Federal Register / Vol. 88, No. 230 / Friday, December 1, 2023 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 1403–068]
Yuba County Water Agency; Notice of
Application Tendered for Filing With
the Commission and Establishing
Procedural Schedule for Licensing and
Deadline for Submission of Final
Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 1403–068.
c. Date Filed: November 14, 2023.
d. Applicant: Yuba County Water
Agency.
e. Name of Project: Narrows
Hydroelectric Project.
f. Location: The existing project is
located on the Yuba River in Nevada
County, California, approximately 23
miles northeast of the City of
Marysville. The project affects 0.55
acres of Federal land managed by the
U.S. Army Corps of Engineers.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Willie
Whittlesey, General Manager, Yuba
County Water Agency, 1220 F Street,
Marysville, CA 95901; Telephone (530)
741–5000 or email WWhittlesey@
yubawater.org.
i. FERC Contact: Rebecca Kipp, (202)
502–8846 or rebecca.kipp@ferc.gov.
j. Cooperating agencies: Federal,
State, local, and Tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item1 below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: January 13, 2024.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, you may submit a
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852. All filings must clearly identify
the project name and docket number on
the first page: Narrows Hydroelectric
Project (P–1403–068).
m. This application is not ready for
environmental analysis at this time.
n. The existing Narrows Hydroelectric
Project consists of the following
facilities: (1) a 1,077-foot-long gunitelined tunnel that connects a U.S. Army
Corps of Engineers tunnel to the project
penstock; (2) a 266-foot-long steel
penstock with a diameter varying
between 7.6 and 8 feet that connects the
project tunnel to the project’s
powerhouse and includes a 277-footlong surge structure; (3) an 82.5-foot by
43.6-foot by 92-foot concrete
powerhouse containing a 48-inchdiameter bypass pipe and a single
Francis turbine with a generating
capacity of 12 megawatts; and (4) a
powerhouse access tram. Yuba County
Water Agency is not proposing any
changes to project facilities or operation.
o. Copies of the application may be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document (P–1403). For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). A copy is also available for
inspection and reproduction at the
address in item (h) above.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
q. Procedural schedule and final
amendments: the application will be
processed according to the following
preliminary schedule. Revisions to the
schedule will be made as appropriate.
lotter on DSK11XQN23PROD with NOTICES1
Milestone
Target date
Issue Deficiency Letter (if necessary) ..............................................................................................................................................
Request Additional Information (if necessary) .................................................................................................................................
Issue Scoping Document 1 for comments .......................................................................................................................................
Issue Acceptance Letter ...................................................................................................................................................................
Request Additional Information (if necessary) .................................................................................................................................
Issue Scoping Document 2 (if necessary) .......................................................................................................................................
Issue Notice of Ready for Environmental Analysis ..........................................................................................................................
VerDate Sep<11>2014
18:47 Nov 30, 2023
Jkt 262001
PO 00000
Frm 00036
Fmt 4703
83931
Sfmt 4703
E:\FR\FM\01DEN1.SGM
01DEN1
January 2024.
January 2024.
March 2024.
April 2024.
May 2024.
June 2024.
June 2024.
83932
Federal Register / Vol. 88, No. 230 / Friday, December 1, 2023 / Notices
r. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: November 27, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–26461 Filed 11–30–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 15328–000]
lotter on DSK11XQN23PROD with NOTICES1
SOLIA 1 Hydroelectric LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On October 18, 2023, SOLIA 1
Hydroelectric LLC., filed an application
for a preliminary permit, pursuant to
section 4(f) of the Federal Power Act
(FPA), proposing to study the feasibility
of hydropower project located to be
located at the U.S. Army Corps of
Engineers’ (Corps) A.I. Selden Lock and
Dam near the City of Eutaw, Greene
County, Alabama. The sole purpose of a
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed A.I. Selden
Hydroelectric Project would consist of
the following: (1) a headrace channel
and intake structure with four, 31-footwide, 39-foot-high trash racks with 8.3inch bar spacing; (2) a 93-foot-long, 158foot-wide, 83-foot-high concrete
powerhouse located on the south west
bank of the river at the existing Corps
dam’s right abutment containing four
Kaplan bulb turbine-generator units
with a total capacity of 22.4 megawatts;
(3) four, 70-foot-long, 198-foot-wide, 73foot-high draft tubes that would convey
water from the turbines to the tailrace;
(4) a 495-foot-long, 495-foot-wide riprap
lined tailrace; (5) a 100-foot-long, 100foot-wide switchyard; and (6) a 2.2mile-long, 115 kilovolt transmission
line. The proposed project would have
an estimated annual generation of 145.5
megawatt-hours.
Applicant Contact: Douglas
Spaulding, Nelson Energy, 1030 Tyrol
VerDate Sep<11>2014
18:47 Nov 30, 2023
Jkt 262001
Trail, Suite 101, Minneapolis, MN
55416; phone: (612) 599–8493.
FERC Contact: Michael Spencer;
phone: (202) 502–6093, or by email at
michael.spencer@ferc.gov.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
ferconline.ferc.gov/eFiling.aspx.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://ferconline.ferc.gov/
QuickComment.aspx. You must include
your name and contact information at
the end of your comments. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, you may submit a
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852. The first page of any filing
should include docket number
P–15328–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of the Commission’s website at
https://elibrary.ferc.gov/eLibrary/search.
Enter the docket number (P–15328) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Dated: November 24, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–26386 Filed 11–30–23; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00037
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP24–17–000]
Columbia Gas Transmission, LLC;
Notice of Request Under Blanket
Authorization and Establishing
Intervention and Protest Deadline
Take notice that on November 16,
2023, Columbia Gas Transmission, LLC
(Columbia), 700 Louisiana Street, Suite
1300, Houston, Texas 77002–2700, filed
in the above referenced docket, a prior
notice request pursuant to sections
157.205, 157.208, and 157.216 of the
Commission’s regulations under the
Natural Gas Act (NGA), and Columbia’s
blanket certificate issued in Docket No.
CP83–76–000, for authorization to
modify the existing Line D322 pipeline
at various locations, including the
installation of two bi-directional
launching and receiving stations for inline inspection devices, and abandoning
approximately 8 miles of its 12-inch
diameter Line D322. All of the above
facilities are located in Morrow, Marion,
Hardin, and Allen Counties, Ohio (Line
D322 West ILI Project). The project will
allow Columbia to perform installations
and activities to enable bi-directional inline inspection, or pigging, as well as
abandon a section of its Line D322. The
estimated cost for the project is 28.7
million, all as more fully set forth in the
request which is on file with the
Commission and open to public
inspection.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page
(www.ferc.gov) using the ‘‘eLibrary’’
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document. At
this time, the Commission has
suspended access to the Commission’s
Public Reference Room. For assistance,
contact the Federal Energy Regulatory
Commission at FercOnlineSupport@
ferc.gov or call toll-free, (886) 208–3676
or TTY (202) 502–8659.
Any questions concerning this request
should be directed to David A. Alonzo,
Manager, Project Authorizations,
Columbia Gas Transmission, LLC, 700
Louisiana Street, Suite 1300, Houston,
Texas 77002–2700, at (832) 320–5477 or
david_alonzo@tcenergy.com.
E:\FR\FM\01DEN1.SGM
01DEN1
Agencies
[Federal Register Volume 88, Number 230 (Friday, December 1, 2023)]
[Notices]
[Pages 83931-83932]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-26461]
[[Page 83931]]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 1403-068]
Yuba County Water Agency; Notice of Application Tendered for
Filing With the Commission and Establishing Procedural Schedule for
Licensing and Deadline for Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 1403-068.
c. Date Filed: November 14, 2023.
d. Applicant: Yuba County Water Agency.
e. Name of Project: Narrows Hydroelectric Project.
f. Location: The existing project is located on the Yuba River in
Nevada County, California, approximately 23 miles northeast of the City
of Marysville. The project affects 0.55 acres of Federal land managed
by the U.S. Army Corps of Engineers.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Willie Whittlesey, General Manager, Yuba
County Water Agency, 1220 F Street, Marysville, CA 95901; Telephone
(530) 741-5000 or email [email protected].
i. FERC Contact: Rebecca Kipp, (202) 502-8846 or
[email protected].
j. Cooperating agencies: Federal, State, local, and Tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item1 below. Cooperating agencies should note the
Commission's policy that agencies that cooperate in the preparation of
the environmental document cannot also intervene. See, 94 FERC ] 61,076
(2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: January 13, 2024.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support
at [email protected], (866) 208-3676 (toll free), or (202)
502-8659 (TTY). In lieu of electronic filing, you may submit a paper
copy. Submissions sent via the U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission,
888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent
via any other carrier must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. All filings must clearly identify the
project name and docket number on the first page: Narrows Hydroelectric
Project (P-1403-068).
m. This application is not ready for environmental analysis at this
time.
n. The existing Narrows Hydroelectric Project consists of the
following facilities: (1) a 1,077-foot-long gunite-lined tunnel that
connects a U.S. Army Corps of Engineers tunnel to the project penstock;
(2) a 266-foot-long steel penstock with a diameter varying between 7.6
and 8 feet that connects the project tunnel to the project's powerhouse
and includes a 277-foot-long surge structure; (3) an 82.5-foot by 43.6-
foot by 92-foot concrete powerhouse containing a 48-inch-diameter
bypass pipe and a single Francis turbine with a generating capacity of
12 megawatts; and (4) a powerhouse access tram. Yuba County Water
Agency is not proposing any changes to project facilities or operation.
o. Copies of the application may be viewed on the Commission's
website at https://www.ferc.gov using the ``eLibrary'' link. Enter the
docket number excluding the last three digits in the docket number
field to access the document (P-1403). For assistance, please contact
FERC Online Support at [email protected], (866) 208-3676 (toll
free), or (202) 502-8659 (TTY). A copy is also available for inspection
and reproduction at the address in item (h) above.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
q. Procedural schedule and final amendments: the application will
be processed according to the following preliminary schedule. Revisions
to the schedule will be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Issue Deficiency Letter (if necessary). January 2024.
Request Additional Information (if January 2024.
necessary).
Issue Scoping Document 1 for comments.. March 2024.
Issue Acceptance Letter................ April 2024.
Request Additional Information (if May 2024.
necessary).
Issue Scoping Document 2 (if necessary) June 2024.
Issue Notice of Ready for Environmental June 2024.
Analysis.
------------------------------------------------------------------------
[[Page 83932]]
r. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: November 27, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-26461 Filed 11-30-23; 8:45 am]