Northern States Power Company; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and Deadline for Submission of Final Amendments, 88064-88065 [2023-27983]
Download as PDF
88064
Federal Register / Vol. 88, No. 243 / Wednesday, December 20, 2023 / Notices
pleadings to the Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426. Hand
delivered submissions in docketed
proceedings should be delivered to
Health and Human Services, 12225
Wilkins Avenue, Rockville, Maryland
20852.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Comment Date: 5 p.m. eastern time on
January 2, 2024.
Dated: December 14, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–27978 Filed 12–19–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2711–025]
ddrumheller on DSK120RN23PROD with NOTICES1
Northern States Power Company;
Notice of Application Tendered for
Filing With the Commission and
Soliciting Additional Study Requests
and Establishing Procedural Schedule
for Relicensing and Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
Minor License.
b. Project No.: 2711–025.
c. Date Filed: November 30, 2023.
d. Applicant: Northern States Power
Company (Northern States Power).
e. Name of Project: Trego
Hydroelectric Project (Trego Project).
f. Location: The project is located on
the Namekagon River in the City of
Trego in Washburn County, Wisconsin.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Donald Hartinger, Director of
Renewable Operation-Hydro, Xcel
Energy, 414 Nicollet Mall, 2,
Minneapolis, MN 55401; phone (651)
261–7668; or Matthew Miller,
Environmental Analyst, Xcel Energy,
1414 W Hamilton Ave., P.O. Box 8, Eau
Claire, WI 54702–0008; phone 715–737–
1353.
i. FERC Contact: Laura Washington
(202) 502–6072, Laura.Washington@
ferc.gov.
j. Cooperating Agencies: Federal,
state, local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 61,076 (2023).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: January 29, 2024.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free),
or(202) 502–8659 (TTY). In lieu of
electronic filing, you may submit a
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852. The first page of any filing
should include docket number P–2711–
025.
m. This application is not ready for
environmental analysis at this time.
n. The existing Trego Project consists
of the following existing facilities: (1) a
435.2-acre reservoir; (2) a 642-foot-long,
43.5-foot-high concrete dam; (3) a 59.5foot-long, 74-feet-high powerhouse
containing two James Leffel Company
vertical Francis-type turbines with a
total generating capacity of 1.2
megawatts; (4) a tailwater; and (5) a 49foot-long transmission line. Northern
States Power is not proposing any
changes to project facilities or operation.
o. A copy of the application can be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
at FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or (202) 502–
8659 (TTY).
You may also register online at https://
www.ferc.gov/docs-filing/esubscription.
asp to be notified via email of new
filings and issuances related to this or
other pending projects. For assistance,
contact FERC Online Support.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
p. Procedural schedule: The
application will be processed according
to the following preliminary schedule.
Revisions to the schedule will be made
as appropriate.
Milestone
Target date
Issue Deficiency Letter (if necessary) ............................................................................................................................................
Request Additional Information (if necessary) ................................................................................................................................
Issue Scoping Document 1 for comments .....................................................................................................................................
Issue Acceptance Letter .................................................................................................................................................................
Request Additional Information (if necessary) ................................................................................................................................
VerDate Sep<11>2014
18:02 Dec 19, 2023
Jkt 262001
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
E:\FR\FM\20DEN1.SGM
20DEN1
February 2024.
February 2024.
May 2024.
June 2024.
July 2024.
88065
Federal Register / Vol. 88, No. 243 / Wednesday, December 20, 2023 / Notices
Milestone
Target date
Issue Scoping Document 2 (if necessary) ......................................................................................................................................
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: December 14, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–27983 Filed 12–19–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2639–000]
ddrumheller on DSK120RN23PROD with NOTICES1
Northern States Power Company;
Notice of Authorization for Continued
Project Operation
The license for the Cornell
Hydroelectric Project No. 2639 was
issued for a period ending November 30,
2023.
Section 15(a)(1) of the FPA, 16 U.S.C.
808(a)(1), requires the Commission, at
the expiration of a license term, to issue
from year-to-year an annual license to
the then licensee(s) under the terms and
conditions of the prior license until a
new license is issued, or the project is
otherwise disposed of as provided in
section 15 or any other applicable
section of the FPA. If the project’s prior
license waived the applicability of
section 15 of the FPA, then, based on
section 9(b) of the Administrative
Procedure Act, 5 U.S.C. 558(c), and as
set forth at 18 CFR 16.21(a), if the
licensee of such project has filed an
application for a subsequent license, the
licensee may continue to operate the
project in accordance with the terms
and conditions of the license after the
minor or minor part license expires,
until the Commission acts on its
application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 2639
is issued to Northern States Power
Company for a period effective
December 1, 2023, through November
30, 2024, or until the issuance of a new
VerDate Sep<11>2014
18:02 Dec 19, 2023
Jkt 262001
license for the project or other
disposition under the FPA, whichever
comes first. If issuance of a new license
(or other disposition) does not take
place on or before November 30, 2024,
notice is hereby given that, pursuant to
18 CFR 16.18(c), an annual license
under section 15(a)(1) of the FPA is
renewed automatically without further
order or notice by the Commission,
unless the Commission orders
otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that Northern States Power Company is
authorized to continue operation of the
Cornell Hydroelectric Project under the
terms and conditions of the prior license
until the issuance of a subsequent
license for the project or other
disposition under the FPA, whichever
comes first.
Dated: December 13, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–27880 Filed 12–19–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 4881–000]
Fulcrum, LLC; Notice of Authorization
for Continued Project Operation
The license for the Barber Dam Project
No. 4881 was issued for a period ending
November 30, 2023.
Section 15(a)(1) of the FPA, 16 U.S.C.
808(a)(1), requires the Commission, at
the expiration of a license term, to issue
from year-to-year an annual license to
the then licensee(s) under the terms and
conditions of the prior license until a
new license is issued, or the project is
otherwise disposed of as provided in
section 15 or any other applicable
section of the FPA. If the project’s prior
license waived the applicability of
section 15 of the FPA, then, based on
section 9(b) of the Administrative
Procedure Act, 5 U.S.C. 558(c), and as
set forth at 18 CFR 16.21(a), if the
licensee of such project has filed an
application for a subsequent license, the
licensee may continue to operate the
project in accordance with the terms
and conditions of the license after the
minor or minor part license expires,
until the Commission acts on its
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
August 2024.
application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 4881
is issued to Fulcrum, LLC for a period
effective December 1, 2023, through
November 30, 2024, or until the
issuance of a new license for the project
or other disposition under the FPA,
whichever comes first. If issuance of a
new license (or other disposition) does
not take place on or before November
30, 2024, notice is hereby given that,
pursuant to 18 CFR 16.18(c), an annual
license under section 15(a)(1) of the
FPA is renewed automatically without
further order or notice by the
Commission, unless the Commission
orders otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that Fulcrum, LLC is authorized to
continue operation of the Barber Dam
Project under the terms and conditions
of the prior license until the issuance of
a subsequent license for the project or
other disposition under the FPA,
whichever comes first.
Dated: December 13, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–27879 Filed 12–19–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP24–22–000]
Southern Star Central Gas Pipeline,
Inc.; Notice of Application and
Establishing Intervention Deadline
Take notice that on December 4, 2023,
Southern Star Central Gas Pipeline, Inc.
(Southern Star), 4700 State Route 56,
Owensboro, Kentucky, 42301, filed an
application under section 7(b) of the
Natural Gas Act (NGA), and Part 157 of
the Commission’s regulations,
requesting authorization to abandon by
sale to Black Hills/Kansas Gas Utility
Company, LLC, d/b/a Black Hills
Energy, 273 domestic meters in the State
E:\FR\FM\20DEN1.SGM
20DEN1
Agencies
[Federal Register Volume 88, Number 243 (Wednesday, December 20, 2023)]
[Notices]
[Pages 88064-88065]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-27983]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2711-025]
Northern States Power Company; Notice of Application Tendered for
Filing With the Commission and Soliciting Additional Study Requests and
Establishing Procedural Schedule for Relicensing and Deadline for
Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Subsequent Minor License.
b. Project No.: 2711-025.
c. Date Filed: November 30, 2023.
d. Applicant: Northern States Power Company (Northern States
Power).
e. Name of Project: Trego Hydroelectric Project (Trego Project).
f. Location: The project is located on the Namekagon River in the
City of Trego in Washburn County, Wisconsin.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Donald Hartinger, Director of Renewable Operation-Hydro, Xcel
Energy, 414 Nicollet Mall, 2, Minneapolis, MN 55401; phone (651) 261-
7668; or Matthew Miller, Environmental Analyst, Xcel Energy, 1414 W
Hamilton Ave., P.O. Box 8, Eau Claire, WI 54702-0008; phone 715-737-
1353.
i. FERC Contact: Laura Washington (202) 502-6072,
[email protected].
j. Cooperating Agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See, 94 FERC ]
61,076 (2023).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: January 29, 2024.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support
at [email protected], (866) 208-3676 (toll free), or(202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy.
Submissions sent via the U.S. Postal Service must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via
any other carrier must be addressed to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville,
Maryland 20852. The first page of any filing should include docket
number P-2711-025.
m. This application is not ready for environmental analysis at this
time.
n. The existing Trego Project consists of the following existing
facilities: (1) a 435.2-acre reservoir; (2) a 642-foot-long, 43.5-foot-
high concrete dam; (3) a 59.5-foot-long, 74-feet-high powerhouse
containing two James Leffel Company vertical Francis-type turbines with
a total generating capacity of 1.2 megawatts; (4) a tailwater; and (5)
a 49-foot-long transmission line. Northern States Power is not
proposing any changes to project facilities or operation.
o. A copy of the application can be viewed on the Commission's
website at https://www.ferc.gov using the ``eLibrary'' link. Enter the
docket number excluding the last three digits in the docket number
field to access the document. For assistance, contact FERC at
[email protected] or call toll-free, (866) 208-3676 or (202)
502-8659 (TTY).
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
p. Procedural schedule: The application will be processed according
to the following preliminary schedule. Revisions to the schedule will
be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Issue Deficiency Letter (if necessary)....... February 2024.
Request Additional Information (if necessary) February 2024.
Issue Scoping Document 1 for comments........ May 2024.
Issue Acceptance Letter...................... June 2024.
Request Additional Information (if necessary) July 2024.
[[Page 88065]]
Issue Scoping Document 2 (if necessary)...... August 2024.
------------------------------------------------------------------------
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: December 14, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-27983 Filed 12-19-23; 8:45 am]