Download as PDF Federal Register / Vol. 89, No. 59 / Tuesday, March 26, 2024 / Notices ddrumheller on DSK120RN23PROD with NOTICES1 To file via any other courier: DebbieAnne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852 The Commission encourages electronic filing of comments (options 1 and 2 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. Persons who comment on the environmental review of this project will be placed on the Commission’s environmental mailing list, and will receive notification when the environmental documents (EA or EIS) are issued for this project and will be notified of meetings associated with the Commission’s environmental review process. The Commission considers all comments received about the project in determining the appropriate action to be taken. However, the filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. For instructions on how to intervene, see below. Interventions Any person, which includes individuals, organizations, businesses, municipalities, and other entities,6 has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission’s orders in the U.S. Circuit Courts of Appeal. To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure 7 and the regulations under the NGA 8 by the intervention deadline for the project, which is April 10, 2024. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https://www.ferc.gov/ resources/guides/how-to/intervene.asp. There are two ways to submit your motion to intervene. In both instances, please reference the Project docket 9 The applicant has 15 days from the submittal of a motion to intervene to file a written objection to the intervention. 10 18 CFR 385.214(c)(1). 6 18 CFR 385.102(d). 7 18 CFR 385.214. 8 18 CFR 157.10. VerDate Sep<11>2014 18:10 Mar 25, 2024 number CP24–88–000 in your submission. (1) You may file your motion to intervene by using the Commission’s eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select ‘‘General’’ and then select ‘‘Intervention.’’ The eFiling feature includes a document-less intervention option; for more information, visit https://www.ferc.gov/docs-filing/efiling/ document-less-intervention.pdf; or (2) You can file a paper copy of your motion to intervene, along with three copies, by mailing the documents to the address below. Your motion to intervene must reference the Project docket number CP24–88–000. To file via USPS: Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426 To file via any other courier: DebbieAnne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852 The Commission encourages electronic filing of motions to intervene (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. Protests and motions to intervene must be served on the applicant either by mail at: Blair Lichtenwalter, Senior Director of Regulatory Affairs, 1300 Main Street, Houston, Texas 77002 or by email at blair.lichtenwalter@ energytransfer.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. Service can be via email with a link to the document. All timely, unopposed 9 motions to intervene are automatically granted by operation of Rule 214(c)(1).10 Motions to intervene that are filed after the intervention deadline are untimely, and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Jkt 262001 PO 00000 Frm 00020 Fmt 4703 Sfmt 4703 20959 Commission’s Rules and Regulations.11 A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s Office of External Affairs, at (866) 208– FERC, or on the FERC website at www.ferc.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/docs-filing/ esubscription.asp. Intervention Deadline: 5:00 p.m. Eastern Time on April 10, 2024. Dated: March 20, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–06425 Filed 3–25–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER17–405–003; ER17–406–003; EL23–51–002. Applicants: American Municipal Power, Inc., et al. v. AEP Appalachian Transmission Company Inc., et al., AEP Appalachian Transmission Company, Inc., Appalachian Power Company. Description: American Power East Companies submit compliance filing as directed by the January 18, 2024 Order. Filed Date: 3/18/24. Accession Number: 20240318–5279. Comment Date: 5 p.m. ET 4/8/24. Docket Numbers: ER24–943–001. Applicants: Cottontail Solar 5, LLC. 11 18 E:\FR\FM\26MRN1.SGM CFR 385.214(b)(3) and (d). 26MRN1 ddrumheller on DSK120RN23PROD with NOTICES1 20960 Federal Register / Vol. 89, No. 59 / Tuesday, March 26, 2024 / Notices Description: Compliance filing: Revised Rate Schedule FERC No. 1 to be effective 1/31/2024. Filed Date: 3/20/24. Accession Number: 20240320–5053. Comment Date: 5 p.m. ET 4/10/24. Docket Numbers: ER24–978–001. Applicants: Midcontinent Independent System Operator, Inc. Description: Tariff Amendment: 2024–03–20_SA 4228 GRE–OTPDiscovery Wind Sub Original GIA (S1036) to be effective 3/24/2024. Filed Date: 3/20/24. Accession Number: 20240320–5195. Comment Date: 5 p.m. ET 4/10/24. Docket Numbers: ER24–1030–001. Applicants: Arizona Public Service Company. Description: Tariff Amendment: Service Agreement No. 406, Amendment 3 Refile to be effective 3/ 30/2024. Filed Date: 3/20/24. Accession Number: 20240320–5106. Comment Date: 5 p.m. ET 4/1/24. Docket Numbers: ER24–1574–000. Applicants: PJM Interconnection, L.L.C. Description: Tariff Amendment: Notice of Cancellation of WMPA, SA No. 6072; Queue No. AF2–293 to be effective 5/10/2024. Filed Date: 3/20/24. Accession Number: 20240320–5064. Comment Date: 5 p.m. ET 4/10/24. Docket Numbers: ER24–1575–000. Applicants: PJM Interconnection, L.L.C. Description: 205(d) Rate Filing: Original NSA SA No. 7198, Queue No. AF1–130 to be effective 5/20/2024. Filed Date: 3/20/24. Accession Number: 20240320–5076. Comment Date: 5 p.m. ET 4/10/24. Docket Numbers: ER24–1576–000. Applicants: Maple Flats Solar Energy Center LLC. Description: Baseline eTariff Filing: Application for Market Based Rate Authorization to be effective 3/21/2024. Filed Date: 3/20/24. Accession Number: 20240320–5094. Comment Date: 5 p.m. ET 4/10/24. Docket Numbers: ER24–1577–000. Applicants: Arizona Public Service Company. Description: 205(d) Rate Filing: Rate Schedule No. 320, Babbitt Ranch Pseudo-Tie to be effective 5/20/2024. Filed Date: 3/20/24. Accession Number: 20240320–5099. Comment Date: 5 p.m. ET 4/10/24. Docket Numbers: ER24–1578–000. Applicants: Arizona Public Service Company. Description: 205(d) Rate Filing: Service Agreement No. 419, E&P w/ VerDate Sep<11>2014 18:10 Mar 25, 2024 Jkt 262001 Elisabeth Solar to be effective 3/11/ 2024. Filed Date: 3/20/24. Accession Number: 20240320–5112. Comment Date: 5 p.m. ET 4/10/24. Docket Numbers: ER24–1579–000. Applicants: Arizona Public Service Company. Description: 205(d) Rate Filing: Administrative Filing for Collation Correction to be effective 3/20/2024. Filed Date: 3/20/24. Accession Number: 20240320–5121. Comment Date: 5 p.m. ET 4/10/24. Docket Numbers: ER24–1580–000. Applicants: Alabama Power Company, Georgia Power Company, Mississippi Power Company. Description: 205(d) Rate Filing: Alabama Power Company submits tariff filing per 35.13(a)(2)(iii: Double Run Solar LGIA Amendment Filing to be effective 3/6/2024. Filed Date: 3/20/24. Accession Number: 20240320–5127. Comment Date: 5 p.m. ET 4/10/24. Docket Numbers: ER24–1581–000. Applicants: Alabama Power Company, Georgia Power Company, Mississippi Power Company. Description: 205(d) Rate Filing: Alabama Power Company submits tariff filing per 35.13(a)(2)(iii: Kirkham Solar Farms I (Kirkham L&MA) LGIA Filing to be effective 3/8/2024. Filed Date: 3/20/24. Accession Number: 20240320–5129. Comment Date: 5 p.m. ET 4/10/24. Docket Numbers: ER24–1582–000. Applicants: Southwest Power Pool, Inc. Description: 205(d) Rate Filing: 4239 Little Blue Wind II GIA to be effective 3/12/2024. Filed Date: 3/20/24. Accession Number: 20240320–5143. Comment Date: 5 p.m. ET 4/10/24. Docket Numbers: ER24–1583–000. Applicants: Southwest Power Pool, Inc. Description: 205(d) Rate Filing: Revisions to Att J to Reallocate Remaining ATRR for Byway Upgrades (RR 584) to be effective 6/1/2024. Filed Date: 3/20/24. Accession Number: 20240320–5166. Comment Date: 5 p.m. ET 4/10/24. Docket Numbers: ER24–1584–000. Applicants: Tucson Electric Power Company. Description: 205(d) Rate Filing: Concurrence to PSE Rate Schedule No. 160 to be effective 5/1/2024. Filed Date: 3/20/24. Accession Number: 20240320–5172. Comment Date: 5 p.m. ET 4/10/24. Docket Numbers: ER24–1585–000. PO 00000 Frm 00021 Fmt 4703 Sfmt 4703 Applicants: California State University Channel Islands Site Authority. Description: 205(d) Rate Filing: CSUCI–SA Settlement Agreement with Participants to be effective 2/1/2022. Filed Date: 3/20/24. Accession Number: 20240320–5182. Comment Date: 5 p.m. ET 4/10/24. Docket Numbers: ER24–1586–000. Applicants: Midcontinent Independent System Operator, Inc. Description: Compliance filing: 2024– 03–20_MISO Petition for a Prospective Tariff Waiver of SPP Tariff to be effective N/A. Filed Date: 3/20/24. Accession Number: 20240320–5193. Comment Date: 5 p.m. ET 4/10/24. Take notice that the Commission received the following electric reliability filings: Docket Numbers: RR24–2–000. Applicants: North American Electric Reliability Corporation. Description: Petition of the North American Electric Reliability Corporation for approval of revisions to the NERC Rules of Procedure to address unregistered inverter-based resources. Filed Date: 3/19/24. Accession Number: 20240319–5204. Comment Date: 5 p.m. ET 4/18/24. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/fercgen search.asp) by querying the docket number. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as E:\FR\FM\26MRN1.SGM 26MRN1 Federal Register / Vol. 89, No. 59 / Tuesday, March 26, 2024 / Notices interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: March 20, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–06427 Filed 3–25–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: ddrumheller on DSK120RN23PROD with NOTICES1 Filings Instituting Proceedings Docket Numbers: RP24–534–000. Applicants: UGI Sunbury, LLC. Description: 4(d) Rate Filing: Annual Retainage Adjustment 2024 w/Waivers to be effective 4/1/2024. Filed Date: 3/19/24. Accession Number: 20240319–5131. Comment Date: 5 p.m. ET 4/1/24. Docket Numbers: RP24–535–000. Applicants: Northwest Pipeline LLC. Description: 4(d) Rate Filing: Non Conforming Service Agreement— Spotlight to be effective 4/1/2024. Filed Date: 3/19/24. Accession Number: 20240319–5171. Comment Date: 5 p.m. ET 4/1/24. Docket Numbers: RP24–536–000. Applicants: Equitrans, L.P. Description: 4(d) Rate Filing: Negotiated Rate Agreement—4/1/2024 to be effective 4/1/2024. Filed Date: 3/20/24. Accession Number: 20240320–5016. Comment Date: 5 p.m. ET 4/1/24. Docket Numbers: RP24–537–000. Applicants: Iroquois Gas Transmission System, L.P. Description: 4(d) Rate Filing: 3.20.24 Negotiated Rates—Emera Energy Services, Inc. R–2715–86 to be effective 4/1/2024. Filed Date: 3/20/24. Accession Number: 20240320–5041. Comment Date: 5 p.m. ET 4/1/24. Docket Numbers: RP24–538–000. Applicants: Iroquois Gas Transmission System, L.P. Description: 4(d) Rate Filing: 3.20.24 Negotiated Rates—Emera Energy Services, Inc. R–2715–87 to be effective 4/1/2024. Filed Date: 3/20/24. Accession Number: 20240320–5046. Comment Date: 5 p.m. ET 4/1/24. Docket Numbers: RP24–539–000. VerDate Sep<11>2014 18:10 Mar 25, 2024 Jkt 262001 Applicants: Iroquois Gas Transmission System, L.P. Description: 4(d) Rate Filing: 3.20.24 Negotiated Rates—Koch Energy Services, LLC R–7755–05 to be effective 4/1/2024. Filed Date: 3/20/24. Accession Number: 20240320–5049. Comment Date: 5 p.m. ET 4/1/24. Docket Numbers: RP24–540–000. Applicants: Iroquois Gas Transmission System, L.P. Description: 4(d) Rate Filing: 3.20.24 Negotiated Rates—Koch Energy Services, LLC R–7755–06 to be effective 4/1/2024. Filed Date: 3/20/24. Accession Number: 20240320–5052. Comment Date: 5 p.m. ET 4/1/24. Docket Numbers: RP24–541–000. Applicants: Big Sandy Pipeline, LLC, Bobcat Gas Storage, East Tennessee Natural Gas, LLC, Egan Hub Storage, LLC, Garden Banks Gas Pipeline, LLC, Maritimes & Northeast Pipeline, L.L.C., Mississippi Canyon Gas Pipeline, L.L.C., Moss Bluff Hub, LLC, Nautilus Pipeline Company, L.L.C., NEXUS Gas Transmission, LLC, Sabal Trail Transmission, LLC, Saltville Gas Storage Company L.L.C., Southeast Supply Header, LLC, Steckman Ridge, LP, Texas Eastern Transmission, LP, Tres Palacios Gas Storage LLC, Algonquin Gas Transmission, LLC. Description: Compliance filing: Big Sandy Pipeline, LLC submits tariff filing per 154.203: Enbridge (U.S.) Pipelines— LINK System Maintenance—Request for Waivers 2024 to be effective N/A. Filed Date: 3/20/24. Accession Number: 20240320–5058. Comment Date: 5 p.m. ET 4/1/24. Docket Numbers: RP24–542–000. Applicants: Bear Creek Storage Company, L.L.C. Description: Compliance filing: Annual Report on Operational Transactions 2024 to be effective N/A. Filed Date: 3/20/24. Accession Number: 20240320–5087. Comment Date: 5 p.m. ET 4/1/24. Docket Numbers: RP24–543–000. Applicants: Algonquin Gas Transmission, LLC. Description: 4(d) Rate Filing: Negotiated Rates—Yankee Gas to Emera Energy eff 3–20–24 to be effective 3/20/ 2024. Filed Date: 3/20/24. Accession Number: 20240320–5100. Comment Date: 5 p.m. ET 4/1/24. Docket Numbers: RP24–544–000. Applicants: Portland Natural Gas Transmission System. Description: 4(d) Rate Filing: Northern Utliites Neg Rate Agreement #284292 to be effective 4/1/2024. PO 00000 Frm 00022 Fmt 4703 Sfmt 4703 20961 Filed Date: 3/20/24. Accession Number: 20240320–5103. Comment Date: 5 p.m. ET 4/1/24. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.vferc.gov/idmws/search/fercgen search.asp) by querying the docket number. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: March 20, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–06426 Filed 3–25–24; 8:45 am] BILLING CODE 6717–01–P ENVIRONMENTAL PROTECTION AGENCY [FRL–11849–01–OAR] Notice of Denial of Petition for Partial Waiver of 2023 Cellulosic Biofuel Standard Under the Renewable Fuel Standard Program Environmental Protection Agency (EPA). ACTION: Denial of petition. AGENCY: The Environmental Protection Agency (EPA) is providing notice of its final action entitled Denial of AFPM Petition for Partial Waiver of 2023 Cellulosic Biofuel Standard (‘‘AFPM Petition Denial Action’’), in which EPA SUMMARY: E:\FR\FM\26MRN1.SGM 26MRN1

Agencies

[Federal Register Volume 89, Number 59 (Tuesday, March 26, 2024)]
[Notices]
[Pages 20959-20961]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-06427]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Combined Notice of Filings #1

    Take notice that the Commission received the following electric 
rate filings:

    Docket Numbers: ER17-405-003; ER17-406-003; EL23-51-002.
    Applicants: American Municipal Power, Inc., et al. v. AEP 
Appalachian Transmission Company Inc., et al., AEP Appalachian 
Transmission Company, Inc., Appalachian Power Company.
    Description: American Power East Companies submit compliance filing 
as directed by the January 18, 2024 Order.
    Filed Date: 3/18/24.
    Accession Number: 20240318-5279.
    Comment Date: 5 p.m. ET 4/8/24.

    Docket Numbers: ER24-943-001.
    Applicants: Cottontail Solar 5, LLC.

[[Page 20960]]

    Description: Compliance filing: Revised Rate Schedule FERC No. 1 to 
be effective 1/31/2024.
    Filed Date: 3/20/24.
    Accession Number: 20240320-5053.
    Comment Date: 5 p.m. ET 4/10/24.

    Docket Numbers: ER24-978-001.
    Applicants: Midcontinent Independent System Operator, Inc.
    Description: Tariff Amendment: 2024-03-20_SA 4228 GRE-OTP-Discovery 
Wind Sub Original GIA (S1036) to be effective 3/24/2024.
    Filed Date: 3/20/24.
    Accession Number: 20240320-5195.
    Comment Date: 5 p.m. ET 4/10/24.

    Docket Numbers: ER24-1030-001.
    Applicants: Arizona Public Service Company.
    Description: Tariff Amendment: Service Agreement No. 406, Amendment 
3 Refile to be effective 3/30/2024.
    Filed Date: 3/20/24.
    Accession Number: 20240320-5106.
    Comment Date: 5 p.m. ET 4/1/24.

    Docket Numbers: ER24-1574-000.
    Applicants: PJM Interconnection, L.L.C.
    Description: Tariff Amendment: Notice of Cancellation of WMPA, SA 
No. 6072; Queue No. AF2-293 to be effective 5/10/2024.
    Filed Date: 3/20/24.
    Accession Number: 20240320-5064.
    Comment Date: 5 p.m. ET 4/10/24.

    Docket Numbers: ER24-1575-000.
    Applicants: PJM Interconnection, L.L.C.
    Description: 205(d) Rate Filing: Original NSA SA No. 7198, Queue 
No. AF1-130 to be effective 5/20/2024.
    Filed Date: 3/20/24.
    Accession Number: 20240320-5076.
    Comment Date: 5 p.m. ET 4/10/24.

    Docket Numbers: ER24-1576-000.
    Applicants: Maple Flats Solar Energy Center LLC.
    Description: Baseline eTariff Filing: Application for Market Based 
Rate Authorization to be effective 3/21/2024.
    Filed Date: 3/20/24.
    Accession Number: 20240320-5094.
    Comment Date: 5 p.m. ET 4/10/24.

    Docket Numbers: ER24-1577-000.
    Applicants: Arizona Public Service Company.
    Description: 205(d) Rate Filing: Rate Schedule No. 320, Babbitt 
Ranch Pseudo-Tie to be effective 5/20/2024.
    Filed Date: 3/20/24.
    Accession Number: 20240320-5099.
    Comment Date: 5 p.m. ET 4/10/24.

    Docket Numbers: ER24-1578-000.
    Applicants: Arizona Public Service Company.
    Description: 205(d) Rate Filing: Service Agreement No. 419, E&P w/
Elisabeth Solar to be effective 3/11/2024.
    Filed Date: 3/20/24.
    Accession Number: 20240320-5112.
    Comment Date: 5 p.m. ET 4/10/24.

    Docket Numbers: ER24-1579-000.
    Applicants: Arizona Public Service Company.
    Description: 205(d) Rate Filing: Administrative Filing for 
Collation Correction to be effective 3/20/2024.
    Filed Date: 3/20/24.
    Accession Number: 20240320-5121.
    Comment Date: 5 p.m. ET 4/10/24.

    Docket Numbers: ER24-1580-000.
    Applicants: Alabama Power Company, Georgia Power Company, 
Mississippi Power Company.
    Description: 205(d) Rate Filing: Alabama Power Company submits 
tariff filing per 35.13(a)(2)(iii: Double Run Solar LGIA Amendment 
Filing to be effective 3/6/2024.
    Filed Date: 3/20/24.
    Accession Number: 20240320-5127.
    Comment Date: 5 p.m. ET 4/10/24.

    Docket Numbers: ER24-1581-000.
    Applicants: Alabama Power Company, Georgia Power Company, 
Mississippi Power Company.
    Description: 205(d) Rate Filing: Alabama Power Company submits 
tariff filing per 35.13(a)(2)(iii: Kirkham Solar Farms I (Kirkham L&MA) 
LGIA Filing to be effective 3/8/2024.
    Filed Date: 3/20/24.
    Accession Number: 20240320-5129.
    Comment Date: 5 p.m. ET 4/10/24.

    Docket Numbers: ER24-1582-000.
    Applicants: Southwest Power Pool, Inc.
    Description: 205(d) Rate Filing: 4239 Little Blue Wind II GIA to be 
effective 3/12/2024.
    Filed Date: 3/20/24.
    Accession Number: 20240320-5143.
    Comment Date: 5 p.m. ET 4/10/24.

    Docket Numbers: ER24-1583-000.
    Applicants: Southwest Power Pool, Inc.
    Description: 205(d) Rate Filing: Revisions to Att J to Reallocate 
Remaining ATRR for Byway Upgrades (RR 584) to be effective 6/1/2024.
    Filed Date: 3/20/24.
    Accession Number: 20240320-5166.
    Comment Date: 5 p.m. ET 4/10/24.

    Docket Numbers: ER24-1584-000.
    Applicants: Tucson Electric Power Company.
    Description: 205(d) Rate Filing: Concurrence to PSE Rate Schedule 
No. 160 to be effective 5/1/2024.
    Filed Date: 3/20/24.
    Accession Number: 20240320-5172.
    Comment Date: 5 p.m. ET 4/10/24.

    Docket Numbers: ER24-1585-000.
    Applicants: California State University Channel Islands Site 
Authority.
    Description: 205(d) Rate Filing: CSUCI-SA Settlement Agreement with 
Participants to be effective 2/1/2022.
    Filed Date: 3/20/24.
    Accession Number: 20240320-5182.
    Comment Date: 5 p.m. ET 4/10/24.

    Docket Numbers: ER24-1586-000.
    Applicants: Midcontinent Independent System Operator, Inc.
    Description: Compliance filing: 2024-03-20_MISO Petition for a 
Prospective Tariff Waiver of SPP Tariff to be effective N/A.
    Filed Date: 3/20/24.
    Accession Number: 20240320-5193.
    Comment Date: 5 p.m. ET 4/10/24.

    Take notice that the Commission received the following electric 
reliability filings:

    Docket Numbers: RR24-2-000.
    Applicants: North American Electric Reliability Corporation.
    Description: Petition of the North American Electric Reliability 
Corporation for approval of revisions to the NERC Rules of Procedure to 
address unregistered inverter-based resources.
    Filed Date: 3/19/24.
    Accession Number: 20240319-5204.
    Comment Date: 5 p.m. ET 4/18/24.

    The filings are accessible in the Commission's eLibrary system 
(https://elibrary.ferc.gov/idmws/search/fercgensearch.asp) by querying 
the docket number.
    Any person desiring to intervene, to protest, or to answer a 
complaint in any of the above proceedings must file in accordance with 
Rules 211, 214, or 206 of the Commission's Regulations (18 CFR 385.211, 
385.214, or 385.206) on or before 5:00 p.m. Eastern time on the 
specified comment date. Protests may be considered, but intervention is 
necessary to become a party to the proceeding.
    eFiling is encouraged. More detailed information relating to filing 
requirements, interventions, protests, service, and qualifying 
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676 
(toll free). For TTY, call (202) 502-8659.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as

[[Page 20961]]

interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].

    Dated: March 20, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-06427 Filed 3-25-24; 8:45 am]
BILLING CODE 6717-01-P