Alice Falls Hydro, LLC; Notice of Authorization for Continued Project Operation, 82345 [2023-25966]
Download as PDF
ddrumheller on DSK120RN23PROD with NOTICES1
Federal Register / Vol. 88, No. 225 / Friday, November 24, 2023 / Notices
turbine-generator units at the Jay
development and increase the
generating capacity from 3.125
Megawatts (MW) to 3.745 MW.
l. Locations of the Application: This
filing may be viewed on the
Commission’s website at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. You may
also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. Agencies may
obtain copies of the application directly
from the applicant.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214,
respectively. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
o. Filing and Service of Documents:
Any filing must (1) bear in all capital
letters the title ‘‘COMMENTS’’,
‘‘PROTEST’’, or ‘‘MOTION TO
INTERVENE’’ as applicable; (2) set forth
in the heading the name of the applicant
and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
commenting, protesting or intervening;
and (4) otherwise comply with the
requirements of 18 CFR 385.2001
through 385.2005. All comments,
motions to intervene, or protests must
set forth their evidentiary basis. Any
filing made by an intervenor must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
385.2010.
p. The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
VerDate Sep<11>2014
21:46 Nov 22, 2023
Jkt 262001
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Dated: November 17, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–25974 Filed 11–22–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 5867–000]
Alice Falls Hydro, LLC; Notice of
Authorization for Continued Project
Operation
The license for the Alice Falls
Hydroelectric Project No. 5867 was
issued for a period ending September
30, 2023.
Section 15(a)(1) of the FPA, 16 U.S.C.
808(a)(1), requires the Commission, at
the expiration of a license term, to issue
from year-to-year an annual license to
the then licensee(s) under the terms and
conditions of the prior license until a
new license is issued, or the project is
otherwise disposed of as provided in
section 15 or any other applicable
section of the FPA. If the project’s prior
license waived the applicability of
section 15 of the FPA, then, based on
section 9(b) of the Administrative
Procedure Act, 5 U.S.C. 558(c), and as
set forth at 18 CFR 16.21(a), if the
licensee of such project has filed an
application for a subsequent license, the
licensee may continue to operate the
project in accordance with the terms
and conditions of the license after the
minor or minor part license expires,
until the Commission acts on its
application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 5867
is issued to Alice Falls Hydro, LLC for
a period effective October 1, 2023,
through September 30, 2024, or until the
issuance of a new license for the project
PO 00000
Frm 00033
Fmt 4703
Sfmt 4703
82345
or other disposition under the FPA,
whichever comes first. If issuance of a
new license (or other disposition) does
not take place on or before September
30, 2024, notice is hereby given that,
pursuant to 18 CFR 16.18(c), an annual
license under section 15(a)(1) of the
FPA is renewed automatically without
further order or notice by the
Commission, unless the Commission
orders otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that Alice Falls Hydro, LLC is
authorized to continue operation of the
Alice Falls Hydroelectric Project under
the terms and conditions of the prior
license until the issuance of a
subsequent license for the project or
other disposition under the FPA,
whichever comes first.
Dated: November 17, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–25966 Filed 11–22–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 10661–000]
Indiana Michigan Power Company;
Notice of Authorization for Continued
Project Operation
The license for the Constantine
Hydroelectric Project No. 10661 was
issued for a period ending September
30, 2023.
Section 15(a)(1) of the FPA, 16 U.S.C.
808(a)(1), requires the Commission, at
the expiration of a license term, to issue
from year-to-year an annual license to
the then licensee(s) under the terms and
conditions of the prior license until a
new license is issued, or the project is
otherwise disposed of as provided in
section 15 or any other applicable
section of the FPA. If the project’s prior
license waived the applicability of
section 15 of the FPA, then, based on
section 9(b) of the Administrative
Procedure Act, 5 U.S.C. 558(c), and as
set forth at 18 CFR 16.21(a), if the
licensee of such project has filed an
application for a subsequent license, the
licensee may continue to operate the
project in accordance with the terms
and conditions of the license after the
minor or minor part license expires,
until the Commission acts on its
application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
E:\FR\FM\24NON1.SGM
24NON1
Agencies
[Federal Register Volume 88, Number 225 (Friday, November 24, 2023)]
[Notices]
[Page 82345]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-25966]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 5867-000]
Alice Falls Hydro, LLC; Notice of Authorization for Continued
Project Operation
The license for the Alice Falls Hydroelectric Project No. 5867 was
issued for a period ending September 30, 2023.
Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the
Commission, at the expiration of a license term, to issue from year-to-
year an annual license to the then licensee(s) under the terms and
conditions of the prior license until a new license is issued, or the
project is otherwise disposed of as provided in section 15 or any other
applicable section of the FPA. If the project's prior license waived
the applicability of section 15 of the FPA, then, based on section 9(b)
of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth
at 18 CFR 16.21(a), if the licensee of such project has filed an
application for a subsequent license, the licensee may continue to
operate the project in accordance with the terms and conditions of the
license after the minor or minor part license expires, until the
Commission acts on its application. If the licensee of such a project
has not filed an application for a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b), to continue project operations
until the Commission issues someone else a license for the project or
otherwise orders disposition of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 5867 is issued to
Alice Falls Hydro, LLC for a period effective October 1, 2023, through
September 30, 2024, or until the issuance of a new license for the
project or other disposition under the FPA, whichever comes first. If
issuance of a new license (or other disposition) does not take place on
or before September 30, 2024, notice is hereby given that, pursuant to
18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is
renewed automatically without further order or notice by the
Commission, unless the Commission orders otherwise.
If the project is not subject to section 15 of the FPA, notice is
hereby given that Alice Falls Hydro, LLC is authorized to continue
operation of the Alice Falls Hydroelectric Project under the terms and
conditions of the prior license until the issuance of a subsequent
license for the project or other disposition under the FPA, whichever
comes first.
Dated: November 17, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-25966 Filed 11-22-23; 8:45 am]
BILLING CODE 6717-01-P