Cottontail Solar 1, LLC; Cottontail Solar 2, LLC; Cottontail Solar 8, LLC; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 13074-13075 [2024-03432]

Download as PDF 13074 Federal Register / Vol. 89, No. 35 / Wednesday, February 21, 2024 / Notices n. Project Descriptions: The Upper Greenwich Project consists of the following existing facilities: (1) an 11.5foot-high, 203-foot-long concrete gravity spillway dam topped with 2-foot-high flashboards; (2) a reservoir with a normal water surface area of 20 acres and a gross storage capacity of 70 acrefeet at a normal water surface elevation of 334 feet mean sea level (MSL); (3) two 12-foot by 7.5-foot intake gates; (4) a 200-foot-long, 40-foot-wide, and 10-foothigh earthen power canal; (5) 60-footwide, 11-foot-high, 1-inch clear trash racks angled at 45 degrees to the flow and toward a 3-foot-wide fish passage sluice; (6) a 53-foot-long, 14-foot-wide, concrete and steel powerhouse containing two turbine-generator units with a rated capacity of 300 kilowatts (kW) each for a total installed capacity of 600 kW; (7) a tailrace channel; (8) a 150-foot-long transmission line; and (9) appurtenant facilities. The Middle Greenwich Project consists of the following existing facilities: (1) a 10-foot-high, 235-footlong concrete gravity spillway dam; (2) a 9-acre reservoir with a gross storage capacity of 80 acre-feet at a normal water surface elevation of 318 feet MSL; (3) a 150-foot-long, 20-foot-wide, and 10-foot-high power canal; (4) 24-footwide, 11-foot-high, 1-inch clear trash racks angled at 45 degrees to the flow and toward a 2.5-foot-wide fish passage sluice; (5) a 15-foot-long by 19.5-footwide concrete and steel powerhouse containing one turbine-generator unit with a capacity of 300 kW; (6) a tailrace channel; (7) a 150-foot-long transmission line; and (8) appurtenant facilities. The Upper and Middle Greenwich projects are operated in a run-of-river mode and release a minimum flow to the bypassed reach of 80 cubic feet per second (cfs) and 20 cfs, respectively, or inflow, whichever is less.2 A 20-cfs attraction flow is conveyed through the fish passage sluice to the bypassed reach at each project. Battenkill Hydro is not proposing any new project facilities or changes to the operation of either project. From 1999 to 2009, average annual generation at the Upper and Middle Greenwich projects was 146 kilowatthours (kWh) and 78 kWh, respectively. o. A copy of the applications can be viewed on the Commission’s website at https://www.ferc.gov, using the ‘‘eLibrary’’ link. Enter the docket number, excluding the last three digits in the docket number field, to access the document (P–6904 or P–6903). For assistance, contact FERC at FERCOnlineSupport@ferc.gov, or call toll-free, (866) 208–3676 or (202) 502– 8659 (TTY). You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to these or other pending projects. For assistance, contact FERC Online Support. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. p. Procedural schedule and final amendments: The applications will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate. Milestone Target date Issue Deficiency Letter (if necessary) ................................................................................................................................. Request Additional Information ........................................................................................................................................... Issue Acceptance Letter ..................................................................................................................................................... Issue Scoping Document 1 for comments .......................................................................................................................... Issue Scoping Document 2 (if necessary) .......................................................................................................................... Issue Notice of Ready for Environmental Analysis ............................................................................................................ Final amendments to the applications must be filed with the Commission no later than 30 days from the issuance date of the notice ready for environmental analysis. Dated: February 13, 2024. Debbie-Anne A. Reese, Acting Secretary. Federal Energy Regulatory Commission [Docket Nos. EL24–56–000; EL24–57–000; EL24–58–000] Cottontail Solar 1, LLC; Cottontail Solar 2, LLC; Cottontail Solar 8, LLC; Notice of Institution of Section 206 Proceeding and Refund Effective Date [FR Doc. 2024–03425 Filed 2–20–24; 8:45 am] BILLING CODE 6717–01–P khammond on DSKJM1Z7X2PROD with NOTICES DEPARTMENT OF ENERGY On February 12, 2024, the Commission issued an order in Docket Nos. EL24–56–000, EL24–57–000, and EL24–58–000, pursuant to section 206 of the Federal Power Act (FPA), 16 U.S.C. 824e, instituting an investigation to determine whether Cottontail Solar 1, LLC, Cottontail Solar 2, LLC, and Cottontail Solar 8, LLC’s (collectively, Applicants), proposed Reactive Service Rate Schedules are unjust, 2 Project operation occurred intermittently from 2009 to 2013. Both projects are currently offline and VerDate Sep<11>2014 17:43 Feb 20, 2024 Jkt 262001 unreasonable, unduly discriminatory or preferential, or otherwise unlawful. Cottontail Solar 1, LLC, Cottontail Solar 2, LLC, and Cottontail Solar 8, LLC, 186 FERC ¶ 61,101 (2024). The refund effective dates in Docket Nos. EL24–56–000, EL24–57–000, and EL24–58–000, established pursuant to section 206(b) of the FPA, will be the date of publication of this notice in the Federal Register, or the dates Applicants’ Rate Schedules each become effective, whichever is later, provided, however, if the Rate Schedules do not become effective until after 5 months from the date of publication of the notice, the refund effective dates shall be 5 months from the date of publication of the notice. Any interested person desiring to be heard in Docket Nos. EL24–56–000, EL24–57–000, and EL24–58–000 must have not operated since June 2013 (see Battenkill Hydro’s letter filed November 7, 2022). PO 00000 Frm 00042 Fmt 4703 Sfmt 4703 April 2024. April 2024. July 2024. August 2024. November 2024. November 2024. E:\FR\FM\21FEN1.SGM 21FEN1 khammond on DSKJM1Z7X2PROD with NOTICES Federal Register / Vol. 89, No. 35 / Wednesday, February 21, 2024 / Notices file a notice of intervention or motion to intervene, as appropriate, with the Federal Energy Regulatory Commission, in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure, 18 CFR 385.214 (2023), within 21 days of the date of issuance of the order. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. From FERC’s Home Page on the internet, this information is available on eLibrary. The full text of this document is available on eLibrary in PDF and Microsoft Word format for viewing, printing, and/or downloading. To access this document in eLibrary, type the docket number excluding the last three digits of this document in the docket number field. User assistance is available for eLibrary and the FERC’s website during normal business hours from FERC Online Support at 202–502– 6652 (toll free at 1–866–208–3676) or email at ferconlinesupport@ferc.gov, or the Public Reference Room at (202) 502– 8371, TTY (202) 502–8659. Email the Public Reference Room at public.referenceroom@ferc.gov. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFile’’ link at https://www.ferc.gov. In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. VerDate Sep<11>2014 17:43 Feb 20, 2024 Jkt 262001 Dated: February 13, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–03432 Filed 2–20–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER19–1507–000. Applicants: Duke Energy Florida, LLC, Duke Energy Progress, LLC, Duke Energy Carolinas, LLC. Description: Order Nos. 845 and 845– A Informational Report on Interconnection Study Delays Under OATT LGIP of Duke Energy Carolinas, LLC and Duke Energy Progress, LLC. Filed Date: 2/13/24. Accession Number: 20240213–5167. Comment Date: 5 p.m. ET 3/5/24. Docket Numbers: ER23–2040–003. Applicants: New York Independent System Operator, Inc. Description: Tariff Amendment: NYISO 2nd Deficiency Response re: DER and Aggregation Market Rule Changes to be effective 4/16/2024. Filed Date: 2/13/24. Accession Number: 20240213–5130. Comment Date: 5 p.m. ET 3/5/24. Docket Numbers: ER23–2333–002. Applicants: PJM Interconnection, L.L.C. Description: Tariff Amendment: Amendment to Filing, Original ISA, SA No. 6961 to be effective 6/6/2023. Filed Date: 2/13/24. Accession Number: 20240213–5132. Comment Date: 5 p.m. ET 3/5/24. Docket Numbers: ER24–731–001. Applicants: Midcontinent Independent System Operator, Inc. Description: Tariff Amendment: 2024–02–13_SA 4163 IMPA–IN Solar 1 Sub Original FSA (J1234) to be effective 2/20/2024. Filed Date: 2/13/24. Accession Number: 20240213–5076. Comment Date: 5 p.m. ET 3/5/24. Docket Numbers: ER24–732–001. Applicants: Midcontinent Independent System Operator, Inc. Description: Tariff Amendment: 2024–02–13_SA 4165 IMPA–IN Solar 1 Sub Original FSA (J1235) to be effective 2/20/2024. Filed Date: 2/13/24. Accession Number: 20240213–5079. Comment Date: 5 p.m. ET 3/5/24. PO 00000 Frm 00043 Fmt 4703 Sfmt 4703 13075 Docket Numbers: ER24–1240–000. Applicants: Public Service Company of New Mexico. Description: Notice of cancellation of Transmission Service Agreements of Public Service Company of New Mexico. Filed Date: 2/8/24. Accession Number: 20240208–5176. Comment Date: 5 p.m. ET 2/29/24. Docket Numbers: ER24–1241–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: 3599R3 Missouri Electric Commission to be effective 2/1/2024. Filed Date: 2/13/24. Accession Number: 20240213–5046. Comment Date: 5 p.m. ET 3/5/24. Docket Numbers: ER24–1242–000. Applicants: PJM Interconnection, L.L.C. Description: Request for prospective waiver, shortened five-day comment period, and expedited action of PJM Interconnection, L.L.C. Filed Date: 2/12/24. Accession Number: 20240212–5190. Comment Date: 5 p.m. ET 2/20/24. Docket Numbers: ER24–1243–000. Applicants: Honeysuckle Solar, LLC. Description: Baseline eTariff Filing: Petition for Blanket MBR Authorization with Waivers & Expedited Treatment to be effective 3/15/2024. Filed Date: 2/13/24. Accession Number: 20240213–5101. Comment Date: 5 p.m. ET 3/5/24. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/fercgen search.asp) by querying the docket number. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice E:\FR\FM\21FEN1.SGM 21FEN1

Agencies

[Federal Register Volume 89, Number 35 (Wednesday, February 21, 2024)]
[Notices]
[Pages 13074-13075]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-03432]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. EL24-56-000; EL24-57-000; EL24-58-000]


Cottontail Solar 1, LLC; Cottontail Solar 2, LLC; Cottontail 
Solar 8, LLC; Notice of Institution of Section 206 Proceeding and 
Refund Effective Date

    On February 12, 2024, the Commission issued an order in Docket Nos. 
EL24-56-000, EL24-57-000, and EL24-58-000, pursuant to section 206 of 
the Federal Power Act (FPA), 16 U.S.C. 824e, instituting an 
investigation to determine whether Cottontail Solar 1, LLC, Cottontail 
Solar 2, LLC, and Cottontail Solar 8, LLC's (collectively, Applicants), 
proposed Reactive Service Rate Schedules are unjust, unreasonable, 
unduly discriminatory or preferential, or otherwise unlawful. 
Cottontail Solar 1, LLC, Cottontail Solar 2, LLC, and Cottontail Solar 
8, LLC, 186 FERC ] 61,101 (2024).
    The refund effective dates in Docket Nos. EL24-56-000, EL24-57-000, 
and EL24-58-000, established pursuant to section 206(b) of the FPA, 
will be the date of publication of this notice in the Federal Register, 
or the dates Applicants' Rate Schedules each become effective, 
whichever is later, provided, however, if the Rate Schedules do not 
become effective until after 5 months from the date of publication of 
the notice, the refund effective dates shall be 5 months from the date 
of publication of the notice.
    Any interested person desiring to be heard in Docket Nos. EL24-56-
000, EL24-57-000, and EL24-58-000 must

[[Page 13075]]

file a notice of intervention or motion to intervene, as appropriate, 
with the Federal Energy Regulatory Commission, in accordance with Rule 
214 of the Commission's Rules of Practice and Procedure, 18 CFR 385.214 
(2023), within 21 days of the date of issuance of the order.
    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (https://www.ferc.gov) using 
the ``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. From FERC's 
Home Page on the internet, this information is available on eLibrary. 
The full text of this document is available on eLibrary in PDF and 
Microsoft Word format for viewing, printing, and/or downloading. To 
access this document in eLibrary, type the docket number excluding the 
last three digits of this document in the docket number field. User 
assistance is available for eLibrary and the FERC's website during 
normal business hours from FERC Online Support at 202-502-6652 (toll 
free at 1-866-208-3676) or email at [email protected], or the 
Public Reference Room at (202) 502-8371, TTY (202) 502-8659. Email the 
Public Reference Room at [email protected].
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFile'' link at 
https://www.ferc.gov. In lieu of electronic filing, you may submit a 
paper copy. Submissions sent via the U.S. Postal Service must be 
addressed to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 
20426. Submissions sent via any other carrier must be addressed to: 
Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory 
Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].

    Dated: February 13, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-03432 Filed 2-20-24; 8:45 am]
BILLING CODE 6717-01-P