Alabama Power Company; Notice of Revised Procedural Schedule for Environmental Impact Statement for the Proposed Project Relicense, 31194-31195 [2024-08777]
Download as PDF
31194
Federal Register / Vol. 89, No. 80 / Wednesday, April 24, 2024 / Notices
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Applicant. On
or before the comment date, it is not
necessary to serve motions to intervene
or protests on persons other than the
Applicant.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document.
The Commission strongly encourages
electronic filings of comments, protests,
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. In lieu of electronic filing,
you may submit a paper copy which
must reference the Project docket
number.
To file via USPS: Debbie-Anne A.
Reese, Acting Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426.
To file via any other courier: DebbieAnne A. Reese, Acting Secretary,
Federal Energy Regulatory Commission,
12225 Wilkins Avenue, Rockville,
Maryland 20852.
Comment Date: 5:00 p.m. Eastern
Time on May 2, 2024.
Dated: April 18, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–08784 Filed 4–23–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 15329–000]
khammond on DSKJM1Z7X2PROD with NOTICES
Ocean Renewable Power Company,
Inc.; Notice of Preliminary Permit
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Competing Applications
a. On October 20, 2023, Ocean
Renewable Power Company, Inc., filed
an application for a preliminary permit,
pursuant to section 4(f) of the Federal
Power Act (FPA), proposing to study the
feasibility of the Buffalo-Niagara
Hydrokinetic Project No. 15329
(project), to be located on the Niagara
River in the City of Buffalo, Erie County,
New York. The sole purpose of a
VerDate Sep<11>2014
16:48 Apr 23, 2024
Jkt 262001
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
b. Project Description: The proposed
project would consist of the following:
(1) up to 265 turbine-generators,
including RivGen and Modular RivGen
hydrokinetic turbine-generators with a
combined installed capacity of 5
megawatts; (2) a mooring system to
anchor each turbine-generator to the
riverbed; (3) an approximately 3,365foot-long bundled data line and 750-volt
generator lead line that connect the
turbine-generators to a 20-foot-long, 8foot-wide onshore station; (4) a 12.5- to
25-kilovolt transmission line and
transformer that connect the onshore
station to an adjacent electric
distribution line owned by National
Grid; and (5) appurtenant facilities. The
estimated annual generation of the
project would be up to 42,050
megawatt-hours.
c. Applicant Contact: Mr. Nathan
Johnson, Ocean Renewable Power
Company, Inc., 254 Commercial Street,
Suite 119B, Portland, Maine 04101;
telephone at (207) 772–7707; email at
njohnson@orpc.co.
d. FERC Contact: Joshua Dub, Project
Coordinator, Great Lakes Branch,
Division of Hydropower Licensing;
telephone at (202) 502–8138; email at
Joshua.Dub@ferc.gov.
e. The preliminary permit application
has been accepted for filing.
f. Deadline for filing comments,
motions to intervene, competing
applications (without notices of intent),
or notices of intent to file competing
applications: 60 days from the issuance
of this notice, June 17, 2024.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
ferconline.ferc.gov/FERCOnline.aspx.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://ferconline.ferc.gov/.aspx. You
must include your name and contact
information at the end of your
comments. For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
PO 00000
Frm 00068
Fmt 4703
Sfmt 4703
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Debbie-Anne A. Reese,
Acting Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Debbie-Anne A.
Reese, Acting Secretary, Federal Energy
Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852.
The first page of any filing should
include docket number P–15329–000.
g. The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202)502–6595 or OPP@
ferc.gov.
h. More information about this
project, including a copy of the
application, can be viewed on the
Commission’s website (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number (P–15329) in
the docket number field to access the
document. For assistance, please contact
FERC Online Support.
Dated: April 18, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–08776 Filed 4–23–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2628–066]
Alabama Power Company; Notice of
Revised Procedural Schedule for
Environmental Impact Statement for
the Proposed Project Relicense
On November 23, 2021, the Alabama
Power Company filed an application for
a new major license for the 135megawatt R.L. Harris Hydroelectric
Project No. 2628 (Harris Project or
project). On March 31, 2023,
Commission staff issued a notice of
intent to prepare an Environmental
Impact Statement (EIS) to evaluate the
effects of relicensing the Harris Project.
The notice of intent included a schedule
for preparing a draft and final EIS.
E:\FR\FM\24APN1.SGM
24APN1
Federal Register / Vol. 89, No. 80 / Wednesday, April 24, 2024 / Notices
By this notice, Commission staff is
updating the procedural schedule for
completing the EIS. The revised
schedule is shown below. Further
revisions to the schedule may be made
as appropriate.
Milestone
Issue draft EIS .........................
Public Meeting on draft EIS ....
Comments on draft EIS due ....
Commission issues final EIS ...
Target date
July 2024.1
August 2024.
September 2024.
March 2025.
Any questions regarding this notice
may be directed to Sarah Salazar at
(202) 502–6863 or sarah.salazar@
ferc.gov.
Dated: April 18, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–08777 Filed 4–23–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
khammond on DSKJM1Z7X2PROD with NOTICES
Combined Notice of Filings # 1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER24–952–001.
Applicants:Alabama Power Company,
Georgia Power Company, Mississippi
Power Company.
Description: Tariff Amendment:
Alabama Power Company submits tariff
filing per 35.17(b): Horus Georgia 2
(Coweta Solar) LGIA Deficiency
Response to be effective 1/10/2024.
Filed Date: 4/18/24.
Accession Number: 20240418–5084.
Comment Date: 5 p.m. ET 5/9/24.
Docket Numbers: ER24–1071–002.
Applicants: Consumers Energy
Company.
Description: Tariff Amendment:
Further Amended Contract-RS with
Alpena Pwr. Co (ER24–1071–) to be
effective 4/1/2024.
Filed Date: 4/18/24.
Accession Number: 20240418–5074.
Comment Date: 5 p.m. ET 5/9/24.
Docket Numbers: ER24–1306–001.
Applicants: Windy Flats Partners,
LLC.
Description: Tariff Amendment:
Windy Flats Filing to be effective 4/22/
2024.
1 The Council on Environmental Quality’s (CEQ)
regulations under 40 CFR 1501.10(b)(2) (2023)
require that EISs be completed within 2 years of the
federal action agency’s decision to prepare an EIS.
See also National Environmental Policy Act, 42
U.S.C. 4321 et seq., amended by section
107(g)(1)(A)(iii) of the Fiscal Responsibility Act of
2023, Public Law 118–5, 4336a, 137 Stat. 42.
VerDate Sep<11>2014
16:48 Apr 23, 2024
Jkt 262001
Filed Date: 4/18/24.
Accession Number: 20240418–5065.
Comment Date: 5 p.m. ET 5/9/24.
Docket Numbers: ER24–1717–001.
Applicants: PJM Interconnection,
L.L.C.
Description: Tariff Amendment:
Amendment of Amended ISA, SA No.
4401; Queue No. AA1–095 to be
effective 1/25/2016.
Filed Date: 4/18/24.
Accession Number: 20240418–5146.
Comment Date: 5 p.m. ET 5/9/24.
Docket Numbers: ER24–1782–000.
Applicants: Alabama Power
Company, Georgia Power Company,
Mississippi Power Company.
Description: § 205(d) Rate Filing:
Alabama Power Company submits tariff
filing per 35.13(a)(2)(iii: Hall Creek
Solar LGIA Filing to be effective 4/5/
2024.
Filed Date: 4/18/24.
Accession Number: 20240418–5085.
Comment Date: 5 p.m. ET 5/9/24.
Docket Numbers: ER24–1783–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: § 205(d) Rate Filing:
2024–04–18_SA 4276 NIPSCO-Monroe
Power GIA (J1355) to be effective 6/18/
2024.
Filed Date: 4/18/24.
Accession Number: 20240418–5086.
Comment Date: 5 p.m. ET 5/9/24.
Docket Numbers: ER24–1784–000.
Applicants: Tri-State Generation and
Transmission Association, Inc.
Description: § 205(d) Rate Filing:
Initial Filing of Rate Schedule FERC No.
369 to be effective 5/2/2024.
Filed Date: 4/18/24.
Accession Number: 20240418–5107.
Comment Date: 5 p.m. ET 5/9/24.
Docket Numbers: ER24–1785–000.
Applicants: MPower Energy NJ LLC.
Description: Baseline eTariff Filing:
MPE_NJ_FERC_Application to be
effective 5/18/2024.
Filed Date: 4/18/24.
Accession Number: 20240418–5116.
Comment Date: 5 p.m. ET 5/9/24.
Docket Numbers: ER24–1786–000.
Applicants: Tri-State Generation and
Transmission Association, Inc.
Description: Tariff Amendment:
Notice of Cancellation of Rate Schedule
FERC No. 216 to be effective 6/17/2024.
Filed Date: 4/18/24.
Accession Number: 20240418–5120.
Comment Date: 5 p.m. ET 5/9/24.
Docket Numbers: ER24–1787–000.
Applicants: H.A. Wagner LLC.
Description: § 205(d) Rate Filing: RMR
Arrangement—Continuing Operations
Rate Schedule to be effective 6/18/2024.
Filed Date: 4/18/24.
PO 00000
Frm 00069
Fmt 4703
Sfmt 4703
31195
Accession Number: 20240418–5128.
Comment Date: 5 p.m. ET 5/9/24.
Docket Numbers: ER24–1788–000.
Applicants: Dogwood Energy LLC.
Description: § 205(d) Rate Filing:
Amendment to Rate Schedule to be
effective 4/19/2024.
Filed Date: 4/18/24.
Accession Number: 20240418–5140.
Comment Date: 5 p.m. ET 5/9/24.
Docket Numbers: ER24–1789–000.
Applicants: Avista Corporation.
Description: § 205(d) Rate Filing:
Avista RS T1224 Haymaker Cert of
Concurrence to be effective 4/12/2024.
Filed Date: 4/18/24.
Accession Number: 20240418–5175.
Comment Date: 5 p.m. ET 5/9/24.
Docket Numbers: ER24–1790–000.
Applicants: Brandon Shores LLC.
Description: § 205(d) Rate Filing: RMR
Arrangement—Continuing Operations
Rate Schedule to be effective 6/18/2024.
Filed Date: 4/18/24.
Accession Number: 20240418–5176.
Comment Date: 5 p.m. ET 5/9/24.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/fercgen
search.asp) by querying the docket
number.
Any person desiring to intervene, to
protest, or to answer a complaint in any
of the above proceedings must file in
accordance with Rules 211, 214, or 206
of the Commission’s Regulations (18
CFR 385.211, 385.214, or 385.206) on or
before 5:00 p.m. Eastern time on the
specified comment date. Protests may be
considered, but intervention is
necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
E:\FR\FM\24APN1.SGM
24APN1
Agencies
[Federal Register Volume 89, Number 80 (Wednesday, April 24, 2024)]
[Notices]
[Pages 31194-31195]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-08777]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2628-066]
Alabama Power Company; Notice of Revised Procedural Schedule for
Environmental Impact Statement for the Proposed Project Relicense
On November 23, 2021, the Alabama Power Company filed an
application for a new major license for the 135-megawatt R.L. Harris
Hydroelectric Project No. 2628 (Harris Project or project). On March
31, 2023, Commission staff issued a notice of intent to prepare an
Environmental Impact Statement (EIS) to evaluate the effects of
relicensing the Harris Project. The notice of intent included a
schedule for preparing a draft and final EIS.
[[Page 31195]]
By this notice, Commission staff is updating the procedural
schedule for completing the EIS. The revised schedule is shown below.
Further revisions to the schedule may be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Issue draft EIS........................... July 2024.\1\
Public Meeting on draft EIS............... August 2024.
Comments on draft EIS due................. September 2024.
Commission issues final EIS............... March 2025.
------------------------------------------------------------------------
Any questions regarding this notice may be directed to Sarah
Salazar at (202) 502-6863 or [email protected].
---------------------------------------------------------------------------
\1\ The Council on Environmental Quality's (CEQ) regulations
under 40 CFR 1501.10(b)(2) (2023) require that EISs be completed
within 2 years of the federal action agency's decision to prepare an
EIS. See also National Environmental Policy Act, 42 U.S.C. 4321 et
seq., amended by section 107(g)(1)(A)(iii) of the Fiscal
Responsibility Act of 2023, Public Law 118-5, 4336a, 137 Stat. 42.
Dated: April 18, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-08777 Filed 4-23-24; 8:45 am]
BILLING CODE 6717-01-P