THSI bn, LLC; Notice of Filing, 88063-88064 [2023-27978]
Download as PDF
Federal Register / Vol. 88, No. 243 / Wednesday, December 20, 2023 / Notices
of the current license.2 As stated above,
Willimantic Power Corporation’s NOI
indicated that it would be filing an
application for a subsequent license;
however, it did not file an application
for a subsequent license or an
application for an exemption from
licensing for the Willimantic #1 Project
by the November 30, 2023 deadline.
Therefore, pursuant to section
16.25(a) of the Commission’s
regulations, we are soliciting
applications from potential applicants
other than the existing licensee.3
Interested parties have 90 days from the
date of this notice to file a NOI to file
an application for a subsequent license.
An application for a subsequent license
or exemption for the Willimantic #1
Project (No. 8051) may be filed within
18 months of the date of filing the NOI.
The existing licensee is prohibited from
filing an application either individually
or in combination with other entities.4
Questions concerning this notice
should be directed to Jeanne Edwards at
(202) 502–6181 or jeanne.edwards@
ferc.gov.
Dated: December 14, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–27981 Filed 12–19–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
ddrumheller on DSK120RN23PROD with NOTICES1
Filings Instituting Proceedings
Docket Numbers: RP24–241–000.
Applicants: Eastern Gas Transmission
and Storage, Inc.
Description: 4(d) Rate Filing: EGTS—
December 13, 2023 Administrative
Changes to be effective 1/16/2024.
Filed Date: 12/13/23.
Accession Number: 20231213–5027.
Comment Date: 5 p.m. ET 12/26/23.
Docket Numbers: RP24–242–000.
Applicants: Cove Point LNG, LP.
Description: 4(d) Rate Filing: Cove
Point—December 13, 2023
Administrative Changes to be effective
1/16/2024.
Filed Date: 12/13/23.
Accession Number: 20231213–5029.
Comment Date: 5 p.m. ET 12/26/23.
CFR 16.20(c) (2022).
§ 16.25(a) (2022).
4 Id. § 16.24(b)(2) (2022).
Docket Numbers: RP24–219–001.
Applicants: Gulf South Pipeline
Company, LLC.
Description: Tariff Amendment:
Amendment filing to RP24–219–000 to
be effective 12/1/2023.
Filed Date: 12/12/23.
Accession Number: 20231212–5109.
Comment Date: 5 p.m. ET 12/26/23.
Any person desiring to protest in any
the above proceedings must file in
accordance with Rule 211 of the
Commission’s Regulations (18 CFR
385.211) on or before 5 p.m. Eastern
time on the specified comment date.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Dated: December 13, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. TX23–5–000]
THSI bn, LLC; Notice of Filing
Take notice that on December 12,
2023, in accordance with the Federal
Energy Regulatory Commission’s
proposed order directing
interconnection service issued October
19, 2023,1 THSI bn, LLC and Arizona
Electric Power Cooperative filed a
proposed Large Generator
Interconnection Agreement and three
other agreements.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Applicant. On
or before the comment date, it is not
necessary to serve motions to intervene
or protests on persons other than the
Applicant.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically may mail similar
BILLING CODE 6717–01–P
3 Id.
18:02 Dec 19, 2023
Filings in Existing Proceedings
[FR Doc. 2023–27884 Filed 12–19–23; 8:45 am]
2 18
VerDate Sep<11>2014
Any person desiring to intervene, to
protest, or to answer a complaint in any
of the above proceedings must file in
accordance with Rules 211, 214, or 206
of the Commission’s Regulations (18
CFR 385.211, 385.214, or 385.206) on or
before 5 p.m. Eastern time on the
specified comment date. Protests may be
considered, but intervention is
necessary to become a party to the
proceeding.
88063
1 THSI
Jkt 262001
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
E:\FR\FM\20DEN1.SGM
bn, LLC, 185 FERC ¶ 61,032 (2023).
20DEN1
88064
Federal Register / Vol. 88, No. 243 / Wednesday, December 20, 2023 / Notices
pleadings to the Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426. Hand
delivered submissions in docketed
proceedings should be delivered to
Health and Human Services, 12225
Wilkins Avenue, Rockville, Maryland
20852.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Comment Date: 5 p.m. eastern time on
January 2, 2024.
Dated: December 14, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–27978 Filed 12–19–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2711–025]
ddrumheller on DSK120RN23PROD with NOTICES1
Northern States Power Company;
Notice of Application Tendered for
Filing With the Commission and
Soliciting Additional Study Requests
and Establishing Procedural Schedule
for Relicensing and Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
Minor License.
b. Project No.: 2711–025.
c. Date Filed: November 30, 2023.
d. Applicant: Northern States Power
Company (Northern States Power).
e. Name of Project: Trego
Hydroelectric Project (Trego Project).
f. Location: The project is located on
the Namekagon River in the City of
Trego in Washburn County, Wisconsin.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Donald Hartinger, Director of
Renewable Operation-Hydro, Xcel
Energy, 414 Nicollet Mall, 2,
Minneapolis, MN 55401; phone (651)
261–7668; or Matthew Miller,
Environmental Analyst, Xcel Energy,
1414 W Hamilton Ave., P.O. Box 8, Eau
Claire, WI 54702–0008; phone 715–737–
1353.
i. FERC Contact: Laura Washington
(202) 502–6072, Laura.Washington@
ferc.gov.
j. Cooperating Agencies: Federal,
state, local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 61,076 (2023).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: January 29, 2024.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free),
or(202) 502–8659 (TTY). In lieu of
electronic filing, you may submit a
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852. The first page of any filing
should include docket number P–2711–
025.
m. This application is not ready for
environmental analysis at this time.
n. The existing Trego Project consists
of the following existing facilities: (1) a
435.2-acre reservoir; (2) a 642-foot-long,
43.5-foot-high concrete dam; (3) a 59.5foot-long, 74-feet-high powerhouse
containing two James Leffel Company
vertical Francis-type turbines with a
total generating capacity of 1.2
megawatts; (4) a tailwater; and (5) a 49foot-long transmission line. Northern
States Power is not proposing any
changes to project facilities or operation.
o. A copy of the application can be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
at FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or (202) 502–
8659 (TTY).
You may also register online at https://
www.ferc.gov/docs-filing/esubscription.
asp to be notified via email of new
filings and issuances related to this or
other pending projects. For assistance,
contact FERC Online Support.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
p. Procedural schedule: The
application will be processed according
to the following preliminary schedule.
Revisions to the schedule will be made
as appropriate.
Milestone
Target date
Issue Deficiency Letter (if necessary) ............................................................................................................................................
Request Additional Information (if necessary) ................................................................................................................................
Issue Scoping Document 1 for comments .....................................................................................................................................
Issue Acceptance Letter .................................................................................................................................................................
Request Additional Information (if necessary) ................................................................................................................................
VerDate Sep<11>2014
18:02 Dec 19, 2023
Jkt 262001
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
E:\FR\FM\20DEN1.SGM
20DEN1
February 2024.
February 2024.
May 2024.
June 2024.
July 2024.
Agencies
[Federal Register Volume 88, Number 243 (Wednesday, December 20, 2023)]
[Notices]
[Pages 88063-88064]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-27978]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. TX23-5-000]
THSI bn, LLC; Notice of Filing
Take notice that on December 12, 2023, in accordance with the
Federal Energy Regulatory Commission's proposed order directing
interconnection service issued October 19, 2023,\1\ THSI bn, LLC and
Arizona Electric Power Cooperative filed a proposed Large Generator
Interconnection Agreement and three other agreements.
---------------------------------------------------------------------------
\1\ THSI bn, LLC, 185 FERC ] 61,032 (2023).
---------------------------------------------------------------------------
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken, but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. Such notices,
motions, or protests must be filed on or before the comment date.
Anyone filing a motion to intervene or protest must serve a copy of
that document on the Applicant. On or before the comment date, it is
not necessary to serve motions to intervene or protests on persons
other than the Applicant.
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (https://ferc.gov) using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to the Commission's Public
Reference Room, due to the proclamation declaring a National Emergency
concerning the Novel Coronavirus Disease (COVID-19), issued by the
President on March 13, 2020. For assistance, contact FERC at
[email protected] or call toll-free, (886) 208-3676 or TYY,
(202) 502-8659.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at https://www.ferc.gov. Persons unable to file electronically may mail
similar
[[Page 88064]]
pleadings to the Federal Energy Regulatory Commission, 888 First Street
NE, Washington, DC 20426. Hand delivered submissions in docketed
proceedings should be delivered to Health and Human Services, 12225
Wilkins Avenue, Rockville, Maryland 20852.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
Comment Date: 5 p.m. eastern time on January 2, 2024.
Dated: December 14, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-27978 Filed 12-19-23; 8:45 am]
BILLING CODE 6717-01-P