Tennessee Gas Pipeline Company, L.L.C; Southern Natural Gas Company, L.L.C; Notice of Requests for Extension of Time, 8196 [2024-02378]
Download as PDF
8196
Federal Register / Vol. 89, No. 25 / Tuesday, February 6, 2024 / Notices
Dated: January 31, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–02381 Filed 2–5–24; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP20–50–000; CP20–51–000]
ddrumheller on DSK120RN23PROD with NOTICES1
Tennessee Gas Pipeline Company,
L.L.C; Southern Natural Gas Company,
L.L.C; Notice of Requests for
Extension of Time
Take notice that on January 26, 2024,
Tennessee Gas Pipeline Company,
L.L.C. (Tennessee) and Southern Natural
Gas Company, L.L.C. (Southern)
requested that the Federal Energy
Regulatory Commission (Commission)
grant an extension of time, until
September 30, 2025, to construct and
place into service its Evangeline Pass
Project (Project) located in Louisiana as
authorized in the Order Issuing
Certificates and Approving
Abandonments (Order).1 The Order
required Tennessee and Southern to
complete construction of the Project and
make it available for service within two
years of the date of the Order, or by
March 25, 2024.
Tennessee and Southern assert that
they faced permitting delays after the
Order Addressing Arguments Raised on
Rehearing was issued on September 29,
2022.2 They submitted an
implementation plan and secured
approval from the Commission on
September 8, 2023, to begin
construction. However, they have faced
delays in securing construction
contractors, finalizing land acquisition,
and obtaining state and local permits.
As a result, they anticipate beginning
construction activities during the first
quarter of 2024. Tennessee and
Southern have requested an extension of
the in-service date to September 30,
2025, to ensure that all necessary
restoration activities are underway, and
the Project facilities are fully
constructed.
This notice establishes a 15-calendar
day intervention and comment period
deadline. Any person wishing to
comment on Tennessee and Southern’s
request for an extension of time may do
so. No reply comments or answers will
1 Tennessee Gas Pipeline Company, L.L.C. and
Southern Natural Gas Company, L.L.C., 178 FERC
¶ 61,199 (2022).
2 Tennessee Gas Pipeline Company, L.L.C. and
Southern Natural Gas Company, L.L.C., 180 FERC
¶ 61,205 (2022).
VerDate Sep<11>2014
18:15 Feb 05, 2024
Jkt 262001
be considered. If you wish to obtain
legal status by becoming a party to the
proceedings for this request, you
should, on or before the comment date
stated below, file a motion to intervene
in accordance with the requirements of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the Natural
Gas Act (NGA) (18 CFR 157.10).
As a matter of practice, the
Commission itself generally acts on
requests for extensions of time to
complete construction for NGA facilities
when such requests are contested before
order issuance. For those extension
requests that are contested,3 the
Commission will aim to issue an order
acting on the request within 45 days.4
The Commission will address all
arguments relating to whether the
applicant has demonstrated there is
good cause to grant the extension.5 The
Commission will not consider
arguments that re-litigate the issuance of
the certificate order, including whether
the Commission properly found the
project to be in the public convenience
and necessity and whether the
Commission’s environmental analysis
for the certificate complied with the
National Environmental Policy Act
(NEPA).6 At the time a pipeline requests
an extension of time, orders on
certificates of public convenience and
necessity are final and the Commission
will not re-litigate their issuance.7 The
Director of the Office of Energy Projects,
or his or her designee, will act on all of
those extension requests that are
uncontested.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. Public
access to records formerly available in
the Commission’s physical Public
Reference Room, which was located at
the Commission’s headquarters, 888
3 Contested proceedings are those where an
intervenor disputes any material issue of the filing.
18 CFR 385.2201(c)(1).
4 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
5 Id. at P 40.
6 Similarly, the Commission will not re-litigate
the issuance of an NGA section 3 authorization,
including whether a proposed project is not
inconsistent with the public interest and whether
the Commission’s environmental analysis for the
permit order complied with NEPA.
7 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
PO 00000
Frm 00055
Fmt 4703
Sfmt 4703
First Street NE, Washington, DC 20426,
are now available via the Commission’s
website. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll free, (866) 208–3676 or TTY (202)
502–8659.
The Commission strongly encourages
electronic filings of comments in lieu of
paper using the ‘‘eFile’’ link at https://
www.ferc.gov. In lieu of electronic filing,
you may submit a paper copy which
must reference the Project docket
number.
To file via USPS: Debbie-Anne A. Reese,
Acting Secretary, Federal Energy
Regulatory Commission, 888 First
Street NE, Washington, DC 20426
To file via any other courier: DebbieAnne A. Reese, Acting Secretary,
Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Comment Date: 5:00 p.m. Eastern
Time on February 15, 2024.
Dated: January 31, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024–02378 Filed 2–5–24; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OPPT–2022–0773; FRL–11730–
01–OMS]
Agency Information Collection
Activities; Submission to the Office of
Management and Budget for Review
and Approval; Comment Request;
Pollution Prevention (P2) Grantee Data
Collection in Standard Electronic
Format (New)
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
The Environmental Protection
Agency (EPA) has submitted the
following information collection request
(ICR), Pollution Prevention (P2) Grantee
Data Collection in Standard, (EPA ICR
SUMMARY:
E:\FR\FM\06FEN1.SGM
06FEN1
Agencies
[Federal Register Volume 89, Number 25 (Tuesday, February 6, 2024)]
[Notices]
[Page 8196]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-02378]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP20-50-000; CP20-51-000]
Tennessee Gas Pipeline Company, L.L.C; Southern Natural Gas
Company, L.L.C; Notice of Requests for Extension of Time
Take notice that on January 26, 2024, Tennessee Gas Pipeline
Company, L.L.C. (Tennessee) and Southern Natural Gas Company, L.L.C.
(Southern) requested that the Federal Energy Regulatory Commission
(Commission) grant an extension of time, until September 30, 2025, to
construct and place into service its Evangeline Pass Project (Project)
located in Louisiana as authorized in the Order Issuing Certificates
and Approving Abandonments (Order).\1\ The Order required Tennessee and
Southern to complete construction of the Project and make it available
for service within two years of the date of the Order, or by March 25,
2024.
---------------------------------------------------------------------------
\1\ Tennessee Gas Pipeline Company, L.L.C. and Southern Natural
Gas Company, L.L.C., 178 FERC ] 61,199 (2022).
---------------------------------------------------------------------------
Tennessee and Southern assert that they faced permitting delays
after the Order Addressing Arguments Raised on Rehearing was issued on
September 29, 2022.\2\ They submitted an implementation plan and
secured approval from the Commission on September 8, 2023, to begin
construction. However, they have faced delays in securing construction
contractors, finalizing land acquisition, and obtaining state and local
permits. As a result, they anticipate beginning construction activities
during the first quarter of 2024. Tennessee and Southern have requested
an extension of the in-service date to September 30, 2025, to ensure
that all necessary restoration activities are underway, and the Project
facilities are fully constructed.
---------------------------------------------------------------------------
\2\ Tennessee Gas Pipeline Company, L.L.C. and Southern Natural
Gas Company, L.L.C., 180 FERC ] 61,205 (2022).
---------------------------------------------------------------------------
This notice establishes a 15-calendar day intervention and comment
period deadline. Any person wishing to comment on Tennessee and
Southern's request for an extension of time may do so. No reply
comments or answers will be considered. If you wish to obtain legal
status by becoming a party to the proceedings for this request, you
should, on or before the comment date stated below, file a motion to
intervene in accordance with the requirements of the Commission's Rules
of Practice and Procedure (18 CFR 385.214 or 385.211) and the
Regulations under the Natural Gas Act (NGA) (18 CFR 157.10).
As a matter of practice, the Commission itself generally acts on
requests for extensions of time to complete construction for NGA
facilities when such requests are contested before order issuance. For
those extension requests that are contested,\3\ the Commission will aim
to issue an order acting on the request within 45 days.\4\ The
Commission will address all arguments relating to whether the applicant
has demonstrated there is good cause to grant the extension.\5\ The
Commission will not consider arguments that re-litigate the issuance of
the certificate order, including whether the Commission properly found
the project to be in the public convenience and necessity and whether
the Commission's environmental analysis for the certificate complied
with the National Environmental Policy Act (NEPA).\6\ At the time a
pipeline requests an extension of time, orders on certificates of
public convenience and necessity are final and the Commission will not
re-litigate their issuance.\7\ The Director of the Office of Energy
Projects, or his or her designee, will act on all of those extension
requests that are uncontested.
---------------------------------------------------------------------------
\3\ Contested proceedings are those where an intervenor disputes
any material issue of the filing. 18 CFR 385.2201(c)(1).
\4\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40
(2020).
\5\ Id. at P 40.
\6\ Similarly, the Commission will not re-litigate the issuance
of an NGA section 3 authorization, including whether a proposed
project is not inconsistent with the public interest and whether the
Commission's environmental analysis for the permit order complied
with NEPA.
\7\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40
(2020).
---------------------------------------------------------------------------
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (https://www.ferc.gov) using
the ``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. Public access
to records formerly available in the Commission's physical Public
Reference Room, which was located at the Commission's headquarters, 888
First Street NE, Washington, DC 20426, are now available via the
Commission's website. For assistance, contact FERC at
[email protected] or call toll free, (866) 208-3676 or TTY
(202) 502-8659.
The Commission strongly encourages electronic filings of comments
in lieu of paper using the ``eFile'' link at https://www.ferc.gov. In
lieu of electronic filing, you may submit a paper copy which must
reference the Project docket number.
To file via USPS: Debbie-Anne A. Reese, Acting Secretary, Federal
Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426
To file via any other courier: Debbie-Anne A. Reese, Acting Secretary,
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville,
Maryland 20852
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
Comment Date: 5:00 p.m. Eastern Time on February 15, 2024.
Dated: January 31, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-02378 Filed 2-5-24; 8:45 am]
BILLING CODE 6717-01-P