Gas Transmission Northwest LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline, 11827-11828 [2024-03171]

Download as PDF Federal Register / Vol. 89, No. 32 / Thursday, February 15, 2024 / Notices Description: § 205(d) Rate Filing: NonConforming Large Generator Interconnection Agreement with SEPA to be effective 4/21/2024. Filed Date: 2/9/24. Accession Number: 20240209–5173. Comment Date: 5 p.m. ET 3/1/24. Docket Numbers: ER24–1228–000. Applicants: PJM Interconnection, L.L.C. Description: Tariff Amendment: Notice of Cancellation of WMPA, SA No. 5753; Queue No. AF2–427 re: withdrawal to be effective 4/10/2024. Filed Date: 2/9/24. Accession Number: 20240209–5176. Comment Date: 5 p.m. ET 3/1/24. khammond on DSKJM1Z7X2PROD with NOTICES Docket Numbers: ER24–1229–000. Applicants: ISO New England Inc. Description: ISO New England Inc. Capital Budget Quarterly Filing for the Fourth Quarter of 2023. Filed Date: 2/9/24. Accession Number: 20240209–5185. Comment Date: 5 p.m. ET 3/1/24. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/fercgen search.asp) by querying the docket number. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. VerDate Sep<11>2014 18:36 Feb 14, 2024 Jkt 262001 Dated: February 9, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–03172 Filed 2–14–24; 8:45 am] BILLING CODE 6717–01–P Federal Energy Regulatory Commission [Docket No. CP24–47–000] Gas Transmission Northwest LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline Take notice that on January 29, 2024, Gas Transmission Northwest LLC (GTN), 700 Louisiana Street, Suite 1300, Houston, Texas 77002–2700, filed in the above referenced docket, a prior notice request pursuant to sections 157.205, 157.208, and 157.216 of the Commission’s regulations under the Natural Gas Act (NGA), and GTN’s blanket certificate issued in Docket No. CP82–530–000, for authorization to replace a total of 2.03 miles of 36-inchdiameter pipeline in three connecting segments on GTN’s B-Line, all located in Boundary County, Idaho (GTN Moyie Class Change Project). The project will allow GTN to comply with U.S. Department of Transportation’s Pipeline and Hazardous Materials Safety Administration’s requirement for class location changes. The estimated cost for the project is $31.8 million, all as more fully set forth in the request which is on file with the Commission and open to public inspection. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. Public access to records formerly available in the Commission’s physical Public Reference Room, which was located at the Commission’s headquarters, 888 First Street NE, Washington, DC 20426, are now available via the Commission’s website. For assistance, contact the Federal Energy Regulatory Commission at FercOnlineSupport@ferc.gov or call tollfree, (866) 208–3676 or TTY (202) 502– 8659. Any questions concerning this request should be directed to David A. Alonzo, Manager of Project Authorizations, Gas Frm 00019 Fmt 4703 Transmission Northwest LLC, 700 Louisiana Street, Suite 1300, Houston, Texas 77002–2700, at (832) 320–5477, or david_alonzo@tcenergy.com. Public Participation DEPARTMENT OF ENERGY PO 00000 11827 Sfmt 4703 There are three ways to become involved in the Commission’s review of this project: you can file a protest to the project, you can file a motion to intervene in the proceeding, and you can file comments on the project. There is no fee or cost for filing protests, motions to intervene, or comments. The deadline for filing protests, motions to intervene, and comments is 5 p.m. eastern time on April 8, 2024. How to file protests, motions to intervene, and comments is explained below. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Protests Pursuant to section 157.205 of the Commission’s regulations under the NGA,1 any person 2 or the Commission’s staff may file a protest to the request. If no protest is filed within the time allowed or if a protest is filed and then withdrawn within 30 days after the allowed time for filing a protest, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request for authorization will be considered by the Commission. Protests must comply with the requirements specified in section 157.205(e) of the Commission’s regulations,3 and must be submitted by the protest deadline, which is April 8, 2024. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor. 1 18 CFR 157.205. include individuals, organizations, businesses, municipalities, and other entities. 18 CFR 385.102(d). 3 18 CFR 157.205(e). 2 Persons E:\FR\FM\15FEN1.SGM 15FEN1 11828 Federal Register / Vol. 89, No. 32 / Thursday, February 15, 2024 / Notices Interventions Any person has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission’s orders in the U.S. Circuit Courts of Appeal. To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure 4 and the regulations under the NGA 5 by the intervention deadline for the project, which is April 8, 2024. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https://www.ferc.gov/ resources/guides/how-to/intervene.asp. All timely, unopposed motions to intervene are automatically granted by operation of Rule 214(c)(1). Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations. A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. khammond on DSKJM1Z7X2PROD with NOTICES Comments Any person wishing to comment on the project may do so. The Commission considers all comments received about the project in determining the appropriate action to be taken. To ensure that your comments are timely and properly recorded, please submit your comments on or before April 8, 2024. The filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. 4 18 5 18 CFR 385.214. CFR 157.10. VerDate Sep<11>2014 18:36 Feb 14, 2024 Jkt 262001 How To File Protests, Interventions, and Comments There are two ways to submit protests, motions to intervene, and comments. In both instances, please reference the Project docket number CP24–47–000 in your submission. (1) You may file your protest, motion to intervene, and comments by using the Commission’s eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select ‘‘General’’ and then select ‘‘Protest’’, ‘‘Intervention’’, or ‘‘Comment on a Filing’’; or 6 (2) You can file a paper copy of your submission by mailing it to the address below. Your submission must reference the Project docket number CP24–47– 000. To file via USPS: Debbie-Anne Reese, Acting Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. To file via any other method: DebbieAnne Reese, Acting Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The Commission encourages electronic filing of submissions (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. Protests and motions to intervene must be served on the applicant either by mail or email (with a link to the document) at: David A. Alonzo, Manager of Project Authorizations, Gas Transmission Northwest LLC, 700 Louisiana Street, Suite 1300, Houston, Texas 77002–2700 or at david_alonzo@ tcenergy.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s Office of External Affairs, at (866) 208– FERC, or on the FERC website at 6 Additionally, you may file your comments electronically by using the eComment feature, which is located on the Commission’s website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project. PO 00000 Frm 00020 Fmt 4703 Sfmt 4703 www.ferc.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/docs-filing/ esubscription.asp. Dated: February 9, 2024. Debbie-Anne A. Reese, Acting Secretary. [FR Doc. 2024–03171 Filed 2–14–24; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL24–26–000] PJM Interconnection L.L.C.; Notice of Institution of Section 206 Proceeding and Refund Effective Date On December 20, 2023, the Commission issued an order in Docket No. EL24–26–000, pursuant to section 206 of the Federal Power Act (FPA), 16 U.S.C. 824e, instituting an investigation to determine whether PJM Interconnection L.L.C.’s Interconnection Construction Service Agreement is unjust, unreasonable, unduly discriminatory or preferential, or otherwise unlawful. PJM Interconnection L.L.C., 185 FERC ¶ 61,202 (2023). The refund effective date in Docket No. EL24–26–000, established pursuant to section 206(b) of the FPA, will be the date of publication of this notice in the Federal Register. Any interested person desiring to be heard in Docket No. EL24–26–000 must file a notice of intervention or motion to intervene, as appropriate, with the Federal Energy Regulatory Commission, in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure, 18 CFR 385.214 (2023), within 21 days of the date of issuance of the order. E:\FR\FM\15FEN1.SGM 15FEN1

Agencies

[Federal Register Volume 89, Number 32 (Thursday, February 15, 2024)]
[Notices]
[Pages 11827-11828]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-03171]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP24-47-000]


Gas Transmission Northwest LLC; Notice of Request Under Blanket 
Authorization and Establishing Intervention and Protest Deadline

    Take notice that on January 29, 2024, Gas Transmission Northwest 
LLC (GTN), 700 Louisiana Street, Suite 1300, Houston, Texas 77002-2700, 
filed in the above referenced docket, a prior notice request pursuant 
to sections 157.205, 157.208, and 157.216 of the Commission's 
regulations under the Natural Gas Act (NGA), and GTN's blanket 
certificate issued in Docket No. CP82-530-000, for authorization to 
replace a total of 2.03 miles of 36-inch-diameter pipeline in three 
connecting segments on GTN's B-Line, all located in Boundary County, 
Idaho (GTN Moyie Class Change Project). The project will allow GTN to 
comply with U.S. Department of Transportation's Pipeline and Hazardous 
Materials Safety Administration's requirement for class location 
changes. The estimated cost for the project is $31.8 million, all as 
more fully set forth in the request which is on file with the 
Commission and open to public inspection.
    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (www.ferc.gov) using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. Public access 
to records formerly available in the Commission's physical Public 
Reference Room, which was located at the Commission's headquarters, 888 
First Street NE, Washington, DC 20426, are now available via the 
Commission's website. For assistance, contact the Federal Energy 
Regulatory Commission at [email protected] or call toll-free, 
(866) 208-3676 or TTY (202) 502-8659.
    Any questions concerning this request should be directed to David 
A. Alonzo, Manager of Project Authorizations, Gas Transmission 
Northwest LLC, 700 Louisiana Street, Suite 1300, Houston, Texas 77002-
2700, at (832) 320-5477, or [email protected].

Public Participation

    There are three ways to become involved in the Commission's review 
of this project: you can file a protest to the project, you can file a 
motion to intervene in the proceeding, and you can file comments on the 
project. There is no fee or cost for filing protests, motions to 
intervene, or comments. The deadline for filing protests, motions to 
intervene, and comments is 5 p.m. eastern time on April 8, 2024. How to 
file protests, motions to intervene, and comments is explained below.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].

Protests

    Pursuant to section 157.205 of the Commission's regulations under 
the NGA,\1\ any person \2\ or the Commission's staff may file a protest 
to the request. If no protest is filed within the time allowed or if a 
protest is filed and then withdrawn within 30 days after the allowed 
time for filing a protest, the proposed activity shall be deemed to be 
authorized effective the day after the time allowed for protest. If a 
protest is filed and not withdrawn within 30 days after the time 
allowed for filing a protest, the instant request for authorization 
will be considered by the Commission.
---------------------------------------------------------------------------

    \1\ 18 CFR 157.205.
    \2\ Persons include individuals, organizations, businesses, 
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------

    Protests must comply with the requirements specified in section 
157.205(e) of the Commission's regulations,\3\ and must be submitted by 
the protest deadline, which is April 8, 2024. A protest may also serve 
as a motion to intervene so long as the protestor states it also seeks 
to be an intervenor.
---------------------------------------------------------------------------

    \3\ 18 CFR 157.205(e).

---------------------------------------------------------------------------

[[Page 11828]]

Interventions

    Any person has the option to file a motion to intervene in this 
proceeding. Only intervenors have the right to request rehearing of 
Commission orders issued in this proceeding and to subsequently 
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
    To intervene, you must submit a motion to intervene to the 
Commission in accordance with Rule 214 of the Commission's Rules of 
Practice and Procedure \4\ and the regulations under the NGA \5\ by the 
intervention deadline for the project, which is April 8, 2024. As 
described further in Rule 214, your motion to intervene must state, to 
the extent known, your position regarding the proceeding, as well as 
your interest in the proceeding. For an individual, this could include 
your status as a landowner, ratepayer, resident of an impacted 
community, or recreationist. You do not need to have property directly 
impacted by the project in order to intervene. For more information 
about motions to intervene, refer to the FERC website at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------

    \4\ 18 CFR 385.214.
    \5\ 18 CFR 157.10.
---------------------------------------------------------------------------

    All timely, unopposed motions to intervene are automatically 
granted by operation of Rule 214(c)(1). Motions to intervene that are 
filed after the intervention deadline are untimely and may be denied. 
Any late-filed motion to intervene must show good cause for being late 
and must explain why the time limitation should be waived and provide 
justification by reference to factors set forth in Rule 214(d) of the 
Commission's Rules and Regulations. A person obtaining party status 
will be placed on the service list maintained by the Secretary of the 
Commission and will receive copies (paper or electronic) of all 
documents filed by the applicant and by all other parties.

Comments

    Any person wishing to comment on the project may do so. The 
Commission considers all comments received about the project in 
determining the appropriate action to be taken. To ensure that your 
comments are timely and properly recorded, please submit your comments 
on or before April 8, 2024. The filing of a comment alone will not 
serve to make the filer a party to the proceeding. To become a party, 
you must intervene in the proceeding.

How To File Protests, Interventions, and Comments

    There are two ways to submit protests, motions to intervene, and 
comments. In both instances, please reference the Project docket number 
CP24-47-000 in your submission.
    (1) You may file your protest, motion to intervene, and comments by 
using the Commission's eFiling feature, which is located on the 
Commission's website (www.ferc.gov) under the link to Documents and 
Filings. New eFiling users must first create an account by clicking on 
``eRegister.'' You will be asked to select the type of filing you are 
making; first select ``General'' and then select ``Protest'', 
``Intervention'', or ``Comment on a Filing''; or \6\
---------------------------------------------------------------------------

    \6\ Additionally, you may file your comments electronically by 
using the eComment feature, which is located on the Commission's 
website at www.ferc.gov under the link to Documents and Filings. 
Using eComment is an easy method for interested persons to submit 
brief, text-only comments on a project.
---------------------------------------------------------------------------

    (2) You can file a paper copy of your submission by mailing it to 
the address below. Your submission must reference the Project docket 
number CP24-47-000.
    To file via USPS: Debbie-Anne Reese, Acting Secretary, Federal 
Energy Regulatory Commission, 888 First Street NE, Washington, DC 
20426.
    To file via any other method: Debbie-Anne Reese, Acting Secretary, 
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, 
Maryland 20852.
    The Commission encourages electronic filing of submissions (option 
1 above) and has eFiling staff available to assist you at (202) 502-
8258 or [email protected].
    Protests and motions to intervene must be served on the applicant 
either by mail or email (with a link to the document) at: David A. 
Alonzo, Manager of Project Authorizations, Gas Transmission Northwest 
LLC, 700 Louisiana Street, Suite 1300, Houston, Texas 77002-2700 or at 
[email protected]. Any subsequent submissions by an intervenor 
must be served on the applicant and all other parties to the 
proceeding. Contact information for parties can be downloaded from the 
service list at the eService link on FERC Online.

Tracking the Proceeding

    Throughout the proceeding, additional information about the project 
will be available from the Commission's Office of External Affairs, at 
(866) 208-FERC, or on the FERC website at www.ferc.gov using the 
``eLibrary'' link as described above. The eLibrary link also provides 
access to the texts of all formal documents issued by the Commission, 
such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. For more information and to register, go to 
www.ferc.gov/docs-filing/esubscription.asp.

    Dated: February 9, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-03171 Filed 2-14-24; 8:45 am]
BILLING CODE 6717-01-P