Federal Register / Vol. 88, No. 240 / Friday, December 15, 2023 / Notices
determine whether non-competing
continuation funds should be awarded
in multi-year grants. Only grantees that
can demonstrate that they are making
substantial progress (or, if not, have
submitted an acceptable plan for
meeting their objectives in subsequent
budget periods) are eligible for
continuation funding.
ED uses the information submitted on
the ED 524B as a final performance
report to determine whether grantees
whose projects have ended have
achieved project objectives and met or
exceeded the Government Performance
and Results Act and/or other program
performance measures and grant
requirements. This determination
enables ED to assure that grants can be
closed out in compliance.
Dated: December 11, 2023.
Stephanie Valentine,
PRA Coordinator, Strategic Collections and
Clearance Governance and Strategy Division,
Office of Chief Data Officer, Office of
Planning, Evaluation and Policy
Development.
[FR Doc. 2023–27533 Filed 12–14–23; 8:45 am]
BILLING CODE 4000–01–P
ELECTION ASSISTANCE COMMISSION
Sunshine Act Meetings
Election Assistance
Commission.
ACTION: Sunshine Act Notice; Notice of
public meeting agenda.
AGENCY:
Public Meeting: U.S. Election
Assistance Commission Local
Leadership Council 2024 Annual
Meeting.
SUMMARY:
Monday, January 8, 1:00 p.m.–
5:00 p.m. Eastern and Tuesday, January
9, 9:00 a.m.–5:00 p.m. Eastern.
ADDRESSES: DoubleTree by Hilton Hotel
Crystal City, 300 Army Navy Drive,
Arlington, Virginia, 22202.
FOR FURTHER INFORMATION CONTACT:
Kristen Muthig, Telephone: (202) 897–
9285, Email: kmuthig@eac.gov.
SUPPLEMENTARY INFORMATION:
Purpose: In accordance with the
Government in the Sunshine Act
(Sunshine Act), Public Law 94–409, as
amended (5 U.S.C. 552b), the U.S.
Election Assistance Commission (EAC)
will conduct an annual meeting of the
EAC Local Leadership Council to
conduct regular business and discuss
EAC updates and upcoming programs.
Agenda: The U.S. Election Assistance
Commission (EAC) Local Leadership
Council will hold its 2024 Annual
Meeting primarily to conduct regular
business, and discuss EAC updates and
ddrumheller on DSK120RN23PROD with NOTICES1
DATES:
VerDate Sep<11>2014
18:50 Dec 14, 2023
Jkt 262001
upcoming programs, such as election
technology and preparing for the 2024
elections. The meeting will include
moderated discussion on topics such as
communications, continuity of
operations planning, and presentations
from federal election partners.
Throughout the meeting, there will be
opportunities for members to ask
questions.
Background: The Local Leadership
Council was established in June 2021
under agency authority pursuant to and
in accordance with the provisions of the
Federal Advisory Committee Act, as
amended (5 U.S.C. App. 2). The
Advisory Committee is governed by the
Federal Advisory Committee Act, which
sets forth standards for the formation
and use of advisory committees. The
Advisory Committee advises the EAC on
how best to fulfill the EAC’s statutory
duties set forth in 52 U.S.C. 20922 as
well as such other matters as the EAC
determines. It shall provide a relevant
and comprehensive source of expert,
unbiased analysis and recommendations
to the EAC on local election
administration topics.
The Local Leadership Council
consists of 100 members. The Election
Assistance Commission appoints two
members from each state after soliciting
nominations from each state’s election
official professional association. At the
time of submission, the Local
Leadership Council has 89 appointed
members. Upon appointment, Advisory
Committee members must be serving or
have previously served in a leadership
role in a state election official
professional association.
The full agenda will be posted in
advance on the EAC website: https://
www.eac.gov.
Status: This meeting will be open to
the public.
Camden Kelliher,
Deputy General Counsel, U.S. Election
Assistance Commission.
[FR Doc. 2023–27755 Filed 12–13–23; 4:15 pm]
exemption from licensing for the
project.1 The existing license for the
project expires on November 30, 2025.2
On September 20, 2023, Fiske Hydro
filed an application to surrender its
license for the project.3
Pursuant to section 16.20 of the
Commission’s regulations, an existing
licensee with a minor license not
subject to sections 14 and 15 of the
Federal Power Act must file an
application for a subsequent license or
exemption at least 24 months prior to
the expiration of the current license,
which with respect to the Fiske Mill
Project, was November 30, 2023.4
Pursuant to section 16.25(a) of the
Commission’s regulations, when an
existing licensee, having previously
filed an NOI to file an application for an
exemption subsequently does not file an
application, the Commission must
solicit applications from potential
applicants other than the existing
licensee.5 Any party interested in filing
an application for the project must file
an NOI document within 90 days from
the date of this notice.6 In addition,
NOIs for a subsequent license must also
include a pre-application document
(PAD). Moreover, while the integrated
licensing process is the default process
for preparing an application for a
subsequent license, a potential
applicant for a subsequent license may
include with the NOI and PAD a request
to use alternative licensing procedures.7
An application for the Fiske Mill
Hydroelectric Project No. 8615 must be
filed within 18 months of the date of
filing the NOI.
Questions concerning the process for
filing an NOI should be directed to
Robert Haltner at 202–502–8612 or
robert.haltner@ferc.gov.
Dated: December 8, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–27520 Filed 12–14–23; 8:45 am]
BILLING CODE 6717–01–P
BILLING CODE 4810–71–P
1 18
FEDERAL ENERGY REGULATORY
COMMISSION
[Project No. 8615–047]
Fiske Hydro, Inc.; Notice Soliciting PreApplication Documents and Notices of
Intent To File a Subsequent License
Application
On November 30, 2020, Fiske Hydro,
Inc. (Fiske Hydro), the current licensee
for the Fiske Mill Hydroelectric Project
No. 8615 (project), filed a Notice of
Intent (NOI) to file an application for an
PO 00000
Frm 00016
Fmt 4703
Sfmt 4703
CFR 16.19(b) (2022).
license for the project was issued with an
effective date of December 1, 1985, for a term of 40
years. Fiske Hydro Inc., 33 FERC ¶ 62,299 (1985).
3 The surrender application filing may be viewed
at https://elibrary.ferc.gov/eLibrary/filedownload?
fileid=E18CC70E-85D5-C3FB-9C8C-8AB7E1600000.
The Commission is not seeking public comment on
the surrender application at this time.
4 18 CFR 16.20(c) (2022).
5 18 CFR 16.25(a) (2022).
6 Pursuant to section 16.24(b)(2) of the
Commission’s regulations, the existing licensee,
Fiske Hydro, Inc., is prohibited from filing an
application for the project, either individually or in
conjunction with other entities. 18 CFR 16.24(b)(2)
(2022).
7 18 CFR 5.3(b) (2022).
2 The
E:\FR\FM\15DEN1.SGM
15DEN1
Agencies
[Federal Register Volume 88, Number 240 (Friday, December 15, 2023)]
[Notices]
[Page 86888]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-27520]
=======================================================================
-----------------------------------------------------------------------
FEDERAL ENERGY REGULATORY COMMISSION
[Project No. 8615-047]
Fiske Hydro, Inc.; Notice Soliciting Pre-Application Documents
and Notices of Intent To File a Subsequent License Application
On November 30, 2020, Fiske Hydro, Inc. (Fiske Hydro), the current
licensee for the Fiske Mill Hydroelectric Project No. 8615 (project),
filed a Notice of Intent (NOI) to file an application for an exemption
from licensing for the project.\1\ The existing license for the project
expires on November 30, 2025.\2\ On September 20, 2023, Fiske Hydro
filed an application to surrender its license for the project.\3\
---------------------------------------------------------------------------
\1\ 18 CFR 16.19(b) (2022).
\2\ The license for the project was issued with an effective
date of December 1, 1985, for a term of 40 years. Fiske Hydro Inc.,
33 FERC ] 62,299 (1985).
\3\ The surrender application filing may be viewed at https://elibrary.ferc.gov/eLibrary/filedownload?fileid=E18CC70E-85D5-C3FB-9C8C-8AB7E1600000. The Commission is not seeking public comment on
the surrender application at this time.
---------------------------------------------------------------------------
Pursuant to section 16.20 of the Commission's regulations, an
existing licensee with a minor license not subject to sections 14 and
15 of the Federal Power Act must file an application for a subsequent
license or exemption at least 24 months prior to the expiration of the
current license, which with respect to the Fiske Mill Project, was
November 30, 2023.\4\
---------------------------------------------------------------------------
\4\ 18 CFR 16.20(c) (2022).
---------------------------------------------------------------------------
Pursuant to section 16.25(a) of the Commission's regulations, when
an existing licensee, having previously filed an NOI to file an
application for an exemption subsequently does not file an application,
the Commission must solicit applications from potential applicants
other than the existing licensee.\5\ Any party interested in filing an
application for the project must file an NOI document within 90 days
from the date of this notice.\6\ In addition, NOIs for a subsequent
license must also include a pre-application document (PAD). Moreover,
while the integrated licensing process is the default process for
preparing an application for a subsequent license, a potential
applicant for a subsequent license may include with the NOI and PAD a
request to use alternative licensing procedures.\7\ An application for
the Fiske Mill Hydroelectric Project No. 8615 must be filed within 18
months of the date of filing the NOI.
---------------------------------------------------------------------------
\5\ 18 CFR 16.25(a) (2022).
\6\ Pursuant to section 16.24(b)(2) of the Commission's
regulations, the existing licensee, Fiske Hydro, Inc., is prohibited
from filing an application for the project, either individually or
in conjunction with other entities. 18 CFR 16.24(b)(2) (2022).
\7\ 18 CFR 5.3(b) (2022).
---------------------------------------------------------------------------
Questions concerning the process for filing an NOI should be
directed to Robert Haltner at 202-502-8612 or [email protected].
Dated: December 8, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-27520 Filed 12-14-23; 8:45 am]