Gas Transmission Northwest LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline, 11827-11828 [2024-03171]
Download as PDF
Federal Register / Vol. 89, No. 32 / Thursday, February 15, 2024 / Notices
Description: § 205(d) Rate Filing: NonConforming Large Generator
Interconnection Agreement with SEPA
to be effective 4/21/2024.
Filed Date: 2/9/24.
Accession Number: 20240209–5173.
Comment Date: 5 p.m. ET 3/1/24.
Docket Numbers: ER24–1228–000.
Applicants: PJM Interconnection,
L.L.C.
Description: Tariff Amendment:
Notice of Cancellation of WMPA, SA
No. 5753; Queue No. AF2–427 re:
withdrawal to be effective 4/10/2024.
Filed Date: 2/9/24.
Accession Number: 20240209–5176.
Comment Date: 5 p.m. ET 3/1/24.
khammond on DSKJM1Z7X2PROD with NOTICES
Docket Numbers: ER24–1229–000.
Applicants: ISO New England Inc.
Description: ISO New England Inc.
Capital Budget Quarterly Filing for the
Fourth Quarter of 2023.
Filed Date: 2/9/24.
Accession Number: 20240209–5185.
Comment Date: 5 p.m. ET 3/1/24.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/fercgen
search.asp) by querying the docket
number.
Any person desiring to intervene, to
protest, or to answer a complaint in any
of the above proceedings must file in
accordance with Rules 211, 214, or 206
of the Commission’s Regulations (18
CFR 385.211, 385.214, or 385.206) on or
before 5:00 p.m. Eastern time on the
specified comment date. Protests may be
considered, but intervention is
necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
VerDate Sep<11>2014
18:36 Feb 14, 2024
Jkt 262001
Dated: February 9, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–03172 Filed 2–14–24; 8:45 am]
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
[Docket No. CP24–47–000]
Gas Transmission Northwest LLC;
Notice of Request Under Blanket
Authorization and Establishing
Intervention and Protest Deadline
Take notice that on January 29, 2024,
Gas Transmission Northwest LLC
(GTN), 700 Louisiana Street, Suite 1300,
Houston, Texas 77002–2700, filed in the
above referenced docket, a prior notice
request pursuant to sections 157.205,
157.208, and 157.216 of the
Commission’s regulations under the
Natural Gas Act (NGA), and GTN’s
blanket certificate issued in Docket No.
CP82–530–000, for authorization to
replace a total of 2.03 miles of 36-inchdiameter pipeline in three connecting
segments on GTN’s B-Line, all located
in Boundary County, Idaho (GTN Moyie
Class Change Project). The project will
allow GTN to comply with U.S.
Department of Transportation’s Pipeline
and Hazardous Materials Safety
Administration’s requirement for class
location changes. The estimated cost for
the project is $31.8 million, all as more
fully set forth in the request which is on
file with the Commission and open to
public inspection.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page
(www.ferc.gov) using the ‘‘eLibrary’’
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document.
Public access to records formerly
available in the Commission’s physical
Public Reference Room, which was
located at the Commission’s
headquarters, 888 First Street NE,
Washington, DC 20426, are now
available via the Commission’s website.
For assistance, contact the Federal
Energy Regulatory Commission at
FercOnlineSupport@ferc.gov or call tollfree, (866) 208–3676 or TTY (202) 502–
8659.
Any questions concerning this request
should be directed to David A. Alonzo,
Manager of Project Authorizations, Gas
Frm 00019
Fmt 4703
Transmission Northwest LLC, 700
Louisiana Street, Suite 1300, Houston,
Texas 77002–2700, at (832) 320–5477,
or david_alonzo@tcenergy.com.
Public Participation
DEPARTMENT OF ENERGY
PO 00000
11827
Sfmt 4703
There are three ways to become
involved in the Commission’s review of
this project: you can file a protest to the
project, you can file a motion to
intervene in the proceeding, and you
can file comments on the project. There
is no fee or cost for filing protests,
motions to intervene, or comments. The
deadline for filing protests, motions to
intervene, and comments is 5 p.m.
eastern time on April 8, 2024. How to
file protests, motions to intervene, and
comments is explained below.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Protests
Pursuant to section 157.205 of the
Commission’s regulations under the
NGA,1 any person 2 or the Commission’s
staff may file a protest to the request. If
no protest is filed within the time
allowed or if a protest is filed and then
withdrawn within 30 days after the
allowed time for filing a protest, the
proposed activity shall be deemed to be
authorized effective the day after the
time allowed for protest. If a protest is
filed and not withdrawn within 30 days
after the time allowed for filing a
protest, the instant request for
authorization will be considered by the
Commission.
Protests must comply with the
requirements specified in section
157.205(e) of the Commission’s
regulations,3 and must be submitted by
the protest deadline, which is April 8,
2024. A protest may also serve as a
motion to intervene so long as the
protestor states it also seeks to be an
intervenor.
1 18
CFR 157.205.
include individuals, organizations,
businesses, municipalities, and other entities. 18
CFR 385.102(d).
3 18 CFR 157.205(e).
2 Persons
E:\FR\FM\15FEN1.SGM
15FEN1
11828
Federal Register / Vol. 89, No. 32 / Thursday, February 15, 2024 / Notices
Interventions
Any person has the option to file a
motion to intervene in this proceeding.
Only intervenors have the right to
request rehearing of Commission orders
issued in this proceeding and to
subsequently challenge the
Commission’s orders in the U.S. Circuit
Courts of Appeal.
To intervene, you must submit a
motion to intervene to the Commission
in accordance with Rule 214 of the
Commission’s Rules of Practice and
Procedure 4 and the regulations under
the NGA 5 by the intervention deadline
for the project, which is April 8, 2024.
As described further in Rule 214, your
motion to intervene must state, to the
extent known, your position regarding
the proceeding, as well as your interest
in the proceeding. For an individual,
this could include your status as a
landowner, ratepayer, resident of an
impacted community, or recreationist.
You do not need to have property
directly impacted by the project in order
to intervene. For more information
about motions to intervene, refer to the
FERC website at https://www.ferc.gov/
resources/guides/how-to/intervene.asp.
All timely, unopposed motions to
intervene are automatically granted by
operation of Rule 214(c)(1). Motions to
intervene that are filed after the
intervention deadline are untimely and
may be denied. Any late-filed motion to
intervene must show good cause for
being late and must explain why the
time limitation should be waived and
provide justification by reference to
factors set forth in Rule 214(d) of the
Commission’s Rules and Regulations. A
person obtaining party status will be
placed on the service list maintained by
the Secretary of the Commission and
will receive copies (paper or electronic)
of all documents filed by the applicant
and by all other parties.
khammond on DSKJM1Z7X2PROD with NOTICES
Comments
Any person wishing to comment on
the project may do so. The Commission
considers all comments received about
the project in determining the
appropriate action to be taken. To
ensure that your comments are timely
and properly recorded, please submit
your comments on or before April 8,
2024. The filing of a comment alone will
not serve to make the filer a party to the
proceeding. To become a party, you
must intervene in the proceeding.
4 18
5 18
CFR 385.214.
CFR 157.10.
VerDate Sep<11>2014
18:36 Feb 14, 2024
Jkt 262001
How To File Protests, Interventions,
and Comments
There are two ways to submit
protests, motions to intervene, and
comments. In both instances, please
reference the Project docket number
CP24–47–000 in your submission.
(1) You may file your protest, motion
to intervene, and comments by using the
Commission’s eFiling feature, which is
located on the Commission’s website
(www.ferc.gov) under the link to
Documents and Filings. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ You will be
asked to select the type of filing you are
making; first select ‘‘General’’ and then
select ‘‘Protest’’, ‘‘Intervention’’, or
‘‘Comment on a Filing’’; or 6
(2) You can file a paper copy of your
submission by mailing it to the address
below. Your submission must reference
the Project docket number CP24–47–
000.
To file via USPS: Debbie-Anne Reese,
Acting Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426.
To file via any other method: DebbieAnne Reese, Acting Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852.
The Commission encourages
electronic filing of submissions (option
1 above) and has eFiling staff available
to assist you at (202) 502–8258 or
FercOnlineSupport@ferc.gov.
Protests and motions to intervene
must be served on the applicant either
by mail or email (with a link to the
document) at: David A. Alonzo,
Manager of Project Authorizations, Gas
Transmission Northwest LLC, 700
Louisiana Street, Suite 1300, Houston,
Texas 77002–2700 or at david_alonzo@
tcenergy.com. Any subsequent
submissions by an intervenor must be
served on the applicant and all other
parties to the proceeding. Contact
information for parties can be
downloaded from the service list at the
eService link on FERC Online.
Tracking the Proceeding
Throughout the proceeding,
additional information about the project
will be available from the Commission’s
Office of External Affairs, at (866) 208–
FERC, or on the FERC website at
6 Additionally, you may file your comments
electronically by using the eComment feature,
which is located on the Commission’s website at
www.ferc.gov under the link to Documents and
Filings. Using eComment is an easy method for
interested persons to submit brief, text-only
comments on a project.
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
www.ferc.gov using the ‘‘eLibrary’’ link
as described above. The eLibrary link
also provides access to the texts of all
formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. For more information and to
register, go to www.ferc.gov/docs-filing/
esubscription.asp.
Dated: February 9, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–03171 Filed 2–14–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL24–26–000]
PJM Interconnection L.L.C.; Notice of
Institution of Section 206 Proceeding
and Refund Effective Date
On December 20, 2023, the
Commission issued an order in Docket
No. EL24–26–000, pursuant to section
206 of the Federal Power Act (FPA), 16
U.S.C. 824e, instituting an investigation
to determine whether PJM
Interconnection L.L.C.’s Interconnection
Construction Service Agreement is
unjust, unreasonable, unduly
discriminatory or preferential, or
otherwise unlawful. PJM
Interconnection L.L.C., 185 FERC
¶ 61,202 (2023).
The refund effective date in Docket
No. EL24–26–000, established pursuant
to section 206(b) of the FPA, will be the
date of publication of this notice in the
Federal Register.
Any interested person desiring to be
heard in Docket No. EL24–26–000 must
file a notice of intervention or motion to
intervene, as appropriate, with the
Federal Energy Regulatory Commission,
in accordance with Rule 214 of the
Commission’s Rules of Practice and
Procedure, 18 CFR 385.214 (2023),
within 21 days of the date of issuance
of the order.
E:\FR\FM\15FEN1.SGM
15FEN1
Agencies
[Federal Register Volume 89, Number 32 (Thursday, February 15, 2024)]
[Notices]
[Pages 11827-11828]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-03171]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP24-47-000]
Gas Transmission Northwest LLC; Notice of Request Under Blanket
Authorization and Establishing Intervention and Protest Deadline
Take notice that on January 29, 2024, Gas Transmission Northwest
LLC (GTN), 700 Louisiana Street, Suite 1300, Houston, Texas 77002-2700,
filed in the above referenced docket, a prior notice request pursuant
to sections 157.205, 157.208, and 157.216 of the Commission's
regulations under the Natural Gas Act (NGA), and GTN's blanket
certificate issued in Docket No. CP82-530-000, for authorization to
replace a total of 2.03 miles of 36-inch-diameter pipeline in three
connecting segments on GTN's B-Line, all located in Boundary County,
Idaho (GTN Moyie Class Change Project). The project will allow GTN to
comply with U.S. Department of Transportation's Pipeline and Hazardous
Materials Safety Administration's requirement for class location
changes. The estimated cost for the project is $31.8 million, all as
more fully set forth in the request which is on file with the
Commission and open to public inspection.
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (www.ferc.gov) using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. Public access
to records formerly available in the Commission's physical Public
Reference Room, which was located at the Commission's headquarters, 888
First Street NE, Washington, DC 20426, are now available via the
Commission's website. For assistance, contact the Federal Energy
Regulatory Commission at [email protected] or call toll-free,
(866) 208-3676 or TTY (202) 502-8659.
Any questions concerning this request should be directed to David
A. Alonzo, Manager of Project Authorizations, Gas Transmission
Northwest LLC, 700 Louisiana Street, Suite 1300, Houston, Texas 77002-
2700, at (832) 320-5477, or [email protected].
Public Participation
There are three ways to become involved in the Commission's review
of this project: you can file a protest to the project, you can file a
motion to intervene in the proceeding, and you can file comments on the
project. There is no fee or cost for filing protests, motions to
intervene, or comments. The deadline for filing protests, motions to
intervene, and comments is 5 p.m. eastern time on April 8, 2024. How to
file protests, motions to intervene, and comments is explained below.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
Protests
Pursuant to section 157.205 of the Commission's regulations under
the NGA,\1\ any person \2\ or the Commission's staff may file a protest
to the request. If no protest is filed within the time allowed or if a
protest is filed and then withdrawn within 30 days after the allowed
time for filing a protest, the proposed activity shall be deemed to be
authorized effective the day after the time allowed for protest. If a
protest is filed and not withdrawn within 30 days after the time
allowed for filing a protest, the instant request for authorization
will be considered by the Commission.
---------------------------------------------------------------------------
\1\ 18 CFR 157.205.
\2\ Persons include individuals, organizations, businesses,
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------
Protests must comply with the requirements specified in section
157.205(e) of the Commission's regulations,\3\ and must be submitted by
the protest deadline, which is April 8, 2024. A protest may also serve
as a motion to intervene so long as the protestor states it also seeks
to be an intervenor.
---------------------------------------------------------------------------
\3\ 18 CFR 157.205(e).
---------------------------------------------------------------------------
[[Page 11828]]
Interventions
Any person has the option to file a motion to intervene in this
proceeding. Only intervenors have the right to request rehearing of
Commission orders issued in this proceeding and to subsequently
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
To intervene, you must submit a motion to intervene to the
Commission in accordance with Rule 214 of the Commission's Rules of
Practice and Procedure \4\ and the regulations under the NGA \5\ by the
intervention deadline for the project, which is April 8, 2024. As
described further in Rule 214, your motion to intervene must state, to
the extent known, your position regarding the proceeding, as well as
your interest in the proceeding. For an individual, this could include
your status as a landowner, ratepayer, resident of an impacted
community, or recreationist. You do not need to have property directly
impacted by the project in order to intervene. For more information
about motions to intervene, refer to the FERC website at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------
\4\ 18 CFR 385.214.
\5\ 18 CFR 157.10.
---------------------------------------------------------------------------
All timely, unopposed motions to intervene are automatically
granted by operation of Rule 214(c)(1). Motions to intervene that are
filed after the intervention deadline are untimely and may be denied.
Any late-filed motion to intervene must show good cause for being late
and must explain why the time limitation should be waived and provide
justification by reference to factors set forth in Rule 214(d) of the
Commission's Rules and Regulations. A person obtaining party status
will be placed on the service list maintained by the Secretary of the
Commission and will receive copies (paper or electronic) of all
documents filed by the applicant and by all other parties.
Comments
Any person wishing to comment on the project may do so. The
Commission considers all comments received about the project in
determining the appropriate action to be taken. To ensure that your
comments are timely and properly recorded, please submit your comments
on or before April 8, 2024. The filing of a comment alone will not
serve to make the filer a party to the proceeding. To become a party,
you must intervene in the proceeding.
How To File Protests, Interventions, and Comments
There are two ways to submit protests, motions to intervene, and
comments. In both instances, please reference the Project docket number
CP24-47-000 in your submission.
(1) You may file your protest, motion to intervene, and comments by
using the Commission's eFiling feature, which is located on the
Commission's website (www.ferc.gov) under the link to Documents and
Filings. New eFiling users must first create an account by clicking on
``eRegister.'' You will be asked to select the type of filing you are
making; first select ``General'' and then select ``Protest'',
``Intervention'', or ``Comment on a Filing''; or \6\
---------------------------------------------------------------------------
\6\ Additionally, you may file your comments electronically by
using the eComment feature, which is located on the Commission's
website at www.ferc.gov under the link to Documents and Filings.
Using eComment is an easy method for interested persons to submit
brief, text-only comments on a project.
---------------------------------------------------------------------------
(2) You can file a paper copy of your submission by mailing it to
the address below. Your submission must reference the Project docket
number CP24-47-000.
To file via USPS: Debbie-Anne Reese, Acting Secretary, Federal
Energy Regulatory Commission, 888 First Street NE, Washington, DC
20426.
To file via any other method: Debbie-Anne Reese, Acting Secretary,
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville,
Maryland 20852.
The Commission encourages electronic filing of submissions (option
1 above) and has eFiling staff available to assist you at (202) 502-
8258 or [email protected].
Protests and motions to intervene must be served on the applicant
either by mail or email (with a link to the document) at: David A.
Alonzo, Manager of Project Authorizations, Gas Transmission Northwest
LLC, 700 Louisiana Street, Suite 1300, Houston, Texas 77002-2700 or at
[email protected]. Any subsequent submissions by an intervenor
must be served on the applicant and all other parties to the
proceeding. Contact information for parties can be downloaded from the
service list at the eService link on FERC Online.
Tracking the Proceeding
Throughout the proceeding, additional information about the project
will be available from the Commission's Office of External Affairs, at
(866) 208-FERC, or on the FERC website at www.ferc.gov using the
``eLibrary'' link as described above. The eLibrary link also provides
access to the texts of all formal documents issued by the Commission,
such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. For more information and to register, go to
www.ferc.gov/docs-filing/esubscription.asp.
Dated: February 9, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-03171 Filed 2-14-24; 8:45 am]
BILLING CODE 6717-01-P