the relationship between the national
government and the States, or on the
distribution of power and
responsibilities among the various
levels of government. A federalism
summary impact statement is not
required.
ddrumheller on DSK120RN23PROD with RULES6
Civil Justice Reform (E.O. 12988)
This rule complies with the
requirements of E.O. 12988.
Specifically, this rule:
a. Meets the criteria of Section 3(a)
requiring that all regulations be
reviewed to eliminate errors and
ambiguity and be written to minimize
litigation; and
b. Meets the criteria of Section 3(b)(2)
requiring that all regulations be written
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
in clear language and contain clear legal
standards.
Consultation and Coordination With
Indian Tribes (E.O. 13175 and
Departmental Policy)
DOI strives to maintain and
strengthen its government-togovernment relationship with Indian
Tribes through a commitment to
consultation with Indian Tribes and
recognition of their right to selfgovernance and Tribal sovereignty. We
have evaluated this rule under the DOI’s
consultation policy and under the
criteria in E.O. 13175 and have
determined that it has no substantial
direct effects on federally recognized
Indian Tribes, on the relationship
between the Federal Government and
Indian tribes, or on the distribution of
power and responsibilities between the
Federal Government and Indian Tribes,
and that consultation under the DOI’s
Tribal consultation policy is not
required. However, consistent with the
DOI’s consultation policy (52
Departmental Manual 4) and the criteria
in E.O. 13175, the BLM will consult
with federally recognized Indian Tribes
on any renewable energy project
proposals that may have a substantial
direct effect on the Tribes.
Paperwork Reduction Act
The Paperwork Reduction Act (PRA)
(44 U.S.C. 3501–3521) generally
provides that an agency may not
conduct or sponsor and, not
withstanding any other provision of
law, a person is not required to respond
to a collection of information, unless it
displays a currently valid OMB control
number. Collections of information
include any request or requirement that
persons obtain, maintain, retain, or
report information to an agency, or
disclose information to a third party or
to the public (44 U.S.C. 3502(3) and 5
CFR 1320.3(c)).
This rule contains informationcollection requirements that are subject
to review by OMB under the PRA. OMB
has generally approved the existing
information-collection requirements
contained in 43 CFR part 2800
associated with wind and solar rightsof-way grants or leases under OMB
control number 1004–0206 (expiration
date: June 30, 2026). Additionally, the
BLM’s regulations at 43 CFR part 2800
require the use of Standard Form 299
(SF–299), ‘‘Application for
Transportation and Utility Systems and
Facilities on Federal Lands,’’ for rightof-way applications and the regulations
at 43 CFR part 2800. OMB has approved
the requirements associated with SF–
PO 00000
Frm 00040
Fmt 4701
Sfmt 4700
299 and has assigned control number
0596–0249.
This rule does not include any
changes to the information-collection
requirements currently contained in 43
CFR parts 2800 and 2880 and approved
by OMB as noted above. There is a new
information-collection requirement
contained in 43 CFR 2806.52(b)(5)
regarding an annual certified statement.
The rule would require that by October
of each year wind and solar grant or
leaseholders must submit to the BLM a
certified statement identifying the first
year’s estimated energy generation on
public lands and the prior year’s actual
energy generation on public lands. The
BLM will determine the capacity fee
based on the certified statement
provided. To prepare the annual
certified statement, grant or leaseholders
will need to compile information based
on capacity fee as instructed in 43 CFR
2806.
The information-collection
requirements contained in 43 CFR 2800
and 2880 and approved under OMB
Control Number 1004–0206 and the
aforementioned new informationcollection pertaining to 43 CFR
2806.52(b)(5) are described below.
Activities That Require SF–299
The following discussion describes
the information-collection activities in
this control number that require use of
SF–299.
Application for a Solar or Wind Energy
Development Project Outside Any
Designated Leasing Area (43 CFR
2804.12, 2804.25(c), 2804.26(a)(5), and
2804.30(g)); and Application for an
Electric Transmission Line With a
Capacity of 100 kV or More (43 CFR
2804.12, 2804.25(c), and 2804.26(a)(5))
Section 2804.12(b) applies to solar
and wind energy development grants
outside any DLA and electric
transmission lines with a capacity of
100 kV or more.
Section 2804.12(b) includes the
following requirements for applications
for a solar or wind energy development
project outside a DLA and for
applications for a transmission line
project with a capacity of 100 kV or
more:
• A discussion of all known potential
resource conflicts with sensitive
resources and values, including special
designations or protections; and
• Applicant-proposed measures to
avoid, minimize, and compensate for
such resource conflicts, if any.
Section 2804.12(b) also requires
applicants to initiate early discussions
with any grazing permittees that may be
affected by the proposed project. This
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
requirement stems from FLPMA Section
402(g) (43 U.S.C. 1752(g)) and a BLM
grazing regulation (section 4110.4–2(b))
that require 2 years’ prior notice to
grazing permittees and lessees before
cancellation of their grazing privileges.
In addition to the information listed at
§ 2804.12(b), an application for a solar
or wind project, or for a transmission
line of at least 100 kV, must include the
information listed at §§ 2804.12(a)(1)
through (a)(7).
Section 2804.25 provides that the
BLM will notify an applicant upon
receipt of an application and may
require the applicant to submit
additional information necessary to
process the application (such as a Plan
of Development or cultural resource
surveys). As amended, § 2084.25(c)
provides that, for solar or wind energy
development projects and transmission
lines with a capacity of 100 kV or more,
the applicant must commence any
required resource surveys or inventories
within 1 year of the request date, unless
otherwise specified by the BLM. The
amended regulation also authorizes an
applicant to submit a request for an
alternative requirement by showing
good cause under § 2804.40.
Applications for solar or wind energy
development outside any DLA, but not
applications for large-scale transmission
lines, are subject to a requirement (at
§ 2804.12(c)(2)) to submit an
‘‘application filing fee’’ of $15 per acre.
As defined in an amendment to
§ 2801.5, an application filing fee is
specific to solar and wind energy rightof-way applications. Section
2804.30(e)(4) provides that the BLM will
refund the fee, except for the reasonable
costs incurred on behalf of the
applicant, if the applicant is not a
successful bidder in the competitive
process outlined in subpart 2804.
Section 2804.26(a)(5) provides the
authority that allows the BLM to deny
an application for a right-of-way grant if
the applicant does not have or cannot
demonstrate the technical or financial
capability to construct the project or
operate facilities within the right-ofway. Amendments to that provision list
the following ways an applicant may
demonstrate their financial and
technical capability to construct,
operate, maintain, and terminate a
project:
• Documenting any previous
successful experience in construction,
operation, and maintenance of similar
facilities on either public or non-public
lands;
• Providing information on the
availability of sufficient capitalization to
carry out development, including the
preliminary study stage of the project
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
and the environmental review and
clearance process; or
• Providing written copies of
conditional commitments of Federal
and other loan guarantees; confirmed
power purchase agreements;
engineering, procurement, and
construction contracts; and supply
contracts with credible third-party
vendors for the manufacture or supply
of key components for the project
facilities.
General Description of a Proposed
Project and Schedule for Submittal of a
Plan of Development (43 CFR
2804.12(b)(1) and (b)(2))
Sections 2804.12(b)(1) and (b)(2)
require applicants for a solar or wind
development project outside a DLA to
submit the following information, using
Form SF–299:
• A general description of the
proposed project and a schedule for the
submission of a Plan of Development
(POD) conforming to the POD template
at https://www.blm.gov;
• A discussion of all known potential
resource conflicts with sensitive
resources and values, including special
designations or protections; and
• Proposals to avoid, minimize, and
compensate for such resource conflicts,
if any.
Application for an Energy Site-Specific
Testing Grant (43 CFR 2804.12(a), and
2804.30(g)); Application for an Energy
Project-Area Testing Grant (43 CFR
2804.12(a), and 2804.30(g)); and
Application for a Short-Term Grant (43
CFR 2804.12(a))
Section 2804.12(a) addresses the
general requirements of an application
for a FLPMA right-of-way grant. Section
2804.30(g) authorizes only one
applicant (i.e., a ‘‘preferred applicant’’)
to apply for an energy project-area
testing grant or an energy site-specific
testing grant for land outside any DLA.
Each of these grants is for 3 years or
less, in accordance with § 2805.11(c)(2).
All of these applications must be
submitted on SF–299. Applications for
project-area grants (but not site-specific
grants) are subject to a $2 per-acre
application filing fee in accordance with
§ 2804.12(c)(2). Applicants for shortterm grants for other purposes (such as
geotechnical testing and temporary
land-disturbing activities) are subject to
a processing fee in accordance with
§ 2804.1.
Request To Assign a Solar or Wind
Energy Development Right-of-Way (43
CFR 2807.21)
Section 2807.21, as amended,
provides for assignment, in whole or in
PO 00000
Frm 00041
Fmt 4701
Sfmt 4700
35673
part, of any right or interest in a grant
or lease for a solar or wind development
right-of-way. Actions that may require
an assignment include the transfer by
the holder (assignor) of any right or
interest in the grant or lease to a third
party (assignee) or any change in control
transaction involving the grant holder or
leaseholder, including corporate
mergers or acquisitions. The proposed
assignee must file an assignment
application, using SF–299, and pay
application and processing fees.
The assignment application must
include:
• Documentation that the assignor
agrees to the assignment; and
• A signed statement that the
proposed assignee agrees to comply
with and be bound by the terms and
conditions of the grant that is being
assigned and all applicable laws and
regulations.
Environmental, Technical, and
Financial Records, Reports, and Other
Information (43 CFR 2805.12(a)(15))
Section 2805.12(a)(15) authorizes the
BLM to require a holder of any type of
right-of-way to provide, or give the BLM
access to, any pertinent environmental,
technical, and financial records, reports,
and other information. The use of SF–
299 is required. The BLM will use the
information for monitoring and
inspection activities.
Application for Renewal of a Solar or
Wind Energy Development Grant or
Lease (43 CFR 2805.14(g) and 2807.22)
Section 2805.14(g) provides that a
holder of a right-of-way grant, which
includes solar or wind energy
generating facilities, may apply for
renewal in accordance with § 2807.22.
Section 2807.22(c) provides that an
application to renew a grant must
include the same information, on SF–
299, that is necessary for a new
application. It also provides that
processing fees, in accordance with
§ 2804.14, as amended, apply to these
renewal applications. Sections
2807.22(a) and (b) provide that an
application for renewal of any right-ofway grant or lease, including a solar or
wind energy development grant or lease,
must be submitted at least 120 calendar
days before the grant or lease expires.
The application must show that the
grantee or lessee is complying with the
renewal terms and conditions (if any),
with the other terms, conditions, and
stipulations of the grant or lease, and
with other applicable laws and
regulations. The application also must
explain why a renewal of the grant or
lease is necessary.
E:\FR\FM\01MYR6.SGM
01MYR6
35674
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES6
Request for Amendment, Assignment, or
Other Change (FLPMA) (43 CFR
2807.11(b) and (d) and 2807.21)
Section 2807.11(b) requires a holder
of any type of right-of-way grant to
contact the BLM to seek an amendment
to the grant under § 2807.20 and obtain
the BLM’s approval before beginning
any activity that is a ‘‘substantial
deviation’’ from what is authorized.
Section 2807.11(d) requires contacting
the BLM to request an amendment to
the pertinent right-of-way grant or lease
and prior approval whenever sitespecific circumstances or conditions
result in the need for changes to an
approved right-of-way grant or lease,
Plan of Development, site plan,
mitigation measures, or construction,
operation, or termination procedures
that are not ‘‘substantial deviations.’’
Section 2807.21 authorizes
assignment of a grant or lease with the
BLM’s approval. It also authorizes the
BLM to require a grant or leaseholder to
file new or revised information in
circumstances that include, but are not
limited to:
• Transactions within the same
corporate family;
• Changes in the holder’s name only;
and
• Changes in the holder’s articles of
incorporation.
A request for an amendment of a
right-of-way, using SF–299, is required
in cases of a substantial deviation (for
example, a change in the boundaries of
the right-of-way, major improvements
not previously approved by the BLM, or
a change in the use of the right-of-way).
Other changes, such as changes in
project materials, or changes in
mitigation measures within the existing,
approved right-of-way area, must be
submitted to the BLM for review and
approval. In order to assign a grant, the
proposed assignee must file an
assignment application and follow the
same procedures and standards as for a
new grant or lease, as well as pay
application and processing fees. In order
to request a name change, the holder
will be required to file an application
and follow the same procedures and
standards as for a new grant or lease and
pay processing fees, but no application
fee is required. The following
documents are also required in the case
of a name change:
• A copy of the court order or legal
document effectuating the name change
of an individual; or
• If the name change is for a
corporation, a copy of the corporate
resolution proposing and approving the
name change, a copy of a document
showing acceptance of the name change
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
by the State in which incorporated, and
a copy of the appropriate resolution,
order, or other document showing the
name change.
In all these cases, the BLM will use
the information to monitor and inspect
rights-of-way, and to maintain current
data.
Activities That Do Not Require Any
Form
Preliminary Application Review
Meetings for a Large-Scale Right-of-Way
(43 CFR 2804.12(b)(4))
‘‘Preliminary application review
meetings’’ are required after submission
of an application for a large-scale rightof-way. A large-scale right-of-way is for
solar or wind energy development
outside a DLA, or for a transmission line
with a capacity of 100 kV or more.
Within 6 months from the date that
the BLM receives the cost recovery fee
for an application for a large-scale
project, the applicant must schedule
and hold at least two preliminary
application review meetings.
In the first meeting, the BLM will
collect information from the applicant
to supplement the application on
subjects such as the general project
proposal. The BLM will also discuss
with the applicant subjects such as the
status of the BLM’s land use planning
for the lands involved, potential siting
issues or concerns, potential
environmental issues or concerns,
potential alternative site locations, and
the right-of-way application process.
In the second meeting, the applicant
and the BLM will meet with appropriate
Federal and State agencies and Tribal
and local governments to facilitate
coordination of potential environmental
and siting issues and concerns.
The applicant and the BLM may agree
to hold additional preliminary
application review meetings.
Application for Renewal of an Energy
Project-Area Testing Grant or Other
Short-Term Grant (43 CFR
2805.11(c)(2)(ii), 2805.14(h), and
2807.22)
Section 2805.11(c)(2)(ii) provides that
holders of energy project-area testing
grants may seek renewal of those grants.
The initial term for such a grant is 3
years or less, with the option to renew
for one additional 3-year period.
For other short-term grants, such as
for geotechnical testing and temporary
land-disturbing activities, the initial
term is 3 years or less. Short-term grants
include an option for renewal.
Section 2805.14(h) provides that
applications to renew an energy projectarea testing grant must include an
PO 00000
Frm 00042
Fmt 4701
Sfmt 4700
energy development application
submitted in accordance with
§ 2801.9(d)(2). Cost recovery fees in
accordance with § 2804.14, as amended,
apply to these renewal applications.
Section 2807.22 provides that an
application for renewal of any right-ofway grant or lease, including an energy
project-area testing grant or a short-term
grant, must be submitted at least 120
calendar days before the grant or lease
expires. The application must show that
the grantee or lessee is complying with
the renewal terms and conditions (if
any), with the other terms, conditions,
and stipulations of the grant or lease,
and with other applicable laws and
regulations. The application also must
explain why a renewal of the grant or
lease is necessary.
Showing of Good Cause (43 CFR
2804.40 and 2805.12)
Under § 2804.40, an applicant for a
FLPMA right-of-way grant who is
unable to meet any of the requirements
in subpart 2804 may request approval
for an alternative requirement from the
BLM. Any such request is not approved
until the applicant receives BLM
approval in writing. This type of request
to the BLM must:
(a) Show good cause for the
applicant’s inability to meet a
requirement;
(b) Suggest an alternative requirement
and explain why that requirement is
appropriate; and
(c) Be received in writing by the BLM
in a timely manner, before the deadline
to meet a particular requirement has
passed.
The BLM will use the information to
determine whether to apply an
alternative requirement.
Other showings of good cause are
authorized or may be required by
§ 2805.12, which requires due diligence
in development and operations of any
right-of-way grant or lease. In
accordance with § 2805.12(c)(6) and
(c)(8), the BLM will notify the holder
before suspending or terminating a
right-of-way for lack of due diligence.
This notice will provide the holder with
a reasonable opportunity to correct any
noncompliance or to start or resume use
of the right-of-way. A showing of good
cause will be required in response. That
showing must include:
• Reasonable justification for any
delays in construction or reductions in
energy generation (for example, delays
in equipment delivery, legal challenges,
and acts of God);
• The anticipated date for the
completion of construction or
resumption of energy generation; and
E:\FR\FM\01MYR6.SGM
01MYR6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES6
evidence of progress toward the start or
resumption of construction; and
• A request for extension of the
timelines in the approved POD or
extension of the period in which the
holder must satisfy the minimum energy
threshold.
Section 2805.12(e), as amended,
applies as soon as a right-of-way holder
anticipates noncompliance with
stipulation, term, or condition of the
approved right-of-way grant or lease, or
in the event of noncompliance with any
such stipulation, term, or condition. In
these circumstances, the holder must
notify the BLM in writing and show
good cause for the noncompliance,
including an explanation of the reasons
for the noncompliance.
In addition, the holder may request
that the BLM consider alternative
stipulations, terms, or conditions. Any
request for an alternative stipulation,
term, or condition must comply with
applicable law in order to be
considered. Any proposed alternative to
applicable bonding requirements must
provide the United States with adequate
financial assurance for potential
liabilities associated with the right-ofway grant or lease. Any such request is
not approved until the holder receives
the BLM’s approval in writing.
Bonding Requirements (43 CFR 2805.20)
Section 2805.20 provides that the
bond amount for projects other than a
solar or wind energy lease under
subpart 2809 (i.e., inside a DLA) will be
determined based on the preparation of
a reclamation cost estimate that
includes the cost to the BLM to
administer a reclamation contract and
review it periodically for adequacy.
Section 2805.20(a)(5) provides that
the reclamation cost estimate must
include at a minimum:
• Remediation of environmental
liabilities such as use of hazardous
materials waste and hazardous
substances, herbicide use, the use of
petroleum-based fluids, and dust
control or soil stabilization materials;
• The decommissioning, removal,
and proper disposal, as appropriate, of
any improvements and facilities; and
• Interim and final reclamation, revegetation, recontouring, and soil
stabilization.
Sections 2805.20(b) and 2805.20(c)
identify specific bond requirements for
solar and wind energy development
respectively outside of DLAs. A holder
of a solar or wind energy grant outside
of a DLA will be required to submit a
reclamation cost estimate to help the
BLM determine the bond amount. For
solar energy development grants outside
of DLAs, the bond amount will be no
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
less than $10,000 per acre. For wind
energy development grants outside of
DLAs, the bond amount will be no less
than $10,000 per authorized turbine
with a nameplate generating capacity of
less than one Megawatt (MW), and no
less than $20,000 per authorized turbine
with a nameplate generating capacity of
one MW or greater.
Section 2805.20(d) separates site- and
project-area testing authorization bond
requirements from § 2805.20(c).
Meteorological and other
instrumentation facilities are required to
be bonded at no less than $2,000 per
location. These bond amounts are the
same as standard bond amounts for
leases required under § 2809.18(e)(3).
Annual Certified Statement (43 CFR
2806.52(b)(5))—New Information
Collection
The rule requires that by October of
each year, wind and solar grant or
leaseholders must submit to the BLM a
certified statement identifying the first
year’s estimated energy generation on
public lands and the prior year’s actual
energy generation on public lands. The
BLM will determine the capacity fee
based on the certified statement
provided. To prepare the annual
certified statement, grant or leaseholders
will need to compile information based
on the capacity fee as instructed in
subpart 2806. This is the only new
information-collection requirement
contained in this rule.
Nomination of a Parcel of Land Inside
a Designated Leasing Area (43 CFR
2809.11)
Sections 2809.10 and 2809.11
authorize the BLM, on its own initiative,
to offer land through a competitive
process for solar or wind energy
development. These regulations also
authorize the BLM to solicit
nominations for such development by
publishing a notice in the Federal
Register. To nominate a parcel under
this process, the nominator must be
qualified to hold a right-of-way under
43 CFR 2803.10. After publication of a
notice by the BLM, anyone meeting the
qualifications may submit a nomination
for a specific parcel of land to be
developed for solar or wind energy.
There is a fee of $5 per acre for each
nomination. The following information
is required:
• The nominator’s name and personal
or business address;
• The legal land description; and
• A map of the nominated lands.
The BLM will use the information to
communicate with the nominator and to
determine whether to proceed with a
competitive process.
PO 00000
Frm 00043
Fmt 4701
Sfmt 4700
35675
Plan of Development for a Solar or Wind
Energy Development Lease Inside a
Designated Leasing Area (43 CFR
2809.18)
Section 2809.l8(c) requires the holder
of a lease for solar or wind energy
development to submit a Plan of
Development (POD) within 2 years of
the lease issuance date. The POD must
be consistent with the development
schedule and other requirements in the
POD template posted at https://
www.blm.gov; and must address all predevelopment and development
activities.
Section 2809.18(d) requires the holder
of a solar or wind energy development
lease for land inside a DLA to pay
reasonable costs for the BLM or other
Federal agencies to review and approve
the POD and monitor the lease. To
expedite review and monitoring, the
holder may notify the BLM in writing of
an intention to pay the full actual costs
incurred by the BLM.
Request for Amendment, Assignment, or
Other Change (MLA) (43 CFR 2886.12(b)
and (d) and 43 CFR 2887.11)
Sections 2886.12 and 2887.11 pertain
to holders of rights-of-way and
temporary use permits authorized under
the MLA. A temporary use permit
authorizes a holder of a MLA right-ofway to use land temporarily in order to
construct, operate, maintain, or
terminate a pipeline, or for purposes of
environmental protection or public
safety. See § 2881.12. The regulations
require these holders to contact the
BLM:
• Before engaging in any activity that
is a ‘‘substantial deviation’’ from what is
authorized;
• Whenever site-specific
circumstances or conditions arise that
result in the need for changes that are
not substantial deviations;
• When the holder submits a
certification of construction;
• Before assigning, in whole or in
part, any right or interest in a grant or
lease;
• Before any change in control
transaction involving the grant- or leaseholder; and
• Before changing the name of a
holder (i.e., when the name change is
not the result of an underlying change
in control of the right-of-way).
A request for an amendment of a
right-of-way or temporary use permit is
required in cases of a substantial
deviation (e.g., a change in the
boundaries of the right-of-way, major
improvements not previously approved
by the BLM, or a change in the use of
the right-of-way). Other changes, such
E:\FR\FM\01MYR6.SGM
01MYR6
35676
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
ddrumheller on DSK120RN23PROD with RULES6
as changes in project materials, or
changes in mitigation measures within
the existing, approved right-of-way area
are required to be submitted to the BLM
for review and approval. In order to
assign a grant, the proposed assignee
must file an assignment application and
follow the same procedures and
standards as for a new grant or lease, as
well as pay processing fees. In order to
request a name change, the holder will
be required to file an application and
follow the same procedures and
standards as for a new grant or lease and
pay processing fees, but no application
fee is required. The following
documents are also required in the case
of a name change:
• A copy of the court order or legal
document effectuating the name change
of an individual; or
• If the name change is for a
corporation, a copy of the corporate
resolution proposing and approving the
name change, a copy of a document
showing acceptance of the name change
by the State in which incorporated, and
a copy of the appropriate resolution,
order, or other document showing the
name change.
In all these cases, the BLM will use
the information gathered for monitoring
and inspection purposes, and to
maintain current data on rights-of-way.
Certification of Construction (43 CFR
2886.12(f))
A certification of construction is a
document a holder of an MLA right-ofway must submit to the BLM after
finishing construction of a facility, but
before operations begin. The BLM will
use the information to verify that the
holder has constructed and tested the
facility to ensure that it complies with
the terms of the right-of-way and is in
accordance with applicable Federal and
State laws and regulations.
The information-collection request for
this rule has been submitted to OMB for
review under 44 U.S.C. 3507(d). You
may view the information-collection
request(s) at https://www.reginfo.gov/
public/do/PRAMain.
As part of our continuing effort to
reduce paperwork and respondent
burdens, we invite the public and other
Federal agencies to comment on any
aspect of this information-collection,
including:
• Whether the collection of
information is necessary for the proper
functioning of the BLM, including
whether the information will have
practical utility;
• The accuracy of the BLM’s estimate
of the burden of collecting the
information, including the validity of
the methodology and assumptions used;
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
• The quality, utility, and clarity of
the information to be collected; and
• How to minimize the informationcollection burden on those who are to
respond, including the use of
appropriate automated, electronic,
mechanical, or other forms of
information technology.
Currently, the information-collection
requirements contained in 43 CFR parts
2800 and 2880 and approved under
OMB control number 1004–0206 are
estimated as follows: 3,042 annual
responses; 47,112, annual burden hours;
and $2,182,302 annual cost burden. We
are projecting a burden increase of 75
new annual responses and 150 new
annual burden hours as result of this
rule. This burden hour increase would
result from a new information collection
requirement contained in
§ 2806.52(b)(5) pertaining to the annual
certified statement. This new
information collection is needed to help
the BLM more accurately determine the
capacity fee based on the certified
statement provided.
The final rule also removes an
existing information collection
previously contained in 43 CFR
2809.11(c) titled, Expression of Interest
in a Parcel of Land Inside a Designated
Leasing Area. The removal of this
information collection results in the
reduction of 1 annual response and 4
annual burden hours.
Therefore, we estimate that the final
rule will result in a net increase of 74
annual responses and 226 annual
burden hours.
We are also adjusting the burden for
two existing and unchanged information
collections to reflect more accurately the
burden those activities would involve
the industry. These adjustments include
the following:
• Preliminary Application Review
Meetings for 2 public meetings for a
Large-Scale Right-of-Way (43 CFR
2804.12(b)(4)). The average response
time is adjusted from 2 hours to 4 hours.
This adjustment resulted in a 40-hour
burden increase (from 40 hours to 80
hours).
• Environmental, Technical, and
Financial Records, Reports, and Other
Information (43 CFR 2805.12(a)(15)).
We have added a 50 percent increase in
the hours required to prepare reports
(from 4 per response to 6 per response).
This resulted in an increasing the
estimated annual burden hours for these
activities from 80 hours to 120 hours.
There are no projected changes to the
non-hour cost burdens as a result of this
rule. The resulting new estimated total
burdens for OMB Control Number
1004–0206 are provided below.
PO 00000
Frm 00044
Fmt 4701
Sfmt 4700
Title of Collection: Competitive
Processes, Terms, and Conditions for
Leasing Public Lands for Solar and
Wind Energy Development (43 CFR
parts 2800 and 2880).
OMB Control Number: 1004–0206.
Form Number: SF–299 (Burden
approved by OMB in Request for
Common Form under OMB Control
Number 0596–0249).
Type of Review: Revision of a
currently approved collection of
information.
Respondents/Affected Public: Private
sector (applicants for and holders of
wind and solar rights-of-way grants or
leases on Federal public lands.
Respondent’s Obligation: Required to
obtain or retain a benefit.
Frequency of Collection: On occasion
and annually for the Annual Certified
Statement in 43 CFR 2806.52(i).
Number of Respondents: 75.
Annual Responses: 3,116.
Annual Burden Hours: 47,338.
Annual Burden Cost: $2,182,302.
If you want to comment on the
information-collection requirements this
in this rule, please send your comments
and suggestions on this informationcollection request within 30 days of
publication of this final rule in the
Federal Register to OMB at
www.reginfo.gov. Click on the link,
‘‘Currently under Review—Open for
Public Comments.’’
National Environmental Policy Act
These proposed regulatory
amendments are of an administrative or
procedural nature and thus are eligible
to be categorically excluded from the
requirement to prepare an EA or an EIS.
See 43 CFR 46.205 and 46.210(i). They
do not present any of the extraordinary
circumstances listed at 43 CFR 46.215.
Actions Concerning Regulations That
Significantly Affect Energy Supply,
Distribution, or Use (Executive Order
13211)
Federal agencies are to prepare and
submit to OMB a Statement of Energy
Effects for any proposed significant
energy action. A ‘‘significant energy
action’’ is defined as any action by an
agency that: (1) Is a significant
regulatory action under Executive Order
12866, or any successor order, and (2)
Is likely to have a significant adverse
effect on the supply, distribution, or use
of energy; or (3) Is designated by the
Administrator of OIRA as a significant
energy action.
The BLM reviewed the rule and
determined that it is not likely a
significant energy action as defined by
E.O. 13211. While the rights-of-way
affected by this rule are for solar and
E:\FR\FM\01MYR6.SGM
01MYR6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
wind energy generation, the rule is
limited in scope and would not likely
have a significant, adverse effect on the
supply, distribution, or use of energy
from these sources. The rule would not
result in a shortfall in supply, price
increases, or increase the use of foreign
supplies.
Authors
The principal authors of this rule are:
Jayme M. Lopez, BLM National Renewable
Energy Coordination Office; Jeremy Bluma,
BLM National Renewable Energy
Coordination Office; Radford Schantz,
Division of Lands, Realty and Cadastral
Survey; Patrick Lee, DOI, Office of Policy
Analysis; Jeff Holdren, BLM Division of
Lands, Realty and Cadastral Survey; Darrin
King, BLM Division of Regulatory Affairs;
Jennifer Noe, BLM Division of Regulatory
Affairs, assisted by the DOI Office of the
Solicitor. This action by the Principal Deputy
Assistant Secretary is taken pursuant to an
existing delegation of authority.
Steven H. Feldgus, Ph.D.,
Principal Deputy Assistant Secretary, Land
and Minerals Management.
List of Subjects in 43 CFR Part 2800
Electric power, Highways and roads,
Penalties, Public lands and rights-ofway, Reporting and recordkeeping
requirements.
Accordingly, for the reasons stated in
the preamble, the BLM amends 43 CFR
part 2800 as set forth below:
PART 2800—RIGHTS–OF–WAY UNDER
THE FEDERAL LAND POLICY AND
MANAGEMENT ACT
1. The authority citation for part 2800
is revised to read as follows:
■
Authority: 43 U.S.C. 1733, 1740, 1763,
1764, and 3003.
Subpart 2801—General information
2. Amend § 2801.5:
a. In paragraph (a) by adding the
acronym for ‘‘FLPMA’’ in alphabetical
order;
■ b. In paragraph (b) by:
■ i. Removing the term ‘‘Act’’;
■ ii. Adding in alphabetical order the
terms ‘‘Domestic Content’’ and
‘‘Capacity fee’’;
■ iii. Revising the term for ‘‘Grant’’;
■ iv. Removing the term ‘‘Megawatt
(mw) capacity fee’’;
■ v. Revising the terms ‘‘Megawatt hour
(MWh) rate’’ and ‘‘Reasonable costs’’;
and
■ vi. Adding in alphabetical order the
terms ‘‘Renewable energy coordination
office (RECO)’’, ‘‘Solar or wind energy
development’’, and ‘‘Solar or wind
energy lease’’.
The additions and revisions to read as
follows:
ddrumheller on DSK120RN23PROD with RULES6
■
■
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
§ 2801.5 What acronyms and terms are
used in the regulations in this part?
(a) * * *
FLPMA means the Federal Land
Policy and Management Act of 1976, as
amended (43 U.S.C. 1701 et seq.).
*
*
*
*
*
(b) * * *
Domestic Content reduction means an
item or product that qualifies for the
domestic content preference under the
Build America, Buy America Act, Public
Law 117–58, 135 Stat. 429, §§ 70901
through 70927 (Nov. 15, 2021), and the
implementing guidance at 2 CFR part
184.
Capacity fee is the fee charged to
right-of-way holders once energy
production commences that is based on
the production of energy on public
lands from solar and wind energy
generating facilities.
*
*
*
*
*
Grant means an authorization or
instrument (e.g., easement, license, or
permit) the BLM issues under Title V of
the Federal Land Policy and
Management Act, 43 U.S.C. 1761 et seq.,
and any authorization or instrument the
BLM and its predecessors issued for like
purposes before October 21, 1976, under
then existing statutory authority, except
for solar or wind energy leases. It does
not include authorizations issued under
the Mineral Leasing Act (30 U.S.C. 185).
*
*
*
*
*
Megawatt hour (MWh) rate means the
5 calendar-year average of the annual
average wholesale electricity prices per
MWh for the major trading hubs serving
the 11 western States of the continental
United States.
*
*
*
*
*
Reasonable costs has the meaning
found in Section 304(b) of FLPMA.
*
*
*
*
*
Renewable energy coordination office
(RECO) means one of the National,
State, district, or field offices
established by the Secretary under 43
U.S.C. 3002(a) that is responsible for
implementing a program for improving
Federal permit coordination with
respect to solar, wind, and geothermal
projects on BLM-administered land, and
such other activities as the Secretary
determines necessary.
*
*
*
*
*
Solar or wind energy development
means the use of public lands to
generate electricity from solar or wind
energy resources. It includes the
construction, operation, maintenance,
and decommissioning of any such
facilities, as well as the subsequent
reclamation of the site.
Solar or wind energy lease means any
right-of-way issued for solar or wind
PO 00000
Frm 00045
Fmt 4701
Sfmt 4700
35677
energy development in an area
classified or allocated for solar or wind
energy (i.e., a designated leasing area) in
a resource management plan.
*
*
*
*
*
■ 3. Amend § 2801.6 by revising
paragraph (a)(1) to read as follows:
§ 2801.6
Scope.
(a) * * *
(1) Grants or leases for necessary
transportation or other systems and
facilities that are in the public interest
and require the use of public lands for
the purposes identified in 43 U.S.C.
1761, and administering, amending,
assigning, monitoring, renewing, and
terminating them;
*
*
*
*
*
■ 4. Amend § 2801.9 by revising
paragraphs (d) introductory text, (d)(3)
and (4), and adding paragraph (d)(6) to
read as follows:
§ 2801.9
When do I need a grant?
*
*
*
*
*
(d) All systems, facilities, and related
activities for energy generation, storage,
or transmission projects are specifically
authorized as follows:
*
*
*
*
*
(3) Energy generation facilities,
including solar and wind energy
development facilities, are authorized
with a right-of-way grant or lease that
may be issued for up to 50 years (plus
initial partial year of issuance);
(4) Energy storage facilities, which are
separate from energy generation
facilities, are authorized with a right-ofway grant that may be issued for up to
50 years;
*
*
*
*
*
(6) Electric transmission lines with a
capacity of 100 kV or more are
authorized with a right-of-way grant that
may be issued for up to 50 years.
■ 5. Revise the heading for subpart 2802
to read as follows:
Subpart 2802—Lands Available for
FLPMA Grants or Leases
6. Amend § 2802.11 by revising
paragraphs (b) introductory text and
(b)(1) and adding paragraphs (b)(10) and
(11) to read as follows:
■
§ 2802.11 How does the BLM designate
right-of-way corridors and designated
leasing areas?
*
*
*
*
*
(b) When determining which public
lands may be suitable for right-of-way
corridors or designated leasing areas,
the BLM may consider various factors,
including:
E:\FR\FM\01MYR6.SGM
01MYR6
35678
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
(1) Federal, State, Tribal, and local
land use plans, and applicable Federal,
State, Tribal, and local laws;
*
*
*
*
*
(10) Access to electric transmission;
and
(11) Whether there are areas for solar
and wind energy development with low
potential for conflict with resources or
uses due to environmental, cultural, and
other relevant criteria, which the BLM
will identify by:
(i) Assessing the demand for new or
expanded areas;
(ii) Applying environmental, cultural,
and other screening criteria; and
(iii) Analyzing proposed areas
through the land use planning process
described in part 1600 of this chapter.
*
*
*
*
*
■ 7. Amend § 2803.10 by revising
paragraph (c) to read as follows:
§ 2803.10
Who may hold a grant or lease?
*
*
*
*
*
(c) Of legal age and authorized to do
business in the State or States where the
right-of-way you seek is located.
■ 8. Revise § 2803.12 to read as follows:
§ 2803.12 What happens to my grant or
lease if I die?
(a) If a grant holder dies, any
inheritable interest in a grant or lease
will be distributed under State law.
(b) If the receiver of a grant or lease
is not qualified to hold a grant or lease
under § 2803.10 of this subpart, the
BLM will recognize the receiver as grant
or leaseholder for up to two years,
subject to full compliance with all
terms, conditions, and stipulations.
During that period, the receiver must
either become qualified or divest itself
of the interest.
Subpart 2804—Applying for FLPMA
Grants
9. Amend § 2804.12 by revising
paragraphs (c) and (f) and adding
paragraph (j) to read as follows:
■
§ 2804.12 What must I do when submitting
my application?
ddrumheller on DSK120RN23PROD with RULES6
*
*
*
*
*
(c) You must meet additional
requirements when applying for a solar
or wind energy development or shortterm right-of-way, as follows:
(1) Pay an application filing fee of $2
per acre for short-term right-of-way
applications or $15 per acre for solar or
wind energy development applications.
The BLM will apply the application
filing fee toward the processing fees
described in §§ 2804.14 through
2804.22. The BLM will refund the
balance of any application filing fee at
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
the end of the BLM’s application review
process if the application filing fee
exceeds the amount of the processing
fee.
(2) Pay additional reasonable costs in
addition to payment of the application
filing fee when processing your
application, pursuant to § 2804.14. A
processing or monitoring Category 6
cost recovery fee may be reduced by the
application filing fee paid when
submitting an application.
*
*
*
*
*
(f) The BLM may require you to
submit additional information at any
time while processing your application.
The BLM will identify additional
information in a written deficiency
notice asking you to provide the
information within a specified time
pursuant to § 2804.25(c).
*
*
*
*
*
(j) Your application will not be
complete until you have met or
addressed the requirements of this
section to the satisfaction of the BLM.
The BLM will notify you in writing
when your application is complete.
■ 10. Revise § 2804.22 to read as
follows:
§ 2804.22 How will the availability of funds
affect the timing of the BLM’s processing
your application?
(a) If the BLM has insufficient funds
to process your application, we will not
continue to process it until funds
become available or you elect to pay full
actual costs under § 2804.14(f) of this
part.
(b) The BLM may deny your
application if we have not received
requested reasonable costs for
processing your application within 90
days.
(c) If your cost recovery agreement
provides that a portion of the funds you
pay will be used in the hiring of
additional staff or contractors, such
funds may not be refundable.
■ 11. Revise § 2804.23 to read as
follows:
§ 2804.23 What costs am I responsible for
when the BLM decides to use a competitive
process for lands included in my
application?
If the BLM decides to use a
competitive process for lands included
in your application and your
application is in:
(a) Processing Categories 1 through 4.
You must reimburse the Federal
Government for processing costs as if
the other application or applications
had not been filed.
(b) Processing Category 6. You are
responsible for processing costs
identified in your application. If the
PO 00000
Frm 00046
Fmt 4701
Sfmt 4700
BLM cannot readily separate costs, such
as costs associated with preparing
environmental analyses, you and any
competing applicants must pay an equal
share, or a proportion agreed to in
writing among all applicants and the
BLM. If you agree to share the costs that
are common to your application and
that of a competing applicant, and the
competitor does not pay the agreed
upon amount, you are liable for the
entire amount due. You must pay the
entire processing fee in advance. The
BLM will not process your application
until we receive the advance payments.
■ 12. Amend § 2804.25 by revising
paragraphs (c), (e)(2), (e)(4), (e)(5), and
(f)(3) to read as follows:
§ 2804.25 How will the BLM process my
application?
*
*
*
*
*
(c) The BLM may require you to
submit additional information necessary
to process the application. This
information may include a detailed
construction, operation, rehabilitation,
and environmental protection plan (i.e.,
a POD), and any needed cultural
resource surveys or inventories for
threatened or endangered species. If the
BLM needs more information, the BLM
will identify this information in a
written deficiency notice asking you to
provide the additional information
within a specified period of time. The
failure to provide additional
information requested by the BLM
under this section may result in the
BLM denying your application pursuant
to § 2804.26.
(e) * * *
(2) If your application is for solar or
wind energy development;
(i) Hold a local public meeting if there
is no other public meeting or
opportunity for early engagement on the
project, such as those completed when
complying with the National
Environmental Policy Act (NEPA).
(ii) Prioritize the application in
accordance with § 2804.35; and
(iii) Evaluate the application based on
the information provided by the
applicant and input from other parties,
such as Federal, State, Tribal, and local
government agencies, as well as
comments received in preliminary
application review meetings held under
§ 2804.12(b)(4) and any public meeting
held under paragraph (e)(1) of this
section. Based on these evaluations, the
BLM will either deny your application
or continue processing it.
*
*
*
*
*
(4) Complete appropriate NEPA
compliance for the application, as
required by 43 CFR part 46 and 40 CFR
chapter V, subchapter A;
E:\FR\FM\01MYR6.SGM
01MYR6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
(5) Determine whether your proposed
use complies with applicable Federal
laws;
*
*
*
*
*
(f) * * *
(3) The segregation period may not
exceed 2 years from the date of
publication in the Federal Register of
the notice initiating the segregation,
unless the state director determines and
documents in writing, prior to the
expiration of the segregation period, that
an extension is necessary for the orderly
administration of the public lands. If the
state director determines an extension is
necessary, the BLM will extend the
segregation for up to 2 years by
publishing a notice in the Federal
Register, prior to the expiration of the
initial segregation period. A segregation
will not be extended unless the
application is complete and cost
recovery has been received.
Segregations under this part may only
be extended once and the total
segregation period may not exceed 4
years.
■ 13. Amend § 2804.26 by revising the
section heading, paragraphs (a)(4) and
(9) and adding paragraph (a)(10), and
removing paragraph (c).
The revisions and additions read as
follows:
§ 2804.26 Under what circumstances may
the BLM deny my application?
(a) * * *
(4) Issuing the grant would be
inconsistent with FLPMA, other laws, or
these or other regulations;
*
*
*
*
*
(10) You fail to pay costs for
processing your application within 90
days of receiving the BLM’s request for
funds under § 2804.22(b).
*
*
*
*
*
§ 2804.30
■
[Removed and Reserved]
14. Remove and reserve § 2804.30.
§ 2804.31
[Removed and Reserved]
15. Remove and reserve § 2804.31.
■ 16. Revise § 2804.35 to read as
follows:
■
ddrumheller on DSK120RN23PROD with RULES6
§ 2804.35 Application prioritization for
solar and wind energy development rightsof-way.
(a) The BLM will prioritize the
processing of applications to ensure that
agency resources are allocated to
applications with the greatest potential
for approval and implementation. The
BLM’s prioritization of an application is
not a decision and is not subject to
appeal under 43 CFR part 4.
(b) The BLM will consider relevant
criteria when prioritizing applications,
including the following:
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
(1) Whether the proposed project is
located within an area preferred for
solar or wind energy development, such
as designated leasing areas, which
include solar energy zones,
development focus areas, and renewable
energy development areas;
(2) Whether the proposed project is
likely to avoid adverse impacts to or
conflicts with known resources or uses
on or adjacent to public lands, and
includes specific measures designed to
further mitigate impacts or conflicts;
(3) Whether the proposed project is in
conformance with the governing BLM
land use plans;
(4) Whether the proposed project is
consistent with relevant State, Tribal,
and local government laws, plans, or
priorities;
(5) Whether the proposed project
incorporates the best management
practices set forth in the applicable BLM
land use plans and other BLM plans and
policies; and
(6) Any other circumstances or
prioritization criteria identified by the
BLM in subsequent policy guidance or
management direction through land use
planning.
(c) The BLM will prioritize your
complete application based on all
available information, including
information you provide to the BLM in
the application or in response to
deficiency notices, and information
provided to the BLM in public meetings
or consultations.
(d) The BLM may re-prioritize your
application at any time.
■ 17. Amend § 2804.40 by revising the
introductory text to read as follows:
§ 2804.40
Alternative requirements.
If you are unable to meet any of the
application requirements in this
subpart, you may request approval for
an alternative requirement from the
BLM. Any such request is not approved
until you receive BLM approval in
writing. Your request to the BLM must:
*
*
*
*
*
Subpart 2805—Terms and Conditions
of Grants
18. Amend § 2805.10 by revising
paragraph (c) to read as follows:
■
§ 2805.10 How will I know whether the
BLM has approved or denied my application
or if my bid for a solar or wind energy
development grant or lease is successful or
unsuccessful?
*
*
*
*
*
(c) If you agree with the terms and
conditions of the unsigned grant or
lease, you should sign and return it to
the BLM with any payment required
PO 00000
Frm 00047
Fmt 4701
Sfmt 4700
35679
under § 2805.16. The BLM will issue the
right-of-way by signing the grant or
lease and transmitting it to you, if the
regulations in this part, including
§ 2804.26, remain satisfied.
*
*
*
*
*
■ 19. Amend § 2805.11 by revising the
section heading and paragraphs (c)(2)
introductory text and (c)(2)(iv) and (v)
and adding paragraph (b)(4) to read as
follows:
§ 2805.11
contain?
What does a grant or lease
*
*
*
*
*
(c) * * *
(2) Specific terms for energy grants
and leases, such as solar or wind energy
development projects, are as follows:
*
*
*
*
*
(iv) Energy generation facilities,
including solar or wind energy
development facilities, are authorized
with a grant or lease for up to 50 years
(plus initial partial year of issuance),
subject to the terms and conditions
including but not limited to
§ 2805.12(c); and
(v) Energy storage facilities which are
separate from energy generation
facilities are authorized with a right-ofway grant for up to 50 years, subject to
the terms and conditions including but
not limited to § 2805.12(c);
*
*
*
*
*
(4) Electric transmission lines with a
capacity of 100 kV or more are
authorized with a right-of-way grant for
up to 50 years.
*
*
*
*
*
■ 20. Amend § 2805.12 by adding
paragraph (c)(8) and by revising
paragraph (e)(2) to read as follows:
§ 2805.12 What terms and conditions must
I comply with?
*
*
*
*
*
(c) * * *
(8) Comply with the operational
standards in this section for solar or
wind energy development projects on
public lands. The holder of a grant or
lease for solar or wind energy
development is authorized to operate for
the purpose of generating energy.
Diligent operation requires the holder to
annually maintain at least 75 percent of
energy generation capacity for the
authorized development. Failure to
meet this required generation in
continuous two calendar year period
during the term of the grant or lease may
support suspension or termination of
the grant or lease under §§ 2807.17
through 2807.19. Before suspending or
terminating the authorization, the BLM
will send you a notice that gives you a
reasonable opportunity to correct any
E:\FR\FM\01MYR6.SGM
01MYR6
35680
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
noncompliance or to start or resume use
of the right-of-way (see § 2807.18). In
response to this notice, you must:
(i) Provide reasonable justification for
any reductions in energy generation (for
example, delays in equipment delivery,
legal challenges, and Acts of God);
(ii) Provide the anticipated date in
which production of energy generation
will resume; and
(iii) Submit a written request under
paragraph (e) of this section for
extension of the period in which the
holder must satisfy the minimum energy
threshold. If you do not comply with the
requirements of paragraph (c)(8) of this
section, the BLM may deny your request
for an extension of the period for
complying with the minimum energy
generation threshold.
*
*
*
*
*
(e) * * *
(2) You may also request that the BLM
consider alternative stipulations, terms,
or conditions, other than rents or fees,
and except as provided in
§ 2806.52(b)(1)(i). Any proposed
alternative stipulation, term, or
condition must comply with applicable
law in order to be considered. Any
proposed alternative to applicable
bonding requirements must provide the
United States with adequate financial
assurance for potential liabilities
associated with your right-of-way grant
or lease. Any such request is not
approved until you receive BLM
approval in writing.
21. Revise § 2805.13 to read as
follows:
■
§ 2805.13 When is a grant or lease
effective?
A grant is effective after both you and
the BLM sign it. You must accept its
terms and conditions in writing and pay
any necessary rent and monitoring fees
as set forth in subpart 2806 of this part
and § 2805.16 of this subpart. Your
written acceptance constitutes an
agreement between you and the BLM
that your right to use the public lands,
as specified in the grant or lease, is
subject to the terms and conditions of
the grant or lease and applicable laws
and regulations.
22. Amend § 2805.14 by revising the
section heading and paragraph (g) to
read as follows:
ddrumheller on DSK120RN23PROD with RULES6
■
*
*
*
*
(g) Apply to renew your right-of-way
grant or lease under § 2807.22;
*
*
*
*
*
VerDate Sep<11>2014
19:07 Apr 30, 2024
Jkt 262001
23. Amend § 2806.10 by revising the
section heading and adding paragraph
(c) to read as follows:
■
§ 2806.10 What rent must I pay for my
grant or lease?
*
*
*
*
*
(c) You must pay rent for your grant
or lease using the per-acre rent schedule
for linear right-of-way grants (see
§ 2806.20) unless a separate rent
schedule is established for your use,
such as for communication sites per
§ 2806.30 or solar and wind energy
development per § 2806.50. The BLM
may also determine that these schedules
do not apply to your right-of-way
pursuant to § 2806.70.
■ 24. Amend § 2806.12 by revising
paragraphs (a)(1) introductory text,
(a)(2), and (b) to read as follows:
greater of the acreage rent or the
capacity fee that would be due in a
given year, and must be paid in advance
each year. The acreage rent will be
calculated consistent with § 2806.11 and
prorated consistent with § 2806.12(a).
The capacity fee will vary depending on
the project’s annual energy generation
on public lands and will be calculated
consistent with § 2806.52(b). Any
underpayment will be billed pursuant to
§ 2806.13 and any overpayment will be
credited pursuant to § 2806.16.
■ 27. Amend § 2806.51 by revising the
section heading and paragraph (c) to
read as follows:
§ 2806.51 Grant and lease rate
adjustments.
(a) * * *
(1) If your grant or lease is effective
on:
*
*
*
*
*
(2) If your grant or lease allows for
multiyear payments, such as a shortterm grant issued for energy site-specific
testing, you may request that your initial
rent bill be for the full term instead of
the initial rent bill periods provided
under paragraph (a)(1)(i) or (ii) of this
section.
(b) You must make all rent payments
for rights-of-way according to the
payment plan described in § 2806.24.
*
*
*
*
*
■ 25. Amend § 2806.20 by revising
paragraph (c) to read as follows:
*
*
*
*
(c) If you hold a right-of-way for solar
or wind energy development that is in
effect prior to July 1, 2024, you may
either request that the BLM apply the
annual rent and fee set forth in
§ 2806.52 or use the rate methodology
applicable to your authorization
immediately prior to this rule. If you
wish to use the annual rent and fee set
forth in § 2806.52, your request must be
received by the BLM before July 1, 2026.
The BLM will continue to apply the rate
in effect immediately prior to this rule
unless it receives your request to use the
rate adjustments in this part. A request
to change your rate methodology will
include your agreement to a re-issuance
of the grant or lease with updated Terms
and Conditions found under this part,
pursuant to § 2807.20(f).
■ 28. Amend § 2806.52 by revising the
section heading, the introductory text
and paragraphs (a), (b), and (c) to read
as follows:
§ 2806.20 What is the rent for a linear
right-of-way grant?
§ 2806.52 Annual rents and fees for solar
and wind energy development.
*
You must pay the greater of either an
annual acreage rent or a capacity fee.
The acreage rent and capacity fee are
determined as follows:
(a) Acreage rent. The BLM will
calculate the acreage rent for your grant
or lease by multiplying the number of
acres of the authorized area (rounded up
to the nearest tenth of an acre) by the
annual per-acre rate for the year in
which the payment is due.
(1) Per-acre rate. The annual per-acre
rate for your grant or lease is calculated
using the State per-acre value from the
solar or wind energy acreage rent
schedule, the encumbrance factor, the
year of the grant or lease term, and the
annual adjustment factor. The
calculation for determining the annual
per-acre rate is A × B × [(1 + C) ∧ D]
where:
§ 2806.12
When and where do I pay rent?
*
*
*
*
(c) You may obtain a copy of the
current Per Acre Rent Schedule from
any BLM state, district, or field office or
by writing the address found under
§ 2804.14(c) of this part. We also post
the current rent schedule at https://
www.blm.gov.
■ 26. Revise the undesignated center
heading that precedes § 2806.50 and
§ 2806.50 to read as follows:
Solar and Wind Energy Development
Rights-of-Way
§ 2805.14 What rights does a right-of-way
grant or lease convey?
*
Subpart 2806—Annual Rents and
Payments
§ 2806.50 Rents and fees for solar and
wind energy development.
If you hold a right-of-way for solar or
wind energy development, you must
pay an annual rent and fee in
accordance with this section and
subpart. The annual rent and fee is the
PO 00000
Frm 00048
Fmt 4701
Sfmt 4700
*
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
(i) A is the state per-acre value from
the solar or wind energy acreage rent
schedule published by the BLM for the
year on which your right-of-way grant or
lease is issued and is based on the
National Agricultural Statistics Service
(NASS) Survey of Pastureland Rents.
The BLM will prepare the rent schedule
by averaging the NASS reported
pastureland rents for the most recent 5year period, using only those years for
which rent is reported by NASS. The
BLM will update the rent schedule
every 5 years consistent with the timing
of rent adjustments under § 2806.22.
(ii) B is the encumbrance factor,
which is 100 percent for solar energy
and 5 percent for wind energy;
(iii) C is the annual adjustment factor,
which is 3 percent; and,
(iv) D is the year of the grant or lease
term, which is the number of years the
grant or lease has been authorized. For
example, the first year (whether partial
or full year) would be 0 and the second
year would be 1.
(2) You may obtain a copy of the
current solar or wind energy acreage
rent schedule from any BLM state,
district, or field office or by writing the
address found under § 2804.14(c) of this
part, Attention: Renewable Energy
Coordination Office. The BLM also
posts the current solar energy acreage
rent schedule at https://www.blm.gov.
(b) Capacity fee. (1) The capacity fee
is calculated using the MWh rate or the
alternative MWh rate, the MWh rate
reduction, the domestic content
reduction, the Project Labor Agreement
(PLA) reduction, the rate of return, the
year of the grant or lease, the annual
adjustment factor, and the annual power
generated on the right-of-way. You must
pay the capacity fee annually, beginning
the year in which electricity generation
begins or is scheduled to begin in the
approved POD, whichever comes first,
unless the acreage rent (see paragraph
(a) of this section) exceeds the capacity
fee in a given year. The calculation for
determining the capacity fee is A × B ×
C × D × [(1 + E) ∧F] × G × H where:
(i) A is the MWh rate or the
alternative MWh rate. The MWh rate is
the annual weighted average wholesale
price per MWh for the major trading
hubs serving the 11 Western States of
the continental United States for the full
5 calendar-year period preceding the
year in which your grant or lease was
issued, rounded to the nearest dollar
increment (see paragraph (7)). An
Alternative MWh rate may be approved
by the BLM if you have entered into a
power purchase agreement, such as with
a utility, and that rate is lower than the
MWh rate. You must provide proof of
the lower rate to the BLM, and if the
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
BLM determines the lower rate is
appropriate, the alternative MWh rate
will be used in place of the MWh rate.
(ii) B is the MWh rate reduction,
which is equal to 80 percent for fee
payments due before 2036. Starting
2036, the MWh rate reduction for new
authorizations transitions to 20 percent,
as follows:
TABLE 1 TO PARAGRAPH (b)(1)(ii)
Calendar year
MWh rate
reduction
(%)
2035 ..................
2036 ..................
2037 ..................
2038 and beyond ..............
B—
calculation
multiplier
(%)
80
60
40
20
40
60
20
80
(iii) C is the Domestic Content
reduction, which is equal to 1.0 for fee
payments when a holder’s project does
not qualify for the domestic content
reduction. C is equal to 0.8 when the
holder can demonstrate that a facility
qualifies for the domestic content
reduction. A facility qualifies for the
domestic content reduction if a holder
documents that the facility would
qualify as ‘‘Produced in the United
States’’, consistent with 2 CFR part 184.
(iv) D is the factor for the Project
Labor Agreement reduction, which is
equal to 1.0 for fee payments when the
holder does not execute a PLA. D is
equal to 0.8 if the holder executes a PLA
for the construction of the project.
(v) Request for conditional approval:
Alternative MWh rate, Domestic Content
reduction and PLA reduction. The
alternative MWh rate, the Domestic
Content reduction and PLA reduction
(paragraphs (b)(1)(ii) and (iii) and (iv) of
this section) may only be applied if a
request for conditional approval is
received by the BLM prior to the
issuance of a grant or lease. A request
for conditional approval must be
submitted with sufficient
documentation to demonstrate that the
development qualifies or may later
qualify for the rate reductions. A request
for conditional approval is subject to the
holder demonstrating, to the satisfaction
of the BLM’s Authorized Officer, that
the development qualifies. If energy
generation begins before the holder has
demonstrated that the facility qualifies,
the BLM will charge the holder the full
capacity fee, without the alternative
MWh rate, Domestic Content reduction,
or PLA reduction. The capacity fee may
be updated for subsequent calendar
years after the holder demonstrates that
the facility qualifies, but the BLM will
not refund past payments made before
PO 00000
Frm 00049
Fmt 4701
Sfmt 4700
35681
the alternative MWh rate, domestic
content reduction, or PLA reduction
went into effect.
(2) E is the annual adjustment factor,
which is 3 percent.
(3) F is the year of the grant or lease
term, which is the number of years the
grant or lease has been authorized. For
example, the first year (whether partial
or full year) would be 0 and the second
year would be 1.
(4) G is the rate of return, which is 7
percent.
(5) H is the annual energy generated
on the right-of-way and will be provided
to the BLM by the grant or leaseholder
in an annual certified statement. The
BLM will bill to coincide with the start
of the calendar year. The first-year
payment in advance will be based on
estimated energy generation and the
BLM will determine final payment for
the first year based on actual energy
generation. Subsequent payments in
advance will be based on the most
recent calendar year’s actual energy
generation reported on the certified
statement, unless exception is approved
in paragraph (vi) of this section.
(i) The holder must submit the annual
certified statement to the BLM before
the first year of energy generation begins
or is scheduled to begin as approved in
the Plan of Development, whichever
comes first. Certified annual statements
must be submitted to the BLM by
October, each year.
(ii) Prior to the start of energy
generation, the holder must submit to
the BLM in the certified statement the
estimated energy generation of the
development for the first year.
(iii) Once energy generation has
begun, the holder must submit to the
BLM in the certified statement the most
recent calendar year’s actual energy
generation of the development.
(iv) The BLM will calculate the
capacity fee from the certified
statement. For projects that include
generation on public and non-public
lands, the holder will prorate the total
energy generation by the percentage of
the right-of-way footprint on public
lands relative to the total development
area footprint.
(v) If the year’s actual energy
generation exceeds or is less than the
amount of energy generation used to bill
for the payment in advance, the holder
will be billed, credited, or refunded for
the underpayment or overpayments
pursuant to §§ 2806.13(e) and 2806.16.
In no event will the total payment be
less than the annual acreage rent.
(vi) The BLM may approve a request
made by a right-of-way holder to
provide a new estimate of energy
generation to the BLM in the annual
E:\FR\FM\01MYR6.SGM
01MYR6
ddrumheller on DSK120RN23PROD with RULES6
35682
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
certified statement to use for billing the
next year’s payment in advance if: the
right-of-way holder has planned
maintenance activities, or other
interruptions to energy generation, that
would reduce the amount of energy
generated by 25 percent or more; or, the
right-of-way holder is aware that the
energy generation in the subsequent
year will exceed the actual energy
generation for the previous year by 25
percent or more. See § 2805.12(c)(8)(i)
through (iii) for the steps to follow when
failing to meet diligent operation
requirements.
(vii) If the right-of-way holder
underestimates energy generation by 25
percent or more of the actual energy
generation or does not provide the BLM
with a new estimate when energy
production will exceed the previous
year’s actual production by more than
25 percent, the BLM may assess the
holder a late payment fee of 10 percent
of the actual generation for each year of
underestimation. This section applies
unless the BLM has approved a request
to provide a new estimate under
§ 2806.52(b)(5)(vi), and the approved
new estimate does not underestimate
energy generation by 25 percent or more
of actual energy generation or if the
holder can provide the BLM with
justification consistent with
§ 2805.12(e).
(6) MWh rate schedule. You may
obtain a copy of the current MWh rate
schedule from any BLM state, district,
or field office or by writing the address
found under § 2804.14(c) of this part,
Attention: Renewable Energy
Coordination Office. The BLM also
posts the current MWh rate schedule at
https://www.blm.gov.
(7) Periodic adjustments. (i) The MWh
rate applicable to your right-of-way will
be the MWh rate in effect the first year
for your grant or lease and will not be
updated with subsequent MWh rate
schedule adjustments. The MWh rate
applicable to your right-of-way will only
be updated each year by the annual
adjustment factor under paragraph (b)(2)
of this section.
(ii) The MWh rate schedule for new
grants and leases will be adjusted once
every 5 years consistent with the timing
of rent adjustments under § 2806.22 of
this part and consistent with paragraph
(b)(1) of this section.
(8) The general payment provisions
for rents described in this subpart,
except for § 2806.14(a)(4), also apply to
the capacity fee.
(c) Implementation of the acreage rent
and capacity fee. The rates for acreage
rent and capacity fees apply to all grants
and leases issued after the effective date
of this rule, and to existing grants and
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
leases if the holder elects to continue
paying under the rate setting
methodology established at the time of
your authorization per § 2806.51(c).
*
*
*
*
*
■ 29. Add an undesignated center
heading between §§ 2806.52 and
2806.54 and revise § 2806.54 to read as
follows:
Renewable Energy Rights-of-Way
§ 2806.54 Rent for energy storage facilities
that are not part of a solar or wind energy
development facility.
Rent for energy storage facilities that
are not part of a solar or wind energy
development facility will be determined
pursuant to the linear rent formula set
forth in § 2806.23. The BLM may
determine your rent pursuant to
§ 2806.70 if we determine the linear rent
schedule does not apply.
§ § 2806.60 through 2806.68
[Removed]
30. Remove the undesignated center
heading ‘‘Wind Energy Rights-of-Way’’
and §§ 2806.60 through 2806.68.
■
Subpart 2807—Grant Administration
and Operation
31. Amend § 2807.17 by revising
paragraph (c) to read as follows:
■
§ 2807.17 Under what conditions may BLM
suspend or terminate my grant or lease?
*
*
*
*
*
(c) Your failure to use your right-ofway for its authorized purpose for any
continuous 5-year period creates a
presumption of abandonment, except
for solar and wind energy rights-of-way.
Consistent with § 2805.12(c)(8), a
presumption of abandonment or
insufficient productivity of a grant or
lease for a solar or wind energy
generation occurs for any continuous
two calendar-year period.
■ 32. Amend § 2807.20 by revising
paragraph (b) and adding paragraph (f)
to read as follows:
§ 2807.20 When must I amend my
application, seek an amendment of my
grant or lease, or obtain a new grant or
lease?
*
*
*
*
*
(b) The requirements to amend an
application or grant are the same as
those for a new application, including
paying processing and monitoring fees
and rent according to §§ 2804.14,
2805.16, and 2806.10, except for solar
and wind energy development grants
and leases per § 2806.51(c) requesting a
rent adjustment addressed under
paragraph (f) of this section.
*
*
*
*
*
PO 00000
Frm 00050
Fmt 4701
Sfmt 4700
(f) A request to the BLM per
§ 2806.51(c) to adjust your solar or wind
energy rates must be received before
July 1, 2026. The BLM will re-issue your
grant or lease, without further review,
for the remainder of your existing term
consistent with the requirements of this
part, including processing and
monitoring costs under §§ 2804.14 and
2805.16, the terms and conditions under
§ 2805.12, and rent provision under
§ 2806.50.
■ 33. Amend § 2807.21 by revising
paragraph (e) to read as follows:
§ 2807.21 May I assign or make other
changes to my grant or lease?
*
*
*
*
*
(e) Your assignment is not recognized
until the BLM approves it in writing.
We will approve the assignment if doing
so is in the public interest. We may
modify the grant or lease or add bonding
and other requirements, including
additional terms and conditions, to the
grant or lease when approving the
assignment, except that we may only
modify solar or wind energy leases
where modification is warranted under
§ 2805.15(e). We may decrease rents if
the new holder qualifies for an
exemption (see § 2806.14) or waiver or
reduction (see § 2806.15) and the
previous holder did not. Similarly, we
may increase rents if the previous
holder qualified for an exemption or
waiver or reduction and the new holder
does not. If we approve the assignment,
the benefits and liabilities of the grant
or lease apply to the new grant or
leaseholder.
*
*
*
*
*
■ 34. Revise the heading of subpart 2809
to read as follows:
Subpart 2809—Competitive Process
for Solar and Wind Energy
Development Applications or Leases
35. Revise § 2809.10 to read as
follows:
■
§ 2809.10 Competitive process for energy
development grants and leases.
(a) The BLM may conduct a
competitive process for solar and wind
energy development grants or leases on
its own initiative; or
(b) The BLM may solicit nominations
for public lands to be included in a
competitive process by publishing a call
for nominations under § 2809.11(a); or
(c) You may request that the BLM
conduct a competitive process by
submitting a request in writing that
complies with § 2809.11(b); or
(d) The BLM may conduct a
competitive process if it receives two or
more competing applications.
E:\FR\FM\01MYR6.SGM
01MYR6
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
(e) Except where an applicant has
failed to timely provide information
requested by the BLM under
§ 2804.25(c), the BLM will not offer
lands in a competitive process for which
the BLM has accepted a complete
application, received a Plan of
Development, and entered into a cost
recovery agreement.
■ 36. Revise § 2809.11 to read as
follows:
ddrumheller on DSK120RN23PROD with RULES6
§ 2809.11 How will the BLM call for
nominations?
(a) Call for nominations. The BLM
may publish a call for nominations for
lands to be included in a competitive
process. The BLM will publish this
notice in the Federal Register and may
also use other notification methods,
such as a newspaper of general
circulation in the area affected, or the
internet. The Federal Register notice
and any other notices will include:
(1) The date, time, and location by
which nominations must be submitted;
(2) The date by which nominators will
be notified of the BLM’s decision on
timely submissions;
(3) The area or areas within which
nominations are being requested; and
(4) The qualification for a nominator,
which must include, at a minimum, the
requirements for an applicant, see
§ 2803.10.
(b) Nomination submission.
Nominations for lands to be included in
a competitive process must be in
writing, and include the following:
(1) A refundable nomination fee of $5
per acre;
(2) The nominator’s name and
personal or business address. The name
of only one citizen, association,
partnership, corporation, or
municipality may appear as the
nominator. All communications relating
to submissions will be sent to that name
and address, which constitutes the
nominator’s name and address of
record; and
(3) The legal land description and a
map of the nominated lands. The lands
nominated may be the entire area or part
of the area made available under the call
for nominations.
(c) The BLM will not accept your
submission if it does not comply with
the requirements of this section, or if
you are not qualified to hold a grant or
lease under § 2803.10.
(d) Withdrawing a nomination. A
nomination cannot be withdrawn,
except by the BLM for cause, in which
case the nomination fee will be
refunded.
(e) The BLM may decide whether to
conduct an offer for nominated lands.
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
37. Revise § 2809.12 to read as
follows:
■
§ 2809.12 How will the BLM select and
prepare parcels?
(a) The BLM will identify parcels for
a competitive process based on
information received in public
nominations, land use designations, and
on any other information it deems
relevant.
(b) The BLM and other Federal
agencies, as applicable, may conduct
necessary studies and site evaluation
work, including applicable
environmental reviews and public
meetings, before offering lands in a
competitive process.
(c) The BLM’s choice to conduct a
competitive process is not a decision to
grant or deny a right-of-way application
and is not subject to appeal under 43
CFR part 4.
■ 38. Amend § 2809.13 by revising
paragraphs (b)(7) and (c) to read as
follows:
§ 2809.13 How will the BLM conduct
competitive processes?
*
*
*
*
*
(b) * * *
(7) The terms and conditions of the
process, including whether a successful
bidder will become a preferred
applicant or a presumptive leaseholder;
the requirements for the successful
bidder to submit an application, see
§ 2804.12, or a Plan of Development, see
§ 2809.18; and any mitigation
requirements, including compensatory
mitigation.
(c) We will notify you in writing of
our decision to conduct a competitive
process at least 30 days prior to the
competitive process if you nominated
lands that are included in the process,
paid the nomination fees, and
demonstrated your qualifications to
hold a grant or lease as required by
§ 2809.11.
■ 39. Amend § 2809.15 by:
■ a. Revising paragraph (a);
■ b. Removing paragraph (d);
■ c. Redesignating paragraphs (b) and
(c) as paragraphs (c) and (d),
respectively;
■ d. Adding a new paragraph (b); and
■ e. Revising newly redesignated
paragraphs (d)(1) through (4);
■ f. Adding paragraph (d)(5); and
■ f. Revising paragraph (e).
The revisions and addition read as
follows:
§ 2809.15 How will the BLM select the
successful bidder?
(a) The bidder with the highest total
bid, prior to any variable offset, is the
successful bidder, and may become the
PO 00000
Frm 00051
Fmt 4701
Sfmt 4700
35683
preferred applicant or the presumptive
leaseholder in accordance with
§ 2809.15(b).
(b) The successful bidder will become
the presumptive leaseholder or
preferred applicant only after making
the payments required in paragraph (d)
and satisfying the requirements of this
section and § 2803.10. If the successful
bidder does not satisfy these
requirements, the BLM may make the
next highest bidder the successful
bidder under § 2809.17(b) or re-offer the
lands under § 2809.17(d).
(1) Presumptive leaseholder. (i) The
successful bidder will become a
presumptive leaseholder if:
(A) The lands for which the bidder
has successfully bid are located within
a designated leasing area; and,
(B) The notice of the competitive
process indicated that a successful
bidder will become a presumptive
leaseholder.
(ii) A presumptive leaseholder will be
awarded a lease only if the presumptive
leaseholder submits a proposed Plan of
Development in accordance with
§ 2804.25(c) and the proposed Plan of
Development is approved by the BLM.
(2) Preferred applicant. A successful
bidder who does not become a
presumptive leaseholder in accordance
with § 2809.15(b)(1) may become a
preferred applicant. The preferred
applicant’s application for a grant or
lease will be processed for the parcel
identified in the submission under
§ 2809.12(b). Approval of the
application is not guaranteed and is
solely at the BLM’s discretion. The BLM
will not process other applications for
solar and wind energy development on
lands where a preferred applicant has
been identified, unless allowed by the
preferred applicant.
*
*
*
*
*
(d) * * *
(1) Make payments by personal check,
cashier’s check, certified check, bank
draft, or money order, or by other means
deemed acceptable by the BLM, payable
to the Department of the Interior—
Bureau of Land Management;
(2) By the close of official business
hours on the day on which the BLM
conducts the competitive process or
such other time as the BLM may have
specified in the offer notices, submit for
each parcel:
(3) Within 15 calendar days after the
day on which the BLM conducts the
competitive process, submit the balance
of the bonus bid (after the variable
offsets are applied under paragraph (c)
of this section) to the BLM office
conducting the process; and
(4) Within 15 calendar days after the
day on which the BLM conducts the
E:\FR\FM\01MYR6.SGM
01MYR6
35684
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules and Regulations
competitive process, submit the
application filing fee under § 2804.12(c)
less the application fee submitted under
§ 2809.11(c)(1) (if you are the preferred
applicant), or submit the acreage rent for
the first full year of the lease as
provided in part 2806 (if you are the
presumptive leaseholder).
(5) You may be required to pay
reasonable costs in addition to payment
of the application filing fee when
processing your application, pursuant to
§ 2804.14. A processing or monitoring
Category 6 cost recovery fee may be
reduced by the application filing fee
paid when submitting an application.
(e) The successful bidder will not
become the preferred applicant or be
offered a lease and the BLM will keep
all money that has been submitted with
the competitive process if the successful
bidder does not satisfy the requirements
of paragraph (d) of this section. In this
case, the BLM may make the next
highest bidder the successful bidder
under § 2809.17(b) or re-offer the lands.
■ 40. Amend § 2809.16 by redesignating
paragraph (c)(11) as paragraph (c)(13),
revising paragraphs (c) introductory text
and (c)(10), adding paragraphs (c)(11)
and (12), revising newly redesignated
paragraph (c)(13), and adding paragraph
(e) to read as follows:
§ 2809.16
When do variable offsets apply?
*
*
*
*
(c) The variable offset may be based
on the following factors, including
progressive steps towards:
*
*
*
*
*
ddrumheller on DSK120RN23PROD with RULES6
*
VerDate Sep<11>2014
18:32 Apr 30, 2024
Jkt 262001
(10) Public benefits;
(11) Use of items qualifying for the
Domestic Content preference;
(12) Use of a project labor agreement;
and
(13) Other factors.
*
*
*
*
*
(e) If the successful bidder’s eligibility
for a variable offset cannot be verified
until a later time, the BLM may require
the successful bidder to submit the full
bid amount, without taking into account
the variable offset, and hold the amount
of the variable offset in suspense. The
amount of the bonus bid corresponding
to the variable offset will be refunded or
credited to the successful bidder once
the successful bidder has demonstrated
that it has qualified for the variable
offset. The BLM may set a deadline in
the notice of competitive process by
which the successful bidder must
demonstrate its qualifications.
41. Amend § 2809.17 by revising
paragraph (b) and removing paragraph
(d) to read as follows:
■
§ 2809.17 Will the BLM ever reject bids or
re-conduct a competitive process?
*
*
*
*
*
(b) We may make the next highest
bidder the successful bidder if the first
successful bidder does not satisfy the
requirements of § 2809.15, does not
execute the lease, or is for any reason
disqualified from holding the lease.
*
*
*
*
*
PO 00000
Frm 00052
Fmt 4701
Sfmt 9990
42. Amend § 2809.18 by revising the
introductory text and paragraphs (a), (b),
and (f) to read as follows:
■
§ 2809.18 What terms and conditions
apply to a solar and wind energy
development lease?
The lease will be issued subject to the
following terms and conditions:
(a) Site control. A lease provides site
control to the leaseholder. The term of
your lease will be consistent with
§ 2805.11(b) and will terminate on
December 31 of the final year of the
lease term. You may submit an
application for renewal under
§ 2805.14(g). A leaseholder may not
construct any facilities on the right-ofway until the BLM issues a notice to
proceed or other written form of
approval to begin surface disturbing
activities.
(b) Rent. You must pay any rent as
specified in § 2806.52.
*
*
*
*
*
(f) Assignments. You may apply to
assign your lease under § 2807.21, and
if an assignment is approved, the BLM
will not make any changes to the lease
terms or conditions, as provided for by
§ 2807.21(e), except for modifications
required under § 2805.15(e).
*
*
*
*
*
§ 2809.19
■
[Removed]
43. Remove § 2809.19.
[FR Doc. 2024–08099 Filed 4–30–24; 8:45 am]
BILLING CODE 4331–29–P
E:\FR\FM\01MYR6.SGM
01MYR6
Agencies
[Federal Register Volume 89, Number 85 (Wednesday, May 1, 2024)]
[Rules and Regulations]
[Pages 35634-35684]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-08099]
[[Page 35633]]
Vol. 89
Wednesday,
No. 85
May 1, 2024
Part VI
Department of the Interior
-----------------------------------------------------------------------
Bureau of Land Management
-----------------------------------------------------------------------
43 CFR Part 2800
Rights-of-Way, Leasing, and Operations for Renewable Energy; Final Rule
Federal Register / Vol. 89, No. 85 / Wednesday, May 1, 2024 / Rules
and Regulations
[[Page 35634]]
-----------------------------------------------------------------------
DEPARTMENT OF THE INTERIOR
Bureau of Land Management
43 CFR Part 2800
[BLM_HQ_FRN_MO# 4500177145]
RIN 1004-AE78
Rights-of-Way, Leasing, and Operations for Renewable Energy
AGENCY: Bureau of Land Management, Interior.
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: This final rule updates procedures governing the BLM's
renewable energy and right-of-way programs, focusing on two main
topics. The first topic is solar and wind energy generation rents and
fees, implementing new authority from the Energy Act of 2020 to
``reduce acreage rental rates and capacity fees, or both, for existing
and new wind and solar authorizations'' and making certain findings
required by the statute. The second topic is expanding agency
discretion to process applications for solar and wind energy generation
rights-of-way inside designated leasing areas (DLAs). In addition to
these two main topics, this final rule makes technical changes,
corrections, and clarifications to the regulations. This final rule
will update the BLM's procedures governing the BLM's administration of
rights-of-way issued under Title V of the Federal Land Policy and
Management Act (FLPMA), including for solar and wind energy
applications and development authorizations.
DATES: This rule is effective July 1, 2024.
FOR FURTHER INFORMATION CONTACT: Jayme Lopez, Interagency Coordination
Liaison, by phone at (520) 235-4581, or by email at [email protected] for
information relating to the BLM Renewable Energy programs and
information about the final rule. Please use ``RIN 1004-AE78'' in the
subject line. Individuals in the United States who are deaf, deafblind,
hard of hearing, or have a speech disability may dial 711 (TTY, TDD, or
TeleBraille) to access telecommunications relay services. Individuals
outside the United States should use the relay services offered within
their country to make international calls to the point-of-contact in
the United States.
SUPPLEMENTARY INFORMATION:
I. Executive Summary
II. Background
III. Discussion of Public Comments on the Proposed Rule
IV. Section-by-Section Discussion
V. Procedural Matters
I. Executive Summary
In 2021, the Bureau of Land Management (BLM) initiated preliminary
activities related to rulemaking through listening sessions seeking
public comment on the BLM's potential use of the Energy Act of 2020 (43
U.S.C. 3003) authority to ``reduce acreage rental rates and capacity
fees'' to ``promote the greatest use of wind and solar energy
resources.'' In May 2022, the BLM published BLM Manual section 2806.60
as interim guidance to implement that authority from the Energy Act of
2020 pending completion of this final rule. On June 16, 2023, the BLM
published a proposed rule (88 FR 39726 \1\) in the Federal Register,
that, among other things, proposed updates to the BLM's methodology for
determining acreage rents and capacity fees for solar and wind energy
development projects, including providing opportunities for reductions
to rents and fees under the authority of the Energy Act of 2020. The
BLM also proposed more flexibility in how the BLM processes
applications for solar and wind energy development inside DLAs, and
updates to how to prioritize solar and wind energy applications. The
proposed rule also suggested technical changes, corrections, and
clarifications to the existing right-of-way regulations. After
considering comments on the proposed rule and other factors, the BLM
prepared this final rule.
---------------------------------------------------------------------------
\1\ https://www.federalregister.gov/documents/2023/06/16/2023-12178/rights-of-way-leasing-and-operations-for-renewable-energy.
---------------------------------------------------------------------------
II. Background
The BLM's governing regulations for rights-of-way, including for
solar and wind energy generation, are found at Title 43 CFR part 2800.
These regulations were last comprehensively updated by a final rule
published in the Federal Register on December 19, 2016, ``Competitive
Processes, Terms, and Conditions for Leasing Public Lands for Solar and
Wind Energy Development and Technical Changes and Corrections'' (81 FR
92122). That final rule built upon existing rights-of-way regulations
and policies to expand BLM's ability to responsibly facilitate solar
and wind energy development.
Most recently, the BLM amended components of 43 CFR part 2800 under
its final rule, ``Update of the Communications Uses Program, Cost
Recovery Fee Schedules, and Section 512 of FLPMA for Rights-of-Way,''
(89 FR 25922) on April 12, 2024. That final rule updated BLM
regulations to enhance the communications uses program, update its cost
recovery fee schedules, and add provisions governing the development
and approval of operations, maintenance, and fire prevention plans and
agreements for rights-of-way for electric transmission and distribution
facilities (i.e., powerlines). That final rule also included technical
changes to certain sections that this renewable energy rule proposed to
make changes to, as will be discussed further in the section-by-section
discussion of this final rule.
Solar and Wind Energy Rents and Fees
Title V of FLPMA (43 U.S.C. 1761-1772) generally requires grant
holders, leaseholders, or both (holders) to ``pay in advance the fair
market value'' for use of the public lands, subject to certain
exceptions. The Energy Act of 2020, 43 U.S.C. 3003, introduced a new
exception to FLPMA's fair market value requirement, authorizing the
Secretary to ``reduce acreage rental rates and capacity fees, or both,
for existing and new wind and solar authorizations'' if the agency
makes certain findings. These findings can include that the existing
rates ``exceed fair market value,'' ``impose economic hardships'' or
``limit commercial interest in a competitive lease sale or right-of-way
grant,'' or ``that a reduced rental rate or capacity fee is necessary
to promote the greatest use of wind and solar energy resources.'' 43
U.S.C. 3003(b)(1)(A)-(C) and 3003(b)(2).
As reflected in this final rule, the BLM determined that the
changes to the acreage rents and capacity fees for solar and wind
energy right-of-way authorizations are needed to ``promote the greatest
use of wind and solar energy resources'' and maximize ``commercial
interest'' in lease sales and right-of-way grants. Reducing the acreage
rent and capacity fee in this final rule will encourage solar and wind
energy development with a goal of increasing the share of clean energy
that is part of the United States' domestic power infrastructure as
authorized by the Energy Act of 2020 and directed by Executive Orders
14008 and 14057. This will be done by decreasing the costs for
developers to construct and operate solar and wind energy development,
allowing them to increase investments in new facilities and thus
promote additional development. These changes will result in the most
additional deployment of solar and wind energy development (see
Regulatory Impact Analysis 3.1.D). The BLM's determination is supported
by a regulatory impact analysis of economic impacts, public comments
received on
[[Page 35635]]
the proposed rule, and the BLM's experience with solar and wind energy
development on public lands.
Reductions in costs will also benefit smaller-scale projects or
projects that are on the margins of being economically profitable.
Additionally, the BLM expects that the rule will not only increase
interest among renewable energy developers to use BLM-administered
public lands, but it will decrease the cost for developers such that
they may be able to invest in additional wind and solar projects on
Tribal, State, or private lands. Further, the decrease in cost to
developers is expected to translate, over time, to a reduction in the
average cost per MW of solar and wind energy, which will make solar-
and wind-generated energy more competitive with other energy sources
and will stabilize or even reduce the cost of energy to consumers, even
as the cost of other energy sources may experience increased
volatility.
The BLM also determined that the authority provided under the
Energy Act of 2020, 43 U.S.C. 3003, supports two other reductions to
the capacity fees under two potentially qualifying circumstances: (1) a
Domestic Content reduction when a grant holder or lease holder
demonstrates the use of American-made iron, steel, construction
materials, or manufactured products in the construction of the project
consistent with the requirements set forth in this final rule; and (2)
a reduction for Project Labor Agreements (PLAs), i.e., when the holder
uses PLAs to hire labor for the development and construction of a solar
or wind development. The additional, voluntary reductions offered in
this final rule advance the Energy Act of 2020 goal of promoting the
greatest use of solar and wind energy resources. First, a Domestic
Content reduction will provide an incentive to use components made or
manufactured in the United States in the construction of the solar or
wind energy development project by offsetting those costs, which, if
broadly adopted, could increase demand for domestically produced
renewable energy parts and materials and, over the long term, lead to
decreased costs for parts and materials, decreased reliance on
potentially volatile foreign-sourced parts and materials, and
ultimately increased economic certainty for and promotion of wind and
solar energy resources on public lands. Second, the PLA reduction will
incentivize good labor practices and in turn lead to responsible and
productive construction, minimize the potential duration, and improve
construction standards, thereby promoting the greatest use of wind and
solar resources. These reductions will also incentivize project
proponents to advance other Congressional and Administration goals that
strengthen the use of American products and manufacturing and the
associated labor markets.
Therefore, reductions in the final rule that rely upon authority
from the Energy Act of 2020 include an 80 percent reduction to the MWh
rate when setting the capacity fee and the two additional reductions to
the capacity fee for which right-of-way holders may qualify: a 20
percent Domestic Content reduction and a 20 percent PLA reduction. The
MWh rate reduction applies to projects when they are permitted (or
grants or rights-of-way are re-issued under 2806.51(c)) and continues
for the life of the grant. The MWh rate reduction will be 80 percent
through 2035, 60 percent for new authorizations in 2036, 40 percent for
new authorizations in 2037, and 20 percent for new authorizations in
2038 and beyond. Additional information on the MWh rate is found under
the discussions of Sec. Sec. 2801.5 and 2806.52(b) of this preamble,
as well as more broadly under part 2806 of this preamble.
This final rule also codifies a new rate-setting methodology for
solar and wind energy development projects. Under this rule, the BLM
will collect from right-of-way holders the greater of either an acreage
rent or a capacity fee. The BLM will assess acreage rent by applying
the rate schedule, based on a survey of values for pastureland from the
National Agricultural Statistics Service (NASS) Cash Rents Survey, to
the number of acres that the right-of-way authorizes for use. Capacity
fees reflect the value of generating electricity from solar and wind
energy resources, which are quantified by the number of megawatt hours
(MWh) of electricity produced from public lands. In this rule, the BLM
has changed the definition of capacity to move away from the maximum
capacity that a solar facility could produce and towards ensuring that
the capacity fee reflects the actual capacity for solar or wind energy
generation of a site covered by a given right-of-way grant or lease,
taking into consideration environmental or other factors that may
impact generation capacity of the site, including weather, servicing,
and Acts of God. As provided in the final rule, the BLM will determine
the capacity fee by considering the wholesale prices for major trading
hubs serving 11 western States, and documentation concerning the price
received by the right-of-way holder under a Power Purchase Agreement.
The final rule provides that, when issuing a grant or lease for
solar or wind energy development, or a renewal of such grant or lease,
the BLM will set the per-acre rate and the MWh rate (including
applicable reductions). The acreage rent and capacity fee will be
adjusted annually, however, using an annual adjustment factor set at
the beginning of the grant or lease term. Upon renewal of a right-of-
way, the per-acre rate and the MWh rate and reductions would be updated
based on the then-current rates, as well as any applicable reductions
for which the right-of-way holder qualifies at that time.
Existing right-of-way holders may elect to continue using their
current rate setting methodology, which may be updated periodically for
changes in the market, or change to the new rate setting methodology in
this final rule. Otherwise, the new rate setting methodology would only
apply to new or renewed rights-of-way. If an existing right-of-way
holder elects to change to the new rate setting methodology, that
methodology will apply until the end of the right-of-way term.
This final rule bases the capacity fee for solar and wind energy
generation facilities on actual energy generation at each facility
rather than on nameplate capacity. The BLM believes this change more
accurately reflects the actual capacity for energy production of an
individual project based on a developer's selection of technology,
project design, and the solar or wind resource available at a
particular site. This change to the capacity fee indexes the required
payment to the projects' energy generation, being greater when the
project generates more energy and less when it generates less.
This rule improves payment predictability for grant and
leaseholders by revising the key data used for determining the acreage
rent and the capacity fee--the state-wide pastureland rent values and
the wholesale price of electricity--at the time the right-of-way is
issued. In doing so, the per-acre and MWh rates are set for the term of
the right-of-way and only adjusted by the annual adjustment factor and,
in the case of the capacity fee, by the holder's actual annual energy
production. See preamble Sec. Sec. 2806.50 and 2805.52 for a more
detailed discussion of the BLM's proposed methodology for determining
the acreage rent and capacity fee.
Solar and Wind Energy Applications Inside Designated Leasing Areas
In this final rule, the BLM clarifies that it will review and
process applications, including on a non-
[[Page 35636]]
competitive basis, for proposed solar and energy generation rights-of-
way inside DLAs, which are defined at 43 CFR 2801.5(b). The BLM retains
discretion to conduct competitive processes, either inside or outside
of DLAs, where the authorized officer decides to do so. In the proposed
rule, the BLM used the terms ``competitive offer'' and ``competitive
process'' interchangeably. To provide clarity and minimize confusion,
the final rule uses only the term ``competitive process'' to describe
the method by with the BLM will offer parcels in a competitive bidding
process. To learn more about BLM's DLAs, see the 2012 Western Solar
Plan (https://blmsolar.anl.gov/documents/solar-peis/), which identified
approximately 285,000 acres of agency preferred development locations
(i.e., DLAs) with high potential for solar energy production and low
conflicts with other resources and uses. Subsequently, the BLM
designated approximately 388,000 acres of preferred development
locations for solar energy in California through the 2016 Desert
Renewable Energy Conservation Plan (https://blmsolar.anl.gov/documents/drecp/) and over 192,000 acres of preferred development locations for
solar, wind, and geothermal energy in Arizona through the 2017
Restoration Design Energy Project. Currently, the BLM is in the process
of updating its 2012 Western Solar Plan to, among other things, make
programmatic planning decisions for solar development on BLM-
administered lands in 11 western states, including Arizona, California
(exclusive of the area covered by the Desert Renewable Energy
Conservation Plan), Colorado, Idaho, Montana, Nevada, New Mexico, Utah,
Oregon, Washington, and Wyoming (See https://eplanning.blm.gov/eplanning-ui/project/2022371/510).
Under this final rule, if no competitive interest exists for a
particular parcel, the BLM may issue leases without a competitive
process. This change to the rule provides the BLM with increased
flexibility and discretion to issue grants and leases through either
competitive or non-competitive processes across all public lands inside
and outside of DLAs, which is expected to maximize interest in
renewable energy leasing and accelerate the deployment of solar and
wind energy on the public lands. See subpart 2809 for a discussion of
the competitive process for solar and wind energy.
Need for the Rule
FLPMA provides the BLM with comprehensive authority for the
administration and protection of the public lands and their resources
and directs that the public lands be managed ``on the basis of multiple
use and sustained yield'' unless otherwise provided by law (43 U.S.C.
1732(a)). Further, FLPMA authorizes the BLM to issue rights-of-way on
the public lands for electric generation systems, including solar and
wind energy generation systems, and mandates that the United States
receive fair market value for the use of the public lands and their
resources unless otherwise provided for by statute (43 U.S.C. 1764(g)).
On December 27, 2020, the Energy Act of 2020 was enacted,
establishing a minimum goal of ``authoriz[ing] production of not less
than 25 gigawatts of electricity from wind, solar, and geothermal
energy projects by not later than 2025'' on Federal lands. 43 U.S.C.
3004. Current information regarding the BLM's approved energy
development projects and number of gigawatts is available on its
website.\2\ The Energy Act of 2020 also provides the BLM with new
authority to reduce rates below fair market value based on specific
findings, including ``that a reduced rental rate or capacity fee is
necessary to promote the greatest use of wind and solar energy
resources'' 43 U.S.C. 3003(b)(2). The BLM has determined that reduced
rates and fees are necessary to promote the greatest use of wind and
solar energy resources, and this rule seeks to implement such
reductions consistent with the direction in the Energy Act of 2020.
---------------------------------------------------------------------------
\2\ https://www.blm.gov/programs/energy-and-minerals/renewable-energy/active-renewable-projects.
---------------------------------------------------------------------------
On January 27, 2021, President Biden issued Executive Order (E.O.)
14008, ``Tackling the Climate Crisis at Home and Abroad.'' Section 207
of E.O. 14008, titled ``Renewable Energy on Public Lands and in
Offshore Waters,'' instructs DOI ``to increase renewable energy
production on (public) lands.''
The changes in this rulemaking will provide clearer direction for
the BLM in processing proposed renewable energy right-of-way
applications on public lands while also supporting the goals of the
Energy Act of 2020 and E.O. 14008.
Statutory Authority
Section 310 of FLPMA (43 U.S.C. 1740) authorizes the Secretary to
promulgate regulations to carry out the purposes of FLPMA and other
laws applicable to public lands. Section 302 of FLPMA (43 U.S.C. 1732)
also provides comprehensive authority for the administration and
protection of the public lands and their resources and directs that the
public lands be managed ``under principles of multiple use and
sustained yield,'' unless otherwise provided by law (43 U.S.C.
1732(a)). Sections 501, 504, and 505 of FLPMA authorize the Secretary
to grant rights-of-way on public lands; to issue regulations governing
such rights-of-way and charge rent for such rights-of-way; and to
impose terms and conditions on rights-of-way grants, respectively (43
U.S.C. 1761, 1764, and 1765). Sections 304 and 504 of FLPMA (43 U.S.C.
1734(b) and 1764(g)) also authorize the BLM to collect funds from
right-of-way applicants or holders to reimburse the agency for its
costs incurred while working on a proposed or authorized right-of-way.
As defined by FLPMA, the term ``right-of-way'' includes an easement,
lease, permit, or license to occupy, use, or traverse public lands (43
U.S.C. 1702(f)). See Title V of FLPMA (43 U.S.C. 1761-1772).
The Energy Act of 2020 authorizes the Secretary to reduce acreage
rental rates and capacity fees if the Secretary makes certain findings,
which can include that the existing rates ``impose economic hardships''
or ``limit commercial interest in a competitive lease sale or right-of-
way grant,'' or ``that a reduced rental rate or capacity fee is
necessary to promote the greatest use of wind and solar energy
resources'' (43 U.S.C. 3003).
III. Discussion of Public Comments on the Proposed Rule
This section of the preamble briefly summarizes broad and general
comments on the proposed rule and the BLM's responses. Comment
responses within this section of the preamble have been grouped and
summarized by category that would apply to one or more sections of this
final rule. You will find additional comments that are more specific to
sections of this final rule, and their responses, in Section IV
(Section-by-Section Discussion) of this preamble.
Solar and Wind Energy Rents and Fees--Part 2806
Summary of Comments: While several commenters supported the
proposal for reduced rents and fees, other commenters questioned the
need for reduced rents and fees and requested more research and
discussion to determine if current costs exceed fair market value,
impose economic hardships, limit commercial interest, are not
competitively priced, or
[[Page 35637]]
disincentivize the greatest use of wind and solar energy resources.
Response: Under the Energy Act of 2020 (43 U.S.C. 3003(b)),
Congress recognized the need to promote wind and solar energy projects
on Federal lands, giving the Secretary the authority to reduce acreage
rental rates, capacity fees, or both if she determines that ``the
existing rates (A) exceed fair market value; (B) impose economic
hardships; (C) limit commercial interest in a competitive lease sale or
right-of-way grant; or (D) are not competitively priced compared to
other available land;'' or that a reduction is ``necessary to promote
the greatest use of wind and solar energy resources.'' 43 U.S.C.
3003(b)(1)-(2). The BLM considered whether capacity fee reductions are
necessary to promote the greatest use of wind and solar energy
resources and has determined reductions are necessary. This final rule
describes how the capacity fee reductions will increase interest in and
incentivize wind and solar energy development on public lands and
thereby accelerate deployment of renewable energy resources in the
United States. This final rule also includes changes to the BLM's rate-
setting methodology that improve future rate predictability (see
Regulatory Impact Analysis) and reduce potential for economic
hardships.
Summary of Comments: Commenters suggested that the BLM should not
speculate on the economic impacts of the proposed rule or requested
additional analysis and use of additional sources to back up statements
made.
Response: The BLM prepared an economic analysis for the proposed
rule and then completed a Regulatory Impact Analysis for this final
rule that provides a transparent analysis of the anticipated economic
consequences for this rulemaking. This analysis informs the agency
decision, including whether this rulemaking would accomplish its goals.
For further information on the economic impacts of this rule, please
see the Regulatory Impact Analysis that is available with a search at
regulations.gov of this Regulatory Identifying Number ``1004-AE78.''
Summary of Comments: Commenters suggested rents and fees should be
increased rather than decreased due to the environmental impacts of
solar and wind energy development, as well as their incompatibility
with other uses. Some further suggested that reducing fees on projects
that are on the margins of being profitable creates the risk of
projects failing and not being properly removed and rehabilitated.
Response: The BLM disagrees with the commenters' suggestion that
rents and fees should be increased rather than decreased. As explained
in more detail in the previous section on Solar and Wind Energy Rents
and Fees, the Energy Act of 2020 (43 U.S.C. 3003) provides the BLM with
authority to reduce acreage rents and capacity fees, including for the
purpose of promoting the greatest use of wind and solar resources. The
BLM has determined that reductions in acreage rents and capacity fees
will promote wind and solar resources and is within the BLM's
discretion under the Energy Act of 2020. Further, the BLM has carefully
considered its final rule and concluded that decreasing rents and fees
is necessary to accomplish the goals set forth by Congress in the
Energy Act of 2020, by the President in E.O. 14008, and by the
Secretary in Secretary's Order 3399. Congress set a national goal for
renewable energy production on Federal land, directing the Secretary to
seek to issue permits authorizing production of not less than 25
gigawatts of electricity from wind, solar, and geothermal energy
projects on Federal land by not later than 2025. 43 U.S.C. 3004.
Congress further provided the Secretary with discretion to reduce the
acreage rental rates and capacity fees, including where necessary to
promote the greatest use of solar and wind energy resources on BLM-
administered public lands, which would advance the goals set by the
Energy Act of 2020, as well as those in E.O. 13990, ``Protecting Public
Health and the Environment and Restoring Science to Tackle the Climate
Crisis,'' 86 FR 7037; E.O. 14008, ``Tackling the Climate Crisis at Home
and Abroad,'' 86 FR 7619; and Secretary's Order 3399, ``Department-Wide
Approach to the Climate Crisis and Restoring Transparency and Integrity
to the Decision-Making Process.'' The use of public lands for energy
generation systems is specifically contemplated in the FLPMA and the
Energy Act of 2020. The BLM considers the potential environmental
effects of solar or wind energy development when conducting land use
planning and evaluating project applications, not when identifying
appropriate rental rates and fees for development projects. The BLM
considers and analyzes environmental impacts of proposed energy
development, including appropriate mitigation measures, before
authorizing any such project. Additionally, the BLM does not believe
there is any correlation between reductions in capacity fees and the
ability of project proponents to properly remove and remediate
facilities. Any applicable fee reductions contemplated in this rule
would not alter a project proponent's obligations to provide for
adequate bonding associated with construction and remediation
associated with terminated or abandoned facilities, as required by 43
CFR 2805.12(b), 2805.20, and 2809.18(e).
Summary of Comments: Commenters noted that reducing rents and fees
for renewable energy projects on public lands would economically impact
the developers of similar projects on private or Tribal lands and could
impact property values.
Response: This final rule changes the BLM's administrative
processes and rates for solar and wind energy development projects on
public lands. While the final rule is intended to encourage solar and
wind energy development on the public lands, it would be speculative
for the BLM to attempt to analyze whether and to what extent there may
be secondary impacts to solar and wind energy development on private or
Tribal property. This is particularly the case due to the wide variety
of factors that influence developers' decisions about whether and where
to pursue solar and wind energy projects, including, but not limited
to, state, Tribal, and local permitting requirements, the ability to
enter into power purchase or offtake agreements, the availability of
existing or proposed transmission, and project-specific financing
considerations. Notwithstanding these different factors, the final rule
will generally decrease costs for developers on public lands, which may
permit them to pursue additional opportunities for development on
Tribal, state, and private lands and thereby further promote the
greatest use of solar and wind energy.
Summary of Comments: Some comments asked about rate changes that
would occur after 2036. Commenters raised four specific issues that the
2036 rate change causes. First, some commenters asserted that rates
after 2036 would run higher than fair market value and are therefore a
violation of FLPMA's requirement that the BLM charge no more than fair
market value. Second, some commenters asserted that the Secretary's
authority to reduce rates under the Energy Act extends beyond 2035, and
America's need for renewable energy, set by Congressional and
Presidential goals, would require incentives beyond 2036. Third, some
commenters asserted that the 2036 rate increase would discourage right-
of-way renewals after that year. Last, some commenters asserted that
the BLM has
[[Page 35638]]
not adequately explained why it is choosing to phase out the final
rule's rate reductions in 2036.
Response: This final rule helps lead the way to accomplishing the
national goal of a carbon pollution-free electricity sector by 2035, as
highlighted in Executive Orders 14008 and 14057. Based on its review of
comments, the BLM has modified the sunset provision in the final rule.
Instead of immediately transitioning the capacity fee reduction from 80
percent to 20 percent, the final rule will lower the reduction by 20
percentage points per year over a period of three years starting in
2036. Instituting a phased sunset period to the 80 percent reduction in
the capacity fee is appropriate as the renewable energy industry may no
longer need this reduction to achieve the greatest use of wind and
solar on public lands, and progress toward our national goal of a
carbon-pollution free electricity sector may indicate that a reduction
is no longer warranted. After the sunset period ends, this final rule
will continue to provide a 20 percent reduction for solar and wind
energy development projects. The BLM will evaluate progress towards
reaching national goals and the benefit of the reduction before 2036
and could reinitiate rulemaking to adjust incentives, including
extending them beyond 2036.
The BLM believes that knowing beforehand what the rates are for a
facility and the increased predictability of those rates in the future
will improve the economic certainty for project development and support
a developer's or operator's decisions in power purchasing, financing,
and other agreements that are necessary for a successful renewable
energy project. This would be the same for existing authorization
holders who choose to change to this new rate setting methodology, as
well as for authorization renewals. Lastly, the BLM believes that the
economics for renewable energy will continue to improve over time, and
that the magnitude of such a reduction in 2036 is uncertain.
Lands Available for Solar and Wind Energy Applications
Summary of Comments: Some commenters recommended that the BLM
further restrict renewable energy development outside of solar energy
zones and prohibit such development close to sensitive habitats or
recreation areas. Commenters stated that competitive offers should not
be allowed outside of designated zones.
Response: Through the National Environmental Policy Act (NEPA)
process, the BLM considers the environmental impacts of proposed uses
on the public lands, including solar and wind energy development, to
inform the BLM decisions to deny, approve, or approve with modification
the proposed use. The BLM will include terms and conditions as
appropriate to address resource and environmental impacts of the
project. The BLM also performs broader analysis to inform whether
certain lands may be made available for that use through the land use
planning process required by FLPMA, 43 U.S.C. 1712. As described
further below, the BLM's ongoing planning process to update to its 2012
Western Solar Plan \3\ will amend BLM land use plans in 11 Western
States (Arizona, California, Colorado, Idaho, Montana, Nevada, New
Mexico, Oregon, Utah, Washington, and Wyoming), or portions thereof, to
identify new priority areas for solar energy development, variance
areas, and public lands that are excluded from solar energy
development, and to update requirements that holders must comply with,
including for sensitive resources and uses that the BLM has previously
authorized. This rulemaking does not make land use planning decisions--
including determining whether areas should be excluded from solar and
wind energy development because they would impact sensitive habitats or
recreation areas--which are completed under a separate BLM process.
This rulemaking does not change the competitive process outside of
designated zones, but rather aligns the competitive process for solar
and wind applications across all areas within and outside of designated
areas. The BLM believes that where competitive interest exists--for
example, in the form of multiple overlapping applications or a high
level of interest in a general area--competitive processes should be
used, regardless of whether the lands are in a DLA, to advance the
projects that are most likely to proceed to development.
---------------------------------------------------------------------------
\3\ https://www.federalregister.gov/documents/2022/12/08/2022-26659/notice-of-intent-to-prepare-a-programmatic-environmental-impact-statement-to-evaluate-utility-scale.
---------------------------------------------------------------------------
Summary of Comments: Commenters noted that the BLM references solar
energy zones from the 2012 Western Solar Plan in the proposed rule
without discussing that the 2012 Plan is now under revision and will
include an additional 5 states (Idaho, Montana, Oregon, Washington, and
Wyoming). Commenters requested that the BLM coordinate the rulemaking
process with the land use planning effort accompanying the Western
Solar Programmatic Environmental Impact Statement (Western Solar PEIS),
recognizing the various alternatives being considered and the impacts
that each (Western Solar PEIS vs. proposed rule) have on the other.
Commenters believed many of the changes in this rule that refer to
decisions or processes that occur prior to project approval are
currently being considered as part of the Western Solar PEIS plan
amendment process and may be better suited for the PEIS.
Response: This rulemaking effort and the Western Solar PEIS are two
separate actions that complement one another, but they have different
goals, are subject to different authorities, and will address different
aspects of the ROW authorization process. This final rule sets out how
the BLM will process applications and calculate rents, in order to
implement new authorities and meet National goals established in the
Energy Act and directed by Executive Order 14008 for both wind and
solar energy development. This rulemaking does not make land use
planning decisions. In contrast, the plan amendment process associated
with the Western Solar PEIS focuses exclusively on solar development on
public lands through a separate process governed by Section 202 of
FLPMA (43 U.S.C. 1712) and the BLM resource management planning
regulations at 43 CFR 1610, et seq. to update the BLM's Western Solar
Plan. That programmatic land use planning process will consider
updating the BLM's Western Solar Plan, with a primary focus on
identifying the best locations for utility-scale solar energy
development, as well as restrictions and mitigation applicable to such
development, on BLM-managed public lands in 11 Western States. The
BLM's land use planning decisions, including any amendments to plans,
will comply with applicable laws and regulations.
Comment Summary: The BLM understands from comments it has received
that some believe that the proposed rule has insufficient analysis
under E.O. 12866. These comments suggest that the BLM must coordinate
more closely with local governments to collect economic data.
Response: The BLM appreciates the interest and engagement from
partners across the multiple landscapes in the United States, however
the BLM disagrees with comments that additional coordination must be
performed with local governments for this rulemaking. This rule governs
the BLM's administration of applications and authorizations for solar
and wind energy development projects on public lands. While the rule
does have some financial
[[Page 35639]]
implications with adjustments to the BLM's rates, these are transfer
payments as explained more fully in the Regulatory Impact Analysis
accompanying this final rule and would not materially affect the
resources available to the American economy. The BLM will continue to
engage with the public it serves, and its many partners through BLM's
public processes, including project-specific analysis and programmatic
and land use planning analysis through NEPA. No change made based on
these comments.
Need for the Rule
Summary of Comments: Commenters requested the BLM include a more
meaningful explanation of the necessity of this rulemaking, including
technical data that supports a need for increased preferences and
favorable treatment for lease terms. Commenters stated that solar
development is not in line with FLPMA and does not allow for multiple
use on public lands.
Response: The BLM received new authority and guidance from Congress
(Energy Act of 2020) and direction from the President (Executive Order
14008, among others) to promote renewable energy generation on public
lands. This rule implements the new authority and direction for
management of the public lands. The BLM disagrees with the comments
suggesting that solar energy development is inconsistent with FLPMA's
multiple use mandate. In managing the public lands, the BLM is not
required to make every parcel of land available for all purposes.
Consistent with FLPMA's multiple use mandate, the BLM has discretion
through land use planning to identify areas that are available for, or
excluded from, solar or wind energy development and to evaluate each
proposed solar or wind energy development through a site-specific
environmental analysis, including the need for environmental
mitigation, as part of the decision-making process prior to issuing a
grant or lease.
Summary of Comments: Other commenters stated that they believe the
BLM must improve its approach to facilitating renewable energy
development to meet congressional goals. Other commenters expressed a
belief that the free market would provide better solutions to
greenhouse gas emissions and the climate crisis without authorizing
projects on public land or providing additional incentives to site
projects on public land.
Response: The BLM does not agree that the free market alone would
provide better solutions to greenhouse gas emissions and the climate
crisis. Additionally, the approach suggested by commenters would be
inconsistent with direction from Congress and the President to promote
renewable energy generation on public lands. Particularly, the Energy
Act of 2020, which is aimed at facilitating and promoting further
development of wind and solar energy on Federal lands, specifically
directs the BLM to ``issue permits that, in total, authorize production
of not less than 25 gigawatts of electricity from wind, solar, and
geothermal energy projects by not later than 2025, through management
of public lands and administration of Federal laws,'' 43 U.S.C. 3004(b)
(emphasis added). Additionally, as described above, on January 27,
2021, President Biden issued E.O. 14008, ``Tackling the Climate Crisis
at Home and Abroad.'' Section 207 of E.O. 14008, titled ``Renewable
Energy on Public Lands and in Offshore Waters,'' instructs DOI ``to
increase renewable energy production on [public] lands.'' This final
rule updates and improves the BLM's approach to facilitating renewable
energy development on public lands based on lessons learned from
implementation of the 2016 rule as well as changes in National
renewable energy goals and the maturation of energy market over the
past eight years. This update to the BLM's rules improves the BLM's
orderly administration of public lands and helps reach the goals set by
Congress and at the direction of the President. The BLM expects to
continue working with the public to provide better solutions to
resource concerns, such as greenhouse gas emissions and climate change,
to best manage the public lands and its resources. Addressing such
resource solutions are not part of this rulemaking.
Summary of Comments: Commenters stated that the current market
conditions, state and Federal mandates and regulations, and demand for
green energy makes reducing fees unnecessary and that the BLM has
failed to explain why the reductions are necessary.
Response: The changes in this rule clarify how the BLM will process
renewable energy right-of-way applications on public lands while
supporting the goals of the Energy Act of 2020 and direction from the
President (E.O. 14008 and 14057). Through the BLM's experience
administering solar and wind energy development rights-of-way, the BLM
understands the importance of stable and predictable rates for the term
of an authorization. The BLM expects that the rule will help to meet
national renewable goals more expeditiously. The BLM expects that the
rule will not only increase interest among renewable energy developers
to use BLM-administered public lands, but will decrease the cost for
developers such that they may be able to invest in additional wind and
solar projects on Tribal, State, or private lands. The BLM explains
more fully the need for the rule and its reductions in the section-by-
section discussion portion of this rule under subpart 2806.
Summary of Comments: A commenter stated that section 3003(b) of the
Energy Act does not explicitly authorize the Secretary of the Interior
to reduce right-of-way rents and fees below fair market value and that
Congress did not explicitly repeal, amend, or supersede FLPMA's
unequivocal fair market value requirement. They questioned if the
Energy Act supersedes FLPMA's fair market value requirement for rights-
of-way.
Response: The BLM disagrees with the comments suggesting that the
Energy Act of 2020 does not authorize the Secretary to reduce right-of-
way rents and fees below fair market value. First, a plain reading of
the Energy Act authorizes the Secretary to reduce rental rates and
capacity fees below fair market value. Specifically, it authorizes the
Secretary to reduce ``acreage rental rates, capacity fees, and other
recurring annual fees in total'' for solar and wind energy generation
projects on BLM-managed public lands under a broad set of
circumstances. Additionally, Congress presumably understood the fair
market value requirement in FLPMA, and the discretion in the Energy Act
to reduce rental rates and capacity fees is as a modification of that
existing requirement. The reductions authorized in Section 3003 of the
Energy Act would be meaningless if Congress intended the reductions to
be limited by FLPMA's general requirement to collect fair market value
for rights-of-way.
Statutory Authority
Summary of Comments: One commenter expressed concern that this
proposed rule will set precedent for a similar issue DOI is trying to
address under the Fluid Mineral Leases and Leasing process.
Response: This final rule modifies procedures that are specific to
identifying rental rates and capacity fees for wind and solar
authorizations; it does not apply to or set a precedent for other BLM
authorizations or processes, including those under the Mineral Leasing
Act (MLA).
Summary of Comments: Another commenter requested information about
how this final rule interacts with other BLM rules and administration
[[Page 35640]]
directives, including the Conservation and Landscape Health Rule,
Secretary's Order 3362, Improving Habitat Quality in Western Big-Game
Winter Range and Migration Corridors (Feb. 9, 2018), and BLM
Instruction Memorandum 2023-005 Change 1, Habitat Connectivity on
Public Lands (Nov. 18, 2022).
Response: This final rule updates the processes used in the BLM's
orderly administration of the public lands. Any decisions made in
connection with right-of-way grants following the procedures laid out
in this rule will also be subject to all other applicable legal
requirements and administrative directives, including the Conservation
and Landscape Health Rule, Secretary's Order 3362, and BLM policies and
guidance.
National Environmental Policy Act (NEPA)
Comment Summary: Commenters requested the BLM prepare a NEPA
analysis to evaluate the environmental effects of the final rule,
including because extraordinary circumstances (43 CFR 46.215) apply and
therefore reliance on a Categorical Exclusion is not appropriate.
Response: The BLM disagrees with comments that an environmental
assessment or environmental impact statement analysis under NEPA is
required, or that extraordinary circumstances apply to this rulemaking.
The BLM has determined that the categorical exclusion at 43 CFR
46.210(i), which excludes, ``regulations . . . that are of an
administrative, financial, legal, technical, or procedural nature; or
whose environmental effects are too broad, speculative, or conjectural
to lend themselves to meaningful analysis and will later be subject to
the NEPA process, either collectively or case-by-case,'' applies to
this final rule. The BLM has reviewed the extraordinary circumstances
listed in 43 CFR 46.215 and determined that none applies. This
categorical exclusion documentation is provided on the BLM's ePlanning
web page at the following URL: https://eplanning.blm.gov/eplanning-ui/project/2016102/510. As such, the final rule fits within the
categorical exclusion for rules, regulations, or policies to establish
bureau-wide administrative procedures, program processes, or
instructions. This final rule does not authorize any project or other
on-the-ground activity and therefore would have no significant
individual or cumulative effect on the quality of the human
environment. At such time that specific solar or wind energy
development projects are proposed, the BLM will consider those proposed
actions in compliance with NEPA.
Comment Summary: Some commenters suggested that there should not be
a requirement of a published environmental assessment (EA) or
environmental impact statement (EIS) before foreclosing the opportunity
to hold a competitive offer. Some commenters believed the BLM should
require analysis of a competitive offer through an EIS to identify and
disclose the impacts of such an action.
Response: The BLM is not required to perform environmental analyses
on whether to hold a competitive process; nonetheless, in Sec.
2809.12(b) the BLM reserves the right to complete a NEPA analysis
before holding a competitive process. The BLM does not typically
complete a NEPA analysis for a competitive leasing process, but at
least one NEPA analysis will be completed before authorizing solar or
wind energy development. Determining that there may be competitive
interest and utilizing a competitive process is administrative and
procedural only, does not trigger the need to prepare an environmental
analysis under NEPA or have any significant effect on the human
environment, and is simply based on whether there is adequate interest
from more than one applicant. The BLM would complete a land use
planning and NEPA analysis were it to change allocations in a current
land use plan to allocate areas of public lands to either allow or
exclude solar or wind energy development--a process the BLM is
currently undertaking regarding solar energy for 11 western states by
updating the 2012 Western Solar Plan through a PEIS.
For example, in the case of solar or wind energy development
leasing, the BLM must first identify public lands as a designated
leasing area for solar or wind energy development through a land use
planning process with an associated NEPA analysis. If the BLM receives
competitive interest in those lands, the BLM would hold a competitive
process to determine the presumptive leaseholder. Alternatively, the
BLM may determine that the NEPA analysis for a designated leasing area
should be updated to reflect new or changing circumstances and in turn
may offer such lands competitively to determine a preferred applicant.
Upon determining the presumptive leaseholder or preferred applicant,
the BLM would then complete a NEPA analysis before determining whether
to authorize the wind or solar energy generation project proposed. For
either the presumptive leaseholder or preferred applicant, even if the
BLM does not complete a NEPA analysis to consider whether to hold a
competitive process, the resulting project will be subject to multiple
NEPA analyses before it is approved.
Additional comments: Additional comments and their responses are
found in Section IV (Section-by-Section Discussion) of this preamble.
The BLM is a multiple-use agency, and solar and wind energy
development is one of the many uses for which the BLM manages the
public lands. While all comments that the BLM received are important,
this final rule does not respond to those that are out of scope for the
action the BLM is taking. Comments that are out of scope for this
rulemaking include those regarding project-specific considerations,
state laws and authorities, national energy policies and priorities
that do not affect solar and wind energy or the public lands, engaging
in specific partnerships, general statements of support or opposition
to the rule which do not require a detailed response, and availability
and distribution of financial resources, among others that are not
specific to the BLM's administration of solar and wind energy
development applications and rights-of-way and rate-setting.
The BLM will continue to engage with the public and Tribal,
Federal, State, and local government partners on the BLM's management
of its public lands, as appropriate. Subsequent actions that the BLM
may take will be subject to the policies, laws, and regulations in
place at that time, including those for consultation, environmental
review, and entering into agreements or partnerships with others.
IV. Section-by-Section Discussion
43 CFR Part 2800 Rights-of-Way Authorized Under FLPMA
Part 2800 of the CFR describes requirements for rights-of-way
issued under Title V of FLPMA. This final rule revises the per acre
rent and per MWh capacity fee schedules for solar and wind energy
development rights-of-way. It updates the application process for
public lands and focuses the BLM's competitive processes to places
where there is competitive interest. This final rule also includes the
principles for prioritizing solar and wind energy applications,
establishing criteria for a ``complete application,'' and corrects or
clarifies existing regulations.
The BLM conducted extensive public and Tribal outreach on this rule
both prior to its publication as a proposed rule and during the public
comment period on the proposed rule. Prior to the
[[Page 35641]]
publication of the proposed rule, the BLM notified Tribes in August
2021 of its upcoming rule and requested any comments and concerns that
Tribes may have on such a rule. The BLM then held three public
listening sessions in September 2021 on its potential use of the Energy
Act of 2020 authority. The BLM also requested and received feedback
from the public on preferred alternatives to use of the Energy Act of
2020 authority in its Manual 2806.60, ``Rent,'' which was later
published in May 2022 after three public listening sessions and public
review and comment on the draft Manual. The BLM published its proposed
rule in June 2023, receiving nearly 900 comments after holding three
virtual public meetings. The BLM also sent Tribes another notice about
the rulemaking in July 2023, requesting Tribal input and whether there
was any interest to consult on the rule. No Tribes responded with
interest to consult on the BLM's rulemaking.
Section 2801.5 What acronyms and terms are used in the regulations in
this part?
The existing Sec. 2801.5 contains the acronyms and defines the
terms used in this part of the regulations. The BLM proposed to remove,
revise, and add acronyms and terms to this section. Section 2801.5 of
this final rule has some revisions in response to comments that are
discussed further in this section for each respective revision.
Under this section, several commenters recommended the BLM engage
relevant stakeholders and industry experts to ensure definitions
accurately reflect industry practices and standards. The BLM regularly
engages, and will continue to engage with, industry; Tribal, Federal,
State and local authorities; and resource experts to supplement its
knowledge about renewable energy and market advancements. The BLM
sought public comment on the proposed rule and will seek public comment
on any changes to its acronyms and terms in future rulemakings.
The BLM received comments requesting the BLM consider the full life
cycle of materials, energy inputs and technology types, and resource
and land use footprints, and suggesting that labeling all wind and
solar energy as renewable energy is misleading. The BLM agrees that it
should analyze land use footprints and resource impacts of proposed
projects on public lands. However, analyzing the full life cycle of
materials, energy inputs, and technology types are addressed by other
parts of the Federal government where such analysis is within their
expertise. The BLM also believes that for purposes of this final rule,
all solar and wind energy generation projects are renewable energy
development projects insofar as they use a natural resource on public
lands that is not depleted to produce power.
One comment suggested that the BLM should include a definition for
``current land use plan'' to mean ``a document developed through a
formal planning process to guide the management of activities and uses
of public lands that has been approved, amended, or recertified within
the past ten years.'' The BLM has separate rules governing its land use
planning processes found at 43 CFR Chapter V, Subchapter A, that
provides definitions related to the BLM's land use planning.
Accordingly, the BLM did not make changes in response to that comment
since they are out of scope for this rule under 43 CFR part 2800.
Commenters suggested that the term ``economic hardship'' under 43
U.S.C. 3003 should be defined in this final rule and that the BLM
should require proof of economic hardship for rent and fee reductions.
The BLM does not define economic hardship in this rule as suggested.
Each instance of hardship is unique to a holder and their circumstances
and will be assessed on a case-by-case basis. The BLM does not intend
to define hardship (economically, financially, or otherwise) so as not
to unintentionally preclude reasonable requests to consider hardship.
Commenters stated that the proposed rule uses unclear language and
is inconsistent with underlying resource management plans, agency
guidance, and regulatory frameworks, and requested the BLM use more
specific language such as pastureland, rangeland, habitat, or other
terminology to denote the uses of the landscape. The BLM disagrees with
the commenters' suggestion that the proposed rule uses unclear language
and that the rule should include other definitions in this final rule.
The BLM's use of ``pastureland rents'' comes from the name of the
survey data used as the basis in determining the acreage rent in this
final rule: The NASS Survey of Pastureland Rents. This is a newer
source of data from NASS that was not available in the original 2012
Western Solar Plan or when the BLM promulgated its 2016 rule for solar
and wind energy and has not yet carried through to other guidance
materials from the BLM. It is appropriate for the BLM to use this
terminology in describing the data used and its source in the
regulations. Future BLM guidance and actions would include this
terminology as appropriate.
Commenters requested the BLM settle on one standard term
(``preferred renewable energy development areas'') for the preferred
renewable energy project locations to avoid conflicts with other
resources and uses. Commenters also suggested that the definitions for
``variance areas'' and ``exclusion areas'' should be added to the rule.
The BLM understands the interest in defining such terms and has already
done so in its land use planning efforts, such as the ongoing Solar
Energy PEIS effort to update the 2012 Western Solar Plan. The BLM
believes these terms are best identified and defined as part of the
land use planning process and is not making any changes to this rule
due to comments.
Paragraph (a) of this final rule provides for the acronyms and
paragraph (b) provides for the terms used in this part. The final rule
would remove, revise, and add certain terms to the BLM's acronyms and
definitions found in part 2800.
This final rule adds the acronym ``FLPMA'' to paragraph (a) meaning
the Federal Land Policy and Management Act of 1976, as amended (43
U.S.C. 1701 et seq.). This acronym replaces the term ``Act'' from
paragraph (b), providing clarity as to which act the BLM is
referencing.
The BLM received no substantive comments on replacing the term
``Act'' with ``FLPMA,'' and therefore this final rule makes no changes
to the proposed rule.
This final rule removes definitions of ``Megawatt (MW) capacity
fee,'' ``Net capacity factor,'' ``Megawatt hour (MWh) price,'' ``Rate
of return,'' and ``Hours per year.'' The BLM no longer charges a
megawatt capacity fee based on solar and wind energy generation
facility nameplate capacity; definitions related to the nameplate
capacity fee are removed. The BLM did not make changes to the
definitions in the final rule.
Some commenters noted inconsistencies related to the terms ``Rate
of Return'' and ``Hours per year.'' Commenters pointed out that the
proposed rule stated that these terms would be removed from Sec.
2801.5(b), noting the paragraph numbering for the Federal Register
instructions were confusing whether the terms were removed or not. The
BLM agrees with commenters and has revised the Federal Register
instructions, removing the proposed instruction number vi, ``removing
paragraphs (1) and (2) in the term ``Megawatt rate'' and redesignating
[[Page 35642]]
paragraphs (3) and (4) as paragraphs (1) and (2). There are no
paragraphs for the revised term, and removing the instructions is
consistent with the proposed definition. The BLM did not make any other
changes to this definition in the final rule.
This final rule adds the term ``Capacity fee'' to mean the fee
based on the amount of electricity produced from solar or wind energy
resources on the public lands. This is consistent with the BLM's change
implementing a capacity fee that is based on electricity production.
There were no substantive comments on the term, and the BLM did not
make changes to this definition in the final rule.
The BLM includes in this final rule a new term ``Domestic Content
reduction'' to define the circumstances in which a holder meets the
domestic content criteria and thus qualifies for a fee reduction. This
final rule includes changes to the term for ``domestic content'' to
mean an item or product that qualifies for the Buy America preference
as set forth in Section 70914 of the Build America, Buy American (BABA)
Act, Public Law 117-58, 135 Stat. 429, Sec. Sec. 70901-70927 (Nov. 15,
2021), and implementing guidance at 2 CFR part 184. The final rule
modifies the definition for ``domestic content'' from the definition of
``domestic end product,'' as that term is used in Section 52.225-1 of
the Federal Acquisition Regulations (FAR) (48 CFR 52.225-1) in the
proposed rule, to the criteria for ``domestic content preference''
provided in the BABA Act and 2 CFR part 184. As described below, the
qualifying definition in this final rule offers clarity and consistency
among Federal programs regarding what constitutes domestic content and
therefore is appropriate to apply to determine when a holder may obtain
a fee reduction as identified under Sec. 2806.52(b).
The BLM has determined that offering a Domestic Content reduction
will further promote the greatest use of solar and wind resources
because it will support the development of secure, reliable domestic
supply chains while also reducing economic hardships for developers. As
discussed in the preamble to the proposed rule, uncertainty in global
supply chain dynamics, as seen in recent years, can delay deployment of
solar and wind energy development projects on public lands (88 FR
39726, 39740-39742). By offsetting some of the costs of domestically
sourced parts and materials, the Domestic Content reduction will
insulate developers from global supply chain shocks of all kinds by
reducing the economic dependence of developers on global supply chains
and will also support the efforts of domestic suppliers. In this way,
the proposed Domestic Content reduction supports the transition to more
reliable domestic supply chains that will, in turn, increase interest
in developing solar and wind energy projects throughout the country,
including on public lands (43 U.S.C. 3003(b)(1)(C)), and thereby would
promote the development of solar and wind energy resources on public
lands (43 U.S.C. 3003(b)(2)).
Similar to the BLM's use in the proposed rule of a definition for
Buy American based on section 52.225-1(b) of the FAR, this final rule's
use of the term ``domestic content,'' following the BABA Act and 2 CFR
part 184, identifies the components of projects through categories--
iron or steel products, manufactured products, or construction
material--that must be produced or manufactured in the United States in
order to qualify for the Domestic Content reduction. The BABA Act
applies to Federal financial assistance funds for ``infrastructure
projects,'' which require the use of material produced in the United
States. The Office of Management and Budget (OMB) published its final
guidance implementing the BABA Act on August 23, 2023, under 2 CFR part
184. Generally, under 2 CFR 184.4(e), a ``domestic content'' preference
would apply to three separate product categories: (i) iron or steel
products; (ii) manufactured products; and (iii) construction materials.
The OMB's guidance defines each of these categories and makes clear how
a proponent satisfies the categorical requirements to demonstrate that
the components of an infrastructure project meet the domestic content
standards. This final rule uses the term ``domestic content'' as a
catch-all term to refer to items for which the holder might satisfy the
Domestic Content reduction based on the definitions established 2 CFR
part 184.
Some commenters suggested that the proposed Buy American definition
should be revised to reflect eligibility for the reduction to mimic the
guidance published by the Treasury Department and Internal Revenue
Service for the domestic content bonus credit from section 13701 of the
Inflation Reduction Act (IRA), 117 Public Law 169, 136 Stat. 1818 (Aug.
16, 2022). Other commenters requested the BLM utilize a domestic
content definition that incentivizes the use of domestically
manufactured core solar components, as laid out in Section 13502 of the
Inflation Reduction Act. Commenters also urged the BLM to refine its
approach and apply more robust origin standards to its domestic content
proposal.
The BLM has considered the various comments suggesting different
definitions for what constitutes American-made products for the
purposes of this reduction. In response to this public input, the BLM
has changed from the FAR definition to the BABA Act (and implementing
guidance at 2 CFR part 184) definition for the domestic content
preference. The BLM is aware that the Treasury Department and Internal
Revenue Service have issued guidance about the domestic content bonus
under the Inflation Reduction Act for clean energy projects and
facilities that meet American manufacturing and sourcing requirements.
However, that guidance describes an intent to propose regulations that
have not yet been finalized. This final rule's definition for domestic
content aligns with definitions in other Federal programs with
oversight over domestic products and content. This approach will
promote consistency among these Federal programs, reducing the
potential for unintended consequences resulting from conflicting
definitions. As noted above, the BABA Act definition focuses on
construction materials and components for infrastructure projects and
is closely aligned with the type of projects covered in this final
rule.
The final rule revises the term ``grant'' to reflect that solar or
wind energy leases are not covered under the definition. The change
provides clarity for where the BLM will issue a solar or wind energy
grant and where a solar or wind energy lease will be issued.
Commenters suggested the term ``lease'' is unnecessary and to use
``grants'' instead, as the difference between a lease and a grant under
the proposed rule is the location of a right-of-way either inside or
outside a DLA. As identified in the BLM's 2012 Western Solar Plan,
leases will be issued in areas designated for leasing under the
relevant land use plan. The BLM disagrees with these comments and
retains the distinction between solar and wind energy grants and leases
in this final rule based on location of their issuance. The BLM did not
make any change to this definition in the final rule.
This final rule adds the term ``Capacity fee'' to mean the fee
based on the amount of electricity produced from solar or wind energy
resources on the public lands. This is consistent with the BLM's change
implementing a capacity fee that is based on electricity production.
There were no substantive
[[Page 35643]]
comments on the term, and the BLM did not make changes to this
definition in the final rule.
The final rule revises the definition of the term ``Megawatt hour
(MWh) rate'' to mean the five-calendar-year average of the annual
weighted average wholesale prices per MWh for major trading hubs
serving the 11 western states of the continental United States. This
revision is consistent with the BLM's change to implement a capacity
fee for solar and wind energy development projects.
Some commenters were unclear whether the BLM had revised the
definition of ``Megawatt hour (MWh) rate'' in the existing regulations,
as Sec. 2801.5(b) currently does not define that term. Commenters
presumed that the BLM proposes to revise the existing definition of
``Megawatt rate.'' The BLM understands the confusion raised by these
comments. The BLM revises the term ``Megawatt rate'' to ``Megawatt hour
(MWh) rate'' in this final rule, consistent with the change to
implement a capacity fee for solar and wind energy development
projects. The BLM did not make any other changes to this definition in
the final rule.
This final rule revises the term ``Reasonable costs'' to be
consistent with the rule change replacing the words ``the Act'' with
the acronym ``FLPMA.'' There were no substantive comments on the term,
and the BLM did not make changes to this definition in the final rule.
``Renewable Energy Coordination Office (RECO)'' is added in this
final rule to mean one of the National, State, district, or field
offices established by the Secretary under 43 U.S.C. 3002(a) that is
responsible for implementing a program to improve Federal permitting
coordination with respect to eligible projects on covered land and such
other activities as the Secretary determines necessary. There were no
substantive comments on the term, and the BLM did not make changes to
this definition in the final rule.
This final rule includes the new term ``solar or wind energy
development'' to mean the use of public lands to generate electricity
from solar or wind energy resources on public lands. This definition
clarifies that the term ``energy development'' refers to uses of public
lands that directly involve the generation of electricity on public
lands. This definition clarifies which right-of-way grants and leases
are subject to the conditions in Section 50265(b)(1) of the IRA, which
apply to ``a right-of-way for wind or solar energy development on
Federal land.''
Commenters suggested revising the definition of ``solar or wind
energy development'' to include language from the BLM's recent
Instruction Memorandum 2023-036, Inflation Reduction Act Conditions for
Issuing Rights-of-Way for Solar or Wind Energy Development (April 23,
2023), according to which solar or wind energy development ``does not
include site-testing, communication sites, transmission lines, gen-tie
lines, pipelines, roads, installation of batteries and other energy
storage systems, or other uses that might indirectly support energy
production or transmission.'' The BLM does not agree that adding
additional language to the definition is necessary for this final rule.
This rule and the BLM's policies were written to complement each other
in how the BLM administers applications and rights-of-way for such
projects. The BLM did not make a change to this definition in the final
rule.
This final rule adds ``Solar and wind energy lease'' to mean any
right-of-way issued under Title V of FLPMA within an area identified in
a BLM land use plan as a DLA. Any right-of-way not issued within an
area identified as a DLA would be a grant. The BLM received comments on
this term, which are discussed with regard to the definition of
``grant'' in this final rule. The BLM did not make changes to this
definition in the final rule.
Section 2801.6 Scope
Section 2801.6 describes the scope of 43 CFR part 2800's
applicability. Paragraph (a)(1) of this final rule includes the
additional language ``or leases'' describing that this part applies to
both authorization types: grants and leases.
A comment requested the following language be added to Sec. 2801.6
Scope: ``Applications for transportation or utility right-of-way
crossing conservation system units, national recreation areas, or
national conservation areas in Alaska are subject to the provisions of
Title XI of the Alaska National Interest Lands Conservation Act and 43
CFR part 36.''
This rule focuses on the BLM's generally applicable process for
administering applications and rights-of-way for solar and wind energy
development projects on the public lands. It does not modify or amend
other applicable statutory or regulatory requirements, and the BLM
would comply with all such requirements during the process set forth in
this rule. The BLM made no changes to this section in the final rule
based upon public comments.
Section 2801.9 When do I need a grant or lease?
Section 2801.9 explains when a grant or lease is required for
systems or facilities located on public lands. Paragraph (d) of this
final rule extends the term for solar or wind energy development
authorizations up to 50 years, and authorizations for other uses that
support solar or wind energy development, to up to 50 years, and make
other technical changes. Paragraph (d)(3) provides that solar or wind
energy development facilities authorized with a grant or lease may be
issued for up to 50 years (plus initial partial year of issuance).
Paragraph (d)(4) provides that energy storage facilities that are
authorized separate from an energy generation facility are authorized
with a right-of-way grant for up to 50 years. Paragraph (d)(6) provides
that electric transmission lines with a capacity of 100 kV or more are
authorized with a right-of-way grant for up to 50 years. The BLM did
not make a change to this section of the final rule.
Commenters raised concerns with a 50-year authorization term for
large development projects because, they suggested, the longer the
public lands are occupied by a wind or solar project the longer it will
likely take for those lands to fully recover after removing the
project. Commenters also suggested that the longer-term authorization
may unreasonably occupy the public lands with a solar or wind energy
development when preferable or newer energy technology could be
deployed there.
The BLM disagrees with comments that assert the increase of the
maximum term of an authorization from 30 years to 50 years is
inappropriate because preferable technology may be desired at that
location in the future. The BLM acknowledges that recovery of impacts
might be greater for a 50-year right-of-way term. However, the BLM will
analyze the environmental impacts of each proposed project, including
the end of project life activities such as reclamation and restoration
of public lands, under NEPA, and will consider the appropriate term for
each proposed right-of-way, before deciding whether to approve for deny
a proposed right-of-way for energy development. Additionally, BLM notes
that most of the ground-disturbing impacts of solar or wind development
come during the construction phase, so the environmental effects of a
50-year authorization are therefore likely to be similar to the effects
of a 30-year authorization with respect to recovery. Any such impacts,
however, will be
[[Page 35644]]
considered on a case-by-case basis, in compliance with NEPA, when the
BLM evaluates each proposed project. Through this process, the BLM will
consider the reasonably foreseeable use of public lands, including the
technology proposed by an applicant and the environmental consequences
of that use, when deciding whether and for what duration to authorize
solar or wind energy development on the public lands.
Some commenters argued against increasing the maximum term length
for a right-of-way and expressed concerns about the economic and
environmental impacts and the lifespan of energy generation equipment.
Commenters suggested that a longer term to an authorization may not be
appropriate due to the shorter lifespans of solar panels and wind
turbines (30 years for solar and 20-25 years for wind), and that a
shorter initial term, like the current 30-year term, instead of 50
years may be more suitable.
The BLM understands the concerns raised by commenters regarding the
proposal to increase the maximum term length for solar and wind energy
development authorizations. In the BLM's experience, the lifespan of
solar and wind energy projects has been increasing over time as the
technologies advance. When the BLM last updated its rules for solar and
wind energy in 2016, the lifespan of a solar or wind project was
approximately 20 years. The 30-year term was appropriate for such a
length, considering the amount of time necessary to construct a project
and then the expected time to decommission and reclaim and restore the
public lands during the authorization term. With increasing lifespans
of solar and wind equipment, a longer-term right-of-way is appropriate.
See recent Berkeley National Laboratory, Results from a Survey of U.S.
Wind Industry Professionals,4 and the Department of
Energy's, Photovoltaics End-of-Life Action Plan,5 for a
discussion of wind and solar energy project lifespans.
---------------------------------------------------------------------------
\4\ https://emp.lbl.gov/publications/benchmarking-anticipated-wind-project.
\5\ https://www.energy.gov/sites/default/files/2022-03/Solar-Energy-Technologies-Office-PV-End-of-Life-Action-Plan_0.pdf.
---------------------------------------------------------------------------
However, the BLM has made changes to other parts of the rule to
address the commenters' concerns about dedicating public lands for up
to 50 years to certain projects or uses that, over time, may become
less efficient, see a significant decrease in production, or become
entirely inactive. These changes also address concerns about public
lands being used unlawfully for purposes other than those identified in
the ROW grant (e.g., a former solar or wind generating site being used
for equipment storage). In particular, the changes impose conditions
aimed at ensuring diligent operations on the public lands, see Sec.
2805.12(c)(8). These are in addition to the BLM's existing diligent
development requirements under Sec. 2805.12(c)(7).
Commenters suggested that the BLM evaluate changes to the
environment or technology during the term of an authorization after it
has been approved. The BLM did not adopt this suggestion. Once the BLM
issues a final decision, the BLM would only re-address technological
changes or environmental impacts during the term of an authorization if
the BLM undertakes a new decision-making process, such as in response
to a ROW holder's proposed change in technology. The BLM's original
analysis for a proposed facility considers the environmental effects of
the facility and technology proposed by the applicant for the term of
the proposed authorization, informing the BLM's decision to deny,
approve, or approve with modification the proposed project. Any
subsequent changes in equipment used at the site that would result in
changes to environmental impacts that may occur after the BLM issues
its decision, would be analyzed at the time the BLM considers issuing a
new decision, based on the relevant information available at that time.
The BLM may complete a new decision-making process to adjust the terms
and conditions of the authorization under existing Sec. 2805.15(e)
under certain circumstances, such as a change to legislation or
regulations, when necessary to protect public safety, an environmental
change (e.g., new threatened or endangered species listing), or if
proposed changes to technology may result in additional or different
environmental impacts.
One comment requested clarification on how Sec. 2801.9 may be
modified based on outcomes of the ongoing update to the Western Solar
Plan. The analysis of environmental impacts of energy development and
decisions made in updating the Western Solar Plan do not affect this
final rule, which that provides BLM procedures and requirements when
administering applications and authorizations for solar and wind energy
development projects.
Some comments suggested that proposed energy storage facilities and
proposed energy generation facilities should be reviewed in separate
NEPA documents due to differences in fire risk and toxicity concerns.
While it is beyond the scope of this rulemaking to speculate as to how
the BLM will comply with NEPA when evaluating individual projects, the
BLM agrees that energy storage facilities may have environmental
impacts that are distinct from those posed by energy generation
facilities. Nevertheless, the BLM can prepare a single NEPA document to
evaluate impacts from energy generation facilities and energy storage
facilities and may find it appropriate to do so in certain
circumstances.
Subpart 2802--Lands Available for FLPMA Grants or Leases
The BLM proposed to revise the title of subpart 2802 to include
``or leases'' to clarify for readers that public lands are available
for both grants and leases, consistent with other revisions in this
rule regarding leases. No comments were received on this, and the BLM
did not make changes to the final rule.
Section 2802.11 How does the BLM designate right-of-way corridors and
DLAs?
Section 2802.11 explains how the BLM designates right-of-way
corridors and DLAs through its land use planning process. This section
includes a non-exhaustive list of factors the BLM could consider when
designating such areas under its land use planning process described in
43 CFR part 1600. Other technical changes in Sec. 2802.11(b) improve
readability and consistency between the BLM's regulatory authority
under part 2800 and its statutory authority under FLPMA. The BLM did
make changes to this section of the final rule.
Paragraph (b)(1) is unchanged from the proposed rule and includes
Tribal land use plans that BLM reviews for consistency when it is
developing, amending, or revising a land use plan in accordance with
Section 202(c)(9) of FLPMA (43 U.S.C. 1712(c)(9)).
Paragraphs (b)(10) and (b)(11) add criteria that the BLM may
consider when designating new leasing areas for solar and wind energy.
Paragraph (b)(10) adds ``access to electric transmission,'' and
paragraph (b)(11) provides for consideration of relatively large areas
where energy development is feasible and there is a low potential for
conflict due to environmental, cultural, and other relevant criteria,
including assessing the demand for new or expanded areas; applying
environmental, cultural, and other screening criteria; and analyzing
proposed areas through the land use planning process described in part
1600.
The BLM received comments about whether the BLM's proposal to carry
forward three of the four criteria from
[[Page 35645]]
the 2012 Western Solar Plan is consistent with other BLM planning
actions. The BLM carried these three criteria forward from the 2012
Western Solar Plan, which is consistent with other BLM plans
identifying solar and wind energy development areas.
Some commenters suggested that the BLM redesignate proposed
paragraph (b)(11) as paragraph (b) and redesignate existing paragraphs
(b)-(d) as newly designated paragraphs (c)-(e). The BLM did not change
the rule due to this comment. Reorganizing the paragraphs as suggested
would be confusing to a reader as considerations for solar energy would
no longer be located together in one subparagraph. The BLM did revise
paragraph (b)(11) to clarify that the factors BLM considers include
``whether there are areas'' consistent with revisions under paragraph
(b).
One comment requested that wording be amended to ``clarify that BLM
may require sharing a gen-tie right of way subject to reasonable
terms.'' The term ``gen-tie'' refers to a generation interconnect
transmission line that connects the original source electric generation
(for the purposes of this rule, a wind or solar energy development) to
the transmission system. These gen-tie lines are typically less than 5
miles long and require a right-of-way grant if they cross public lands.
The BLM retains authority under 43 CFR 2805.15(b) to allow or not allow
such common use of the right-of-way.
Commenters suggested that the BLM alter the language of proposed
Sec. 2802.11(b), which identifies factors or criteria that the BLM may
consider when designating an area of public land as a right-of-way
corridor or a DLA. Some commenters recommended replacing the proposed
term ``may'' with ``must.'' Other commenters suggested expressly
incorporating all of the considerations listed in 43 U.S.C. 1712(c),
which governs criteria for consideration by BLM when it prepares land
use plans, to this section. Other commenters suggested that the BLM add
transmission and electric infrastructure to the list of criteria or
factors. Finally, some commenters agreed with the language in the
proposed rule, which provides a non-exclusive list of factors or
criteria that the BLM may consider when designating a corridor or a
DLA.
After considering comments on this section, the BLM did make some
changes to this paragraph in the final rule. While Sec. 2802.11(b)
provides examples of criteria that the BLM may consider, some of the
listed criteria might not be relevant in all cases, and the BLM may
consider additional factors or criteria as appropriate. Further, the
BLM's land use planning regulations, 43 CFR 1600, provide additional
direction for complying with the requirements of Section 202 of FLPMA,
43 U.S.C. 1712. The BLM did not add transmission and electric
infrastructure to the list of criteria or factors because the proposed
rule already included ``access to electric transmission,'' which is
retained as a criterion or factor in the final rule. However, the BLM
revised paragraph (b) to replace ``factors the BLM may consider
include, but are not limited to, the following'' to read as ``the BLM
may consider various factors, including'' to clarify what the BLM
considers when designating such areas.
Commenters suggested that adding three criteria to a list of other
criteria for the BLM to consider may create confusion. Some commenters
supported the BLM adding paragraphs (b)(10) and (b)(11) to provide more
detail of what and how the BLM considers when designating new leasing
areas. Other commenters requested the BLM evaluate criteria for
designating exclusion areas in addition to the criteria for designating
DLAs and right-of-way corridors. The BLM believes that adding the three
additional criteria for consideration when designated corridors and
leasing areas is appropriate and provides for transparency when the BLM
begins its land use planning processes to designate leasing areas. The
BLM does not agree that exclusion criteria are appropriate when
identifying DLAs. However, paragraph (d) of the existing regulations
provides broad discretion for the BLM to identify areas where the BLM
will not allow rights-of-way, which may include criteria to identify
exclusion areas during the land use planning process. During the land
use planning process, the BLM engages Federal, Tribal, State, and local
government partners and the public to inform and clarify the factors
analyzed when considering whether to designate exclusion areas.
Including these criteria in the final rule will minimize the confusion
that may arise in the future.
Some comments requested that the final rule include additional
criteria for designating exclusion and avoidance or variance areas.
Commenters suggested that including these criteria would encourage the
appropriate designation of such areas and thus focus on processing
right-of-way applications only in areas where development is best
suited. The BLM disagrees with commenters that additional criteria for
designating exclusion and avoidance or variance areas should be
included in the final rule. Such criteria do not need to be included in
the final rule and are better suited for policy (e.g., instruction
memoranda), which can be implemented consistent with this rule and
other applicable regulatory authority and environmental analysis, while
also providing appropriate flexibility in the process. Further,
exclusion criteria are based on the environmental impacts of a program
on the public lands, which are identified through a NEPA analysis, such
as the ongoing Western Solar PEIS that is updating the 2012 Western
Solar Plan. Lastly, this final rule updates its prioritization
principles under 2804.35, which were not in place in 2012 with the
Western Solar Plan. The BLM believes that with the robust public
engagement, prioritization principles, and other preliminary
application review meetings, holding a variance process is not
necessary in administering applications for solar and wind energy
development.
Section 2803.10 Who may hold a grant or lease?
Section 2803.10 provides the criteria for who may hold a grant or
lease. In this final rule, the BLM clarifies that a holder who is of
legal age and authorized to do business in one State must also meet
this requirement in each other State in which the right-of-way grant
they seek is located. No comments were received on this section, and
the BLM did not make changes to this section of the final rule.
Section 2803.12 What happens to my grant if I die?
In the notice of proposed rulemaking for this rule, the BLM
proposed to add new paragraph (a) and redesignate existing paragraphs
(a) and (b) as paragraphs (b) and (c). This final rule does not carry
forward those proposed revisions because another final rule included
revisions that addressed those concerns. The BLM's final rule ``Update
of the Communications Uses Program, Cost Recovery Fee Schedules, and
Section 512 of FLPMA for Rights-of-Way,'' (89 FR 25922) [April 12,
2024] updated Sec. 2803.12 to remove reference to applications in the
section title and paragraph (a).
This final rule retitles this section and revises paragraphs (a)
and (b) to include ``or lease'' clarifying that this section applies to
both grants and leases.
Paragraph (b) of this final rule replaces the word ``distributee''
with ``receiver'' to improve clarity to readers that when the BLM
distributes a grant or lease, the instrument would be received by the
holder. This final rule also includes the provision that unqualified
receivers of a right-of-way
[[Page 35646]]
must comply with all terms, conditions, and stipulations.
One comment suggested that the BLM clarify paragraph (b) to state
that distribution will take place under state law in the state where
the grant or lease is located. Including this suggested change could be
inaccurate and potentially unenforceable. The BLM's rules should not
dictate distribution of a lease as an inheritable interest in all
instances.
Section 2804.12 What must I do when submitting my application?
Section 2804.12 explains what an applicant must do when submitting
a right-of-way application. The BLM proposed changes to paragraphs (c)
and proposed to add paragraphs (f) and (j). The BLM did make a change
to this section of the final rule.
Paragraph (c) provides for additional requirements for solar and
wind energy development or short-term rights-of-way. Paragraph (c)(1)
requires payment of an application filing fee for solar and wind energy
development and short-term applications as an initial payment toward
cost recovery payments. The BLM will refund the balance of the
application filing fee if it exceeds the processing costs. Paragraph
(c)(1) is revised for readability and now reads ``payment toward cost
recovery'' instead of ``payment towards cost recovery.'' Paragraph
(c)(2) requires payment of additional reasonable costs in addition to
application filing fees. See existing Sec. 2804.14 of this part for
further information on reasonable costs in processing an application.
Payment of category 6 cost recovery fees--which are based on full costs
and are collected if the BLM has determined that processing efforts
will take more than 64 hours to complete--may be reduced by the
application filing fee that is paid when submitting an application.
Some comments requested lower fees for application submittal.
Another comment suggested that the BLM keep the application fee until
all ``reasonable costs'' are paid before any refund is given. Under the
existing regulations, application filing fees are a payment of
reasonable costs for the United States to process an application and
are intended to discourage applicants from unnecessarily applying for
more land than is reasonable for a solar or wind energy development. As
updated by this final rule, these application filing fees continue to
be a payment of reasonable costs and may now clearly be applied to the
processing fees, such as through a cost recovery agreement. Any
overpayment of these costs may be reimbursed to the applicant or
carried to cover the inspection and monitoring of the right-of-way, if
authorized. Entering into a cost recovery agreement requires action by
the BLM and applicant to complete, including the prioritization of an
application under Sec. 2804.35 by the BLM and payment of reasonable
costs identified by the BLM in a cost recovery agreement.
Multiple comments suggested the BLM issue a cost recovery agreement
within a certain timeframe, such as 30 days of receiving the required
information. The BLM agrees that it is important for the BLM to be
responsive to applicants who have provided the required information
under this section. The proposed rule added paragraph (j) providing
that an application is complete when an applicant submits the required
information under this section. Upon receiving a complete application,
the BLM would determine what cost recovery amounts would be necessary,
and whether that should be under a cost recovery agreement. See Sec.
2804.14 for further information. The BLM would notify an applicant
within 30 days pursuant to Sec. 2804.25(d) whether processing their
application will take longer than 60 calendar days and what the
expected processing timeframe is for the application. Section 2804.19
of the BLM's right-of-way regulations provides that the BLM and
applicant work together to establish and issue the cost recovery
agreement; the length of that process can vary widely based on a number
of variables including project complexity, analysis of the needs from a
cost recovery agreement, and needed inputs from the developer. As noted
under the previous comment response, entering into a cost recovery
agreement requires action by the BLM and applicant to complete,
including prioritization under Sec. 2804.35 by the BLM and payment of
reasonable costs identified by the BLM in a cost recovery agreement.
Section 2804.12(f) of this final rule clarifies that the BLM may
require additional information at any time while processing an
application. Additional information may be necessary, such as
environmental resource data. The BLM will issue a deficiency notice
pursuant to existing Sec. 2804.25(c) to inform applicants of
additional information requirements.
Comments requested that the BLM provide clear application
requirements and limit the BLM's ability to request additional
information beyond those requirements. The BLM believes that the
existing rules clearly state what is required for applications under
2804.10, What Should I do before I file my application?; in Sec.
2804.11, Where do I file my grant application?; and as updated by this
final rule, Sec. 2804.12, What must I do when submitting my
application? Paragraph (f) of this final rule provides that BLM may
request additional information while processing an application.
Additional information may be requested under 2804.25(c) after an
application is determined to be complete pursuant to added paragraph
(j) of this final rule.
Paragraph (j) describes that a complete application meets or
addresses the requirements of Sec. 2804.12, as appropriate for the
application submitted. Some comments asked the BLM to clarify the
definition of ``complete application'' in paragraph (j). The BLM
believes that new paragraph (j) clearly describes what a complete
application is. Upon satisfying the requirements of this section, the
BLM will provide the applicant notice in writing that the application
is complete.
Some commenters suggested that the BLM provide a determination of
application completeness within specified timeframes to promote a
timelier application process. The BLM agrees that it is important to
remain diligent in processing an application. However, the BLM did not
propose to implement any timeframes for determining an application is
complete as this section of the rules applies to applications for all
rights-of-way, not just solar or wind energy applications. Reasonable
expectations for timely and diligent application requirements will vary
depending on the complexity of processing a certain type of system or
use on the public lands.
Section 2804.14 What is the processing fee for a grant application?
The BLM recently published its final rule ``Update of the
Communications Uses Program, Cost Recovery Fee Schedules, and Section
512 of FLPMA for Rights-of-Way'' (89 FR 25922) [April 12, 2024]. In
that final rule, the BLM updated its address within this section. The
proposed updates that the BLM included in this rulemaking are no longer
necessary. No comments were received, and the BLM did not make a change
to this section in this final rule.
Section 2804.22 How will the availability of funds affect the timing of
the BLM's processing?
Section 2804.22 of this final rule clarifies how the availability
of funds may affect the BLM's schedule for processing an application.
Paragraph (a) clarifies that when the BLM is processing an application,
it will not continue to process the application until funds become
available or the applicant
[[Page 35647]]
elects to pay full actual costs under Sec. 2804.14(f). Paragraph (b)
provides that the BLM may deny an application after 90 days if it has
requested reasonable costs for processing an application and the
proponent has failed to provide funds for reimbursement. The BLM did
not change this section of the final rule.
One commenter supported denying applications for which fees had not
been paid. Such a procedure, the commenter suggested, would
disincentivize applicants from submitting applications that they do not
intend to diligently process. While the BLM will not deny an
application without cause, as described in more detail under Sec.
2804.26, the BLM agrees that failure to diligently pursue an
application, including unfunded application cost recovery agreements,
and incomplete applications, among other reasons are good cause for
denying an application. Denying applications for these reasons would
deter applicants from submitting applications for projects that they do
not intend to diligently pursue. Paragraph (c) of this final rule
provides that funds paid towards the cost recovery agreement for a
project may not be refundable. Such funds would be those identified in
the cost recovery agreement for hiring additional staff or contractors
and agreed to by the applicant or right-of-way holder.
Some comments supported the idea of cost recovery agreements that
would allow the BLM to hire additional staff or contractors to aid in
application processing and reduce processing times. This requirement
helps ensure that there is available funding to the United States for
reasonable costs of the government, including those BLM hiring and
contracting decisions made to support processing applications.
Section 2804.23 What costs am I responsible for when the BLM decides to
use a competitive process for my application?
Section 2804.23 of the final rule describes what costs an applicant
is responsible for when the BLM decides to use a competitive process.
Paragraph (b) requires, for cost recovery processing categories one
through four, payment of cost recovery processing fees as if the other
applications had not been filed. Paragraph (c) clarifies who is
responsible for processing costs within processing category six.
The BLM did not make a change to this section of the final rule.
One comment suggested the language be changed to read, ``What costs
am I responsible for if the BLM decides to use a competitive process
for my application?'' The BLM considered this change in title to the
section and believes that the proposed naming of this section is clear
with respect to what costs the applicant will be responsible for when
the BLM determines it will use a competitive process.
Section 2804.25 How will the BLM process my application?
In the final rule, the BLM revised Sec. 2804.25(c) to add that, if
an applicant fails to comply with a deficiency notice under this
section, the BLM may deny the application. To ensure that developers
proceed diligently after entering into a cost recovery agreement, Sec.
2804.25(c)(1) requires applicants to ``commence any required resource
surveys or inventories within one year of the request date, unless
otherwise specified by the BLM.'' If the applicant fails to comply with
a deficiency notice under that provision, the BLM may deny the
application. See Sec. 2804.26(a)(9). To clarify that the BLM retains
the discretion to deny an application where the applicant does not
proceed diligently, the final rule adds to Sec. 2804.25(c): ``Failure
to meet requirements under this section may result in the BLM denying
your application pursuant to Sec. 2804.26.''
This added provision clarifies that the BLM retains the discretion
to deny an application where the applicant does not proceed diligently.
This change is consistent with changes made to Sec. 2809.10(e)
regarding when the BLM will no longer hold a competitive process.
Together these amendments give the industry the certainty it needs to
proceed with projects while retaining the BLM's discretion to deny an
application or offer lands competitively if the applicant does not
proceed diligently. In that way, these amendments balance the BLM's
obligations to incentivize renewable energy development on public lands
and to recover a fair return for U.S. taxpayers.
In this section, the BLM proposed removing a mandatory public
meeting that is unique to solar and wind energy rights-of-way
applications and is in addition to other public participation that
would occur as part of the BLM's environmental review process.
Paragraph (e)(2) describes public meeting requirements for solar or
wind energy right-of-way applications. In the final rule, paragraph
(e)(2) provides that the BLM may hold a local public meeting if there
is no other public meeting or opportunity for early engagement. In
other words, the final rule would require the BLM to hold a public
meeting, offering the public opportunity to engage early, though the
BLM could satisfy this requirement by holding a public scoping meeting
or other public meeting that facilitates early engagement by the
public.
Commenters suggested that the BLM provide a website of applications
and authorizations for interested parties so that they could receive
up-to-date information on the applications and authorized projects. The
BLM agrees with comments about maintaining a site that is accessible to
the public on existing and proposed (i.e., applications for) projects
on public lands. The BLM currently maintains an active web page at
https://www.blm.gov/programs/energy-and-minerals/renewable-energy/active-renewable-projects where the public may access the most recent
information on applications for solar, wind, and geothermal development
projects, gen-tie-lines, upcoming lease sales, and other relevant
application and development information about these sites.
Some comments supported the removal of the requirement that BLM
hold pre-processing public meetings, noting that solar and wind energy
technologies are better known now than they have been previously and
that these meetings are unnecessary. The BLM also received comments
that did not support removing that requirement. These comments
expressed concerns that by removing this public meeting the BLM would
be excluding the public and should instead increase outreach to the
public in the area affected by these proposed development projects. To
address these concerns, the BLM has changed the regulatory text in
paragraph (e)(2)(i) to ensure that a public meeting is held if there is
no other opportunity for the public's early engagement. The BLM also
would retain discretion to hold additional public meetings under Sec.
2804.25(e).
Paragraph (e)(4) is updated to replace ``the National Environmental
Policy Act (NEPA)'' with ``NEPA,'' consistent with the changes in
paragraph (e)(2) of this section. The BLM updates the reference in this
final rule, consistent with changes that CEQ has made to its
regulations, such that 40 CFR parts 1501 through 1508 are now referred
to as 40 CFR Chapter V, Subchapter A.
Paragraph (e)(5) provides that the BLM will determine whether the
proposed use complies with applicable Federal laws.
Paragraph (f) addresses the segregation of lands within a right-of-
way application. Paragraph (f)(3) now provides that a segregation may
be extended when an application is complete and cost recovery has been
received.
[[Page 35648]]
Some comments suggested that the 2-year segregation limit is
appropriate, that the BLM should begin NEPA within 2 years of
segregating the lands, and that such limitations should be consistent
with the NEPA timeline requirements within the Fiscal Responsibility
Act. The BLM agrees that the agency should be diligent in processing
applications, including initiating NEPA. Because separate legal
authority and policy guidance applies to NEPA compliance procedures,
including applicable timelines to complete the NEPA process, the BLM
did not make a change to this paragraph of the final rule in response
to these comments.
Some comments suggested additional language should be added to
establish timelines and deadlines supporting quick action in processing
applications. Section 2804.25(c) in the existing regulations provides
specific due diligence requirements for applications. Unless another
timeline is specified by the BLM, applicants have one year to complete
certain actions, and the BLM may deny an application for failure to
comply with the one-year requirement or other specified timeframe for
submitting necessary information to the BLM. The BLM believes this
timeline is generally adequate to promote the timely processing of
applications and permitting of solar and wind development projects and
to ensure that developers cannot hold public lands by submitting, but
not diligently pursuing, an application, thus precluding other uses of
such lands. The BLM did not change the final rule in response to these
comments.
The BLM received requests to revise the rule to require automatic
segregation once an applicant has filed a complete application and has
paid the required application fees and grant extensions past the four-
year mark. Changing the method to segregate lands and the timeframes of
those segregations is outside the scope of this rule. The BLM did not
propose to change the method and timing of segregation, but only to
make this paragraph consistent with new provisions in the final rule
for complete applications and cost recovery.
Section 2804.26 Under what circumstances may the BLM deny my
application?
Section 2804.26 of this final rule explains the circumstances under
which the BLM may deny an application.
Paragraph (a)(4), consistent with this final rule replacing the
term ``the Act'' with ``FLPMA'' discussed under Sec. 2801.5, provides
that the BLM may deny your application if issuing the grant would be
inconsistent with applicable law or regulation.
The BLM did not carry forward paragraph (a)(9) of the proposed rule
because the BLM's final rule, ``Update of the Communications Uses
Program, Cost Recovery Fee Schedules, and Section 512 of FLPMA for
Rights-of-Way,'' 89 FR 25922 (April 12, 2024) revised the BLM
regulations at Sec. 2804.26(a) to add the same provision allowing the
BLM to deny applications that fail to comply with a deficiency notice .
Thus, the revision in the proposed rule that would have added this
provision is no longer necessary.
Paragraph (10) incorporate requirements of this final rule that are
discussed elsewhere. Paragraph (a)(10) provides that an application may
be denied for failing to pay costs, as noted in Sec. 2804.22(b).
As proposed, paragraph (c) is removed in this final rule. Any
request for an alternative requirement received after an application
has been denied is not a timely request. Requests for an alternative
requirement must be timely. See Sec. 2804.40(c) for further
information on timely requests.
The BLM received a comment recommending that the BLM add another
provision following section (a)(4), suggesting that this new provision
address protection of special conservation areas managed by the BLM or
other federal or state agencies. The BLM believes that including the
suggested change to this section is unnecessary. The BLM's process to
deny an application under this section is addressed in the existing
regulations at Sec. 2804.26. The BLM's management of special
conservation and other sensitive areas is generally determined through
the BLM's resource management planning and NEPA processes. The BLM
retains broad authority to deny an application on the basis that it
would not be in the public interest, which may also address this
concern to deny certain applications.
Section 2804.30 [Removed and Reserved]
Section 2804.30 is removed and reserved in this final rule. No
comments were received on this section and the BLM did not make any
changes to this section in the final rule. Prior Sec. 2804.30
addressed competitive leasing inside of designated areas. The content
of the prior Sec. 2804.30 is now duplicative of this final rule in
Sec. Sec. 2809.13, 2809.14, and 2809.17.
Section 2804.31 [Removed and Reserved]
Section 2804.31 is removed and reserved in this final rule. Prior
Sec. 2804.31 addressed competitive process for site testing. This
portion of the rule was not used since first put in place in 2016 and
is removed. The BLM may still hold competitive processes for site
testing if there is a competitive interest or other reasons as
identified in Sec. 2809.10 of this final rule.
Some comments supported the removal of competitive processes for
site testing grants, and other commenters suggested that the section
may be useful in local field office decision making in the future. The
BLM agrees that retaining requirements for competitive processes
related to solar and wind energy is important. Subpart 2809 of this
final rule provides the requirements for solar and wind energy
competitive processes, which includes the requirements of this section.
Section 2804.35 Application Prioritization for Solar and Wind Energy
Development Rights-of-Way
Section 2804.35 is retitled to ``Application prioritization for
solar and wind energy development rights-of-way.'' This section
provides for the relative importance of different criteria that vary
from location to location, giving weight to local resource issues and
circumstances that are not equally relevant for every application.
Additionally, there are practical concerns for the BLM when processing
solar and wind energy applications. This section provides that the
relevant criteria are to be applied holistically to prioritize
applications in a manner that would facilitate environmentally
responsible projects and ensure that agency workloads are allocated
appropriately. The revised section would also explicitly recognize that
the BLM may identify additional criteria in guidance, which may be
national in scope or specific to an area.
Paragraph (a) clarifies that the purpose of prioritizing
applications is to allocate agency resources to processing applications
that have the greatest potential for approval and implementation. The
BLM revised this section from the proposed rule to clarify that the
BLM's prioritization of an application is not a decision and is not
subject to appeal under 43 CFR part 4.
One commenter asked whether the BLM's prioritization process might
hinder development of renewable energy and potentially conflict with
national priorities for renewable energy deployment. The BLM is
endeavoring to
[[Page 35649]]
increase the responsible deployment of renewable energy on the public
lands consistent with congressional and presidential direction. In
addition, the BLM must continue to manage public lands under the
principles of multiple use and sustained yield unless otherwise
provided by law (43 U.S.C. 1732(a)). The prioritization criteria
support national renewable energy goals by helping the BLM to consider
applications for the projects that are most likely to succeed and
ensure the BLM's continued stewardship of the public lands.
Paragraph (b) identifies criteria that the BLM may consider when
prioritizing applications. This section provides discretion to the BLM
as to how best to apply the criteria to prioritize processing solar or
wind energy generation applications.
Some comments suggested prioritizing applications for projects
inside DLAs. Other comments suggested other criteria that should be
considered when prioritizing applications, such as the presence of
existing leasing agreements and rights-of-way, whether the application
complies with all state and federal regulations, the size or location
of the project, project features, proximity to transmission, and
protection of natural resources.
The BLM believes that these considerations are important, but no
changes to the regulatory text are warranted since these considerations
were already included in the proposed rule. The six listed criteria in
the rule provide flexibility in how the BLM may apply the criteria for
applications in the BLM's varied landscapes on which a resource may
have different sensitivities in one location as compared to another
location. Prioritizing projects based on siting in designated or
preferred areas is addressed in paragraph (b)(1). The BLM addressed
comments concerning existing leasing agreements or rights-of-way in the
BLM's application processing steps in subpart 2804 of these rules.
Paragraph (b)(4) addresses commenter suggestions regarding prioritizing
applications based on compliance with federal regulation. Paragraphs
(b)(2) and (b)(5) address the size or location, project features,
proximity to electric transmission, and the protection of natural
resources.
Several comments requested clarity on the application of the
prioritization criteria, including a description of the relative
importance of each criterion. Other commenters also suggested that they
believe the BLM should be prohibited from prioritizing applications
based on additional criteria that are not expressly listed in this
section of the rule. In the BLM's experience, the relative importance
of different criteria may vary from location to location due to
resource considerations. Likewise, not all prioritization criteria are
equally relevant for every application. The BLM has intentionally not
set specific preferences or weights for the criteria it will apply when
prioritizing applications. This final rule confirms that the BLM will
consider the prioritization criteria holistically when considering
applications, and that the BLM may establish additional criteria
through local or national policy guidance.
In the final rule, the BLM changed paragraph (b) to refer to
``criteria'' instead of ``factors'' as proposed. This change is
consistent with the BLM's use of the term ``criteria'' in paragraph
(b)(6).
The first criterion is whether the proposed project is located
within an area preferred for such development, such as a DLA. The BLM
may reasonably presume that development projects proposed within these
areas are more likely to proceed to approval as they pose less severe
resource conflicts than other lands.
Some comments suggested that wind energy is disadvantaged since
there are no wind energy designated leasing areas or equivalents. The
BLM disagrees with these comments. First, the 2016 Desert Renewable
Energy Conservation Plan (https://blmsolar.anl.gov/documents/drecp/)
designated more than 192,000 acres of preferred development locations
for solar, wind, and geothermal energy. Additionally, the criteria are
not given specific preferences or weights when compared with one
another, and, as such, the BLM would take into account the lack of wind
DLAs when prioritizing wind energy development applications.
The second criterion is whether the proposed development avoids
adverse impacts to or conflicts with known resources or uses on or
adjacent to public lands and includes specific measures designed to
further mitigate impacts or conflicts. When submitting an application
to the BLM, the applicant must address known potential adverse resource
conflicts, including those for sensitive resources and values that are
the basis for special designations and protections, as well as
potential conflicts with existing uses on or adjacent to the proposed
energy generation facility. Under section 2804.12(b)(2), the applicant
must also include specific measures to mitigate impacts or conflicts
with resources and uses. Including this information is necessary for
the BLM to determine that an application is complete. While subsequent
consultation, public comment, and environmental review processes may
reveal unknown resource or use conflicts, based on previous experience
permitting wind and solar projects on public land, the BLM understands
that projects with fewer known conflicts are more likely to proceed to
approval and successful implementation.
The third criterion is whether the proposed project is in
conformance with the governing BLM land use plans. Applications
identify whether the proposed project is in conformance with the
governing land use plan or would require an amendment or revision to
the plan. The BLM may, in its discretion, consider applications for
solar or wind energy generation facilities that would require an
amendment or a revision to the governing land use plan under part 1600
of these regulations. However, such application could require greater
resources to process and could present resource conflicts, which would
result in a lower priority.
The fourth criterion is whether the proposed project is consistent
with relevant State, local, and Tribal government laws, plans, or
priorities. The purpose of this determination is not to enforce these
State, local, or Tribal laws, plans, or priorities, but rather to
promote comity and identify projects that are more likely to be
successfully approved. In addition, applying this principle helps to
ensure that the BLM takes into account the existing resource knowledge
and expertise that may be available through State, local, and Tribal
plans and priorities. To carry out this prioritization, the BLM may
enter into or rely on existing agreements with State, local, or Tribal
governments.
Some comments suggested that prioritization of an application
should be subject to Tribal consultation. The BLM engages Federally
recognized Tribes early in the application process under Sec.
2804.12(b)(4), which allows Tribes to participate in preliminary
application review meetings with the BLM and provide early information
to the BLM about an application. Additionally, under paragraph (b)(4),
the BLM will consider ``whether the proposed project is consistent with
relevant State, Tribal, and local government laws, plans, or
priorities,'' which may also include consultation with Tribes. Finally,
the BLM acknowledges that E.O. 13175 sets forth criteria for when the
BLM is required to consult with Tribes, and the BLM is committed to
consulting with Tribes whenever such consultation is required
[[Page 35650]]
under the E.O., without regard to whether that requirement is
specifically articulated in this rule.
The fifth criterion is whether the proposed project incorporates
the best management practices set forth in the applicable BLM land use
plans and other BLM plans and policies. This principle ensures that the
BLM takes into account the knowledge and expertise that has gone into
formulating these existing plans and policies. Should an application
require amending a BLM land use or other plan, it is likely to require
more time and effort to process.
The sixth criterion considers any other circumstances or
prioritization criteria identified by the BLM in subsequent policy
guidance or land use planning for an area.
Paragraph (c) provides that the BLM will prioritize applications,
once complete (as described in Sec. 2804.12(j) of this part). The
BLM's prioritization may use any available information provided in the
application or its Plan of Development, applicant responses to
deficiency notices, and information provided to the BLM in public
meetings or by other Federal agencies and State, local, or Tribal
governments.
Paragraph (d) clarifies the BLM discretion to re-categorize an
application's priority at any time. Re-categorizing an application may
be based on new information that the BLM has received or on changes the
applicant has made to the application. Re-categorizing an application
may also be based on the BLM's need to adjust its workload, if
circumstances warrant such re-prioritization.
Some comments expressed concern that denying or de-prioritizing an
application prior to any final land use designation, such as those
which may be made in the ongoing update to the 2012 Western Solar Plan,
is inappropriate or pre-decisional. Comments further expressed that
pending applications should not be denied before land use designations
are made. The BLM is not constrained by ongoing or potential future
land use planning processes, but it must manage public lands in
conformance with the land use plans currently in effect. Accordingly,
the BLM generally will not deny or deprioritize an application based on
non-conformance with a future or ongoing land use planning effort. The
criteria in the rule refer to consideration of governing land use
plans. The BLM would deny or de-prioritize an application pursuant to
its broad discretion in considering right-of-way applications based on
existing information and existing land use plans. At the same time, the
BLM retains authority to deny an application based on appropriate
information even if the project would conform to the applicable land
use plan, including, for example, where an application conflicts with
current management policies that have not yet been incorporated into a
land use plan.
Some comments suggested that the BLM should adopt a first-come,
first-served system when processing applications or self-prioritization
by an applicant for multiple applications within a single BLM field
office. While in practice the BLM often processes applications on a
first-come, first-served basis, it retains discretion to prioritize
applications according to other considerations including input from an
applicant about their applications. In practice, the BLM has observed
that the prioritization of projects, particularly in Field and District
Offices with high workloads, provides a number of benefits for the BLM
and applicants. In coordinating with applicants, the BLM discusses
workload capacities and will receive input from developers on the
priority of their applications and whether there is a specific
preferred order. Due to the many factors the BLM considers in this
decision, however, the BLM's determination on a project's priority for
processing may be different than that requested by a particular
developer. Targeting workloads for BLM staff and management facilitates
accelerated decision-making for those solar and wind energy development
proposals with the greatest technical and financial feasibility and the
least anticipated natural and cultural resource conflicts and increases
consistency in processing project applications for the BLM and
applicant. As detailed in the discussion of subpart 2809 in this rule,
the BLM may also determine that there is a competitive interest for a
right-of-way or system and hold a competitive process.
Section 2804.40 Alternative Requirements
Section 2804.40 of this final rule provides for situations when an
applicant requests alternative requirements from the BLM if the
requestor is unable to meet the requirements of this subpart. The final
rule clarifies that this section applies specifically to the BLM's
consideration of alternatives to the application requirements set forth
in subpart 2804. Other requirements related to rights-of-way, such as
the requirement to pay rent as set forth in subpart 2806, cannot be
adjusted under this section. The BLM did not make a change to this
section of the final rule.
Some commenters suggested that state and local governments should
be brought into the decision-making process if an applicant is unable
to meet the application requirements and they request an alternative to
one or more application requirements. It is the BLM's responsibility to
determine whether an alternative requirement for the application
process should be allowed. Through agreements, including with
cooperating agencies, the BLM engages with Tribal, Federal, State, and
local government offices when it considers solar and wind energy
development projects. The BLM would inform such partners of any changes
to its requirements. Additionally, the BLM will consider under this
section only requests for alternatives to modify the alternative
requirements found in part 2804--Applying for FLPMA Grants. Requests to
modify other requirements, including those identified in a decision
authorizing a right-of-way, such as terms and conditions, cannot be
approved under this section. This would include requests for
alternative access.
Section 2805.10 How will I know whether the BLM has approved or denied
my application or if my bid for a solar or wind energy development
grant or lease is successful or unsuccessful?
Section 2805.10 of this final rule clarifies that agency decisions
about whether to approve rights-of-way are generally administratively
appealable while the issuance of a right-of-way grant or lease itself
is not an opportunity for appeal.
Paragraph (c) of this final rule clarifies that ``The BLM will
issue the right-of-way by signing the grant or lease and transmitting
it to you.'' The BLM's act of returning the signed instrument to the
holder constitutes the ``issuance'' of the right-of-way. Identifying
the point in time at which the right-of-way is ``issued'' is important
for calculating when the term of a right-of-way begins to run (see
Sec. 2805.11) and when the holder's obligation to pay rent begins (see
Sec. 2806.12). Identifying the point at which the right-of-way is
``issued'' is also important for clarifying which actions are subject
to the conditions in Section 50265(b)(1) of the IRA, which imposes
conditions on when the Secretary may ``issue a right-of-way for wind or
solar energy development on Federal land.'' The BLM did not make a
change to this section of the final rule.
[[Page 35651]]
Section 2805.11 What does a grant or lease contain?
Section 2805.11 of this final rule revises the right-of-way
authorization term length for certain facilities, and the final rule
includes minor updates to the proposed rule to improve technical
clarity. No change was made in this section of the final rule due to
public comment.
The BLM's final rule ``Update of the Communications Uses Program,
Cost Recovery Fee Schedules, and Section 512 of FLPMA for Rights-of-
Way,'' 89 FR 25922 (April 12, 2024), updated Sec. 2805.11 to
redesignate paragraph (b) to paragraph (c). Proposed revisions from
this rule under Sec. 2805.11(b) are now finalized under 2805.11(c)
consistent with the redesignation of this paragraph.
Redesignated Sec. 2805.11(c) addresses the duration of rights-of-
way. Section 2805.11(c)(2) provides specific terms for solar and wind
energy grants and leases. Paragraphs (c)(2)(iv), (c)(2)(v), and (c)(4)
now show the maximum terms for solar and wind energy generation
facilities, energy storage facilities that are separate from energy
generation facilities, and electric transmission lines with a capacity
of 100 kV or more. The term for a grant or lease for these types of
authorizations may be up to 50 years. Revisions under this section are
consistent with those made under Sec. 2801.9(d).
Paragraph (c)(2)(iv) is updated for the maximum term for both
grants and leases, for up to 50 years (plus initial partial year of
issuance).
Paragraph (c)(2)(v) is updated for the maximum term for rights-of-
way for energy storage facilities that are separate from energy
generation facilities. Although the BLM generally treats energy storage
facilities as linear rights-of-way, rather than solar or wind energy
development rights-of-way, for purposes such as rent calculation, the
BLM believes that the longer term of ``up to 50 years,'' commensurate
with the maximum term for solar or wind energy development rights-of-
way, will facilitate the transition to cleaner sources of energy in the
United States.
Paragraph (c)(4) would be added to update the term for electric
transmission lines with a capacity of 100 kV or more, for up to 50
years, commensurate with the term for solar and wind energy development
projects and energy storage facilities that are separate from energy
generation facilities.
Some comments sought clarification on whether a presumptive
leaseholder's (which is defined at Sec. 2809.15(b)(1)) control of the
property would preclude other uses, such as grazing or recreation, or
during any period when use is not immediately initiated. Prior to the
competitive process, a prospective bidder would be informed as to
whether they were bidding on a location with existing authorized uses,
such as recreation or grazing or other known casual uses. The BLM's
identification of a presumptive leaseholder or issuance of a lease
would not automatically exclude authorized uses. Rather, the BLM must
follow its existing processes prior to ending existing uses; for
example, in the context of livestock grazing, notice and cancellation
is provided, subject to any required public comment periods.
The BLM understands from comments it has received that there is
some confusion whether solar and wind energy developments may also be
projects. In the final rule, the BLM revised paragraph (b)(2) to add
``projects'' to clarify that solar and wind energy developments may be
projects.
Section 2805.12 What terms and conditions must I comply with?
Section 2805.12 of this final rule lists certain terms and
conditions that apply to all right-of-way grants and leases. The BLM
revised this section to address public comments regarding the term
length authorized for certain facilities. The BLM also included
revisions to prevent a holder's non-use of the public lands for the
authorized energy generation facilities.
Paragraph (c)(8) is added to this final rule addressing concerns
raised in relation to Sec. 2801.9(d) regarding the longer term for
grants and leases. This rule provides diligent operation requirements
wherein the holder of a solar or wind energy development grant or lease
must maintain at least 75 percent of energy generation capacity for the
authorized facility for the grant or lease term. A failure to meet this
operational capacity for two consecutive years may support the
suspension or termination of the grant or lease under Sec. Sec.
2807.17 through 2807.19. The BLM would send notice to the grant or
leaseholder with a reasonable opportunity to correct any noncompliance
with the diligent operation requirement, including resuming use of the
right-of-way.
The BLM believes it is reasonable to establish a requirement that
solar and wind energy generation developments must operate within 75
percent of their generation capacity, allowing a 25 percent operational
change for each year. \6\ This allows a solar or wind operator to
safely accommodate operational changes related to unforeseen
circumstances and maximize their energy production without the need to
coordinate with the BLM for normal operations. A sustained reduction in
output, such as for anomalous storm years or changes to a development's
technology, that reduce the energy generation below 75 percent of the
project's capacity would require coordination with the BLM to update
project information. The energy generation capacity is first
established by the right-of-way holder under section 2806.52(b)(5) in
the first annual certified statement, and then informed by subsequent
years' operational capacities in the annual statement. Since the BLM
bills in advance for a calendar year (see part 2806 for further
information on solar and wind energy capacity fee), the BLM believes
that this operational standard is appropriate for the orderly
administration of the public lands and to ensure appropriate use of its
resources.
---------------------------------------------------------------------------
\6\ As demonstrated in a 2018 NREL study, forecast modeling for
solar photovoltaic and wind energy developments is generally within
10 percent of expected capacities over a one-year period. https://www.nrel.gov/docs/fy23osti/79498.pdf, Solar PV, Wind Generation, and
Load Forecasting Dataset for ERCOT 2018: Performance-Based Energy
Resource Feedback, Optimization, and Risk Management
(P.E.R.F.O.R.M.)
---------------------------------------------------------------------------
In response to the BLM's notice, a holder must provide reasonable
justification for the reductions in energy generation, such as delays
in equipment delivery, legal challenges, or Acts of God. Holders must
also provide the anticipated date when energy generation will resume
and a request for extension under paragraph (e) for an extension of
operations period to satisfy the two-year diligent operation
requirements of paragraph (c)(8). The BLM may deny a request for
extension for failure to comply with this section.
The BLM will use the annual certified statement required under
Sec. 2806.52(b)(5) to determine whether a holder has been meeting the
minimum energy generation capacity for the diligent operation
requirement. Under paragraph 2806.52(b)(5)(vi), the holder must notify
the BLM if they will reduce the amount of energy generated by 25
percent or more for that year. Two consecutive years with reduced
energy generation would support the BLM's notice to the grant or
leaseholder of noncompliance with the diligent operation requirement.
Paragraph (e)(2) of this final rule clarifies that the option of
requesting alternative stipulations, terms, or conditions does not
apply to terms or conditions related to rents or fees. As with requests
for alternative application requirements under Sec. 2804.40, requests
[[Page 35652]]
for alternative stipulations, terms, or conditions under Sec. 2805.12
are limited to technical obligations of the applicant or holder and not
to the holder's obligation to compensate the United States for the use
of the public lands and their resources. Requests for exemptions or
deviations from the general rent provisions of subpart 2806 should be
made under provisions of that subpart that specifically address such
exemptions or deviations, such as existing Sec. 2806.15(c) (not
revised in this rulemaking), which sets forth a procedure for asking
the BLM State Director to waive or reduce a holder's rent payment, or
Sec. 2806.52(b)(1)(i), which describes certain circumstances under
which the BLM may calculate the capacity fee based on an alternative
MWh rate.
A comment suggested that the fees could be based on third-party
evaluations, such as an appraisal. The BLM considered whether an
appraisal specific to each authorization would be appropriate and
determined that using such a process would be costly and add
considerable time to the processing of an application. The BLM chose
not to use an appraisal, except when it determines under Sec. 2806.70
that its rent schedules do not apply to the underlying right-of-way
use. For example, if the BLM receives a right-of-way application
requesting a permit for a long-term landscape art installation, the
schedules for transmission, solar or wind energy development, or
communications sites would not apply, and the BLM may elect to use an
appraisal to determine the appropriate rent. This final rule also
provides for a specific alternative MWh rate for determining the
capacity fee under Sec. 2805.62(b)(1)(i) for development projects that
use a Power Purchase Agreement (PPA). Such agreements must be provided
to the BLM for review. If the BLM determines the lower rate is
appropriate, it will use such agreements in place of the calculated MWh
rate. The BLM did not make a change in response to this comment.
A comment requested that the BLM require applicants to include PLAs
and add union labor protections as a term and condition of solar and
wind energy rights-of-way. In this final rule, the BLM has elected to
provide an opportunity for holders to receive capacity fee reductions
under certain conditions, including where the holder can show it is
using PLAs for the construction of the planned facility (see Sec.
2806.52(b)), consistent with the reduction authority under the Energy
Act of 2020. However, in administering the public lands, the BLM is
making such compliance voluntary, offering the capacity fee reduction
to incentivize the use of PLAs for solar and wind energy development
projects instead of mandating compliance with such a term. The BLM
believes this voluntary option provides opportunities to a wide variety
of potential holders and recognizes the effort of those who qualify for
such reductions consistent with criteria in Sec. 2806.52(b). No change
was made in the final rule due to this comment.
Section 2805.13 When is a grant or lease effective?
Section 2805.13 of this final rule includes a minor technical
clarification to the title and section, adding ``or lease,'' to build
consistency for authorization term lengths inside and outside of DLAs.
The BLM received comments opposing this section regarding term
length of authorizations. One comment recommended the BLM extend the
maximum term from 30 years to 50 years only for leases inside DLAs.
Another comment opposed extending the maximum term to 50 years for any
authorization. The BLM addressed this and other similar comments under
Sec. 2801.9 of this preamble.
Section 2805.14 What rights does a right-of-way grant or lease convey?
Section 2805.14 of this final rule clarifies that the term ``right-
of-way'' is the category of authorizations that generally are issued as
a grant or a lease under Title V of FLPMA. This clarity has become
increasingly important for the internal and external understanding of
right-of-way authorizations with the passage of new legislation. The
BLM did not receive comments on this section.
The title is revised to ``What rights does a right-of-way grant or
lease convey?'' The title clarifies that this section applies to both
grants and leases.
Paragraph (g) removes the text ``solar or wind energy development''
and adds ``right-of-way'' to now read as ``right-of-way grant or
lease.'' This section provides for when an applicant applies to renew
any right-of-way grant or lease under Sec. 2807.22.
Section 2805.16 If I hold a grant or lease, what monitoring fees must I
pay?
The BLM's final rule ``Update of the Communications Uses Program,
Cost Recovery Fee Schedules, and Section 512 of FLPMA for Rights-of-
Way'' 89 FR 25922 (April 12, 2024) updated the BLM Headquarters address
in Sec. 2805.16. Thus, the proposed rule's update to the BLM
Headquarters address is no longer necessary. The BLM did not receive
comments on this section and did not include it in the final rule.
Subpart 2806 Annual Rents and Payments
Subpart 2806 of this final rule clarifies that the term ``right-of-
way'' is the category of authorizations that are generally issued as a
grant or a lease under Title V of FLPMA. This clarity has become
increasingly important for the internal and external understanding of
right-of-way authorizations with the passage of new legislation.
In subpart 2806, the BLM sets the acreage rent and capacity fee
calculation methodologies for solar and wind energy development rights-
of-way. Section 504(g) of FLPMA, 43 U.S.C. 1764(g), requires right-of-
way holders, subject to several narrow exceptions, ``to pay in advance
the fair market value'' for the use of the public lands. Section 102(a)
of FLPMA, 43 U.S.C. 1701(a), clarifies that ``it is the policy of the
United States that . . . the United States receive fair market value of
the use of the public lands and their resources unless otherwise
provided for by statute.'' The BLM has consistently taken the position
that this statutory mandate includes the authority to charge acreage
rent and capacity fees that reflect the fair market value of the public
lands and their resources. For example, the preamble to the BLM's 2016
Final Rule, Competitive Processes, Terms, and Conditions for Leasing
Public Lands for Solar and Wind Energy Development and Technical
Changes and Corrections, explained that ``(t)he BLM has determined that
the most appropriate way to obtain fair market value is through the
collection of multicomponent fee [sic] that comprises an acreage rent,
a MW capacity fee, and, where applicable, a minimum and a bonus bid for
lands offered competitively . . . . [T]he collection of this
multicomponent fee will ensure that the BLM obtains fair market value
for the BLM authorized uses of the public lands, including for solar
and wind energy generation.'' 81 FR 92122, 92134 (Dec. 19, 2016). In
that final rule, the BLM further explained that the use of a
multicomponent rent and fee structure that comprises an acreage rent, a
MW capacity fee, and in some cases also a minimum and a bonus bid
assists the BLM in achieving important objectives, including
identifying and capturing fair market value for the use of public land,
providing a consistent approach with other categories of public land
uses, encouraging efficient use of the public lands by reducing
relative costs for comparable projects using fewer acres, and employing
an approach
[[Page 35653]]
consistent with existing policies and regulations governing the BLM's
renewable energy program. See id. The multicomponent fee of this final
rule will continue to advance important objectives that serve the
public interest, including allowing the BLM to capture fair market
value for use of the land (subject to reductions pursuant to Energy Act
of 2020 authority).
In the Energy Act of 2020, 43 U.S.C. 3003, Congress amended the
fair market value requirement of Section 504(g) of FLPMA by providing
the Secretary with discretion to ``consider acreage rental rates,
capacity fees, and other recurring annual fees in total when evaluating
existing rates paid for the use of Federal land'' for solar and wind
energy projects and reduce acreage rental rates and capacity fees if
the Secretary makes certain findings, including ``that a reduced rental
rate or capacity fee is necessary to promote the greatest use of wind
and solar energy resources.'' Consistent with FLPMA and the Energy Act
of 2020, the BLM will continue to charge solar and wind energy rights-
of-way acreage rent and capacity fees. The final rule implements a
methodology that bases rent and fee rates on local land values and
wholesale energy market prices. This methodology also supports the
direction in the Energy Act of 2020, 43 U.S.C. 3004, of meeting
national clean energy objectives, including the congressional goal of
permitting 25 GW of renewable energy by 2025 on Federal lands through
reductions in rental rates and capacity fees. As described in the
section-by-section discussion for subpart 2806, this final rule is
utilizing the authority in 43 U.S.C. 3003 to adjust the fair market
value requirement through reductions in rental rates and capacity fees
for solar and wind energy projects on public lands.
Under the final rule, acreage rent rates for solar and wind energy
rights-of-way are determined using the NASS Cash Rents Survey, which
reflects a nominal value of the land at the time the right-of-way is
issued and prior to commercial use. This per-acre land rental value
will be multiplied by an encumbrance factor (which differentiates
between solar and wind energy facilities) and an annual adjustment
factor that accounts for changes in the value of the land over the
lifetime of the right-of-way due to inflation and similar factors.
Because the NASS Cash Rents Survey used for solar and wind acreage
rents reflects a valuation of annual rent, no rate of return is applied
when determining solar and wind energy acreage rents. The acreage rent
rate reflects a nominal value of the land to continue to maintain site
control after the right-of-way is issued.
Once a solar or wind energy generation facility is utilizing the
solar or wind resources on public land to produce electricity, the BLM
may charge the capacity fee for the right-of-way unless the acreage
rent remains higher than the fee. The capacity fee is determined in
part using the annual MWh production multiplied by either wholesale
power pricing information or pricing figures specific to a project's
PPA to determine the market value of the electricity generated from the
project. The wholesale power pricing information or other pricing basis
variables in the BLM's calculation, like the pastureland rental value
based on the NASS Cash Rents Survey used for calculating acreage rents,
will be fixed at the time the right-of-way is issued and will be
updated using a fixed annual adjustment factor. This market value of
the electricity generated will then be multiplied by a rate of return
based on a percentage of wholesale pricing and by certain qualifying
fee reductions to arrive at a capacity fee for the authorized project.
Some comments suggested that fees should be compared with the fees
associated with other energy sources instead of being based on the per-
acre values for pastureland. Other comments expressed support for the
BLM using the NASS Cash Rents Survey to calculate acreage rent rates.
The BLM manages different energy sources, e.g., oil and gas and
geothermal, consistent with the applicable laws for each. As such, rent
and fee values promulgated in regulations consider differences under
law. Solar and wind energy generation facilities on public lands are
authorized under Title V of the FLPMA (43 U.S.C. 1761-1771) and its
implementing regulations at 43 CFR part 2800. Section 504(g) of FLPMA
generally sets the requirements for how the BLM will collect rents and
fees for use of the public lands and their resources through a right-
of-way. These requirements differ from those in the MLA (30 U.S.C. 181
et seq.) and the Geothermal Steam Act (30 U.S.C. 1001 et seq.), and
thus a comparison of fees for production of these different energy
sources on public lands would be inappropriate and irrelevant. In this
final rule, the BLM updates rents and fees for solar and wind energy
development rights-of-way under the authority provided by FLPMA to
reflect the fair market value for use of the public lands and their
resources by using acreage rental rates that reflect local land values
prior to commercial electricity production through using pastureland
cash rent survey values by NASS. The BLM then applies its authority
under the Energy Act of 2020 to provide reductions that are necessary
to promote the greatest use of wind and solar energy resources.
One comment suggested that the proposed rule should not offer
acreage rent and capacity fee reductions to projects outside DLAs and
instead should implement project-specific reductions and other
incentives to promote responsible development inside DLAs. DLAs are
locations on public lands that the BLM has designated through the land
use planning process as priority areas for solar and/or wind energy
development. Limiting acreage rent and capacity fee reductions to DLAs
would not, however, meet the Energy Act of 2020's direction to promote
the greatest use of wind and solar resources. To date, the BLM has only
allocated DLAs for solar facilities on public lands within six
southwestern states for locations that are predominately favorable for
thermal solar projects (i.e., concentrated solar). The BLM currently
has no DLAs allocated for solar in other states. Furthermore, the BLM
has no DLAs allocated for wind energy development on public lands in
any state. The BLM determined that limiting rent and fee reductions to
only DLAs would be sub-optimal in supporting clean energy goals. As
such, the final rule will provide for rent and fee reductions on public
lands both inside and outside DLAs, which will serve the BLM's purpose
of promoting the greatest use of wind and solar energy resources on
public lands.
One comment suggested that subpart 2806 should not eliminate fair
market value for rental and leases on public lands or the competitive
bid process. The commenter did not support incentivizing renewable
development for a specific project by eliminating the competitive
leasing process. Contrary to the commenter's suggestion, this final
rule does not eliminate the BLM's ability to utilize a competitive bid
process for solar and wind energy development. The final rule adjusts
the competitive process requirements for wind and solar energy
development proposals within DLAs by aligning it to be consistent with
agency discretion for utilizing a competitive process outside DLAs when
the BLM's authorized officer decides to use a competitive process.
Some comments suggested that this rule should generally raise fees
for developers and require more upfront mitigation money to address
long term environmental issues. Related
[[Page 35654]]
comments suggested that the BLM should establish an environmental
mitigation fund in addition to rents and fees to accommodate the high
probability of direct and cumulative impacts. The BLM considered these
comments and is not making these suggested changes. The BLM believes
such changes are unnecessary because the final rule does not limit the
BLM's existing authority and ability to appropriately impose mitigation
requirements as a component of the terms, conditions, and stipulations
for a solar or wind energy development. The BLM will continue to
require appropriate mitigation and conditions of approval to address
environmental impacts for right-of-way grants and leases without
further requirements promulgated under this final rule.
Other commenters stated that the BLM should implement a minimum
efficiency criterion to ensure that consumers receive the necessary
amount of power to keep up with demand. The BLM disagrees with comments
suggesting that the BLM should regulate how efficiently a project must
operate. Developing a project is a complex process that depends on
several factors, including the availability and cost of appropriate
technology. The BLM has included a provision in this final rule that
sets an operational standard requiring a development project to
annually maintain at least 75 percent of its energy generation
capacity. See Sec. 2805.12(c)(8) for further information on the
operational standards for solar and wind energy development projects on
public lands.
Section 2806.10 What rent must I pay for my grant or lease?
Section 2806.10 of this final rule provides a minor technical
clarification described below. The BLM did not receive comments on this
section and has made no changes to it in the final rule.
Section 2806.10 provides rent requirements that apply to all grants
and leases, requiring payment in advance, consistent with Section
504(g) of FLPMA, as amended. New Sec. 2806.10(c) would clarify to a
reader that the per acre rent schedule for linear right-of-way grants
must be used unless a separate rent schedule is established for your
use--such as with communication sites under Sec. 2806.30 or solar and
wind energy development facilities per Sec. 2806.50--or the BLM
determines under Sec. 2806.70 that its rent schedules do not apply to
the underlying right-of-way use.
Section 2806.12 When and where do I pay rent?
Section 2806.12 of this final rule provides a minor technical
clarification as described below. The BLM did not receive comments on
this section and has made no changes to it in the final rule.
Paragraphs 2806.12(a) and (b) describe the proration of rent for
the first year of a grant and the schedule for payment of rents.
Paragraphs 2806.12(a) and (b) would be revised by deleting the term
``non-linear,'' which is not defined in the regulations, to clarify
that these provisions apply to all right-of-way grants or leases.
Section 2806.20 What is the rent for a linear right-of-way grant?
Section 2806.20 of this final rule clarifies the BLM's mailing
address. Section 2806.20(c) addresses how to obtain a current rent
schedule for linear rights-of-way. This paragraph provides the BLM's
mailing address of record by reference to Sec. 2804.14(c).
Solar and Wind Energy Development Rights-of-Way
The existing regulations contain two undesignated center headings
to organize and differentiate sections pertaining to solar (see
existing Sec. Sec. 2806.50 through 58) and wind (see existing
Sec. Sec. 2806.60 through 68) energy rights-of-way. The final rule
revises those sections and undesignated headings to provide a single
set of provisions for all solar and wind energy development rights-of-
way. The rent, fee, and payment requirements under the final rule are
discussed in the following sections and are identical for solar and
wind except for the difference in the encumbrance factor used in
calculating the acreage rent that is discussed under Sec. 2806.52(a).
Sections 2806.50 through 2806.58 address solar and wind energy rents
and capacity fees.
The final rule updates the acreage rent and capacity fee
calculation methods to improve predictability of rates for solar and
wind energy development projects on public land. The combined rent and
fee calculation methodologies have the flexibility to meet FLPMA's fair
market value requirement while also applying calculation factors to
reduce rates to promote the greatest use of wind and solar energy
resources on the public lands consistent with the Energy Act of 2020.
The final rule retains flexibility to utilize different data
sources for electricity market values over time. Developers of solar
and wind energy on public lands will have improved rate predictability
over the term of an authorization. This is accomplished by establishing
an acreage rate and capacity fee rate at the beginning of a grant or
lease term with upfront built-in rate adjustments and by indexing the
capacity fee to the annual energy production.
The BLM's acreage rent is the average of the state-wide pastureland
rent from the NASS Cash Rent Survey. The acreage rent is the minimum
payment made to the BLM each year by the developer. See Sec.
2806.52(a) for further information on the acreage rent.
The capacity fee, based on wholesale power prices, serves to
compensate the United States for long-term site control and the
production value of the electricity generated by solar and wind energy
projects on public lands. The capacity fee will be collected annually,
but only when the capacity fee exceeds the acreage rent for the year.
See Sec. 2806.52(b) for further information on the capacity fee.
The final rule includes certain reductions that may be applied
under the authority granted to the Secretary in the Energy Act of 2020,
which provides that annual acreage rent and capacity fees may be
reduced if the Secretary determines that a reduced rental rate or
capacity fee is necessary to promote the greatest use of wind and solar
energy resources, among other reasons. Adjustments to the capacity fee
from the MWh rate reduction, The Domestic Content reduction, and PLA
reduction are discussed in greater detail in Sec. 2806.52(b)(1)(ii)
through (iv). The BLM has determined that the rate reductions in this
final rule would help to promote the greatest use of wind and solar
energy resources on public lands.
Section 2806.50 Rents and Fees for Solar and Wind Energy Development
Section 2806.50 of the final rule requires the holder of a solar or
wind energy right-of-way to pay in advance the greater of either an
annual acreage rent or a capacity fee, consistent with Section 504(g)
of FLPMA (43 U.S.C. 1764(g)). There are no provisions in this rule for
a phased-in rent or fee.
The acreage rent or capacity fee, as applicable, is calculated
based on the requirements found in Sec. Sec. 2806.11 and 2806.12. The
acreage rent is calculated according to the formula set forth in Sec.
2806.52(a), while the capacity fee is calculated according to the
formula set forth in Sec. 2806.52(b).
Some comments expressed concern that this rule creates negative
market incentives by keeping acreage rents and capacity fees
artificially low. These
[[Page 35655]]
commenters suggest that the BLM should implement a consistent yearly
increase in acreage rent and capacity fees based on initial rates, with
reductions provided only for projects in specific circumstances, such
as siting within solar zones or on disturbed lands, and with strong
commitments to domestic content. The BLM is cognizant that the rent and
fee rate structure is important for promoting the greatest use of wind
and solar energy resources and is a critical component to providing
short- to medium-term stability for emerging energy markets. There is a
strong public interest in maintaining rate predictability for
electricity generating entities that are subject to long-term
interconnect and PPAs. This final rule sets rates that are also
increased annually, through the annual adjustment factor (see Sec.
2806.52(b)(2)). The annual adjustment continues through the term of the
authorization. Additionally, this final rule provides an opportunity
for rate reductions for all solar and wind energy development projects
that further the goals of the Energy Act of 2020, which is to authorize
25 gigawatts of renewable energy on Federal lands by 2025 and further
national clean energy priorities. The BLM did not make a change to this
section of the final rule.
Section 2806.51 Grant and Lease Rate Adjustments
Section 2806.51's title is changed from the proposed rule to
clarify that this section applies to all grants and leases. This
section provides for right-of-way grant and leaseholders to transition
to the new rate making under this final rule through an affirmative
request to the BLM. Absent a request, they would retain the rate
setting method in effect prior to this final rule.
Paragraph (c) informs holders of existing solar or wind energy
development rights-of-way that they may request the new rate
methodology in this final rule be applied to their existing grant or
lease. Existing holders have two years from the date this final rule
becomes effective to request a change to the new rate making method.
The BLM will continue to apply the grant holder's or lessee's current
rate methodology if a timely request is not received.
The BLM received a comment that does not support any rate reduction
based on an estimation of energy generated because all rates should be
assessed on actual production. The BLM has the administrative
flexibility to collect payment in advance based on estimated energy.
The amount the BLM may collect for the right-of-way may change once the
BLM determines the actual energy production on the right-of-way. The
BLM will reconcile any difference in the amount due and credit any
overpayment, and right-of-way grant holders and lessees are liable for
any underpayment. See Sec. 2806.52(b)(5) of this rule for the BLM's
annual certified statement that provides more information about the
estimated and actual energy generation. The BLM did not change this
section of the final rule in response to this comment.
Some comments recommended that the final rule cap the total amount
of reduction in acreage rents and capacity fees that an individual
leaseholder can claim for a right-of-way. The final rule does not cap
the number or level of reductions an applicant or holder may qualify
for; however, the final rule does require that the BLM collect no less
than the acreage rent for the right-of-way each year, notwithstanding
the number of reductions that apply to the grant per Sec. 2806.52(b).
The BLM did not change this section of the final rule in response to
this comment.
Some comments suggested that rate reductions may be achieved
without any changes to where the BLM sources its market pricing data.
In the final rule, the BLM preserves its discretion to change the
source of market data. In the BLM's experience, access to such
information may change over time. For this final rule, the BLM is using
the Energy Information Administration pricing data that may be found at
https://www.eia.gov/electricity/wholesale/. Energy Information
Administration data is free and open to the public, increasing
transparency into the BLM's rate schedule. The BLM did not change to
this section of the final rule in response to this comment.
Some comments recommended that the BLM seek to increase
domestically sourced products and materials and that the BLM should use
this rule to mandate robust domestic content thresholds for projects
permitted on Federal land. The BLM agrees with these commenters'
interest in increased use of domestic content for solar and wind energy
development projects. This final rule includes a financial incentive in
the form of a ``Domestic Content reduction'' under Sec.
2806.52(b)(1)(iii) to encourage holders to use components made or
manufactured in the United States in the construction of the solar or
wind energy project. This capacity fee reduction is intended to offset
costs associated with using only iron, steel, manufactured products,
and construction materials incorporated into the project that are
produced in the United States consistent with the direction in the
Energy Act of 2020. The BLM anticipates that this proposed capacity fee
reduction would increase economic certainty for renewable energy
projects on BLM-managed public lands. By incentivizing the use of
domestically made parts and materials in exchange for a reduced
capacity fee, the BLM expects to reduce costs for developers that
choose to incorporate domestically produced materials into their
projects. The BLM believes that this reduction will help increase
demand for domestically produced renewable energy parts and materials.
These intended outcomes would serve to promote the greatest use of wind
and solar energy resources on public lands. Currently, wind and solar
energy developers face a choice between relying on foreign-sourced
parts and materials or paying higher prices for domestically sourced
parts and materials, if available. (See for example the Department of
Energy's Solar Photovoltaics--Supply Chain Deep Dive Assessment,
available at https://www.energy.gov/sites/default/files/2022-02/Solar%20Energy%20Supply%20Chain%20Report%20-%20Final.pdf). As seen in
recent years, uncertainty in global supply chain dynamics has the
potential to delay deployment of solar and wind energy development
projects on public lands. Using incentives to create demand for
American-made renewable energy parts and materials will help develop
domestic supply chains and reduce impacts on renewable energy
deployment on public lands from potential supply chain delays. The BLM
believes that incentivizing the use of parts and materials that qualify
for the Domestic Content reduction will increase the responsible
deployment of renewable energy and will increase commercial interest in
the use of public lands, promoting the development of solar and wind
energy resources on public lands. This final rule changes the
definition used for domestic content to align with the BABA Act and
implementing guidance at 2 CFR 184. See Sec. 2806.52(b) for further
information on the domestic content reduction.
Some comments suggested that a broad approach to rate reductions
may have revenue implications and fail to guarantee that taxpayers
obtain a fair return for the utilization of our public lands.
Consistent with congressional and presidential direction, the BLM is
endeavoring to increase the responsible deployment of renewable energy
on the public lands and as part of that direction has been authorized
to reduce rents and fees to promote the greatest
[[Page 35656]]
use of wind and solar resources on public lands. As part of this
rulemaking process, the BLM carefully deliberated on how to implement
the directives and new authorities while maintaining a reasonable
return for the use of the public lands and their resources. Following
the BLM's implementation of previous rate reductions in calendar year
2022 for solar and wind energy development projects, the agency
received feedback which generally indicated that overall costs for
permitting, development, and operations on Federal public lands were
still perceived as a barrier to entry and a disincentive to the BLM's
ability to promote solar and wind deployment on public lands. The BLM
believes the fee reductions will assist in removing barriers inhibiting
deployment of solar and wind development on public lands.
Section 2806.52 Annual Rents and Fees for Solar and Wind Energy
Development
Section 2806.52 of this final rule describes the BLM's methodology
to determine the acreage rent and capacity fee for solar and wind
development rights-of-way. Payment is required of the greater of either
an acreage rent, which is calculated in advance of authorization, or a
capacity fee, which is calculated upon the start of energy generation.
This section was revised based on public comments.
Section 2806.52(a) provides that acreage rent would be determined
by multiplying the number of acres authorized for a project (rounded up
to the nearest tenth) by the state-specific per-acre rate from the
solar and wind energy acreage rent schedule in effect at the time a
grant or lease is issued. The acreage rent would be the minimum yearly
payment for a grant or lease and would not be required if the capacity
fee under paragraph (b) of this section exceeds the acreage rent.
Paragraph (a)(1) explains that the per-acre rate is calculated by
multiplying the state-specific per-acre value by the encumbrance factor
and a factor that reflects the compound annual adjustment since the
start of the grant or lease term, according to the formula A x B x ((1
+ C) [supcaret] D)).
Paragraph (a)(1)(i) identifies ``A'' as the per-acre rate, using
the state-specific per-acre value from the solar or wind energy acreage
rent schedule for the state where a project is located for the year
when the grant or lease is issued. The average per acre value will be
determined using the NASS pastureland rents reported within the
previous 5-year period. The BLM will update the acreage rent schedule
and its per-acre rate every 5 years consistent with the timing of rent
adjustments under Sec. 2806.22 for the linear rents schedule. Based on
the pastureland rent value in the NASS Cash Rents Survey through 2021,
the most recent 5-year average ranges from $2.10 per acre in Arizona to
$12.60 per acre in California with a median value of $6.62 per acre in
the Western States. The next year the BLM will update its rent schedule
will be for calendar year 2026.
Using Nevada as an example for how the BLM will average NASS
pastureland rents, assume that NASS reported values of $10.00, $13.00,
and $10.00 per acre respectively for 2019, 2020, and 2021. NASS
reported values during the 5-year period only for those 3 years and did
not report values for 2017 and 2018. In that case, the BLM would
average the reported values using three years for that 5-year period,
which would equate to $11.00 per acre.
The per-acre rate charged to the right-of-way holder for a grant or
lease will not change once calculated and the authorization is issued.
Rates for an existing authorization will not change with updates to the
acreage rent schedule; instead, the acreage rent will be adjusted by
the annual adjustment factor, ``C'' in the formula above, under
2806.52(a)(1)(iii).
Paragraph (a)(1)(ii) identifies ``B'' in the formula above as the
encumbrance factor. The encumbrance factor is applied to account for
the intensity of the solar or wind development's surface use of the
public lands. In the final rule, solar energy generation facilities are
subject to a 100 percent encumbrance factor and wind energy generation
facilities are subject to a five percent encumbrance factor. The 100
percent encumbrance factor for solar facilities reflects a greater
intensity of development on the surface of public lands and a virtual
exclusion of other uses on the right-of-way. The five percent
encumbrance factor for wind facilities recognizes that a wind energy
facility only partially encumbers the land, allowing other uses to co-
exist.
Some comments suggest that a lower encumbrance value for solar is
appropriate, noting that facilities may incorporate design elements or
construction methods that reduce impacts to resources, such as raised
fences for wildlife passage or vegetation disturbance caps. The BLM
appreciates that projects incorporating such improvements may cause
fewer impacts to public land resources. However, the BLM disagrees that
such improvements reduce the encumbrance factor, which is based on the
occupancy of the land and impact to other uses of the land. Solar
energy developments have a greater occupancy of the land and impact to
other uses because they preclude the majority and sometimes all other
uses. This encumbrance factor for solar energy developments is
appropriate for public lands, and the BLM retains its 100 percent
encumbrance factor for this rule.
One comment asserted that the proposed encumbrance value of five
percent for wind energy is too low and should be set around 50 percent
and that if the BLM decreases the encumbrance factor from 10 percent,
the BLM should a explain its rationale in this rule. Others believed
the encumbrance factor should be lower, asserting that a mid-point
encumbrance factor of 3 percent is appropriate based on the Department
of Energy's Wind Vision analysis. The BLM considered the intensity of
the surface use and exclusion of other uses when setting the
encumbrance factor in this final rule. While the commenters that
advocated for a 50 percent encumbrance factor did not provide data
supporting that figure, the National Renewable Energy Laboratory has
found that generally ``only a small fraction of that area (<1%-4%) is
estimated to be directly impacted or permanently occupied by physical
wind energy infrastructure.'' \7\ In practice, the BLM has found that,
based on geography or project design, and effect on other uses, the
encumbrance may be more or less than that reported by NREL occupied
land percentages and therefore set a five percent encumbrance factor
for wind energy.
---------------------------------------------------------------------------
\7\ https://www.nrel.gov/news/program/2022/nrel-explores-the-dynamic-nature-of-wind-deployment-and-land-use.html.
---------------------------------------------------------------------------
Paragraph (a)(1)(iii) clarifies that ``C'' in the formula above is
the annual adjustment factor, which is three percent, and Paragraph
(a)(1)(iv) clarifies that ``D'' is the year of the grant or lease term,
where the first year (whether partial or a full year) would be 0 (that
is, there is no inflation for the first year of the term). Under the
final rule, the annual adjustment factor would be fixed at three
percent and compounded annually for the term of the authorization.
Paragraph (a)(2) describes where you may obtain a copy of the
current per-acre rates for the solar and wind energy rent schedule.
Paragraph (b) describes that the capacity fee is calculated by
multiplying the MWh rate or the alternative MWh rate (which is
described below), the MWh rate reduction, the Domestic Content
reduction, PLA reduction, the
[[Page 35657]]
rate of return, and the annual power generated on public lands for the
grant or lease in question (measured in MWh) by a factor that reflects
the compound annual adjustment. The capacity fee is required to be paid
annually beginning in the first year that generation begins for the
energy generation facility. There will be no capacity fee levied for
the first year or any other year if the acreage rent exceeds the
capacity fee. The formula for calculating the annual capacity fee is A
x B x C x D x [(1 + E) [supcaret]F] x G x H.
Paragraph (b)(1)(i) describes that ``A'' is either the MWh rate, an
amount determined based on the average of the annual weighted average
wholesale price per MWh for the major trading hubs serving the 11
Western States of the continental United States, or the alternative MWh
rate. The MWh rate is calculated based on the wholesale prices from the
full five calendar-year period preceding the most recent MWh rate
adjustment before the right-of-way was issued, rounded to the nearest
dollar. There is no MWh rate phase-in for energy generation facilities
except for existing holders that elect to continue paying under their
current rate adjustment method per Sec. 2806.51(c).
The BLM may use an alternative MWh rate when a grant or leaseholder
enters into a PPA with a utility for a price per MWh that is lower than
the average of the annual weighted average wholesale price. In those
instances, the BLM will determine if the rate in the PPA is appropriate
to use instead of the MWh rate. For example, an alternative MWh rate
may not be appropriate if a utility issues itself a PPA for its solar
or wind energy development. If the rate in the PPA is appropriate, then
the BLM would set an alternative MWh rate for the grant or lease at the
rate in the PPA.
The BLM received a request to remove the BLM's discretion to use an
alternative MWh rate rather than a MWh rate calculated on the average
wholesale pricing as described under Sec. 2806.52(b)(1)(i). The BLM
provides an opportunity for an alternative MWh rate in this rule in the
event that there is a difference between wholesale pricing (energy
pricing at market) compared to the negotiated pricing that may be
achieved in a PPA. The BLM understands from a recent report from
Lawrence Berkeley National Lab (available at https://emp.lbl.gov/utility-scale-solar/) that PPA pricing may be less than wholesale
market pricing. The BLM does not want to disincentivize reasonable
development on public lands or more favorable power purchase rates,
which would be contrary to national goals set by law and directed by
executive order, by disincentivizing such actions. However, the BLM
also wishes to ensure it retains the discretion necessary to ensure
that an alternative MWh rate is appropriate. The BLM did not make
changes in the final rule due to these comments.
In paragraph (b)(1)(ii), ``B'' is the MWh rate reduction. The final
rule sets the capacity fee at 20 percent of the wholesale price per MWh
or alternative MWh rate through calendar year 2035. This reduction is
consistent with the authority provided in the Energy Act of 2020
allowing the Secretary to reduce acreage rental rates and capacity fees
if, among other things, the Secretary determines ``that a reduced
rental rate or capacity fee is necessary to promote the greatest use of
wind and solar energy resources.'' Further, this reduction would help
BLM meet the goal under the Energy Act of 2020 of ``authoriz[ing]
production of not less than 25 gigawatts of electricity from wind,
solar, and geothermal projects by not later than 2025.'' Implementing
this reduction is necessary to promote the greatest use of wind and
solar energy resources and maximize commercial interest in lease sales
by lowering the entry cost of prospective energy generating facilities.
Additionally, implementing this reduction puts the rates the BLM
charges closer to what the BLM charged developers in 2007 and 2008 when
interest in solar and wind energy development on public lands began to
increase. The reduced rates and new rate setting methodology lower the
potential that existing right-of-way holders who agreed to terms and
conditions for using public lands that were later updated based on
market changes will experience economic hardship as a result of those
adjustments. This final rule uses predetermined adjustments instead.
For example, the MWh rate reduction for a newly authorized solar or
wind energy grant or lease in 2035 will be set at 20 percent of the
wholesale price per MWh or alternative MWh rate. This will yield a
continued 80 percent reduction through the end of that authorization's
term consistent with the Energy Act of 2020 authority.
Starting in 2036, the BLM will begin to transition the MWh rate
reduction to 20 percent by 2038. The MWh rate reduction will be reduced
to 60 percent for new projects authorized in 2036, 40 percent for new
projects authorized in 2037, and 20 percent for new projects authorized
in 2038 and beyond. The rates for existing authorizations will not
change with this transition to a 20 percent reduction. For example, an
authorization for solar or wind energy development in 2037 would
receive a 40 percent reduction through the end of the authorization's
term. The BLM would similarly apply this reduction to authorizations it
issues based on the year of issuance.
Some comments suggested the transition from an 80 percent MWh rate
reduction to a 20 percent MWh rate reduction appears arbitrary and
without grounding in economic analysis of market conditions and
suggested instead allowing the 80 percent reduction to continue until a
future rulemaking. The BLM understands the concerns raised by the
commenters regarding the change to the reduction in the proposed rule.
However, the BLM disagrees that the 80 percent MWh rate reduction
should continue until a future rulemaking. Instituting a phased sunset
period to the 80 percent reduction in the capacity fee is appropriate
as the renewable energy industry may no longer need this reduction to
achieve the greatest use of wind and solar on public lands, and
progress toward our national goal of a carbon-pollution free
electricity sector may indicate that a reduction is no longer
warranted. In this final rule, the BLM is revising the transition from
MWh rate reduction from 80 percent to 20 percent over several years.
This transition would lessen the year-over-year rate change until 2038,
when the MWh rate reduction would remain at 20 percent. The BLM will
evaluate progress towards reaching national goals before 2036 and could
reinitiate rulemaking to adjust incentives, including extending them
beyond 2036, if appropriate under the authority in the Energy Act of
2020 or other applicable authority.
In paragraph (b)(1)(iii), ``C'' is the Domestic Content reduction.
This paragraph is revised consistent with the changes discussed under
Sec. 2801.5. As explained previously, the BLM is promoting the
development of solar and wind energy resources on public lands by
offsetting some of the costs of using items and materials produced in
the United States in the construction of solar and wind energy
development facilities. The BABA Act, Public Law 117-58, 135 Stat. 429,
Sec. Sec. 70901 through 70927 (Nov. 15, 2021) and the implementing
regulations at 2 CFR part 184, describe certain categories of items or
products that are eligible for the domestic content preference. As
noted in Sec. 2801.5, the BLM adopts the term ``domestic content'' to
refer to the items and materials associated with the construction of a
solar or wind energy facility on public lands that are eligible for the
domestic content preference. Paragraph (b)(1)(iii) of Sec. 2806.52 of
the BLM's regulation would reduce the
[[Page 35658]]
capacity fee for solar or wind energy generation facilities if the
holder can demonstrate that the construction of the facilities for the
right-of-way--excluding labor costs--qualify as produced in the United
States as described in 2 CFR 184.4. The Domestic Content reduction is
20 percent for facilities qualifying for the domestic content
preference defined in 2 CFR part 184. To qualify for this capacity fee
reduction, the percent of the energy generation facility's total cost
that consists of items qualifying for the domestic content preference
would have to meet or exceed the ``Produced in the United States''
requirements in 2 CFR 184.3. Generally, this would mean that: (1) all
manufacturing processes for iron or steel products used as a component
of the project occurred in the United States; (2) manufactured products
(a) were manufactured in the United States, and (b) the cost of the
components of the manufactured product that are mined, produced, or
manufactured in the United States is greater than 55 percent of the
total cost of the manufactured product, as determined in 2 CFR 184.5;
and (3) all manufacturing processes for construction materials occurred
in the United States, as defined in 2 CFR 184.6. The holder would have
to provide sufficient documentation (e.g., purchase orders for end
products, materials, and supplies of the facility; as-built or
construction plans) to demonstrate that the products used in the energy
generation facility meet the thresholds identified in 2 CFR part 184.
Once an energy generation facility qualifies for a Domestic Content
reduction, the facility will continue to benefit from the reduction for
the term of the grant or lease. The BLM will only revisit the reduction
at the time of an assignment, amendment, or renewal of an energy
generation facility grant or lease to determine what reduction, if any,
it may qualify for. The BLM will apply the criteria defining the
domestic content preference and the components of construction for the
version of 2 CFR part 184 in effect at the time the right-of-way is
issued unless OMB amends that guidance in the future in such a way that
the current definition contemplated in this final rule no longer
provides a clear meaning. In that circumstance, the BLM will apply the
most recent version of 2 CFR part 184 that provides a workable
definition until such time as the BLM is able to amend its rules.
In addition to changing the definition to qualify for a domestic
content reduction from a FAR to a BABA-based definition, this final
rule only provides for a single 20 percent reduction that interested
parties qualify for if they meet the requirements of 2 CFR part 184
instead of the incremental reduction that the BLM had proposed. Under
the BABA definition described above, projects qualify for the domestic
content preference by meeting or exceeding specific materials
requirements. As this is a binary qualification, an incremental
reduction would be untenable. Further, using a single reduction based
on the BABA threshold will provide for simpler implementation of the
regulation and more clarity to applicants.
One comment suggested that the BLM use the Electronic Product
Environmental Assessment Tool (EPEAT) product registry for photovoltaic
module use in development projects and any Domestic Content reduction.
EPEAT is a global label managed by the Global Electronics Council that
identifies environmentally sustainable electronic products. Currently,
however, EPEAT only covers a narrow set of products and construction
material related to solar development facilities (specifically,
photovoltaic modules and inverters) and does not cover any materials
related to wind energy generation facilities. As a result, requiring
applicants to use EPEAT-registered products for renewable energy
facilities on public lands could frustrate the goals of the Domestic
Content reduction. Further, such a requirement would not serve the
purposes Energy Act of 2020 or relevant direction in Executive Orders
because it would limit the technology that could be deployed on public
lands. The BLM may, however, consider such criteria for the Domestic
Content reduction in the future once the EPEAT covers a broader range
of solar and wind energy materials. The BLM made no changes to the
final rule due to this comment.
Some comments suggested that the BLM should require proof of
compliance with the domestic content incentive prior to reducing rates.
The BLM agrees with these comments and will require confirmation that
the holder seeking to obtain this reduction satisfies the qualifying
definitions the BLM is utilizing: the standard in 2 CFR part 184. See
Sec. 2806.52(b)(5) regarding conditional approvals where the BLM makes
it clear that approval will be granted by the BLM once it has been
demonstrated to the satisfaction of the BLM that the facility qualifies
for the reduction.
Some comments suggested that rate reductions in the final rule
should be consistent with the IRA. The BLM considered a reduction based
on the domestic content bonus tax credits in the IRA and its definition
of Buy America bonus tax credits. The BLM is aware that the Treasury
Department has issued guidance about the domestic content bonus under
the IRA for clean energy projects and facilities that meet American
manufacturing and sourcing requirements. However, that guidance
describes an intent to propose regulations that have not yet been
finalized, and this final rule's definition for domestic content aligns
with definitions in other Federal programs with oversight over domestic
products and content. No changes were made due to these comments.
Paragraph (b)(1)(iv) is ``D'', the Project Labor Agreement
reduction. The BLM is promoting the development of solar and wind
energy resources on public lands by offsetting some of the costs when
using a PLA during construction of solar and wind energy development
projects consistent with authority under the Energy Act of 2020. The
BLM's approach also is consistent with the policy direction in
Executive Order 14063 directing Federal agencies to use PLAs in
connection with large-scale construction projects to promote economy
and efficiency in the context of Federal procurement. A PLA is a pre-
hire collective bargaining agreement negotiated between one or more
construction unions and one or more construction employers that
establishes the terms and conditions of employment for a specific
construction project, consistent with 29 U.S.C. 158(f).
The 20 percent reduction of the capacity fee offered in this final
rule to incentivize the use of a PLA is necessary to promote the
greatest use of solar and wind energy resources on public land, as
authorized by the Energy Act of 2020 (43 U.S.C. 3003(b)(2). In
particular, PLAs lead to better and more efficient outcomes in the
construction of solar and wind energy projects in the following ways,
which in turn leads to the greatest use of solar and wind resources.
First, PLAs provide better access to and retention of skilled laborers,
especially in a limited labor market.\8\ Studies and reports
demonstrate that skilled labor provided through PLAs offer a higher
quality of work, increased labor standards, more timely construction,
and fewer
[[Page 35659]]
deviations from construction plans.\9\ Second, PLAs improve workplace
safety by offering more apprentice-trained journey workers, which
studies have shown lead to fewer injuries.\10\ Third, PLAs can ensure
construction administration is streamlined, which minimizes undue
costs, delays, and inefficiencies in construction projects,
particularly complex projects such as wind or solar energy generation
facilities.\11\ Finally, PLAs contain no-strike, no-lockout clauses
that can prevent project construction delays associated with labor
disputes.\12\
---------------------------------------------------------------------------
\8\ Greg Lacurci, CNBC: Workers till Quitting At High Rates--And
Getting a Big Bump In Pay (Jan. 4, 2023); Jo Constantz, Bloomberg:
The Great Resignation Worked: Most Job-Swappers Got a Raise (July
29, 2022); Frank Manzo IV, Larissa Petrucci, & Robert Bruno, Ill.
Econ. Policy Inst.: The Union Advantage During the Construction
Labor Shortage 5 (2022).
\9\ McFadden, Sai Santosh, and Ronit Shetty: Quantifying the
Value of Union Labor in Construction Projects, Independent Project
Analysis, 2 and 8-9 (December 2022): https://acrobat.adobe.com/link/review?uri=urn%3Aaaid%3Ascds%3AUS%3Ad9e7f15b-9bf9-313f-b4eb-de7a1dc11d9f; and Fred B. Kotler: Project Labor Agreements in New
York State II: In the Public Interest and of Proven Value, Cornell
University ILR School, 10, 19 and 36 (May 1, 2011), https://ecommons.cornell.edu/bitstream/handle/1813/74333/LaborAgreementsinNYS_II.pdf?sequence=1.
\10\ Emma Waitzman & Peter Philips, UC Berkeley Labor Ctr:
Project Labor Agreements and Bidding Outcomes: The Case of Community
College Construction in California 10, 16 (2017); Bureau of Labor
Statistics, National Census of Occupational Injuries in 2021, USDL-
22-2309 (2022) (construction work is second highest for occupational
deaths).
\11\ Dep't of Labor, Implementation of Project Labor Agreements
in Federal Construction Projects: An Evaluation 20 (2011).
\12\ Dep't of Labor, Implementation of Project Labor Agreements
in Federal Construction Projects: An Evaluation 30 (2011).
---------------------------------------------------------------------------
The benefits associated with PLAs, in turn, would have positive
impacts for renewable energy projects on public lands, including
ensuring responsible and productive construction, and minimizing the
potential duration. These improved construction standards will better
meet resource management objectives and ensure authorized uses on
public lands are meeting the goal of the Energy Act of 2020 to promote
the greatest use of solar and wind energy resources. These improved
construction standards also are consistent with the BLM's authority
under FLPMA to incorporate right-of-way terms and conditions that,
among other things, ``protect Federal property and economic
interests,'' ``manage efficiently the lands . . . subject to the right-
of-way,'' and ``protect lives and property.'' (43 U.S.C. 1765(b)).
Further, as demonstrated by the reports and studies cited above, the
use of PLAs leads to higher and more stable wages for workers. These
reductions to the rates will further incentivize the use of PLAs by
developers and will help to offset higher wages for workers, which, in
turn, may help to reduce or eliminate economic hardships for workers
who would otherwise not benefit from the higher standards and
protections in PLAs.
Some comments argued against the use of the labor union incentives
included in the proposed rule and questioned the BLM's authority to
offer these incentives. Other comments requested additional provisions
be added to ensure responsible use of labor. As described above, the
BLM has concluded that, under the authority provided in the Energy Act
of 2020 and FLPMA, it has discretion to include reductions for the use
of PLAs. These reductions will incentivize the use of PLAs, providing
for increased assurances of timely, efficient construction; improved
worker safety; and higher and more stable wages for workers. The BLM
expects to publish additional policy guidance, such as through
instruction memoranda, to clarify how qualifying PLAs will be
identified, among other things. In providing this reduction in the
final rule, the BLM is promoting responsible use of labor and the
greatest use of solar and wind energy resources, as authorized by the
Energy Act of 2020, by encouraging solar and wind energy development on
public lands.
Some comments suggested that the rule should apply a tiered
incentive for developers based on the percentage of local labor they
commit to hire, which could be implemented by certified payroll reports
that include employee permanent addresses and in consultation with
local officials. Several comments supported the inclusion of a
reduction for Union Labor or PLAs. In the proposed rule, the BLM
described the potential of adding a 20 percent capacity fee reduction
for a holder's use of Union Labor or on the contingency of a PLA. In
this final rule, the BLM has decided to include a reduction for holders
who have entered into, or expect to enter into, a PLA for the
construction of a project, based on comments and additional support for
the benefits of using PLAs to advance infrastructure projects such as
renewable energy projects. This additional reduction parallels the
domestic content reduction in this rule in how it is applied in the
calculation. This reduction is based on the use of a PLA in project
construction and would offset some developer costs. The BLM does not
include in this final rule the suggested local labor reduction, but the
BLM believes the reduction for a PLA may also support the use of local
labor.
Paragraph (b)(1)(v) explains how the BLM applies the alternative
MWh rate and the Domestic Content and PLA reductions from paragraphs
(b)(1)(ii), (iii), and (iv) of this section. By default, the BLM will
apply the ordinary MWh rate under paragraph (b)(1)(i) and the MWh rate
reduction under paragraph (b)(1)(ii). A developer who wished to benefit
from the alternative MWh rate, the domestic content reduction, or the
PLA reduction will need to submit a request for conditional approval
prior to the issuance of a grant or lease, along with sufficient
documentation to demonstrate that the development qualifies or may
later qualify for these rate reductions. In some cases, the BLM will
not be able to determine definitively in advance whether the proponent
qualifies for these reductions. The BLM may then conditionally approve
the requested reductions, but the reductions will not go into effect
until the proponent adequately demonstrates that the facility qualifies
for the relevant reduction. If energy generation begins before the
holder has demonstrated that the facility qualifies, the BLM will
charge the holder the capacity fee absent the reduction. The capacity
fee could be updated for subsequent calendar years after the holder
demonstrates that the facility qualifies, but the BLM will not refund
past payments made before the holder demonstrates that they qualify and
rate reductions go into effect.
For example, an applicant or presumptive leaseholder (see
Sec. Sec. 2809.13 and 2809.15, below) might request conditional
approval of an alternative MWh rate. In that situation, a request for
conditional approval for an energy generation facility may be granted
if the presumptive leaseholder has entered into or intends to enter
into a PPA (see (b)(1)(i) of this section) that has a lower rate than
the MWh rate. Documentation submitted to the BLM when requesting
conditional approval may include draft or interim PPAs or confirmation
in writing from the purchasing party that the parties have entered into
negotiations. While the BLM may then conditionally approve the request
for an alternative MWh rate, the alternative rate would not go into
effect and be used when calculating the payment obligations until the
PPA is finalized and the BLM determines, in writing, that the facility
qualifies for the alternative rate. The holder's MWh rate would then be
updated for the next year's billing. Payments for past years would not
be adjusted retroactively.
In another example of a request for conditional approval, an
applicant or presumptive leaseholder might request conditional approval
of a Domestic Content reduction. In this example, a request for
conditional approval may be granted if the proponent demonstrates that
it has firm plans to use items
[[Page 35660]]
qualifying for the preference. Documentation submitted to the BLM when
requesting conditional approval may include procurement contracts or
design documents showing that the facility would qualify for this
reduction. While the BLM may then conditionally approve the request for
a Domestic Content reduction, the reduction would not go into effect
and be used to calculate the proponent's payment obligations until the
proponent submits documentation of actual costs associated with the
construction of the facility, such as fulfilled purchase orders and as-
built design documents demonstrating installation of the qualifying
domestic content items in that facility and the BLM determines, in
writing, that the facility actually qualifies for the reduction. The
holder's MWh rate then would be updated for the next year's billing.
Payments for past years would not be adjusted retroactively.
Paragraph (b)(2) clarifies that ``E'' is the annual adjustment
factor, which is set at three percent. This is the same adjustment
factor used for the annual acreage rent under Sec. 2806.52(a)(1)(iii).
See Sec. 2806.52(a) of this preamble for further discussion on the
annual adjustment factor.
The BLM understands that generally when a solar or wind energy
operator begins generating electricity, it has entered into an
agreement with a utility or other party to sell its power. It is
customary that such agreements include an escalation clause that
increases the purchase price of power each year of the agreement. These
annual escalations vary by agreement; however, in general, the annual
increase is approximately one percent to five percent each year for the
contract term to account for gradual decreases in system operational
efficiency, operating and maintenance costs, and increases in the
retail rate of electricity. There may be some higher annual escalation
rates, but that is not common. The BLM determined that a three percent
annual adjustment factor is a reasonable escalation for the MWh rate
based on a review of the average inflation rate over the previous
fifteen years. The BLM considered both an adjustment for inflation that
is predictable and an adjustment that changes more precisely with
inflation over time. The BLM determined that a set inflationary
adjustment that would alter the starting electricity price per MWh by a
fixed factor each year was preferrable, because it would increase the
predictability of future annual payments. While it is possible that the
market price of electricity will deviate from this fixed rate over
time, the benefit of rate predictability is important to renewable
energy deployment on public lands. Future inflation may be higher than
the historically low inflation of the decade or more prior to 2019. To
accommodate the more recent inflationary trends, the BLM relied on the
IDP-GDP average annual change for the most recent five-year period,
2018-2022 (estimating 2022 with data for three available quarters),
which was 3.36 percent, while taking into account that for the ten-year
period preceding 2018, the rate was 1.52 percent. The BLM derived the 3
percent rate in the final rule by rounding to the nearest whole percent
of the recent inflationary trends.
Some comments requested that the BLM remove the annual adjustment
factor or reduce it, possibly using the prior year's IPD-GDP
calculation as an adjustment factor. These comments noted that the BLM
should be promoting the greatest use of solar and wind energy resources
and maximize commercial interest in development on public lands. Other
commenters suggested a higher annual adjustment factor, noting that
recent inflation amounts are higher than the three percent proposed.
The BLM considered a range of annual adjustment factors, including
those based on IPD-GDP calculations. The BLM's use of three percent
aims to capture a reasonable annual adjustment based on changes over
time. This rule promotes the greatest use of solar and wind energy
resources by applying and offering reductions to the capacity fee for
qualifying developments. Additionally, the BLM's methodology focuses on
rate predictability; making a recurring calculation using the IPD-GDP
is a disincentive for solar or wind development because future rates
change by uncertain amounts making the BLM rates unpredictable. This
final rule does not change the annual adjustment factor due to these
comments.
The regular adjustment factor also provides improved predictability
of rates over time for renewable energy developers compared to the
BLM's previous periodic adjustments of the MWh fee, which were based on
a combination of the annual weighted average wholesale price per MWh
and the adjusted rate of return for certain U.S. Treasury Bonds, both
of which are variable.
Paragraph (b)(3) clarifies that ``F'' is the year of the grant or
lease term, which is the same number used for the annual acreage rent
under Sec. 2806.52(a)(1)(iv). See Sec. 2806.52(a) of this preamble
for further discussion on the year of the grant or lease term.
Paragraph (b)(4) clarifies that ``G'' is the rate of return, which
is set at seven percent. By setting the rate of return in this rule,
the BLM increases the rate predictability of its capacity fee. This
rate of return will not adjust during the term of the authorization. In
this final rule, the rate of return is the relationship of income to
the total value for a granted use of the public land resource. The rate
of return accounts for the value of the authorization each year for use
of the resource on public lands that is provided to the BLM through an
annual payment.
A comment recommended that the BLM recalculate the rate of return
using a 30-year average rate of return for 10-year Treasury Bond rates.
The BLM appreciates the suggested recalculation of the rate of return
over a 30-year period. The BLM selected the 50-year average of the 10-
year Treasury Bond as the reasonable rate to set its rate of return for
this rule. See the BLM's Regulatory Impact Analysis accompanying this
final rule for further information on how the BLM calculated the rate
of return. No changes were made in this final rule due to this comment.
The 50-year simple (i.e., arithmetic) average of the real annual
return on 10-year Treasury Bonds is approximately seven percent. This
50-year period includes times when the United States went through
periods of stagflation, high inflation, economic boom, and relatively
calm market conditions. The BLM's use of the average of the 10-year
Treasury Bond rates is a reasonable reflection of a modest return to
the government reflective of relatively low risk to the public. The
proposed seven percent rate of return is also supported by the Council
of Economic Advisors, which estimates a real return to U.S. capital of
around seven percent from 1960 to 2014 using data from the National
Income Product Accounts and other sources.\13\ By setting the rate of
return in this final rule, it would not be adjusted in the future,
except by further rulemaking.
---------------------------------------------------------------------------
\13\ Council of Economic Advisers Issue Brief, ``Discounting for
Public Policy: Theory and Recent Evidence on the Merits of Updating
the Discount Rate'' (January 2017).
---------------------------------------------------------------------------
One comment suggested that the rate of return stay at two percent
as currently provided in BLM Manual 2806.60. The comment further
suggested that the proposed increase from two to seven percent does not
appear to be reasonable and is inconsistent with the Energy Act of
2020. The updated rate setting
[[Page 35661]]
methodology in this final rule includes an increased rate of return,
consistent with the BLM's authority under FLPMA to collect fair market
value. The change in the rate of return is commensurate with other
sectors of the energy market that base their return on a percentage of
the commodity or energy generation value. It is appropriate that the
rate of return change when transitioning from a capacity fee based on
nameplate capacities to one based on the value of energy generation at
market. The former rate setting methodology (see BLM Manual 2806.60)
implemented the authority of the Energy Act of 2020 by reducing the
rate of return to two percent. In this final rule, the BLM is applying
the authority of the Energy Act of 2020 to the MWh Rate as reductions
under Sec. 2806.52(b) instead of reducing the rate of return. In this
final rule, the BLM has determined that reductions under Sec.
2806.52(b) for solar and wind energy are more meaningful than the
reductions in the Manual 2806.60 and are necessary to promote the
greatest use of solar and wind energy resources on the public lands.
The BLM did not change this section of the final rule in response to
this comment.
Paragraph (b)(5) clarifies that ``H'' is the annual energy
generated on public lands for the right-of-way in question. The BLM
will issue a bill to coincide with the calendar year based on the
annual certified statement provided to the BLM that gives either the
amount of estimated or actual electricity generated by the development.
The payment for the first year of energy generation will be based on an
estimate of energy generation, and then the BLM will determine final
payment for that first year based on actual energy generation. The
following years of payments made in advance, pursuant to 504(g) of
FLPMA, will be based on the most recent calendar year's actual energy
generation reported on the certified statement. Exception to using
actual energy generation is provided for, in certain circumstances,
under paragraph (b)(5)(vi) of this section. Paragraph (vii) addresses
late payments specific to underestimating energy generation in certain
circumstances.
Paragraph (b)(5) has changed from the proposed rule due to public
comments. The BLM proposed to require developers to provide an estimate
for each year of energy generation of a development project to
calculate the payment in advance. Those estimated energy generation
amounts would be updated after that calendar year using actual energy
generation amounts and any over or underpayment would be determined at
that time. Revisions to this paragraph now provide in the following
subparagraphs that:
(i) The holder must submit an annual certified statement to the BLM
before the first year of energy generation begins or is scheduled to
begin. Thereafter, annual certified statements must be submitted by the
end of October.
(ii) Prior to the start of energy generation, the holder must
submit the annual certified statement containing an estimate of energy
generation on the right-of-way (estimate of first year's energy
generation).
(iii) Once energy generation has begun, the holder must submit to
the BLM an annual certified statement of the most recent calendar
year's actual energy generation on the right-of-way.
(iv) The BLM's calculation for payment of the capacity fee will be
based on the certified annual statement. Calculation for payment of the
capacity fee for development projects that contain both public and non-
public lands will be prorated by multiplying the total energy generated
by the percentage of the total development area made up of the right-
of-way footprint on public lands.
(v) If the year's actual energy generation exceeds or is less than
the amount of energy generation used to bill for the payment in
advance, the holder will be billed, credited, or refunded for the
underpayment or overpayments pursuant to Sec. Sec. 2806.13(e) and
2806.16. In no event will the total payment required be less than the
annual acreage rent.
(vi) The BLM may approve a request by a holder to provide a new
estimate of energy generation in certain circumstances. Circumstances
would including those when energy generation is expected to be
interrupted, such as with planned maintenance activities, where the
amount of energy generated is expected to interrupt energy generation
by 25 percent or more, or where the right-of-way holder is aware that
the energy generation in the subsequent year will exceed the actual
energy generation for the previous year by 25 percent or more such that
the BLM's use of the actual generation from the previous year as the
basis for a bill would result in an underestimate of more than 25
percent.
(vii) The BLM may assess a late payment fee of 10 percent of actual
energy generation for the year in which the underestimation occurs. The
holder will pay a late payment fee for each year of underestimation if
the right-of-way holder underestimates energy generation by 25 percent
or more of the actual energy generation or does not provide the BLM
with a new estimate when energy production will exceed the previous
year's actual production by more than 25 percent. The BLM may decide
not to assess the late payment if the right-of-way holder provides an
adequate justification that the underestimation was reasonably
unforeseeable prior to payment of the annual bill, consistent with
Sec. 2805.12(e).
Some comments asserted that penalties for underestimating
generation are inappropriate as factors outside of a developer's
control, such as weather or grid related interruptions, may cause
unexpected generation shortfalls. Additionally, comments noted that
developers have every incentive to maximize production, which may
itself cause a developer to underestimate generation. The BLM has
revised the rule to reduce the potential that a holder would be subject
to a penalty while minimizing the potential for underestimation.
Consistent with other comments related to the term length under 2801.9,
the BLM has made revisions to Sec. 2806.52(b)(5) that are consistent
with revisions made under Sec. Sec. 2805.12(c)(8) and 2807.17(c). The
BLM revised paragraph (vi) and added paragraph (vii) to this final rule
due to comments.
Pursuant to Sec. 2805.12(c)(8), a holder may receive a notice from
the BLM of their noncompliance with the right-of-way and that they are
subject to right-of-way termination. Additionally, the BLM may address
a holder's chronic underestimation through existing Sec. 2807.17(a),
resulting in suspension or termination of the authorization. The BLM
may make such a determination after collecting relevant information,
including information provided pursuant to Sec. 2805.12(a)(15).
Some comments requested that the rule preserve sensitive
competitive information amongst operators of solar and wind energy
development projects. These comments suggested that the BLM could allow
developers to submit generation data based on Form 923, which is
provided to the Energy Information Administration. The final rule does
not carry forward the suggested use of Form 923. The BLM disagrees with
waiting the additional time to collect actual energy generation and
update or validate prior year bill and payments with rights-of-way
holders. As suggested by commenters, using Form 923 would delay billing
for actual energy generation amount by an additional year, which is not
acceptable for the BLM's responsible stewardship of the public lands.
No changes were made due to this comment.
Section 2805.12(c)(8) sets the diligent operation standards for
solar and wind
[[Page 35662]]
energy development projects and provides steps to follow when a holder
expects to fail in meeting diligent operation requirements. Holders may
follow the steps outlined in this section to ensure compliance with
this final rule.
Paragraph (b)(6) of this section describes where you may obtain a
copy of the current MWh rate schedule for solar and wind energy
generation.
Paragraph (b)(7) of this section provides for periodic adjustments
to the MWh rate. This paragraph applies unless you are an existing
holder and elect to continue paying under your current rate adjustment
method per Sec. 2806.51(c).
Paragraph (b)(7)(i) of this section clarifies that the rate from
the MWh rate schedule for the first year of energy generation will not
change once your grant or lease is authorized. The annual adjustment
factor under Sec. 2806.52(b)(1)(i) applies to the MWh rate during the
term of the grant or lease. Any subsequent MWh rate schedule updates
will apply to new grants and leases.
Paragraph (b)(7)(ii) of this section provides that the MWh rate
schedule will be updated once every five years consistent with the
timing of acreage rent adjustments. The MWh rate schedule will include
the annual adjustment factor for the five-year period it covers.
Paragraph (b)(8) of this section provides that the general payment
provisions for rents under Sec. 2806.14(a)(4) also apply to the
capacity fee.
Paragraph (c) applies unless you are an existing grant or
leaseholder and elect to continue with your current MW capacity fee
adjustment method. The fee is set at the time of authorization or re-
issuance and not adjusted further except by the annual adjustment
factor from Sec. 2806.52(b)(2).
Some comments suggested that the BLM should retain discretion under
Sec. 2805.12(e) to adjust rent and fee values, including at the
request of a right-of-way applicant or holder. While section
2805.12(e)(2) of this final rule does not include a mechanism for
applicants or holders to request alternative rent or fee rates in
general, the BLM has revised Sec. 2806.52(b)(1)(i) to identify
circumstances where the BLM would have discretion to select an
alternative MWh rate.
Some comments suggested a wide range of potential fee structures to
address environmental and economic factors. Some comments also
requested that the BLM clarify how the rents and fee numbers were
developed. The BLM's development of the acreage rent and capacity fee
was an iterative process that included consideration of the BLM's legal
authority; taxpayer concerns for the collection of reasonable rent for
the use of public lands and resources; the BLM's prior policies for
rents and fees and their impact to solar and wind deployment on public
lands; and the national renewable energy goals on public lands set in
section 3004 of the Energy Act of 2020. The BLM initially solicited
comments in September 2021 after which the BLM published interim
guidance in Manual section 2806.60--Rent.
Some comments requested a publication or annual report from the BLM
on the payments it has received from solar and wind energy development
projects. This information can be found in the BLM's annual publication
of Public Land Statistics, which enumerates annual revenues from energy
resources including wind and solar rents and fees.
Some comments requested that the BLM provide fee reductions for
projects that are sited on previously disturbed lands or outside of
sensitive wildlife habitats. The BLM contemplated various methods and
models by which to potentially apply rate reductions in this final
rule. Additional information on the alternatives considered may be seen
in the proposed rule's preamble discussion under subpart 2806. The BLM
determined that an across-the-board reduction best meets national
energy goals. This methodology provides flexibility and financial
incentives without regard to where projects may be sited. Having
reduced rent and fee rates that are independent of location complements
the BLM's ability to update land use planning, which defines where
project applications may be proposed and where projects will not become
obsolete if or when technology advances and siting needs shift for
economic or environmental reasons.
One comment suggested that a holder should be able to select
whether they wish to pay an acreage rent or capacity fee. The BLM
disagrees with this comment. This final rule clearly provides for both
an acreage rent or a capacity fee for solar and wind energy development
projects. Generally, the acreage rent is required for the intensity of
use and the occupancy, including site control, of the surface of the
public lands. The capacity fee reflects the value of the energy
generated from the solar or wind energy resource located on public
lands. The BLM will collect the greater of either the acreage rent or
the capacity fee for a solar or wind energy development.
One comment suggested rate reductions be made available for
existing right-of-way holders who enter into new PPAs for a project
during the term of an authorization, such as when they repower. This
final rule provides for greatly increased rate predictability for solar
and wind energy development rights-of-way. Under Sec. 2806.52(b)(v),
the BLM provides an opportunity for conditionally approving a reduction
if it receives a request with sufficient documentation demonstrating
that the holder may qualify for the reduction before the BLM issues the
right-of-way. No other opportunity for later qualifying for a reduction
is made available in this rule as the reductions to its rates are
available prior to the BLM issuing the ROW. The BLM believes that the
adjustments to improve rate predictability, including allowing for a
longer term (see Sec. 2801.9) for certain rights-of-way, will provide
for the longer economical life of a particular project. An operator or
a holder of an existing authorization may elect to keep their current
rate methodology, including future adjustments that may be made, if
they do not wish to change to the rate-setting methodology of this
final rule.
Some comments suggested that the 80 percent reduction of capacity
fees without any qualifying stipulations will adversely distort the
energy market and land uses. The BLM does not expect this final rule to
alter the solar or wind energy markets or uses of public lands
adversely. This final rule implements the authority of the Energy Act
of 2020 and direction of Executive Order 14008, among others, that set
goals to promote the greatest use of solar and wind energy resources on
public lands. The rule is intended to incentivize development of wind
and solar energy projects on BLM-managed lands. The BLM sees any
resulting change that benefits solar or wind in energy markets as a
positive development. See Reductions and Discounts under 5.1 of the
Regulatory Impact Analysis for further information on the 80 percent
reduction and the economic impacts of the rule.
Some comments suggested that the BLM should collect fair market
value for the use of federal lands under the BLM's rule. While FLPMA
generally requires the BLM to collect the fair market value for the use
of the public lands, the Energy Act of 2020 provides the Secretary of
the Interior with additional authority to reduce acreage rents and
capacity fees, including to less than fair market value in certain
circumstances. The BLM is implementing this authority to reduce the
financial burden to solar
[[Page 35663]]
and wind energy developers to promote the national interest of
developing a clean energy economy.
Section 2806.54 Energy Storage Facilities That are Not Part of a Solar
or Wind Energy Development
Section 2806.54 clarifies that the rent the BLM determines for an
energy storage facility that is not part of a solar or wind energy
development facility is based on the linear rent schedule. Energy
storage facilities may be authorized separately from a solar or wind
energy development facility. In these instances, the BLM will apply the
linear rent schedule unless the BLM determines that the linear rent
schedule does not apply to the underlying right-of-way use under Sec.
2806.70, such as when the BLM may determine that a small site rent
schedule applies to an energy storage facility.
The BLM will not charge the rent or fee of a solar or wind energy
development right-of-way for an energy storage facility that is
separate and independent from a right-of-way for an energy generation
facility. Charging a capacity fee would be inappropriate as no energy
generation from the facility would be occurring from the use of public
lands. Using the pastureland rents for energy storage would also be
inappropriate, as use of those acreage rates is intended to be coupled
with the capacity fee to determine solar and wind energy generation
payments for use of public lands.
Sections 2806.60 through 2806.68 are removed from the final rule.
Information formerly contained in these sections is now found in
sections 2806.50 through 2806.58.
Subpart 2807--Grant Administration and Operation
Section 2807.17 Under what conditions may BLM suspend or terminate my
grant?
Section 2807.17 of this final rule is updated based upon comments
on Sec. 2801.9 regarding term length and updates to Sec. 2805.12
regarding new diligent operation requirements for solar and wind energy
development. See the respective sections of this preamble for further
information on the term length and the terms and conditions of grants
and leases for solar and wind energy.
Section 2807.17(c) provides that the BLM may suspend or terminate a
right-of-way upon abandonment. The BLM presumes that a right-of-way
holder has abandoned its right-of-way by failing to use it for a
continuous 5-year period, except for solar and wind energy. Solar and
wind energy rights-of-way are presumed to be abandoned after two
continuous years of insufficient productivity or upon abandonment. This
section is updated consistent with the new provision in Sec.
2805.12(c)(8), which provides for a holder to receive notice of the
BLM's presumption and gives a reasonable time to cure the noncompliance
with the diligent operations requirement.
Section 2807.20 When must I amend my application, seek an amendment of
my grant or lease, or obtain a new grant or lease?
Section 2807.20 describes when a right-of-way applicant must seek
to amend its application, grant, or lease.
Paragraph (b) clarifies that ``except for qualifying energy
development grants and leases per Sec. 2806.51(c),'' the requirements
for amending an application or grant are the same as processing a new
application, including payment of processing and monitoring cost
recovery fees. Section 2806.51(c) provides a unique exception for
existing solar and wind energy rights-of-way authorized before this
final rule that may convert to the rent adjustment methodology of this
final rule. See Sec. 2806.51(c) of this preamble for further
information on qualifying authorizations.
Paragraph (f) describes how the BLM would administer an approved
solar and wind energy grant or lease if the holder requests to change
the rent adjustment methodology. Any request would have to be received
within 2 years of the date this rule becomes effective and would be
processed as an amendment by which the BLM would re-issue the grant or
lease and update the terms and conditions under Sec. 2805.12 and rent
provisions under Sec. Sec. 2806.50 through 2806.52. The BLM would be
able to collect or use processing and monitoring costs under Sec. Sec.
2804.14 and 2805.16 for handling the request. See Sec. 2806.51(c) for
further discussion regarding requests to use the rent adjustment
methodology of this rule.
One comment suggested that State and local governments should have
a shared decision-making role with the BLM when the BLM considers re-
issuing a grant or lease to convert the right-of-way over to the new
rate adjustment methodology. The BLM does not agree with the suggestion
that State or local government offices should share in a decision-
making role when the BLM decides whether to authorize a change to the
rent adjustment methodology. Re-issuing an authorization under this
final rule is an administrative action that will convert existing
authorized projects to the new rate setting methodology for the use of
BLM-administered public lands and resources. The BLM will continue to
engage with the public, and Tribal, Federal, State and local government
partners on the BLM's management of its public lands, as appropriate.
The BLM did not change this section of the final rule.
Section 2807.21 May I assign or make other changes to my grant or
lease?
Section 2807.21 describes the requirements for a holder seeking to
assign or make other changes to a grant or lease.
Paragraph (e) clarifies that when the BLM assigns a right-of-way
from one holder to another, it may modify a grant or lease, such as by
adding additional terms and conditions. The paragraph exempts solar and
wind energy leases from that provision unless modifications are
warranted under Sec. 2805.15(e), which provides for changes to terms
and conditions as a result of changes in legislation, regulation, or as
otherwise necessary to protect the public health or safety or the
environment. This final rule removes provisions that distinguished
between inside and outside DLAs for solar and wind energy development.
The BLM may assign leases inside of DLAs without competition.
One comment suggested that the BLM should retain the authority to
impose additional requirements on solar and wind projects. The
commenter expressed concern that the BLM may be constrained when it
comes to regulating a bad operator especially with regards to excepting
a bond requirement and that bond requirements should be mandatory on
solar and wind projects, so the BLM does not have to clean up sites
after company closure or refusal to perform reclamation. The BLM
requires a bond for all solar and wind energy grants and leases. The
BLM requires this bonding upfront to cover reclamation costs and to
enforce the terms and conditions, such as those for rent and capacity
fees. Paragraph (e) provides that the BLM, when assigning a grant or
lease to a new holder, may modify the right-of-way and add bonding and
other requirements, including additional terms and conditions, except
for wind and solar leases which the BLM can only modify when warranted
as a result of changes in legislation, regulation, or as otherwise
necessary to protect public health or safety or the environment as
reflected in Sec. 2805.15(e). The BLM also has diligent development
and operation requirements, among other terms and conditions, in Sec.
2805.12 that further ensure a holders' compliance with the
[[Page 35664]]
right-of-way authorization and all its requirements. The BLM did not
change this section of the final rule.
Subpart 2809--Competitive Process for Solar and Wind Energy Development
Applications or Leases
Subpart 2809, ``Competitive Process for Leasing Lands for Solar and
Wind Energy Development Inside Designated Leasing Areas'' is dedicated
to competitive solar and wind energy processes. In the final rule,
Subpart 2809 generally applies the same competitive process both within
and outside DLAs.
Section 2809.10 Competitive Process for Energy Development Grants and
Leases
Section 2809.10, ``Competitive process for energy development
grants and leases,'' applies to public lands located both inside and
outside of DLAs. Paragraphs (a) through (d) explain that the BLM may
conduct a competitive process to consider solar or wind energy
development applications or leases: (1) on its own initiative; (2)
based on responses to a call for nominations; (3) based on a request
submitted by a member of the public in writing; or (4) when it receives
two or more competing applications. These provisions incorporate the
BLM's broad discretion under FLPMA to determine under what
circumstances it may utilize a competitive process. This section is
revised to replace ``offer'' with ``process'' to remain consistent with
this section's requirements for solar and wind energy development grant
and leases competitive process.
The BLM has determined that it will implement its discretion under
FLPMA to potentially utilize a competitive process for lands both
inside and outside of DLAs and thus standardize a competitive process
where competitive interest exists. More specifically, the BLM will use
the most appropriate process given the circumstances of a particular
location, spurring more competition for the most desirable areas, while
continuing to increase solar and wind energy deployment consistent with
the statutory direction in the Energy Act of 2020.
As proposed, prior paragraph (d) is removed consistent with changes
made under Sec. 2804.35(b) and elsewhere in subpart 2809. The BLM has
discretion to process applications inside DLAs without going through a
competitive process. Accepting applications inside DLAs reduces
timelines and costs and removes barriers for considering development
projects where there is no competitive interest.
Proposed Sec. 2809.10(e) would have precluded the BLM from holding
a competitive process when the BLM has accepted a complete application,
received a Plan of Development, entered into a cost recovery agreement,
and published an EA or Draft EIS. Industry comments suggested that the
BLM commit to not holding a competitive process earlier than in the
proposed rule. In response to those comments, the final rule
establishes that the BLM will not initiate a competitive process for
those lands where the BLM has accepted a completed application,
received a Plan of Development, and entered into a cost recovery
agreement, while removing the requirement that the BLM must have
published an EA or a draft EIS.
The final rule also adds to Sec. 2809.10(e) an exception
referencing Sec. 2804.25(c). Even where the BLM has accepted a
complete application, received a Plan of Development, and entered into
a cost recovery agreement, it may nonetheless offer lands in a
competitive process if the applicant has not proceeded diligently as
required by Sec. 2804.25(c). These amendments give the industry the
certainty it needs to proceed with projects while retaining the BLM's
discretion to deny an application or offer lands competitively if the
applicant does not proceed diligently. In that way, these amendments
balance the BLM's obligations to incentivize renewable energy
development on public lands and to recover a fair return for U.S.
taxpayers.
Some comments suggested that requiring a competitive leasing
process in designated leasing areas has helped ensure that only well-
thought-out projects are proposed. These commenters raised concerns
that eliminating a required competitive process will cause a rush of
poorly planned projects and will decrease use of the designated leasing
areas. Several comments argued in favor of requiring a competitive
process in designated areas, emphasizing that it shifts the burden from
taxpayers to those who stand to profit, validates demand, increases
financial return for use of public lands, drives innovation, and
ensures transparency and fairness in the process. These comments
expressed concerns that non-competitive leasing may discourage
investment and lead to inefficiencies.
In this final rule, the BLM's change in the use of competitive
processes is intended to provide flexibility in addressing interest in
the use of public lands for solar and wind energy and will not allow
for or authorize poorly planned projects. The BLM retains its
discretion to authorize or deny solar or wind energy development
projects. As explained in the preamble to the proposed rule, the
requirement to undertake competitive processes for all applications in
DLA's extends the timeline and increases costs, creating a barrier for
authorizing projects in areas where there is no competitive interest.
The BLM has broad discretion under FLPMA to determine under what
circumstances it may utilize a competitive process for lands both
inside and outside of DLAs and to use competitive processes only where
competitive interest exists. The BLM anticipates that accepting
applications in DLAs without the prerequisite of holding a competitive
process will likely generate more applications in the most desirable
locations. The final rule also provides the BLM with the flexibility to
utilize a competitive process where there are multiple competing
applications. The purpose of these changes is to ensure that the BLM
can use the most appropriate process given the circumstances of a
particular location, which the BLM believes will spur more competition
for the most desirable areas, while continuing to increase solar and
wind energy deployment consistent with the statutory direction in the
Energy Act of 2020.
For the same reasons, the BLM disagrees with the comments that
focusing the BLM's competitive process and resources to where there is
competitive interest on public lands is a negative impact to taxpayers,
demand, financial return, innovation, and transparency. This final rule
improves transparency over all processes of the BLM's administration of
applications and right-of-way authorizations and achieves the goals set
by the Energy Act of 2020 and direction of Executive Order 14008.
Moreover, although DLAs represent areas specifically designated for
renewable energy development, they are not the only areas where such
development may be appropriate, nor are they the only areas where use
of a competitive process may be appropriate. These projects are complex
and require many different steps and actions to occur to be successful.
The BLM believes offering areas outside of DLAs for a competitive
process is appropriate and would help to meet the goals of the Energy
Act of 2020 and direction of Executive Order 14008.
Some comments suggested leasing should not be competitive, or at
least only be considered in specific circumstances, such as when
multiple applications for the same area are
[[Page 35665]]
submitted or when certain conditions are met, such as when labor
agreements are not used. This section of the final rule clarifies when
the BLM may conduct a competitive process, including for competing
applications under paragraph (d). The BLM disagrees that attaining an
agreement to use certain labor should determine whether the BLM holds a
competitive process or not. The BLM's discretion to hold a competitive
process includes when there is competitive interest for that system or
land or upon the BLM's own initiative, among other reasons identified
in this section of the rule.
Some comments highlighted the interest in a clear and standardized
process and suggested that the potential for competition should be
limited to avoid deterring investment. In this final rule, the BLM has
provided a clear process that the BLM will follow for solar and wind
energy development projects when a competitive process is held.
However, the BLM does not agree with comments to limit competition. The
BLM will generally hold a competitive process where there is a
competitive interest, whether it is inside or outside of designated
leasing areas, or on its own initiative.
Other comments recommended adding steps to ensure no competition
exists before processing applications without a competitive process.
Suggestions given to the BLM include filing a notice in the local
newspaper, online, or in the Federal Register whenever the BLM receives
an application requesting any other applications to be submitted. This
final rule does not include provisions to require solicitation of
public interest with every application submitted to the BLM for a solar
or wind energy development. The Energy Act of 2020 and direction of
Executive Order 14008 are clear in seeking expedited deployment of
renewable energy projects on public lands. Adding provisions in the
BLM's rules that require additional steps to solicit competitive
interest where there may not be any may slow the deployment of
renewable energy. Historically, the majority of solar and wind rights-
of-way authorized on BLM-administered public lands have been authorized
after an application process without a competitive process, and there
are only six existing competitively issued leases, which is only
approximately six percent of authorized development projects on public
lands. You may find information on the BLM's authorized and pending
solar and wind energy projects on its website at: https://www.blm.gov/programs/energy-and-minerals/renewable-energy/active-renewable-projects. More specifically, since the BLM began using competitive
processes for permitting solar leases on BLM public lands, the agency
has held five competitive processes for 16 parcels. These have resulted
in multiple bids for nine parcels, a single bid for three parcels, and
no bids for four parcels. In the circumstances that BLM held a
competitive process and received no bids, the BLM had previously
received several expressions of interest and applications for those
public lands. The BLM then held a competitive auction resulting in no
bids for three parcels. The BLM did not change this section of the
final rule.
A comment requested that the final rule clarify when the BLM will
not require an auction. The BLM does not believe additional
clarification is necessary, as Sec. 2809.10(e) provides that the BLM
would not offer lands through a competitive process when the BLM has
accepted a completed application, received a Plan of Development, and
entered into a cost recovery agreement.
One comment suggested that the final rule clarify that the BLM
should be precluded from using a competitive process to award a solar
or wind energy development lease or grant on an area of public lands
once an applicant has either submitted a right-of-way application for
solar or wind energy development or made substantial investments in
potentially developing that area of the public lands. While the
proposed rule provided that BLM would not offer lands in a competitive
process if four criteria were met, this final rule removes the fourth
proposed criterion in section (e): ``on publication of an Environmental
Assessment or Draft Environmental Statement.'' The final rule retains
the first three, such that the BLM would not offer lands in a
competitive process for which it has accepted a complete application
(see Sec. 2804.12(j)), received a Plan of Development (see Sec.
2804.12(b)), and entered into a cost recovery agreement (see Sec.
2804.14). This change requires fewer milestones to close the window for
holding a competitive process than the proposed rule and improves
certainty for interested developers to proceed with applications but it
does not move the threshold for prohibiting competitive processes
earlier than in the existing regulations as the commenter suggested.
In addition to the changes under 2809.10(e), the BLM revised Sec.
2804.25(c) to clarify that the BLM retains discretion to deny an
application where the applicant does not proceed diligently. An
applicant's failure to remain diligent in processing an application may
result in the BLM denying the application and offering the lands
competitively. These amendments balance the BLM's obligations to
incentivize renewable energy development on public lands and to recover
a fair return for U.S. taxpayers.
A comment suggested that the BLM should not require a competitive
process where an applicant's facilities are located on both private and
federal lands and the applicant has secured agreements with the
adjacent landowners. This final rule governs the BLM's administration
of applications and authorizations, including competitive processes.
The BLM will consider all relevant and available information when
determining whether a competitive process is appropriate, including
whether separate agreements had already been met for adjacent lands.
However, this rule does not preclude the BLM from holding a competitive
process when agreements are held for adjacent lands, which would allow
developers and adjacent landholders to effectively monopolize the use
of the public lands without first obtaining authorization from the BLM.
In instances where the BLM believes it is appropriate, it may determine
to hold a competitive process.
Other commenters suggested that the BLM should only have the
discretion to move to a competitive process in the initiation phase of
a project and not after an application is complete and the cost
recovery is funded. This final rule maintains the BLM's discretion to
determine whether there is a competitive interest in the public lands.
In the BLM's experience, some applications progress more slowly than
others once the existing requirements of the BLM rules are met. By
requiring a complete application pursuant to Sec. 2804.12(j), a Plan
of Development pursuant to Sec. 2804.12(b), and a cost recovery
agreement pursuant to Sec. 2804.14, the BLM will help ensure that
applicants remain diligent in pursuing their use of the public lands,
while preserving discretion to utilize a competitive process. Even
after that point, Sec. 2804.25(c) of the final rule clarifies that the
BLM retains discretion to deny an application where the applicant does
not proceed diligently. These additional conditions will not
unreasonably burden diligent applicants and will help identify those
applicants who are not working with the BLM to process applications
diligently.
[[Page 35666]]
Section 2809.11 How will the BLM call for nominations?
Section 2809.11 is retitled to improve consistency with this
section of the final rule. No changes were made to this section due to
comments. Consistent with the change in terminology of Sec. 2809.10,
the BLM changed ``offer'' with ``process'' throughout this section.
Paragraph (a) provides that the BLM may publish a notice in the
Federal Register calling for nominations of lands to be offered through
a competitive process for solar and wind energy development. Other
notification methods may also be used, such as a newspaper of general
circulation in the affected area or the internet. The section allows
for the BLM's discretionary use of a competitive process discussed in
Sec. 2809.10. The paragraph would also specify information that will
be included in a call for nominations as follows:
(1) The date, time, and location by which nominations must be
submitted;
(2) The date by which nominators will be notified of the BLM's
decision on timely submissions;
(3) The area or areas for which nominations are being requested;
and
(4) The qualification for a nominator, which must include at a
minimum the requirements for an applicant, see Sec. 2803.10.
Paragraph (b) provides the requirements for nominating a parcel of
land for a competitive process. Paragraph (b)(1) requires payment of $5
per acre for nominated parcels. The nomination fee is collected by the
BLM under its cost recovery authority under Sections 304(b) and 504(g)
of FLPMA, and the portion not spent in processing the nomination and
preparing for a competitive process may be refunded to the nominator if
not successful in the competitive process. These fees reimburse the BLM
for the expense of preparing and holding a competitive process.
Paragraph (b)(2) requires the nomination to include the nominator's
name and address of record. This information is necessary for the BLM
to communicate with the nominator about a future competitive process
for the parcel.
Paragraph (b)(3) requires that a nomination be accompanied by a
legal land description and a map of the parcel of land. This
information helps identify nominated parcels for the competitive
process.
Paragraph (c) provides that the BLM will not accept nomination
submissions that do not comply with this section or from submitters who
are not qualified per Sec. 2803.10 to hold a grant or lease.
Paragraph (d) provides that a nomination cannot be withdrawn except
by the BLM for cause, in which case the nomination fee would be
refunded.
Paragraph (e) provides that the decision whether to hold a
competitive process in response to a nomination lies in the BLM's
discretion.
Some comments requested that the BLM make the nomination fee non-
refundable. One comment further suggested that the BLM require ``skin
in the game'' from project proponents and that the BLM should keep the
fee to cover at least any reasonable costs it incurred in pursuing the
nomination. The BLM agrees with comments suggesting that the fee should
be used in recovering its reasonable costs in processing the nomination
and preparing for a competitive process. The BLM's authority under
Sections 304(b) and 504(g) of FLPMA allows for the use of these funds
in processing applications. Per existing rules, the BLM may refund the
balance, if any, of collected cost recovery funds when they are no
longer needed. Please see existing subpart 2804, starting with Sec.
2804.14, for more information on the BLM's administration of cost
recovery fees.
Section 2809.12 How will the BLM select and prepare parcels?
Section 2809.12 describes how the BLM identifies parcels suitable
for competitive processes. The BLM did not make changes to this section
of the final rule in response to comments received, except that,
consistent with the change in terminology of prior sections, the BLM
changed ``offer'' to ``process'' throughout this section. The BLM also
removed ``on existing'' when describing land use designations to avoid
confusion and clarify that only existing land use designations may be
considered.
Paragraph (a) clarifies that the BLM may rely on any information it
deems relevant in identifying parcels for competitive processes, but
also describes more precisely the most common sources of information,
which include public nominations and existing land use designations.
The BLM is not constrained to consider only these listed sources of
information when deciding whether to conduct competitive processes for
certain parcels.
Paragraph (b) clarifies that the BLM may conduct necessary studies
and site evaluation work, including applicable environmental reviews
and public meetings, either before or after offering lands for a
competitive process. The BLM has sometimes found that the necessary
studies and site evaluation work cannot be completed until the
competitive process is held and the successful bidder has submitted an
application or Plan of Development. The BLM must complete site-specific
NEPA analysis even when the BLM has identified a successful bidder as
the presumptive leaseholder. The BLM retains discretion to approve,
approve with modification, or deny a proposed energy development.
The BLM revised the language of proposed paragraph (c) to clarify
that it is the BLM's choice whether to use a competitive process or not
and that such choices do not constitute a decision to approve or deny a
grant or lease and are not subject to appeal under 43 CFR part 4.
A comment suggested that under paragraph (c), the final rule should
allow for administrative appeals, as it relates to BLM procedures used
to make decisions. Paragraph (c) of the final rule clarifies that the
BLM's choice about whether to use a competitive process is not a
decision to grant or deny a right-of-way or otherwise final agency
action; instead it represents only an intermediate step that may or may
not lead to a decision. The public's ability to administratively appeal
an agency decision to grant or deny a right-of-way is unaffected by
this provision. The BLM will continue to provide ample opportunities to
the public for engagement throughout both the competitive and non-
competitive permitting processes. An appeal may be considered when the
BLM issues a decision under 43 CFR part 2800.
A comment suggested that allowing for an administrative appeal
process to challenge a BLM choice to use a non-competitive process
would assist the BLM in identifying whether there is any competitive
interest in the public land, getting a better return for the public.
The BLM disagrees with this comment. Administrative appeals may be
submitted only for agency decisions (see existing Sec. 2801.10).
Additionally, allowing for administrative appeals over interim choices
by the BLM about which procedures to follow to reach a decision would
likely delay its decision-making process substantially.
Section 2809.13 How will the BLM conduct competitive processes?
Section 2809.13 is retitled from the proposed rule consistent with
other changes to replace ``offer'' with ``process.'' The change from
the proposed rule to read ``process'' when describing the BLM's
competitive process is made throughout this section when appropriate.
This section describes how the BLM conducts competitive processes.
[[Page 35667]]
Paragraph (b) provides that the BLM publishes a notice of competitive
process in the Federal Register and through other notification methods,
such as a newspaper of general circulation in the area affected or the
internet. Paragraph (b)(7) clarifies that the notice of competitive
process would state whether a successful bidder would become a
preferred applicant or a presumptive leaseholder. Preferred applicants
are required to meet application submission requirements under Sec.
2804.12, and presumptive leaseholders are required to submit a Plan of
Development per Sec. 2809.18. The preferred applicants and presumptive
leaseholders are discussed further in Sec. 2809.15.
Under paragraph (c) of this final rule, the BLM will notify
nominators of its decision to conduct a competitive process at least 30
days in advance of the bidding for the lands that were nominated if the
nominator has paid the nomination fees and demonstrated qualifications
to hold a grant or lease.
Some comments suggested that under paragraph (b)(7) the BLM should
continue to require a successful bidder to submit a Plan of
Development. The BLM agrees with these comments. A Plan of Development
is required in this final rule by a presumptive leaseholder under
paragraph 2809.15(a)(ii) and by a preferred applicant who would follow
the application process for solar and wind energy applications,
including the submission of a Plan of Development required under Sec.
2804.25(c).
Section 2809.15 How will the BLM select the successful bidder?
Section 2809.15 explains how the successful bidder is selected. In
this final rule, the distinction between preferred applicants and
presumptive leaseholders reflects the fact that the BLM may conduct
competitive processes in a variety of circumstances with different
outcomes. The distinction between presumptive leaseholder and preferred
applicant is intended to ensure that the BLM can expedite approval of
proposed projects in areas where the environmental impacts of solar and
wind energy development have been previously analyzed and disclosed
through a land use planning process. This will help ensure that the BLM
does not commit public land resources before completing the necessary
analyses. This section is also revised, consistent with other changes
in this rule, to refer to ``process'' where appropriate when describing
the BLM's competitive process.
Paragraph (a) of this final rule provides that the highest bidder,
prior to any variable offsets, is the successful bidder. Successful
bidders may become either the presumptive leaseholder or the preferred
applicant.
The term ``presumptive leaseholder'' describes situations in which
at least one round of environmental review for solar or wind energy
development has been conducted before the competitive process is held,
so that the environmental impacts of potential development are
relatively well understood before the competitive process is held and
the successful bidder has a high likelihood of being able to obtain an
authorization to develop its proposed project. As set forth in
paragraph (b)(1)(i), a successful bidder would only be designated as a
presumptive leaseholder if the lands for which the competitive process
is held are located within a DLA and the BLM has indicated in advance
that the successful bidder would become a presumptive leaseholder (see
also Sec. 2809.13(b)(7)). These requirements would limit the use of
the term ``presumptive leaseholder'' to situations in which the BLM has
previously completed an environmental analysis for solar or wind energy
development in the area through the land use planning process and has
specified in advance (through the notice of competitive process) many
of the terms, conditions, and mitigation measures that would need to be
incorporated into an approved authorization. A presumptive leaseholder
does not have to complete the initial application review stage, which
is designed to ensure that the site is generally appropriate for solar
or wind energy development. A presumptive leaseholder has site control
for a solar or wind energy development, precluding other competing
solar or wind energy development projects from siting on that land,
unless allowed by the presumptive leaseholder. The BLM would also not
process other applications for use of that land unless allowed by the
presumptive leaseholder.
This final rule also recognizes that even with a presumptive
leaseholder, an additional site-specific environmental analysis may be
required before the BLM irretrievably commits to allowing a facility to
be developed. The BLM retains its full discretion in considering
whether to approve a presumptive leaseholder's proposal based on site-
specific environmental analysis, which would typically be tiered to the
area-wide environmental analysis accompanying the identification of the
area as a DLA. Paragraph (b)(1)(ii) therefore notes that the
presumptive leaseholder's right to develop a project on the site is
contingent upon the BLM's approval of the presumptive leaseholder's
Plan of Development. Once the BLM approves the proposed Plan of
Development, following a site-specific environmental analysis, a lease
could be awarded, conferring a right to develop a project on the site,
and the presumptive leaseholder would become a leaseholder.
In other cases, the BLM could conduct a competitive process without
having completed an initial environmental analysis for solar or wind
energy development for that area. In such cases, as set forth in
paragraph (b)(2), the successful bidder would become the ``preferred
applicant'' and would obtain only the exclusive right to submit an
application for solar or wind energy development on that site without
further competition from other applicants for solar or wind energy
development. Such an application would be processed under subpart 2804
in the same manner as other, non-competitive applications. The BLM
would conduct a full environmental analysis before the preferred
applicant may obtain a grant and the right to develop a project on the
site. A preferred applicant that fails to meet the requirements of
subpart 2804 may lose their status as the preferred applicant, and the
BLM may deny their application consistent with Sec. 2804.26.
Paragraph (b) provides that a successful bidder becomes a
presumptive leaseholder or preferred applicant only after making
payments required in paragraph (d) of this section and satisfying the
requirements for holding a grant or lease under Sec. 2803.10. The BLM
could move on to the next highest bidder or re-offer the lands under
Sec. 2809.17 if the successful bidder does not satisfy these
requirements.
Paragraph (b)(1) describes the requirements to become a presumptive
leaseholder, which are that the public lands successfully bid upon are
located within a DLA and that the notice of competitive process
indicated successful bidders would become presumptive leaseholders.
This paragraph also provides that the BLM would only award a
presumptive leaseholder a lease if the BLM approves the Plan of
Development that is submitted in accordance with Sec. 2804.25(c).
Paragraph (b)(2) describes the requirements for a preferred
applicant. A successful bidder who does not become a presumptive
leaseholder in accordance with paragraph (b)(1) would become a
preferred applicant. The BLM would process applications for a grant or
lease under Sec. 2809.12. As with presumptive leaseholders, approval
of a
[[Page 35668]]
preferred applicant's application is not guaranteed. However, the BLM
would not process other applications for solar and wind energy
development on lands where a preferred applicant has been identified,
unless allowed by the preferred applicant.
The BLM may consider issuing authorizations for other uses, such as
roadways, testing facilities, recreation permits, or even rights-of-way
under MLA authority on the lands for which there is a preferred
applicant. Processing authorizations for other uses under Title V of
FLPMA would be performed under subpart 2804. Recreation permits and
rights-of-way under MLA authority would be processed under parts 2920
and 2880, respectively. In some instances, such as with applications
for incompatible uses, the BLM may determine that the proposed uses
would be incompatible, and therefore that processing these other
applications must wait until it issues a decision on a preferred
applicant's application for solar or wind energy development.
Previous paragraphs (b) and (c) are redesignated as (c) and (d)
respectively. Redesignated paragraph (c) is not revised; it provides
that the BLM will determine variable offsets for the successful bidder
in accordance with Sec. 2809.16.
Redesignated paragraph (d) provides for bidder payment terms.
Paragraph (d)(1) provides for certain payment methods, such as personal
check, cashier's check, certified check, bank draft, or money order, as
well as other methods deemed acceptable by the BLM, should be paid to
the Department of the Interior--Bureau of Land Management.
Paragraph (d)(2) requires payment of 20 percent of the bonus bid
and the minimum bid amount by the close of official business hours on
the day on which the BLM conducts the competitive process or other time
the BLM has specified in its notice.
Paragraph (d)(3) requires payment of the balance of the bonus bid
within 15 days after the day on which the BLM conducts the competitive
process. Variable offsets are applied under paragraph (c) of this
section. Such payments are made to the BLM office conducting the
competitive process.
Paragraph (d)(4) requires payment within 15 days after the day on
which the BLM conducts the competitive process to pay: for preferred
applicants, the application filing fee under Sec. 2804.12(c) less any
application fee already paid under Sec. 2809.11(c)(1); or for
presumptive leaseholders, the acreage rent for the first full year of
the lease as provided in subpart 2806.
Paragraph (d)(5) clarifies that the BLM may require successful
bidders to pay reasonable costs in addition to the application filing
fee when processing an application. Additional reasonable costs may
include a Category 6 cost recovery for the BLM to complete processing
the application. If a Category 6 cost recovery fee is required, it will
be reduced by the amount of the application filing fee already paid.
See Sec. 2804.19 of existing regulations for further information on
Category 6 cost recovery.
Paragraph (e) explains that the successful bidder will not become a
preferred applicant or a presumptive leaseholder and the BLM will keep
all money that has been submitted with the competitive process if the
successful bidder does not satisfy the payment terms under paragraph
(d) of this section. In such a case, the BLM could proceed to the next
highest bidder or re-offer the lands through a competitive process
under Sec. 2809.17.
A comment questioned the rationale behind determining the highest
bidder as the presumptive leaseholder instead of the BLM making an
offer to the highest bidder. The commenter suggested that the BLM would
then offer the lease to subsequent bidders if the preceding highest
bidder declines. The BLM's competitive process in this final rule
informs prospective bidders what they would be bidding for in advance
of a competitive process. The BLM's required process under this final
rule provides important information to prospective bidders up front,
reducing uncertainty on what they may bid on. Prospective bidders will
be able to bid more confidently with that information. This will also
likely result in more and higher bids than would be received if the BLM
provided such information after a competitive process and will reduce
the need for the BLM to engage the second highest bidder should the
highest bidder decline.
The BLM understands from a comment that there may have been some
confusion on how the rule distinguishes between holding a competitive
process and selecting a presumptive leaseholder or preferred applicant.
In this final rule, Sec. 2809.15(b) makes clear that both of the
following criteria must be met to be a presumptive leaseholder: first,
lands offered must be located within a DLA, and second, the notice of
competitive process must indicate that bidders are bidding to become a
presumptive leaseholder. The requirement that the lands be within a DLA
is important because DLAs, by definition, have been subject to prior
environmental analysis and a land use plan decision to designate the
area for solar or wind energy leasing. The environmental analysis would
have identified potential conflicts and assessed the environmental
impacts of siting a solar or wind energy generation facility, and
through the land use planning process the BLM would have determined any
necessary mitigation measures prior to the BLM offering the site for
leasing. The requirement that the notice of competitive process must
indicate that bidders are bidding to become a presumptive leaseholder,
meanwhile, is important because it ensures that the terms and
consequences of the competitive process are clear to all parties before
the bidding occurs, and because it retains the BLM's discretion to
conduct a competitive process for a preferred applicant, rather than a
presumptive leaseholder, even within a DLA.
Some comments expressed concern that the BLM continues to determine
that processing of applications for ``incompatible'' uses must wait
until it issues a decision for a first-in-line solar or wind energy
development and believe this violates the intent of FLPMA. Commenters
believed the language of the rule is unclear about whether these other
applications are from other applicants for a similar right-of-way or
whether it would apply to applications for other land uses. These
commenters assert that either scenario is inconsistent with FLPMA's
multiple-use mandate.
In this portion of the rule, the BLM's presumption is that the BLM
has already identified a ``preferred applicant'' or that the lands have
already been identified in the BLM's land use planning process as a
DLA. The FLPMA gives BLM discretion as to how it will process
applications, including competing ones for the same parcel. This does
not violate FLPMA's multiple-use mandate.
Section 2809.16 When do variable offsets apply?
Section 2809.16 provides that a successful bidder may be eligible
for a variable offset of bonus bids. This section is also revised,
consistent with other changes in this rule, to read as ``process''
where appropriate when describing the BLM's competitive process.
Paragraph (c) in this final rule clarifies to readers that the
offsets are not limited explicitly to what is listed and that the BLM
may use other factors, including progressive steps towards the listed
factors.
[[Page 35669]]
Paragraph (c)(10) is unchanged except for formatting to account for
new paragraphs (c)(11) and (12).
Paragraph (c)(11) provides an incentive for use of items that
qualify for the Domestic Content preference in solar and wind energy
generation facilities on public lands, to complement the fee reduction
described in Sec. 2806.52(b)(1)(iii). To qualify for the Domestic
Content variable offset, prospective bidders must demonstrate how they
will meet the thresholds to qualify for the variable offset. Similar to
the Domestic Content reduction for the capacity fee described in
2806.52(b)(1)(iii), the thresholds identified in the notice of
competitive process are consistent with the requirements for the
domestic content preference in 2 CFR part 184. A prospective bidder is
required to provide sufficient documentation to the BLM prior to the
competitive process to show how the bidder qualifies or will qualify
for this variable offset. This may be documentation in an initial Plan
of Development provided to the BLM or other methods discussed in Sec.
2806.52(b)(1)(v) of this preamble. As discussed below, the BLM may hold
in suspense the amounts corresponding to the variable offset until
construction of the facility is substantially complete or the
successful bidder otherwise demonstrates to the BLM that the project
has met the domestic content thresholds.
Some comments suggested that including a requirement for a domestic
content preference as a variable offset would raise the cost to
taxpayers. The BLM disagrees with commenters that this rule will
increase costs to taxpayers. This final rule does not require bidders
or holders to qualify for the Domestic Content preference as a variable
offset or other reductions and variable offsets. As the comments were
based on an incorrect assumption that the rule requires buying domestic
equipment, no change was made in response to comments.
Paragraph (c)(12) provides an incentive for use of qualifying PLAs,
such as during the construction of a solar or wind energy generation
facility on public lands, to complement the fee reduction described in
Sec. 2806.52(b)(1)(iv). To receive the PLA variable offset,
prospective bidders must demonstrate how they qualify in the notice of
competitive process. A prospective bidder is required to provide
sufficient documentation to the BLM to show how they qualify, such as
in an initial Plan of Development or other methods discussed in Sec.
2806.52(b)(1)(v) of this final rule. The BLM may hold in suspense the
amounts corresponding to the variable offset until construction of the
facility is substantially complete or the successful bidder can
otherwise demonstrate to the BLM that the PLA has been executed for the
facility.
Some comments supported the use of a PLA as a basis for offering a
variable offset. These comments requested that the BLM hold a second
competitive process if the BLM does not receive bidders qualifying for
a PLA variable offset. This second competitive process would allow for
other potential bidders to qualify. The final rule does not limit the
number of competitive processes that the BLM may hold. However, the BLM
has included PLAs as an optional variable offset.
Some comments noted that union labor laws vary from State to State,
suggesting that oversight should be by the State. This final rule
provides a variable offset for interested bidders when using a
qualifying PLA for competitive processes for solar or wind energy. The
BLM's offer of a PLA variable offset does not rely on or necessarily
preclude applicable State laws as they may apply to project labor. The
BLM may not approve a variable offset from a bidder if it does not
comply with applicable laws.
Some commenters disagreed with the BLM offering variable offsets,
such as for domestic content and the use of union labor, because
developers may also receive reduced payments under Sec. 2806.52. This
final rule offers a bidder potential benefits from both a variable
offset and a capacity fee reduction. The BLM believes these variable
offsets will incentivize prospective bidders to initiate projects with
known benefits and approaches that will further benefit the public.
Moreover, as described above, reductions to the capacity fee under
Sec. 2806.52(b) will promote the greatest use of solar and wind energy
resources on public lands consistent with 43 U.S.C. 3003.
Paragraph (c)(13) provides that the BLM may use other factors when
determining whether additional types of variable offsets for a
competitive process are appropriate.
Some comments requested additional variable offsets to promote
responsible wind and solar development, using efficient technology,
agreements with local authorities that benefit communities,
redevelopment of disturbed sites, and combining or collocating energy
infrastructure. The final rule continues to provide an opportunity for
additional variable offsets in a competitive process under Sec.
2809.16(c)(13). The BLM will describe the additional variable offsets,
including how you may qualify for such additional variable offsets, in
the notice of competitive process.
Paragraph (e) provides for bidders to qualify for a variable offset
after the BLM holds a competitive process. This final rule recognizes
that a bidder may not be able to demonstrate the qualifications for
some variable offsets to the BLM's satisfaction until after the BLM
holds the competitive process, such as with new provisions in
Sec. Sec. 2809.16(c)(11) or 2809.16(c)(12) for energy development
facilities that would contain items qualifying for the Domestic Content
preference or use of a PLA. A bidder may conditionally qualify for a
variable offset before the competitive process and then later
demonstrate their qualification to the BLM and perfect their
qualification. The BLM will describe in the notice of competitive
process the way a bidder may conditionally qualify for the variable
offset and could include methods such as a written statement to the BLM
that they intend to qualify for the variable offset. The bidder, if
successful, must later demonstrate to the BLM that they have qualified
for the variable offset. The BLM may set a deadline in the notice for
bidders to demonstrate that the proposed facility qualifies for the
variable offset. If the bidder does not qualify for the variable offset
in the time provided or the bidder is not able to adequately
demonstrate they qualify for the variable offset, the U.S. Government
will retain the bid money as the balance of the bonus bid.
A comment stated that if the BLM sets a deadline to qualify for a
variable offset in the notice of competitive process, there should be a
reasonable deadline given to demonstrate qualifications. The BLM agrees
with this comment and provides a deadline, including the timeframe to
qualify for the variable offset, in its notice of competitive process.
See Sec. 2809.16(e) of this part.
Section 2809.17 Will the BLM ever reject bids or re-conduct a
competitive process?
Section 2809.17 identifies situations when the BLM may reject a
bid, offer a lease to another bidder, or re-offer a parcel. This
section is retitled from the proposed rule, consistent with other
changes in the final rule to read ``process'' when describing the BLM's
competitive process.
Paragraph (b) provides that the BLM may make the next highest
bidder the successful bidder if the named successful bidder does not
satisfy the successful bidder requirements identified under Sec.
2809.15, does not
[[Page 35670]]
execute the lease, or is for any reason disqualified from holding the
lease.
As proposed, paragraph (d) is removed from this section as it is
unnecessary with other revisions made in this final rule to make public
lands inside of DLAs available to application without a competitive
process.
Section 2809.18 What terms and conditions apply to a solar or wind
energy development lease?
Section 2809.18 lists the terms and conditions of solar and wind
energy leases, which are issued inside of areas classified or allocated
for solar or wind energy (e.g., DLAs).
Paragraph (a) clarifies that a lease awarded from a competitive
process provides site control to a lessee. However, the presumptive
leaseholder may not construct any facilities on the right-of-way until
the BLM issues a subsequent notice to proceed, see paragraph
2809.15(b)(1)(ii) of this final rule. The term of a lease is consistent
with Sec. 2805.11(c) of this final rule, which provides for a
reasonable term up to 50 years, considering the cost of the facility,
its useful life, and the public purpose it serves.
Paragraph (b) provides for rent terms for solar and wind energy
leases as specified in Sec. 2806.52.
Paragraph (f) provides that lease assignments are applied for under
Sec. 2807.21. The BLM will not make any changes to the lease terms or
conditions, as provided in Sec. 2807.21(e), except for modifications
required under Sec. 2805.15(e). Changes to right-of-way terms or
conditions would involve an amendment action by the BLM in addition to
the assignment action.
One comment recommended that the BLM adjust the terms and
conditions with an assignment to provide for land access, lease length,
processes, collaboration with other agencies, and decommissioning. This
final rule maintains the BLM's process for assigning leases. Generally,
a solar or wind energy lease assignment is an administrative action
transferring the lease from a holder to a prospective holder. The BLM's
analysis to approve or approve with modification the development lease
includes analyzing the access, lease term length, participation from
public and partners, and the end-of-life decommissioning and
restoration of the public lands. The BLM does not need to revisit these
considerations before assigning a lease unless there are substantial
changes that may justify a change to the lease. For example, the BLM
may modify a lease under Sec. 2805.15(e), which reserve the BLM's
right to change the terms and conditions as a result in changes in
legislation, regulation, or as otherwise necessary to protect public
health or safety or the environment.
Section 2809.19 Applications in Designated Leasing Areas or on Lands
That Later Become Designated Leasing Areas
As proposed, Section 2809.19 is removed from the BLM's rules in its
entirety. In this former section, the BLM explained how it would
evaluate applications for public lands that later become a DLA. The
former section is inconsistent with the changes in this rule that allow
for applications in DLAs without first holding a competitive process.
Because designation of a DLA does not preclude non-competitive leasing,
there is no need for the BLM to automatically suspend a non-competitive
leasing application because the lands at issue are being considered for
designation. At the same time, the BLM may in its discretion deny an
application or assign the application a low priority under Sec.
2804.35.
Some commenters supported the BLM making public lands inside DLAs
available for non-competitive leasing by application. These commenters
continued to suggest that the BLM should provide public notice
regarding how the BLM will handle non-competitive lease applications.
The notice should provide for at least a 30-day cutoff date for any
expressions of interest regarding a competitive interest for offering
lands within the DLA. The BLM agrees with comments that notice to the
public is appropriate regarding how the BLM will administer solar and
wind energy applications in an area affected by a land use plan
amendment. However, each planning action or programmatic analysis is
unique, and the BLM will respond to the unique conditions for solar and
wind energy applications specific to that plan amendment or
programmatic analysis. This may or may not include a period of time in
which the BLM would continue to accept applications.
Severability
Existing Sec. 2801.8 provides: ``If a court holds any provisions
of the regulations in this part or their applicability to any person or
circumstances invalid, the remainder of these rules and their
applicability to other people or circumstances will not be affected.''
If any portion of this final rule were to be stayed or invalidated by a
reviewing court, the remaining elements would continue to provide BLM
with important and independently effective tools relating to the
administration of its right-of-way and renewable energy programs.
Hence, if a court prevents any provision of one part of this rule from
taking effect, that should not affect the other parts of the rule. The
remaining provisions would remain in force because they could still
operate sensibly.
For example, the provisions that reduce rents and fees to implement
the Energy Act of 2020 may function independently of the rest of the
rule. Indeed, each particular change in rents and fees may function
independently. Thus, if a court were to invalidate the Domestic Content
reduction or Project Labor Agreement reduction, the other rent and fee
provisions should remain undisturbed. Similarly, the provisions that
reduce rents and fees may function independently of the provisions that
allow the BLM to choose whether to conduct competitive processes inside
and outside DLAs.
V. Procedural Matters
Regulatory Planning and Review (Executive Orders 12866 and 13563) and
Modernizing Regulatory Review (Executive Order 14094)
Executive Order (E.O.) 12866 provides that the Office of
Information and Regulatory Affairs (OIRA) in the Office of Management
and Budget will review all significant rules. E.O. 14094 updates the
significance criteria in section 3(f) of E.O. 12866.
OIRA has determined that this final rule is a ``significant
regulatory action'' within the scope of E.O. 12866, as amended by E.O.
14094.
The BLM's Regulatory Impact Analysis concluded that the rule may
have an annual effect on the economy of $200 million or more. These
effects are associated with construction of projects induced by this
rule. Additionally, the BLM estimated that the rule would have
distributional impacts in the form of transfer payments from right-of-
way applicants and holders to the BLM. Transfer payments are monetary
payments from one group to another that do not affect total resources
available to society. While disclosing the estimated transfers are
important for describing the distributional effects of the rule, these
payments should not be included in the estimated costs and benefits per
OMB Circular A-4.
For more detailed information, see the Regulatory Impact Analysis
for Revisions to 43 CFR 2800 (Regulatory Impact Analysis) prepared for
this rule. This Regulatory Impact Analysis has been posted in the
docket for the rule on the Federal eRulemaking Portal: https://
[[Page 35671]]
www.regulations.gov. In the Searchbox, enter ``RIN 1004-AE78,'' click
the ``Search'' button, open the Docket Folder, and look under
Supporting Documents.
E.O. 13563 reaffirms the principles of E.O. 12866 while calling for
improvements in the Nation's regulatory system to promote
predictability, reduce uncertainty, and use the best, most innovative,
and least burdensome tools for achieving regulatory ends. The E.O.
directs agencies to consider regulatory approaches that reduce burdens
and maintain flexibility and freedom of choice for the public where
these approaches are relevant, feasible, and consistent with regulatory
objectives. E.O. 13563 emphasizes further that regulations must be
based on the best available science and that the rule making process
must allow for public participation and an open exchange of ideas. The
BLM has developed this rule in a manner consistent with these
requirements.
Regulatory Flexibility Act
This rule will not likely have a significant economic effect on a
substantial number of small entities under the Regulatory Flexibility
Act (RFA) (5 U.S.C. 601 et seq.). The RFA generally requires that
Federal agencies prepare a regulatory flexibility analysis for rules
subject to the ``notice-and-comment'' rulemaking requirements found in
the Administrative Procedure Act (5 U.S.C. 500 et seq.), if the rule
would have a significant economic impact, whether detrimental or
beneficial, on a substantial number of small entities. See 5 U.S.C.
601-612. Congress enacted the RFA to ensure that government regulations
do not unnecessarily or disproportionately burden small entities. Small
entities include small businesses, small governmental jurisdictions,
and small not-for-profit enterprises.
The BLM reviewed the Small Business Size standards for the affected
industries. We determined that a small share of the entities in the
affected industries are small businesses as defined by the Small
Business Act (SBA). However, the BLM believes that the impact on the
small entities is not significant. Although the rule could potentially
affect a substantial number of small entities, the BLM does not believe
that these effects would be economically significant.
The rule would benefit small businesses by streamlining the BLM's
processes and reducing annual rent and capacity fee payments. These
reductions may motivate investment in additional generation capacity
and facilities by freeing up money that would have otherwise been paid
to the BLM as rents or fees. The rule also modifies provisions that
allow for an entity to request a waiver or reduction to annual rent and
capacity fee payments.
For the purpose of conducting its review pursuant to the RFA, the
BLM believes that the rule would not likely have a ``significant
economic impact on a substantial number of small entities,'' as that
phrase is used in 5 U.S.C. 605. Therefore, the BLM has not prepared a
final regulatory flexibility analysis.
Some comments noted that they believe there has been insufficient
analysis on this rule and request the BLM perform an initial and final
regulatory flexibility analysis, as it is required by Sections 603 and
604 of the Regulatory Flexibility Act for rules that may have a
significant economic impact on a substantial number of small business
and governmental entities. Some commenters also believe the BLM has
broken down connected and interrelated rule-making processes to avoid
significance and therefore has failed to conduct the necessary impacts
analysis under the Regulatory Flexibility Act, NEPA, E.O. 12866 and
other applicable authorities as required under the Administrative
Procedure Act.
The BLM determines that solar and wind projects with generating
capacities of less than 100 MW have average annual receipts of $5.2
million (solar) and $4.1 million (wind), which falls within the range
of receipts identified for small businesses in the SBA size standards.
The average size of projects currently under review by the BLM is
500MW. Also, projects smaller than 100MW may still fail to be small
businesses if they are owned by larger corporations or governmental
entities. While it is reasonable to expect that some small businesses
will be affected, it is not expected to be a substantial number.
Further, the principal effect will be a reduction in rents and capacity
fees for the small businesses--a benefit. In general, the share of
rents and capacity fees is small relative to project revenues.
Therefore, the benefits are not a significant economic impact on the
small businesses.
Congressional Review Act
This action is subject to the CRA, and BLM will submit a rule
report to each chamber of Congress and to the Comptroller General of
the United States. This action meets the criteria in 5 U.S.C. 804(2).
Comment Summary: In response to the proposed rule, a commenter
requested that the BLM explain contradictory conclusions of regulatory
impact in accordance with the Congressional Review Act and E.O 12866,
and coordinate with local governments and businesses to collect
inclusive and broad economic data to make an informed determination.
Response: The commenter's concern has been overtaken because DOI
will report to Congress on the promulgation of this rule prior to its
effective date. The report will state that the Office of Information
and Regulatory Affairs has determined that this rule meets the criteria
set forth in 5 U.S.C. 804(2).''
Unfunded Mandates Reform Act
This rule does not impose an unfunded mandate on State, local, or
Tribal governments, or the private sector of more than $100 million per
year. The rule does not have a significant or unique effect on State,
local, or Tribal governments, or the private sector. Under the Unfunded
Mandates Reform Act (UMRA) (2 U.S.C. 1531 et seq.), agencies must
prepare a written statement about benefits and costs, prior to issuing
a proposed or final rule that may result in aggregate expenditure by
State, local, and Tribal governments, or the private sector, of $100
million or more in any 1 year.
This rule is not subject to the requirements under the UMRA. The
rule does not contain a Federal mandate that may result in expenditures
of $100 million or more for State, local, and Tribal governments, in
the aggregate, or to the private sector in any one year. The rule would
not significantly or uniquely affect small governments. A statement
containing the information required by the UMRA is not required.
One comment requested that the BLM submit documentation that is
complete, transparent, and factual for this rulemaking and that is
informed by economic data obtained through coordination with local
governments and a diverse range of private sector industries, such as
grazing, mining and recreation. The resubmitted documentation should
support the claim that this rule does not impose an unfunded mandate
under the UMRA. If a finding shows that the rule does impose an
unfunded mandate, then the BLM must complete a cost and benefit
analysis as required by the UMRA. The BLM disagrees that this rule
requires resubmitting documentation supporting the BLM's unfunded
mandate determination. This final rule, including its Regulatory Impact
Analysis, clearly, transparently, and factually discusses the impacts
of the rule, which governs the BLM's administration of applications and
right-of-way grants and
[[Page 35672]]
leases for solar and wind energy. This rule does not result in Tribal,
State, or local governments having to expend funds. Therefore, this
rule does not impose an unfunded federal mandate and does not require a
cost and benefit analysis. In any event, this rule and the accompanying
Regulatory Impact Analysis provide all the information the UMRA
requires.
Governmental Actions and Interference With Constitutionally Protected
Property Right--Takings (E.O. 12630)
This rule does not affect a taking of private property or otherwise
have taking implications under E.O. 12630. Section 2(a) of E.O. 12630
identifies policies that do not have takings implications, such as
those that abolish regulations, discontinue governmental programs, or
modify regulations in a manner that lessens interference with the use
of private property. The rule would not interfere with private
property. A takings implication assessment is not required.
Some comments noted that access across federal, state, or county
managed lands should not entail encumbrances or restrictions on private
property. This final rule does not restrict access across any lands.
Through separate environmental review, such as through land use
planning, the BLM may consider actions that affect access. Tribal,
Federal, State, and local government offices, as well as communities
and private citizens will have opportunity to engage in those
environmental processes.
Federalism (E.O. 13132)
Under the criteria in Section 1 of E.O. 13132, this rule does not
have sufficient federalism implications to warrant the preparation of a
federalism summary impact statement. It does not have substantial
direct effects on the States, on the relationship between the national
government and the States, or on the distribution of power and
responsibilities among the various levels of government. A federalism
summary impact statement is not required.
Civil Justice Reform (E.O. 12988)
This rule complies with the requirements of E.O. 12988.
Specifically, this rule:
a. Meets the criteria of Section 3(a) requiring that all
regulations be reviewed to eliminate errors and ambiguity and be
written to minimize litigation; and
b. Meets the criteria of Section 3(b)(2) requiring that all
regulations be written in clear language and contain clear legal
standards.
Consultation and Coordination With Indian Tribes (E.O. 13175 and
Departmental Policy)
DOI strives to maintain and strengthen its government-to-government
relationship with Indian Tribes through a commitment to consultation
with Indian Tribes and recognition of their right to self-governance
and Tribal sovereignty. We have evaluated this rule under the DOI's
consultation policy and under the criteria in E.O. 13175 and have
determined that it has no substantial direct effects on federally
recognized Indian Tribes, on the relationship between the Federal
Government and Indian tribes, or on the distribution of power and
responsibilities between the Federal Government and Indian Tribes, and
that consultation under the DOI's Tribal consultation policy is not
required. However, consistent with the DOI's consultation policy (52
Departmental Manual 4) and the criteria in E.O. 13175, the BLM will
consult with federally recognized Indian Tribes on any renewable energy
project proposals that may have a substantial direct effect on the
Tribes.
Paperwork Reduction Act
The Paperwork Reduction Act (PRA) (44 U.S.C. 3501-3521) generally
provides that an agency may not conduct or sponsor and, not
withstanding any other provision of law, a person is not required to
respond to a collection of information, unless it displays a currently
valid OMB control number. Collections of information include any
request or requirement that persons obtain, maintain, retain, or report
information to an agency, or disclose information to a third party or
to the public (44 U.S.C. 3502(3) and 5 CFR 1320.3(c)).
This rule contains information-collection requirements that are
subject to review by OMB under the PRA. OMB has generally approved the
existing information-collection requirements contained in 43 CFR part
2800 associated with wind and solar rights-of-way grants or leases
under OMB control number 1004-0206 (expiration date: June 30, 2026).
Additionally, the BLM's regulations at 43 CFR part 2800 require the use
of Standard Form 299 (SF-299), ``Application for Transportation and
Utility Systems and Facilities on Federal Lands,'' for right-of-way
applications and the regulations at 43 CFR part 2800. OMB has approved
the requirements associated with SF-299 and has assigned control number
0596-0249.
This rule does not include any changes to the information-
collection requirements currently contained in 43 CFR parts 2800 and
2880 and approved by OMB as noted above. There is a new information-
collection requirement contained in 43 CFR 2806.52(b)(5) regarding an
annual certified statement. The rule would require that by October of
each year wind and solar grant or leaseholders must submit to the BLM a
certified statement identifying the first year's estimated energy
generation on public lands and the prior year's actual energy
generation on public lands. The BLM will determine the capacity fee
based on the certified statement provided. To prepare the annual
certified statement, grant or leaseholders will need to compile
information based on capacity fee as instructed in 43 CFR 2806.
The information-collection requirements contained in 43 CFR 2800
and 2880 and approved under OMB Control Number 1004-0206 and the
aforementioned new information-collection pertaining to 43 CFR
2806.52(b)(5) are described below.
Activities That Require SF-299
The following discussion describes the information-collection
activities in this control number that require use of SF-299.
Application for a Solar or Wind Energy Development Project Outside Any
Designated Leasing Area (43 CFR 2804.12, 2804.25(c), 2804.26(a)(5), and
2804.30(g)); and Application for an Electric Transmission Line With a
Capacity of 100 kV or More (43 CFR 2804.12, 2804.25(c), and
2804.26(a)(5))
Section 2804.12(b) applies to solar and wind energy development
grants outside any DLA and electric transmission lines with a capacity
of 100 kV or more.
Section 2804.12(b) includes the following requirements for
applications for a solar or wind energy development project outside a
DLA and for applications for a transmission line project with a
capacity of 100 kV or more:
A discussion of all known potential resource conflicts
with sensitive resources and values, including special designations or
protections; and
Applicant-proposed measures to avoid, minimize, and
compensate for such resource conflicts, if any.
Section 2804.12(b) also requires applicants to initiate early
discussions with any grazing permittees that may be affected by the
proposed project. This
[[Page 35673]]
requirement stems from FLPMA Section 402(g) (43 U.S.C. 1752(g)) and a
BLM grazing regulation (section 4110.4-2(b)) that require 2 years'
prior notice to grazing permittees and lessees before cancellation of
their grazing privileges.
In addition to the information listed at Sec. 2804.12(b), an
application for a solar or wind project, or for a transmission line of
at least 100 kV, must include the information listed at Sec. Sec.
2804.12(a)(1) through (a)(7).
Section 2804.25 provides that the BLM will notify an applicant upon
receipt of an application and may require the applicant to submit
additional information necessary to process the application (such as a
Plan of Development or cultural resource surveys). As amended, Sec.
2084.25(c) provides that, for solar or wind energy development projects
and transmission lines with a capacity of 100 kV or more, the applicant
must commence any required resource surveys or inventories within 1
year of the request date, unless otherwise specified by the BLM. The
amended regulation also authorizes an applicant to submit a request for
an alternative requirement by showing good cause under Sec. 2804.40.
Applications for solar or wind energy development outside any DLA,
but not applications for large-scale transmission lines, are subject to
a requirement (at Sec. 2804.12(c)(2)) to submit an ``application
filing fee'' of $15 per acre. As defined in an amendment to Sec.
2801.5, an application filing fee is specific to solar and wind energy
right-of-way applications. Section 2804.30(e)(4) provides that the BLM
will refund the fee, except for the reasonable costs incurred on behalf
of the applicant, if the applicant is not a successful bidder in the
competitive process outlined in subpart 2804.
Section 2804.26(a)(5) provides the authority that allows the BLM to
deny an application for a right-of-way grant if the applicant does not
have or cannot demonstrate the technical or financial capability to
construct the project or operate facilities within the right-of-way.
Amendments to that provision list the following ways an applicant may
demonstrate their financial and technical capability to construct,
operate, maintain, and terminate a project:
Documenting any previous successful experience in
construction, operation, and maintenance of similar facilities on
either public or non-public lands;
Providing information on the availability of sufficient
capitalization to carry out development, including the preliminary
study stage of the project and the environmental review and clearance
process; or
Providing written copies of conditional commitments of
Federal and other loan guarantees; confirmed power purchase agreements;
engineering, procurement, and construction contracts; and supply
contracts with credible third-party vendors for the manufacture or
supply of key components for the project facilities.
General Description of a Proposed Project and Schedule for Submittal of
a Plan of Development (43 CFR 2804.12(b)(1) and (b)(2))
Sections 2804.12(b)(1) and (b)(2) require applicants for a solar or
wind development project outside a DLA to submit the following
information, using Form SF-299:
A general description of the proposed project and a
schedule for the submission of a Plan of Development (POD) conforming
to the POD template at https://www.blm.gov;
A discussion of all known potential resource conflicts
with sensitive resources and values, including special designations or
protections; and
Proposals to avoid, minimize, and compensate for such
resource conflicts, if any.
Application for an Energy Site-Specific Testing Grant (43 CFR
2804.12(a), and 2804.30(g)); Application for an Energy Project-Area
Testing Grant (43 CFR 2804.12(a), and 2804.30(g)); and Application for
a Short-Term Grant (43 CFR 2804.12(a))
Section 2804.12(a) addresses the general requirements of an
application for a FLPMA right-of-way grant. Section 2804.30(g)
authorizes only one applicant (i.e., a ``preferred applicant'') to
apply for an energy project-area testing grant or an energy site-
specific testing grant for land outside any DLA.
Each of these grants is for 3 years or less, in accordance with
Sec. 2805.11(c)(2). All of these applications must be submitted on SF-
299. Applications for project-area grants (but not site-specific
grants) are subject to a $2 per-acre application filing fee in
accordance with Sec. 2804.12(c)(2). Applicants for short-term grants
for other purposes (such as geotechnical testing and temporary land-
disturbing activities) are subject to a processing fee in accordance
with Sec. 2804.1.
Request To Assign a Solar or Wind Energy Development Right-of-Way (43
CFR 2807.21)
Section 2807.21, as amended, provides for assignment, in whole or
in part, of any right or interest in a grant or lease for a solar or
wind development right-of-way. Actions that may require an assignment
include the transfer by the holder (assignor) of any right or interest
in the grant or lease to a third party (assignee) or any change in
control transaction involving the grant holder or leaseholder,
including corporate mergers or acquisitions. The proposed assignee must
file an assignment application, using SF-299, and pay application and
processing fees.
The assignment application must include:
Documentation that the assignor agrees to the assignment;
and
A signed statement that the proposed assignee agrees to
comply with and be bound by the terms and conditions of the grant that
is being assigned and all applicable laws and regulations.
Environmental, Technical, and Financial Records, Reports, and Other
Information (43 CFR 2805.12(a)(15))
Section 2805.12(a)(15) authorizes the BLM to require a holder of
any type of right-of-way to provide, or give the BLM access to, any
pertinent environmental, technical, and financial records, reports, and
other information. The use of SF-299 is required. The BLM will use the
information for monitoring and inspection activities.
Application for Renewal of a Solar or Wind Energy Development Grant or
Lease (43 CFR 2805.14(g) and 2807.22)
Section 2805.14(g) provides that a holder of a right-of-way grant,
which includes solar or wind energy generating facilities, may apply
for renewal in accordance with Sec. 2807.22. Section 2807.22(c)
provides that an application to renew a grant must include the same
information, on SF-299, that is necessary for a new application. It
also provides that processing fees, in accordance with Sec. 2804.14,
as amended, apply to these renewal applications. Sections 2807.22(a)
and (b) provide that an application for renewal of any right-of-way
grant or lease, including a solar or wind energy development grant or
lease, must be submitted at least 120 calendar days before the grant or
lease expires. The application must show that the grantee or lessee is
complying with the renewal terms and conditions (if any), with the
other terms, conditions, and stipulations of the grant or lease, and
with other applicable laws and regulations. The application also must
explain why a renewal of the grant or lease is necessary.
[[Page 35674]]
Request for Amendment, Assignment, or Other Change (FLPMA) (43 CFR
2807.11(b) and (d) and 2807.21)
Section 2807.11(b) requires a holder of any type of right-of-way
grant to contact the BLM to seek an amendment to the grant under Sec.
2807.20 and obtain the BLM's approval before beginning any activity
that is a ``substantial deviation'' from what is authorized.
Section 2807.11(d) requires contacting the BLM to request an
amendment to the pertinent right-of-way grant or lease and prior
approval whenever site-specific circumstances or conditions result in
the need for changes to an approved right-of-way grant or lease, Plan
of Development, site plan, mitigation measures, or construction,
operation, or termination procedures that are not ``substantial
deviations.''
Section 2807.21 authorizes assignment of a grant or lease with the
BLM's approval. It also authorizes the BLM to require a grant or
leaseholder to file new or revised information in circumstances that
include, but are not limited to:
Transactions within the same corporate family;
Changes in the holder's name only; and
Changes in the holder's articles of incorporation.
A request for an amendment of a right-of-way, using SF-299, is
required in cases of a substantial deviation (for example, a change in
the boundaries of the right-of-way, major improvements not previously
approved by the BLM, or a change in the use of the right-of-way). Other
changes, such as changes in project materials, or changes in mitigation
measures within the existing, approved right-of-way area, must be
submitted to the BLM for review and approval. In order to assign a
grant, the proposed assignee must file an assignment application and
follow the same procedures and standards as for a new grant or lease,
as well as pay application and processing fees. In order to request a
name change, the holder will be required to file an application and
follow the same procedures and standards as for a new grant or lease
and pay processing fees, but no application fee is required. The
following documents are also required in the case of a name change:
A copy of the court order or legal document effectuating
the name change of an individual; or
If the name change is for a corporation, a copy of the
corporate resolution proposing and approving the name change, a copy of
a document showing acceptance of the name change by the State in which
incorporated, and a copy of the appropriate resolution, order, or other
document showing the name change.
In all these cases, the BLM will use the information to monitor and
inspect rights-of-way, and to maintain current data.
Activities That Do Not Require Any Form
Preliminary Application Review Meetings for a Large-Scale Right-of-Way
(43 CFR 2804.12(b)(4))
``Preliminary application review meetings'' are required after
submission of an application for a large-scale right-of-way. A large-
scale right-of-way is for solar or wind energy development outside a
DLA, or for a transmission line with a capacity of 100 kV or more.
Within 6 months from the date that the BLM receives the cost
recovery fee for an application for a large-scale project, the
applicant must schedule and hold at least two preliminary application
review meetings.
In the first meeting, the BLM will collect information from the
applicant to supplement the application on subjects such as the general
project proposal. The BLM will also discuss with the applicant subjects
such as the status of the BLM's land use planning for the lands
involved, potential siting issues or concerns, potential environmental
issues or concerns, potential alternative site locations, and the
right-of-way application process.
In the second meeting, the applicant and the BLM will meet with
appropriate Federal and State agencies and Tribal and local governments
to facilitate coordination of potential environmental and siting issues
and concerns.
The applicant and the BLM may agree to hold additional preliminary
application review meetings.
Application for Renewal of an Energy Project-Area Testing Grant or
Other Short-Term Grant (43 CFR 2805.11(c)(2)(ii), 2805.14(h), and
2807.22)
Section 2805.11(c)(2)(ii) provides that holders of energy project-
area testing grants may seek renewal of those grants. The initial term
for such a grant is 3 years or less, with the option to renew for one
additional 3-year period.
For other short-term grants, such as for geotechnical testing and
temporary land-disturbing activities, the initial term is 3 years or
less. Short-term grants include an option for renewal.
Section 2805.14(h) provides that applications to renew an energy
project-area testing grant must include an energy development
application submitted in accordance with Sec. 2801.9(d)(2). Cost
recovery fees in accordance with Sec. 2804.14, as amended, apply to
these renewal applications.
Section 2807.22 provides that an application for renewal of any
right-of-way grant or lease, including an energy project-area testing
grant or a short-term grant, must be submitted at least 120 calendar
days before the grant or lease expires. The application must show that
the grantee or lessee is complying with the renewal terms and
conditions (if any), with the other terms, conditions, and stipulations
of the grant or lease, and with other applicable laws and regulations.
The application also must explain why a renewal of the grant or lease
is necessary.
Showing of Good Cause (43 CFR 2804.40 and 2805.12)
Under Sec. 2804.40, an applicant for a FLPMA right-of-way grant
who is unable to meet any of the requirements in subpart 2804 may
request approval for an alternative requirement from the BLM. Any such
request is not approved until the applicant receives BLM approval in
writing. This type of request to the BLM must:
(a) Show good cause for the applicant's inability to meet a
requirement;
(b) Suggest an alternative requirement and explain why that
requirement is appropriate; and
(c) Be received in writing by the BLM in a timely manner, before
the deadline to meet a particular requirement has passed.
The BLM will use the information to determine whether to apply an
alternative requirement.
Other showings of good cause are authorized or may be required by
Sec. 2805.12, which requires due diligence in development and
operations of any right-of-way grant or lease. In accordance with Sec.
2805.12(c)(6) and (c)(8), the BLM will notify the holder before
suspending or terminating a right-of-way for lack of due diligence.
This notice will provide the holder with a reasonable opportunity to
correct any noncompliance or to start or resume use of the right-of-
way. A showing of good cause will be required in response. That showing
must include:
Reasonable justification for any delays in construction or
reductions in energy generation (for example, delays in equipment
delivery, legal challenges, and acts of God);
The anticipated date for the completion of construction or
resumption of energy generation; and
[[Page 35675]]
evidence of progress toward the start or resumption of construction;
and
A request for extension of the timelines in the approved
POD or extension of the period in which the holder must satisfy the
minimum energy threshold.
Section 2805.12(e), as amended, applies as soon as a right-of-way
holder anticipates noncompliance with stipulation, term, or condition
of the approved right-of-way grant or lease, or in the event of
noncompliance with any such stipulation, term, or condition. In these
circumstances, the holder must notify the BLM in writing and show good
cause for the noncompliance, including an explanation of the reasons
for the noncompliance.
In addition, the holder may request that the BLM consider
alternative stipulations, terms, or conditions. Any request for an
alternative stipulation, term, or condition must comply with applicable
law in order to be considered. Any proposed alternative to applicable
bonding requirements must provide the United States with adequate
financial assurance for potential liabilities associated with the
right-of-way grant or lease. Any such request is not approved until the
holder receives the BLM's approval in writing.
Bonding Requirements (43 CFR 2805.20)
Section 2805.20 provides that the bond amount for projects other
than a solar or wind energy lease under subpart 2809 (i.e., inside a
DLA) will be determined based on the preparation of a reclamation cost
estimate that includes the cost to the BLM to administer a reclamation
contract and review it periodically for adequacy.
Section 2805.20(a)(5) provides that the reclamation cost estimate
must include at a minimum:
Remediation of environmental liabilities such as use of
hazardous materials waste and hazardous substances, herbicide use, the
use of petroleum-based fluids, and dust control or soil stabilization
materials;
The decommissioning, removal, and proper disposal, as
appropriate, of any improvements and facilities; and
Interim and final reclamation, re-vegetation,
recontouring, and soil stabilization.
Sections 2805.20(b) and 2805.20(c) identify specific bond
requirements for solar and wind energy development respectively outside
of DLAs. A holder of a solar or wind energy grant outside of a DLA will
be required to submit a reclamation cost estimate to help the BLM
determine the bond amount. For solar energy development grants outside
of DLAs, the bond amount will be no less than $10,000 per acre. For
wind energy development grants outside of DLAs, the bond amount will be
no less than $10,000 per authorized turbine with a nameplate generating
capacity of less than one Megawatt (MW), and no less than $20,000 per
authorized turbine with a nameplate generating capacity of one MW or
greater.
Section 2805.20(d) separates site- and project-area testing
authorization bond requirements from Sec. 2805.20(c). Meteorological
and other instrumentation facilities are required to be bonded at no
less than $2,000 per location. These bond amounts are the same as
standard bond amounts for leases required under Sec. 2809.18(e)(3).
Annual Certified Statement (43 CFR 2806.52(b)(5))--New Information
Collection
The rule requires that by October of each year, wind and solar
grant or leaseholders must submit to the BLM a certified statement
identifying the first year's estimated energy generation on public
lands and the prior year's actual energy generation on public lands.
The BLM will determine the capacity fee based on the certified
statement provided. To prepare the annual certified statement, grant or
leaseholders will need to compile information based on the capacity fee
as instructed in subpart 2806. This is the only new information-
collection requirement contained in this rule.
Nomination of a Parcel of Land Inside a Designated Leasing Area (43 CFR
2809.11)
Sections 2809.10 and 2809.11 authorize the BLM, on its own
initiative, to offer land through a competitive process for solar or
wind energy development. These regulations also authorize the BLM to
solicit nominations for such development by publishing a notice in the
Federal Register. To nominate a parcel under this process, the
nominator must be qualified to hold a right-of-way under 43 CFR
2803.10. After publication of a notice by the BLM, anyone meeting the
qualifications may submit a nomination for a specific parcel of land to
be developed for solar or wind energy. There is a fee of $5 per acre
for each nomination. The following information is required:
The nominator's name and personal or business address;
The legal land description; and
A map of the nominated lands.
The BLM will use the information to communicate with the nominator
and to determine whether to proceed with a competitive process.
Plan of Development for a Solar or Wind Energy Development Lease Inside
a Designated Leasing Area (43 CFR 2809.18)
Section 2809.l8(c) requires the holder of a lease for solar or wind
energy development to submit a Plan of Development (POD) within 2 years
of the lease issuance date. The POD must be consistent with the
development schedule and other requirements in the POD template posted
at https://www.blm.gov; and must address all pre-development and
development activities.
Section 2809.18(d) requires the holder of a solar or wind energy
development lease for land inside a DLA to pay reasonable costs for the
BLM or other Federal agencies to review and approve the POD and monitor
the lease. To expedite review and monitoring, the holder may notify the
BLM in writing of an intention to pay the full actual costs incurred by
the BLM.
Request for Amendment, Assignment, or Other Change (MLA) (43 CFR
2886.12(b) and (d) and 43 CFR 2887.11)
Sections 2886.12 and 2887.11 pertain to holders of rights-of-way
and temporary use permits authorized under the MLA. A temporary use
permit authorizes a holder of a MLA right-of-way to use land
temporarily in order to construct, operate, maintain, or terminate a
pipeline, or for purposes of environmental protection or public safety.
See Sec. 2881.12. The regulations require these holders to contact the
BLM:
Before engaging in any activity that is a ``substantial
deviation'' from what is authorized;
Whenever site-specific circumstances or conditions arise
that result in the need for changes that are not substantial
deviations;
When the holder submits a certification of construction;
Before assigning, in whole or in part, any right or
interest in a grant or lease;
Before any change in control transaction involving the
grant- or lease-holder; and
Before changing the name of a holder (i.e., when the name
change is not the result of an underlying change in control of the
right-of-way).
A request for an amendment of a right-of-way or temporary use
permit is required in cases of a substantial deviation (e.g., a change
in the boundaries of the right-of-way, major improvements not
previously approved by the BLM, or a change in the use of the right-of-
way). Other changes, such
[[Page 35676]]
as changes in project materials, or changes in mitigation measures
within the existing, approved right-of-way area are required to be
submitted to the BLM for review and approval. In order to assign a
grant, the proposed assignee must file an assignment application and
follow the same procedures and standards as for a new grant or lease,
as well as pay processing fees. In order to request a name change, the
holder will be required to file an application and follow the same
procedures and standards as for a new grant or lease and pay processing
fees, but no application fee is required. The following documents are
also required in the case of a name change:
A copy of the court order or legal document effectuating
the name change of an individual; or
If the name change is for a corporation, a copy of the
corporate resolution proposing and approving the name change, a copy of
a document showing acceptance of the name change by the State in which
incorporated, and a copy of the appropriate resolution, order, or other
document showing the name change.
In all these cases, the BLM will use the information gathered for
monitoring and inspection purposes, and to maintain current data on
rights-of-way.
Certification of Construction (43 CFR 2886.12(f))
A certification of construction is a document a holder of an MLA
right-of-way must submit to the BLM after finishing construction of a
facility, but before operations begin. The BLM will use the information
to verify that the holder has constructed and tested the facility to
ensure that it complies with the terms of the right-of-way and is in
accordance with applicable Federal and State laws and regulations.
The information-collection request for this rule has been submitted
to OMB for review under 44 U.S.C. 3507(d). You may view the
information-collection request(s) at https://www.reginfo.gov/public/do/PRAMain.
As part of our continuing effort to reduce paperwork and respondent
burdens, we invite the public and other Federal agencies to comment on
any aspect of this information-collection, including:
Whether the collection of information is necessary for the
proper functioning of the BLM, including whether the information will
have practical utility;
The accuracy of the BLM's estimate of the burden of
collecting the information, including the validity of the methodology
and assumptions used;
The quality, utility, and clarity of the information to be
collected; and
How to minimize the information-collection burden on those
who are to respond, including the use of appropriate automated,
electronic, mechanical, or other forms of information technology.
Currently, the information-collection requirements contained in 43
CFR parts 2800 and 2880 and approved under OMB control number 1004-0206
are estimated as follows: 3,042 annual responses; 47,112, annual burden
hours; and $2,182,302 annual cost burden. We are projecting a burden
increase of 75 new annual responses and 150 new annual burden hours as
result of this rule. This burden hour increase would result from a new
information collection requirement contained in Sec. 2806.52(b)(5)
pertaining to the annual certified statement. This new information
collection is needed to help the BLM more accurately determine the
capacity fee based on the certified statement provided.
The final rule also removes an existing information collection
previously contained in 43 CFR 2809.11(c) titled, Expression of
Interest in a Parcel of Land Inside a Designated Leasing Area. The
removal of this information collection results in the reduction of 1
annual response and 4 annual burden hours.
Therefore, we estimate that the final rule will result in a net
increase of 74 annual responses and 226 annual burden hours.
We are also adjusting the burden for two existing and unchanged
information collections to reflect more accurately the burden those
activities would involve the industry. These adjustments include the
following:
Preliminary Application Review Meetings for 2 public
meetings for a Large-Scale Right-of-Way (43 CFR 2804.12(b)(4)). The
average response time is adjusted from 2 hours to 4 hours. This
adjustment resulted in a 40-hour burden increase (from 40 hours to 80
hours).
Environmental, Technical, and Financial Records, Reports,
and Other Information (43 CFR 2805.12(a)(15)). We have added a 50
percent increase in the hours required to prepare reports (from 4 per
response to 6 per response). This resulted in an increasing the
estimated annual burden hours for these activities from 80 hours to 120
hours.
There are no projected changes to the non-hour cost burdens as a
result of this rule. The resulting new estimated total burdens for OMB
Control Number 1004-0206 are provided below.
Title of Collection: Competitive Processes, Terms, and Conditions
for Leasing Public Lands for Solar and Wind Energy Development (43 CFR
parts 2800 and 2880).
OMB Control Number: 1004-0206.
Form Number: SF-299 (Burden approved by OMB in Request for Common
Form under OMB Control Number 0596-0249).
Type of Review: Revision of a currently approved collection of
information.
Respondents/Affected Public: Private sector (applicants for and
holders of wind and solar rights-of-way grants or leases on Federal
public lands.
Respondent's Obligation: Required to obtain or retain a benefit.
Frequency of Collection: On occasion and annually for the Annual
Certified Statement in 43 CFR 2806.52(i).
Number of Respondents: 75.
Annual Responses: 3,116.
Annual Burden Hours: 47,338.
Annual Burden Cost: $2,182,302.
If you want to comment on the information-collection requirements
this in this rule, please send your comments and suggestions on this
information-collection request within 30 days of publication of this
final rule in the Federal Register to OMB at www.reginfo.gov. Click on
the link, ``Currently under Review--Open for Public Comments.''
National Environmental Policy Act
These proposed regulatory amendments are of an administrative or
procedural nature and thus are eligible to be categorically excluded
from the requirement to prepare an EA or an EIS. See 43 CFR 46.205 and
46.210(i). They do not present any of the extraordinary circumstances
listed at 43 CFR 46.215.
Actions Concerning Regulations That Significantly Affect Energy Supply,
Distribution, or Use (Executive Order 13211)
Federal agencies are to prepare and submit to OMB a Statement of
Energy Effects for any proposed significant energy action. A
``significant energy action'' is defined as any action by an agency
that: (1) Is a significant regulatory action under Executive Order
12866, or any successor order, and (2) Is likely to have a significant
adverse effect on the supply, distribution, or use of energy; or (3) Is
designated by the Administrator of OIRA as a significant energy action.
The BLM reviewed the rule and determined that it is not likely a
significant energy action as defined by E.O. 13211. While the rights-
of-way affected by this rule are for solar and
[[Page 35677]]
wind energy generation, the rule is limited in scope and would not
likely have a significant, adverse effect on the supply, distribution,
or use of energy from these sources. The rule would not result in a
shortfall in supply, price increases, or increase the use of foreign
supplies.
Authors
The principal authors of this rule are: Jayme M. Lopez, BLM
National Renewable Energy Coordination Office; Jeremy Bluma, BLM
National Renewable Energy Coordination Office; Radford Schantz,
Division of Lands, Realty and Cadastral Survey; Patrick Lee, DOI,
Office of Policy Analysis; Jeff Holdren, BLM Division of Lands,
Realty and Cadastral Survey; Darrin King, BLM Division of Regulatory
Affairs; Jennifer Noe, BLM Division of Regulatory Affairs, assisted
by the DOI Office of the Solicitor. This action by the Principal
Deputy Assistant Secretary is taken pursuant to an existing
delegation of authority.
Steven H. Feldgus, Ph.D.,
Principal Deputy Assistant Secretary, Land and Minerals Management.
List of Subjects in 43 CFR Part 2800
Electric power, Highways and roads, Penalties, Public lands and
rights-of-way, Reporting and recordkeeping requirements.
Accordingly, for the reasons stated in the preamble, the BLM amends
43 CFR part 2800 as set forth below:
PART 2800--RIGHTS-OF-WAY UNDER THE FEDERAL LAND POLICY AND
MANAGEMENT ACT
0
1. The authority citation for part 2800 is revised to read as follows:
Authority: 43 U.S.C. 1733, 1740, 1763, 1764, and 3003.
Subpart 2801--General information
0
2. Amend Sec. 2801.5:
0
a. In paragraph (a) by adding the acronym for ``FLPMA'' in alphabetical
order;
0
b. In paragraph (b) by:
0
i. Removing the term ``Act'';
0
ii. Adding in alphabetical order the terms ``Domestic Content'' and
``Capacity fee'';
0
iii. Revising the term for ``Grant'';
0
iv. Removing the term ``Megawatt (mw) capacity fee'';
0
v. Revising the terms ``Megawatt hour (MWh) rate'' and ``Reasonable
costs''; and
0
vi. Adding in alphabetical order the terms ``Renewable energy
coordination office (RECO)'', ``Solar or wind energy development'', and
``Solar or wind energy lease''.
The additions and revisions to read as follows:
Sec. 2801.5 What acronyms and terms are used in the regulations in
this part?
(a) * * *
FLPMA means the Federal Land Policy and Management Act of 1976, as
amended (43 U.S.C. 1701 et seq.).
* * * * *
(b) * * *
Domestic Content reduction means an item or product that qualifies
for the domestic content preference under the Build America, Buy
America Act, Public Law 117-58, 135 Stat. 429, Sec. Sec. 70901 through
70927 (Nov. 15, 2021), and the implementing guidance at 2 CFR part 184.
Capacity fee is the fee charged to right-of-way holders once energy
production commences that is based on the production of energy on
public lands from solar and wind energy generating facilities.
* * * * *
Grant means an authorization or instrument (e.g., easement,
license, or permit) the BLM issues under Title V of the Federal Land
Policy and Management Act, 43 U.S.C. 1761 et seq., and any
authorization or instrument the BLM and its predecessors issued for
like purposes before October 21, 1976, under then existing statutory
authority, except for solar or wind energy leases. It does not include
authorizations issued under the Mineral Leasing Act (30 U.S.C. 185).
* * * * *
Megawatt hour (MWh) rate means the 5 calendar-year average of the
annual average wholesale electricity prices per MWh for the major
trading hubs serving the 11 western States of the continental United
States.
* * * * *
Reasonable costs has the meaning found in Section 304(b) of FLPMA.
* * * * *
Renewable energy coordination office (RECO) means one of the
National, State, district, or field offices established by the
Secretary under 43 U.S.C. 3002(a) that is responsible for implementing
a program for improving Federal permit coordination with respect to
solar, wind, and geothermal projects on BLM-administered land, and such
other activities as the Secretary determines necessary.
* * * * *
Solar or wind energy development means the use of public lands to
generate electricity from solar or wind energy resources. It includes
the construction, operation, maintenance, and decommissioning of any
such facilities, as well as the subsequent reclamation of the site.
Solar or wind energy lease means any right-of-way issued for solar
or wind energy development in an area classified or allocated for solar
or wind energy (i.e., a designated leasing area) in a resource
management plan.
* * * * *
0
3. Amend Sec. 2801.6 by revising paragraph (a)(1) to read as follows:
Sec. 2801.6 Scope.
(a) * * *
(1) Grants or leases for necessary transportation or other systems
and facilities that are in the public interest and require the use of
public lands for the purposes identified in 43 U.S.C. 1761, and
administering, amending, assigning, monitoring, renewing, and
terminating them;
* * * * *
0
4. Amend Sec. 2801.9 by revising paragraphs (d) introductory text,
(d)(3) and (4), and adding paragraph (d)(6) to read as follows:
Sec. 2801.9 When do I need a grant?
* * * * *
(d) All systems, facilities, and related activities for energy
generation, storage, or transmission projects are specifically
authorized as follows:
* * * * *
(3) Energy generation facilities, including solar and wind energy
development facilities, are authorized with a right-of-way grant or
lease that may be issued for up to 50 years (plus initial partial year
of issuance);
(4) Energy storage facilities, which are separate from energy
generation facilities, are authorized with a right-of-way grant that
may be issued for up to 50 years;
* * * * *
(6) Electric transmission lines with a capacity of 100 kV or more
are authorized with a right-of-way grant that may be issued for up to
50 years.
0
5. Revise the heading for subpart 2802 to read as follows:
Subpart 2802--Lands Available for FLPMA Grants or Leases
0
6. Amend Sec. 2802.11 by revising paragraphs (b) introductory text and
(b)(1) and adding paragraphs (b)(10) and (11) to read as follows:
Sec. 2802.11 How does the BLM designate right-of-way corridors and
designated leasing areas?
* * * * *
(b) When determining which public lands may be suitable for right-
of-way corridors or designated leasing areas, the BLM may consider
various factors, including:
[[Page 35678]]
(1) Federal, State, Tribal, and local land use plans, and
applicable Federal, State, Tribal, and local laws;
* * * * *
(10) Access to electric transmission; and
(11) Whether there are areas for solar and wind energy development
with low potential for conflict with resources or uses due to
environmental, cultural, and other relevant criteria, which the BLM
will identify by:
(i) Assessing the demand for new or expanded areas;
(ii) Applying environmental, cultural, and other screening
criteria; and
(iii) Analyzing proposed areas through the land use planning
process described in part 1600 of this chapter.
* * * * *
0
7. Amend Sec. 2803.10 by revising paragraph (c) to read as follows:
Sec. 2803.10 Who may hold a grant or lease?
* * * * *
(c) Of legal age and authorized to do business in the State or
States where the right-of-way you seek is located.
0
8. Revise Sec. 2803.12 to read as follows:
Sec. 2803.12 What happens to my grant or lease if I die?
(a) If a grant holder dies, any inheritable interest in a grant or
lease will be distributed under State law.
(b) If the receiver of a grant or lease is not qualified to hold a
grant or lease under Sec. 2803.10 of this subpart, the BLM will
recognize the receiver as grant or leaseholder for up to two years,
subject to full compliance with all terms, conditions, and
stipulations. During that period, the receiver must either become
qualified or divest itself of the interest.
Subpart 2804--Applying for FLPMA Grants
0
9. Amend Sec. 2804.12 by revising paragraphs (c) and (f) and adding
paragraph (j) to read as follows:
Sec. 2804.12 What must I do when submitting my application?
* * * * *
(c) You must meet additional requirements when applying for a solar
or wind energy development or short-term right-of-way, as follows:
(1) Pay an application filing fee of $2 per acre for short-term
right-of-way applications or $15 per acre for solar or wind energy
development applications. The BLM will apply the application filing fee
toward the processing fees described in Sec. Sec. 2804.14 through
2804.22. The BLM will refund the balance of any application filing fee
at the end of the BLM's application review process if the application
filing fee exceeds the amount of the processing fee.
(2) Pay additional reasonable costs in addition to payment of the
application filing fee when processing your application, pursuant to
Sec. 2804.14. A processing or monitoring Category 6 cost recovery fee
may be reduced by the application filing fee paid when submitting an
application.
* * * * *
(f) The BLM may require you to submit additional information at any
time while processing your application. The BLM will identify
additional information in a written deficiency notice asking you to
provide the information within a specified time pursuant to Sec.
2804.25(c).
* * * * *
(j) Your application will not be complete until you have met or
addressed the requirements of this section to the satisfaction of the
BLM. The BLM will notify you in writing when your application is
complete.
0
10. Revise Sec. 2804.22 to read as follows:
Sec. 2804.22 How will the availability of funds affect the timing of
the BLM's processing your application?
(a) If the BLM has insufficient funds to process your application,
we will not continue to process it until funds become available or you
elect to pay full actual costs under Sec. 2804.14(f) of this part.
(b) The BLM may deny your application if we have not received
requested reasonable costs for processing your application within 90
days.
(c) If your cost recovery agreement provides that a portion of the
funds you pay will be used in the hiring of additional staff or
contractors, such funds may not be refundable.
0
11. Revise Sec. 2804.23 to read as follows:
Sec. 2804.23 What costs am I responsible for when the BLM decides to
use a competitive process for lands included in my application?
If the BLM decides to use a competitive process for lands included
in your application and your application is in:
(a) Processing Categories 1 through 4. You must reimburse the
Federal Government for processing costs as if the other application or
applications had not been filed.
(b) Processing Category 6. You are responsible for processing costs
identified in your application. If the BLM cannot readily separate
costs, such as costs associated with preparing environmental analyses,
you and any competing applicants must pay an equal share, or a
proportion agreed to in writing among all applicants and the BLM. If
you agree to share the costs that are common to your application and
that of a competing applicant, and the competitor does not pay the
agreed upon amount, you are liable for the entire amount due. You must
pay the entire processing fee in advance. The BLM will not process your
application until we receive the advance payments.
0
12. Amend Sec. 2804.25 by revising paragraphs (c), (e)(2), (e)(4),
(e)(5), and (f)(3) to read as follows:
Sec. 2804.25 How will the BLM process my application?
* * * * *
(c) The BLM may require you to submit additional information
necessary to process the application. This information may include a
detailed construction, operation, rehabilitation, and environmental
protection plan (i.e., a POD), and any needed cultural resource surveys
or inventories for threatened or endangered species. If the BLM needs
more information, the BLM will identify this information in a written
deficiency notice asking you to provide the additional information
within a specified period of time. The failure to provide additional
information requested by the BLM under this section may result in the
BLM denying your application pursuant to Sec. 2804.26.
(e) * * *
(2) If your application is for solar or wind energy development;
(i) Hold a local public meeting if there is no other public meeting
or opportunity for early engagement on the project, such as those
completed when complying with the National Environmental Policy Act
(NEPA).
(ii) Prioritize the application in accordance with Sec. 2804.35;
and
(iii) Evaluate the application based on the information provided by
the applicant and input from other parties, such as Federal, State,
Tribal, and local government agencies, as well as comments received in
preliminary application review meetings held under Sec. 2804.12(b)(4)
and any public meeting held under paragraph (e)(1) of this section.
Based on these evaluations, the BLM will either deny your application
or continue processing it.
* * * * *
(4) Complete appropriate NEPA compliance for the application, as
required by 43 CFR part 46 and 40 CFR chapter V, subchapter A;
[[Page 35679]]
(5) Determine whether your proposed use complies with applicable
Federal laws;
* * * * *
(f) * * *
(3) The segregation period may not exceed 2 years from the date of
publication in the Federal Register of the notice initiating the
segregation, unless the state director determines and documents in
writing, prior to the expiration of the segregation period, that an
extension is necessary for the orderly administration of the public
lands. If the state director determines an extension is necessary, the
BLM will extend the segregation for up to 2 years by publishing a
notice in the Federal Register, prior to the expiration of the initial
segregation period. A segregation will not be extended unless the
application is complete and cost recovery has been received.
Segregations under this part may only be extended once and the total
segregation period may not exceed 4 years.
0
13. Amend Sec. 2804.26 by revising the section heading, paragraphs
(a)(4) and (9) and adding paragraph (a)(10), and removing paragraph
(c).
The revisions and additions read as follows:
Sec. 2804.26 Under what circumstances may the BLM deny my
application?
(a) * * *
(4) Issuing the grant would be inconsistent with FLPMA, other laws,
or these or other regulations;
* * * * *
(10) You fail to pay costs for processing your application within
90 days of receiving the BLM's request for funds under Sec.
2804.22(b).
* * * * *
Sec. 2804.30 [Removed and Reserved]
0
14. Remove and reserve Sec. 2804.30.
Sec. 2804.31 [Removed and Reserved]
0
15. Remove and reserve Sec. 2804.31.
0
16. Revise Sec. 2804.35 to read as follows:
Sec. 2804.35 Application prioritization for solar and wind energy
development rights-of-way.
(a) The BLM will prioritize the processing of applications to
ensure that agency resources are allocated to applications with the
greatest potential for approval and implementation. The BLM's
prioritization of an application is not a decision and is not subject
to appeal under 43 CFR part 4.
(b) The BLM will consider relevant criteria when prioritizing
applications, including the following:
(1) Whether the proposed project is located within an area
preferred for solar or wind energy development, such as designated
leasing areas, which include solar energy zones, development focus
areas, and renewable energy development areas;
(2) Whether the proposed project is likely to avoid adverse impacts
to or conflicts with known resources or uses on or adjacent to public
lands, and includes specific measures designed to further mitigate
impacts or conflicts;
(3) Whether the proposed project is in conformance with the
governing BLM land use plans;
(4) Whether the proposed project is consistent with relevant State,
Tribal, and local government laws, plans, or priorities;
(5) Whether the proposed project incorporates the best management
practices set forth in the applicable BLM land use plans and other BLM
plans and policies; and
(6) Any other circumstances or prioritization criteria identified
by the BLM in subsequent policy guidance or management direction
through land use planning.
(c) The BLM will prioritize your complete application based on all
available information, including information you provide to the BLM in
the application or in response to deficiency notices, and information
provided to the BLM in public meetings or consultations.
(d) The BLM may re-prioritize your application at any time.
0
17. Amend Sec. 2804.40 by revising the introductory text to read as
follows:
Sec. 2804.40 Alternative requirements.
If you are unable to meet any of the application requirements in
this subpart, you may request approval for an alternative requirement
from the BLM. Any such request is not approved until you receive BLM
approval in writing. Your request to the BLM must:
* * * * *
Subpart 2805--Terms and Conditions of Grants
0
18. Amend Sec. 2805.10 by revising paragraph (c) to read as follows:
Sec. 2805.10 How will I know whether the BLM has approved or denied
my application or if my bid for a solar or wind energy development
grant or lease is successful or unsuccessful?
* * * * *
(c) If you agree with the terms and conditions of the unsigned
grant or lease, you should sign and return it to the BLM with any
payment required under Sec. 2805.16. The BLM will issue the right-of-
way by signing the grant or lease and transmitting it to you, if the
regulations in this part, including Sec. 2804.26, remain satisfied.
* * * * *
0
19. Amend Sec. 2805.11 by revising the section heading and paragraphs
(c)(2) introductory text and (c)(2)(iv) and (v) and adding paragraph
(b)(4) to read as follows:
Sec. 2805.11 What does a grant or lease contain?
* * * * *
(c) * * *
(2) Specific terms for energy grants and leases, such as solar or
wind energy development projects, are as follows:
* * * * *
(iv) Energy generation facilities, including solar or wind energy
development facilities, are authorized with a grant or lease for up to
50 years (plus initial partial year of issuance), subject to the terms
and conditions including but not limited to Sec. 2805.12(c); and
(v) Energy storage facilities which are separate from energy
generation facilities are authorized with a right-of-way grant for up
to 50 years, subject to the terms and conditions including but not
limited to Sec. 2805.12(c);
* * * * *
(4) Electric transmission lines with a capacity of 100 kV or more
are authorized with a right-of-way grant for up to 50 years.
* * * * *
0
20. Amend Sec. 2805.12 by adding paragraph (c)(8) and by revising
paragraph (e)(2) to read as follows:
Sec. 2805.12 What terms and conditions must I comply with?
* * * * *
(c) * * *
(8) Comply with the operational standards in this section for solar
or wind energy development projects on public lands. The holder of a
grant or lease for solar or wind energy development is authorized to
operate for the purpose of generating energy. Diligent operation
requires the holder to annually maintain at least 75 percent of energy
generation capacity for the authorized development. Failure to meet
this required generation in continuous two calendar year period during
the term of the grant or lease may support suspension or termination of
the grant or lease under Sec. Sec. 2807.17 through 2807.19. Before
suspending or terminating the authorization, the BLM will send you a
notice that gives you a reasonable opportunity to correct any
[[Page 35680]]
noncompliance or to start or resume use of the right-of-way (see Sec.
2807.18). In response to this notice, you must:
(i) Provide reasonable justification for any reductions in energy
generation (for example, delays in equipment delivery, legal
challenges, and Acts of God);
(ii) Provide the anticipated date in which production of energy
generation will resume; and
(iii) Submit a written request under paragraph (e) of this section
for extension of the period in which the holder must satisfy the
minimum energy threshold. If you do not comply with the requirements of
paragraph (c)(8) of this section, the BLM may deny your request for an
extension of the period for complying with the minimum energy
generation threshold.
* * * * *
(e) * * *
(2) You may also request that the BLM consider alternative
stipulations, terms, or conditions, other than rents or fees, and
except as provided in Sec. 2806.52(b)(1)(i). Any proposed alternative
stipulation, term, or condition must comply with applicable law in
order to be considered. Any proposed alternative to applicable bonding
requirements must provide the United States with adequate financial
assurance for potential liabilities associated with your right-of-way
grant or lease. Any such request is not approved until you receive BLM
approval in writing.
0
21. Revise Sec. 2805.13 to read as follows:
Sec. 2805.13 When is a grant or lease effective?
A grant is effective after both you and the BLM sign it. You must
accept its terms and conditions in writing and pay any necessary rent
and monitoring fees as set forth in subpart 2806 of this part and Sec.
2805.16 of this subpart. Your written acceptance constitutes an
agreement between you and the BLM that your right to use the public
lands, as specified in the grant or lease, is subject to the terms and
conditions of the grant or lease and applicable laws and regulations.
0
22. Amend Sec. 2805.14 by revising the section heading and paragraph
(g) to read as follows:
Sec. 2805.14 What rights does a right-of-way grant or lease convey?
* * * * *
(g) Apply to renew your right-of-way grant or lease under Sec.
2807.22;
* * * * *
Subpart 2806--Annual Rents and Payments
0
23. Amend Sec. 2806.10 by revising the section heading and adding
paragraph (c) to read as follows:
Sec. 2806.10 What rent must I pay for my grant or lease?
* * * * *
(c) You must pay rent for your grant or lease using the per-acre
rent schedule for linear right-of-way grants (see Sec. 2806.20) unless
a separate rent schedule is established for your use, such as for
communication sites per Sec. 2806.30 or solar and wind energy
development per Sec. 2806.50. The BLM may also determine that these
schedules do not apply to your right-of-way pursuant to Sec. 2806.70.
0
24. Amend Sec. 2806.12 by revising paragraphs (a)(1) introductory
text, (a)(2), and (b) to read as follows:
Sec. 2806.12 When and where do I pay rent?
(a) * * *
(1) If your grant or lease is effective on:
* * * * *
(2) If your grant or lease allows for multiyear payments, such as a
short-term grant issued for energy site-specific testing, you may
request that your initial rent bill be for the full term instead of the
initial rent bill periods provided under paragraph (a)(1)(i) or (ii) of
this section.
(b) You must make all rent payments for rights-of-way according to
the payment plan described in Sec. 2806.24.
* * * * *
0
25. Amend Sec. 2806.20 by revising paragraph (c) to read as follows:
Sec. 2806.20 What is the rent for a linear right-of-way grant?
* * * * *
(c) You may obtain a copy of the current Per Acre Rent Schedule
from any BLM state, district, or field office or by writing the address
found under Sec. 2804.14(c) of this part. We also post the current
rent schedule at https://www.blm.gov.
0
26. Revise the undesignated center heading that precedes Sec. 2806.50
and Sec. 2806.50 to read as follows:
Solar and Wind Energy Development Rights-of-Way
Sec. 2806.50 Rents and fees for solar and wind energy development.
If you hold a right-of-way for solar or wind energy development,
you must pay an annual rent and fee in accordance with this section and
subpart. The annual rent and fee is the greater of the acreage rent or
the capacity fee that would be due in a given year, and must be paid in
advance each year. The acreage rent will be calculated consistent with
Sec. 2806.11 and prorated consistent with Sec. 2806.12(a). The
capacity fee will vary depending on the project's annual energy
generation on public lands and will be calculated consistent with Sec.
2806.52(b). Any underpayment will be billed pursuant to Sec. 2806.13
and any overpayment will be credited pursuant to Sec. 2806.16.
0
27. Amend Sec. 2806.51 by revising the section heading and paragraph
(c) to read as follows:
Sec. 2806.51 Grant and lease rate adjustments.
* * * * *
(c) If you hold a right-of-way for solar or wind energy development
that is in effect prior to July 1, 2024, you may either request that
the BLM apply the annual rent and fee set forth in Sec. 2806.52 or use
the rate methodology applicable to your authorization immediately prior
to this rule. If you wish to use the annual rent and fee set forth in
Sec. 2806.52, your request must be received by the BLM before July 1,
2026. The BLM will continue to apply the rate in effect immediately
prior to this rule unless it receives your request to use the rate
adjustments in this part. A request to change your rate methodology
will include your agreement to a re-issuance of the grant or lease with
updated Terms and Conditions found under this part, pursuant to Sec.
2807.20(f).
0
28. Amend Sec. 2806.52 by revising the section heading, the
introductory text and paragraphs (a), (b), and (c) to read as follows:
Sec. 2806.52 Annual rents and fees for solar and wind energy
development.
You must pay the greater of either an annual acreage rent or a
capacity fee. The acreage rent and capacity fee are determined as
follows:
(a) Acreage rent. The BLM will calculate the acreage rent for your
grant or lease by multiplying the number of acres of the authorized
area (rounded up to the nearest tenth of an acre) by the annual per-
acre rate for the year in which the payment is due.
(1) Per-acre rate. The annual per-acre rate for your grant or lease
is calculated using the State per-acre value from the solar or wind
energy acreage rent schedule, the encumbrance factor, the year of the
grant or lease term, and the annual adjustment factor. The calculation
for determining the annual per-acre rate is A x B x [(1 + C) [supcaret]
D] where:
[[Page 35681]]
(i) A is the state per-acre value from the solar or wind energy
acreage rent schedule published by the BLM for the year on which your
right-of-way grant or lease is issued and is based on the National
Agricultural Statistics Service (NASS) Survey of Pastureland Rents. The
BLM will prepare the rent schedule by averaging the NASS reported
pastureland rents for the most recent 5-year period, using only those
years for which rent is reported by NASS. The BLM will update the rent
schedule every 5 years consistent with the timing of rent adjustments
under Sec. 2806.22.
(ii) B is the encumbrance factor, which is 100 percent for solar
energy and 5 percent for wind energy;
(iii) C is the annual adjustment factor, which is 3 percent; and,
(iv) D is the year of the grant or lease term, which is the number
of years the grant or lease has been authorized. For example, the first
year (whether partial or full year) would be 0 and the second year
would be 1.
(2) You may obtain a copy of the current solar or wind energy
acreage rent schedule from any BLM state, district, or field office or
by writing the address found under Sec. 2804.14(c) of this part,
Attention: Renewable Energy Coordination Office. The BLM also posts the
current solar energy acreage rent schedule at https://www.blm.gov.
(b) Capacity fee. (1) The capacity fee is calculated using the MWh
rate or the alternative MWh rate, the MWh rate reduction, the domestic
content reduction, the Project Labor Agreement (PLA) reduction, the
rate of return, the year of the grant or lease, the annual adjustment
factor, and the annual power generated on the right-of-way. You must
pay the capacity fee annually, beginning the year in which electricity
generation begins or is scheduled to begin in the approved POD,
whichever comes first, unless the acreage rent (see paragraph (a) of
this section) exceeds the capacity fee in a given year. The calculation
for determining the capacity fee is A x B x C x D x [(1 + E)
[supcaret]F] x G x H where:
(i) A is the MWh rate or the alternative MWh rate. The MWh rate is
the annual weighted average wholesale price per MWh for the major
trading hubs serving the 11 Western States of the continental United
States for the full 5 calendar-year period preceding the year in which
your grant or lease was issued, rounded to the nearest dollar increment
(see paragraph (7)). An Alternative MWh rate may be approved by the BLM
if you have entered into a power purchase agreement, such as with a
utility, and that rate is lower than the MWh rate. You must provide
proof of the lower rate to the BLM, and if the BLM determines the lower
rate is appropriate, the alternative MWh rate will be used in place of
the MWh rate.
(ii) B is the MWh rate reduction, which is equal to 80 percent for
fee payments due before 2036. Starting 2036, the MWh rate reduction for
new authorizations transitions to 20 percent, as follows:
Table 1 to Paragraph (b)(1)(ii)
------------------------------------------------------------------------
B--
MWh rate calculation
Calendar year reduction multiplier
(%) (%)
------------------------------------------------------------------------
2035.......................................... 80 20
2036.......................................... 60 40
2037.......................................... 40 60
2038 and beyond............................... 20 80
------------------------------------------------------------------------
(iii) C is the Domestic Content reduction, which is equal to 1.0
for fee payments when a holder's project does not qualify for the
domestic content reduction. C is equal to 0.8 when the holder can
demonstrate that a facility qualifies for the domestic content
reduction. A facility qualifies for the domestic content reduction if a
holder documents that the facility would qualify as ``Produced in the
United States'', consistent with 2 CFR part 184.
(iv) D is the factor for the Project Labor Agreement reduction,
which is equal to 1.0 for fee payments when the holder does not execute
a PLA. D is equal to 0.8 if the holder executes a PLA for the
construction of the project.
(v) Request for conditional approval: Alternative MWh rate,
Domestic Content reduction and PLA reduction. The alternative MWh rate,
the Domestic Content reduction and PLA reduction (paragraphs (b)(1)(ii)
and (iii) and (iv) of this section) may only be applied if a request
for conditional approval is received by the BLM prior to the issuance
of a grant or lease. A request for conditional approval must be
submitted with sufficient documentation to demonstrate that the
development qualifies or may later qualify for the rate reductions. A
request for conditional approval is subject to the holder
demonstrating, to the satisfaction of the BLM's Authorized Officer,
that the development qualifies. If energy generation begins before the
holder has demonstrated that the facility qualifies, the BLM will
charge the holder the full capacity fee, without the alternative MWh
rate, Domestic Content reduction, or PLA reduction. The capacity fee
may be updated for subsequent calendar years after the holder
demonstrates that the facility qualifies, but the BLM will not refund
past payments made before the alternative MWh rate, domestic content
reduction, or PLA reduction went into effect.
(2) E is the annual adjustment factor, which is 3 percent.
(3) F is the year of the grant or lease term, which is the number
of years the grant or lease has been authorized. For example, the first
year (whether partial or full year) would be 0 and the second year
would be 1.
(4) G is the rate of return, which is 7 percent.
(5) H is the annual energy generated on the right-of-way and will
be provided to the BLM by the grant or leaseholder in an annual
certified statement. The BLM will bill to coincide with the start of
the calendar year. The first-year payment in advance will be based on
estimated energy generation and the BLM will determine final payment
for the first year based on actual energy generation. Subsequent
payments in advance will be based on the most recent calendar year's
actual energy generation reported on the certified statement, unless
exception is approved in paragraph (vi) of this section.
(i) The holder must submit the annual certified statement to the
BLM before the first year of energy generation begins or is scheduled
to begin as approved in the Plan of Development, whichever comes first.
Certified annual statements must be submitted to the BLM by October,
each year.
(ii) Prior to the start of energy generation, the holder must
submit to the BLM in the certified statement the estimated energy
generation of the development for the first year.
(iii) Once energy generation has begun, the holder must submit to
the BLM in the certified statement the most recent calendar year's
actual energy generation of the development.
(iv) The BLM will calculate the capacity fee from the certified
statement. For projects that include generation on public and non-
public lands, the holder will prorate the total energy generation by
the percentage of the right-of-way footprint on public lands relative
to the total development area footprint.
(v) If the year's actual energy generation exceeds or is less than
the amount of energy generation used to bill for the payment in
advance, the holder will be billed, credited, or refunded for the
underpayment or overpayments pursuant to Sec. Sec. 2806.13(e) and
2806.16. In no event will the total payment be less than the annual
acreage rent.
(vi) The BLM may approve a request made by a right-of-way holder to
provide a new estimate of energy generation to the BLM in the annual
[[Page 35682]]
certified statement to use for billing the next year's payment in
advance if: the right-of-way holder has planned maintenance activities,
or other interruptions to energy generation, that would reduce the
amount of energy generated by 25 percent or more; or, the right-of-way
holder is aware that the energy generation in the subsequent year will
exceed the actual energy generation for the previous year by 25 percent
or more. See Sec. 2805.12(c)(8)(i) through (iii) for the steps to
follow when failing to meet diligent operation requirements.
(vii) If the right-of-way holder underestimates energy generation
by 25 percent or more of the actual energy generation or does not
provide the BLM with a new estimate when energy production will exceed
the previous year's actual production by more than 25 percent, the BLM
may assess the holder a late payment fee of 10 percent of the actual
generation for each year of underestimation. This section applies
unless the BLM has approved a request to provide a new estimate under
Sec. 2806.52(b)(5)(vi), and the approved new estimate does not
underestimate energy generation by 25 percent or more of actual energy
generation or if the holder can provide the BLM with justification
consistent with Sec. 2805.12(e).
(6) MWh rate schedule. You may obtain a copy of the current MWh
rate schedule from any BLM state, district, or field office or by
writing the address found under Sec. 2804.14(c) of this part,
Attention: Renewable Energy Coordination Office. The BLM also posts the
current MWh rate schedule at https://www.blm.gov.
(7) Periodic adjustments. (i) The MWh rate applicable to your
right-of-way will be the MWh rate in effect the first year for your
grant or lease and will not be updated with subsequent MWh rate
schedule adjustments. The MWh rate applicable to your right-of-way will
only be updated each year by the annual adjustment factor under
paragraph (b)(2) of this section.
(ii) The MWh rate schedule for new grants and leases will be
adjusted once every 5 years consistent with the timing of rent
adjustments under Sec. 2806.22 of this part and consistent with
paragraph (b)(1) of this section.
(8) The general payment provisions for rents described in this
subpart, except for Sec. 2806.14(a)(4), also apply to the capacity
fee.
(c) Implementation of the acreage rent and capacity fee. The rates
for acreage rent and capacity fees apply to all grants and leases
issued after the effective date of this rule, and to existing grants
and leases if the holder elects to continue paying under the rate
setting methodology established at the time of your authorization per
Sec. 2806.51(c).
* * * * *
0
29. Add an undesignated center heading between Sec. Sec. 2806.52 and
2806.54 and revise Sec. 2806.54 to read as follows:
Renewable Energy Rights-of-Way
Sec. 2806.54 Rent for energy storage facilities that are not part of
a solar or wind energy development facility.
Rent for energy storage facilities that are not part of a solar or
wind energy development facility will be determined pursuant to the
linear rent formula set forth in Sec. 2806.23. The BLM may determine
your rent pursuant to Sec. 2806.70 if we determine the linear rent
schedule does not apply.
Sec. Sec. 2806.60 through 2806.68 [Removed]
0
30. Remove the undesignated center heading ``Wind Energy Rights-of-
Way'' and Sec. Sec. 2806.60 through 2806.68.
Subpart 2807--Grant Administration and Operation
0
31. Amend Sec. 2807.17 by revising paragraph (c) to read as follows:
Sec. 2807.17 Under what conditions may BLM suspend or terminate my
grant or lease?
* * * * *
(c) Your failure to use your right-of-way for its authorized
purpose for any continuous 5-year period creates a presumption of
abandonment, except for solar and wind energy rights-of-way. Consistent
with Sec. 2805.12(c)(8), a presumption of abandonment or insufficient
productivity of a grant or lease for a solar or wind energy generation
occurs for any continuous two calendar-year period.
0
32. Amend Sec. 2807.20 by revising paragraph (b) and adding paragraph
(f) to read as follows:
Sec. 2807.20 When must I amend my application, seek an amendment of
my grant or lease, or obtain a new grant or lease?
* * * * *
(b) The requirements to amend an application or grant are the same
as those for a new application, including paying processing and
monitoring fees and rent according to Sec. Sec. 2804.14, 2805.16, and
2806.10, except for solar and wind energy development grants and leases
per Sec. 2806.51(c) requesting a rent adjustment addressed under
paragraph (f) of this section.
* * * * *
(f) A request to the BLM per Sec. 2806.51(c) to adjust your solar
or wind energy rates must be received before July 1, 2026. The BLM will
re-issue your grant or lease, without further review, for the remainder
of your existing term consistent with the requirements of this part,
including processing and monitoring costs under Sec. Sec. 2804.14 and
2805.16, the terms and conditions under Sec. 2805.12, and rent
provision under Sec. 2806.50.
0
33. Amend Sec. 2807.21 by revising paragraph (e) to read as follows:
Sec. 2807.21 May I assign or make other changes to my grant or lease?
* * * * *
(e) Your assignment is not recognized until the BLM approves it in
writing. We will approve the assignment if doing so is in the public
interest. We may modify the grant or lease or add bonding and other
requirements, including additional terms and conditions, to the grant
or lease when approving the assignment, except that we may only modify
solar or wind energy leases where modification is warranted under Sec.
2805.15(e). We may decrease rents if the new holder qualifies for an
exemption (see Sec. 2806.14) or waiver or reduction (see Sec.
2806.15) and the previous holder did not. Similarly, we may increase
rents if the previous holder qualified for an exemption or waiver or
reduction and the new holder does not. If we approve the assignment,
the benefits and liabilities of the grant or lease apply to the new
grant or leaseholder.
* * * * *
0
34. Revise the heading of subpart 2809 to read as follows:
Subpart 2809--Competitive Process for Solar and Wind Energy
Development Applications or Leases
0
35. Revise Sec. 2809.10 to read as follows:
Sec. 2809.10 Competitive process for energy development grants and
leases.
(a) The BLM may conduct a competitive process for solar and wind
energy development grants or leases on its own initiative; or
(b) The BLM may solicit nominations for public lands to be included
in a competitive process by publishing a call for nominations under
Sec. 2809.11(a); or
(c) You may request that the BLM conduct a competitive process by
submitting a request in writing that complies with Sec. 2809.11(b); or
(d) The BLM may conduct a competitive process if it receives two or
more competing applications.
[[Page 35683]]
(e) Except where an applicant has failed to timely provide
information requested by the BLM under Sec. 2804.25(c), the BLM will
not offer lands in a competitive process for which the BLM has accepted
a complete application, received a Plan of Development, and entered
into a cost recovery agreement.
0
36. Revise Sec. 2809.11 to read as follows:
Sec. 2809.11 How will the BLM call for nominations?
(a) Call for nominations. The BLM may publish a call for
nominations for lands to be included in a competitive process. The BLM
will publish this notice in the Federal Register and may also use other
notification methods, such as a newspaper of general circulation in the
area affected, or the internet. The Federal Register notice and any
other notices will include:
(1) The date, time, and location by which nominations must be
submitted;
(2) The date by which nominators will be notified of the BLM's
decision on timely submissions;
(3) The area or areas within which nominations are being requested;
and
(4) The qualification for a nominator, which must include, at a
minimum, the requirements for an applicant, see Sec. 2803.10.
(b) Nomination submission. Nominations for lands to be included in
a competitive process must be in writing, and include the following:
(1) A refundable nomination fee of $5 per acre;
(2) The nominator's name and personal or business address. The name
of only one citizen, association, partnership, corporation, or
municipality may appear as the nominator. All communications relating
to submissions will be sent to that name and address, which constitutes
the nominator's name and address of record; and
(3) The legal land description and a map of the nominated lands.
The lands nominated may be the entire area or part of the area made
available under the call for nominations.
(c) The BLM will not accept your submission if it does not comply
with the requirements of this section, or if you are not qualified to
hold a grant or lease under Sec. 2803.10.
(d) Withdrawing a nomination. A nomination cannot be withdrawn,
except by the BLM for cause, in which case the nomination fee will be
refunded.
(e) The BLM may decide whether to conduct an offer for nominated
lands.
0
37. Revise Sec. 2809.12 to read as follows:
Sec. 2809.12 How will the BLM select and prepare parcels?
(a) The BLM will identify parcels for a competitive process based
on information received in public nominations, land use designations,
and on any other information it deems relevant.
(b) The BLM and other Federal agencies, as applicable, may conduct
necessary studies and site evaluation work, including applicable
environmental reviews and public meetings, before offering lands in a
competitive process.
(c) The BLM's choice to conduct a competitive process is not a
decision to grant or deny a right-of-way application and is not subject
to appeal under 43 CFR part 4.
0
38. Amend Sec. 2809.13 by revising paragraphs (b)(7) and (c) to read
as follows:
Sec. 2809.13 How will the BLM conduct competitive processes?
* * * * *
(b) * * *
(7) The terms and conditions of the process, including whether a
successful bidder will become a preferred applicant or a presumptive
leaseholder; the requirements for the successful bidder to submit an
application, see Sec. 2804.12, or a Plan of Development, see Sec.
2809.18; and any mitigation requirements, including compensatory
mitigation.
(c) We will notify you in writing of our decision to conduct a
competitive process at least 30 days prior to the competitive process
if you nominated lands that are included in the process, paid the
nomination fees, and demonstrated your qualifications to hold a grant
or lease as required by Sec. 2809.11.
0
39. Amend Sec. 2809.15 by:
0
a. Revising paragraph (a);
0
b. Removing paragraph (d);
0
c. Redesignating paragraphs (b) and (c) as paragraphs (c) and (d),
respectively;
0
d. Adding a new paragraph (b); and
0
e. Revising newly redesignated paragraphs (d)(1) through (4);
0
f. Adding paragraph (d)(5); and
0
f. Revising paragraph (e).
The revisions and addition read as follows:
Sec. 2809.15 How will the BLM select the successful bidder?
(a) The bidder with the highest total bid, prior to any variable
offset, is the successful bidder, and may become the preferred
applicant or the presumptive leaseholder in accordance with Sec.
2809.15(b).
(b) The successful bidder will become the presumptive leaseholder
or preferred applicant only after making the payments required in
paragraph (d) and satisfying the requirements of this section and Sec.
2803.10. If the successful bidder does not satisfy these requirements,
the BLM may make the next highest bidder the successful bidder under
Sec. 2809.17(b) or re-offer the lands under Sec. 2809.17(d).
(1) Presumptive leaseholder. (i) The successful bidder will become
a presumptive leaseholder if:
(A) The lands for which the bidder has successfully bid are located
within a designated leasing area; and,
(B) The notice of the competitive process indicated that a
successful bidder will become a presumptive leaseholder.
(ii) A presumptive leaseholder will be awarded a lease only if the
presumptive leaseholder submits a proposed Plan of Development in
accordance with Sec. 2804.25(c) and the proposed Plan of Development
is approved by the BLM.
(2) Preferred applicant. A successful bidder who does not become a
presumptive leaseholder in accordance with Sec. 2809.15(b)(1) may
become a preferred applicant. The preferred applicant's application for
a grant or lease will be processed for the parcel identified in the
submission under Sec. 2809.12(b). Approval of the application is not
guaranteed and is solely at the BLM's discretion. The BLM will not
process other applications for solar and wind energy development on
lands where a preferred applicant has been identified, unless allowed
by the preferred applicant.
* * * * *
(d) * * *
(1) Make payments by personal check, cashier's check, certified
check, bank draft, or money order, or by other means deemed acceptable
by the BLM, payable to the Department of the Interior--Bureau of Land
Management;
(2) By the close of official business hours on the day on which the
BLM conducts the competitive process or such other time as the BLM may
have specified in the offer notices, submit for each parcel:
(3) Within 15 calendar days after the day on which the BLM conducts
the competitive process, submit the balance of the bonus bid (after the
variable offsets are applied under paragraph (c) of this section) to
the BLM office conducting the process; and
(4) Within 15 calendar days after the day on which the BLM conducts
the
[[Page 35684]]
competitive process, submit the application filing fee under Sec.
2804.12(c) less the application fee submitted under Sec. 2809.11(c)(1)
(if you are the preferred applicant), or submit the acreage rent for
the first full year of the lease as provided in part 2806 (if you are
the presumptive leaseholder).
(5) You may be required to pay reasonable costs in addition to
payment of the application filing fee when processing your application,
pursuant to Sec. 2804.14. A processing or monitoring Category 6 cost
recovery fee may be reduced by the application filing fee paid when
submitting an application.
(e) The successful bidder will not become the preferred applicant
or be offered a lease and the BLM will keep all money that has been
submitted with the competitive process if the successful bidder does
not satisfy the requirements of paragraph (d) of this section. In this
case, the BLM may make the next highest bidder the successful bidder
under Sec. 2809.17(b) or re-offer the lands.
0
40. Amend Sec. 2809.16 by redesignating paragraph (c)(11) as paragraph
(c)(13), revising paragraphs (c) introductory text and (c)(10), adding
paragraphs (c)(11) and (12), revising newly redesignated paragraph
(c)(13), and adding paragraph (e) to read as follows:
Sec. 2809.16 When do variable offsets apply?
* * * * *
(c) The variable offset may be based on the following factors,
including progressive steps towards:
* * * * *
(10) Public benefits;
(11) Use of items qualifying for the Domestic Content preference;
(12) Use of a project labor agreement; and
(13) Other factors.
* * * * *
(e) If the successful bidder's eligibility for a variable offset
cannot be verified until a later time, the BLM may require the
successful bidder to submit the full bid amount, without taking into
account the variable offset, and hold the amount of the variable offset
in suspense. The amount of the bonus bid corresponding to the variable
offset will be refunded or credited to the successful bidder once the
successful bidder has demonstrated that it has qualified for the
variable offset. The BLM may set a deadline in the notice of
competitive process by which the successful bidder must demonstrate its
qualifications.
0
41. Amend Sec. 2809.17 by revising paragraph (b) and removing
paragraph (d) to read as follows:
Sec. 2809.17 Will the BLM ever reject bids or re-conduct a
competitive process?
* * * * *
(b) We may make the next highest bidder the successful bidder if
the first successful bidder does not satisfy the requirements of Sec.
2809.15, does not execute the lease, or is for any reason disqualified
from holding the lease.
* * * * *
0
42. Amend Sec. 2809.18 by revising the introductory text and
paragraphs (a), (b), and (f) to read as follows:
Sec. 2809.18 What terms and conditions apply to a solar and wind
energy development lease?
The lease will be issued subject to the following terms and
conditions:
(a) Site control. A lease provides site control to the leaseholder.
The term of your lease will be consistent with Sec. 2805.11(b) and
will terminate on December 31 of the final year of the lease term. You
may submit an application for renewal under Sec. 2805.14(g). A
leaseholder may not construct any facilities on the right-of-way until
the BLM issues a notice to proceed or other written form of approval to
begin surface disturbing activities.
(b) Rent. You must pay any rent as specified in Sec. 2806.52.
* * * * *
(f) Assignments. You may apply to assign your lease under Sec.
2807.21, and if an assignment is approved, the BLM will not make any
changes to the lease terms or conditions, as provided for by Sec.
2807.21(e), except for modifications required under Sec. 2805.15(e).
* * * * *
Sec. 2809.19 [Removed]
0
43. Remove Sec. 2809.19.
[FR Doc. 2024-08099 Filed 4-30-24; 8:45 am]
BILLING CODE 4331-29-P