Mississippi Hub, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed MS Hub Capacity Expansion Project, 26874-26876 [2024-08073]
Download as PDF
26874
Federal Register / Vol. 89, No. 74 / Tuesday, April 16, 2024 / Notices
company operating in the United
States.’’ 2
In the case of EWGs, the person filing
a notice of self-certification must also
file a copy of the notice of selfcertification with the state regulatory
authority of the state in which the
facility is located. In addition, that
person must represent to the
Commission in its submission that it has
filed a copy of the notice with the
appropriate state regulatory authority.3
Type of Respondents: EWGs and
FUCOs.
Estimate of Annual Burden: 4 The
Commission estimates the total annual
burden and cost 5 for this information
collection as follows.
FERC–598
[Self-certification for entities seeking exempt wholesale generator status or foreign utility company status]
A.
Number of respondents
(EWGs and FUCOs)
B.
Annual number of
responses per
respondent
C.
Total number of
responses
D.
Average burden hrs. & cost
($) per response
E.
Total annual burden hours &
total annual cost
F.
Average Cost per
respondent
($)
(Column C × Column D)
(Column E ÷ Column 1)
6 hrs.; $600 ............................
1,800 hrs.; $180,000 ..............
(Column A × Column B)
300 ..................................
1
300
Comments: Comments are invited on:
(1) whether the collection of
information is necessary for the proper
performance of the functions of the
Commission, including whether the
information will have practical utility;
(2) the accuracy of the agency’s estimate
of the burden and cost of the collection
of information, including the validity of
the methodology and assumptions used;
(3) ways to enhance the quality, utility,
and clarity of the information collection;
and (4) ways to minimize the burden of
the collection of information on those
who are to respond, including the use
of automated collection techniques or
other forms of information technology.
Dated: April 10, 2024.
Debbie-Anne Reese,
Acting Secretary.
[FR Doc. 2024–08075 Filed 4–15–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP24–80–000]
khammond on DSKJM1Z7X2PROD with NOTICES
Mississippi Hub, LLC; Notice of
Scoping Period Requesting Comments
on Environmental Issues for the
Proposed MS Hub Capacity Expansion
Project
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental document that will
discuss the environmental impacts of
the MS Hub Capacity Expansion Project
involving construction and operation of
facilities by Mississippi Hub, LLC (MS
Hub) in Simpson, Covington, and
2 Id.
3 18
CFR 366.7(a).
4 ‘‘Burden’’ is the total time, effort, or financial
resources expended by persons to generate,
maintain, retain, or disclose or provide information
VerDate Sep<11>2014
19:09 Apr 15, 2024
Jkt 262001
$600
Jefferson Davis Counties, Mississippi.
The Commission will use this
environmental document in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies regarding the
project. As part of the National
Environmental Policy Act (NEPA)
review process, the Commission takes
into account concerns the public may
have about proposals and the
environmental impacts that could result
from its action whenever it considers
the issuance of a Certificate of Public
Convenience and Necessity. This
gathering of public input is referred to
as ‘‘scoping.’’ The main goal of the
scoping process is to focus the analysis
in the environmental document on the
important environmental issues.
Additional information about the
Commission’s NEPA process is
described below in the NEPA Process
and Environmental Document section of
this notice.
By this notice, the Commission
requests public comments on the scope
of issues to address in the
environmental document. To ensure
that your comments are timely and
properly recorded, please submit your
comments so that the Commission
receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on May
10, 2024. Comments may be submitted
in written form. Further details on how
to submit comments are provided in the
Public Participation section of this
notice.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
Your input will help the Commission
staff determine what issues it needs to
evaluate in the environmental
document. Commission staff will
consider all written comments during
the preparation of the environmental
document.
If you submitted comments on this
project to the Commission before the
opening of this docket on March 5,
2024, you will need to file those
comments in Docket No. CP24–80–000
to ensure they are considered as part of
this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
easement agreement. You are not
required to enter into an agreement.
However, if the Commission approves
the project, the Natural Gas Act conveys
the right of eminent domain to the
company. Therefore, if you and the
company do not reach an easement
agreement, the pipeline company could
initiate condemnation proceedings in
court. In such instances, compensation
would be determined by a judge in
accordance with state law. The
Commission does not subsequently
grant, exercise, or oversee the exercise
of that eminent domain authority. The
to or for a Federal agency. For further explanation
of what is included in the information collection
burden, refer to 5 CFR 1320.3.
5 The Commission staff thinks that the average
respondent for this collection is similarly situated
to the Commission, in terms of salary plus benefits.
Based upon FERC’s FY 2024 annual full-time
equivalent average of $207,786 (for salary plus
benefits), the average hourly cost is $100 per hour.
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
E:\FR\FM\16APN1.SGM
16APN1
Federal Register / Vol. 89, No. 74 / Tuesday, April 16, 2024 / Notices
khammond on DSKJM1Z7X2PROD with NOTICES
courts have exclusive authority to
handle eminent domain cases; the
Commission has no jurisdiction over
these matters.
MS Hub provided landowners with a
fact sheet prepared by the FERC entitled
‘‘An Interstate Natural Gas Facility On
My Land? What Do I Need To Know?’’
which addresses typically asked
questions, including the use of eminent
domain and how to participate in the
Commission’s proceedings. This fact
sheet along with other landowner topics
of interest are available for viewing on
the FERC website (www.ferc.gov) under
the Natural Gas, Landowner Topics link.
Public Participation
There are three methods you can use
to submit your comments to the
Commission. Please carefully follow
these instructions so that your
comments are properly recorded. The
Commission encourages electronic filing
of comments and has staff available to
assist you at (866) 208–3676 or
FercOnlineSupport@ferc.gov.
(1) You can file your comments
electronically using the eComment
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. Using
eComment is an easy method for
submitting brief, text-only comments on
a project;
(2) You can file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. With
eFiling, you can provide comments in a
variety of formats by attaching them as
a file with your submission. New
eFiling users must first create an
account by clicking on ‘‘eRegister.’’ You
will be asked to select the type of filing
you are making; a comment on a
particular project is considered a
‘‘Comment on a Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
Commission. Be sure to reference the
project docket number (CP24–80–000)
on your letter. Submissions sent via the
U.S. Postal Service must be addressed
to: Debbie-Anne A. Reese, Acting
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Debbie-Anne A.
Reese, Acting Secretary, Federal Energy
Regulatory Commission, 12225 Wilkins
Avenue, Rockville, MD 20852.
Additionally, the Commission offers a
free service called eSubscription which
makes it easy to stay informed of all
issuances and submittals regarding the
dockets/projects to which you
VerDate Sep<11>2014
19:09 Apr 15, 2024
Jkt 262001
subscribe. These instant email
notifications are the fastest way to
receive notification and provide a link
to the document files which can reduce
the amount of time you spend
researching proceedings. Go to https://
www.ferc.gov/ferc-online/overview to
register for eSubscription.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members, and
others access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202)502–6595 or OPP@
ferc.gov.
Summary of the Proposed Project
In Simpson County, MS Hub would
make the following modifications to its
existing MS Hub Storage Facility:
• increase the certificated capacity of
Gas Storage Caverns No. 1 and No. 2 by
a total of 3.87 billion cubic feet (Bcf);
• construct three new gas storage
caverns Nos. 4, 5, and 6 totaling
approximately 33.9 Bcf of working gas
capacity;
• construct three electric motordriven compressor units each rated at
7,000 horsepower (hp) and two
Caterpillar model G3616 A4
reciprocating internal combustion
engine natural gas-fired compressor
units each rated at 5,500 hp, and
dehydration and ancillary equipment at
the existing Gas Handling Facility; and
• expand the existing Leaching
Facility for the solution mining of each
cavern by installing additional pumps,
water tanks and separators.
Also in Simpson County, MS Hub
would construct:
• one meter skid and one filter
separator on the existing Southern
Natural Gas (‘‘SONAT’’) Meter Station
site;
• four raw water wells Nos. 6 through
9;
• one new saltwater disposal well No.
9; and
• two saltwater disposal wells Nos. 5
and 7 collocated at the existing raw
water well No. 3 and saltwater disposal
well No. 3 wellpad.
In Covington County, MS Hub would
construct:
• two meter skids, two flow control
skids, and one filter separator on the
existing Transcontinental Gas Pipeline
(‘‘Transco’’) Meter Station site;
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
26875
• one meter skid and one filter
separator on the existing Southeast
Supply Header (‘‘SESH’’) Meter Station
site; and
• one booster compressor station
(‘‘MS Hub Booster Station’’) and
associated equipment at the site of the
existing Transco Meter Station
consisting of three Solar Mars model
100–16000S natural gas-fired turbine
compression units each rated at 13,486
hp.
In Jefferson Davis County, MS Hub
would construct:
• two saltwater disposal wells Nos. 6
and 8 at the existing raw water well No.
4 and saltwater disposal well No. 4
wellpad.
As the MS Hub Facility is currently
operational, the facilities contemplated
by the project would be added to
complement the current infrastructure.
Upon completion, the project would
add up to 0.7 Bcf per day of injection
capacity, and up to 1.0 Bcf per day of
delivery capacity, but would not
increase MS Hub’s maximum
certificated capacity withdrawal and
injection levels. With the additional
injection and delivery capacity, the MS
Hub Storage Facility would be capable
of providing additional high-turn
services to the Gulf Coast and Southeast
market areas.
The general location of the project
facilities is shown in appendix 1.1
Land Requirements for Construction
Construction of the project facilities
would disturb about 108.3 acres.
Following construction, MS Hub would
maintain about 75.6 acres for permanent
operation of the project’s facilities; the
remaining acreage would be restored
and revert to former uses.
NEPA Process and the Environmental
Document
Any environmental document issued
by the Commission will discuss impacts
that could occur as a result of the
construction and operation of the
proposed project under the relevant
general resource areas:
• geology and soils;
• water resources and wetlands;
• vegetation and wildlife;
• threatened and endangered species;
• cultural resources;
• land use;
• socioeconomics;
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of the
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary.’’ For instructions on
connecting to eLibrary, refer to the last page of this
notice. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll free, (886)
208–3676 or TTY (202) 502–8659.
E:\FR\FM\16APN1.SGM
16APN1
khammond on DSKJM1Z7X2PROD with NOTICES
26876
Federal Register / Vol. 89, No. 74 / Tuesday, April 16, 2024 / Notices
• environmental justice;
• air quality and noise; and
• reliability and safety.
Commission staff will also evaluate
reasonable alternatives to the proposed
project or portions of the project and
make recommendations on how to
lessen or avoid impacts on the various
resource areas. Your comments will
help Commission staff identify and
focus on the issues that might have an
effect on the human environment and
potentially eliminate others from further
study and discussion in the
environmental document.
Following this scoping period,
Commission staff will determine
whether to prepare an Environmental
Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the
EIS will present Commission staff’s
independent analysis of the issues. If
Commission staff prepares an EA, a
Notice of Schedule for the Preparation
of an Environmental Assessment will be
issued. The EA may be issued for an
allotted public comment period. The
Commission would consider timely
comments on the EA before making its
decision regarding the proposed project.
If Commission staff prepares an EIS, a
Notice of Intent to Prepare an EIS/
Notice of Schedule will be issued,
which will open up an additional
comment period. Staff will then prepare
a draft EIS which will be issued for
public comment. Commission staff will
consider all timely comments received
during the comment period on the draft
EIS and revise the document, as
necessary, before issuing a final EIS.
Any EA or draft and final EIS will be
available in electronic format in the
public record through eLibrary 2 and the
Commission’s natural gas
environmental documents web page
(https://www.ferc.gov/industries-data/
natural-gas/environment/
environmental-documents). If
eSubscribed, you will receive instant
email notification when the
environmental document is issued.
With this notice, the Commission is
asking agencies with jurisdiction by law
and/or special expertise with respect to
the environmental issues of this project
to formally cooperate in the preparation
of the environmental document.3
Agencies that would like to request
cooperating agency status should follow
the instructions for filing comments
2 For
instructions on connecting to eLibrary, refer
to the last page of this notice.
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Section 1501.8.
VerDate Sep<11>2014
19:09 Apr 15, 2024
Jkt 262001
provided under the Public Participation
section of this notice.
Consultation Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, the Commission is
using this notice to initiate consultation
with the applicable State Historic
Preservation Office(s), and to solicit
their views and those of other
government agencies, interested Indian
tribes, and the public on the project’s
potential effects on historic properties.4
The environmental document for this
project will document findings on the
impacts on historic properties and
summarize the status of consultations
under section 106.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project and includes a
mailing address with their comments.
Commission staff will update the
environmental mailing list as the
analysis proceeds to ensure that
Commission notices related to this
environmental review are sent to all
individuals, organizations, and
government entities interested in and/or
potentially affected by the proposed
project.
If you need to make changes to your
name/address, or if you would like to
remove your name from the mailing list,
please complete one of the following
steps:
(1) Send an email to
GasProjectAddressChange@ferc.gov
stating your request. You must include
the docket number CP24–80–000 in
your request. If you are requesting a
change to your address, please be sure
to include your name and the correct
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
address. If you are requesting to delete
your address from the mailing list,
please include your name and address
as it appeared on this notice. This email
address is unable to accept comments.
OR
(2) Return the attached ‘‘Mailing List
Update Form’’ (appendix 2).
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website at www.ferc.gov using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number in the ‘‘Docket Number’’
field. Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or (866)
208–3676, or for TTY, contact (202)
502–8659. The eLibrary link also
provides access to the texts of all formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
Public sessions or site visits will be
posted on the Commission’s calendar
located at https://www.ferc.gov/newsevents/events along with other related
information.
Dated: April 10, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–08073 Filed 4–15–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. AC24–40–000]
Black Hills Shoshone Pipeline, LLC;
Notice of Filing
Take notice that on April 5, 2024,
Black Hills Shoshone Pipeline LLC,
submitted a request for a two year
waiver of the Federal Energy Regulatory
Commission’s (Commission)
requirement to provide its certified
public accountant (CPA) certification
statement for the 2023 FERC Form No.
2–A on the basis of the calendar year
ending December 31.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
E:\FR\FM\16APN1.SGM
16APN1
Agencies
[Federal Register Volume 89, Number 74 (Tuesday, April 16, 2024)]
[Notices]
[Pages 26874-26876]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-08073]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP24-80-000]
Mississippi Hub, LLC; Notice of Scoping Period Requesting
Comments on Environmental Issues for the Proposed MS Hub Capacity
Expansion Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental document that will discuss
the environmental impacts of the MS Hub Capacity Expansion Project
involving construction and operation of facilities by Mississippi Hub,
LLC (MS Hub) in Simpson, Covington, and Jefferson Davis Counties,
Mississippi. The Commission will use this environmental document in its
decision-making process to determine whether the project is in the
public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies regarding the project. As part of the National Environmental
Policy Act (NEPA) review process, the Commission takes into account
concerns the public may have about proposals and the environmental
impacts that could result from its action whenever it considers the
issuance of a Certificate of Public Convenience and Necessity. This
gathering of public input is referred to as ``scoping.'' The main goal
of the scoping process is to focus the analysis in the environmental
document on the important environmental issues. Additional information
about the Commission's NEPA process is described below in the NEPA
Process and Environmental Document section of this notice.
By this notice, the Commission requests public comments on the
scope of issues to address in the environmental document. To ensure
that your comments are timely and properly recorded, please submit your
comments so that the Commission receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on May 10, 2024. Comments may be
submitted in written form. Further details on how to submit comments
are provided in the Public Participation section of this notice.
Your comments should focus on the potential environmental effects,
reasonable alternatives, and measures to avoid or lessen environmental
impacts. Your input will help the Commission staff determine what
issues it needs to evaluate in the environmental document. Commission
staff will consider all written comments during the preparation of the
environmental document.
If you submitted comments on this project to the Commission before
the opening of this docket on March 5, 2024, you will need to file
those comments in Docket No. CP24-80-000 to ensure they are considered
as part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable easement agreement. You
are not required to enter into an agreement. However, if the Commission
approves the project, the Natural Gas Act conveys the right of eminent
domain to the company. Therefore, if you and the company do not reach
an easement agreement, the pipeline company could initiate condemnation
proceedings in court. In such instances, compensation would be
determined by a judge in accordance with state law. The Commission does
not subsequently grant, exercise, or oversee the exercise of that
eminent domain authority. The
[[Page 26875]]
courts have exclusive authority to handle eminent domain cases; the
Commission has no jurisdiction over these matters.
MS Hub provided landowners with a fact sheet prepared by the FERC
entitled ``An Interstate Natural Gas Facility On My Land? What Do I
Need To Know?'' which addresses typically asked questions, including
the use of eminent domain and how to participate in the Commission's
proceedings. This fact sheet along with other landowner topics of
interest are available for viewing on the FERC website (www.ferc.gov)
under the Natural Gas, Landowner Topics link.
Public Participation
There are three methods you can use to submit your comments to the
Commission. Please carefully follow these instructions so that your
comments are properly recorded. The Commission encourages electronic
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected].
(1) You can file your comments electronically using the eComment
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. Using eComment is an easy method for
submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. With eFiling, you can provide comments
in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making; a comment on a particular project is considered a ``Comment
on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the project docket number (CP24-
80-000) on your letter. Submissions sent via the U.S. Postal Service
must be addressed to: Debbie-Anne A. Reese, Acting Secretary, Federal
Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any other carrier must be addressed to:
Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue, Rockville, MD 20852.
Additionally, the Commission offers a free service called
eSubscription which makes it easy to stay informed of all issuances and
submittals regarding the dockets/projects to which you subscribe. These
instant email notifications are the fastest way to receive notification
and provide a link to the document files which can reduce the amount of
time you spend researching proceedings. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members, and others access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202)502-6595 or [email protected].
Summary of the Proposed Project
In Simpson County, MS Hub would make the following modifications to
its existing MS Hub Storage Facility:
increase the certificated capacity of Gas Storage Caverns
No. 1 and No. 2 by a total of 3.87 billion cubic feet (Bcf);
construct three new gas storage caverns Nos. 4, 5, and 6
totaling approximately 33.9 Bcf of working gas capacity;
construct three electric motor-driven compressor units
each rated at 7,000 horsepower (hp) and two Caterpillar model G3616 A4
reciprocating internal combustion engine natural gas-fired compressor
units each rated at 5,500 hp, and dehydration and ancillary equipment
at the existing Gas Handling Facility; and
expand the existing Leaching Facility for the solution
mining of each cavern by installing additional pumps, water tanks and
separators.
Also in Simpson County, MS Hub would construct:
one meter skid and one filter separator on the existing
Southern Natural Gas (``SONAT'') Meter Station site;
four raw water wells Nos. 6 through 9;
one new saltwater disposal well No. 9; and
two saltwater disposal wells Nos. 5 and 7 collocated at
the existing raw water well No. 3 and saltwater disposal well No. 3
wellpad.
In Covington County, MS Hub would construct:
two meter skids, two flow control skids, and one filter
separator on the existing Transcontinental Gas Pipeline (``Transco'')
Meter Station site;
one meter skid and one filter separator on the existing
Southeast Supply Header (``SESH'') Meter Station site; and
one booster compressor station (``MS Hub Booster
Station'') and associated equipment at the site of the existing Transco
Meter Station consisting of three Solar Mars model 100-16000S natural
gas-fired turbine compression units each rated at 13,486 hp.
In Jefferson Davis County, MS Hub would construct:
two saltwater disposal wells Nos. 6 and 8 at the existing
raw water well No. 4 and saltwater disposal well No. 4 wellpad.
As the MS Hub Facility is currently operational, the facilities
contemplated by the project would be added to complement the current
infrastructure. Upon completion, the project would add up to 0.7 Bcf
per day of injection capacity, and up to 1.0 Bcf per day of delivery
capacity, but would not increase MS Hub's maximum certificated capacity
withdrawal and injection levels. With the additional injection and
delivery capacity, the MS Hub Storage Facility would be capable of
providing additional high-turn services to the Gulf Coast and Southeast
market areas.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
www.ferc.gov using the link called ``eLibrary.'' For instructions on
connecting to eLibrary, refer to the last page of this notice. For
assistance, contact FERC at [email protected] or call toll
free, (886) 208-3676 or TTY (202) 502-8659.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the project facilities would disturb about 108.3
acres. Following construction, MS Hub would maintain about 75.6 acres
for permanent operation of the project's facilities; the remaining
acreage would be restored and revert to former uses.
NEPA Process and the Environmental Document
Any environmental document issued by the Commission will discuss
impacts that could occur as a result of the construction and operation
of the proposed project under the relevant general resource areas:
geology and soils;
water resources and wetlands;
vegetation and wildlife;
threatened and endangered species;
cultural resources;
land use;
socioeconomics;
[[Page 26876]]
environmental justice;
air quality and noise; and
reliability and safety.
Commission staff will also evaluate reasonable alternatives to the
proposed project or portions of the project and make recommendations on
how to lessen or avoid impacts on the various resource areas. Your
comments will help Commission staff identify and focus on the issues
that might have an effect on the human environment and potentially
eliminate others from further study and discussion in the environmental
document.
Following this scoping period, Commission staff will determine
whether to prepare an Environmental Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the EIS will present Commission
staff's independent analysis of the issues. If Commission staff
prepares an EA, a Notice of Schedule for the Preparation of an
Environmental Assessment will be issued. The EA may be issued for an
allotted public comment period. The Commission would consider timely
comments on the EA before making its decision regarding the proposed
project. If Commission staff prepares an EIS, a Notice of Intent to
Prepare an EIS/Notice of Schedule will be issued, which will open up an
additional comment period. Staff will then prepare a draft EIS which
will be issued for public comment. Commission staff will consider all
timely comments received during the comment period on the draft EIS and
revise the document, as necessary, before issuing a final EIS. Any EA
or draft and final EIS will be available in electronic format in the
public record through eLibrary \2\ and the Commission's natural gas
environmental documents web page (https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents). If eSubscribed, you
will receive instant email notification when the environmental document
is issued.
---------------------------------------------------------------------------
\2\ For instructions on connecting to eLibrary, refer to the
last page of this notice.
---------------------------------------------------------------------------
With this notice, the Commission is asking agencies with
jurisdiction by law and/or special expertise with respect to the
environmental issues of this project to formally cooperate in the
preparation of the environmental document.\3\ Agencies that would like
to request cooperating agency status should follow the instructions for
filing comments provided under the Public Participation section of this
notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Section 1501.8.
---------------------------------------------------------------------------
Consultation Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, the Commission is using this notice to initiate
consultation with the applicable State Historic Preservation Office(s),
and to solicit their views and those of other government agencies,
interested Indian tribes, and the public on the project's potential
effects on historic properties.\4\ The environmental document for this
project will document findings on the impacts on historic properties
and summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project and includes a mailing address with their
comments. Commission staff will update the environmental mailing list
as the analysis proceeds to ensure that Commission notices related to
this environmental review are sent to all individuals, organizations,
and government entities interested in and/or potentially affected by
the proposed project.
If you need to make changes to your name/address, or if you would
like to remove your name from the mailing list, please complete one of
the following steps:
(1) Send an email to [email protected] stating your
request. You must include the docket number CP24-80-000 in your
request. If you are requesting a change to your address, please be sure
to include your name and the correct address. If you are requesting to
delete your address from the mailing list, please include your name and
address as it appeared on this notice. This email address is unable to
accept comments.
OR
(2) Return the attached ``Mailing List Update Form'' (appendix 2).
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website at www.ferc.gov using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number
in the ``Docket Number'' field. Be sure you have selected an
appropriate date range. For assistance, please contact FERC Online
Support at [email protected] or (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of all formal documents issued by the Commission, such as orders,
notices, and rulemakings.
Public sessions or site visits will be posted on the Commission's
calendar located at https://www.ferc.gov/news-events/events along with
other related information.
Dated: April 10, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-08073 Filed 4-15-24; 8:45 am]