Public Utility District No. 1 of Chelan County, Washington; Notice of Application for Approval of Contract for the Sale of Power Under Section 22 of the Federal Power Act, 78013-78014 [2023-24992]

Download as PDF Federal Register / Vol. 88, No. 218 / Tuesday, November 14, 2023 / Notices of the Commission staff’s environmental document for the Project. This notice identifies Commission staff’s intention to prepare an environmental assessment (EA) for the Project and the planned schedule for the completion of the environmental review.1 Schedule for Environmental Review Issuance of EA—February 1, 2024 90-day Federal Authorization Decision Deadline 2—May 1, 2024 If a schedule change becomes necessary, additional notice will be provided so that the relevant agencies are kept informed of the Project’s progress. Project Description GTS proposes to construct and operate two underground salt dome natural gas storage caverns at its existing storage site, six additional 5,500 horsepower compressor units at its existing compressor station, a new brine disposal well and brine pipeline, and appurtenant facilities, in Jefferson County, Texas. Construction of the proposed facilities would temporarily disturb about 31 acres of land. Following construction, GTS would maintain about 5.2 acres of land for permanent operation of the Project’s facilities; the remaining acreage would be restored and revert to former uses. Background On September 21, 2023, the Commission issued a Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Golden Triangle Storage Expansion Project (Notice of Scoping). The Notice of Scoping was sent to affected landowners; Federal, State, and local government agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. In response to the Notice of Scoping, the Commission received comments from the Texas Parks and Wildlife Department, the Sierra Club, and U.S. Environmental Protection Agency. The primary issues raised by the commentors are construction procedures, flood risks, effects on threatened and endangered species, water quality, air quality, hazardous waste management, and impacts to environmental justice communities. All substantive comments will be addressed in the EA. DEPARTMENT OF ENERGY Additional Information [Project No. 943–142] In order to receive notification of the issuance of the EA and to keep track of formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This service provides automatic notification of filings made to subscribed dockets, document summaries, and direct links to the documents. Go to https:// www.ferc.gov/ferc-online/overview to register for eSubscription. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the ‘‘eLibrary’’ link, select ‘‘General Search’’ from the eLibrary menu, enter the selected date range and ‘‘Docket Number’’ excluding the last three digits (i.e., CP23–542), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Public Utility District No. 1 of Chelan County, Washington; Notice of Application for Approval of Contract for the Sale of Power Under Section 22 of the Federal Power Act Dated: November 7, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–25039 Filed 11–13–23; 8:45 am] khammond on DSKJM1Z7X2PROD with NOTICES BILLING CODE 6717–01–P 1 40 CFR 1501.10 (2020). 2 The Commission’s deadline applies to the decisions of other Federal agencies, and State agencies acting under federally delegated authority, that are responsible for Federal authorizations, permits, and other approvals necessary for proposed projects under the Natural Gas Act. Per 18 CFR 157.22(a), the Commission’s deadline for other agency’s decisions applies unless a schedule is otherwise established by Federal law. VerDate Sep<11>2014 16:48 Nov 13, 2023 Jkt 262001 78013 PO 00000 Frm 00066 Fmt 4703 Sfmt 4703 Federal Energy Regulatory Commission Take notice that on May 16, 2023, Public Utility District No. 1 of Chelan County, Washington (Chelan PUD) filed with the Commission an application for approval of a contract for the sale of power from its licensed Rock Island Hydroelectric Project No. 943 for a period beyond the expiration of its existing license for the project. The project is located on the Columbia River in Chelan and Douglas Counties, Washington. Section 22 of the Federal Power Act, 16 U.S.C. 815, provides that contracts for the sale and delivery of power for periods extending beyond the termination date of a license may be entered into upon the joint approval of the Commission and the appropriate state public service commission or other similar authority in the state in which the sale or delivery of power is made. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy of that document on the Petitioner. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, notices of intent, and competing applications using the Commission’s eFiling system at https:// ferconline.ferc.gov/LogIn.aspx. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://ferconline.ferc.gov/ QuickComment.aspx. You must include your name and contact information at the end of your comments. In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 E:\FR\FM\14NON1.SGM 14NON1 78014 Federal Register / Vol. 88, No. 218 / Tuesday, November 14, 2023 / Notices Filed Date: 11/6/23. Accession Number: 20231106–5167. Comment Date: 5 p.m. ET 11/27/23. Docket Numbers: ER12–779–000; ER12–995–000. Applicants: Cherokee County Cogeneration Partners, LLC, Cherokee County Cogeneration Partners, LLC. Description: Notice of Cancellation of Rate Market-Based Rate Authority and Tariff of Cherokee County Cogeneration Partners, LLC. Filed Date: 11/2/23. Accession Number: 20231102–5248. Comment Date: 5 p.m. ET 11/24/23. Docket Numbers: ER23–2398–003. Applicants: Arizona Public Service Company. Description: Compliance filing: Amendment No. 2 to APS Compliance Filing on Interconnection Reforms to be Dated: November 6, 2023. effective 9/30/2023. Kimberly D. Bose, Filed Date: 11/6/23. Secretary. Accession Number: 20231106–5148. [FR Doc. 2023–24992 Filed 11–13–23; 8:45 am] Comment Date: 5 p.m. ET 11/27/23. BILLING CODE 6717–01–P Docket Numbers: ER23–2813–000. Applicants: Castle Solar, LLC. Description: Supplement to DEPARTMENT OF ENERGY September 12, 2023, Castle Solar, LLC tariff filing. Federal Energy Regulatory Filed Date: 11/6/23. Commission Accession Number: 20231106–5165. Combined Notice of Filings #1 Comment Date: 5 p.m. ET 11/16/23. Docket Numbers: ER23–2927–001. Take notice that the Commission Applicants: Southwest Power Pool, received the following electric corporate Inc. filings: Description: Tariff Amendment: Docket Numbers: EC23–112–000. Amended Filing in ER23–2927—MultiApplicants: Elliott Associates, L.P., Day Reliability Assessment Design to be Elliott International, L.P., The Liverpool effective 1/16/2024. Limited Partnership. Filed Date: 11/7/23. Description: Elliott Associates, L.P., et Accession Number: 20231107–5073. al. submits Response to FERC’s October Comment Date: 5 p.m. ET 11/28/23. 6, 2023 Deficiency Letter. Docket Numbers: ER24–1–001. Filed Date: 11/2/23. Applicants: Consolidated Edison Accession Number: 20231102–5193. Company of New York, Inc. Comment Date: 5 p.m. ET 11/28/23. Description: Tariff Amendment: Docket Numbers: EC23–112–000. Amended Value Stack Monthly Credit Applicants: Elliott Associates, L.P., Elliott International, L.P., The Liverpool to be effective 10/2/2023. Filed Date: 11/7/23. Limited Partnership. Accession Number: 20231107–5111. Description: Gibson, Dunn & Crutcher, Comment Date: 5 p.m. ET 11/28/23. LLP submits work papers in support of Docket Numbers: ER24–352–000. the November 2, 2023 response to Applicants: AEP Texas Inc. FERC’s Deficiency Letter re the July 21, Description: § 205(d) Rate Filing: 2023 application of Elliot Associates, AEPTX–CGRP 10 (Copano & Port Bay L.P. et al. Solar) Generation Interconnection Agr Filed Date: 11/6/23. Accession Number: 20231106–0007. to be effective 10/18/2023. Comment Date: 5 p.m. ET 11/28/23. Filed Date: 11/6/23. Accession Number: 20231106–5135. Take notice that the Commission Comment Date: 5 p.m. ET 11/27/23. received the following electric rate filings: Docket Numbers: ER24–353–000. Applicants: Massachusetts Electric Docket Numbers: ER10–2924–017. Company. Applicants: Kleen Energy Systems, Description: Notice of Cancellation of LLC. Description: Notice of Non-Material Interconnection Agreement with Change in Status of Kleen Energy Dichotomy Collins Hydro LLC of Systems, LLC. Massachusetts Electric Company. khammond on DSKJM1Z7X2PROD with NOTICES First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number P–943– 142. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s website at https:// www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number (P–943–142) in the docket number field to access the document. For assistance, contact FERC Online Support. Comment Date: 5:00 p.m. Eastern Time on December 6, 2023. VerDate Sep<11>2014 16:48 Nov 13, 2023 Jkt 262001 PO 00000 Frm 00067 Fmt 4703 Sfmt 4703 Filed Date: 11/3/23. Accession Number: 20231103–5259. Comment Date: 5 p.m. ET 11/24/23. Docket Numbers: ER24–354–000. Applicants: Pacific Gas and Electric Company. Description: Notice of Termination of Service Agreement No. 99 under Pacific Gas and Electric Company’s FERC Electric Tariff Volume No. 5. Filed Date: 11/1/23. Accession Number: 20231101–5289. Comment Date: 5 p.m. ET 11/22/23. Docket Numbers: ER24–355–000. Applicants: California Independent System Operator Corporation. Description: Petition for Approval of Disposition of Penalty Assessment Proceeds and non-Refundable Interconnection Financial Security of the California Independent System Operator Corporation. Filed Date: 11/2/23. Accession Number: 20231102–5249. Comment Date: 5 p.m. ET 11/24/23. Docket Numbers: ER24–356–000. Applicants: San Diego Gas & Electric Company. Description: TO5 Formula Depreciation Rate Change for Common Plant and Electric General Plant of San Diego Gas & Electric Company. Filed Date: 11/2/23. Accession Number: 20231102–5252. Comment Date: 5 p.m. ET 11/24/23. Docket Numbers: ER24–357–000. Applicants: Midcontinent Independent System Operator, Inc., Ameren Illinois Company. Description: § 205(d) Rate Filing: Midcontinent Independent System Operator, Inc. submits tariff filing per 35.13(a)(2)(iii: 2023–11–07_SA 3028 Ameren IL-Prairie Power Project #40 Mason City Tap to be effective 1/7/2024. Filed Date: 11/7/23. Accession Number: 20231107–5066. Comment Date: 5 p.m. ET 11/28/23. Docket Numbers: ER24–358–000. Applicants: AEP Texas Inc. Description: § 205(d) Rate Filing: AEPTX-Industrial Bravo Project Generation Interconnection Agreement to be effective 10/18/2023. Filed Date: 11/7/23. Accession Number: 20231107–5110. Comment Date: 5 p.m. ET 11/28/23. Take notice that the Commission received the following public utility holding company filings: Docket Numbers: PH24–2–000. Applicants: ArcLight Capital Holdings, LLC. Description: ArcLight Capital Holdings, LLC submits FERC 65–A Exemption Notification. Filed Date: 11/3/23. E:\FR\FM\14NON1.SGM 14NON1

Agencies

[Federal Register Volume 88, Number 218 (Tuesday, November 14, 2023)]
[Notices]
[Pages 78013-78014]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-24992]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 943-142]


Public Utility District No. 1 of Chelan County, Washington; 
Notice of Application for Approval of Contract for the Sale of Power 
Under Section 22 of the Federal Power Act

    Take notice that on May 16, 2023, Public Utility District No. 1 of 
Chelan County, Washington (Chelan PUD) filed with the Commission an 
application for approval of a contract for the sale of power from its 
licensed Rock Island Hydroelectric Project No. 943 for a period beyond 
the expiration of its existing license for the project. The project is 
located on the Columbia River in Chelan and Douglas Counties, 
Washington.
    Section 22 of the Federal Power Act, 16 U.S.C. 815, provides that 
contracts for the sale and delivery of power for periods extending 
beyond the termination date of a license may be entered into upon the 
joint approval of the Commission and the appropriate state public 
service commission or other similar authority in the state in which the 
sale or delivery of power is made.
    Any person desiring to intervene or to protest this filing must 
file in accordance with Rules 211 and 214 of the Commission's Rules of 
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be 
considered by the Commission in determining the appropriate action to 
be taken but will not serve to make protestants parties to the 
proceeding. Any person wishing to become a party must file a notice of 
intervention or motion to intervene, as appropriate. Such notices, 
motions, or protests must be filed on or before the comment date. 
Anyone filing a motion to intervene or protest must serve a copy of 
that document on the Petitioner.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at https://ferconline.ferc.gov/LogIn.aspx. Commenters can submit brief comments up 
to 6,000 characters, without prior registration, using the eComment 
system at https://ferconline.ferc.gov/QuickComment.aspx. You must 
include your name and contact information at the end of your comments. 
In lieu of electronic filing, you may submit a paper copy. Submissions 
sent via the U.S. Postal Service must be addressed to: Kimberly D. 
Bose, Secretary, Federal Energy Regulatory Commission, 888

[[Page 78014]]

First Street NE, Room 1A, Washington, DC 20426. Submissions sent via 
any other carrier must be addressed to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, 
Maryland 20852. The first page of any filing should include docket 
number P-943-142.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's website at https://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-943-142) in the docket number field to 
access the document. For assistance, contact FERC Online Support.
    Comment Date: 5:00 p.m. Eastern Time on December 6, 2023.

    Dated: November 6, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-24992 Filed 11-13-23; 8:45 am]
BILLING CODE 6717-01-P