Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline, 73836-73837 [2023-23798]
Download as PDF
73836
Federal Register / Vol. 88, No. 207 / Friday, October 27, 2023 / Notices
ESTIMATES OF THE EFFECTS DUE TO THE PROPOSED POLICY STATEMENT IN DOCKET NO. PL24–1–000
A. Information collection
B. Number of
respondents
D. Total
number of
responses
(column B ×
column C)
C. Annual
number of
responses per
respondent
E. Average
burden hrs. &
cost per
response
F. Total annual hr.
burdens & total
annual cost
(column D × column
E)
15 hrs. $1,440 .......
15 hrs. $1,440 .......
15 hrs. $1,440 .......
1 hr. $96 ................
330 hrs. $31,680 ...
90 hrs. $8,640 .......
165 hrs. $15,840 ...
170 hrs. $16,320 ...
$1,440
1,440
1,440
96
G. Cost per
respondent
(column F ÷
column B)
FERC–1006 17
FERC–537
FERC 516
FERC 545
FERC 555
...............................
...............................
...............................
...............................
22
6
11
170
1
1
1
1
22
6
11
170
Other Affected Collections
FERC–538 ...............................
FERC–546 ...............................
FERC–550 ...............................
1
16
7
1
1
1
1
16
7
15 hrs. $1,440 .......
15 hrs. $1,440 .......
15 hrs. $1,440 .......
15 hrs. $1,440 .......
240 hrs. $23,040 ...
105 hrs. $10,080 ...
1,440
1,440
1,440
Total Effect of the Proposed Policy Statement.
........................
........................
233
................................
1,115 hrs. $107,040
........................
IV. Document Availability
DEPARTMENT OF ENERGY
22. In addition to publishing the full
text of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov).
23. From the Commission’s Home
Page on the internet, this information is
available on eLibrary. The full text of
this document is available on eLibrary
in PDF and Microsoft Word format for
viewing, printing, and/or downloading.
To access this document in eLibrary,
type the docket number excluding the
last three digits of this document in the
docket number field.
24. User assistance is available for
eLibrary and the Commission’s website
during normal business hours from the
Commission’s Online Support at (202)
502–6652 (toll free at 1–866–208–3676)
or email at ferconlinesupport@ferc.gov,
or the Public Reference Room at (202)
502–8371, TTY (202) 502–8659. Email
the Public Reference Room at
public.referenceroom@ferc.gov.
Federal Energy Regulatory
Commission
ddrumheller on DSK120RN23PROD with NOTICES1
By direction of the Commission.
Issued: October 19, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–23590 Filed 10–26–23; 8:45 am]
BILLING CODE 6717–01–P
17 The FERC 1006 is a new temporary collection
number that includes the burden changes due to the
proposed policy statement in the FERC–545, –537,
–516, and –555, which are pending at OMB for
unrelated purposes.
VerDate Sep<11>2014
17:44 Oct 26, 2023
Jkt 262001
[Docket No. CP24–5–000]
Columbia Gas Transmission, LLC;
Notice of Request Under Blanket
Authorization and Establishing
Intervention and Protest Deadline
Take notice that on October 13, 2023,
Columbia Gas Transmission (Columbia),
700 Louisiana Street, Suite 1300,
Houston, Texas 77002–2700, filed in the
above referenced docket, a prior notice
request pursuant to sections 157.208
and 157.216 of the Commission’s
regulations under the Natural Gas Act
(NGA), and Columbia’s blanket
certificate issued in Docket No. CP83–
76–000, for authorization to abandon
and replace sections of its existing
SR538 pipeline, abandon its existing
SR424 pipeline, install a bi-directional
launching and receiving station for inline inspection devices, and perform
other related appurtenant activities. All
of the above facilities are located in
Hocking County, Ohio (SR538 Pipeline
Replacement Project). The project will
allow Columbia to conduct in-line
inspection, or pigging, of Line SR538 to
ensure compliance with DOT
requirements for inspections of pipeline
systems. The estimated cost for the
project is $24.7 million, all as more fully
set forth in the request which is on file
with the Commission and open to
public inspection.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
PO 00000
Frm 00014
Fmt 4703
Sfmt 4703
Commission’s Home Page
(www.ferc.gov) using the ‘‘eLibrary’’
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document. At
this time, the Commission has
suspended access to the Commission’s
Public Reference Room. For assistance,
contact the Federal Energy Regulatory
Commission at FercOnlineSupport@
ferc.gov or call toll-free, (886) 208–3676
or TTY (202) 502–8659.
Any questions concerning this request
should be directed to David A. Alonzo,
700 Louisiana Street, Suite 1300,
Houston, Texas 77002–2700 at (832)
320–5477 or email at david_alonzo@
tcenergy.com.
Public Participation
There are three ways to become
involved in the Commission’s review of
this project: you can file a protest to the
project, you can file a motion to
intervene in the proceeding, and you
can file comments on the project. There
is no fee or cost for filing protests,
motions to intervene, or comments. The
deadline for filing protests, motions to
intervene, and comments is 5 p.m.
Eastern Time on December 22, 2023.
How to file protests, motions to
intervene, and comments is explained
below.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
E:\FR\FM\27OCN1.SGM
27OCN1
Federal Register / Vol. 88, No. 207 / Friday, October 27, 2023 / Notices
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Protests
Pursuant to section 157.205 of the
Commission’s regulations under the
NGA,1 any person 2 or the Commission’s
staff may file a protest to the request. If
no protest is filed within the time
allowed or if a protest is filed and then
withdrawn within 30 days after the
allowed time for filing a protest, the
proposed activity shall be deemed to be
authorized effective the day after the
time allowed for protest. If a protest is
filed and not withdrawn within 30 days
after the time allowed for filing a
protest, the instant request for
authorization will be considered by the
Commission.
Protests must comply with the
requirements specified in section
157.205(e) of the Commission’s
regulations,3 and must be submitted by
the protest deadline, which is December
22, 2023. A protest may also serve as a
motion to intervene so long as the
protestor states it also seeks to be an
intervenor.
ddrumheller on DSK120RN23PROD with NOTICES1
Interventions
Any person has the option to file a
motion to intervene in this proceeding.
Only intervenors have the right to
request rehearing of Commission orders
issued in this proceeding and to
subsequently challenge the
Commission’s orders in the U.S. Circuit
Courts of Appeal.
To intervene, you must submit a
motion to intervene to the Commission
in accordance with Rule 214 of the
Commission’s Rules of Practice and
Procedure 4 and the regulations under
the NGA 5 by the intervention deadline
for the project, which is December 22,
2023. As described further in Rule 214,
your motion to intervene must state, to
the extent known, your position
regarding the proceeding, as well as
your interest in the proceeding. For an
individual, this could include your
status as a landowner, ratepayer,
resident of an impacted community, or
recreationist. You do not need to have
property directly impacted by the
project in order to intervene. For more
information about motions to intervene,
refer to the FERC website at https://
1 18
CFR 157.205.
include individuals, organizations,
businesses, municipalities, and other entities. 18
CFR 385.102(d).
3 18 CFR 157.205(e).
4 18 CFR 385.214.
5 18 CFR 157.10.
2 Persons
VerDate Sep<11>2014
17:44 Oct 26, 2023
Jkt 262001
www.ferc.gov/resources/guides/how-to/
intervene.asp.
All timely, unopposed motions to
intervene are automatically granted by
operation of Rule 214(c)(1). Motions to
intervene that are filed after the
intervention deadline are untimely and
may be denied. Any late-filed motion to
intervene must show good cause for
being late and must explain why the
time limitation should be waived and
provide justification by reference to
factors set forth in Rule 214(d) of the
Commission’s Rules and Regulations. A
person obtaining party status will be
placed on the service list maintained by
the Secretary of the Commission and
will receive copies (paper or electronic)
of all documents filed by the applicant
and by all other parties.
Comments
Any person wishing to comment on
the project may do so. The Commission
considers all comments received about
the project in determining the
appropriate action to be taken. To
ensure that your comments are timely
and properly recorded, please submit
your comments on or before December
22, 2023. The filing of a comment alone
will not serve to make the filer a party
to the proceeding. To become a party,
you must intervene in the proceeding.
How To File Protests, Interventions,
and Comments
There are two ways to submit
protests, motions to intervene, and
comments. In both instances, please
reference the Project docket number
CP24–5–000 in your submission.
(1) You may file your protest, motion
to intervene, and comments by using the
Commission’s eFiling feature, which is
located on the Commission’s website
(www.ferc.gov) under the link to
Documents and Filings. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ You will be
asked to select the type of filing you are
making; first select ‘‘General’’ and then
select ‘‘Protest’’, ‘‘Intervention’’, or
‘‘Comment on a Filing’’; or 6
(2) You can file a paper copy of your
submission by mailing it to the address
below. Your submission must reference
the Project docket number CP24–5–000.
To file via USPS: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE,
Washington, DC 20426.
6 Additionally, you may file your comments
electronically by using the eComment feature,
which is located on the Commission’s website at
www.ferc.gov under the link to Documents and
Filings. Using eComment is an easy method for
interested persons to submit brief, text-only
comments on a project.
PO 00000
Frm 00015
Fmt 4703
Sfmt 4703
73837
To file via any other method:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852.
The Commission encourages
electronic filing of submissions (option
1 above) and has eFiling staff available
to assist you at (202) 502–8258 or
FercOnlineSupport@ferc.gov.
Protests and motions to intervene
must be served on the applicant either
by mail or email (with a link to the
document) at: David A. Alonzo,
Manager, Project Authorizations, 700
Louisiana Street, Suite 1300, Houston,
Texas 77002–2700 at (832) 320–5477, or
at david_alonzo@tcenergy.com. Any
subsequent submissions by an
intervenor must be served on the
applicant and all other parties to the
proceeding. Contact information for
parties can be downloaded from the
service list at the eService link on FERC
Online.
Tracking the Proceeding
Throughout the proceeding,
additional information about the project
will be available from the Commission’s
Office of External Affairs, at (866) 208–
FERC, or on the FERC website at
www.ferc.gov using the ‘‘eLibrary’’ link
as described above. The eLibrary link
also provides access to the texts of all
formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. For more information and to
register, go to www.ferc.gov/docs-filing/
esubscription.asp.
Dated: October 23, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–23798 Filed 10–26–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC23–124–000.
E:\FR\FM\27OCN1.SGM
27OCN1
Agencies
[Federal Register Volume 88, Number 207 (Friday, October 27, 2023)]
[Notices]
[Pages 73836-73837]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-23798]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP24-5-000]
Columbia Gas Transmission, LLC; Notice of Request Under Blanket
Authorization and Establishing Intervention and Protest Deadline
Take notice that on October 13, 2023, Columbia Gas Transmission
(Columbia), 700 Louisiana Street, Suite 1300, Houston, Texas 77002-
2700, filed in the above referenced docket, a prior notice request
pursuant to sections 157.208 and 157.216 of the Commission's
regulations under the Natural Gas Act (NGA), and Columbia's blanket
certificate issued in Docket No. CP83-76-000, for authorization to
abandon and replace sections of its existing SR538 pipeline, abandon
its existing SR424 pipeline, install a bi-directional launching and
receiving station for in-line inspection devices, and perform other
related appurtenant activities. All of the above facilities are located
in Hocking County, Ohio (SR538 Pipeline Replacement Project). The
project will allow Columbia to conduct in-line inspection, or pigging,
of Line SR538 to ensure compliance with DOT requirements for
inspections of pipeline systems. The estimated cost for the project is
$24.7 million, all as more fully set forth in the request which is on
file with the Commission and open to public inspection.
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (www.ferc.gov) using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to the Commission's Public
Reference Room. For assistance, contact the Federal Energy Regulatory
Commission at [email protected] or call toll-free, (886) 208-
3676 or TTY (202) 502-8659.
Any questions concerning this request should be directed to David
A. Alonzo, 700 Louisiana Street, Suite 1300, Houston, Texas 77002-2700
at (832) 320-5477 or email at [email protected].
Public Participation
There are three ways to become involved in the Commission's review
of this project: you can file a protest to the project, you can file a
motion to intervene in the proceeding, and you can file comments on the
project. There is no fee or cost for filing protests, motions to
intervene, or comments. The deadline for filing protests, motions to
intervene, and comments is 5 p.m. Eastern Time on December 22, 2023.
How to file protests, motions to intervene, and comments is explained
below.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for
[[Page 73837]]
rehearing, the public is encouraged to contact OPP at (202) 502-6595 or
[email protected].
Protests
Pursuant to section 157.205 of the Commission's regulations under
the NGA,\1\ any person \2\ or the Commission's staff may file a protest
to the request. If no protest is filed within the time allowed or if a
protest is filed and then withdrawn within 30 days after the allowed
time for filing a protest, the proposed activity shall be deemed to be
authorized effective the day after the time allowed for protest. If a
protest is filed and not withdrawn within 30 days after the time
allowed for filing a protest, the instant request for authorization
will be considered by the Commission.
---------------------------------------------------------------------------
\1\ 18 CFR 157.205.
\2\ Persons include individuals, organizations, businesses,
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------
Protests must comply with the requirements specified in section
157.205(e) of the Commission's regulations,\3\ and must be submitted by
the protest deadline, which is December 22, 2023. A protest may also
serve as a motion to intervene so long as the protestor states it also
seeks to be an intervenor.
---------------------------------------------------------------------------
\3\ 18 CFR 157.205(e).
---------------------------------------------------------------------------
Interventions
Any person has the option to file a motion to intervene in this
proceeding. Only intervenors have the right to request rehearing of
Commission orders issued in this proceeding and to subsequently
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
To intervene, you must submit a motion to intervene to the
Commission in accordance with Rule 214 of the Commission's Rules of
Practice and Procedure \4\ and the regulations under the NGA \5\ by the
intervention deadline for the project, which is December 22, 2023. As
described further in Rule 214, your motion to intervene must state, to
the extent known, your position regarding the proceeding, as well as
your interest in the proceeding. For an individual, this could include
your status as a landowner, ratepayer, resident of an impacted
community, or recreationist. You do not need to have property directly
impacted by the project in order to intervene. For more information
about motions to intervene, refer to the FERC website at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------
\4\ 18 CFR 385.214.
\5\ 18 CFR 157.10.
---------------------------------------------------------------------------
All timely, unopposed motions to intervene are automatically
granted by operation of Rule 214(c)(1). Motions to intervene that are
filed after the intervention deadline are untimely and may be denied.
Any late-filed motion to intervene must show good cause for being late
and must explain why the time limitation should be waived and provide
justification by reference to factors set forth in Rule 214(d) of the
Commission's Rules and Regulations. A person obtaining party status
will be placed on the service list maintained by the Secretary of the
Commission and will receive copies (paper or electronic) of all
documents filed by the applicant and by all other parties.
Comments
Any person wishing to comment on the project may do so. The
Commission considers all comments received about the project in
determining the appropriate action to be taken. To ensure that your
comments are timely and properly recorded, please submit your comments
on or before December 22, 2023. The filing of a comment alone will not
serve to make the filer a party to the proceeding. To become a party,
you must intervene in the proceeding.
How To File Protests, Interventions, and Comments
There are two ways to submit protests, motions to intervene, and
comments. In both instances, please reference the Project docket number
CP24-5-000 in your submission.
(1) You may file your protest, motion to intervene, and comments by
using the Commission's eFiling feature, which is located on the
Commission's website (www.ferc.gov) under the link to Documents and
Filings. New eFiling users must first create an account by clicking on
``eRegister.'' You will be asked to select the type of filing you are
making; first select ``General'' and then select ``Protest'',
``Intervention'', or ``Comment on a Filing''; or \6\
---------------------------------------------------------------------------
\6\ Additionally, you may file your comments electronically by
using the eComment feature, which is located on the Commission's
website at www.ferc.gov under the link to Documents and Filings.
Using eComment is an easy method for interested persons to submit
brief, text-only comments on a project.
---------------------------------------------------------------------------
(2) You can file a paper copy of your submission by mailing it to
the address below. Your submission must reference the Project docket
number CP24-5-000.
To file via USPS: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE, Washington, DC 20426.
To file via any other method: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland
20852.
The Commission encourages electronic filing of submissions (option
1 above) and has eFiling staff available to assist you at (202) 502-
8258 or [email protected].
Protests and motions to intervene must be served on the applicant
either by mail or email (with a link to the document) at: David A.
Alonzo, Manager, Project Authorizations, 700 Louisiana Street, Suite
1300, Houston, Texas 77002-2700 at (832) 320-5477, or at
[email protected]. Any subsequent submissions by an intervenor
must be served on the applicant and all other parties to the
proceeding. Contact information for parties can be downloaded from the
service list at the eService link on FERC Online.
Tracking the Proceeding
Throughout the proceeding, additional information about the project
will be available from the Commission's Office of External Affairs, at
(866) 208-FERC, or on the FERC website at www.ferc.gov using the
``eLibrary'' link as described above. The eLibrary link also provides
access to the texts of all formal documents issued by the Commission,
such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. For more information and to register, go to
www.ferc.gov/docs-filing/esubscription.asp.
Dated: October 23, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-23798 Filed 10-26-23; 8:45 am]
BILLING CODE 6717-01-P