EPA Determinations of Compliance and Applicability Under CAA 111, 112, and 129 Dashboard: EPA Formal Responses to Inquiries Concerning Compliance With the Clean Air Act Stationary Source Program (Since May 2019), 82350-82355 [2023-25950]

Download as PDF 82350 Federal Register / Vol. 88, No. 225 / Friday, November 24, 2023 / Notices Accession Number: 20231116–5129. Comment Date: 5 p.m. ET 11/28/23. Any person desiring to protest in any the above proceedings must file in accordance with Rule 211 of the Commission’s Regulations (18 CFR 385.211) on or before 5:00 p.m. Eastern time on the specified comment date. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: November 17, 2023. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2023–25965 Filed 11–22–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 6951–000] ddrumheller on DSK120RN23PROD with NOTICES1 Tallassee Shoals, LLC; Notice of Authorization for Continued Project Operation 21:46 Nov 22, 2023 Jkt 262001 Filed November 13, 2023 10 a.m. EST Through November 17, 2023 10 a.m. EST Pursuant to 40 CFR 1506.9. Notice Section 309(a) of the Clean Air Act requires that EPA make public its comments on EISs issued by other Federal agencies. EPA’s comment letters on EISs are available at: https:// cdxapps.epa.gov/cdx-enepa-II/public/ action/eis/search. EIS No. 20230162, Final, USAF, FL, KC– 46A Main Operating Base No. 6 Beddown, Review Period Ends: 12/ 26/2023, Contact: Austin Naranjo 813–263–9331. EIS No. 20230163, Draft Supplement, USACE, HI, Draft General Reevaluation Report with Integrated Supplemental Environmental Impact Statement: Ala Wai Canal Flood Risk Management Study, Oahu, Hawaii, Comment Period Ends: 01/08/2024, Contact: Eric Merriam 412–395–7185. Dated: November 17, 2023. Julie Smith, Acting Director, NEPA Compliance Division, Office of Federal Activities. [FR Doc. 2023–25936 Filed 11–22–23; 8:45 am] BILLING CODE 6560–50–P ENVIRONMENTAL PROTECTION AGENCY [EPA–HQ–OAR–2023–0194; FRL–11557–01– OAR] EPA Determinations of Compliance and Applicability Under CAA 111, 112, and 129 Dashboard: EPA Formal Responses to Inquiries Concerning Compliance With the Clean Air Act Stationary Source Program (Since May 2019) Environmental Protection Agency (EPA). ACTION: Notice of availability. Dated: November 17, 2023. Debbie-Anne A. Reese, Deputy Secretary. AGENCY: [FR Doc. 2023–25972 Filed 11–22–23; 8:45 am] SUMMARY: BILLING CODE 6717–01–P The license for the Tallassee Shoals Hydroelectric Project No. 6951 was issued for a period ending September 30, 2023. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the Commission, at the expiration of a license term, to issue from year-to-year an annual license to the then licensee(s) under the terms and conditions of the prior license until a new license is issued, or the project is otherwise disposed of as provided in section 15 or any other applicable section of the FPA. If the project’s prior license waived the applicability of VerDate Sep<11>2014 section 15 of the FPA, then, based on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth at 18 CFR 16.21(a), if the licensee of such project has filed an application for a subsequent license, the licensee may continue to operate the project in accordance with the terms and conditions of the license after the minor or minor part license expires, until the Commission acts on its application. If the licensee of such a project has not filed an application for a subsequent license, then it may be required, pursuant to 18 CFR 16.21(b), to continue project operations until the Commission issues someone else a license for the project or otherwise orders disposition of the project. If the project is subject to section 15 of the FPA, notice is hereby given that an annual license for Project No. 6951 is issued to Tallassee Shoals, LLC for a period effective October 1, 2023, through September 30, 2024, or until the issuance of a new license for the project or other disposition under the FPA, whichever comes first. If issuance of a new license (or other disposition) does not take place on or before September 30, 2024, notice is hereby given that, pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is renewed automatically without further order or notice by the Commission, unless the Commission orders otherwise. If the project is not subject to section 15 of the FPA, notice is hereby given that Tallassee Shoals, LLC is authorized to continue operation of the Tallassee Shoals Hydroelectric Project under the terms and conditions of the prior license until the issuance of a subsequent license for the project or other disposition under the FPA, whichever comes first. ENVIRONMENTAL PROTECTION AGENCY [FRL OP–OFA–097] Environmental Impact Statements; Notice of Availability Responsible Agency: Office of Federal Activities, General Information 202– 564–5632 or https://www.epa.gov/nepa. Weekly receipt of Environmental Impact Statements (EIS) PO 00000 Frm 00038 Fmt 4703 Sfmt 4703 This notice announces the availability of applicability determinations, alternative monitoring decisions, and regulatory interpretations made by the Environmental Protection Agency (EPA) with regard to the New Source Performance Standards (NSPS); the National Emission Standards for Hazardous Air Pollutants (NESHAP); the Emission Guidelines and Federal Plan Requirements for existing sources; and/or the Stratospheric Ozone Protection Program. FOR FURTHER INFORMATION CONTACT: An electronic copy of each complete document posted on the Clean Air Act 111, 112, and 129 Dashboard, which E:\FR\FM\24NON1.SGM 24NON1 Federal Register / Vol. 88, No. 225 / Friday, November 24, 2023 / Notices contains determinations signed after May 2019, is available on the internet through the Resources and Guidance Documents for Compliance Assistance page of the Clean Air Act Compliance Monitoring website under ‘‘Air’’ at: https://www.epa.gov/complying-airemissions-standards-stationary-sources/ epa-determinations-compliance-and. All previously issued responses are posted on the Applicability Determination Index (ADI) data system available on the internet through the Resources and Guidance Documents for Compliance Assistance page of the Clean Air Act Compliance Monitoring website under ‘‘Air’’ at: https:// www.epa.gov/compliance/resourcesand-guidance-documents-complianceassistance. The letters and memoranda on the Clean Air Act 111, 112, and 129 Dashboard may be located by facility name, affected subpart, or by response date and is searchable by string word searches. For questions about the Clean Air Act 111, 112, and 129 Dashboard or this notice, contact Diana Felix, Air Quality Policy Division, Operating Permits Group; telephone number: (919) 541–7627; email address: felix.diana@ epa.gov. SUPPLEMENTARY INFORMATION: General Information The General Provisions of the NSPS in 40 Code of Federal Regulations (CFR) part 60 and the General Provisions of the NESHAP in 40 CFR part 61 provide that a source owner or operator may request a determination of whether certain intended actions constitute the commencement of construction, reconstruction, or modification. 40 CFR 60.5 and 61.06. The General Provisions in part 60 also apply to Federal and EPA-approved state plans for existing sources in 40 CFR part 62. See 40 CFR 62.02(b)(2). The EPA’s written responses to source or facility-specific inquiries on provisions in parts 60, 61 and 62 are commonly referred to as applicability determinations. Although the NESHAP part 63 regulations [which include Maximum Achievable Control Technology (MACT) standards and/or Generally Available Control Technology (GACT) standards] contain no specific regulatory provision providing that sources may request applicability determinations, the EPA also responds to written inquiries regarding applicability for the part 63 regulations. In addition, the General Provisions in parts 60 and 63 allow sources to seek permission to use monitoring or recordkeeping that is different from the promulgated requirements. See 40 CFR 60.13(i), 61.14(g), 63.8(b)(1), 63.8(f), and 63.10(f). The EPA’s written responses to these inquiries are commonly referred to as alternative monitoring decisions. Furthermore, the EPA responds to written inquiries about the broad range of regulatory requirements in 40 CFR parts 60 through 63 as they pertain to 82351 a whole source category. These inquiries may pertain, for example, to the type of sources to which the regulation applies, or to the testing, monitoring, recordkeeping, or reporting requirements contained in the regulation. The EPA’s written responses to these inquiries are commonly referred to as regulatory interpretations. The EPA previously compiled EPAissued NSPS and NESHAP applicability determinations, alternative monitoring decisions, and regulatory interpretations, and posted them to the ADI. As of October 2, 2023, the EPA determinations of compliance and applicability under Clean Air Act 111, 112, and 129 will be posted to the Clean Air Act 111, 112, and 129 Dashboard. The Clean Air Act 111, 112, and 129 Dashboard is a data system, accessed via the internet, containing all determinations signed after May 2019. This notice comprises a list of 173 such documents added to the Clean Air Act 111, 112, and 129 Dashboard on October 2, 2023. This notice lists the title of each letter and memorandum. Complete copies of these documents may be obtained from the Clean Air Act 111, 112 and 129 Dashboard on the internet through the Resources and Guidance Documents for Compliance Assistance page of the Clean Air Act Compliance Monitoring website under ‘‘Air’’ at: https://www.epa.gov/ compliance/resources-and-guidancedocuments-compliance-assistance. APPLICABILITY DETERMINATIONS, ALTERNATIVE MONITORING PLANS AND REGULATORY INTERPRETATIONS UPLOADED TO CLEAN AIR ACT 111, 112, AND 129 DASHBOARD ON OCTOBER 2, 2023 Title Affected subpart East Carolina Regional Solid Waste Landfill ...... Eaton Corporation—Auburn Facility ................... Other Request—Well Decommissioning ............ Applicability Determination for Stationary Combustion Engines. Alternative Monitoring for Stationary Gas Turbines. Alternative Monitoring for Stationary Gas Turbines. Alternative Monitoring for Pulp and Paper Production. Applicability Determination for SOCMI Distillation Operations. Alternative Monitoring for Petroleum Refineries Alternative Monitoring for Stationary Gas Turbines. Other Request—Approval of a continuous monitoring system (CMS) plan petition. Alternative Monitoring for Petroleum Refineries Alternative Monitoring for Phosphate Fertilizer Production Plants. Alternative Test Method for MSWLF .................. Alternative Test Method for Secondary Aluminum Production. Performance Test Extension for Stationary Combustion Turbines. Alternative Monitoring for Lime Manufacturing Plant. Other Request—Request for Operating Limits/ Monitoring Petition. Other Request—Revision to your approved continuous monitoring system (CMS) plan. Part 62, Subpart OOO ....................................... Part 63, Subpart ZZZZ; Part 60, Subpart IIII ..... 2023–09–12 2023–09–07 Part 63, Subpart YYYY ...................................... 2023–08–25 Part 63, Subpart YYYY ...................................... 2023–08–25 Part 63, Subpart S ............................................. 2023–08–10 Part 60, Subpart NNN ........................................ 2023–08–07 Part 60, Subpart J; Part 60, Subpart Ja: ........... Part 63, Subpart YYYY ...................................... 2023–07–27 2023–07–27 Part 63, Subpart YYYY ...................................... 2023–07–25 Part 60, Subpart J; Part 60, Subpart Ja ............ Part 63, Subpart BB ........................................... 2023–07–25 2023–07–21 Part 62, Subpart OOO ....................................... Part 63, Subpart RRR ........................................ 2023–07–14 2023–07–11 Part 60, Subpart KKKK ...................................... 2023–07–10 Part 63, Subpart AAAAA .................................... 2023–06–21 Part 63, Subpart YYYY ...................................... 2023–06–15 Part 63, Subpart YYYY ...................................... 2023–06–12 ANR Pipeline Company—LaGrange Compressor Station. ANR Pipeline Company—Sulpher Springs Compressor Station. International Paper (IP)—Columbus Mill ............ Valero Renewable Fuels ..................................... Diversified Vapor Technologies .......................... Xcel Energy—High Bridge .................................. Tampa Electric Company—Big Bend Station ..... DVT/Multiple R4 Refineries ................................ Mosaic Fertilizer New Whales Facility ................ ddrumheller on DSK120RN23PROD with NOTICES1 Date of response Facility name Maple Hill Landfill ................................................ Owl’s Head Alloys, Inc ........................................ Alyeska TAPS Pump Station #1 ......................... Carmeuse Americas—Longview ......................... University of Michigan—Central Power Plant ..... Entergy Services LLC ......................................... VerDate Sep<11>2014 21:46 Nov 22, 2023 Jkt 262001 PO 00000 Frm 00039 Fmt 4703 Sfmt 4703 E:\FR\FM\24NON1.SGM 24NON1 82352 Federal Register / Vol. 88, No. 225 / Friday, November 24, 2023 / Notices APPLICABILITY DETERMINATIONS, ALTERNATIVE MONITORING PLANS AND REGULATORY INTERPRETATIONS UPLOADED TO CLEAN AIR ACT 111, 112, AND 129 DASHBOARD ON OCTOBER 2, 2023—Continued Title Affected subpart Dominion Energy ................................................ Performance Test Waiver for Coil and Oil-Fired Electric Generating Units. Alternative Monitoring for Miscellaneous Organic Chemical Manufacturing. Applicability Determination for Stationary Reciprocating Combustion Engines. Alternative Test Method for Stationary Gas Turbines. Applicability Determination for Stationary Gas Turbines. Alternative Monitoring for Stationary Gas Turbines. Applicability Determination for HMIWI ............... Alternative Monitoring for MSWL ....................... Applicability Determination for Nine Metal Fabrication and Finishing Source Categories. Alternative Monitoring Procedure for Wastewater Treatment Facility. Other Request—Well Decommissioning ............ Other Request—Well Decommissioning ............ Applicability Determination for Hospital/Medical/ Infectious Waste Incinerators. Other Request—Compliance Option for Plywood and Composite Wood Products. Other Request—Approval of CMS Plan ............ Part 63, Subpart UUUUU ................................... 2023–06–12 Part 63, Subpart FFFF ....................................... 2023–06–07 Part 63, Subpart ZZZZ ....................................... 2023–05–31 Part 63, Subpart YYYY ...................................... 2023–05–23 Part 63, Subpart YYYY ...................................... 2023–05–23 Part 63, Subpart YYYY ...................................... 2023–05–22 Part 60, Subpart Ec ............................................ Part 62, Subpart OOO ....................................... Part 63, Subpart XXXXXX ................................. 2023–05–08 2023–04–24 2023–04–10 Part 60, Subpart MMMM .................................... 2023–03–23 Part 62, Subpart OOO; Part 63, Subpart AAAA Part 62, Subpart OOO; Part 63, Subpart AAAA Part 60, Subpart Ec ............................................ 2023–03–23 2023–03–23 2023–03–23 Part 63, Subpart DDDD ..................................... 2023–03–23 Part 63, Subpart YYYY ...................................... 2023–03–17 Other Request—Approval of CMS Plan ............ Regulatory Interpretation for Stationary Reciprocating Internal Combustion Engines. Alternative Monitoring for Petroleum Refineries Other Request—Approval of CMS Plan ............ Part 63, Subpart YYYY ...................................... Part 63, Subpart ZZZZ ....................................... 2023–03–17 2023–03–17 Part 60, Subpart Ja ............................................ Part 63, Subpart YYYY ...................................... 2023–03–14 2023–03–09 Other Request—Well Decommissioning ............ Performance Test Extension for Stationary Gas Turbines. Alternative Monitoring for MSWL ....................... Applicability Determination for Other Solid Waste Incineration Units. Applicability Determination for Hospital/Medical/ Infectious Waste Incinerators. Other Request—Approval of CMS Plan ............ Part 62, Subpart OOO; Part 63, Subpart AAAA Part 63, Subpart A; Part 63, Subpart YYYY ...... 2023–03–03 2023–02–16 Part 62, Subpart OOO ....................................... Part 60, Subpart EEEE ...................................... 2023–02–08 2023–01–27 Part 60, Subpart Ec ............................................ 2023–01–19 Part 63, Subpart YYYY ...................................... 2023–01–18 Alternative Monitoring for Petroleum Refineries Other Request—Approval of CMS Plan ............ Part 60, Subpart Ja ............................................ Part 63, Subpart YYYY ...................................... 2023–01–13 2023–01–13 Performance Test Waiver for Stationary Combustion Turbine. Alternative Monitoring for Pulp and Paper Production. Performance Test Extension for Stationary Gas Turbine. Regulatory Interpretation for NESAHP MMMM Part 60, Subpart KKKK ...................................... 2023–01–05 Part 63, Subpart S ............................................. 2022–12–19 Part 63, Subpart YYYY ...................................... 2022–12–06 Part 63, Subpart MMMM .................................... 2022–11–30 Alternative Monitoring for Petroleum Refineries Part 63, Subpart CC ........................................... 2022–11–09 Other Request—Well Decommissioning ............ Other Request—Well Decommissioning ............ Applicability Determination for Miscellaneous Coating Manufacturing. Other Request—Petition for Operating Limitations. Alternative Monitoring Plan for Petroleum Refinery. Alternative Monitoring for MSWL ....................... Alternative Monitoring for Hazardous Waste Combustor. Performance Test Waiver for VOC Emissions from SOCMI Distillation Operations. Other Request—Approval of CMS Plan ............ Regulatory Interpretation for Grain Elevators .... Performance Test Waiver for Mercury ............... Other Request—Well Decommissioning ............ Other Request—Approval of CMS Plan ............ Alternative Monitoring Plan for Wastewater Treatment Plant. Alternative Monitoring Procedure for Sewage Sludge Incineration Unit. Applicability Determination for Hospital/Medical/ Infectious Waste Incinerators. Part 62, Subpart OOO; Part 60, Subpart AAAA Part 62, Subpart OOO ....................................... Part 63, Subpart HHHHHH ................................ 2022–10–25 2022–10–25 2022–10–14 Part 63, Subpart YYYY ...................................... 2022–09–21 Part 60, Subpart Ja ............................................ 2022–09–07 Part 62, Subpart OOO ....................................... Part 63, Subpart EEE ......................................... 2022–09–06 2022–08–30 Part 60, Subpart NNN; Part 60, Subpart RRR .. 2022–08–30 Part Part Part Part Part Part YYYY ...................................... DD ........................................... E ............................................. OOO; Part 63, Subpart AAAA YYYY ...................................... MMMM .................................... 2022–08–30 2022–08–17 2022–08–01 2022–07–26 2022–07–26 2022–07–22 Part 60, Subpart MMMM .................................... 2022–07–22 Part 60, Subpart Ec ............................................ 2022–07–14 Advansix Hopewell Virginia ................................ Materion Brush Inc .............................................. XCEL Energy—Riverside Generating Plant ....... Texas Eastern Transmission—Somerset ........... XCEL Energy—High Bridge Combined Cycle .... Safe Dispose, LLC (SD–40) ............................... Uwharrie Environmental Landfill ......................... Buchanan Marine, LP ......................................... City of High Point (Eastside Waste Water Treatment Plant) Revised AMP Resubmittal. East Carolina Regional Landfill .......................... Hanes Mill Road Landfill ..................................... Safe Dispose, LLC (SD–9 & SD–21) ................. Kronospan ........................................................... Duke Energy Florida, LLC, Citrus Combined Cycle Station. Florida Power and Light ...................................... Johns Hopkins All Children’s Hospital ................ CITGO Corpus Christi East Refinery .................. TC Energy (ANR Brownsville Compressor Station, TN). South Wake Landfill ............................................ Petro Nova Parish Holdings-Capture Plant ........ Timber Ridge Landfill, Richwoods, MO .............. Capital Region Airport Authority ......................... Safe Dispose, LLC (SD–27) ............................... Transcontinental Gas Pipe Line Company, LLC (Transco), Compressor Station 85. Valero Refining—St Charles Refinery ................ Transcontinental Gas Pipe Line Company, LLC (Transco) Station 110. Nikaitchuq Development Site .............................. International Paper ORANGE MILL PLANT ....... Consumers Energy Company—Muskegon River Compressor Station. Misc Metal Parts and Products Surface Coating Facilities. ExxonMobil Beaumont Refinery-Flare Vent Gas Composition Monitoring AMP. Hanes Mill Road Landfill ..................................... East Carolina Regional Landfill .......................... Tesla Salt Lake City ............................................ Pratt & Whitney 1 Aircraft Road Middletown, CT 06457. Marathon Petroleum Company Garyville Refinery. East Carolina Regional Solid Waste Landfill ...... Giant Cement ...................................................... Artesia Renewable Diesel Company LLC .......... ddrumheller on DSK120RN23PROD with NOTICES1 Date of response Facility name Choctaw County Generating Plant ..................... Kansas Department of Health and Environment Packaging Corporation of America Filer City Mill East Carolina Regional Solid Waste Landfill ...... Georgia Pacific Wood Products .......................... City of High Point (Eastside Waste Water Treatment Plant). City of Greensboro (T.Z. Osborne Water Reclamation Facility) Revised AMP Submittal. Safe Dispose, LLC .............................................. VerDate Sep<11>2014 21:46 Nov 22, 2023 Jkt 262001 PO 00000 Frm 00040 Fmt 4703 Sfmt 4703 63, 60, 61, 62, 63, 60, Subpart Subpart Subpart Subpart Subpart Subpart E:\FR\FM\24NON1.SGM 24NON1 Federal Register / Vol. 88, No. 225 / Friday, November 24, 2023 / Notices 82353 APPLICABILITY DETERMINATIONS, ALTERNATIVE MONITORING PLANS AND REGULATORY INTERPRETATIONS UPLOADED TO CLEAN AIR ACT 111, 112, AND 129 DASHBOARD ON OCTOBER 2, 2023—Continued Title Affected subpart American Environmental Inc ............................... EGGER ............................................................... Alternative Monitoring for Petroleum Refineries Regulatory Interpretation for Plywood and Composite Wood Products. Performance Test Extension for Secondary Aluminum Production. Applicability Determination for Commercial and Industrial Solid Waste Incineration Units. Alternative Monitoring for Petroleum Refineries Performance Test Extension for Existing Sewage Sludge Incineration Units. Regulatory Interpretation for Stationary Reciprocating Internal Combustion Engines. Alternative Monitoring for MSW Landfill ............. Other Request—Testing Minimum Time Notification Waiver. Alternative Monitoring for Petroleum Refineries Applicability Determination for Crude Oil and Natural Gas Facilities. Regulatory Interpretation for Crude Oil and Natural Gas Facilities. Applicability Determination for Secondary Aluminum Production. Alternative Monitoring for Existing Sewage Sludge Incineration Units. Alternative Monitoring for Kraft Pulp Mills .......... Alternative Monitoring for Asphalt Processing and Asphalt Roofing. Regulatory Interpretation for Municipal Solid Waste Landfills. Alternative Monitoring for Municipal Solid Waste Landfills. Alternative Monitoring for Taconite Iron Ore Processing. Performance Test Waiver for Stationary Spark Ignition Internal Combustion Engines. Alternative Monitoring for Petroleum Refineries Alternative Monitoring for Polyvinyl Chloride and Copolymers Production. Alternative Monitoring for Calciners and Dryers in Mineral Industries. Performance Test Waiver for Lead Acid Batter Manufacturing Area Sources. Regulatory Interpretation for MSW Landfills ...... Part 60, Subpart J; Part 60, Subpart Ja ............ Part 63 Subpart DDDD ...................................... 2022–06–28 2022–06–15 Part 61, Subpart RRR ........................................ 2022–06–07 Part 60, Subpart CCCC ..................................... 2022–05–26 Part 60, Subpart J .............................................. Part 62, Subpart LLL .......................................... 2022–05–23 2022–05–12 Part 63, Subpart ZZZZ ....................................... 2022–04–27 Part 62, Subpart OOO ....................................... Part 63, Subpart YYYY ...................................... 2022–04–20 2022–04–14 Part 60, Subpart Ja ............................................ Part 60, Subpart Db ........................................... 2022–04–11 2022–03–31 Part 60, Subpart OOOO; Part 60, Subpart OOOOa. Part 63, Subpart RRR ........................................ 2022–03–29 2022–03–25 Part 60, Subpart MMMM; Part 62, Subpart LLL 2022–03–15 Part 60, Subpart BB ........................................... Part 63, Subpart LLLLLL .................................... 2022–02–16 2022–02–03 Part 62, Subpart OOO; Part 63, Subpart AAAA 2022–02–03 Part 62, OOO; Part 63, Subpart AAAA .............. 2022–01–07 Part 63, Subpart RRRRR ................................... 2021–12–28 Part 60, Subpart JJJJ ......................................... 2021–12–17 Part 60, Subpart Ja ............................................ Part 63, Subpart HHHHHHH .............................. 2021–12–13 2021–12–06 Part 60, Subpart UUU ........................................ 2021–12–03 Part 60, Subpart KK; Part 63, Subpart PPPPPP 2021–11–29 Part 62, Subpart OOO ....................................... 2021–11–18 Applicability Determination for Nonmetallic Mineral Processing Plants. Applicability Determination for New Sewage Sludge Incineration Units. Alternative Monitoring for Steel Pickling HCl Process Facilities and Hydrochloric Acid Regeneration Plants. Performance Test Waiver for Coal- and OilFired Electric Utility Steam Generating Units. Alternative Monitoring for Phosphate Fertilizers Production Plants. Applicability Determination for Other Solid Waste Incineration Units. Alternative Monitoring for Petroleum Refineries Alternative Monitoring for Pulp and Paper Industry. Applicability Determination for New Sewage Sludge Incineration Units. Alternative Monitoring for Petroleum Refineries Alternative Monitoring for Ethylene Oxide Emissions Standards for Sterilization Facilities. Performance Test Waiver for Commercial and Industrial Solid Waste Incineration Units. Alternative Monitoring for SOCMI Air Oxidation Units and Distillation Operations. Applicability Determination for Stationary Compression Ignition Internal Combustion Engines. Alternative Monitoring for Petroleum Refineries Regulatory Interpretation for Municipal Solid Waste Landfills. Alternative Monitoring for Equipment Leaks of VOC in the Synthetic Organic Chemicals Manufacturing Industry. Alternative Monitoring for Petroleum Refineries Part 60, Subpart OOO ....................................... 2021–11–09 Part 60, Subpart LLLL ........................................ 2021–10–28 Part 63, Subpart CCC ........................................ 2021–10–21 Part 63, Subpart UUUUU ................................... 2021–10–21 Part 63, Subpart BB ........................................... 2021–10–14 Part 60, Subpart EEEE ...................................... 2021–09–30 Part 60, Subpart J; Part 60 Subpart Ja ............. Part 63, Subpart S ............................................. 2021–09–30 2021–09–29 Part 60, Subpart LLLL ........................................ 2021–09–09 Part 60, Subpart J; Part 60 Subpart Ja ............. Part 63, Subpart O ............................................. 2021–09–07 2021–08–26 Part 60, Subpart DDDD ..................................... 2021–08–19 Part 60, Subpart III, NNN ................................... 2021–08–17 Part 60, Subpart IIII ............................................ 2021–07–30 Part 60, Subpart J; Part 60 Subpart Ja ............. Part 60, Subpart WWW ...................................... 2021–07–28 2021–07–20 Part 60, Subpart VVa ......................................... 2021–07–09 Part 60, Subpart J; Part 60 Subpart Ja ............. 2021–07–09 Spectro Alloys Performance Test Extension Furnace 1 Performance. Taiga Ventures .................................................... Southern Earth Sciences .................................... Lynnwood Sewage Sludge Incinerator ............... US Army Garrison Command, Ft. Knox ............. St. Lucie County Landfill ..................................... Tampa Electric Big Bend Station ........................ Superior Refinery ................................................ Parkchester South Condominium ....................... EAP Ohio ............................................................ U.S. Granules—Henrietta Facility ....................... City of Greensboro (T.Z. Osborne Water Reclamation Facility). Westrock, Florence Mill ...................................... Toray Composite Materials America, Inc ........... Palmetto Landfill and Recycling Center ............. North Dade Landfill ............................................. United Taconite LLC (Cleveland-Cliffs) .............. Weld County Landfill ........................................... Total Energies-Port Arthur, TX ........................... Oxy Vinyls Houston Operations–Pasadena Polyvinyl Chloride Plant. Urschel Laboratories, Inc .................................... Battery Builders Inc ............................................. Bituminous Resources, Inc., dba Hopkins County Regional Landfill. Triangle Rock (A Subsidiary of Vulcan Materials Company). Veolia WWTP Biosolids Warren Michigan Project. Nucor Steel Gallatin ............................................ Holcomb Station .................................................. Mosaic Fertilizer—Faustina Plant ....................... U.S. Air Force Long Range Radar Station— Oliktok, Alaska. Vapor Point ......................................................... International Paper—Columbus, MS Mill ............ Ecoremedy .......................................................... Clean Harbors Industrial Services ...................... Sterigenics .......................................................... Eastman Chemical Company, Kingsport, Tennessee. BASF Freeport, TX ............................................. ddrumheller on DSK120RN23PROD with NOTICES1 Date of response Facility name Santee Cooper, Horray Generating Station ....... Vapor Point LLC ................................................. Morehead, Kentucky Landfill .............................. Accoya USA, LLC ............................................... Vapor Point ......................................................... VerDate Sep<11>2014 21:46 Nov 22, 2023 Jkt 262001 PO 00000 Frm 00041 Fmt 4703 Sfmt 4703 E:\FR\FM\24NON1.SGM 24NON1 82354 Federal Register / Vol. 88, No. 225 / Friday, November 24, 2023 / Notices APPLICABILITY DETERMINATIONS, ALTERNATIVE MONITORING PLANS AND REGULATORY INTERPRETATIONS UPLOADED TO CLEAN AIR ACT 111, 112, AND 129 DASHBOARD ON OCTOBER 2, 2023—Continued Title Affected subpart Marathon St. Paul Park ...................................... Conoco Phillips Alaska Exploration Wells .......... Alternative Monitoring for Petroleum Refineries Alternative Reporting Schedule for Crude Oil and Natural Gas Facilities. Alternative Monitoring for Pulp and Paper Industry. Alternative Reporting Schedule for Pulp and Paper Industry. Applicability Determination for Miscellaneous Coating Manufacturing. Regulatory Interpretation of Equipment Leaks of VOC in the Synthetic Organic Chemicals Manufacturing Industry. Applicability Determination for Asbestos ............ Part 60, Subpart Ja ............................................ Part 60, Subpart OOOOa ................................... 2021–06–29 2021–06–28 Part 63, Subpart S ............................................. 2021–06–25 Part 63, Subpart S ............................................. 2021–06–25 Part 63, Subpart HHHHHH ................................ 2021–06–23 Part 60, Subpart GGG/GGGa, Part 60, Subpart VV/Vva; Part 63, Subpart CC. 2021–06–07 Part 61, Subpart M ............................................. 2021–05–26 Alternative Monitoring for Petroleum Refineries Other Request—Alternative Sampling Method .. Applicability Determination for Miscellaneous Coating Manufacturing. Applicability Determination for Miscellaneous Coating Manufacturing. Applicability Determination for Coal Preparation Plants. Regulatory Interpretation for Asbestos .............. Applicability Determination for Miscellaneous Coating Manufacturing. Alternative Monitoring for Petroleum Refineries Technical Compliance Extension for Lime Manufacturing Plants. Applicability Determination for Miscellaneous Coating Manufacturing. Applicability Determination for Miscellaneous Coating Manufacturing. Other Request—Revised Alternative Monitoring Plan. Performance Test Waiver for Petroleum Refineries. Alternative Monitoring for Industrial, Commercial, and Institutional Boilers and Process Heaters. Applicability Determination for Miscellaneous Coating Manufacturing. Applicability Determination for Miscellaneous Coating Manufacturing. Applicability Determination for Other Solid Waste Incineration Units. Performance Test Waiver for Volatile Organic Compound (VOC) Emissions From Synthetic Organic Chemical Manufacturing Industry (SOCMI) Distillation Operations. Alternative Monitoring for Sewage Sludge Incineration Units. Alternative Test Method for Lime Manufacturing Plants. Applicability Determination for Miscellaneous Coating Manufacturing. Applicability Determination for Miscellaneous Coating Manufacturing. Applicability Determination for Stationary Reciprocating Internal Combustion Engines. Applicability Determination for Gasoline Dispensing Facilities. Regulatory Interpretation for Stationary Compression Ignition Internal Combustion Engines. Alternative Monitoring for Petroleum Refineries Applicability Determination for Lime Manufacturing Plants. Applicability Determination for Small Municipal Waste Combustion Units. Alternative Monitoring for Lime Manufacturing Plants. Alternative Monitoring for Petroleum Refineries Alternative Test Method for Petroleum Refineries. Applicability Determination for Miscellaneous Coating Manufacturing. Applicability Determination for Miscellaneous Coating Manufacturing. Part 60, Subpart J; Part 60 Subpart Ja ............. Part 60, Subpart WWW ...................................... Part 63, Subpart HHHHHH ................................ 2021–05–25 2021–05–11 2021–05–05 Part 63, Subpart HHHHHH ................................ 2021–05–05 Part 60, Subpart Y; Part 63 Subpart LLL .......... 2021–04–30 Part 61, Subpart M ............................................. Part 63, Subpart HHHHHH ................................ 2021–04–28 2021–04–15 Part 60, Subpart Ja ............................................ Part 63, Subpart AAAAA .................................... 2021–04–13 2021–04–09 Part 63, Subpart HHHHHH ................................ 2021–04–08 Part 63, Subpart HHHHHH ................................ 2021–04–08 Part 63, Subpart UUU ........................................ 2021–04–05 Part 60, Subpart Ja ............................................ 2021–03–22 Part 60, Subpart Db; Part 63, Subpart DDDDD 2021–03–19 Part 63, Subpart HHHHHH ................................ 2021–03–16 Part 63, Subpart HHHHHH ................................ 2021–03–16 Part 60, Subpart EEEE ...................................... 2021–03–15 Part 60, Subpart NNN and previously approved AMP 02/24/2005. 2021–03–09 Part 60, Subpart MMMM .................................... 2021–03–05 Part 63, Subpart AAAAA .................................... 2021–03–03 Part 63, Subpart HHHHHH ................................ 2021–02–24 Part 63, Subpart HHHHHH ................................ 2021–02–16 Part 63, Subpart ZZZZ ....................................... 2021–02–11 Part 63, Subpart CCCCCC ................................ 2021–02–02 Part 60, Subparts IIII and JJJJ .......................... 2021–01–19 Part 60, Subpart J; Part 60 Subpart Ja ............. Part 63, Subpart AAAAA .................................... 2021–01–19 2021–01–15 Part 60, Subpart AAAA ...................................... 2021–01–15 Part 63, Subpart AAAAA .................................... 2021–01–11 Part 60, Subpart Ja ............................................ Part 60, Subpart Ja ............................................ 2020–12–23 2020–12–22 Part 63, Subpart HHHHHH ................................ 2020–12–14 Part 63, Subpart HHHHHH ................................ 2020–12–14 International Paper- New Bern Mill ..................... Domtar AW LLC-Ashdown, AR .......................... Crash Champions, multiple facilities in Colorado BP Cherry Point .................................................. EPA NESHAP Residential Building Exemption Clarification Request. Vapor Point-La Porte, TX ................................... Covanta Haverhill ................................................ Complete Auto Body and Paint .......................... Michael’s Auto Body and Glass .......................... CEMEX Construction Materials Atlantic, Knoxville Cement Plant. Florida Department of Environmental Protection Denver Auto Body ............................................... USA DeBusk ....................................................... Lhoist North America—Montevallo Plant ............ Accurate Auto Body ............................................ Boulder Bump Shop ............................................ Motiva Enterprises-Port Arthur, TX Refinery ...... Chevron Salt Lake City Refinery ........................ Foley Cellulose, LLC ........................................... Arapahoe Collision and Mechanical ................... Colorado and Fitzsimons Auto Body .................. City of Selawik WTP ........................................... BASF Freeport .................................................... Metropolitan Sewerage District of Buncombe County, NC. Lhoist North America of Alabama, LLC— Montevallo Plant. Perry and Terry Autobody .................................. Hartford Finishing ................................................ Citation Oil and Gas (Holland & Hart LLP) ........ Palisades Nuclear Station ................................... Mainspring Energy .............................................. Shelton Services ................................................. Westvaco Facility ................................................ ddrumheller on DSK120RN23PROD with NOTICES1 Date of response Facility name Synergy Solutions of Crisp County, LP .............. Mississippi Lime .................................................. Marathon Petroleum Garyville LA Refinery ........ Flint Hills Resources Pine Bend Refinery .......... Porter Auto Body ................................................ Gerber Collision and Glass ................................. VerDate Sep<11>2014 21:46 Nov 22, 2023 Jkt 262001 PO 00000 Frm 00042 Fmt 4703 Sfmt 4703 E:\FR\FM\24NON1.SGM 24NON1 Federal Register / Vol. 88, No. 225 / Friday, November 24, 2023 / Notices 82355 APPLICABILITY DETERMINATIONS, ALTERNATIVE MONITORING PLANS AND REGULATORY INTERPRETATIONS UPLOADED TO CLEAN AIR ACT 111, 112, AND 129 DASHBOARD ON OCTOBER 2, 2023—Continued Title Affected subpart Gingerminion DBA Colors on Parade ................. Applicability Determination for Miscellaneous Coating Manufacturing. Applicability Determination for Miscellaneous Coating Manufacturing. Alternative Monitoring for VOC Emissions from SOCMI Distillation Operations. Performance Test Waiver for Beryllium ............. Performance Testing Extension Request and Force Majeure Claim. Part 63, Subpart HHHHHH ................................ 2020–12–14 Part 63, Subpart HHHHHH ................................ 2020–12–14 Part 60, Subpart NNN, Part 60 Subpart RRR ... 2020–12–02 Part 61, Subpart C ............................................. Part 62, Subpart LLL .......................................... 2020–12–02 2020–11–20 Performance Test Extension .............................. Other Request—Alternative Remedy and Timeline. Applicability Determination for Nitric Acid Plant Part 62, Subpart LLL .......................................... Part 60, Subpart WWW ...................................... 2020–11–20 2020–11–10 Part 60, Subpart Ga ........................................... 2020–11–06 Alternative Monitoring for Industrial Stream Generating Units. Alternative Monitoring for Municipal Solid Waste Landfills. Alternative Monitoring for Petroleum Refineries Performance Test Extension for Chemical Recovery Combustion Sources at Kraft, Soda, Sulfite, and Stand-Alone Semichemical Pulp Mills. Alternative Test Method for Coal and Oil-Fired Electric Utility Steam Generating Units. Applicability Determination for Other Solid Waste Incineration Units. Alternative Test Method for Sewage Sludge Incinerator. Other Request—Alternative Remedy and Timeline. Applicability Determination for Other Solid Waste Incineration Units. Alternative Monitoring for Synthetic Organic Chemical Manufacturing Industry (SOCMI) Distillation Operations. Applicability Determination for Secondary Copper Smelting Area Sources. Applicability Determination for Perchloroethylene Dry Cleaning Facilities. Applicability Determination for Municipal Solid Waste Landfills. Alternative Monitoring for Municipal Solid Waste Landfills. Applicability Determination for Surface Coating Of Miscellaneous Plastic Parts and Products. Applicability Determination for Nine Metal Fabrication and Finishing Source Categories. Other Request—Alternating Monitoring Request and Site-Specific NOX Emission Limit. Part 60, Subpart Db ........................................... 2020–10–22 Part 60, Subpart WWW ...................................... 2020–10–20 Part 60, Subpart Ja ............................................ Part 63, Subpart MM .......................................... 2020–10–13 2020–10–01 Part 63, Subpart UUUUU ................................... 2020–09–29 Part 60, Subpart EEEE ...................................... 2020–09–23 Part 62, Subpart LLL .......................................... 2020–09–14 Part 60, Subpart WWW ...................................... 2020–09–01 Part 60, Subpart EEEE ...................................... 2020–08–20 Part 60, Subpart NNN ........................................ 2020–08–17 Part 63, Subpart FFFFFF ................................... 2020–08–14 Part 63, Subpart M ............................................. 2020–08–06 Part 60, Subpart WWW ...................................... 2020–07–28 Part 60, Subpart WWW ...................................... 2020–07–23 Part 63, Subpart PPPP ...................................... 2020–06–16 Part 63, Subpart XXXXXX ................................. 2020–04–16 Part 60, Subpart Ja ............................................ 2019–05–22 Tesla ................................................................... KMTEX LLC ........................................................ Barry Industries, Attleboro, MA ........................... Sewerage & Water Board of New Orleans (SWBNO)-East Bank Sewage Treatment Plant. Sewerage & Water Board of New Orleans ........ Anchorage Regional Landfill ............................... Ascend Performance Materials Operations, LLC, Pensacola, Florida; Pensacola Adipic Acid Plant. WestRock CP, LLC—Stevenson Mill, Stevenson, Alabama. Anchorage Regional Landfill ............................... Flint Hills Resources Pine Bend Refinery .......... Westrock Evadale Mill ........................................ GVEA Healy ........................................................ Providence Kodiak .............................................. Manchester Wastewater Treatment Plant .......... Anchorage Regional Landfill ............................... U.S. Air Force Oliktok Alaska Incinerator ........... Trecora Chemical-Pasadena, TX ....................... AMES Copper Group, Formerly IMC Metals ...... Jackson Cleaners ............................................... Twin Landfill Corporation, Milner Landfill ........... Wake County Solid Waste Management Division—North Wake County Landfill. King Systems Corporation .................................. Vicor Corporation ................................................ HollyFrontier El Dorado Refining ........................ Panagiotis Tsirigotis, Director, Office of Air Quality Planning and Standards. [FR Doc. 2023–25950 Filed 11–22–23; 8:45 am] BILLING CODE 6560–50–P ENVIRONMENTAL PROTECTION AGENCY ddrumheller on DSK120RN23PROD with NOTICES1 Date of response Facility name [EPA–HQ–OPP–2017–0751; FRL–11376–02– OCSPP] Pesticide Registration Review; Decisions and Case Closures for Several Pesticides; Notice of Availability; Technical Correction Environmental Protection Agency (EPA). AGENCY: VerDate Sep<11>2014 21:46 Nov 22, 2023 Jkt 262001 ACTION: Notice, correction. In the Federal Register of October 18, 2023, EPA issued a notice to announce the availability of EPA’s interim registration review decisions for the following chemicals: Citric acid and salts, and linalool; and the closure of the registration review case for triadimenol. That notice incorrectly included a DATES section that established a comment deadline of December 18, 2023. A comment period is not necessary or appropriate for that document because the decisions announced in that document are final for triadimenol, and final for the interim phase of the process for citric acid and salts, and linalool. This document corrects that document SUMMARY: PO 00000 Frm 00043 Fmt 4703 Sfmt 4703 by reaffirming the nature of all the decisions announced in that document and by closing the comment period it incorrectly established. The comment period established in the Federal Register of October 18, 2023, i.e., December 18, 2023, is hereby closed on November 24, 2023. DATES: The docket for this action, identified by docket identification (ID) number EPA–HQ–OPP–2017–0751, is available online at https:// www.regulations.gov. Additional instructions for visiting the docket, along with more information about dockets generally, is available at https:// www.epa.gov/dockets. ADDRESSES: FOR FURTHER INFORMATION CONTACT: E:\FR\FM\24NON1.SGM 24NON1

Agencies

[Federal Register Volume 88, Number 225 (Friday, November 24, 2023)]
[Notices]
[Pages 82350-82355]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-25950]


-----------------------------------------------------------------------

ENVIRONMENTAL PROTECTION AGENCY

[EPA-HQ-OAR-2023-0194; FRL-11557-01-OAR]


EPA Determinations of Compliance and Applicability Under CAA 111, 
112, and 129 Dashboard: EPA Formal Responses to Inquiries Concerning 
Compliance With the Clean Air Act Stationary Source Program (Since May 
2019)

AGENCY: Environmental Protection Agency (EPA).

ACTION: Notice of availability.

-----------------------------------------------------------------------

SUMMARY: This notice announces the availability of applicability 
determinations, alternative monitoring decisions, and regulatory 
interpretations made by the Environmental Protection Agency (EPA) with 
regard to the New Source Performance Standards (NSPS); the National 
Emission Standards for Hazardous Air Pollutants (NESHAP); the Emission 
Guidelines and Federal Plan Requirements for existing sources; and/or 
the Stratospheric Ozone Protection Program.

FOR FURTHER INFORMATION CONTACT: An electronic copy of each complete 
document posted on the Clean Air Act 111, 112, and 129 Dashboard, which

[[Page 82351]]

contains determinations signed after May 2019, is available on the 
internet through the Resources and Guidance Documents for Compliance 
Assistance page of the Clean Air Act Compliance Monitoring website 
under ``Air'' at: https://www.epa.gov/complying-air-emissions-standards-stationary-sources/epa-determinations-compliance-and. All 
previously issued responses are posted on the Applicability 
Determination Index (ADI) data system available on the internet through 
the Resources and Guidance Documents for Compliance Assistance page of 
the Clean Air Act Compliance Monitoring website under ``Air'' at: 
https://www.epa.gov/compliance/resources-and-guidance-documents-compliance-assistance.
    The letters and memoranda on the Clean Air Act 111, 112, and 129 
Dashboard may be located by facility name, affected subpart, or by 
response date and is searchable by string word searches. For questions 
about the Clean Air Act 111, 112, and 129 Dashboard or this notice, 
contact Diana Felix, Air Quality Policy Division, Operating Permits 
Group; telephone number: (919) 541-7627; email address: 
[email protected].

SUPPLEMENTARY INFORMATION: 

General Information

    The General Provisions of the NSPS in 40 Code of Federal 
Regulations (CFR) part 60 and the General Provisions of the NESHAP in 
40 CFR part 61 provide that a source owner or operator may request a 
determination of whether certain intended actions constitute the 
commencement of construction, reconstruction, or modification. 40 CFR 
60.5 and 61.06. The General Provisions in part 60 also apply to Federal 
and EPA-approved state plans for existing sources in 40 CFR part 62. 
See 40 CFR 62.02(b)(2). The EPA's written responses to source or 
facility-specific inquiries on provisions in parts 60, 61 and 62 are 
commonly referred to as applicability determinations. Although the 
NESHAP part 63 regulations [which include Maximum Achievable Control 
Technology (MACT) standards and/or Generally Available Control 
Technology (GACT) standards] contain no specific regulatory provision 
providing that sources may request applicability determinations, the 
EPA also responds to written inquiries regarding applicability for the 
part 63 regulations. In addition, the General Provisions in parts 60 
and 63 allow sources to seek permission to use monitoring or 
recordkeeping that is different from the promulgated requirements. See 
40 CFR 60.13(i), 61.14(g), 63.8(b)(1), 63.8(f), and 63.10(f). The EPA's 
written responses to these inquiries are commonly referred to as 
alternative monitoring decisions. Furthermore, the EPA responds to 
written inquiries about the broad range of regulatory requirements in 
40 CFR parts 60 through 63 as they pertain to a whole source category. 
These inquiries may pertain, for example, to the type of sources to 
which the regulation applies, or to the testing, monitoring, 
recordkeeping, or reporting requirements contained in the regulation. 
The EPA's written responses to these inquiries are commonly referred to 
as regulatory interpretations.
    The EPA previously compiled EPA-issued NSPS and NESHAP 
applicability determinations, alternative monitoring decisions, and 
regulatory interpretations, and posted them to the ADI. As of October 
2, 2023, the EPA determinations of compliance and applicability under 
Clean Air Act 111, 112, and 129 will be posted to the Clean Air Act 
111, 112, and 129 Dashboard. The Clean Air Act 111, 112, and 129 
Dashboard is a data system, accessed via the internet, containing all 
determinations signed after May 2019.
    This notice comprises a list of 173 such documents added to the 
Clean Air Act 111, 112, and 129 Dashboard on October 2, 2023. This 
notice lists the title of each letter and memorandum. Complete copies 
of these documents may be obtained from the Clean Air Act 111, 112 and 
129 Dashboard on the internet through the Resources and Guidance 
Documents for Compliance Assistance page of the Clean Air Act 
Compliance Monitoring website under ``Air'' at: https://www.epa.gov/compliance/resources-and-guidance-documents-compliance-assistance.

 Applicability Determinations, Alternative Monitoring Plans and Regulatory Interpretations Uploaded to Clean Air
                               Act 111, 112, and 129 Dashboard on October 2, 2023
----------------------------------------------------------------------------------------------------------------
                                                                                                      Date of
              Facility name                          Title                 Affected subpart          response
----------------------------------------------------------------------------------------------------------------
East Carolina Regional Solid Waste        Other Request--Well         Part 62, Subpart OOO......      2023-09-12
 Landfill.                                 Decommissioning.
Eaton Corporation--Auburn Facility......  Applicability               Part 63, Subpart ZZZZ;          2023-09-07
                                           Determination for           Part 60, Subpart IIII.
                                           Stationary Combustion
                                           Engines.
ANR Pipeline Company--LaGrange            Alternative Monitoring for  Part 63, Subpart YYYY.....      2023-08-25
 Compressor Station.                       Stationary Gas Turbines.
ANR Pipeline Company--Sulpher Springs     Alternative Monitoring for  Part 63, Subpart YYYY.....      2023-08-25
 Compressor Station.                       Stationary Gas Turbines.
International Paper (IP)--Columbus Mill.  Alternative Monitoring for  Part 63, Subpart S........      2023-08-10
                                           Pulp and Paper Production.
Valero Renewable Fuels..................  Applicability               Part 60, Subpart NNN......      2023-08-07
                                           Determination for SOCMI
                                           Distillation Operations.
Diversified Vapor Technologies..........  Alternative Monitoring for  Part 60, Subpart J; Part        2023-07-27
                                           Petroleum Refineries.       60, Subpart Ja:.
Xcel Energy--High Bridge................  Alternative Monitoring for  Part 63, Subpart YYYY.....      2023-07-27
                                           Stationary Gas Turbines.
Tampa Electric Company--Big Bend Station  Other Request--Approval of  Part 63, Subpart YYYY.....      2023-07-25
                                           a continuous monitoring
                                           system (CMS) plan
                                           petition.
DVT/Multiple R4 Refineries..............  Alternative Monitoring for  Part 60, Subpart J; Part        2023-07-25
                                           Petroleum Refineries.       60, Subpart Ja.
Mosaic Fertilizer New Whales Facility...  Alternative Monitoring for  Part 63, Subpart BB.......      2023-07-21
                                           Phosphate Fertilizer
                                           Production Plants.
Maple Hill Landfill.....................  Alternative Test Method     Part 62, Subpart OOO......      2023-07-14
                                           for MSWLF.
Owl's Head Alloys, Inc..................  Alternative Test Method     Part 63, Subpart RRR......      2023-07-11
                                           for Secondary Aluminum
                                           Production.
Alyeska TAPS Pump Station #1............  Performance Test Extension  Part 60, Subpart KKKK.....      2023-07-10
                                           for Stationary Combustion
                                           Turbines.
Carmeuse Americas--Longview.............  Alternative Monitoring for  Part 63, Subpart AAAAA....      2023-06-21
                                           Lime Manufacturing Plant.
University of Michigan--Central Power     Other Request--Request for  Part 63, Subpart YYYY.....      2023-06-15
 Plant.                                    Operating Limits/
                                           Monitoring Petition.
Entergy Services LLC....................  Other Request--Revision to  Part 63, Subpart YYYY.....      2023-06-12
                                           your approved continuous
                                           monitoring system (CMS)
                                           plan.

[[Page 82352]]

 
Dominion Energy.........................  Performance Test Waiver     Part 63, Subpart UUUUU....      2023-06-12
                                           for Coil and Oil-Fired
                                           Electric Generating Units.
Advansix Hopewell Virginia..............  Alternative Monitoring for  Part 63, Subpart FFFF.....      2023-06-07
                                           Miscellaneous Organic
                                           Chemical Manufacturing.
Materion Brush Inc......................  Applicability               Part 63, Subpart ZZZZ.....      2023-05-31
                                           Determination for
                                           Stationary Reciprocating
                                           Combustion Engines.
XCEL Energy--Riverside Generating Plant.  Alternative Test Method     Part 63, Subpart YYYY.....      2023-05-23
                                           for Stationary Gas
                                           Turbines.
Texas Eastern Transmission--Somerset....  Applicability               Part 63, Subpart YYYY.....      2023-05-23
                                           Determination for
                                           Stationary Gas Turbines.
XCEL Energy--High Bridge Combined Cycle.  Alternative Monitoring for  Part 63, Subpart YYYY.....      2023-05-22
                                           Stationary Gas Turbines.
Safe Dispose, LLC (SD-40)...............  Applicability               Part 60, Subpart Ec.......      2023-05-08
                                           Determination for HMIWI.
Uwharrie Environmental Landfill.........  Alternative Monitoring for  Part 62, Subpart OOO......      2023-04-24
                                           MSWL.
Buchanan Marine, LP.....................  Applicability               Part 63, Subpart XXXXXX...      2023-04-10
                                           Determination for Nine
                                           Metal Fabrication and
                                           Finishing Source
                                           Categories.
City of High Point (Eastside Waste Water  Alternative Monitoring      Part 60, Subpart MMMM.....      2023-03-23
 Treatment Plant) Revised AMP              Procedure for Wastewater
 Resubmittal.                              Treatment Facility.
East Carolina Regional Landfill.........  Other Request--Well         Part 62, Subpart OOO; Part      2023-03-23
                                           Decommissioning.            63, Subpart AAAA.
Hanes Mill Road Landfill................  Other Request--Well         Part 62, Subpart OOO; Part      2023-03-23
                                           Decommissioning.            63, Subpart AAAA.
Safe Dispose, LLC (SD-9 & SD-21)........  Applicability               Part 60, Subpart Ec.......      2023-03-23
                                           Determination for
                                           Hospital/Medical/
                                           Infectious Waste
                                           Incinerators.
Kronospan...............................  Other Request--Compliance   Part 63, Subpart DDDD.....      2023-03-23
                                           Option for Plywood and
                                           Composite Wood Products.
Duke Energy Florida, LLC, Citrus          Other Request--Approval of  Part 63, Subpart YYYY.....      2023-03-17
 Combined Cycle Station.                   CMS Plan.
Florida Power and Light.................  Other Request--Approval of  Part 63, Subpart YYYY.....      2023-03-17
                                           CMS Plan.
Johns Hopkins All Children's Hospital...  Regulatory Interpretation   Part 63, Subpart ZZZZ.....      2023-03-17
                                           for Stationary
                                           Reciprocating Internal
                                           Combustion Engines.
CITGO Corpus Christi East Refinery......  Alternative Monitoring for  Part 60, Subpart Ja.......      2023-03-14
                                           Petroleum Refineries.
TC Energy (ANR Brownsville Compressor     Other Request--Approval of  Part 63, Subpart YYYY.....      2023-03-09
 Station, TN).                             CMS Plan.
South Wake Landfill.....................  Other Request--Well         Part 62, Subpart OOO; Part      2023-03-03
                                           Decommissioning.            63, Subpart AAAA.
Petro Nova Parish Holdings-Capture Plant  Performance Test Extension  Part 63, Subpart A; Part        2023-02-16
                                           for Stationary Gas          63, Subpart YYYY.
                                           Turbines.
Timber Ridge Landfill, Richwoods, MO....  Alternative Monitoring for  Part 62, Subpart OOO......      2023-02-08
                                           MSWL.
Capital Region Airport Authority........  Applicability               Part 60, Subpart EEEE.....      2023-01-27
                                           Determination for Other
                                           Solid Waste Incineration
                                           Units.
Safe Dispose, LLC (SD-27)...............  Applicability               Part 60, Subpart Ec.......      2023-01-19
                                           Determination for
                                           Hospital/Medical/
                                           Infectious Waste
                                           Incinerators.
Transcontinental Gas Pipe Line Company,   Other Request--Approval of  Part 63, Subpart YYYY.....      2023-01-18
 LLC (Transco), Compressor Station 85.     CMS Plan.
Valero Refining--St Charles Refinery....  Alternative Monitoring for  Part 60, Subpart Ja.......      2023-01-13
                                           Petroleum Refineries.
Transcontinental Gas Pipe Line Company,   Other Request--Approval of  Part 63, Subpart YYYY.....      2023-01-13
 LLC (Transco) Station 110.                CMS Plan.
Nikaitchuq Development Site.............  Performance Test Waiver     Part 60, Subpart KKKK.....      2023-01-05
                                           for Stationary Combustion
                                           Turbine.
International Paper ORANGE MILL PLANT...  Alternative Monitoring for  Part 63, Subpart S........      2022-12-19
                                           Pulp and Paper Production.
Consumers Energy Company--Muskegon River  Performance Test Extension  Part 63, Subpart YYYY.....      2022-12-06
 Compressor Station.                       for Stationary Gas
                                           Turbine.
Misc Metal Parts and Products Surface     Regulatory Interpretation   Part 63, Subpart MMMM.....      2022-11-30
 Coating Facilities.                       for NESAHP MMMM.
ExxonMobil Beaumont Refinery-Flare Vent   Alternative Monitoring for  Part 63, Subpart CC.......      2022-11-09
 Gas Composition Monitoring AMP.           Petroleum Refineries.
Hanes Mill Road Landfill................  Other Request--Well         Part 62, Subpart OOO; Part      2022-10-25
                                           Decommissioning.            60, Subpart AAAA.
East Carolina Regional Landfill.........  Other Request--Well         Part 62, Subpart OOO......      2022-10-25
                                           Decommissioning.
Tesla Salt Lake City....................  Applicability               Part 63, Subpart HHHHHH...      2022-10-14
                                           Determination for
                                           Miscellaneous Coating
                                           Manufacturing.
Pratt & Whitney 1 Aircraft Road           Other Request--Petition     Part 63, Subpart YYYY.....      2022-09-21
 Middletown, CT 06457.                     for Operating Limitations.
Marathon Petroleum Company Garyville      Alternative Monitoring      Part 60, Subpart Ja.......      2022-09-07
 Refinery.                                 Plan for Petroleum
                                           Refinery.
East Carolina Regional Solid Waste        Alternative Monitoring for  Part 62, Subpart OOO......      2022-09-06
 Landfill.                                 MSWL.
Giant Cement............................  Alternative Monitoring for  Part 63, Subpart EEE......      2022-08-30
                                           Hazardous Waste Combustor.
Artesia Renewable Diesel Company LLC....  Performance Test Waiver     Part 60, Subpart NNN; Part      2022-08-30
                                           for VOC Emissions from      60, Subpart RRR.
                                           SOCMI Distillation
                                           Operations.
Choctaw County Generating Plant.........  Other Request--Approval of  Part 63, Subpart YYYY.....      2022-08-30
                                           CMS Plan.
Kansas Department of Health and           Regulatory Interpretation   Part 60, Subpart DD.......      2022-08-17
 Environment.                              for Grain Elevators.
Packaging Corporation of America Filer    Performance Test Waiver     Part 61, Subpart E........      2022-08-01
 City Mill.                                for Mercury.
East Carolina Regional Solid Waste        Other Request--Well         Part 62, Subpart OOO; Part      2022-07-26
 Landfill.                                 Decommissioning.            63, Subpart AAAA.
Georgia Pacific Wood Products...........  Other Request--Approval of  Part 63, Subpart YYYY.....      2022-07-26
                                           CMS Plan.
City of High Point (Eastside Waste Water  Alternative Monitoring      Part 60, Subpart MMMM.....      2022-07-22
 Treatment Plant).                         Plan for Wastewater
                                           Treatment Plant.
City of Greensboro (T.Z. Osborne Water    Alternative Monitoring      Part 60, Subpart MMMM.....      2022-07-22
 Reclamation Facility) Revised AMP         Procedure for Sewage
 Submittal.                                Sludge Incineration Unit.
Safe Dispose, LLC.......................  Applicability               Part 60, Subpart Ec.......      2022-07-14
                                           Determination for
                                           Hospital/Medical/
                                           Infectious Waste
                                           Incinerators.

[[Page 82353]]

 
American Environmental Inc..............  Alternative Monitoring for  Part 60, Subpart J; Part        2022-06-28
                                           Petroleum Refineries.       60, Subpart Ja.
EGGER...................................  Regulatory Interpretation   Part 63 Subpart DDDD......      2022-06-15
                                           for Plywood and Composite
                                           Wood Products.
Spectro Alloys Performance Test           Performance Test Extension  Part 61, Subpart RRR......      2022-06-07
 Extension Furnace 1 Performance.          for Secondary Aluminum
                                           Production.
Taiga Ventures..........................  Applicability               Part 60, Subpart CCCC.....      2022-05-26
                                           Determination for
                                           Commercial and Industrial
                                           Solid Waste Incineration
                                           Units.
Southern Earth Sciences.................  Alternative Monitoring for  Part 60, Subpart J........      2022-05-23
                                           Petroleum Refineries.
Lynnwood Sewage Sludge Incinerator......  Performance Test Extension  Part 62, Subpart LLL......      2022-05-12
                                           for Existing Sewage
                                           Sludge Incineration Units.
US Army Garrison Command, Ft. Knox......  Regulatory Interpretation   Part 63, Subpart ZZZZ.....      2022-04-27
                                           for Stationary
                                           Reciprocating Internal
                                           Combustion Engines.
St. Lucie County Landfill...............  Alternative Monitoring for  Part 62, Subpart OOO......      2022-04-20
                                           MSW Landfill.
Tampa Electric Big Bend Station.........  Other Request--Testing      Part 63, Subpart YYYY.....      2022-04-14
                                           Minimum Time Notification
                                           Waiver.
Superior Refinery.......................  Alternative Monitoring for  Part 60, Subpart Ja.......      2022-04-11
                                           Petroleum Refineries.
Parkchester South Condominium...........  Applicability               Part 60, Subpart Db.......      2022-03-31
                                           Determination for Crude
                                           Oil and Natural Gas
                                           Facilities.
EAP Ohio................................  Regulatory Interpretation   Part 60, Subpart OOOO;          2022-03-29
                                           for Crude Oil and Natural   Part 60, Subpart OOOOa.
                                           Gas Facilities.
U.S. Granules--Henrietta Facility.......  Applicability               Part 63, Subpart RRR......      2022-03-25
                                           Determination for
                                           Secondary Aluminum
                                           Production.
City of Greensboro (T.Z. Osborne Water    Alternative Monitoring for  Part 60, Subpart MMMM;          2022-03-15
 Reclamation Facility).                    Existing Sewage Sludge      Part 62, Subpart LLL.
                                           Incineration Units.
Westrock, Florence Mill.................  Alternative Monitoring for  Part 60, Subpart BB.......      2022-02-16
                                           Kraft Pulp Mills.
Toray Composite Materials America, Inc..  Alternative Monitoring for  Part 63, Subpart LLLLLL...      2022-02-03
                                           Asphalt Processing and
                                           Asphalt Roofing.
Palmetto Landfill and Recycling Center..  Regulatory Interpretation   Part 62, Subpart OOO; Part      2022-02-03
                                           for Municipal Solid Waste   63, Subpart AAAA.
                                           Landfills.
North Dade Landfill.....................  Alternative Monitoring for  Part 62, OOO; Part 63,          2022-01-07
                                           Municipal Solid Waste       Subpart AAAA.
                                           Landfills.
United Taconite LLC (Cleveland-Cliffs)..  Alternative Monitoring for  Part 63, Subpart RRRRR....      2021-12-28
                                           Taconite Iron Ore
                                           Processing.
Weld County Landfill....................  Performance Test Waiver     Part 60, Subpart JJJJ.....      2021-12-17
                                           for Stationary Spark
                                           Ignition Internal
                                           Combustion Engines.
Total Energies-Port Arthur, TX..........  Alternative Monitoring for  Part 60, Subpart Ja.......      2021-12-13
                                           Petroleum Refineries.
Oxy Vinyls Houston Operations-Pasadena    Alternative Monitoring for  Part 63, Subpart HHHHHHH..      2021-12-06
 Polyvinyl Chloride Plant.                 Polyvinyl Chloride and
                                           Copolymers Production.
Urschel Laboratories, Inc...............  Alternative Monitoring for  Part 60, Subpart UUU......      2021-12-03
                                           Calciners and Dryers in
                                           Mineral Industries.
Battery Builders Inc....................  Performance Test Waiver     Part 60, Subpart KK; Part       2021-11-29
                                           for Lead Acid Batter        63, Subpart PPPPPP.
                                           Manufacturing Area
                                           Sources.
Bituminous Resources, Inc., dba Hopkins   Regulatory Interpretation   Part 62, Subpart OOO......      2021-11-18
 County Regional Landfill.                 for MSW Landfills.
Triangle Rock (A Subsidiary of Vulcan     Applicability               Part 60, Subpart OOO......      2021-11-09
 Materials Company).                       Determination for
                                           Nonmetallic Mineral
                                           Processing Plants.
Veolia WWTP Biosolids Warren Michigan     Applicability               Part 60, Subpart LLLL.....      2021-10-28
 Project.                                  Determination for New
                                           Sewage Sludge
                                           Incineration Units.
Nucor Steel Gallatin....................  Alternative Monitoring for  Part 63, Subpart CCC......      2021-10-21
                                           Steel Pickling HCl
                                           Process Facilities and
                                           Hydrochloric Acid
                                           Regeneration Plants.
Holcomb Station.........................  Performance Test Waiver     Part 63, Subpart UUUUU....      2021-10-21
                                           for Coal- and Oil-Fired
                                           Electric Utility Steam
                                           Generating Units.
Mosaic Fertilizer--Faustina Plant.......  Alternative Monitoring for  Part 63, Subpart BB.......      2021-10-14
                                           Phosphate Fertilizers
                                           Production Plants.
U.S. Air Force Long Range Radar Station-- Applicability               Part 60, Subpart EEEE.....      2021-09-30
 Oliktok, Alaska.                          Determination for Other
                                           Solid Waste Incineration
                                           Units.
Vapor Point.............................  Alternative Monitoring for  Part 60, Subpart J; Part        2021-09-30
                                           Petroleum Refineries.       60 Subpart Ja.
International Paper--Columbus, MS Mill..  Alternative Monitoring for  Part 63, Subpart S........      2021-09-29
                                           Pulp and Paper Industry.
Ecoremedy...............................  Applicability               Part 60, Subpart LLLL.....      2021-09-09
                                           Determination for New
                                           Sewage Sludge
                                           Incineration Units.
Clean Harbors Industrial Services.......  Alternative Monitoring for  Part 60, Subpart J; Part        2021-09-07
                                           Petroleum Refineries.       60 Subpart Ja.
Sterigenics.............................  Alternative Monitoring for  Part 63, Subpart O........      2021-08-26
                                           Ethylene Oxide Emissions
                                           Standards for
                                           Sterilization Facilities.
Eastman Chemical Company, Kingsport,      Performance Test Waiver     Part 60, Subpart DDDD.....      2021-08-19
 Tennessee.                                for Commercial and
                                           Industrial Solid Waste
                                           Incineration Units.
BASF Freeport, TX.......................  Alternative Monitoring for  Part 60, Subpart III, NNN.      2021-08-17
                                           SOCMI Air Oxidation Units
                                           and Distillation
                                           Operations.
Santee Cooper, Horray Generating Station  Applicability               Part 60, Subpart IIII.....      2021-07-30
                                           Determination for
                                           Stationary Compression
                                           Ignition Internal
                                           Combustion Engines.
Vapor Point LLC.........................  Alternative Monitoring for  Part 60, Subpart J; Part        2021-07-28
                                           Petroleum Refineries.       60 Subpart Ja.
Morehead, Kentucky Landfill.............  Regulatory Interpretation   Part 60, Subpart WWW......      2021-07-20
                                           for Municipal Solid Waste
                                           Landfills.
Accoya USA, LLC.........................  Alternative Monitoring for  Part 60, Subpart VVa......      2021-07-09
                                           Equipment Leaks of VOC in
                                           the Synthetic Organic
                                           Chemicals Manufacturing
                                           Industry.
Vapor Point.............................  Alternative Monitoring for  Part 60, Subpart J; Part        2021-07-09
                                           Petroleum Refineries.       60 Subpart Ja.

[[Page 82354]]

 
Marathon St. Paul Park..................  Alternative Monitoring for  Part 60, Subpart Ja.......      2021-06-29
                                           Petroleum Refineries.
Conoco Phillips Alaska Exploration Wells  Alternative Reporting       Part 60, Subpart OOOOa....      2021-06-28
                                           Schedule for Crude Oil
                                           and Natural Gas
                                           Facilities.
International Paper- New Bern Mill......  Alternative Monitoring for  Part 63, Subpart S........      2021-06-25
                                           Pulp and Paper Industry.
Domtar AW LLC-Ashdown, AR...............  Alternative Reporting       Part 63, Subpart S........      2021-06-25
                                           Schedule for Pulp and
                                           Paper Industry.
Crash Champions, multiple facilities in   Applicability               Part 63, Subpart HHHHHH...      2021-06-23
 Colorado.                                 Determination for
                                           Miscellaneous Coating
                                           Manufacturing.
BP Cherry Point.........................  Regulatory Interpretation   Part 60, Subpart GGG/GGGa,      2021-06-07
                                           of Equipment Leaks of VOC   Part 60, Subpart VV/Vva;
                                           in the Synthetic Organic    Part 63, Subpart CC.
                                           Chemicals Manufacturing
                                           Industry.
EPA NESHAP Residential Building           Applicability               Part 61, Subpart M........      2021-05-26
 Exemption Clarification Request.          Determination for
                                           Asbestos.
Vapor Point-La Porte, TX................  Alternative Monitoring for  Part 60, Subpart J; Part        2021-05-25
                                           Petroleum Refineries.       60 Subpart Ja.
Covanta Haverhill.......................  Other Request--Alternative  Part 60, Subpart WWW......      2021-05-11
                                           Sampling Method.
Complete Auto Body and Paint............  Applicability               Part 63, Subpart HHHHHH...      2021-05-05
                                           Determination for
                                           Miscellaneous Coating
                                           Manufacturing.
Michael's Auto Body and Glass...........  Applicability               Part 63, Subpart HHHHHH...      2021-05-05
                                           Determination for
                                           Miscellaneous Coating
                                           Manufacturing.
CEMEX Construction Materials Atlantic,    Applicability               Part 60, Subpart Y; Part        2021-04-30
 Knoxville Cement Plant.                   Determination for Coal      63 Subpart LLL.
                                           Preparation Plants.
Florida Department of Environmental       Regulatory Interpretation   Part 61, Subpart M........      2021-04-28
 Protection.                               for Asbestos.
Denver Auto Body........................  Applicability               Part 63, Subpart HHHHHH...      2021-04-15
                                           Determination for
                                           Miscellaneous Coating
                                           Manufacturing.
USA DeBusk..............................  Alternative Monitoring for  Part 60, Subpart Ja.......      2021-04-13
                                           Petroleum Refineries.
Lhoist North America--Montevallo Plant..  Technical Compliance        Part 63, Subpart AAAAA....      2021-04-09
                                           Extension for Lime
                                           Manufacturing Plants.
Accurate Auto Body......................  Applicability               Part 63, Subpart HHHHHH...      2021-04-08
                                           Determination for
                                           Miscellaneous Coating
                                           Manufacturing.
Boulder Bump Shop.......................  Applicability               Part 63, Subpart HHHHHH...      2021-04-08
                                           Determination for
                                           Miscellaneous Coating
                                           Manufacturing.
Motiva Enterprises-Port Arthur, TX        Other Request--Revised      Part 63, Subpart UUU......      2021-04-05
 Refinery.                                 Alternative Monitoring
                                           Plan.
Chevron Salt Lake City Refinery.........  Performance Test Waiver     Part 60, Subpart Ja.......      2021-03-22
                                           for Petroleum Refineries.
Foley Cellulose, LLC....................  Alternative Monitoring for  Part 60, Subpart Db; Part       2021-03-19
                                           Industrial, Commercial,     63, Subpart DDDDD.
                                           and Institutional Boilers
                                           and Process Heaters.
Arapahoe Collision and Mechanical.......  Applicability               Part 63, Subpart HHHHHH...      2021-03-16
                                           Determination for
                                           Miscellaneous Coating
                                           Manufacturing.
Colorado and Fitzsimons Auto Body.......  Applicability               Part 63, Subpart HHHHHH...      2021-03-16
                                           Determination for
                                           Miscellaneous Coating
                                           Manufacturing.
City of Selawik WTP.....................  Applicability               Part 60, Subpart EEEE.....      2021-03-15
                                           Determination for Other
                                           Solid Waste Incineration
                                           Units.
BASF Freeport...........................  Performance Test Waiver     Part 60, Subpart NNN and        2021-03-09
                                           for Volatile Organic        previously approved AMP
                                           Compound (VOC) Emissions    02/24/2005.
                                           From Synthetic Organic
                                           Chemical Manufacturing
                                           Industry (SOCMI)
                                           Distillation Operations.
Metropolitan Sewerage District of         Alternative Monitoring for  Part 60, Subpart MMMM.....      2021-03-05
 Buncombe County, NC.                      Sewage Sludge
                                           Incineration Units.
Lhoist North America of Alabama, LLC--    Alternative Test Method     Part 63, Subpart AAAAA....      2021-03-03
 Montevallo Plant.                         for Lime Manufacturing
                                           Plants.
Perry and Terry Autobody................  Applicability               Part 63, Subpart HHHHHH...      2021-02-24
                                           Determination for
                                           Miscellaneous Coating
                                           Manufacturing.
Hartford Finishing......................  Applicability               Part 63, Subpart HHHHHH...      2021-02-16
                                           Determination for
                                           Miscellaneous Coating
                                           Manufacturing.
Citation Oil and Gas (Holland & Hart      Applicability               Part 63, Subpart ZZZZ.....      2021-02-11
 LLP).                                     Determination for
                                           Stationary Reciprocating
                                           Internal Combustion
                                           Engines.
Palisades Nuclear Station...............  Applicability               Part 63, Subpart CCCCCC...      2021-02-02
                                           Determination for
                                           Gasoline Dispensing
                                           Facilities.
Mainspring Energy.......................  Regulatory Interpretation   Part 60, Subparts IIII and      2021-01-19
                                           for Stationary              JJJJ.
                                           Compression Ignition
                                           Internal Combustion
                                           Engines.
Shelton Services........................  Alternative Monitoring for  Part 60, Subpart J; Part        2021-01-19
                                           Petroleum Refineries.       60 Subpart Ja.
Westvaco Facility.......................  Applicability               Part 63, Subpart AAAAA....      2021-01-15
                                           Determination for Lime
                                           Manufacturing Plants.
Synergy Solutions of Crisp County, LP...  Applicability               Part 60, Subpart AAAA.....      2021-01-15
                                           Determination for Small
                                           Municipal Waste
                                           Combustion Units.
Mississippi Lime........................  Alternative Monitoring for  Part 63, Subpart AAAAA....      2021-01-11
                                           Lime Manufacturing Plants.
Marathon Petroleum Garyville LA Refinery  Alternative Monitoring for  Part 60, Subpart Ja.......      2020-12-23
                                           Petroleum Refineries.
Flint Hills Resources Pine Bend Refinery  Alternative Test Method     Part 60, Subpart Ja.......      2020-12-22
                                           for Petroleum Refineries.
Porter Auto Body........................  Applicability               Part 63, Subpart HHHHHH...      2020-12-14
                                           Determination for
                                           Miscellaneous Coating
                                           Manufacturing.
Gerber Collision and Glass..............  Applicability               Part 63, Subpart HHHHHH...      2020-12-14
                                           Determination for
                                           Miscellaneous Coating
                                           Manufacturing.

[[Page 82355]]

 
Gingerminion DBA Colors on Parade.......  Applicability               Part 63, Subpart HHHHHH...      2020-12-14
                                           Determination for
                                           Miscellaneous Coating
                                           Manufacturing.
Tesla...................................  Applicability               Part 63, Subpart HHHHHH...      2020-12-14
                                           Determination for
                                           Miscellaneous Coating
                                           Manufacturing.
KMTEX LLC...............................  Alternative Monitoring for  Part 60, Subpart NNN, Part      2020-12-02
                                           VOC Emissions from SOCMI    60 Subpart RRR.
                                           Distillation Operations.
Barry Industries, Attleboro, MA.........  Performance Test Waiver     Part 61, Subpart C........      2020-12-02
                                           for Beryllium.
Sewerage & Water Board of New Orleans     Performance Testing         Part 62, Subpart LLL......      2020-11-20
 (SWBNO)-East Bank Sewage Treatment        Extension Request and
 Plant.                                    Force Majeure Claim.
Sewerage & Water Board of New Orleans...  Performance Test Extension  Part 62, Subpart LLL......      2020-11-20
Anchorage Regional Landfill.............  Other Request--Alternative  Part 60, Subpart WWW......      2020-11-10
                                           Remedy and Timeline.
Ascend Performance Materials Operations,  Applicability               Part 60, Subpart Ga.......      2020-11-06
 LLC, Pensacola, Florida; Pensacola        Determination for Nitric
 Adipic Acid Plant.                        Acid Plant.
WestRock CP, LLC--Stevenson Mill,         Alternative Monitoring for  Part 60, Subpart Db.......      2020-10-22
 Stevenson, Alabama.                       Industrial Stream
                                           Generating Units.
Anchorage Regional Landfill.............  Alternative Monitoring for  Part 60, Subpart WWW......      2020-10-20
                                           Municipal Solid Waste
                                           Landfills.
Flint Hills Resources Pine Bend Refinery  Alternative Monitoring for  Part 60, Subpart Ja.......      2020-10-13
                                           Petroleum Refineries.
Westrock Evadale Mill...................  Performance Test Extension  Part 63, Subpart MM.......      2020-10-01
                                           for Chemical Recovery
                                           Combustion Sources at
                                           Kraft, Soda, Sulfite, and
                                           Stand-Alone Semichemical
                                           Pulp Mills.
GVEA Healy..............................  Alternative Test Method     Part 63, Subpart UUUUU....      2020-09-29
                                           for Coal and Oil-Fired
                                           Electric Utility Steam
                                           Generating Units.
Providence Kodiak.......................  Applicability               Part 60, Subpart EEEE.....      2020-09-23
                                           Determination for Other
                                           Solid Waste Incineration
                                           Units.
Manchester Wastewater Treatment Plant...  Alternative Test Method     Part 62, Subpart LLL......      2020-09-14
                                           for Sewage Sludge
                                           Incinerator.
Anchorage Regional Landfill.............  Other Request--Alternative  Part 60, Subpart WWW......      2020-09-01
                                           Remedy and Timeline.
U.S. Air Force Oliktok Alaska             Applicability               Part 60, Subpart EEEE.....      2020-08-20
 Incinerator.                              Determination for Other
                                           Solid Waste Incineration
                                           Units.
Trecora Chemical-Pasadena, TX...........  Alternative Monitoring for  Part 60, Subpart NNN......      2020-08-17
                                           Synthetic Organic
                                           Chemical Manufacturing
                                           Industry (SOCMI)
                                           Distillation Operations.
AMES Copper Group, Formerly IMC Metals..  Applicability               Part 63, Subpart FFFFFF...      2020-08-14
                                           Determination for
                                           Secondary Copper Smelting
                                           Area Sources.
Jackson Cleaners........................  Applicability               Part 63, Subpart M........      2020-08-06
                                           Determination for
                                           Perchloroethylene Dry
                                           Cleaning Facilities.
Twin Landfill Corporation, Milner         Applicability               Part 60, Subpart WWW......      2020-07-28
 Landfill.                                 Determination for
                                           Municipal Solid Waste
                                           Landfills.
Wake County Solid Waste Management        Alternative Monitoring for  Part 60, Subpart WWW......      2020-07-23
 Division--North Wake County Landfill.     Municipal Solid Waste
                                           Landfills.
King Systems Corporation................  Applicability               Part 63, Subpart PPPP.....      2020-06-16
                                           Determination for Surface
                                           Coating Of Miscellaneous
                                           Plastic Parts and
                                           Products.
Vicor Corporation.......................  Applicability               Part 63, Subpart XXXXXX...      2020-04-16
                                           Determination for Nine
                                           Metal Fabrication and
                                           Finishing Source
                                           Categories.
HollyFrontier El Dorado Refining........  Other Request--Alternating  Part 60, Subpart Ja.......      2019-05-22
                                           Monitoring Request and
                                           Site-Specific NOX
                                           Emission Limit.
----------------------------------------------------------------------------------------------------------------


Panagiotis Tsirigotis,
Director, Office of Air Quality Planning and Standards.
[FR Doc. 2023-25950 Filed 11-22-23; 8:45 am]
BILLING CODE 6560-50-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.