Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions; Northfield Mountain LLC, 14827-14828 [2024-04174]
Download as PDF
Federal Register / Vol. 89, No. 41 / Thursday, February 29, 2024 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2333–094]
khammond on DSKJM1Z7X2PROD with NOTICES
Notice of Availability of Draft
Environmental Assessment; Rumford
Falls Hydro LLC
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s (Commission)
regulations, 18 CFR part 380, the Office
of Energy Projects has reviewed the
application for license for the Rumford
Falls Hydroelectric Project, located on
the Androscoggin River in the Town of
Rumford, Oxford County, Maine and
has prepared a Draft Environmental
Assessment (DEA) for the project. No
federal land is occupied by project
works or located within the project
boundary.
The DEA contains staff’s analysis of
the potential environmental impacts of
the project and concludes that licensing
the project, with appropriate
environmental protective measures,
would not constitute a major federal
action that would significantly affect the
quality of the human environment.
The Commission provides all
interested persons with an opportunity
to view and/or print the DEA via the
internet through the Commission’s
Home Page (https://www.ferc.gov/), using
the ‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits
in the docket number field, to access the
document. For assistance, contact FERC
Online Support at FERCOnline
Support@ferc.gov, or toll-free at (866)
208–3676, or for TTY, (202) 502–8659.
You may also register online at
https://ferconline.ferc.gov/
eSubscription.aspx to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Any comments should be filed within
30 days from the date of this notice.
The Commission strongly encourages
electronic filing. Please file comments
using the Commission’s eFiling system
at https://ferconline.ferc.gov/
FERCOnline.aspx. Commenters can
submit brief comments up to 6,000
characters, without prior registration,
using the eComment system at https://
ferconline.ferc.gov/QuickComment.
aspx. You must include your name and
contact information at the end of your
comments. For assistance, please
contact FERC Online Support. In lieu of
electronic filing, you may submit a
paper copy. Submissions sent via the
VerDate Sep<11>2014
16:39 Feb 28, 2024
Jkt 262001
U.S. Postal Service must be addressed
to: Debbie-Anne A. Reese, Acting
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first
page of any filing should include docket
number P–4784–106.
Any questions regarding this notice
may be directed to Ryan Hansen at (202)
502–8074 or ryan.hansen@ferc.gov.
Dated: February 22, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–04175 Filed 2–28–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2485–071]
Notice of Application Accepted for
Filing, Soliciting Motions To Intervene
and Protests, Ready for Environmental
Analysis, and Soliciting Comments,
Recommendations, Preliminary Terms
and Conditions, and Preliminary
Fishway Prescriptions; Northfield
Mountain LLC
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 2485–071.
c. Date Filed: April 29, 2016; material
amendment filed December 4, 2020.
d. Applicant: Northfield Mountain
LLC (Northfield).
e. Name of Project: Northfield
Mountain Pumped Storage Project
(project).
f. Location: The project is located on
the Connecticut River in Windham
County, Vermont, Cheshire County,
New Hampshire, and Franklin County,
Massachusetts.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Alan
Douglass, Regulatory Compliance
Manager, 99 Millers Falls Road,
Northfield, MA 01360; (413) 659–4416
or alan.douglass@firstlightpower.com.
i. FERC Contact: Steve Kartalia, (202)
502–6131 or stephen.kartalia@ferc.gov.
j. Deadline for filing motions to
intervene and protests, comments,
recommendations, preliminary terms
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
14827
and conditions, and preliminary
fishway prescriptions: 60 days from the
issuance date of this notice; reply
comments are due 105 days from the
issuance date of this notice.
The Commission strongly encourages
electronic filing. Please file motions to
intervene and protests, comments,
recommendations, terms and
conditions, and prescriptions using the
Commission’s eFiling system at https://
ferconline.ferc.gov/FERCOnline.aspx.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://ferconline.ferc.gov/
QuickComment.aspx. You must include
your name and contact information at
the end of your comments. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, you may submit a
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Debbie-Anne A. Reese, Acting
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Debbie-Anne A.
Reese, Acting Secretary, Federal Energy
Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852.
The first page of any filing should
include docket number P–2485–071.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
and is ready for environmental analysis
at this time.
l. Project Description: The Northfield
Mountain Pumped Storage Project
consists of: (1) a 1-mile-long, 30-footwide, 30- to 140-foot-high main dam
that includes: (i) an intake structure
with two 7-foot-wide, 9-foot-high sluice
gates and an 8-foot-diameter outlet pipe;
and (ii) a 589-foot-long, 2-foot-diameter
low-level outlet pipe; (2) a 425-footlong, 25-foot-high dike (North dike); (3)
a 2,800-foot-long, 45-foot-high dike
(Northwest dike); (4) a 1,700-foot-long,
40-foot-long dike (West dike); (5) a 327foot-long, 10- to 20-foot-high gravity
dam; (6) an ungated 550-foot-long, 6foot-high spillway structure with a 20foot-long notch at an elevation of
E:\FR\FM\29FEN1.SGM
29FEN1
khammond on DSKJM1Z7X2PROD with NOTICES
14828
Federal Register / Vol. 89, No. 41 / Thursday, February 29, 2024 / Notices
1,005.0 feet National Geodetic Vertical
Datum of 1929 (NGVD 29); (7) a 286acre impoundment (upper reservoir)
with a useable storage volume of 12,318
acre-feet between elevations 938.0 feet
and 1,000.5 feet NGVD 29; (8) a 2,110acre impoundment (lower reservoir or
Turners Falls impoundment); (9) a
1,890-foot-long, 130-foot-wide intake
channel with a 63-foot-long, 9-foot-high
submerged check dam and two 6-footwide, 2.75-foot-high sluice gates and
two 18-foot-wide stoplogs; (10) a 200foot-long, 55-foot-wide, 80-foot-high
pressure shaft; (11) an 853-foot-long, 31foot-diameter penstock; (12) two 22foot-diameter, 100- to 150-foot-long
penstocks; (13) four 340-foot-long, 9.5to 14-foot-diameter penstocks; (14) a
328-foot-long, 70-foot-wide powerhouse
that contains four reversible pump
turbine-generator units with a total
installed capacity of 1,166.8 megawatts
(MW); (15) four 25-foot-long, 11-footdiameter draft tubes that transition to a
20-foot-long, 17-foot-diameter draft
tube; (16) a 5,136-foot-long, 33-footwide, 31-foot-high horseshoe-shaped
tailrace tunnel; (17) 35-foot-long, 40foot-high trapezoid-shaped stoplogs
with 74.3- to 99.5-foot-wide, 48-foothigh trashracks with 6-inch clear-bar
spacing; (18) four 26-foot-long, 13.8kilovolt (kV) generator leads that
connect the turbine-generator units to
four transformers; (19) two 3,000-footlong, 345-kV transmission lines; and
(20) appurtenant facilities.
The Northfield Mountain Pumped
Storage Project generally operates in
pumping mode when electricity
demand is low and generating mode
when electricity demand is high. In the
summer and winter, the project
generally operates in a peaking mode in
the morning and late afternoon. In the
spring and fall, the project may operate
in a peaking mode one or two times a
day depending on electricity demand.
The existing license requires
maintaining the upper reservoir
between elevations 938.0 feet and
1,000.5 feet NGVD 29 (i.e., a maximum
reservoir drawdown of 62.5 feet).
Average annual generation at the
Northfield Mountain Project from 2011–
2019 was 889,845 MW-hours, and
average annual energy consumption for
pumping from 2011 to 2019 was
1,189,640 MW-hours.
Northfield proposes three changes to
the current project boundary: (1) remove
0.2 acre of land associated with
residential property; (2) remove 8.1
acres of land referred to as ‘‘Fuller
Farm’’ that include residential and
agricultural structures; and (3) add
135.5 acres of land that include
recreation trails.
VerDate Sep<11>2014
16:39 Feb 28, 2024
Jkt 262001
Northfield proposes to increase the
maximum water surface elevation of the
upper reservoir to 1,004.5 feet NGVD 29
and decrease the minimum water
surface elevation of the upper reservoir
to 920.0 feet NGVD 29 (i.e., a maximum
reservoir drawdown of 84.5 feet) yearround. Northfield proposes to install a
barrier net in the lower impoundment to
prevent fish entrainment. Northfield
also proposes to periodically dredge the
upper reservoir and to construct new
recreation access trails. The specific
proposed changes are described in the
amended application and the settlement
agreements filed on March 31, 2023 and
June 12, 2023.
m. A copy of the application can be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
n. Anyone may submit comments, a
protest, or a motion to intervene in
accordance with the requirements of
Rules of Practice and Procedure, 18 CFR
385.210, .211, and .214. In determining
the appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
All filings must: (1) bear in all capital
letters the title ‘‘PROTEST,’’ ‘‘MOTION
TO INTERVENE,’’ ‘‘COMMENTS,’’
‘‘REPLY COMMENTS,’’
‘‘RECOMMENDATIONS,’’
‘‘PRELIMINARY TERMS AND
CONDITIONS,’’ or ‘‘PRELIMINARY
FISHWAY PRESCRIPTIONS;’’ (2) set
forth in the heading the name of the
applicant and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
submitting the filing; and (4) otherwise
comply with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, recommendations, terms and
conditions, or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. A copy of all other filings
in reference to this application must be
accompanied by proof of service on all
PO 00000
Frm 00029
Fmt 4703
Sfmt 4703
persons listed on the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b) and 385.2010.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
You may also register online at
https://ferconline.ferc.gov/FERCOnline.
aspx to be notified via email of new
filings and issuances related to this or
other pending projects. For assistance,
contact FERC Online Support.
o. The applicant must file no later
than 60 days following the date of
issuance of this notice: (1) a copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
p. Procedural Schedule: The
application will be processed according
to the following schedule. Revisions to
the schedule will be made as
appropriate.
Milestone
Deadline for filing motions to intervene, protests, comments, recommendations, preliminary terms
and conditions, and preliminary
fishway prescriptions.
Deadline for filing reply comments ...
Target date
April 2024.
May 2024.
q. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of this notice.
Dated: February 22, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–04174 Filed 2–28–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
E:\FR\FM\29FEN1.SGM
29FEN1
Agencies
[Federal Register Volume 89, Number 41 (Thursday, February 29, 2024)]
[Notices]
[Pages 14827-14828]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-04174]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2485-071]
Notice of Application Accepted for Filing, Soliciting Motions To
Intervene and Protests, Ready for Environmental Analysis, and
Soliciting Comments, Recommendations, Preliminary Terms and Conditions,
and Preliminary Fishway Prescriptions; Northfield Mountain LLC
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 2485-071.
c. Date Filed: April 29, 2016; material amendment filed December 4,
2020.
d. Applicant: Northfield Mountain LLC (Northfield).
e. Name of Project: Northfield Mountain Pumped Storage Project
(project).
f. Location: The project is located on the Connecticut River in
Windham County, Vermont, Cheshire County, New Hampshire, and Franklin
County, Massachusetts.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mr. Alan Douglass, Regulatory Compliance
Manager, 99 Millers Falls Road, Northfield, MA 01360; (413) 659-4416 or
[email protected].
i. FERC Contact: Steve Kartalia, (202) 502-6131 or
[email protected].
j. Deadline for filing motions to intervene and protests, comments,
recommendations, preliminary terms and conditions, and preliminary
fishway prescriptions: 60 days from the issuance date of this notice;
reply comments are due 105 days from the issuance date of this notice.
The Commission strongly encourages electronic filing. Please file
motions to intervene and protests, comments, recommendations, terms and
conditions, and prescriptions using the Commission's eFiling system at
https://ferconline.ferc.gov/FERCOnline.aspx. Commenters can submit
brief comments up to 6,000 characters, without prior registration,
using the eComment system at https://ferconline.ferc.gov/QuickComment.aspx. You must include your name and contact information
at the end of your comments. For assistance, please contact FERC Online
Support at [email protected], (866) 208-3676 (toll free), or
(202) 502-8659 (TTY). In lieu of electronic filing, you may submit a
paper copy. Submissions sent via the U.S. Postal Service must be
addressed to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC
20426. Submissions sent via any other carrier must be addressed to:
Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first
page of any filing should include docket number P-2485-071.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application has been accepted and is ready for
environmental analysis at this time.
l. Project Description: The Northfield Mountain Pumped Storage
Project consists of: (1) a 1-mile-long, 30-foot-wide, 30- to 140-foot-
high main dam that includes: (i) an intake structure with two 7-foot-
wide, 9-foot-high sluice gates and an 8-foot-diameter outlet pipe; and
(ii) a 589-foot-long, 2-foot-diameter low-level outlet pipe; (2) a 425-
foot-long, 25-foot-high dike (North dike); (3) a 2,800-foot-long, 45-
foot-high dike (Northwest dike); (4) a 1,700-foot-long, 40-foot-long
dike (West dike); (5) a 327-foot-long, 10- to 20-foot-high gravity dam;
(6) an ungated 550-foot-long, 6-foot-high spillway structure with a 20-
foot-long notch at an elevation of
[[Page 14828]]
1,005.0 feet National Geodetic Vertical Datum of 1929 (NGVD 29); (7) a
286-acre impoundment (upper reservoir) with a useable storage volume of
12,318 acre-feet between elevations 938.0 feet and 1,000.5 feet NGVD
29; (8) a 2,110-acre impoundment (lower reservoir or Turners Falls
impoundment); (9) a 1,890-foot-long, 130-foot-wide intake channel with
a 63-foot-long, 9-foot-high submerged check dam and two 6-foot-wide,
2.75-foot-high sluice gates and two 18-foot-wide stoplogs; (10) a 200-
foot-long, 55-foot-wide, 80-foot-high pressure shaft; (11) an 853-foot-
long, 31-foot-diameter penstock; (12) two 22-foot-diameter, 100- to
150-foot-long penstocks; (13) four 340-foot-long, 9.5- to 14-foot-
diameter penstocks; (14) a 328-foot-long, 70-foot-wide powerhouse that
contains four reversible pump turbine-generator units with a total
installed capacity of 1,166.8 megawatts (MW); (15) four 25-foot-long,
11-foot-diameter draft tubes that transition to a 20-foot-long, 17-
foot-diameter draft tube; (16) a 5,136-foot-long, 33-foot-wide, 31-
foot-high horseshoe-shaped tailrace tunnel; (17) 35-foot-long, 40-foot-
high trapezoid-shaped stoplogs with 74.3- to 99.5-foot-wide, 48-foot-
high trashracks with 6-inch clear-bar spacing; (18) four 26-foot-long,
13.8-kilovolt (kV) generator leads that connect the turbine-generator
units to four transformers; (19) two 3,000-foot-long, 345-kV
transmission lines; and (20) appurtenant facilities.
The Northfield Mountain Pumped Storage Project generally operates
in pumping mode when electricity demand is low and generating mode when
electricity demand is high. In the summer and winter, the project
generally operates in a peaking mode in the morning and late afternoon.
In the spring and fall, the project may operate in a peaking mode one
or two times a day depending on electricity demand. The existing
license requires maintaining the upper reservoir between elevations
938.0 feet and 1,000.5 feet NGVD 29 (i.e., a maximum reservoir drawdown
of 62.5 feet). Average annual generation at the Northfield Mountain
Project from 2011-2019 was 889,845 MW-hours, and average annual energy
consumption for pumping from 2011 to 2019 was 1,189,640 MW-hours.
Northfield proposes three changes to the current project boundary:
(1) remove 0.2 acre of land associated with residential property; (2)
remove 8.1 acres of land referred to as ``Fuller Farm'' that include
residential and agricultural structures; and (3) add 135.5 acres of
land that include recreation trails.
Northfield proposes to increase the maximum water surface elevation
of the upper reservoir to 1,004.5 feet NGVD 29 and decrease the minimum
water surface elevation of the upper reservoir to 920.0 feet NGVD 29
(i.e., a maximum reservoir drawdown of 84.5 feet) year-round.
Northfield proposes to install a barrier net in the lower impoundment
to prevent fish entrainment. Northfield also proposes to periodically
dredge the upper reservoir and to construct new recreation access
trails. The specific proposed changes are described in the amended
application and the settlement agreements filed on March 31, 2023 and
June 12, 2023.
m. A copy of the application can be viewed on the Commission's
website at https://www.ferc.gov using the ``eLibrary'' link. Enter the
docket number excluding the last three digits in the docket number
field to access the document. For assistance, contact FERC Online
Support.
n. Anyone may submit comments, a protest, or a motion to intervene
in accordance with the requirements of Rules of Practice and Procedure,
18 CFR 385.210, .211, and .214. In determining the appropriate action
to take, the Commission will consider all protests or other comments
filed, but only those who file a motion to intervene in accordance with
the Commission's Rules may become a party to the proceeding. Any
comments, protests, or motions to intervene must be received on or
before the specified comment date for the particular application.
All filings must: (1) bear in all capital letters the title
``PROTEST,'' ``MOTION TO INTERVENE,'' ``COMMENTS,'' ``REPLY COMMENTS,''
``RECOMMENDATIONS,'' ``PRELIMINARY TERMS AND CONDITIONS,'' or
``PRELIMINARY FISHWAY PRESCRIPTIONS;'' (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person submitting the filing; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, recommendations, terms and conditions, or prescriptions must
set forth their evidentiary basis and otherwise comply with the
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the
application directly from the applicant. A copy of any protest or
motion to intervene must be served upon each representative of the
applicant specified in the particular application. A copy of all other
filings in reference to this application must be accompanied by proof
of service on all persons listed on the service list prepared by the
Commission in this proceeding, in accordance with 18 CFR 4.34(b) and
385.2010.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
You may also register online at https://ferconline.ferc.gov/FERCOnline.aspx to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
o. The applicant must file no later than 60 days following the date
of issuance of this notice: (1) a copy of the water quality
certification; (2) a copy of the request for certification, including
proof of the date on which the certifying agency received the request;
or (3) evidence of waiver of water quality certification.
p. Procedural Schedule: The application will be processed according
to the following schedule. Revisions to the schedule will be made as
appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Deadline for filing motions to intervene, April 2024.
protests, comments, recommendations,
preliminary terms and conditions, and
preliminary fishway prescriptions.
Deadline for filing reply comments........ May 2024.
------------------------------------------------------------------------
q. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of this notice.
Dated: February 22, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-04174 Filed 2-28-24; 8:45 am]
BILLING CODE 6717-01-P