Fulcrum, LLC; Notice of Authorization for Continued Project Operation, 88065 [2023-27879]
Download as PDF
88065
Federal Register / Vol. 88, No. 243 / Wednesday, December 20, 2023 / Notices
Milestone
Target date
Issue Scoping Document 2 (if necessary) ......................................................................................................................................
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: December 14, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–27983 Filed 12–19–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2639–000]
ddrumheller on DSK120RN23PROD with NOTICES1
Northern States Power Company;
Notice of Authorization for Continued
Project Operation
The license for the Cornell
Hydroelectric Project No. 2639 was
issued for a period ending November 30,
2023.
Section 15(a)(1) of the FPA, 16 U.S.C.
808(a)(1), requires the Commission, at
the expiration of a license term, to issue
from year-to-year an annual license to
the then licensee(s) under the terms and
conditions of the prior license until a
new license is issued, or the project is
otherwise disposed of as provided in
section 15 or any other applicable
section of the FPA. If the project’s prior
license waived the applicability of
section 15 of the FPA, then, based on
section 9(b) of the Administrative
Procedure Act, 5 U.S.C. 558(c), and as
set forth at 18 CFR 16.21(a), if the
licensee of such project has filed an
application for a subsequent license, the
licensee may continue to operate the
project in accordance with the terms
and conditions of the license after the
minor or minor part license expires,
until the Commission acts on its
application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 2639
is issued to Northern States Power
Company for a period effective
December 1, 2023, through November
30, 2024, or until the issuance of a new
VerDate Sep<11>2014
18:02 Dec 19, 2023
Jkt 262001
license for the project or other
disposition under the FPA, whichever
comes first. If issuance of a new license
(or other disposition) does not take
place on or before November 30, 2024,
notice is hereby given that, pursuant to
18 CFR 16.18(c), an annual license
under section 15(a)(1) of the FPA is
renewed automatically without further
order or notice by the Commission,
unless the Commission orders
otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that Northern States Power Company is
authorized to continue operation of the
Cornell Hydroelectric Project under the
terms and conditions of the prior license
until the issuance of a subsequent
license for the project or other
disposition under the FPA, whichever
comes first.
Dated: December 13, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–27880 Filed 12–19–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 4881–000]
Fulcrum, LLC; Notice of Authorization
for Continued Project Operation
The license for the Barber Dam Project
No. 4881 was issued for a period ending
November 30, 2023.
Section 15(a)(1) of the FPA, 16 U.S.C.
808(a)(1), requires the Commission, at
the expiration of a license term, to issue
from year-to-year an annual license to
the then licensee(s) under the terms and
conditions of the prior license until a
new license is issued, or the project is
otherwise disposed of as provided in
section 15 or any other applicable
section of the FPA. If the project’s prior
license waived the applicability of
section 15 of the FPA, then, based on
section 9(b) of the Administrative
Procedure Act, 5 U.S.C. 558(c), and as
set forth at 18 CFR 16.21(a), if the
licensee of such project has filed an
application for a subsequent license, the
licensee may continue to operate the
project in accordance with the terms
and conditions of the license after the
minor or minor part license expires,
until the Commission acts on its
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
August 2024.
application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 4881
is issued to Fulcrum, LLC for a period
effective December 1, 2023, through
November 30, 2024, or until the
issuance of a new license for the project
or other disposition under the FPA,
whichever comes first. If issuance of a
new license (or other disposition) does
not take place on or before November
30, 2024, notice is hereby given that,
pursuant to 18 CFR 16.18(c), an annual
license under section 15(a)(1) of the
FPA is renewed automatically without
further order or notice by the
Commission, unless the Commission
orders otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that Fulcrum, LLC is authorized to
continue operation of the Barber Dam
Project under the terms and conditions
of the prior license until the issuance of
a subsequent license for the project or
other disposition under the FPA,
whichever comes first.
Dated: December 13, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–27879 Filed 12–19–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP24–22–000]
Southern Star Central Gas Pipeline,
Inc.; Notice of Application and
Establishing Intervention Deadline
Take notice that on December 4, 2023,
Southern Star Central Gas Pipeline, Inc.
(Southern Star), 4700 State Route 56,
Owensboro, Kentucky, 42301, filed an
application under section 7(b) of the
Natural Gas Act (NGA), and Part 157 of
the Commission’s regulations,
requesting authorization to abandon by
sale to Black Hills/Kansas Gas Utility
Company, LLC, d/b/a Black Hills
Energy, 273 domestic meters in the State
E:\FR\FM\20DEN1.SGM
20DEN1
Agencies
[Federal Register Volume 88, Number 243 (Wednesday, December 20, 2023)]
[Notices]
[Page 88065]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-27879]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 4881-000]
Fulcrum, LLC; Notice of Authorization for Continued Project
Operation
The license for the Barber Dam Project No. 4881 was issued for a
period ending November 30, 2023.
Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the
Commission, at the expiration of a license term, to issue from year-to-
year an annual license to the then licensee(s) under the terms and
conditions of the prior license until a new license is issued, or the
project is otherwise disposed of as provided in section 15 or any other
applicable section of the FPA. If the project's prior license waived
the applicability of section 15 of the FPA, then, based on section 9(b)
of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth
at 18 CFR 16.21(a), if the licensee of such project has filed an
application for a subsequent license, the licensee may continue to
operate the project in accordance with the terms and conditions of the
license after the minor or minor part license expires, until the
Commission acts on its application. If the licensee of such a project
has not filed an application for a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b), to continue project operations
until the Commission issues someone else a license for the project or
otherwise orders disposition of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 4881 is issued to
Fulcrum, LLC for a period effective December 1, 2023, through November
30, 2024, or until the issuance of a new license for the project or
other disposition under the FPA, whichever comes first. If issuance of
a new license (or other disposition) does not take place on or before
November 30, 2024, notice is hereby given that, pursuant to 18 CFR
16.18(c), an annual license under section 15(a)(1) of the FPA is
renewed automatically without further order or notice by the
Commission, unless the Commission orders otherwise.
If the project is not subject to section 15 of the FPA, notice is
hereby given that Fulcrum, LLC is authorized to continue operation of
the Barber Dam Project under the terms and conditions of the prior
license until the issuance of a subsequent license for the project or
other disposition under the FPA, whichever comes first.
Dated: December 13, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-27879 Filed 12-19-23; 8:45 am]
BILLING CODE 6717-01-P