Carolina Gas Transmission, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline, 70963-70964 [2023-22698]

Download as PDF Federal Register / Vol. 88, No. 197 / Friday, October 13, 2023 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP23–549–000] lotter on DSK11XQN23PROD with NOTICES1 Carolina Gas Transmission, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline Take notice that on September 28, 2023, Carolina Gas Transmission, LLC (Carolina Gas), 121 Moore Hopkins Lane, Columbia, SC 29210, filed in the above referenced docket, a prior notice requests pursuant to sections 157.205(b) and 157.210 of the Commission’s regulations under the Natural Gas Act (NGA), and Carolina Gas’ blanket certificate issued in Docket No. CP06– 72–000, for authorization to construct and operate its Aiken Compressor Expansion Project (ACE Project) located in Aiken County, South Carolina. The proposed project will allow Carolina Gas to provide 73,000 dekatherms per day (Dth/d) of firm transportation service to three project customers. Specifically, the Project consists of a new compressor unit at the Southern Compressor Station of 6,248 nominal horsepower and ancillary equipment, and the replacement of approximately 0.33 miles of existing 16-inch-diameter natural gas pipeline. The estimated, cost for the project is $35,254,000, all as more fully set forth in the request which is on file with the Commission and open to public inspection. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room. For assistance, contact the Federal Energy Regulatory Commission at FercOnlineSupport@ ferc.gov or call toll-free, (886) 208–3676 or TTY (202) 502–8659. Any questions concerning this request should be directed to James Scribner, Regulatory Analyst, BHE GT&S, LLC, 10700 Energy Way, Glen Allen, VA 23060, or by phone at (804) 397–5113 or via email at James.scribner@bhegts.com. Public Participation There are three ways to become involved in the Commission’s review of this project: you can file a protest to the VerDate Sep<11>2014 16:55 Oct 12, 2023 Jkt 262001 project, you can file a motion to intervene in the proceeding, and you can file comments on the project. There is no fee or cost for filing protests, motions to intervene, or comments. The deadline for filing protests, motions to intervene, and comments is 5:00 p.m. Eastern Time on December 5, 2023. How to file protests, motions to intervene, and comments is explained below. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Protests Pursuant to section 157.205 of the Commission’s regulations under the NGA,1 any person 2 or the Commission’s staff may file a protest to the request. If no protest is filed within the time allowed or if a protest is filed and then withdrawn within 30 days after the allowed time for filing a protest, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request for authorization will be considered by the Commission. Protests must comply with the requirements specified in section 157.205(e) of the Commission’s regulations,3 and must be submitted by the protest deadline, which is December 5, 2023. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor. Interventions Any person has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission’s orders in the U.S. Circuit Courts of Appeal. To intervene, you must submit a motion to intervene to the Commission 1 18 CFR 157.205. include individuals, organizations, businesses, municipalities, and other entities. 18 CFR 385.102(d). 3 18 CFR 157.205(e). 2 Persons PO 00000 Frm 00044 Fmt 4703 Sfmt 4703 70963 in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure 4 and the regulations under the NGA 5 by the intervention deadline for the project, which is December 5, 2023. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https:// www.ferc.gov/resources/guides/how-to/ intervene.asp. All timely, unopposed motions to intervene are automatically granted by operation of Rule 214(c)(1). Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations. A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. Comments Any person wishing to comment on the project may do so. The Commission considers all comments received about the project in determining the appropriate action to be taken. To ensure that your comments are timely and properly recorded, please submit your comments on or before December 5, 2023. The filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. How To File Protests, Interventions, and Comments There are two ways to submit protests, motions to intervene, and comments. In both instances, please reference the Project docket number CP23–549–000 in your submission. (1) You may file your protest, motion to intervene, and comments by using the Commission’s eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. New eFiling 4 18 5 18 E:\FR\FM\13OCN1.SGM CFR 385.214. CFR 157.10. 13OCN1 70964 Federal Register / Vol. 88, No. 197 / Friday, October 13, 2023 / Notices lotter on DSK11XQN23PROD with NOTICES1 users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select ‘‘General’’ and then select ‘‘Protest’’, ‘‘Intervention’’, or ‘‘Comment on a Filing’’; or 6 (2) You can file a paper copy of your submission by mailing it to the address below. Your submission must reference the Project docket number CP23–549– 000. To file via USPS: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. To file via any other method: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The Commission encourages electronic filing of submissions (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. Protests and motions to intervene must be served on the applicant either by mail or email (with a link to the document) at: James Scribner, Regulatory Analyst, BHE GT&S, LLC, 10700 Energy Way, Glen Allen, VA 23060 or via email at James.scribner@ bhegts.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s Office of External Affairs, at (866) 208– FERC, or on the FERC website at www.ferc.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the 6 Additionally, you may file your comments electronically by using the eComment feature, which is located on the Commission’s website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project. VerDate Sep<11>2014 16:55 Oct 12, 2023 Jkt 262001 documents. For more information and to register, go to www.ferc.gov/docs-filing/ esubscription.asp. Dated: October 6, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–22698 Filed 10–12–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. DI22–5–000] Antelope Valley Water Storage LLC; Notice of Declaration of Intention and Soliciting Comments, Protests, and Motions To Intervene Take notice that the following application has been filed with the Commission and is available for public inspection: a. Application Type: Declaration of Intention. b. Docket No: DI22–5–000. c. Date Filed: February 16, 2022. d. Applicant: Antelope Valley Water Storage LLC. e. Name of Project: Antelope Valley Water Storage Aquifer Pumped Hydroelectric Project. f. Location: The proposed project would be located at the Antelope Valley Groundwater Basin in Rosamond, Kern County, California. g. Filed Pursuant to: Section 23(b)(1) of the Federal Power Act, 16 U.S.C. 817(b). h. Applicant Contact: Lon House; 10645 N Oracle, Ste. 121–216, Oro Valley, AZ 85704; telephone: (530) 409– 9702; email: lonwhouse@gmail.com. i. FERC Contact: Ashish Desai, (202) 502–8370, or Ashish.Desai@ferc.gov. j. Deadline for filing comments, protests, and motions to intervene is November 6, 2023. The Commission strongly encourages electronic filing. Please file comments, protests, and motions to intervene using the Commission’s eFiling at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be PO 00000 Frm 00045 Fmt 4703 Sfmt 4703 addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number DI22–5–000. Comments emailed to Commission staff are not considered part of the Commission record. k. Description of Project: The proposed Antelope Valley Water Storage Aquifer Pumped Hydroelectric Project would consist of: (1) a 600-foot-deep groundwater well; (2) a reversible pump/turbine rated at 150kW; (3) three flexible storage tanks connected by 12inch pipe; and (4) appurtenant facilities. When a Declaration of Intention is filed with the Federal Energy Regulatory Commission, the Federal Power Act requires the Commission to investigate and determine if the project would affect the interests of interstate or foreign commerce. l. Locations of the Application: This filing may be viewed on the Commission’s website at https:// www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, and .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Responsive Documents: All filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTESTS’’, and ‘‘MOTIONS TO E:\FR\FM\13OCN1.SGM 13OCN1

Agencies

[Federal Register Volume 88, Number 197 (Friday, October 13, 2023)]
[Notices]
[Pages 70963-70964]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-22698]



[[Page 70963]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP23-549-000]


Carolina Gas Transmission, LLC; Notice of Request Under Blanket 
Authorization and Establishing Intervention and Protest Deadline

    Take notice that on September 28, 2023, Carolina Gas Transmission, 
LLC (Carolina Gas), 121 Moore Hopkins Lane, Columbia, SC 29210, filed 
in the above referenced docket, a prior notice requests pursuant to 
sections 157.205(b) and 157.210 of the Commission's regulations under 
the Natural Gas Act (NGA), and Carolina Gas' blanket certificate issued 
in Docket No. CP06-72-000, for authorization to construct and operate 
its Aiken Compressor Expansion Project (ACE Project) located in Aiken 
County, South Carolina. The proposed project will allow Carolina Gas to 
provide 73,000 dekatherms per day (Dth/d) of firm transportation 
service to three project customers. Specifically, the Project consists 
of a new compressor unit at the Southern Compressor Station of 6,248 
nominal horsepower and ancillary equipment, and the replacement of 
approximately 0.33 miles of existing 16-inch-diameter natural gas 
pipeline. The estimated, cost for the project is $35,254,000, all as 
more fully set forth in the request which is on file with the 
Commission and open to public inspection.
    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (www.ferc.gov) using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to the Commission's Public 
Reference Room. For assistance, contact the Federal Energy Regulatory 
Commission at [email protected] or call toll-free, (886) 208-
3676 or TTY (202) 502-8659.
    Any questions concerning this request should be directed to James 
Scribner, Regulatory Analyst, BHE GT&S, LLC, 10700 Energy Way, Glen 
Allen, VA 23060, or by phone at (804) 397-5113 or via email at 
[email protected].

Public Participation

    There are three ways to become involved in the Commission's review 
of this project: you can file a protest to the project, you can file a 
motion to intervene in the proceeding, and you can file comments on the 
project. There is no fee or cost for filing protests, motions to 
intervene, or comments. The deadline for filing protests, motions to 
intervene, and comments is 5:00 p.m. Eastern Time on December 5, 2023. 
How to file protests, motions to intervene, and comments is explained 
below.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].

Protests

    Pursuant to section 157.205 of the Commission's regulations under 
the NGA,\1\ any person \2\ or the Commission's staff may file a protest 
to the request. If no protest is filed within the time allowed or if a 
protest is filed and then withdrawn within 30 days after the allowed 
time for filing a protest, the proposed activity shall be deemed to be 
authorized effective the day after the time allowed for protest. If a 
protest is filed and not withdrawn within 30 days after the time 
allowed for filing a protest, the instant request for authorization 
will be considered by the Commission.
---------------------------------------------------------------------------

    \1\ 18 CFR 157.205.
    \2\ Persons include individuals, organizations, businesses, 
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------

    Protests must comply with the requirements specified in section 
157.205(e) of the Commission's regulations,\3\ and must be submitted by 
the protest deadline, which is December 5, 2023. A protest may also 
serve as a motion to intervene so long as the protestor states it also 
seeks to be an intervenor.
---------------------------------------------------------------------------

    \3\ 18 CFR 157.205(e).
---------------------------------------------------------------------------

Interventions

    Any person has the option to file a motion to intervene in this 
proceeding. Only intervenors have the right to request rehearing of 
Commission orders issued in this proceeding and to subsequently 
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
    To intervene, you must submit a motion to intervene to the 
Commission in accordance with Rule 214 of the Commission's Rules of 
Practice and Procedure \4\ and the regulations under the NGA \5\ by the 
intervention deadline for the project, which is December 5, 2023. As 
described further in Rule 214, your motion to intervene must state, to 
the extent known, your position regarding the proceeding, as well as 
your interest in the proceeding. For an individual, this could include 
your status as a landowner, ratepayer, resident of an impacted 
community, or recreationist. You do not need to have property directly 
impacted by the project in order to intervene. For more information 
about motions to intervene, refer to the FERC website at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------

    \4\ 18 CFR 385.214.
    \5\ 18 CFR 157.10.
---------------------------------------------------------------------------

    All timely, unopposed motions to intervene are automatically 
granted by operation of Rule 214(c)(1). Motions to intervene that are 
filed after the intervention deadline are untimely and may be denied. 
Any late-filed motion to intervene must show good cause for being late 
and must explain why the time limitation should be waived and provide 
justification by reference to factors set forth in Rule 214(d) of the 
Commission's Rules and Regulations. A person obtaining party status 
will be placed on the service list maintained by the Secretary of the 
Commission and will receive copies (paper or electronic) of all 
documents filed by the applicant and by all other parties.

Comments

    Any person wishing to comment on the project may do so. The 
Commission considers all comments received about the project in 
determining the appropriate action to be taken. To ensure that your 
comments are timely and properly recorded, please submit your comments 
on or before December 5, 2023. The filing of a comment alone will not 
serve to make the filer a party to the proceeding. To become a party, 
you must intervene in the proceeding.

How To File Protests, Interventions, and Comments

    There are two ways to submit protests, motions to intervene, and 
comments. In both instances, please reference the Project docket number 
CP23-549-000 in your submission.
    (1) You may file your protest, motion to intervene, and comments by 
using the Commission's eFiling feature, which is located on the 
Commission's website (www.ferc.gov) under the link to Documents and 
Filings. New eFiling

[[Page 70964]]

users must first create an account by clicking on ``eRegister.'' You 
will be asked to select the type of filing you are making; first select 
``General'' and then select ``Protest'', ``Intervention'', or ``Comment 
on a Filing''; or \6\
---------------------------------------------------------------------------

    \6\ Additionally, you may file your comments electronically by 
using the eComment feature, which is located on the Commission's 
website at www.ferc.gov under the link to Documents and Filings. 
Using eComment is an easy method for interested persons to submit 
brief, text-only comments on a project.
---------------------------------------------------------------------------

    (2) You can file a paper copy of your submission by mailing it to 
the address below. Your submission must reference the Project docket 
number CP23-549-000.
    To file via USPS: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426.
    To file via any other method: Kimberly D. Bose, Secretary, Federal 
Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 
20852.
    The Commission encourages electronic filing of submissions (option 
1 above) and has eFiling staff available to assist you at (202) 502-
8258 or [email protected].
    Protests and motions to intervene must be served on the applicant 
either by mail or email (with a link to the document) at: James 
Scribner, Regulatory Analyst, BHE GT&S, LLC, 10700 Energy Way, Glen 
Allen, VA 23060 or via email at [email protected].
    Any subsequent submissions by an intervenor must be served on the 
applicant and all other parties to the proceeding. Contact information 
for parties can be downloaded from the service list at the eService 
link on FERC Online.

Tracking the Proceeding

    Throughout the proceeding, additional information about the project 
will be available from the Commission's Office of External Affairs, at 
(866) 208-FERC, or on the FERC website at www.ferc.gov using the 
``eLibrary'' link as described above. The eLibrary link also provides 
access to the texts of all formal documents issued by the Commission, 
such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. For more information and to register, go to 
www.ferc.gov/docs-filing/esubscription.asp.

    Dated: October 6, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-22698 Filed 10-12-23; 8:45 am]