Federal Register / Vol. 88, No. 196 / Thursday, October 12, 2023 / Notices
within 90 days of the date of issuance
of the Commission staff’s environmental
document for the Project.
This notice identifies Commission
staff’s intention to prepare an
environmental assessment (EA) for the
Project and the planned schedule for the
completion of the environmental
review.1
Schedule for Environmental Review
Issuance of EA—March 1, 2024
90-day Federal Authorization Decision
Deadline 2—May 30, 2024
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Project Description
The Oak Grove Enhancement Project
would consist of the following facilities:
• Installation of 34.1 miles of new 30inch-diameter segment of natural gas
pipeline, which will begin at ANR’s
existing Delhi Compressor Station (CS)
in Richland Parish, Louisiana and
primarily parallel the existing Line 0–
501, 1–501, and 2–501 pipelines before
the new segment ties into the existing
route just south of State Route 586 in
West Carroll Parish, Louisiana at the
terminus of the existing Line 0–501
segment to be abandoned.
• Abandonment in place and by
removal of 33.6 miles of existing 30inch-diameter natural gas pipeline,
which begins at ANR’s existing Delhi CS
in Richland Parish and terminates just
south of State Route 586 in West Carroll
Parish. Approximately one percent (0.25
mile) of the existing Line 0–501 segment
would be abandoned by removal, while
the remaining existing pipeline
segments (totaling 33.35 miles) would
be abandoned in place.
The Oak Grove Enhancement Project
would not increase or reduce service to
any existing ANR customer and no
changes to system capacity are
proposed. ANR’s Project design would
allow the existing segment to remain in
operation until the replacement pipeline
is placed into service.
ddrumheller on DSK120RN23PROD with NOTICES1
Background
On August 23, 2023, the Commission
issued a Notice of Scoping Period
Requesting Comments on
1 40
CFR 1501.10 (2020).
Commission’s deadline applies to the
decisions of other federal agencies, and state
agencies acting under federally delegated authority,
that are responsible for federal authorizations,
permits, and other approvals necessary for
proposed projects under the Natural Gas Act. Per
18 CFR 157.22(a), the Commission’s deadline for
other agency’s decisions applies unless a schedule
is otherwise established by federal law.
2 The
VerDate Sep<11>2014
17:34 Oct 11, 2023
Jkt 262001
Environmental Issues for the Proposed
Oak Grove Enhancement Project (Notice
of Scoping). The Notice of Scoping was
sent to affected landowners; federal,
state, and local government agencies;
elected officials; environmental and
public interest groups; Native American
tribes; other interested parties; and local
libraries and newspapers. In response to
the Notice of Scoping, the Commission
received one comment from the
Louisiana Department of Wildlife and
Fisheries regarding impacts on wildlife
habitats. All substantive comments will
be addressed in the EA.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
service provides automatic notification
of filings made to subscribed dockets,
document summaries, and direct links
to the documents. Go to https://
www.ferc.gov/ferc-online/overview to
register for eSubscription.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP23–523), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: October 4, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–22481 Filed 10–11–23; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
FEDERAL ELECTION COMMISSION
Sunshine Act Meetings
Tuesday, October 17,
2023 at 10:30 a.m. and its continuation
at the conclusion of the open meeting
on October 19, 2023.
PLACE: 1050 First Street NE,
Washington, DC and virtual (this
meeting will be a hybrid meeting).
STATUS: This meeting will be closed to
the public.
MATTERS TO BE CONSIDERED: Compliance
matters pursuant to 52 U.S.C. 30109.
Investigatory records compiled for
law enforcement purposes and
production would disclose investigative
techniques.
Information the premature disclosure
of which would be likely to have a
considerable adverse effect on the
implementation of a proposed
Commission action.
Matters concerning participation in
civil actions or proceedings or
arbitration.
CONTACT PERSON FOR MORE INFORMATION:
Judith Ingram, Press Officer, Telephone:
(202) 694–1220.
TIME AND DATE:
(Authority: Government in the Sunshine Act,
5 U.S.C. 552b)
Vicktoria J. Allen,
Deputy Secretary of the Commission.
[FR Doc. 2023–22685 Filed 10–10–23; 4:15 pm]
BILLING CODE 6715–01–P
FEDERAL RESERVE SYSTEM
Change in Bank Control Notices;
Acquisitions of Shares of a Bank or
Bank Holding Company
The notificants listed below have
applied under the Change in Bank
Control Act (Act) (12 U.S.C. 1817(j)) and
§ 225.41 of the Board’s Regulation Y (12
CFR 225.41) to acquire shares of a bank
or bank holding company. The factors
that are considered in acting on the
applications are set forth in paragraph 7
of the Act (12 U.S.C. 1817(j)(7)).
The public portions of the
applications listed below, as well as
other related filings required by the
Board, if any, are available for
immediate inspection at the Federal
Reserve Bank(s) indicated below and at
the offices of the Board of Governors.
This information may also be obtained
on an expedited basis, upon request, by
contacting the appropriate Federal
Reserve Bank and from the Board’s
Freedom of Information Office at
https://www.federalreserve.gov/foia/
request.htm. Interested persons may
express their views in writing on the
E:\FR\FM\12OCN1.SGM
12OCN1
Agencies
[Federal Register Volume 88, Number 196 (Thursday, October 12, 2023)]
[Notices]
[Page 70660]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-22685]
=======================================================================
-----------------------------------------------------------------------
FEDERAL ELECTION COMMISSION
Sunshine Act Meetings
TIME AND DATE: Tuesday, October 17, 2023 at 10:30 a.m. and its
continuation at the conclusion of the open meeting on October 19, 2023.
PLACE: 1050 First Street NE, Washington, DC and virtual (this meeting
will be a hybrid meeting).
STATUS: This meeting will be closed to the public.
MATTERS TO BE CONSIDERED: Compliance matters pursuant to 52 U.S.C.
30109.
Investigatory records compiled for law enforcement purposes and
production would disclose investigative techniques.
Information the premature disclosure of which would be likely to
have a considerable adverse effect on the implementation of a proposed
Commission action.
Matters concerning participation in civil actions or proceedings or
arbitration.
CONTACT PERSON FOR MORE INFORMATION: Judith Ingram, Press Officer,
Telephone: (202) 694-1220.
(Authority: Government in the Sunshine Act, 5 U.S.C. 552b)
Vicktoria J. Allen,
Deputy Secretary of the Commission.
[FR Doc. 2023-22685 Filed 10-10-23; 4:15 pm]
BILLING CODE 6715-01-P