Transcontinental Gas Pipe Line Company, LLC and Northern Natural Gas Company; Notice of Availability of the Environmental Assessment for the Proposed Pelto Area Abandonment Project, 85282-85283 [2023-26871]

Download as PDF 85282 Federal Register / Vol. 88, No. 234 / Thursday, December 7, 2023 / Notices language for the PD program in section 6122 of the ESSA. It is a competitive discretionary grant program. The grant application submitted for this program is evaluated on the basis of how well an applicant addresses the selection criteria, and is used to determine applicant eligibility and amount of award for projects selected for funding. This collection is being submitted under the Streamlined Clearance Process for Discretionary Grant Information Collections (1894–0001). Therefore, the 30-day public comment period notice will be the only public comment notice published for this information collection. Dated: December 4, 2023. Kun Mullan, PRA Coordinator, Strategic Collections and Clearance, Governance and Strategy Division, Office of Chief Data Officer, Office of Planning, Evaluation and Policy Development. [FR Doc. 2023–26875 Filed 12–6–23; 8:45 am] BILLING CODE 4000–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP23–200–000] ddrumheller on DSK120RN23PROD with NOTICES1 Transcontinental Gas Pipe Line Company, LLC and Northern Natural Gas Company; Notice of Availability of the Environmental Assessment for the Proposed Pelto Area Abandonment Project The staff of the Federal Energy Regulatory Commission (FERC or Commission) has prepared an environmental assessment (EA) for the Pelto Area Abandonment Project (Project), in Louisiana state waters offshore of Terrebonne Parish and within the Pelto and Ship Shoal Blocks of Federal offshore waters. Transcontinental Gas Pipe Line Company, LLC (Transco) and Northern Natural Gas Company (Northern) propose to abandon six pipeline segments with different ownership interests that account for a total of about 32.1 miles of natural gas pipelines. The EA assesses the potential environmental effects of the Project in accordance with the requirements of the National Environmental Policy Act (NEPA). The FERC staff concludes that approval of the Project, with appropriate mitigating measures, would not constitute a major Federal action significantly affecting the quality of the human environment. The Commission mailed a copy of the Notice of Availability of the EA to VerDate Sep<11>2014 20:23 Dec 06, 2023 Jkt 262001 Federal, State, and local government representatives and agencies; elected officials; non-governmental organizations, environmental and public interest groups; and newspapers and libraries in the project area. The EA is only available in electronic format. It may be viewed and downloaded from the FERC’s website (www.ferc.gov), on the natural gas environmental documents page (https://www.ferc.gov/ industries-data/natural-gas/ environment/environmentaldocuments). In addition, the EA may be accessed by using the eLibrary link on the FERC’s website. Click on the eLibrary link (https://elibrary.ferc.gov/ eLibrary/search), select ‘‘General Search’’ and enter the docket number in the ‘‘Docket Number’’ field, (i.e. CP23– 200). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The EA is not a decision document. It presents Commission staff’s independent analysis of the environmental issues for the Commission to consider when addressing the merits of all issues in this proceeding. Any person wishing to comment on the EA may do so. Your comments should focus on the EA’s disclosure and discussion of potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure consideration of your comments on the proposal, it is important that the Commission receive your comments on or before 5:00 p.m. Eastern Time on January 2, 2024. For your convenience, there are three methods you can use to submit your comments to the Commission. The Commission encourages electronic filing of comments and has staff available to assist you at (866) 208–3676 or FercOnlineSupport@ferc.gov. Please carefully follow these instructions so that your comments are properly recorded. (1) You can file your comments electronically using the eComment feature on the Commission’s website (www.ferc.gov) under the link to FERC Online. This is an easy method for submitting brief, text-only comments on a project; (2) You can also file your comments electronically using the eFiling feature on the Commission’s website (www.ferc.gov) under the link to FERC Online. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your PO 00000 Frm 00079 Fmt 4703 Sfmt 4703 submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You must select the type of filing you are making. If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the Commission. Be sure to reference the Project docket number (CP23–200–000) on your letter. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. Filing environmental comments will not give you intervenor status, but you do not need intervenor status to have your comments considered. Only intervenors have the right to seek rehearing or judicial review of the Commission’s decision. At this point in this proceeding, the timeframe for filing timely intervention requests has expired. Any person seeking to become a party to the proceeding must file a motion to intervene out-of-time pursuant to Rule 214(b)(3) and (d) of the Commission’s Rules of Practice and Procedures (18 CFR 385.214(b)(3) and (d)) and show good cause why the time limitation should be waived. Motions to intervene are more fully described at https://www.ferc.gov/how-intervene. Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC website (www.ferc.gov) using the eLibrary link. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific E:\FR\FM\07DEN1.SGM 07DEN1 Federal Register / Vol. 88, No. 234 / Thursday, December 7, 2023 / Notices dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to https://www.ferc.gov/ ferc-online/overview to register for eSubscription. Dated: December 1, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–26871 Filed 12–6–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission ddrumheller on DSK120RN23PROD with NOTICES1 Combined Notice of Filings #1 Take notice that the Commission received the following exempt wholesale generator filings: Docket Numbers: EG24–47–000. Applicants: Elkhart County Solar Project LLC. Description: Elkhart County Solar Project LLC submits Notice of SelfCertification of Exempt Wholesale Generator Status. Filed Date: 12/1/23. Accession Number: 20231201–5295. Comment Date: 5 p.m. ET 12/22/23. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER22–910–004. Applicants: Rockland Electric Company PJM Interconnection L.L.C. Description: Compliance filing: Rockland Electric Company submits tariff filing per 35: RECO Compliance Filing in ER22–910 to be effective 1/1/ 2024. Filed Date: 12/1/23. Accession Number: 20231201–5230. Comment Date: 5 p.m. ET 12/22/23. Docket Numbers: ER23–2820–001. Applicants: Alabama Power Company Georgia Power Company Mississippi Power Company. Description: Tariff Amendment: Alabama Power Company submits tariff filing per 35.17(b): Laurens Solar I LGIA Deficiency Response Filing to be effective 9/6/2023. Filed Date: 12/1/23. Accession Number: 20231201–5229. Comment Date: 5 p.m. ET 12/22/23. Docket Numbers: ER24–228–002. Applicants: South Cheyenne Solar LLC. Description: Tariff Amendment: Revision of Proposed Market-Based Rate Tariff to be effective 12/1/2023. Filed Date: 12/1/23. VerDate Sep<11>2014 20:23 Dec 06, 2023 Jkt 262001 Accession Number: 20231201–5248. Comment Date: 5 p.m. ET 12/22/23. Docket Numbers: ER24–509–000. Applicants: Pacific Gas and Electric Company. Description: § 205(d) Rate Filing: November 2023 Western WDT Service Agreement Biannual Filing (SA 17) to be effective 2/1/2024. Filed Date: 11/30/23. Accession Number: 20231130–5254. Comment Date: 5 p.m. ET 12/21/23. Docket Numbers: ER24–510–000. Applicants: Pacific Gas and Electric Company. Description: § 205(d) Rate Filing: November 2023 Western Interconnection Biannual Filing (SA 59) to be effective 2/1/2024. Filed Date: 11/30/23. Accession Number: 20231130–5260. Comment Date: 5 p.m. ET 12/21/23. Docket Numbers: ER24–511–000. Applicants: Duke Energy Florida LLC. Description: § 205(d) Rate Filing: DEF–SECI Reimbursement Agmt RS No. 357 to be effective 1/30/2024. Filed Date: 11/30/23. Accession Number: 20231130–5268. Comment Date: 5 p.m. ET 12/21/23. Docket Numbers: ER24–512–000. Applicants: New England Power Pool Participants Committee. Description: § 205(d) Rate Filing: Dec 2023 Membership Filing to be effective 12/1/2023. Filed Date: 11/30/23. Accession Number: 20231130–5280. Comment Date: 5 p.m. ET 12/21/23. Docket Numbers: ER24–513–000. Applicants: Idaho Power Company. Description: § 205(d) Rate Filing: Revisions to Attachment C to be effective 2/1/2024. Filed Date: 12/1/23. Accession Number: 20231201–5000. Comment Date: 5 p.m. ET 12/22/23. Docket Numbers: ER24–513–001. Applicants: Idaho Power Company. Description: Tariff Amendment: Errata to Revisions to Attachment C to be effective 2/1/2024. Filed Date: 12/1/23. Accession Number: 20231201–5292. Comment Date: 5 p.m. ET 12/22/23. Docket Numbers: ER24–515–000. Applicants: Midcontinent Independent System Operator Inc. American Transmission Company LLC. Description: § 205(d) Rate Filing: Midcontinent Independent System Operator Inc. submits tariff filing per 35.13(a)(2)(iii): 2023–12–01_SA 4200– 4205 ATC–WEPCo PCAs (SW WI ED Area) to be effective 1/31/2024. Filed Date: 12/1/23. Accession Number: 20231201–5022. PO 00000 Frm 00080 Fmt 4703 Sfmt 4703 85283 Comment Date: 5 p.m. ET 12/22/23. Docket Numbers: ER24–516–000. Applicants: Midcontinent Independent System Operator Inc. Description: § 205(d) Rate Filing: 2023–12–01_SA 6522 MISO-Manitowoc Public Utilities Second SSR Agrmt Lakefront 9 to be effective 2/1/2024. Filed Date: 12/1/23. Accession Number: 20231201–5156. Comment Date: 5 p.m. ET 12/22/23. Docket Numbers: ER24–517–000. Applicants: Duke Energy Florida LLC. Description: § 205(d) Rate Filing: DEF–SECI Reimbursement Agmt (Gilchrist) RS No. 356 to be effective 1/ 31/2024. Filed Date: 12/1/23. Accession Number: 20231201–5177. Comment Date: 5 p.m. ET 12/22/23. Docket Numbers: ER24–518–000. Applicants: Duke Energy Florida LLC. Description: § 205(d) Rate Filing: DEF–SECI Reimbursement Agmt (Columbia) RS No. 355 to be effective 1/ 31/2024. Filed Date: 12/1/23. Accession Number: 20231201–5193. Comment Date: 5 p.m. ET 12/22/23. Docket Numbers: ER24–519–000. Applicants: Morongo Transmission LLC. Description: § 205(d) Rate Filing: Annual Operating Cost Update Filing 2024 to be effective 1/1/2024. Filed Date: 12/1/23. Accession Number: 20231201–5199. Comment Date: 5 p.m. ET 12/22/23. Docket Numbers: ER24–520–000. Applicants: Morongo Transmission LLC. Description: § 205(d) Rate Filing: Annual TRBAA Filing 2024 to be effective 1/1/2024. Filed Date: 12/1/23. Accession Number: 20231201–5205. Comment Date: 5 p.m. ET 12/22/23. Docket Numbers: ER24–521–000. Applicants: Duke Energy Florida LLC. Description: § 205(d) Rate Filing: DEFShady Hills Amended and Restated LGIA to be effective 11/14/2023. Filed Date: 12/1/23. Accession Number: 20231201–5215. Comment Date: 5 p.m. ET 12/22/23. Docket Numbers: ER24–522–000. Applicants: Alabama Power Company Georgia Power Company Mississippi Power Company. Description: § 205(d) Rate Filing: Alabama Power Company submits tariff filing per 35.13(a)(2)(iii): Amendment of Americus Solar & Battery Amended and Restated LGIA to be effective 11/20/ 2023. Filed Date: 12/1/23. Accession Number: 20231201–5225. E:\FR\FM\07DEN1.SGM 07DEN1

Agencies

[Federal Register Volume 88, Number 234 (Thursday, December 7, 2023)]
[Notices]
[Pages 85282-85283]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-26871]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP23-200-000]


Transcontinental Gas Pipe Line Company, LLC and Northern Natural 
Gas Company; Notice of Availability of the Environmental Assessment for 
the Proposed Pelto Area Abandonment Project

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) has prepared an environmental assessment (EA) for the Pelto 
Area Abandonment Project (Project), in Louisiana state waters offshore 
of Terrebonne Parish and within the Pelto and Ship Shoal Blocks of 
Federal offshore waters. Transcontinental Gas Pipe Line Company, LLC 
(Transco) and Northern Natural Gas Company (Northern) propose to 
abandon six pipeline segments with different ownership interests that 
account for a total of about 32.1 miles of natural gas pipelines.
    The EA assesses the potential environmental effects of the Project 
in accordance with the requirements of the National Environmental 
Policy Act (NEPA). The FERC staff concludes that approval of the 
Project, with appropriate mitigating measures, would not constitute a 
major Federal action significantly affecting the quality of the human 
environment.
    The Commission mailed a copy of the Notice of Availability of the 
EA to Federal, State, and local government representatives and 
agencies; elected officials; non-governmental organizations, 
environmental and public interest groups; and newspapers and libraries 
in the project area. The EA is only available in electronic format. It 
may be viewed and downloaded from the FERC's website (www.ferc.gov), on 
the natural gas environmental documents page (https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents). In 
addition, the EA may be accessed by using the eLibrary link on the 
FERC's website. Click on the eLibrary link (https://elibrary.ferc.gov/eLibrary/search), select ``General Search'' and enter the docket number 
in the ``Docket Number'' field, (i.e. CP23-200). Be sure you have 
selected an appropriate date range. For assistance, please contact FERC 
Online Support at [email protected] or toll free at (866) 208-
3676, or for TTY, contact (202) 502-8659.
    The EA is not a decision document. It presents Commission staff's 
independent analysis of the environmental issues for the Commission to 
consider when addressing the merits of all issues in this proceeding. 
Any person wishing to comment on the EA may do so. Your comments should 
focus on the EA's disclosure and discussion of potential environmental 
effects, reasonable alternatives, and measures to avoid or lessen 
environmental impacts. The more specific your comments, the more useful 
they will be. To ensure consideration of your comments on the proposal, 
it is important that the Commission receive your comments on or before 
5:00 p.m. Eastern Time on January 2, 2024.
    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected]. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's website (www.ferc.gov) under the link to 
FERC Online. This is an easy method for submitting brief, text-only 
comments on a project;
    (2) You can also file your comments electronically using the 
eFiling feature on the Commission's website (www.ferc.gov) under the 
link to FERC Online. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the Commission. Be sure to reference the Project docket number (CP23-
200-000) on your letter. Submissions sent via the U.S. Postal Service 
must be addressed to: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 
20426. Submissions sent via any other carrier must be addressed to: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 
12225 Wilkins Avenue, Rockville, Maryland 20852.
    Filing environmental comments will not give you intervenor status, 
but you do not need intervenor status to have your comments considered. 
Only intervenors have the right to seek rehearing or judicial review of 
the Commission's decision. At this point in this proceeding, the 
timeframe for filing timely intervention requests has expired. Any 
person seeking to become a party to the proceeding must file a motion 
to intervene out-of-time pursuant to Rule 214(b)(3) and (d) of the 
Commission's Rules of Practice and Procedures (18 CFR 385.214(b)(3) and 
(d)) and show good cause why the time limitation should be waived. 
Motions to intervene are more fully described at https://www.ferc.gov/how-intervene.
    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC website (www.ferc.gov) using the eLibrary link. The eLibrary link 
also provides access to the texts of all formal documents issued by the 
Commission, such as orders, notices, and rulemakings.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific

[[Page 85283]]

dockets. This can reduce the amount of time you spend researching 
proceedings by automatically providing you with notification of these 
filings, document summaries, and direct links to the documents. Go to 
https://www.ferc.gov/ferc-online/overview to register for 
eSubscription.

    Dated: December 1, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-26871 Filed 12-6-23; 8:45 am]
BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.