Ampersand Gilman Hydro LP; Notice of Authorization for Continued Project Operation, 26872 [2024-08077]

Download as PDF 26872 Federal Register / Vol. 89, No. 74 / Tuesday, April 16, 2024 / Notices collection techniques or other forms of information technology. Statutory Authority: 15 U.S.C. 772(b) and 42 U.S.C. 7101 et seq. Signed in Washington, DC, on April 11, 2024. Samson A. Adeshiyan, Director, Office of Statistical Methods and Research, U.S. Energy Information Administration. [FR Doc. 2024–08062 Filed 4–15–24; 8:45 am] BILLING CODE 6450–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 7189–000] khammond on DSKJM1Z7X2PROD with NOTICES Green Lake Water Power Company; Notice of Authorization for Continued Project Operation The license for the Green Lake Hydroelectric Project No. 7189 was issued for a period ending March 31, 2024. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the Commission, at the expiration of a license term, to issue from year-to-year an annual license to the then licensee(s) under the terms and conditions of the prior license until a new license is issued, or the project is otherwise disposed of as provided in section 15 or any other applicable section of the FPA. If the project’s prior license waived the applicability of section 15 of the FPA, then, based on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth at 18 CFR 16.21(a), if the licensee of such project has filed an application for a subsequent license, the licensee may continue to operate the project in accordance with the terms and conditions of the license after the minor or minor part license expires, until the Commission acts on its application. If the licensee of such a project has not filed an application for a subsequent license, then it may be required, pursuant to 18 CFR 16.21(b), to continue project operations until the Commission issues someone else a license for the project or otherwise orders disposition of the project. If the project is subject to section 15 of the FPA, notice is hereby given that an annual license for Project No. 7189 is issued to Green Lake Water Power Company for a period effective April 1, 2024, through March 31, 2025, or until the issuance of a new license for the project or other disposition under the FPA, whichever comes first. If issuance of a new license (or other disposition) does not take place on or VerDate Sep<11>2014 19:09 Apr 15, 2024 Jkt 262001 before March 31, 2025, notice is hereby given that, pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is renewed automatically without further order or notice by the Commission, unless the Commission orders otherwise. If the project is not subject to section 15 of the FPA, notice is hereby given that Green Lake Water Power Company is authorized to continue operation of the Green Lake Hydroelectric Project under the terms and conditions of the prior license until the issuance of a subsequent license for the project or other disposition under the FPA, whichever comes first. Dated: April 10, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–08080 Filed 4–15–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2392–000] Ampersand Gilman Hydro LP; Notice of Authorization for Continued Project Operation The license for the Gilman Hydroelectric Project No. 2392 was issued for a period ending March 31, 2024. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the Commission, at the expiration of a license term, to issue from year-to-year an annual license to the then licensee(s) under the terms and conditions of the prior license until a new license is issued, or the project is otherwise disposed of as provided in section 15 or any other applicable section of the FPA. If the project’s prior license waived the applicability of section 15 of the FPA, then, based on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth at 18 CFR 16.21(a), if the licensee of such project has filed an application for a subsequent license, the licensee may continue to operate the project in accordance with the terms and conditions of the license after the minor or minor part license expires, until the Commission acts on its application. If the licensee of such a project has not filed an application for a subsequent license, then it may be required, pursuant to 18 CFR 16.21(b), to continue project operations until the Commission issues someone else a license for the project or otherwise orders disposition of the project. PO 00000 Frm 00017 Fmt 4703 Sfmt 4703 If the project is subject to section 15 of the FPA, notice is hereby given that an annual license for Project No. 2392 is issued to Ampersand Gilman Hydro LP for a period effective April 1, 2024, through March 31, 2025, or until the issuance of a new license for the project or other disposition under the FPA, whichever comes first. If issuance of a new license (or other disposition) does not take place on or before March 31, 2025, notice is hereby given that, pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is renewed automatically without further order or notice by the Commission, unless the Commission orders otherwise. If the project is not subject to section 15 of the FPA, notice is hereby given that Ampersand Gilman Hydro LP is authorized to continue operation of the Gilman Hydroelectric Project under the terms and conditions of the prior license until the issuance of a subsequent license for the project or other disposition under the FPA, whichever comes first. Dated: April 10, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–08077 Filed 4–15–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 3025–000] Green Mountain Power Corporation; Notice of Authorization for Continued Project Operation The license for the Kelley’s Falls Hydroelectric Project No. 3025 was issued for a period ending March 31, 2024. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the Commission, at the expiration of a license term, to issue from year-to-year an annual license to the then licensee(s) under the terms and conditions of the prior license until a new license is issued, or the project is otherwise disposed of as provided in section 15 or any other applicable section of the FPA. If the project’s prior license waived the applicability of section 15 of the FPA, then, based on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth at 18 CFR 16.21(a), if the licensee of such project has filed an application for a subsequent license, the licensee may continue to operate the project in accordance with the terms E:\FR\FM\16APN1.SGM 16APN1

Agencies

[Federal Register Volume 89, Number 74 (Tuesday, April 16, 2024)]
[Notices]
[Page 26872]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-08077]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2392-000]


Ampersand Gilman Hydro LP; Notice of Authorization for Continued 
Project Operation

    The license for the Gilman Hydroelectric Project No. 2392 was 
issued for a period ending March 31, 2024.
    Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the 
Commission, at the expiration of a license term, to issue from year-to-
year an annual license to the then licensee(s) under the terms and 
conditions of the prior license until a new license is issued, or the 
project is otherwise disposed of as provided in section 15 or any other 
applicable section of the FPA. If the project's prior license waived 
the applicability of section 15 of the FPA, then, based on section 9(b) 
of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth 
at 18 CFR 16.21(a), if the licensee of such project has filed an 
application for a subsequent license, the licensee may continue to 
operate the project in accordance with the terms and conditions of the 
license after the minor or minor part license expires, until the 
Commission acts on its application. If the licensee of such a project 
has not filed an application for a subsequent license, then it may be 
required, pursuant to 18 CFR 16.21(b), to continue project operations 
until the Commission issues someone else a license for the project or 
otherwise orders disposition of the project.
    If the project is subject to section 15 of the FPA, notice is 
hereby given that an annual license for Project No. 2392 is issued to 
Ampersand Gilman Hydro LP for a period effective April 1, 2024, through 
March 31, 2025, or until the issuance of a new license for the project 
or other disposition under the FPA, whichever comes first.
    If issuance of a new license (or other disposition) does not take 
place on or before March 31, 2025, notice is hereby given that, 
pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1) 
of the FPA is renewed automatically without further order or notice by 
the Commission, unless the Commission orders otherwise.
    If the project is not subject to section 15 of the FPA, notice is 
hereby given that Ampersand Gilman Hydro LP is authorized to continue 
operation of the Gilman Hydroelectric Project under the terms and 
conditions of the prior license until the issuance of a subsequent 
license for the project or other disposition under the FPA, whichever 
comes first.

    Dated: April 10, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-08077 Filed 4-15-24; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.