WBI Energy Transmission, Inc.; Notice of Request for Extension of Time, 75584-75585 [2023-24317]

Download as PDF lotter on DSK11XQN23PROD with NOTICES1 75584 Federal Register / Vol. 88, No. 212 / Friday, November 3, 2023 / Notices tariff filing per 35.13(a)(2)(iii): Met-Ed Amends 10 ECSAs (5435 6048 6150 6292 6297 6300 6301 6302 6336 6351) to be effective 12/31/9998. Filed Date: 10/27/23. Accession Number: 20231027–5136. Comment Date: 5 p.m. ET 11/17/23. Docket Numbers: ER24–236–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2023–10–27_Att X NERC Facility Interconnection Studies to be effective 1/1/2024. Filed Date: 10/27/23. Accession Number: 20231027–5139 Comment Date: 5 p.m. ET 11/17/23. Docket Numbers: ER24–237–000. Applicants: Josco Energy Corp. Description: Tariff Amendment: Notice of Cancellation of MBR Tariff to be effective 10/28/2023. Filed Date: 10/27/23. Accession Number: 20231027–5163. Comment Date: 5 p.m. ET 11/17/23. Docket Numbers: ER24–238–000. Applicants: Josco Energy USA, LLC. Description: Tariff Amendment: Notice of Cancellation for MBR Tariff to be effective 10/28/2023. Filed Date: 10/27/23. Accession Number: 20231027–5166. Comment Date: 5 p.m. ET 11/17/23. Docket Numbers: ER24–239–000. Applicants: Tyr Energy, LLC. Description: Compliance filing: Tyr Energy Seller Category Status Change to be effective 12/27/2023. Filed Date: 10/27/23. Accession Number: 20231027–5220. Comment Date: 5 p.m. ET 11/17/23. Take notice that the Commission received the following electric securities filings: Docket Numbers: ES24–10–000. Applicants: NorthWestern Corporation. Description: Application Under Section 204 of the Federal Power Act for Authorization to Issue Securities of NorthWestern Corporation. Filed Date: 10/25/23. Accession Number: 20231025–5290. Comment Date: 5 p.m. ET 11/15/23. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be VerDate Sep<11>2014 17:02 Nov 02, 2023 Jkt 262001 considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at:https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202)502–6595 or OPP@ ferc.gov. Dated: October 27, 2023. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2023–24262 Filed 11–2–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP22–512–001] WBI Energy Transmission, Inc.; Notice of Request for Extension of Time Take notice that on October 25, 2023, WBI Energy Transmission, Inc. (WBI Energy) requested that the Federal Energy Regulatory Commission (Commission) grant an extension of time (2023 Extension of Time Request), until June 1, 2024, to construct to construct and operate a new compressor station, tie-in facilities including pipeline, and associated measurement facilities on its Line Section 27 Expansion Project (Project) to provide incremental natural gas firm transportation service in McKenzie County, North Dakota authorized by the Commission in Docket Nos. CP82–487–000, et al.1 In its 2023 Extension of Time Request, WBI Energy states that it will not complete all work associated with the project by the November 21, 2023, deadline. Accordingly, WBI Energy requests an extension of time until June 1, 2024, to complete construction of project facilities. 1 WBI Energy Transmission et al., 30 FERC ¶ 61,143, (1985). PO 00000 Frm 00048 Fmt 4703 Sfmt 4703 This notice establishes a 15-calendar day intervention and comment period deadline. Any person wishing to comment on WBI Energy’s request for an extension of time may do so. No reply comments or answers will be considered. If you wish to obtain legal status by becoming a party to the proceedings for this request, you should, on or before the comment date stated below, file a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act (18 CFR 157.10). As a matter of practice, the Commission itself generally acts on requests for extensions of time to complete construction for Natural Gas Act facilities when such requests are contested before order issuance. For those extension requests that are contested,2 the Commission will aim to issue an order acting on the request within 45 days.3 The Commission will address all arguments relating to whether the applicant has demonstrated there is good cause to grant the extension.4 The Commission will not consider arguments that re-litigate the issuance of the certificate order, including whether the Commission properly found the project to be in the public convenience and necessity and whether the Commission’s environmental analysis for the certificate complied with the National Environmental Policy Act.5 At the time a pipeline requests an extension of time, orders on certificates of public convenience and necessity are final and the Commission will not re-litigate their issuance.6 The OEP Director, or his or her designee, will act on all of those extension requests that are uncontested. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number 2 Contested proceedings are those where an intervenor disputes any material issue of the filing. 18 CFR 385.2201(c)(1) (2022). 3 Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 40 (2020). 4 Id. at P 40. 5 Similarly, the Commission will not re-litigate the issuance of an NGA section 3 authorization, including whether a proposed project is not inconsistent with the public interest and whether the Commission’s environmental analysis for the permit order complied with NEPA. 6 Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 40 (2020). E:\FR\FM\03NON1.SGM 03NON1 Federal Register / Vol. 88, No. 212 / Friday, November 3, 2023 / Notices field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TTY, (202) 502–8659. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and three copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Comment Date: 5:00 p.m. Eastern Time on, November 14, 2023. Dated: October 30, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–24317 Filed 11–2–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER24–201–000] lotter on DSK11XQN23PROD with NOTICES1 Karbone Energy LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding of Karbone Energy LLC’s application for marketbased rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is November 16, 2023. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic VerDate Sep<11>2014 17:02 Nov 02, 2023 Jkt 262001 service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202)502–6595 or OPP@ ferc.gov. Dated: October 27, 2023. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2023–24258 Filed 11–2–23; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00049 Fmt 4703 Sfmt 4703 75585 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings Take notice that the Commission has received the following Natural Gas and Oil Pipeline Rate and Refund Report filings: Filings Instituting Proceedings Docket Numbers: RP24–72–000. Applicants: El Paso Natural Gas Company, L.L.C. Description: 4(d) Rate Filing: Negotiated Rate Agreements Update (Pioneer Nov 2023) to be effective 11/1/ 2023. Filed Date: 10/27/23. Accession Number: 20231027–5131. Comment Date: 5 p.m. ET 11/8/23. Docket Numbers: RP24–73–000. Applicants: Cheniere Creole Trail Pipeline, L.P. Description: Compliance filing: CTPL Transportation Retainage Adjustment and Housekeeping Changes to be effective 12/1/2023. Filed Date: 10/27/23. Accession Number: 20231027–5149. Comment Date: 5 p.m. ET 11/8/23. Docket Numbers: RP24–74–000. Applicants: Cheniere Corpus Christi Pipeline, LP. Description: Compliance filing: CCPL Address Change Filing to be effective 12/1/2023. Filed Date: 10/27/23. Accession Number: 20231027–5152. Comment Date: 5 p.m. ET 11/8/23. Docket Numbers: RP24–75–000. Applicants: El Paso Natural Gas Company, L.L.C. Description: 4(d) Rate Filing: Negotiated Rate Agmts Update (Hartree Nov 23) to be effective 11/1/2023. Filed Date: 10/27/23. Accession Number: 20231027–5171. Comment Date: 5 p.m. ET 11/8/23. Docket Numbers: RP24–76–000. Applicants: Midship Pipeline Company, LLC. Description: Compliance filing: Midship Pipeline Change of Address Filing to be effective 12/1/2023. Filed Date: 10/27/23. Accession Number: 20231027–5183. Comment Date: 5 p.m. ET 11/8/23. Docket Numbers: RP24–77–000. Applicants: Tennessee Gas Pipeline Company, L.L.C. Description: 4(d) Rate Filing: Negotiated Rate Agreements—Various Shippers Nov 2023 to be effective 11/1/ 2023. Filed Date: 10/27/23. E:\FR\FM\03NON1.SGM 03NON1

Agencies

[Federal Register Volume 88, Number 212 (Friday, November 3, 2023)]
[Notices]
[Pages 75584-75585]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-24317]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP22-512-001]


WBI Energy Transmission, Inc.; Notice of Request for Extension of 
Time

    Take notice that on October 25, 2023, WBI Energy Transmission, Inc. 
(WBI Energy) requested that the Federal Energy Regulatory Commission 
(Commission) grant an extension of time (2023 Extension of Time 
Request), until June 1, 2024, to construct to construct and operate a 
new compressor station, tie-in facilities including pipeline, and 
associated measurement facilities on its Line Section 27 Expansion 
Project (Project) to provide incremental natural gas firm 
transportation service in McKenzie County, North Dakota authorized by 
the Commission in Docket Nos. CP82-487-000, et al.\1\
---------------------------------------------------------------------------

    \1\ WBI Energy Transmission et al., 30 FERC ] 61,143, (1985).
---------------------------------------------------------------------------

    In its 2023 Extension of Time Request, WBI Energy states that it 
will not complete all work associated with the project by the November 
21, 2023, deadline. Accordingly, WBI Energy requests an extension of 
time until June 1, 2024, to complete construction of project 
facilities.
    This notice establishes a 15-calendar day intervention and comment 
period deadline. Any person wishing to comment on WBI Energy's request 
for an extension of time may do so. No reply comments or answers will 
be considered. If you wish to obtain legal status by becoming a party 
to the proceedings for this request, you should, on or before the 
comment date stated below, file a motion to intervene in accordance 
with the requirements of the Commission's Rules of Practice and 
Procedure (18 CFR 385.214 or 385.211) and the Regulations under the 
Natural Gas Act (18 CFR 157.10).
    As a matter of practice, the Commission itself generally acts on 
requests for extensions of time to complete construction for Natural 
Gas Act facilities when such requests are contested before order 
issuance. For those extension requests that are contested,\2\ the 
Commission will aim to issue an order acting on the request within 45 
days.\3\ The Commission will address all arguments relating to whether 
the applicant has demonstrated there is good cause to grant the 
extension.\4\ The Commission will not consider arguments that re-
litigate the issuance of the certificate order, including whether the 
Commission properly found the project to be in the public convenience 
and necessity and whether the Commission's environmental analysis for 
the certificate complied with the National Environmental Policy Act.\5\ 
At the time a pipeline requests an extension of time, orders on 
certificates of public convenience and necessity are final and the 
Commission will not re-litigate their issuance.\6\ The OEP Director, or 
his or her designee, will act on all of those extension requests that 
are uncontested.
---------------------------------------------------------------------------

    \2\ Contested proceedings are those where an intervenor disputes 
any material issue of the filing. 18 CFR 385.2201(c)(1) (2022).
    \3\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40 
(2020).
    \4\ Id. at P 40.
    \5\ Similarly, the Commission will not re-litigate the issuance 
of an NGA section 3 authorization, including whether a proposed 
project is not inconsistent with the public interest and whether the 
Commission's environmental analysis for the permit order complied 
with NEPA.
    \6\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40 
(2020).
---------------------------------------------------------------------------

    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (https://www.ferc.gov) using 
the ``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number

[[Page 75585]]

field to access the document. At this time, the Commission has 
suspended access to the Commission's Public Reference Room. For 
assistance, contact FERC at [email protected] or call toll-
free, (886) 208-3676 or TTY, (202) 502-8659.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at https://www.ferc.gov. Persons unable to file electronically should 
submit an original and three copies of the protest or intervention to 
the Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426.
    Comment Date: 5:00 p.m. Eastern Time on, November 14, 2023.

    Dated: October 30, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-24317 Filed 11-2-23; 8:45 am]