Golden Triangle Storage, L.L.C.; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Golden Triangle Storage Expansion Project, 66439-66441 [2023-21095]
Download as PDF
Federal Register / Vol. 88, No. 186 / Wednesday, September 27, 2023 / Notices
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
The application will be processed
according to the following schedule.
Revisions to the schedule may be made
as appropriate.
Milestone
Commission issues
draft EA.
Comments on draft
EA.
Commission issues
final EA.
Target date
March 2024.
April 2024.
July 2024.1
1 The Council on Environmental Quality’s
(CEQ)
regulations
under
40
CFR
1501.10(b)(1) (2022) require that EAs be completed within 1 year of the Federal action
agency’s decision to prepare an EA. See National Environmental Policy Act, 42 U.S.C.
4321 et seq., as amended by section
107(g)(1)(B)(iii) of the Fiscal Responsibility Act
of 2023, Public Law 118–5, 4336a, 137 Stat.
42.
Any questions regarding this notice
may be directed to Ingrid Brofman at
(202) 502–8347, or Ingrid.brofman@
ferc.gov.
Dated: September 20, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–21048 Filed 9–26–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
ddrumheller on DSK120RN23PROD with NOTICES1
Combined Notice of Filings #1
Docket Numbers: EG23–300–000.
Applicants: Proxima Solar, LLC.
Description: Proxima Solar, LLC
submits Notice of Self-Certification of
Exempt Wholesale Generator Status.
Filed Date: 9/19/23.
Accession Number: 20230919–5131.
Comment Date: 5 p.m. ET 10/10/23.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER23–2889–000.
Applicants: Bayou Galion Solar
Project, LLC.
Description: Request for Limited and
Prospective Tariff Waiver, et al. of
Bayou Galion Solar Project, LLC.
Filed Date: 9/19/23.
Accession Number: 20230919–5055.
Comment Date: 5 p.m. ET 10/10/23.
Docket Numbers: ER23–2897–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Amendment to ISA, Service Agreement
No. 6725; Queue No. AE2–117 to be
effective 11/20/2023.
VerDate Sep<11>2014
19:58 Sep 26, 2023
Jkt 259001
Filed Date: 9/21/23.
Accession Number: 20230921–5017.
Comment Date: 5 p.m. ET 10/12/23.
Docket Numbers: ER23–2898–000.
Applicants: PJM Interconnection,
L.L.C.
Description: Tariff Amendment:
Notice of Cancellation of NSA, Service
Agreement No. 6266; Queue No. AB2–
175 to be effective 11/20/2023.
Filed Date: 9/21/23.
Accession Number: 20230921–5032.
Comment Date: 5 p.m. ET 10/12/23.
Docket Numbers: ER23–2899–000.
Applicants: MS Solar 6, LLC.
Description: Baseline eTariff Filing:
MS Solar 6, LLC MBR Application
Filing to be effective 10/15/2023.
Filed Date: 9/21/23.
Accession Number: 20230921–5036.
Comment Date: 5 p.m. ET 10/12/23.
Docket Numbers: ER23–2900–000.
Applicants: Southern California
Edison Company.
Description: Tariff Amendment:
Termination Kramer Junction 6
TOT695/Kramer Junction 7 TOT696Q
LGIAs to be effective 11/21/2023.
Filed Date: 9/21/23.
Accession Number: 20230921–5052.
Comment Date: 5 p.m. ET 10/12/23.
Docket Numbers: ER23–2901–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Amendment to WMPA, Service
Agreement No. 5729; Queue No. AF1–
021 to be effective 11/20/2023.
Filed Date: 9/21/23.
Accession Number: 20230921–5097.
Comment Date: 5 p.m. ET 10/12/23.
Docket Numbers: ER23–2902–000.
Applicants: Tri-State Generation and
Transmission Association, Inc.
Description: § 205(d) Rate Filing:
Amendment to Rate Schedule FERC No.
6 to be effective 11/20/2023.
Filed Date: 9/21/23.
Accession Number: 20230921–5105.
Comment Date: 5 p.m. ET 10/12/23.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene, to
protest, or to answer a complaint in any
of the above proceedings must file in
accordance with Rules 211, 214, or 206
of the Commission’s Regulations (18
CFR 385.211, 385.214, or 385.206) on or
before 5:00 p.m. Eastern time on the
specified comment date. Protests may be
considered, but intervention is
necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed
information relating to filing
PO 00000
Frm 00079
Fmt 4703
Sfmt 4703
66439
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Dated: September 21, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–21097 Filed 9–26–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP23–542–000]
Golden Triangle Storage, L.L.C.; Notice
of Scoping Period Requesting
Comments on Environmental Issues
for the Proposed Golden Triangle
Storage Expansion Project
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental document, that will
discuss the environmental impacts of
the Golden Triangle Storage Expansion
Project involving construction and
operation of facilities by Golden
Triangle Storage, L.L.C. (GTS) in
Jefferson County, Texas. The
Commission will use this environmental
document in its decision-making
process to determine whether the
project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies regarding the
project. As part of the National
Environmental Policy Act (NEPA)
review process, the Commission takes
into account concerns the public may
have about proposals and the
environmental impacts that could result
from its action whenever it considers
the issuance of a Certificate of Public
Convenience and Necessity. This
E:\FR\FM\27SEN1.SGM
27SEN1
ddrumheller on DSK120RN23PROD with NOTICES1
66440
Federal Register / Vol. 88, No. 186 / Wednesday, September 27, 2023 / Notices
gathering of public input is referred to
as ‘‘scoping.’’ The main goal of the
scoping process is to focus the analysis
in the environmental document on the
important environmental issues.
Additional information about the
Commission’s NEPA process is
described below in the NEPA Process
and the Environmental Document
section of this notice.
By this notice, the Commission
requests public comments on the scope
of issues to address in the
environmental document. To ensure
that your comments are timely and
properly recorded, please submit your
comments so that the Commission
receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on
October 20, 2023. Comments may be
submitted in written form. Further
details on how to submit comments are
provided in the Public Participation
section of this notice.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
Your input will help the Commission
staff determine what issues they need to
evaluate in the environmental
document. Commission staff will
consider all written comments during
the preparation of the environmental
document.
If you submitted comments on this
project to the Commission before the
opening of this docket on September 12,
2023, you will need to file those
comments in Docket No. CP23–542–000
to ensure they are considered as part of
this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
easement agreement. You are not
required to enter into an agreement.
However, if the Commission approves
the project, the Natural Gas Act conveys
the right of eminent domain to the
company. Therefore, if you and the
company do not reach an easement
agreement, the pipeline company could
initiate condemnation proceedings in
court. In such instances, compensation
would be determined by a judge in
accordance with State law. The
Commission does not subsequently
VerDate Sep<11>2014
18:44 Sep 26, 2023
Jkt 259001
grant, exercise, or oversee the exercise
of that eminent domain authority. The
courts have exclusive authority to
handle eminent domain cases; the
Commission has no jurisdiction over
these matters.
GTS provided landowners with a fact
sheet prepared by the FERC entitled
‘‘An Interstate Natural Gas Facility On
My Land? What Do I Need To Know?’’
which addresses typically asked
questions, including the use of eminent
domain and how to participate in the
Commission’s proceedings. This fact
sheet along with other landowner topics
of interest are available for viewing on
the FERC website (www.ferc.gov) under
the Natural Gas, Landowner Topics link.
Public Participation
There are three methods you can use
to submit your comments to the
Commission. Please carefully follow
these instructions so that your
comments are properly recorded. The
Commission encourages electronic filing
of comments and has staff available to
assist you at (866) 208–3676 or
FercOnlineSupport@ferc.gov.
(1) You can file your comments
electronically using the eComment
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. Using
eComment is an easy method for
submitting brief, text-only comments on
a project;
(2) You can file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. With
eFiling, you can provide comments in a
variety of formats by attaching them as
a file with your submission. New
eFiling users must first create an
account by clicking on ‘‘eRegister.’’ You
will be asked to select the type of filing
you are making; a comment on a
particular project is considered a
‘‘Comment on a Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
Commission. Be sure to reference the
project docket number (CP23–542–000)
on your letter. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852.
Additionally, the Commission offers a
free service called eSubscription which
makes it easy to stay informed of all
PO 00000
Frm 00080
Fmt 4703
Sfmt 4703
issuances and submittals regarding the
dockets/projects to which you
subscribe. These instant email
notifications are the fastest way to
receive notification and provide a link
to the document files which can reduce
the amount of time you spend
researching proceedings. Go to https://
www.ferc.gov/ferc-online/overview to
register for eSubscription.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Summary of the Proposed Project
GTS proposes to construct and
operate two underground natural gas
storage caverns, six compressor units, a
new brine disposal well and brine
pipeline, and appurtenant facilities, in
Jefferson County, Texas. The Golden
Triangle Storage Expansion Project
would add about 14.4 billion cubic feet
of natural gas storage capacity to the
existing storage facilities.
The Golden Triangle Storage
Expansion Project would consist of the
following activities:
• developing and operating two new
salt dome natural gas storage caverns;
• constructing and operating
appurtenant facilities related to the two
storage caverns;
• constructing and operating a brine
disposal well and brine disposal
pipeline;
• constructing and operating six new
compressor units and appurtenances;
and
• constructing and operating two new
service corridors and three new
permanent access roads.
The general location of the project
facilities is shown in Appendix 1.1
Land Requirements for Construction
Construction of the proposed facilities
would temporarily disturb about 31
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of the
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’. For instructions on
connecting to eLibrary, refer to the last page of this
notice. At this time, the Commission has suspended
access to the Commission’s Public Reference Room.
For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll free, (886)
208–3676 or TTY (202) 502–8659.
E:\FR\FM\27SEN1.SGM
27SEN1
Federal Register / Vol. 88, No. 186 / Wednesday, September 27, 2023 / Notices
acres of land. Following construction,
GTS would maintain about 5.2 acres for
permanent operation of the project’s
facilities; the remaining acreage would
be restored and revert to former uses.
About 81 percent of the proposed
construction would occur within GTS’
existing Central Storage Site.
ddrumheller on DSK120RN23PROD with NOTICES1
NEPA Process and the Environmental
Document
Any environmental document issued
by the Commission will discuss impacts
that could occur as a result of the
construction and operation of the
proposed project under the relevant
general resource areas:
• geology and soils;
• water resources and wetlands;
• vegetation and wildlife;
• threatened and endangered species;
• cultural resources;
• land use;
• environmental justice;
• air quality and noise; and
• reliability and safety.
Commission staff will also evaluate
reasonable alternatives to the proposed
project or portions of the project and
make recommendations on how to
lessen or avoid impacts on the various
resource areas. Your comments will
help Commission staff identify and
focus on the issues that might have an
effect on the human environment and
potentially eliminate others from further
study and discussion in the
environmental document.
Following this scoping period,
Commission staff will determine
whether to prepare an Environmental
Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the
EIS will present Commission staff’s
independent analysis of the issues. If
Commission staff prepares an EA, a
Notice of Schedule for the Preparation
of an Environmental Assessment will be
issued. The EA may be issued for an
allotted public comment period. The
Commission would consider timely
comments on the EA before making its
decision regarding the proposed project.
If Commission staff prepares an EIS, a
Notice of Intent to Prepare an EIS/
Notice of Schedule will be issued,
which will open up an additional
comment period. Staff will then prepare
a draft EIS which will be issued for
public comment. Commission staff will
consider all timely comments received
during the comment period on the draft
EIS and revise the document, as
necessary, before issuing a final EIS.
Any EA or draft and final EIS will be
available in electronic format in the
VerDate Sep<11>2014
18:44 Sep 26, 2023
Jkt 259001
public record through eLibrary 2 and the
Commission’s natural gas
environmental documents web page
(https://www.ferc.gov/industries-data/
natural-gas/environment/
environmental-documents). If
eSubscribed, you will receive instant
email notification when the
environmental document is issued.
With this notice, the Commission is
asking agencies with jurisdiction by law
and/or special expertise with respect to
the environmental issues of this project
to formally cooperate in the preparation
of the environmental document.3
Agencies that would like to request
cooperating agency status should follow
the instructions for filing comments
provided under the Public Participation
section of this notice.
Consultation Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, the Commission is
using this notice to initiate consultation
with the applicable State Historic
Preservation Office(s), and to solicit
their views and those of other
government agencies, interested Indian
tribes, and the public on the project’s
potential effects on historic properties.4
The environmental document for this
project will document findings on the
impacts on historic properties and
summarize the status of consultations
under section 106.
Environmental Mailing List
The environmental mailing list
includes Federal, State, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
2 For
instructions on connecting to eLibrary, refer
to the last page of this notice.
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at title 40, Code of Federal
Regulations, section 1501.8.
4 The Advisory Council on Historic Preservation’s
regulations are at title 36, Code of Federal
Regulations, part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
PO 00000
Frm 00081
Fmt 4703
Sfmt 4703
66441
facilities, and anyone who submits
comments on the project and includes a
mailing address with their comments.
Commission staff will update the
environmental mailing list as the
analysis proceeds to ensure that
Commission notices related to this
environmental review are sent to all
individuals, organizations, and
government entities interested in and/or
potentially affected by the proposed
project.
If you need to make changes to your
name/address, or if you would like to
remove your name from the mailing list,
please complete one of the following
steps:
(1) Send an email to
GasProjectAddressChange@ferc.gov
stating your request. You must include
the docket number CP23–542–000 in
your request. If you are requesting a
change to your address, please be sure
to include your name and the correct
address. If you are requesting to delete
your address from the mailing list,
please include your name and address
as it appeared on this notice. This email
address is unable to accept comments.
OR
(2) Return the attached ‘‘Mailing List
Update Form’’ (Appendix 2).
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website at www.ferc.gov using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number in the ‘‘Docket Number’’
field. Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or (866)
208–3676, or for TTY, contact (202)
502–8659. The eLibrary link also
provides access to the texts of all formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
Public sessions or site visits will be
posted on the Commission’s calendar
located at https://www.ferc.gov/newsevents/events along with other related
information.
Dated: September 21, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–21095 Filed 9–26–23; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\27SEN1.SGM
27SEN1
Agencies
[Federal Register Volume 88, Number 186 (Wednesday, September 27, 2023)]
[Notices]
[Pages 66439-66441]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-21095]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP23-542-000]
Golden Triangle Storage, L.L.C.; Notice of Scoping Period
Requesting Comments on Environmental Issues for the Proposed Golden
Triangle Storage Expansion Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental document, that will discuss
the environmental impacts of the Golden Triangle Storage Expansion
Project involving construction and operation of facilities by Golden
Triangle Storage, L.L.C. (GTS) in Jefferson County, Texas. The
Commission will use this environmental document in its decision-making
process to determine whether the project is in the public convenience
and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies regarding the project. As part of the National Environmental
Policy Act (NEPA) review process, the Commission takes into account
concerns the public may have about proposals and the environmental
impacts that could result from its action whenever it considers the
issuance of a Certificate of Public Convenience and Necessity. This
[[Page 66440]]
gathering of public input is referred to as ``scoping.'' The main goal
of the scoping process is to focus the analysis in the environmental
document on the important environmental issues. Additional information
about the Commission's NEPA process is described below in the NEPA
Process and the Environmental Document section of this notice.
By this notice, the Commission requests public comments on the
scope of issues to address in the environmental document. To ensure
that your comments are timely and properly recorded, please submit your
comments so that the Commission receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on October 20, 2023. Comments may be
submitted in written form. Further details on how to submit comments
are provided in the Public Participation section of this notice.
Your comments should focus on the potential environmental effects,
reasonable alternatives, and measures to avoid or lessen environmental
impacts. Your input will help the Commission staff determine what
issues they need to evaluate in the environmental document. Commission
staff will consider all written comments during the preparation of the
environmental document.
If you submitted comments on this project to the Commission before
the opening of this docket on September 12, 2023, you will need to file
those comments in Docket No. CP23-542-000 to ensure they are considered
as part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable easement agreement. You
are not required to enter into an agreement. However, if the Commission
approves the project, the Natural Gas Act conveys the right of eminent
domain to the company. Therefore, if you and the company do not reach
an easement agreement, the pipeline company could initiate condemnation
proceedings in court. In such instances, compensation would be
determined by a judge in accordance with State law. The Commission does
not subsequently grant, exercise, or oversee the exercise of that
eminent domain authority. The courts have exclusive authority to handle
eminent domain cases; the Commission has no jurisdiction over these
matters.
GTS provided landowners with a fact sheet prepared by the FERC
entitled ``An Interstate Natural Gas Facility On My Land? What Do I
Need To Know?'' which addresses typically asked questions, including
the use of eminent domain and how to participate in the Commission's
proceedings. This fact sheet along with other landowner topics of
interest are available for viewing on the FERC website (www.ferc.gov)
under the Natural Gas, Landowner Topics link.
Public Participation
There are three methods you can use to submit your comments to the
Commission. Please carefully follow these instructions so that your
comments are properly recorded. The Commission encourages electronic
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected].
(1) You can file your comments electronically using the eComment
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. Using eComment is an easy method for
submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. With eFiling, you can provide comments
in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making; a comment on a particular project is considered a ``Comment
on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the project docket number (CP23-
542-000) on your letter. Submissions sent via the U.S. Postal Service
must be addressed to: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC
20426. Submissions sent via any other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission,
12225 Wilkins Avenue, Rockville, Maryland 20852.
Additionally, the Commission offers a free service called
eSubscription which makes it easy to stay informed of all issuances and
submittals regarding the dockets/projects to which you subscribe. These
instant email notifications are the fastest way to receive notification
and provide a link to the document files which can reduce the amount of
time you spend researching proceedings. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
Summary of the Proposed Project
GTS proposes to construct and operate two underground natural gas
storage caverns, six compressor units, a new brine disposal well and
brine pipeline, and appurtenant facilities, in Jefferson County, Texas.
The Golden Triangle Storage Expansion Project would add about 14.4
billion cubic feet of natural gas storage capacity to the existing
storage facilities.
The Golden Triangle Storage Expansion Project would consist of the
following activities:
developing and operating two new salt dome natural gas
storage caverns;
constructing and operating appurtenant facilities related
to the two storage caverns;
constructing and operating a brine disposal well and brine
disposal pipeline;
constructing and operating six new compressor units and
appurtenances; and
constructing and operating two new service corridors and
three new permanent access roads.
The general location of the project facilities is shown in Appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
www.ferc.gov using the link called ``eLibrary''. For instructions on
connecting to eLibrary, refer to the last page of this notice. At
this time, the Commission has suspended access to the Commission's
Public Reference Room. For assistance, contact FERC at
[email protected] or call toll free, (886) 208-3676 or TTY
(202) 502-8659.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would temporarily disturb
about 31
[[Page 66441]]
acres of land. Following construction, GTS would maintain about 5.2
acres for permanent operation of the project's facilities; the
remaining acreage would be restored and revert to former uses. About 81
percent of the proposed construction would occur within GTS' existing
Central Storage Site.
NEPA Process and the Environmental Document
Any environmental document issued by the Commission will discuss
impacts that could occur as a result of the construction and operation
of the proposed project under the relevant general resource areas:
geology and soils;
water resources and wetlands;
vegetation and wildlife;
threatened and endangered species;
cultural resources;
land use;
environmental justice;
air quality and noise; and
reliability and safety.
Commission staff will also evaluate reasonable alternatives to the
proposed project or portions of the project and make recommendations on
how to lessen or avoid impacts on the various resource areas. Your
comments will help Commission staff identify and focus on the issues
that might have an effect on the human environment and potentially
eliminate others from further study and discussion in the environmental
document.
Following this scoping period, Commission staff will determine
whether to prepare an Environmental Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the EIS will present Commission
staff's independent analysis of the issues. If Commission staff
prepares an EA, a Notice of Schedule for the Preparation of an
Environmental Assessment will be issued. The EA may be issued for an
allotted public comment period. The Commission would consider timely
comments on the EA before making its decision regarding the proposed
project. If Commission staff prepares an EIS, a Notice of Intent to
Prepare an EIS/Notice of Schedule will be issued, which will open up an
additional comment period. Staff will then prepare a draft EIS which
will be issued for public comment. Commission staff will consider all
timely comments received during the comment period on the draft EIS and
revise the document, as necessary, before issuing a final EIS. Any EA
or draft and final EIS will be available in electronic format in the
public record through eLibrary \2\ and the Commission's natural gas
environmental documents web page (https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents). If eSubscribed, you
will receive instant email notification when the environmental document
is issued.
---------------------------------------------------------------------------
\2\ For instructions on connecting to eLibrary, refer to the
last page of this notice.
---------------------------------------------------------------------------
With this notice, the Commission is asking agencies with
jurisdiction by law and/or special expertise with respect to the
environmental issues of this project to formally cooperate in the
preparation of the environmental document.\3\ Agencies that would like
to request cooperating agency status should follow the instructions for
filing comments provided under the Public Participation section of this
notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at title 40, Code of Federal
Regulations, section 1501.8.
---------------------------------------------------------------------------
Consultation Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, the Commission is using this notice to initiate
consultation with the applicable State Historic Preservation Office(s),
and to solicit their views and those of other government agencies,
interested Indian tribes, and the public on the project's potential
effects on historic properties.\4\ The environmental document for this
project will document findings on the impacts on historic properties
and summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at title 36, Code of Federal Regulations, part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes Federal, State, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project and includes a mailing address with their
comments. Commission staff will update the environmental mailing list
as the analysis proceeds to ensure that Commission notices related to
this environmental review are sent to all individuals, organizations,
and government entities interested in and/or potentially affected by
the proposed project.
If you need to make changes to your name/address, or if you would
like to remove your name from the mailing list, please complete one of
the following steps:
(1) Send an email to [email protected] stating your
request. You must include the docket number CP23-542-000 in your
request. If you are requesting a change to your address, please be sure
to include your name and the correct address. If you are requesting to
delete your address from the mailing list, please include your name and
address as it appeared on this notice. This email address is unable to
accept comments. OR
(2) Return the attached ``Mailing List Update Form'' (Appendix 2).
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website at www.ferc.gov using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number
in the ``Docket Number'' field. Be sure you have selected an
appropriate date range. For assistance, please contact FERC Online
Support at [email protected] or (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of all formal documents issued by the Commission, such as orders,
notices, and rulemakings.
Public sessions or site visits will be posted on the Commission's
calendar located at https://www.ferc.gov/news-events/events along with
other related information.
Dated: September 21, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-21095 Filed 9-26-23; 8:45 am]
BILLING CODE 6717-01-P