Download as PDF Federal Register / Vol. 88, No. 237 / Tuesday, December 12, 2023 / Notices contact FERC Online Support at FERCOnlineSupport@ferc.gov. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. n. Scoping Process. Pursuant to the National Environmental Policy Act (NEPA), Commission staff intends to prepare either an environmental assessment (EA) or an environmental impact statement (EIS) (collectively referred to as the ‘‘NEPA document’’) that describes and evaluates the probable effects, including an assessment of the sitespecific and cumulative effects, if any, of the proposed action and alternatives. The Commission’s scoping process will help determine the required level of analysis and satisfy the NEPA scoping requirements, irrespective of whether the Commission issues an EA or an EIS. At this time, we do not anticipate holding on-site scoping meetings. Instead, we are soliciting written comments and suggestions on the preliminary list of issues and alternatives to be addressed in the NEPA document, as described in scoping document 1 (SD1), issued December 6, 2023. Copies of the SD1 outlining the proposed project and subject areas to be addressed in the NEPA document were distributed to the parties on the Commission’s mailing list and the applicant’s distribution list. Copies of SD1 may be viewed on the web at https://www.ferc.gov using the ‘‘eLibrary’’ link (see item m above). Dated: December 6, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–27226 Filed 12–11–23; 8:45 am] ddrumheller on DSK120RN23PROD with NOTICES1 BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following electric corporate filings: VerDate Sep<11>2014 18:03 Dec 11, 2023 Jkt 262001 Docket Numbers: EC24–21–000. Applicants: TotalEnergies Flexible Power USA, LLC, TexGen Power, LLC. Description: Joint Application for Authorization Under Section 203 of the Federal Power Act of TotalEnergies Flexible Power USA, LLC, et. al. Filed Date: 12/4/23. Accession Number: 20231204–5280. Comment Date: 5 p.m. ET 12/26/23. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER24–86–000. Applicants: EFS Parlin Holdings, LLC. Description: Supplement to October 12, 2023 EFS Parlin Holdings, LLC tariff filing. Filed Date: 11/30/23. Accession Number: 20231130–5353. Comment Date: 5 p.m. ET 12/21/23. Docket Numbers: ER24–228–002. Applicants: South Cheyenne Solar, LLC. Description: Tariff Amendment: Revision of Proposed Market-Based Rate Tariff to be effective 12/1/2023. Filed Date: 12/1/23. Accession Number: 20231201–5248. Comment Date: 5 pm ET 12/11/23. Docket Numbers: ER24–537–000. Applicants: Southwestern Public Service Company Description: Petition for Limited Waiver of Southwestern Public Service Company. Filed Date: 12/4/23. Accession Number: 20231204–5142. Comment Date: 5 pm ET 12/18/23. Docket Numbers: ER24–543–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Amendment to 10 Service Agreements re: FirstEnergy Reorganization to be effective 12/31/9998. Filed Date: 12/4/23. Accession Number: 20231204–5212. Comment Date: 5 pm ET 12/26/23. Docket Numbers: ER24–544–000. Applicants: Robin Hollow Solar Lessee, LLC. Description: Tariff Amendment: Notice of MBR Cancellation to be effective 12/5/2023. Filed Date: 12/4/23. Accession Number: 20231204–5223. Comment Date: 5 pm ET 12/26/23. Docket Numbers: ER24–545–000. Applicants: American Electric Power Service Corporation, Appalachian Power Company. Description: Petition for Limited Waiver of Appalachian Power Company. Filed Date: 12/4/23. Accession Number: 20231204–5283. PO 00000 Frm 00024 Fmt 4703 Sfmt 4703 86127 Comment Date: 5 pm ET 12/26/23. Docket Numbers: ER24–546–000. Applicants: Virginia Electric and Power Company, PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Virginia Electric and Power Company submits tariff filing per 35.13(a)(2)(iii: VEPCO submits One WDSA, SA No. 7136 to be effective 11/6/2023. Filed Date: 12/5/23. Accession Number: 20231205–5045. Comment Date: 5 pm ET 12/26/23. Docket Numbers: ER24–547–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: Revisions to Modify Operating Tolerances for Uninstructued Resource Deviation to be effective 12/31/9998. Filed Date: 12/5/23. Accession Number: 20231205–5071. Comment Date: 5 pm ET 12/26/23. Docket Numbers: ER24–548–000. Applicants: Dow Hydrocarbons and Resources LLC. Description: Baseline eTariff Filing: Petition for Approval of Initial MarketBased Rate Tariff to be effective 2/4/ 2024. Filed Date: 12/5/23. Accession Number: 20231205–5078. Comment Date: 5 pm ET 12/26/23. Docket Numbers: ER24–549–000. Applicants: Santa Rosa Energy Center, LLC. Description: § 205(d) Rate Filing: Market-Based Rate Tariff Revisions to be effective 12/6/2023. Filed Date: 12/5/23. Accession Number: 20231205–5102. Comment Date: 5 pm ET 12/26/23. Docket Numbers: ER24–550–000. Applicants: Arizona Public Service Company. Description: § 205(d) Rate Filing: Rate Schedule No. 292, Amendment No. 1 to be effective 2/4/2024. Filed Date: 12/5/23. Accession Number: 20231205–5125. Comment Date: 5 pm ET 12/26/23. Docket Numbers: ER24–551–000. Applicants: Elkhart County Solar Project, LLC. Description: Baseline eTariff Filing: Market-Based Rate Application to be effective 2/4/2024. Filed Date: 12/5/23. Accession Number: 20231205–5133. Comment Date: 5 pm ET 12/26/23. Docket Numbers: ER24–552–000. Applicants: Martin County II Solar Project, LLC. Description: Baseline eTariff Filing: Market-Based Rate Application to be effective 2/4/2024. Filed Date: 12/5/23. E:\FR\FM\12DEN1.SGM 12DEN1 86128 Federal Register / Vol. 88, No. 237 / Tuesday, December 12, 2023 / Notices [Project No. 11426–000] issued for a period ending October 31, 2023. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the Commission, at the expiration of a license term, to issue from year-to-year an annual license to the then licensee(s) under the terms and conditions of the prior license until a new license is issued, or the project is otherwise disposed of as provided in section 15 or any other applicable section of the FPA. If the project’s prior license waived the applicability of section 15 of the FPA, then, based on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth at 18 CFR 16.21(a), if the licensee of such project has filed an application for a subsequent license, the licensee may continue to operate the project in accordance with the terms and conditions of the license after the minor or minor part license expires, until the Commission acts on its application. If the licensee of such a project has not filed an application for a subsequent license, then it may be required, pursuant to 18 CFR 16.21(b), to continue project operations until the Commission issues someone else a license for the project or otherwise orders disposition of the project. If the project is subject to section 15 of the FPA, notice is hereby given that an annual license for Project No. 11426 is issued to T.A. Keck III and H.S. Keck for a period effective November 1, 2023, through October 31, 2024, or until the issuance of a new license for the project or other disposition under the FPA, whichever comes first. If issuance of a new license (or other disposition) does not take place on or before October 31, 2024, notice is hereby given that, pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is renewed automatically without further order or notice by the Commission, unless the Commission orders otherwise. If the project is not subject to section 15 of the FPA, notice is hereby given that T.A. Keck III and H.S. Keck is authorized to continue operation of the Blackstone Mill Hydroelectric Project under the terms and conditions of the prior license until the issuance of a subsequent license for the project or other disposition under the FPA, whichever comes first. T.A. Keck III and H.S. Keck; Notice of Authorization for Continued Project Operation Dated: December 5, 2023. Kimberly D. Bose, Secretary. The license for the Blackstone Mill Hydroelectric Project No. 11426 was [FR Doc. 2023–27227 Filed 12–11–23; 8:45 am] Accession Number: 20231205–5135. Comment Date: 5 pm ET 12/26/23. Docket Numbers: ER24–553–000. Applicants: Martin County Solar Project, LLC. Description: Baseline eTariff Filing: Market-Based Rate Application to be effective 2/4/2024. Filed Date: 12/5/23. Accession Number: 20231205–5136. Comment Date: 5 pm ET 12/26/23. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/fercgen search.asp) by querying the docket number. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: December 5, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–27230 Filed 12–11–23; 8:45 am] BILLING CODE 6717–01–P ddrumheller on DSK120RN23PROD with NOTICES1 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission VerDate Sep<11>2014 18:03 Dec 11, 2023 Jkt 262001 BILLING CODE 6717–01–P PO 00000 Frm 00025 Fmt 4703 Sfmt 4703 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER24–373–000] Yellow Pine Solar Interconnect, LLC; Supplemental Notice That Filing Includes Request for Blanket Section 204 Authorization This supplemental notice in the above-referenced proceeding of Yellow Pine Solar Interconnect, LLC’s filing includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is December 26, 2023. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended E:\FR\FM\12DEN1.SGM 12DEN1

Agencies

[Federal Register Volume 88, Number 237 (Tuesday, December 12, 2023)]
[Notices]
[Pages 86127-86128]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-27230]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Combined Notice of Filings #1

    Take notice that the Commission received the following electric 
corporate filings:

     Docket Numbers: EC24-21-000.
    Applicants: TotalEnergies Flexible Power USA, LLC, TexGen Power, 
LLC.
    Description: Joint Application for Authorization Under Section 203 
of the Federal Power Act of TotalEnergies Flexible Power USA, LLC, et. 
al.
    Filed Date: 12/4/23.
    Accession Number: 20231204-5280.
    Comment Date: 5 p.m. ET 12/26/23.

    Take notice that the Commission received the following electric 
rate filings:

     Docket Numbers: ER24-86-000.
    Applicants: EFS Parlin Holdings, LLC.
    Description: Supplement to October 12, 2023 EFS Parlin Holdings, 
LLC tariff filing.
    Filed Date: 11/30/23.
    Accession Number: 20231130-5353.
    Comment Date: 5 p.m. ET 12/21/23.

    Docket Numbers: ER24-228-002.
    Applicants: South Cheyenne Solar, LLC.
    Description: Tariff Amendment: Revision of Proposed Market-Based 
Rate Tariff to be effective 12/1/2023.
    Filed Date: 12/1/23.
    Accession Number: 20231201-5248.
    Comment Date: 5 pm ET 12/11/23.

    Docket Numbers: ER24-537-000.
    Applicants: Southwestern Public Service Company
    Description: Petition for Limited Waiver of Southwestern Public 
Service Company.
    Filed Date: 12/4/23.
    Accession Number: 20231204-5142.
    Comment Date: 5 pm ET 12/18/23.

    Docket Numbers: ER24-543-000.
    Applicants: PJM Interconnection, L.L.C.
    Description: Sec.  205(d) Rate Filing: Amendment to 10 Service 
Agreements re: FirstEnergy Reorganization to be effective 12/31/9998.
    Filed Date: 12/4/23.
    Accession Number: 20231204-5212.
    Comment Date: 5 pm ET 12/26/23.

    Docket Numbers: ER24-544-000.
    Applicants: Robin Hollow Solar Lessee, LLC.
    Description: Tariff Amendment: Notice of MBR Cancellation to be 
effective 12/5/2023.
    Filed Date: 12/4/23.
    Accession Number: 20231204-5223.
    Comment Date: 5 pm ET 12/26/23.

    Docket Numbers: ER24-545-000.
    Applicants: American Electric Power Service Corporation, 
Appalachian Power Company.
    Description: Petition for Limited Waiver of Appalachian Power 
Company.
    Filed Date: 12/4/23.
    Accession Number: 20231204-5283.
    Comment Date: 5 pm ET 12/26/23.

    Docket Numbers: ER24-546-000.
    Applicants: Virginia Electric and Power Company, PJM 
Interconnection, L.L.C.
    Description: Sec.  205(d) Rate Filing: Virginia Electric and Power 
Company submits tariff filing per 35.13(a)(2)(iii: VEPCO submits One 
WDSA, SA No. 7136 to be effective 11/6/2023.
    Filed Date: 12/5/23.
    Accession Number: 20231205-5045.
    Comment Date: 5 pm ET 12/26/23.

    Docket Numbers: ER24-547-000.
    Applicants: Southwest Power Pool, Inc.
    Description: Sec.  205(d) Rate Filing: Revisions to Modify 
Operating Tolerances for Uninstructued Resource Deviation to be 
effective 12/31/9998.
    Filed Date: 12/5/23.
    Accession Number: 20231205-5071.
    Comment Date: 5 pm ET 12/26/23.

    Docket Numbers: ER24-548-000.
    Applicants: Dow Hydrocarbons and Resources LLC.
    Description: Baseline eTariff Filing: Petition for Approval of 
Initial Market-Based Rate Tariff to be effective 2/4/2024.
    Filed Date: 12/5/23.
    Accession Number: 20231205-5078.
    Comment Date: 5 pm ET 12/26/23.

    Docket Numbers: ER24-549-000.
    Applicants: Santa Rosa Energy Center, LLC.
    Description: Sec.  205(d) Rate Filing: Market-Based Rate Tariff 
Revisions to be effective 12/6/2023.
    Filed Date: 12/5/23.
    Accession Number: 20231205-5102.
    Comment Date: 5 pm ET 12/26/23.

    Docket Numbers: ER24-550-000.
    Applicants: Arizona Public Service Company.
    Description: Sec.  205(d) Rate Filing: Rate Schedule No. 292, 
Amendment No. 1 to be effective 2/4/2024.
    Filed Date: 12/5/23.
    Accession Number: 20231205-5125.
    Comment Date: 5 pm ET 12/26/23.

    Docket Numbers: ER24-551-000.
    Applicants: Elkhart County Solar Project, LLC.
    Description: Baseline eTariff Filing: Market-Based Rate Application 
to be effective 2/4/2024.
    Filed Date: 12/5/23.
    Accession Number: 20231205-5133.
    Comment Date: 5 pm ET 12/26/23.

    Docket Numbers: ER24-552-000.
    Applicants: Martin County II Solar Project, LLC.
    Description: Baseline eTariff Filing: Market-Based Rate Application 
to be effective 2/4/2024.
    Filed Date: 12/5/23.

[[Page 86128]]

    Accession Number: 20231205-5135.
    Comment Date: 5 pm ET 12/26/23.

    Docket Numbers: ER24-553-000.
    Applicants: Martin County Solar Project, LLC.
    Description: Baseline eTariff Filing: Market-Based Rate Application 
to be effective 2/4/2024.
    Filed Date: 12/5/23.
    Accession Number: 20231205-5136.
    Comment Date: 5 pm ET 12/26/23.
    The filings are accessible in the Commission's eLibrary system 
(https://elibrary.ferc.gov/idmws/search/fercgensearch.asp) by querying 
the docket number.
    Any person desiring to intervene, to protest, or to answer a 
complaint in any of the above proceedings must file in accordance with 
Rules 211, 214, or 206 of the Commission's Regulations (18 CFR 385.211, 
385.214, or 385.206) on or before 5 p.m. Eastern time on the specified 
comment date. Protests may be considered, but intervention is necessary 
to become a party to the proceeding.
    eFiling is encouraged. More detailed information relating to filing 
requirements, interventions, protests, service, and qualifying 
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676 
(toll free). For TTY, call (202) 502-8659.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].

    Dated: December 5, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-27230 Filed 12-11-23; 8:45 am]
BILLING CODE 6717-01-P