Florida Gas Transmission Company, LLC; Notice of Availability of the Environmental Assessment for the Proposed South Louisiana Project, 88387-88388 [2023-28131]

Download as PDF khammond on DSKJM1Z7X2PROD with NOTICES Federal Register / Vol. 88, No. 244 / Thursday, December 21, 2023 / Notices LGIA for Sithe Independence Facility SA1160 to be effective 12/1/2023. Filed Date: 12/15/23. Accession Number: 20231215–5047. Comment Date: 5 p.m. ET 1/5/24. Docket Numbers: ER24–678–000. Applicants: PJM Interconnection, L.L.C. Description: Tariff Amendment: Notice of Cancellation of WMPA, SA No. 6228; Queue No. AF2–057 Re: Withdrawal to be effective 2/14/2024. Filed Date: 12/15/23. Accession Number: 20231215–5065. Comment Date: 5 p.m. ET 1/5/24. Docket Numbers: ER24–679–000. Applicants: Duke Energy Florida, LLC, Duke Energy Carolinas, LLC. Description: Compliance filing: Duke Energy Florida, LLC submits tariff filing per 35: DEF-Compliance Filing— Attachment J to Joint OATT (LGIP/ LGIA) to be effective 4/1/2024. Filed Date: 12/15/23. Accession Number: 20231215–5067. Comment Date: 5 p.m. ET 1/5/24. Docket Numbers: ER24–680–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Revisions to CTOA re: Removal of ITCI as TO to be effective 2/14/2024. Filed Date: 12/15/23. Accession Number: 20231215–5082. Comment Date: 5 p.m. ET 1/5/24. Docket Numbers: ER24–681–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Revisions to Tariff RE: Removal of ITCI as TO to be effective 2/14/2024. Filed Date: 12/15/23. Accession Number: 20231215–5100. Comment Date: 5 p.m. ET 1/5/24. Docket Numbers: ER24–682–000. Applicants: Southern California Edison Company. Description: § 205(d) Rate Filing: SCE 3rd Amend LGIA, Genesis McCoy Solar TOT223/SA109 + Termination LA (SA252) to be effective 2/14/2024. Filed Date: 12/15/23. Accession Number: 20231215–5105. Comment Date: 5 p.m. ET 1/5/24. Docket Numbers: ER24–683–000. Applicants: Duke Energy Carolinas, LLC, Duke Energy Florida, LLC, Duke Energy Progress, LLC. Description: Compliance filing: Duke Energy Carolinas, LLC submits tariff filing per 35: Revisions to Attachment M to Joint OATT (SGIP/SGIA) to be effective 4/1/2024. Filed Date: 12/15/23. Accession Number: 20231215–5112. Comment Date: 5 p.m. ET 1/5/24. Docket Numbers: ER24–684–000. VerDate Sep<11>2014 18:15 Dec 20, 2023 Jkt 262001 Applicants: Fitchburg Gas and Electric Light Company, ISO New England Inc. Description: § 205(d) Rate Filing: Fitchburg Gas and Electric Light Company submits tariff filing per 35.13(a)(2)(iii: FG&E; Request to Correct the Tariff Record to be effective 3/1/ 2020. Filed Date: 12/15/23. Accession Number: 20231215–5128. Comment Date: 5 p.m. ET 1/5/24. Docket Numbers: ER24–685–000. Applicants: Alabama Power Company, Georgia Power Company, Mississippi Power Company. Description: § 205(d) Rate Filing: Alabama Power Company submits tariff filing per 35.13(a)(2)(iii: PowerSouth NITSA Amendment (Add Five Points 115 kV DP) to be effective 11/20/2023. Filed Date: 12/15/23. Accession Number: 20231215–5141. Comment Date: 5 p.m. ET 1/5/24. Docket Numbers: ER24–686–000. Applicants: New York Independent System Operator, Inc., PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: New York Independent System Operator, Inc. submits tariff filing per 35.13(a)(2)(iii: NYISO–PJM Joint 205 re: JOA tariff revisions to be effective 2/14/2024. Filed Date: 12/15/23. Accession Number: 20231215–5165. Comment Date: 5 p.m. ET 1/5/24. Docket Numbers: ER24–687–000. Applicants: Golden Fields Solar III, LLC. Description: § 205(d) Rate Filing: Certificate of Concurrence to be effective 12/16/2023. Filed Date: 12/15/23. Accession Number: 20231215–5166. Comment Date: 5 p.m. ET 1/5/24. Docket Numbers: ER24–688–000. Applicants: Florida Power & Light Company. Description: § 205(d) Rate Filing: FPL Amendments to OATT NWFL System Formula Rate Template to be effective 2/ 15/2024. Filed Date: 12/15/23. Accession Number: 20231215–5171. Comment Date: 5 p.m. ET 1/5/24. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be PO 00000 Frm 00028 Fmt 4703 Sfmt 4703 88387 considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: December 15, 2023. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2023–28133 Filed 12–20–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP23–492–000] Florida Gas Transmission Company, LLC; Notice of Availability of the Environmental Assessment for the Proposed South Louisiana Project The staff of the Federal Energy Regulatory Commission (FERC or Commission) has prepared an environmental assessment (EA) for the South Louisiana Project, proposed by Florida Gas Transmission Company, LLC (FGT) in the above-referenced docket. FGT requests to increase its certificated capacity and throughput by 100,000 million British thermal units per day to its shipper, Florida Power & Light Company, to diversify its supply sources of natural gas for downstream customers. FGT would accomplish this by modifying certain compressor stations in St. Landry, East Baton Rouge, and Washington Parishes, Louisiana, and Perry County, Mississippi. The EA assesses the potential environmental effects of the construction and operation of the South Louisiana Project in accordance with the requirements of the National Environmental Policy Act. The FERC E:\FR\FM\21DEN1.SGM 21DEN1 khammond on DSKJM1Z7X2PROD with NOTICES 88388 Federal Register / Vol. 88, No. 244 / Thursday, December 21, 2023 / Notices staff concludes that approval of the proposed project, with appropriate mitigating measures, would not constitute a major federal action significantly affecting the quality of the human environment. The proposed South Louisiana Project includes the following facilities: • uprating two existing natural gasfired compressor turbine units at FGT’s existing Compressor Station 7.5 in St. Landry Parish, Louisiana from 6,500 horsepower (hp) to 7,700 hp, each; • adding process cooling units to support the existing gas compressor units at FGT’s existing Compressor Station 8 in East Baton Rouge Parish, Louisiana; • installing one new 7,700 hp natural gas-fired turbine compressor unit at FGT’s existing Compressor Station 9 in Washington Parish, Louisiana; • installing one new 15,900 hp natural gas-fired compressor turbine unit at FGT’s existing Compressor Station 10 in Perry County, Mississippi; and • installing and modifying auxiliary facilities as needed at each location. The Commission mailed a copy of the Notice of Availability to federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American tribes; potentially affected landowners and other interested individuals and groups; and newspapers and libraries in the project area. The EA is only available in electronic format. It may be viewed and downloaded from the FERC’s website (www.ferc.gov), on the natural gas environmental documents page (https:// www.ferc.gov/industries-data/naturalgas/environment/environmentaldocuments). In addition, the EA may be accessed by using the eLibrary link on the FERC’s website. Click on the eLibrary link (https://elibrary.ferc.gov/ eLibrary/search), select ‘‘General Search’’ and enter the docket number in the ‘‘Docket Number’’ field (i.e., CP23– 492). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The EA is not a decision document. It presents Commission staff’s independent analysis of the environmental issues for the Commission to consider when addressing the merits of all issues in this proceeding. Any person wishing to comment on the EA may do so. Your comments should focus on the EA’s disclosure and discussion of potential environmental effects, reasonable VerDate Sep<11>2014 18:15 Dec 20, 2023 Jkt 262001 alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that the Commission has the opportunity to consider your comments prior to making its decision on this project, it is important that we receive your comments in Washington, DC on or before 5:00 p.m. Eastern Time on January 16, 2024. For your convenience, there are three methods you can use to file your comments to the Commission. The Commission encourages electronic filing of comments and has staff available to assist you at (866) 208–3676 or FercOnlineSupport@ferc.gov. Please carefully follow these instructions so that your comments are properly recorded. (1) You can file your comments electronically using the eComment feature on the Commission’s website (www.ferc.gov) under the link to FERC Online. This is an easy method for submitting brief, text-only comments on a project; (2) You can also file your comments electronically using the eFiling feature on the Commission’s website (www.ferc.gov) under the link to FERC Online. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You must select the type of filing you are making. If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the Commission. Be sure to reference the project docket number (CP23–492–000) on your letter. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. Filing environmental comments will not give you intervenor status, but you do not need intervenor status to have your comments considered. Only intervenors have the right to seek rehearing or judicial review of the Commission’s decision. At this point in this proceeding, the timeframe for filing timely intervention requests has expired. Any person seeking to become a party to the proceeding must file a motion to intervene out-of-time pursuant to Rule 214(b)(3) and (d) of the PO 00000 Frm 00029 Fmt 4703 Sfmt 4703 Commission’s Rules of Practice and Procedures (18 CFR 385.214(b)(3) and (d)) and show good cause why the time limitation should be waived. Motions to intervene are more fully described at https://www.ferc.gov/how-intervene. Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC website (www.ferc.gov) using the eLibrary link. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to https://www.ferc.gov/ ferc-online/overview to register for eSubscription. Dated: December 15, 2023. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2023–28131 Filed 12–20–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. RM19–12–000] Revisions to the Filing Process for Commission Forms; Notice of eForms Updates Notice is hereby given that, on March 28, 2024, the eXtensible Business Reporting Language (XBRL) taxonomies, validation rules, and rendering files needed to file the FERC Form Nos. 1, 1– F, 2, 2–A, 3–Q electric, 3–Q natural gas, E:\FR\FM\21DEN1.SGM 21DEN1

Agencies

[Federal Register Volume 88, Number 244 (Thursday, December 21, 2023)]
[Notices]
[Pages 88387-88388]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-28131]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP23-492-000]


Florida Gas Transmission Company, LLC; Notice of Availability of 
the Environmental Assessment for the Proposed South Louisiana Project

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) has prepared an environmental assessment (EA) for the South 
Louisiana Project, proposed by Florida Gas Transmission Company, LLC 
(FGT) in the above-referenced docket. FGT requests to increase its 
certificated capacity and throughput by 100,000 million British thermal 
units per day to its shipper, Florida Power & Light Company, to 
diversify its supply sources of natural gas for downstream customers. 
FGT would accomplish this by modifying certain compressor stations in 
St. Landry, East Baton Rouge, and Washington Parishes, Louisiana, and 
Perry County, Mississippi.
    The EA assesses the potential environmental effects of the 
construction and operation of the South Louisiana Project in accordance 
with the requirements of the National Environmental Policy Act. The 
FERC

[[Page 88388]]

staff concludes that approval of the proposed project, with appropriate 
mitigating measures, would not constitute a major federal action 
significantly affecting the quality of the human environment.
    The proposed South Louisiana Project includes the following 
facilities:
     uprating two existing natural gas-fired compressor turbine 
units at FGT's existing Compressor Station 7.5 in St. Landry Parish, 
Louisiana from 6,500 horsepower (hp) to 7,700 hp, each;
     adding process cooling units to support the existing gas 
compressor units at FGT's existing Compressor Station 8 in East Baton 
Rouge Parish, Louisiana;
     installing one new 7,700 hp natural gas-fired turbine 
compressor unit at FGT's existing Compressor Station 9 in Washington 
Parish, Louisiana;
     installing one new 15,900 hp natural gas-fired compressor 
turbine unit at FGT's existing Compressor Station 10 in Perry County, 
Mississippi; and
     installing and modifying auxiliary facilities as needed at 
each location.
    The Commission mailed a copy of the Notice of Availability to 
federal, state, and local government representatives and agencies; 
elected officials; environmental and public interest groups; Native 
American tribes; potentially affected landowners and other interested 
individuals and groups; and newspapers and libraries in the project 
area. The EA is only available in electronic format. It may be viewed 
and downloaded from the FERC's website (www.ferc.gov), on the natural 
gas environmental documents page (https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents). In addition, the EA 
may be accessed by using the eLibrary link on the FERC's website. Click 
on the eLibrary link (https://elibrary.ferc.gov/eLibrary/search), 
select ``General Search'' and enter the docket number in the ``Docket 
Number'' field (i.e., CP23-492). Be sure you have selected an 
appropriate date range. For assistance, please contact FERC Online 
Support at [email protected] or toll free at (866) 208-3676, 
or for TTY, contact (202) 502-8659.
    The EA is not a decision document. It presents Commission staff's 
independent analysis of the environmental issues for the Commission to 
consider when addressing the merits of all issues in this proceeding. 
Any person wishing to comment on the EA may do so. Your comments should 
focus on the EA's disclosure and discussion of potential environmental 
effects, reasonable alternatives, and measures to avoid or lessen 
environmental impacts. The more specific your comments, the more useful 
they will be. To ensure that the Commission has the opportunity to 
consider your comments prior to making its decision on this project, it 
is important that we receive your comments in Washington, DC on or 
before 5:00 p.m. Eastern Time on January 16, 2024.
    For your convenience, there are three methods you can use to file 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected]. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's website (www.ferc.gov) under the link to 
FERC Online. This is an easy method for submitting brief, text-only 
comments on a project;
    (2) You can also file your comments electronically using the 
eFiling feature on the Commission's website (www.ferc.gov) under the 
link to FERC Online. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the Commission. Be sure to reference the project docket number (CP23-
492-000) on your letter. Submissions sent via the U.S. Postal Service 
must be addressed to: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 
20426. Submissions sent via any other carrier must be addressed to: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 
12225 Wilkins Avenue, Rockville, Maryland 20852.
    Filing environmental comments will not give you intervenor status, 
but you do not need intervenor status to have your comments considered. 
Only intervenors have the right to seek rehearing or judicial review of 
the Commission's decision. At this point in this proceeding, the 
timeframe for filing timely intervention requests has expired. Any 
person seeking to become a party to the proceeding must file a motion 
to intervene out-of-time pursuant to Rule 214(b)(3) and (d) of the 
Commission's Rules of Practice and Procedures (18 CFR 385.214(b)(3) and 
(d)) and show good cause why the time limitation should be waived. 
Motions to intervene are more fully described at https://www.ferc.gov/how-intervene.
    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC website (www.ferc.gov) using the eLibrary link. The eLibrary link 
also provides access to the texts of all formal documents issued by the 
Commission, such as orders, notices, and rulemakings.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to https://www.ferc.gov/ferc-online/overview to 
register for eSubscription.

    Dated: December 15, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-28131 Filed 12-20-23; 8:45 am]
BILLING CODE 6717-01-P