Download as PDF ddrumheller on DSK120RN23PROD with NOTICES1 Federal Register / Vol. 88, No. 196 / Thursday, October 12, 2023 / Notices Comment Date: 5 p.m. ET 10/25/23. Docket Numbers: ER24–20–000. Applicants: Cottontail Solar 2, LLC. Description: Baseline eTariff Filing: Reactive Power Compensation Baseline to be effective 12/4/2023. Filed Date: 10/4/23. Accession Number: 20231004–5069. Comment Date: 5 p.m. ET 10/25/23. Docket Numbers: ER24–21–000. Applicants: Cottontail Solar 8, LLC. Description: Baseline eTariff Filing: Reactive Power Compensation Baseline to be effective 12/15/2023. Filed Date: 10/4/23. Accession Number: 20231004–5078. Comment Date: 5 p.m. ET 10/25/23. Docket Numbers: ER24–22–000. Applicants: Pennsylvania Electric Company, PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Pennsylvania Electric Company submits tariff filing per 35.13(a)(2)(iii: Penelec Amends 10 ECSAs (6053 6137 6138 6141 6148 6287 6288 6289 6294 6295) to be effective 12/31/9998. Filed Date: 10/4/23. Accession Number: 20231004–5091. Comment Date: 5 p.m. ET 10/25/23. Docket Numbers: ER24–23–000. Applicants: Florida Power & Light Company. Description: § 205(d) Rate Filing: FPL OATT Attachment M (LGIP) Appendix 7 Standard (LGIA) Preamble and Recitals to be effective 12/4/2023. Filed Date: 10/4/23. Accession Number: 20231004–5114. Comment Date: 5 p.m. ET 10/25/23. Docket Numbers: ER24–24–000. Applicants: ISO New England Inc., Versant Power. Description: § 205(d) Rate Filing: ISO New England Inc. submits tariff filing per 35.13(a)(2)(iii: ISO–NE/Versant Power; Local Service Agreement LSA/ ISONE/VERSANT–23–01 to be effective 12/2/2022. Filed Date: 10/4/23. Accession Number: 20231004–5118. Comment Date: 5 p.m. ET 10/25/23. Docket Numbers: ER24–25–000. Applicants: Northern States Power Company, a Minnesota corporation. Description: § 205(d) Rate Filing: 2023–10–5 GRE Century Sub-FSA 743– NSP to be effective 10/5/2023. Filed Date: 10/4/23. Accession Number: 20231004–5126. Comment Date: 5 p.m. ET 10/25/23. Docket Numbers: ER24–26–000. Applicants: East Point Energy Center, LLC. Description: Baseline eTariff Filing: East Point Energy Center, LLC Application for Market-Based Rate Authorization to be effective 12/4/2023. VerDate Sep<11>2014 17:34 Oct 11, 2023 Jkt 262001 Filed Date: 10/4/23. Accession Number: 20231004–5131. Comment Date: 5 p.m. ET 10/25/23. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: October 4, 2023. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2023–22471 Filed 10–11–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 4334–017] EONY Generation Limited; Notice of Waiver Period for Water Quality Certification Application On September 29, 2023, EONY Generation Limited submitted to the Federal Energy Regulatory Commission (Commission) a copy of its application for a Clean Water Act section 401(a)(1) water quality certification filed with New York State Department of Environmental Conservation (New York DEC), in conjunction with the above PO 00000 Frm 00022 Fmt 4703 Sfmt 4703 70659 captioned project. Pursuant to 40 CFR 121.6 and section 4.34(b)(5) of the Commission’s regulations,1 we hereby notify the New York DEC of the following: Date of Receipt of the Certification Request: September 26, 2023. Reasonable Period of Time to Act on the Certification Request: One year (September 26, 2024). If New York DEC fails or refuses to act on the water quality certification request on or before the above date, then the agency certifying authority is deemed waived pursuant to section 401(a)(1) of the Clean Water Act, 33 U.S.C. 1341(a)(1). Dated: October 4, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–22478 Filed 10–11–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP23–523–000] ANR Pipeline Company; Notice of Schedule for the Preparation of an Environmental Assessment for the Oak Grove Enhancement Project On August 1, 2023, ANR Pipeline Company (ANR) filed an application in Docket No. CP23–523–000 requesting a Certificate of Public Convenience and Necessity pursuant to section 7(c) and Authorization pursuant to section 7(b) of the Natural Gas Act to construct, operate, and abandon certain natural gas pipeline facilities. The proposed project is known as the Oak Grove Enhancement Project (Project). The Project would include construction of 34.1 miles of new 30-inch-diameter natural gas pipeline to replace 33.6 miles of existing 30-inch-diameter natural gas pipeline in Richland and West Carroll Parishes, Louisiana. According to ANR, its project would improve the integrity and reliability of ANR’s system by replacing vintage pipeline facilities installed in the 1950’s with new pipeline facilities. On August 11, 2023, the Federal Energy Regulatory Commission (Commission or FERC) issued its Notice of Application for the Project. Among other things, that notice alerted agencies issuing federal authorizations of the requirement to complete all necessary reviews and to reach a final decision on a request for a federal authorization 1 18 E:\FR\FM\12OCN1.SGM CFR 4.34(b)(5). 12OCN1

Agencies

[Federal Register Volume 88, Number 196 (Thursday, October 12, 2023)]
[Notices]
[Page 70659]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-22478]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 4334-017]


EONY Generation Limited; Notice of Waiver Period for Water 
Quality Certification Application

    On September 29, 2023, EONY Generation Limited submitted to the 
Federal Energy Regulatory Commission (Commission) a copy of its 
application for a Clean Water Act section 401(a)(1) water quality 
certification filed with New York State Department of Environmental 
Conservation (New York DEC), in conjunction with the above captioned 
project. Pursuant to 40 CFR 121.6 and section 4.34(b)(5) of the 
Commission's regulations,\1\ we hereby notify the New York DEC of the 
following:
---------------------------------------------------------------------------

    \1\ 18 CFR 4.34(b)(5).
---------------------------------------------------------------------------

    Date of Receipt of the Certification Request: September 26, 2023.
    Reasonable Period of Time to Act on the Certification Request: One 
year (September 26, 2024).
    If New York DEC fails or refuses to act on the water quality 
certification request on or before the above date, then the agency 
certifying authority is deemed waived pursuant to section 401(a)(1) of 
the Clean Water Act, 33 U.S.C. 1341(a)(1).

    Dated: October 4, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-22478 Filed 10-11-23; 8:45 am]
BILLING CODE 6717-01-P