ECOsponsible, LLC; Soliciting Notices of Intent To File a New License Application and Pre-Application Documents, 25256 [2024-07552]

Download as PDF 25256 Federal Register / Vol. 89, No. 70 / Wednesday, April 10, 2024 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 9709–071] ECOsponsible, LLC; Soliciting Notices of Intent To File a New License Application and Pre-Application Documents ddrumheller on DSK120RN23PROD with NOTICES1 The current license for the Herkimer Hydroelectric Project No. 9709 was issued to the original licensee, Trafalgar Power, Inc., on April 22, 1987, for a term of 40 years, ending March 31, 2027.1 The project has fallen into disrepair and has not operated since 2006. The license was transferred to the current licensee, ECOsponsible, LLC, (ECOsponsible) on March 12, 2015.2 The 1,680-kilowatt (kW) project is located on West Canada Creek in Herkimer County, New York. The project works consist of: (1) a timber crib dam with: (a) a 9-foot-high, 95-foot-long section with a crest elevation of 420.0 feet mean sea level (msl) and (b) a 12-foot-high, 145-footlong section with a crest elevation of 419.2 feet msl; (2) an impoundment with a surface area of 19 acres, a storage capacity of 163 acre-feet, and a normal water surface elevation of 420.5 feet msl; (3) timber flashboards; (4) an intake structure; (5) a reinforced concrete and steel powerhouse containing four turbine-generating units with a capacity of 400 kW each and an 80-kW minimum flow generator for a total installed capacity of 1,680 kW; (6) a 50-foot-long, 13.2-kilovolt transmission line; and (7) appurtenant facilities. At least five years before the expiration of a license for a major water power project subject to sections 14 and 15 of the Federal Power Act, the Commission’s regulations require the license applicant to file with the Commission a notice of intent (NOI) that contains an unequivocal statement of the licensee’s intention to file or not to file an application for a new license, details on the principal project works and installed plant capacity, and other information.3 Accordingly, NOIs for the 1 Trafalgar Power, Inc., 39 FERC ¶ 62,077 (1987). The original license was for a minor project with an authorized installed capacity of 1,050 kilowatts (kW). In 1988 Trafalgar Power applied to amend its license to increase the authorized installed capacity of the Herkimer Project to 1,680 kW. The increase caused the project to be redefined as a major project. Trafalgar Power, Inc., 48 FERC ¶ 62,105 (1989). 2 Trafalgar Power, Inc., 150 FERC ¶ 62,144 (2015). 3 18 CFR 5.5(d) (2023); id. at 16.6(b–c); see also 16 U.S.C. 808(b)(1) (‘‘Each existing licensee shall notify the Commission whether the licensee intends to file an application for a new license or not. Such VerDate Sep<11>2014 18:10 Apr 09, 2024 Jkt 262001 Herkimer Project were due by March 31, 2022. On March 9, 2022, Stone Ridge Hydro, LLC, filed an NOI to file an application for a small hydropower project exemption for the Herkimer Project, which was rejected on May 17, 2022.4 On March 31, 2022, Mr. Dennis Ryan, Jr. filed an NOI to file a relicense application for the Herkimer Project, which Commission staff is rejecting in an order issued in conjunction with this notice.5 Because all timely-filed NOIs have been rejected, the Commission is soliciting applications from applicants other than the existing licensee. An existing licensee that fails to timely file an NOI is prohibited from filing an application for a new license or exemption for the project, either individually or in conjunction with an entity or entities that are not currently licensees.6 Any party interested in filing a license application for the project must first file an NOI 7 and PAD 8 pursuant to part 5 of the Commission’s regulations. Although the integrated licensing process (ILP) is the default pre-filing process, section 5.3(b) of the Commission’s regulations allows a potential license applicant to request to use the traditional licensing process or alternative procedures when it files its NOI.9 This notice sets a deadline of 90 days from the date of this notice for interested applicants, other than the existing licensee, to file NOIs, PADs, and requests to use the traditional licensing process or alternative procedures. Applications for a new license from potential (non-licensee) applicants must be filed with the Commission at least 24 months prior to the expiration of the current license.10 notice shall be submitted at least 5 years before the expiration of the existing license. 4 Division of Hydropower Licensing May 17, 2022 Rejection of Notice of Intent. The Commission’s regulations state that if there is an unexpired license in effect for a project, the Commission will accept an application for exemption only if the exemption applicant is the licensee. 18 CFR 4.33(d)(ii) (2023); see also Stone Ridge Hydro, LLC, 180 FERC ¶ 61,123 (2022). 5 See Division of Hydropower Licensing April 2, 2024 Order Rejecting Notice of Intent and PreApplication Document. Commission staff finds: (1) Mr. Ryan, Jr. failed to demonstrate that the existing licensee filed the NOI, (2) the entity that filed the NOI was not a valid business entity at the time of filing, and (3) Mr. Ryan, Jr. was not authorized to act for the entity that filed the NOI. 6 18 CFR 16.24(a)(1) (2023); see also id. 16.23(a) (deeming failure to file an NOI as the same as filing an NOI indicating an intention not to file an application for a new license.). Note that this prohibition extends only to the existing licensee. 7 18 CFR 5.5 (2023). 8 18 CFR 5.6. 9 18 CFR 5.3(b). 10 18 CFR 16.9(b)(1). PO 00000 Frm 00027 Fmt 4703 Sfmt 4703 Because the current license expires on March 31, 2027, applications for a license for this project must be filed by March 31, 2025. Questions concerning this notice should be directed to Jody Callihan at (202) 502–8278 or jody.callihan@ ferc.gov. Dated: April 3, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–07552 Filed 4–9–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER24–1694–000] Groton BESS 1 LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding of Groton BESS 1 LLC’s application for marketbased rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is April 24, 2024. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, E:\FR\FM\10APN1.SGM 10APN1

Agencies

[Federal Register Volume 89, Number 70 (Wednesday, April 10, 2024)]
[Notices]
[Page 25256]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-07552]



[[Page 25256]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 9709-071]


ECOsponsible, LLC; Soliciting Notices of Intent To File a New 
License Application and Pre-Application Documents

    The current license for the Herkimer Hydroelectric Project No. 9709 
was issued to the original licensee, Trafalgar Power, Inc., on April 
22, 1987, for a term of 40 years, ending March 31, 2027.\1\ The project 
has fallen into disrepair and has not operated since 2006. The license 
was transferred to the current licensee, ECOsponsible, LLC, 
(ECOsponsible) on March 12, 2015.\2\ The 1,680-kilowatt (kW) project is 
located on West Canada Creek in Herkimer County, New York.
---------------------------------------------------------------------------

    \1\ Trafalgar Power, Inc., 39 FERC ] 62,077 (1987). The original 
license was for a minor project with an authorized installed 
capacity of 1,050 kilowatts (kW). In 1988 Trafalgar Power applied to 
amend its license to increase the authorized installed capacity of 
the Herkimer Project to 1,680 kW. The increase caused the project to 
be redefined as a major project. Trafalgar Power, Inc., 48 FERC ] 
62,105 (1989).
    \2\ Trafalgar Power, Inc., 150 FERC ] 62,144 (2015).
---------------------------------------------------------------------------

    The project works consist of: (1) a timber crib dam with: (a) a 9-
foot-high, 95-foot-long section with a crest elevation of 420.0 feet 
mean sea level (msl) and (b) a 12-foot-high, 145-foot-long section with 
a crest elevation of 419.2 feet msl; (2) an impoundment with a surface 
area of 19 acres, a storage capacity of 163 acre-feet, and a normal 
water surface elevation of 420.5 feet msl; (3) timber flashboards; (4) 
an intake structure; (5) a reinforced concrete and steel powerhouse 
containing four turbine-generating units with a capacity of 400 kW each 
and an 80-kW minimum flow generator for a total installed capacity of 
1,680 kW; (6) a 50-foot-long, 13.2-kilovolt transmission line; and (7) 
appurtenant facilities.
    At least five years before the expiration of a license for a major 
water power project subject to sections 14 and 15 of the Federal Power 
Act, the Commission's regulations require the license applicant to file 
with the Commission a notice of intent (NOI) that contains an 
unequivocal statement of the licensee's intention to file or not to 
file an application for a new license, details on the principal project 
works and installed plant capacity, and other information.\3\ 
Accordingly, NOIs for the Herkimer Project were due by March 31, 2022. 
On March 9, 2022, Stone Ridge Hydro, LLC, filed an NOI to file an 
application for a small hydropower project exemption for the Herkimer 
Project, which was rejected on May 17, 2022.\4\ On March 31, 2022, Mr. 
Dennis Ryan, Jr. filed an NOI to file a relicense application for the 
Herkimer Project, which Commission staff is rejecting in an order 
issued in conjunction with this notice.\5\
---------------------------------------------------------------------------

    \3\ 18 CFR 5.5(d) (2023); id. at 16.6(b-c); see also 16 U.S.C. 
808(b)(1) (``Each existing licensee shall notify the Commission 
whether the licensee intends to file an application for a new 
license or not. Such notice shall be submitted at least 5 years 
before the expiration of the existing license.
    \4\ Division of Hydropower Licensing May 17, 2022 Rejection of 
Notice of Intent. The Commission's regulations state that if there 
is an unexpired license in effect for a project, the Commission will 
accept an application for exemption only if the exemption applicant 
is the licensee. 18 CFR 4.33(d)(ii) (2023); see also Stone Ridge 
Hydro, LLC, 180 FERC ] 61,123 (2022).
    \5\ See Division of Hydropower Licensing April 2, 2024 Order 
Rejecting Notice of Intent and Pre-Application Document. Commission 
staff finds: (1) Mr. Ryan, Jr. failed to demonstrate that the 
existing licensee filed the NOI, (2) the entity that filed the NOI 
was not a valid business entity at the time of filing, and (3) Mr. 
Ryan, Jr. was not authorized to act for the entity that filed the 
NOI.
---------------------------------------------------------------------------

    Because all timely-filed NOIs have been rejected, the Commission is 
soliciting applications from applicants other than the existing 
licensee. An existing licensee that fails to timely file an NOI is 
prohibited from filing an application for a new license or exemption 
for the project, either individually or in conjunction with an entity 
or entities that are not currently licensees.\6\
---------------------------------------------------------------------------

    \6\ 18 CFR 16.24(a)(1) (2023); see also id. 16.23(a) (deeming 
failure to file an NOI as the same as filing an NOI indicating an 
intention not to file an application for a new license.). Note that 
this prohibition extends only to the existing licensee.
---------------------------------------------------------------------------

    Any party interested in filing a license application for the 
project must first file an NOI \7\ and PAD \8\ pursuant to part 5 of 
the Commission's regulations. Although the integrated licensing process 
(ILP) is the default pre-filing process, section 5.3(b) of the 
Commission's regulations allows a potential license applicant to 
request to use the traditional licensing process or alternative 
procedures when it files its NOI.\9\
---------------------------------------------------------------------------

    \7\ 18 CFR 5.5 (2023).
    \8\ 18 CFR 5.6.
    \9\ 18 CFR 5.3(b).
---------------------------------------------------------------------------

    This notice sets a deadline of 90 days from the date of this notice 
for interested applicants, other than the existing licensee, to file 
NOIs, PADs, and requests to use the traditional licensing process or 
alternative procedures. Applications for a new license from potential 
(non-licensee) applicants must be filed with the Commission at least 24 
months prior to the expiration of the current license.\10\ Because the 
current license expires on March 31, 2027, applications for a license 
for this project must be filed by March 31, 2025.
---------------------------------------------------------------------------

    \10\ 18 CFR 16.9(b)(1).
---------------------------------------------------------------------------

    Questions concerning this notice should be directed to Jody 
Callihan at (202) 502-8278 or [email protected].

    Dated: April 3, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-07552 Filed 4-9-24; 8:45 am]
BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.