Brookfield White Pine Hydro, LLC, Merimil Limited Partnership, Hydro-Kennebec, LLC; Notice of Revised Procedural Schedule for Environmental Impact Statement for the Proposed Project Relicense, Interim Species Protection Plan, and Final Species Protection Plan, 65382 [2023-20569]

Download as PDF lotter on DSK11XQN23PROD with NOTICES1 65382 Federal Register / Vol. 88, No. 183 / Friday, September 22, 2023 / Notices Applicants: Florida Power & Light Company. Description: § 205(d) Rate Filing: Rate Schedule FERC No. 317 Agreement Regarding Hold Harmless Commitment to be effective 11/18/2023. Filed Date: 9/18/23. Accession Number: 20230918–5073. Comment Date: 5 p.m. ET 10/10/23. Docket Numbers: ER23–2884–000. Applicants: Florida Power & Light Company. Description: § 205(d) Rate Filing: Rate Schedule FERC No. 322 Agreement Regarding Hold Harmless Commitment to be effective 11/18/2023. Filed Date: 9/18/23. Accession Number: 20230918–5074. Comment Date: 5 p.m. ET 10/10/23. Docket Numbers: ER23–2885–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Original NSA, Service Agreement No. 7076; Queue No. AD1–031 to be effective 8/18/2023. Filed Date: 9/18/23. Accession Number: 20230918–5094. Comment Date: 5 p.m. ET 10/10/23. Docket Numbers: ER23–2886–000. Applicants: South Energy Investments, LLC. Description: Baseline eTariff Filing: Application for Market-Based Rate Authorization to be effective 11/18/ 2023. Filed Date: 9/18/23. Accession Number: 20230918–5100. Comment Date: 5 p.m. ET 10/10/23. Docket Numbers: ER23–2887–000. Applicants: Arizona Public Service Company. Description: § 205(d) Rate Filing: Rate Schedule No. 265 to be effective 11/18/ 2023. Filed Date: 9/18/23. Accession Number: 20230918–5107. Comment Date: 5 p.m. ET 10/10/23. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings VerDate Sep<11>2014 16:40 Sep 21, 2023 Jkt 259001 can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: September 18, 2023. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2023–20583 Filed 9–21–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project Nos. 2322–069; 2322–071; 2325– 100; 2574–092; 2611–091] Brookfield White Pine Hydro, LLC, Merimil Limited Partnership, HydroKennebec, LLC; Notice of Revised Procedural Schedule for Environmental Impact Statement for the Proposed Project Relicense, Interim Species Protection Plan, and Final Species Protection Plan On January 31, 2020, Brookfield White Pine Hydro, LLC filed an application for a new license to continue to operate and maintain the 8.65-megawatt (MW) Shawmut Hydroelectric Project No. 2322 (Shawmut Project). On June 1, 2021, in a separate compliance proceeding for the Shawmut Project, Brookfield White Pine Hydro, LLC filed an Interim Species Protection Plan (Interim Plan) for Atlantic salmon and requested Commission approval to amend the current Shawmut license to incorporate the Interim Plan. The Interim Plan includes measures to protect endangered Atlantic salmon until the Commission issues a decision on the relicense application for the Shawmut Project. Also on June 1, 2021, Brookfield Power US Asset Management, LLC (Brookfield), on behalf of the affiliated licensees for the 6.915–MW Lockwood Hydroelectric Project No. 2574, 15.433MW Hydro-Kennebec Hydroelectric PO 00000 Frm 00024 Fmt 4703 Sfmt 9990 Project No. 2611, and 15.98-MW Weston Hydroelectric Project No. 2325, filed a Final Species Protection Plan (Final Plan) for Atlantic salmon, Atlantic sturgeon, and shortnose sturgeon and requested Commission approval to amend the three project licenses to incorporate the Final Plan. All four projects are located on the Kennebec River, in Kennebec and Somerset Counties, Maine. On November 23, 2021, Commission staff issued a notice of intent to prepare a draft and final Environmental Impact Statement (EIS) to evaluate the effects of relicensing the Shawmut Project and amending the licenses of all four projects to incorporate the measures in the Interim and Final Plans. The notice of intent included a schedule for preparing a draft and final EIS. The schedule was updated on February 15, 2023, in response to Brookfield’s filing of supplemental information for the Final Plan, Interim Plan, and License Application. On March 29, 2023, Commission staff initiated Tribal consultation with potentially affected Indian Tribes on the proposed license amendments. The Houlton Band of Maliseet Indians filed comments and recommendations on May 4, 2023, and the Penobscot Indian Nation filed comments and recommendations on May 1, 2023, and August 17, 2023. The EIS will consider the comments and recommendations from the Tribes. Therefore, by this notice, Commission staff is updating the procedural schedule for completing a draft and final EIS. The revised schedule is shown below. Further revisions to the schedule may be made as appropriate. Milestone Target date Issue Draft EIS ................ Issue Final EIS ................ March 2024. September 2024. Any questions regarding this notice may be directed to Matt Cutlip at (503) 552–2762, or by email at matt.cutlip@ ferc.gov. Dated: September 18, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–20569 Filed 9–21–23; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\22SEN1.SGM 22SEN1

Agencies

[Federal Register Volume 88, Number 183 (Friday, September 22, 2023)]
[Notices]
[Page 65382]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-20569]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project Nos. 2322-069; 2322-071; 2325-100; 2574-092; 2611-091]


Brookfield White Pine Hydro, LLC, Merimil Limited Partnership, 
Hydro-Kennebec, LLC; Notice of Revised Procedural Schedule for 
Environmental Impact Statement for the Proposed Project Relicense, 
Interim Species Protection Plan, and Final Species Protection Plan

    On January 31, 2020, Brookfield White Pine Hydro, LLC filed an 
application for a new license to continue to operate and maintain the 
8.65-megawatt (MW) Shawmut Hydroelectric Project No. 2322 (Shawmut 
Project). On June 1, 2021, in a separate compliance proceeding for the 
Shawmut Project, Brookfield White Pine Hydro, LLC filed an Interim 
Species Protection Plan (Interim Plan) for Atlantic salmon and 
requested Commission approval to amend the current Shawmut license to 
incorporate the Interim Plan. The Interim Plan includes measures to 
protect endangered Atlantic salmon until the Commission issues a 
decision on the relicense application for the Shawmut Project.
    Also on June 1, 2021, Brookfield Power US Asset Management, LLC 
(Brookfield), on behalf of the affiliated licensees for the 6.915-MW 
Lockwood Hydroelectric Project No. 2574, 15.433-MW Hydro-Kennebec 
Hydroelectric Project No. 2611, and 15.98-MW Weston Hydroelectric 
Project No. 2325, filed a Final Species Protection Plan (Final Plan) 
for Atlantic salmon, Atlantic sturgeon, and shortnose sturgeon and 
requested Commission approval to amend the three project licenses to 
incorporate the Final Plan. All four projects are located on the 
Kennebec River, in Kennebec and Somerset Counties, Maine.
    On November 23, 2021, Commission staff issued a notice of intent to 
prepare a draft and final Environmental Impact Statement (EIS) to 
evaluate the effects of relicensing the Shawmut Project and amending 
the licenses of all four projects to incorporate the measures in the 
Interim and Final Plans. The notice of intent included a schedule for 
preparing a draft and final EIS. The schedule was updated on February 
15, 2023, in response to Brookfield's filing of supplemental 
information for the Final Plan, Interim Plan, and License Application.
    On March 29, 2023, Commission staff initiated Tribal consultation 
with potentially affected Indian Tribes on the proposed license 
amendments. The Houlton Band of Maliseet Indians filed comments and 
recommendations on May 4, 2023, and the Penobscot Indian Nation filed 
comments and recommendations on May 1, 2023, and August 17, 2023. The 
EIS will consider the comments and recommendations from the Tribes. 
Therefore, by this notice, Commission staff is updating the procedural 
schedule for completing a draft and final EIS.
    The revised schedule is shown below. Further revisions to the 
schedule may be made as appropriate.

------------------------------------------------------------------------
               Milestone                           Target date
------------------------------------------------------------------------
Issue Draft EIS........................  March 2024.
Issue Final EIS........................  September 2024.
------------------------------------------------------------------------

    Any questions regarding this notice may be directed to Matt Cutlip 
at (503) 552-2762, or by email at [email protected].

    Dated: September 18, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-20569 Filed 9-21-23; 8:45 am]
BILLING CODE 6717-01-P