Tridam Energy LLC, Madko Hydro LLC; Notice of Transfer of Exemption, 80293 [2023-25401]
Download as PDF
80293
Federal Register / Vol. 88, No. 221 / Friday, November 17, 2023 / Notices
TO INTERVENE’’, ‘‘COMMENTS,’’
‘‘REPLY COMMENTS,’’
‘‘RECOMMENDATIONS,’’
‘‘PRELIMINARY TERMS AND
CONDITIONS,’’ or ‘‘PRELIMINARY
FISHWAY PRESCRIPTIONS;’’ (2) set
forth in the heading the name of the
applicant and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
protesting or intervening; and (4)
otherwise comply with the requirements
of 18 CFR 385.2001 through 385.2005.
All comments, recommendations, terms
and conditions or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. A copy of all other filings
in reference to this application must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b) and 385.2010.
o. Procedural schedule: The
application will be processed according
to the following schedule. Revisions to
the schedule will be made as
appropriate.
Milestone
Target date
Deadline for Filing Protest, Motion to Intervene, Comments, Recommendations, Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions.
Deadline for Filing Reply Comments ..............................................................................................................................................
khammond on DSKJM1Z7X2PROD with NOTICES
p. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of this notice.
q. The license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) a copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification. Please note that the
certification request must comply with
40 CFR 121.5(b), including
documentation that a pre-filing meeting
request was submitted to the certifying
authority at least 30 days prior to
submitting the certification request.
Please note that the certification request
must be sent to the certifying authority
and to the Commission concurrently.
r. The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202)502–6595 or OPP@
ferc.gov.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Western Area Power Administration
[Project No. 7920–006]
Tridam Energy LLC, Madko Hydro LLC;
Notice of Transfer of Exemption
1. On October 13, 2023, Tridam
Energy LLC filed a notification of the
transfer for the 150-kilowatt Waterloom
Falls Hydroelectric Project No. 7920
from Tridam Energy LLC to Madko
Hydro LLC. The exemption from
licensing was originally issued on
March 11, 1985.1 The project is located
on the Merrimack River, Hillsboro
County, New Hampshire. The transfer of
an exemption does not require
Commission approval.
2. Madko Hydro LLC is now the
exemptee of the Waterloom Falls
Hydroelectric Project No. 7920. All
correspondence must be forwarded to
Jacob Komar, Madko Hydro LLC, 94
River Road, New Ipswich, NH 03071,
Phone: 860–214–3219, Email:
jacobkomar@me.com.
Dated: November 9, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–25401 Filed 11–16–23; 8:45 am]
BILLING CODE 6717–01–P
[FR Doc. 2023–25397 Filed 11–16–23; 8:45 am]
BILLING CODE 6717–01–P
1 Alden T. Greenwood (Environmental
Assessment 1985). Subsequently, on June 6, 2014,
the project was transferred to Tridam Energy LLC.
18:57 Nov 16, 2023
Jkt 262001
February 2024
DEPARTMENT OF ENERGY
Dated: November 9, 2023.
Kimberly D. Bose,
Secretary.
VerDate Sep<11>2014
January 2024
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
Extension of Public Comment Period
for Central Valley Project Power,
Transmission, and Ancillary Services;
and the California-Oregon
Transmission Project Transmission
Service—Rate Order No. WAPA–207
Western Area Power
Administration, DOE.
ACTION: Notice of extension of public
comment period for power,
transmission, and ancillary services
formula rates.
AGENCY:
The Sierra Nevada Region
(SN) of the Western Area Power
Administration (WAPA) is extending
the public comment period for 30 days
on its proposed formula rates for Central
Valley Project (CVP) power,
transmission, and ancillary services;
and California-Oregon Transmission
Project (COTP) transmission service
under Rate Order No. WAPA–207.
DATES: The consultation and comment
period for the proposed formula rates
under Rate Order No. WAPA–207 is
extended from November 28, 2023, to
December 28, 2023.
FOR FURTHER INFORMATION CONTACT:
Autumn Wolfe, Rates Manager, Sierra
Nevada Region, Western Area Power
Administration, (916) 353–4686 or
email: SNR-RateCase@wapa.gov.
SUPPLEMENTARY INFORMATION: On August
30, 2023, SN published a notice in the
Federal Register (88 FR 59909)
announcing proposed formula rates for
Central Valley Project power,
transmission, and ancillary services;
and California-Oregon Transmission
Project transmission service under Rate
Order No. WAPA–207. In that notice,
the consultation and comment period
was reported to close November 28,
SUMMARY:
E:\FR\FM\17NON1.SGM
17NON1
Agencies
[Federal Register Volume 88, Number 221 (Friday, November 17, 2023)]
[Notices]
[Page 80293]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-25401]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 7920-006]
Tridam Energy LLC, Madko Hydro LLC; Notice of Transfer of
Exemption
1. On October 13, 2023, Tridam Energy LLC filed a notification of
the transfer for the 150-kilowatt Waterloom Falls Hydroelectric Project
No. 7920 from Tridam Energy LLC to Madko Hydro LLC. The exemption from
licensing was originally issued on March 11, 1985.\1\ The project is
located on the Merrimack River, Hillsboro County, New Hampshire. The
transfer of an exemption does not require Commission approval.
---------------------------------------------------------------------------
\1\ Alden T. Greenwood (Environmental Assessment 1985).
Subsequently, on June 6, 2014, the project was transferred to Tridam
Energy LLC.
---------------------------------------------------------------------------
2. Madko Hydro LLC is now the exemptee of the Waterloom Falls
Hydroelectric Project No. 7920. All correspondence must be forwarded to
Jacob Komar, Madko Hydro LLC, 94 River Road, New Ipswich, NH 03071,
Phone: 860-214-3219, Email: [email protected].
Dated: November 9, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-25401 Filed 11-16-23; 8:45 am]