Notice of Institution of Section 206 Proceeding and Refund Effective Date, 73330 [2023-23577]
Download as PDF
73330
Federal Register / Vol. 88, No. 205 / Wednesday, October 25, 2023 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Institution of Section 206
Proceeding and Refund Effective Date
Docket Nos.
Blossburg Power, LLC .............
Brunot Island Power, LLC ........
Gilbert Power, LLC ...................
Hamilton Power, LLC ...............
Hunterstown Power, LLC .........
Mountain Power, LLC ...............
New Castle Power, LLC ...........
Orrtanna Power, LLC ...............
Portland Power, LLC ................
Sayreville Power, LLC ..............
Shawnee Power, LLC ..............
Shawville Power, LLC ..............
Titus Power, LLC ......................
Tolna Power, LLC ....................
Warren Generation, LLC ..........
EL23–107–000
EL23–108–000
EL23–109–000
EL23–110–000
EL23–111–000
EL23–112–000
EL23–113–000
EL23–114–000
EL23–115–000
EL23–116–000
EL23–117–000
EL23–118–000
EL23–119–000
EL23–120–000
EL23–121–000
lotter on DSK11XQN23PROD with NOTICES1
On October 6, 2023, the Commission
issued an order in Docket No. EL23–
107–000, et al., pursuant to section 206
of the Federal Power Act (FPA), 16
U.S.C. 824e, instituting an investigation
regarding the continued justness and
reasonableness of Heritage Reactive
Suppliers’ 1 Rate Schedules. Blossburg
Power, LLC, et al., 185 FERC ¶ 61,018
(2023).
The refund effective date in Docket
No. EL23–107–000, et al., established
pursuant to section 206(b) of the FPA,
will be the date of publication of this
notice in the Federal Register.
Any interested person desiring to be
heard in Docket No. EL23–107–000, et
al., must file a notice of intervention or
motion to intervene, as appropriate,
with the Federal Energy Regulatory
Commission, in accordance with Rule
214 of the Commission’s Rules of
Practice and Procedure, 18 CFR 385.214
(2022), within 21 days of the date of
issuance of the order.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
1 Heritage Reactive Suppliers include: Blossburg
Power, LLC; Brunot Island Power, LLC; Gilbert
Power, LLC; Hamilton Power, LLC; Hunterstown
Power, LLC; Mountain Power, LLC; New Castle
Power, LLC; Orrtanna Power, LLC; Portland Power,
LLC; Sayreville Power, LLC; Shawnee Power, LLC;
Shawville Power, LLC; Titus Power, LLC; Tolna
Power, LLC; and Warren Generation, LLC.
VerDate Sep<11>2014
17:01 Oct 24, 2023
Jkt 262001
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFile’’ link at https://www.ferc.gov.
In lieu of electronic filing, you may
submit a paper copy. Submissions sent
via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Dated: October 19, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–23577 Filed 10–24–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[P–1888–044]
York Haven Power Company, LLC;
Notice Of Application Accepted for
Filing and Soliciting Comments,
Motions To Intervene, and Protests
October 18, 2023.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Amendment
of license.
b. Project No.: 1888–044.
c. Dates Filed: June 20 and August 30,
2023.
d. Applicant: York Haven Power
Company, LLC.
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
e. Name of Project: York Haven
Hydroelectric Project.
f. Location: The project is located on
the Susquehanna River in York,
Lancaster, and Dauphin counties,
Pennsylvania.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Ms. Jody Smet,
York Haven Power Company, LLC c/o
Eagle Creek Renewable Energy, LLC,
7315 Wisconsin Avenue, Suite 1100W,
Bethesda, MD, 04462, (804) 382–1764.
i. FERC Contact: Mr. Steven Sachs,
(202) 502–8666, Steven.Sachs@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests is 30
days from the issuance of this notice by
the Commission. The Commission
strongly encourages electronic filing.
Please file comments, motions to
intervene, and protests using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/doc-sfiling/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, MD 20852. The first page of
any filing should include docket
number P–1888–044.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. Description of Request: The
applicant proposes to replace the
turbines and gearboxes for units 8 and
10. The proposal would not result in a
change to the hydraulic capacity of the
project but would increase the
authorized installed capacity by 350
kilowatts. The applicant does not
E:\FR\FM\25OCN1.SGM
25OCN1
Agencies
[Federal Register Volume 88, Number 205 (Wednesday, October 25, 2023)]
[Notices]
[Page 73330]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-23577]
[[Page 73330]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Institution of Section 206 Proceeding and Refund
Effective Date
------------------------------------------------------------------------
Docket Nos.
------------------------------------------------------------------------
Blossburg Power, LLC................... EL23-107-000
Brunot Island Power, LLC............... EL23-108-000
Gilbert Power, LLC..................... EL23-109-000
Hamilton Power, LLC.................... EL23-110-000
Hunterstown Power, LLC................. EL23-111-000
Mountain Power, LLC.................... EL23-112-000
New Castle Power, LLC.................. EL23-113-000
Orrtanna Power, LLC.................... EL23-114-000
Portland Power, LLC.................... EL23-115-000
Sayreville Power, LLC.................. EL23-116-000
Shawnee Power, LLC..................... EL23-117-000
Shawville Power, LLC................... EL23-118-000
Titus Power, LLC....................... EL23-119-000
Tolna Power, LLC....................... EL23-120-000
Warren Generation, LLC................. EL23-121-000
------------------------------------------------------------------------
On October 6, 2023, the Commission issued an order in Docket No.
EL23-107-000, et al., pursuant to section 206 of the Federal Power Act
(FPA), 16 U.S.C. 824e, instituting an investigation regarding the
continued justness and reasonableness of Heritage Reactive Suppliers'
\1\ Rate Schedules. Blossburg Power, LLC, et al., 185 FERC ] 61,018
(2023).
---------------------------------------------------------------------------
\1\ Heritage Reactive Suppliers include: Blossburg Power, LLC;
Brunot Island Power, LLC; Gilbert Power, LLC; Hamilton Power, LLC;
Hunterstown Power, LLC; Mountain Power, LLC; New Castle Power, LLC;
Orrtanna Power, LLC; Portland Power, LLC; Sayreville Power, LLC;
Shawnee Power, LLC; Shawville Power, LLC; Titus Power, LLC; Tolna
Power, LLC; and Warren Generation, LLC.
---------------------------------------------------------------------------
The refund effective date in Docket No. EL23-107-000, et al.,
established pursuant to section 206(b) of the FPA, will be the date of
publication of this notice in the Federal Register.
Any interested person desiring to be heard in Docket No. EL23-107-
000, et al., must file a notice of intervention or motion to intervene,
as appropriate, with the Federal Energy Regulatory Commission, in
accordance with Rule 214 of the Commission's Rules of Practice and
Procedure, 18 CFR 385.214 (2022), within 21 days of the date of
issuance of the order.
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (https://www.ferc.gov) using
the ``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to the Commission's Public
Reference Room, due to the proclamation declaring a National Emergency
concerning the Novel Coronavirus Disease (COVID-19), issued by the
President on March 13, 2020. For assistance, contact FERC at
[email protected] or call toll-free, (886) 208-3676 or TYY,
(202) 502-8659.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFile'' link at
https://www.ferc.gov. In lieu of electronic filing, you may submit a
paper copy. Submissions sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
Dated: October 19, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-23577 Filed 10-24-23; 8:45 am]