Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline, 63950-63951 [2023-20114]
Download as PDF
63950
Federal Register / Vol. 88, No. 179 / Monday, September 18, 2023 / Notices
Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact the Federal Energy
Regulatory Commission at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Dated: September 12, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–20118 Filed 9–15–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP23–537–000]
lotter on DSK11XQN23PROD with NOTICES1
Columbia Gas Transmission, LLC;
Notice of Request Under Blanket
Authorization and Establishing
Intervention and Protest Deadline
Take notice that on September 5,
2023, Columbia Gas Transmission, LLC,
(Columbia), 700 Louisiana Street, Suite
1300, Houston, Texas 77002–2700, filed
in the above referenced docket, a prior
notice request pursuant to sections
157.205 and 157.208 of the
Commission’s regulations under the
Natural Gas Act (NGA), and Columbia’s
blanket certificate issued in Docket No.
VerDate Sep<11>2014
18:29 Sep 15, 2023
Jkt 259001
CP83–76–000, for authorization to
perform installations and activities to
enable the bi-directional in-line
inspection, or pigging, of its 20-inch
diameter Line D100 (Project). The
proposed Project involves modifying the
existing 20-inch Line D100 pipeline at
various locations, including the
installation of two bi-directional
launching and receiving stations for inline inspection devices, and other
appurtenant facilities in Richland,
Crawford, Huron, and Seneca Counties,
Ohio. The estimated cost for the project
is $16,400,000, all as more fully set forth
in the request which is on file with the
Commission and open to public
inspection.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page
(www.ferc.gov) using the ‘‘eLibrary’’
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document. At
this time, the Commission has
suspended access to the Commission’s
Public Reference Room. For assistance,
contact the Federal Energy Regulatory
Commission at FercOnlineSupport@
ferc.gov or call toll-free, (886) 208–3676
or TTY (202) 502–8659.
Any questions concerning this request
should be directed to David A. Alonzo,
Manager, Project Authorizations,
Columbia Gas Transmission, LLC, 700
Louisiana Street, Suite 1300, Houston,
Texas, 77002–2700, at (832) 320–5477
or david_alonzo@tcenergy.com.
Public Participation
There are three ways to become
involved in the Commission’s review of
this project: you can file a protest to the
project, you can file a motion to
intervene in the proceeding, and you
can file comments on the project. There
is no fee or cost for filing protests,
motions to intervene, or comments. The
deadline for filing protests, motions to
intervene, and comments is 5:00 p.m.
Eastern Time on November 13, 2023.
How to file protests, motions to
intervene, and comments is explained
below.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Protests
Pursuant to section 157.205 of the
Commission’s regulations under the
NGA,1 any person 2 or the Commission’s
staff may file a protest to the request. If
no protest is filed within the time
allowed or if a protest is filed and then
withdrawn within 30 days after the
allowed time for filing a protest, the
proposed activity shall be deemed to be
authorized effective the day after the
time allowed for protest. If a protest is
filed and not withdrawn within 30 days
after the time allowed for filing a
protest, the instant request for
authorization will be considered by the
Commission.
Protests must comply with the
requirements specified in section
157.205(e) of the Commission’s
regulations,3 and must be submitted by
the protest deadline, which is November
13, 2023. A protest may also serve as a
motion to intervene so long as the
protestor states it also seeks to be an
intervenor.
Interventions
Any person has the option to file a
motion to intervene in this proceeding.
Only intervenors have the right to
request rehearing of Commission orders
issued in this proceeding and to
subsequently challenge the
Commission’s orders in the U.S. Circuit
Courts of Appeal.
To intervene, you must submit a
motion to intervene to the Commission
in accordance with Rule 214 of the
Commission’s Rules of Practice and
Procedure 4 and the regulations under
the NGA 5 by the intervention deadline
for the project, which is November 13,
2023. As described further in Rule 214,
your motion to intervene must state, to
the extent known, your position
regarding the proceeding, as well as
your interest in the proceeding. For an
individual, this could include your
status as a landowner, ratepayer,
resident of an impacted community, or
recreationist. You do not need to have
property directly impacted by the
project in order to intervene. For more
information about motions to intervene,
refer to the FERC website at https://
1 18
CFR 157.205.
include individuals, organizations,
businesses, municipalities, and other entities. 18
CFR 385.102(d).
3 18 CFR 157.205(e).
4 18 CFR 385.214.
5 18 CFR 157.10.
2 Persons
E:\FR\FM\18SEN1.SGM
18SEN1
Federal Register / Vol. 88, No. 179 / Monday, September 18, 2023 / Notices
www.ferc.gov/resources/guides/how-to/
intervene.asp.
All timely, unopposed motions to
intervene are automatically granted by
operation of Rule 214(c)(1). Motions to
intervene that are filed after the
intervention deadline are untimely and
may be denied. Any late-filed motion to
intervene must show good cause for
being late and must explain why the
time limitation should be waived and
provide justification by reference to
factors set forth in Rule 214(d) of the
Commission’s Rules and Regulations. A
person obtaining party status will be
placed on the service list maintained by
the Secretary of the Commission and
will receive copies (paper or electronic)
of all documents filed by the applicant
and by all other parties.
Comments
Any person wishing to comment on
the project may do so. The Commission
considers all comments received about
the project in determining the
appropriate action to be taken. To
ensure that your comments are timely
and properly recorded, please submit
your comments on or before November
13, 2023. The filing of a comment alone
will not serve to make the filer a party
to the proceeding. To become a party,
you must intervene in the proceeding.
lotter on DSK11XQN23PROD with NOTICES1
How To File Protests, Interventions,
and Comments
There are two ways to submit
protests, motions to intervene, and
comments. In both instances, please
reference the Project docket number
CP23–537–000 in your submission.
(1) You may file your protest, motion
to intervene, and comments by using the
Commission’s eFiling feature, which is
located on the Commission’s website
(www.ferc.gov) under the link to
Documents and Filings. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ You will be
asked to select the type of filing you are
making; first select ‘‘General’’ and then
select ‘‘Protest’’, ‘‘Intervention’’, or
‘‘Comment on a Filing’’; or 6
(2) You can file a paper copy of your
submission by mailing it to the address
below. Your submission must reference
the Project docket number CP23–537–
000.
To file via USPS: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE,
Washington, DC 20426.
To file via any other method:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852.
The Commission encourages
electronic filing of submissions (option
1 above) and has eFiling staff available
to assist you at (202) 502–8258 or
FercOnlineSupport@ferc.gov.
Protests and motions to intervene
must be served on the applicant either
by mail or email (with a link to the
document) at: David A. Alonzo,
Manager, Project Authorizations, 700
Louisiana Street, Suite 1300, Houston,
Texas 77002–2700, or by david_alonzo@
tcenergy.com. Any subsequent
submissions by an intervenor must be
served on the applicant and all other
parties to the proceeding. Contact
information for parties can be
downloaded from the service list at the
eService link on FERC Online.
Tracking the Proceeding
Throughout the proceeding,
additional information about the project
will be available from the Commission’s
Office of External Affairs, at (866) 208–
FERC, or on the FERC website at
www.ferc.gov using the ‘‘eLibrary’’ link
as described above. The eLibrary link
also provides access to the texts of all
formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. For more information and to
register, go to www.ferc.gov/docs-filing/
esubscription.asp.
Dated: September 12, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–20114 Filed 9–15–23; 8:45 am]
BILLING CODE 6717–01–P
6 Additionally, you may file your comments
electronically by using the eComment feature,
which is located on the Commission’s website at
www.ferc.gov under the link to Documents and
Filings. Using eComment is an easy method for
interested persons to submit brief, text-only
comments on a project.
VerDate Sep<11>2014
18:29 Sep 15, 2023
Jkt 259001
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
63951
ENVIRONMENTAL PROTECTION
AGENCY
[FRL–11371–01–R8]
Clean Air Act Operating Permit
Program; Order on Petitions for
Objection to State Operating Permit for
Suncor Energy, Inc. Plant 2 (East
Plant)
Environmental Protection
Agency (EPA).
ACTION: Notice of final order on
petitions.
AGENCY:
The Environmental Protection
Agency (EPA) Administrator signed an
order dated July 31, 2023, granting in
part and denying in part a petition dated
October 11, 2022, from Earthjustice on
behalf of Elyria and Swansea
Neighborhood Association, Cultivando,
Colorado Latino Forum, GreenLatinos,
Center for Biological Diversity, and
Sierra Club, and denying a petition
dated October 11, 2022, from 350
Colorado. The petitions requested that
the EPA object to a Clean Air Act (CAA)
operating permit issued by the Colorado
Department of Public Health and
Environment (CDPHE) to Suncor
Energy, Inc. for its Refinery Plant 2
Facility in Adams County, Colorado.
FOR FURTHER INFORMATION CONTACT:
Donald Law, EPA Region 8, telephone
number: (303) 312–7015, email address:
law.donald@epa.gov. The final order
and petition are available at: https://
www.epa.gov/title-v-operating-permits/
title-v-petition-database.
SUPPLEMENTARY INFORMATION: The EPA
received a petition from Earthjustice on
behalf of Elyria and Swansea
Neighborhood Association, Cultivando,
Colorado Latino Forum, GreenLatinos,
Center for Biological Diversity, and
Sierra Club dated October 11, 2022, and
a petition from 350 Colorado dated
October 11, 2022, requesting that the
EPA object to the issuance of operating
permit no. 95OPAD108, issued by
CDPHE to Suncor Energy, Inc. in Adams
County, Colorado. On July 31, 2023, the
EPA Administrator issued an order
granting in part and denying in part the
petition from the Elyria and Swansea
Neighborhood Association and other
groups, and denying the petition from
350 Colorado. The order itself explains
the basis for the EPA’s decision.
Under sections 307(b) and 505(b)(2) of
the CAA, a petitioner may request
judicial review of those portions of an
order that deny issues in a petition. Any
petition for review must be filed in the
United States Court of Appeals for the
appropriate circuit no later than
November 17, 2023.
SUMMARY:
E:\FR\FM\18SEN1.SGM
18SEN1
Agencies
[Federal Register Volume 88, Number 179 (Monday, September 18, 2023)]
[Notices]
[Pages 63950-63951]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-20114]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP23-537-000]
Columbia Gas Transmission, LLC; Notice of Request Under Blanket
Authorization and Establishing Intervention and Protest Deadline
Take notice that on September 5, 2023, Columbia Gas Transmission,
LLC, (Columbia), 700 Louisiana Street, Suite 1300, Houston, Texas
77002-2700, filed in the above referenced docket, a prior notice
request pursuant to sections 157.205 and 157.208 of the Commission's
regulations under the Natural Gas Act (NGA), and Columbia's blanket
certificate issued in Docket No. CP83-76-000, for authorization to
perform installations and activities to enable the bi-directional in-
line inspection, or pigging, of its 20-inch diameter Line D100
(Project). The proposed Project involves modifying the existing 20-inch
Line D100 pipeline at various locations, including the installation of
two bi-directional launching and receiving stations for in-line
inspection devices, and other appurtenant facilities in Richland,
Crawford, Huron, and Seneca Counties, Ohio. The estimated cost for the
project is $16,400,000, all as more fully set forth in the request
which is on file with the Commission and open to public inspection.
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (www.ferc.gov) using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to the Commission's Public
Reference Room. For assistance, contact the Federal Energy Regulatory
Commission at [email protected] or call toll-free, (886) 208-
3676 or TTY (202) 502-8659.
Any questions concerning this request should be directed to David
A. Alonzo, Manager, Project Authorizations, Columbia Gas Transmission,
LLC, 700 Louisiana Street, Suite 1300, Houston, Texas, 77002-2700, at
(832) 320-5477 or [email protected].
Public Participation
There are three ways to become involved in the Commission's review
of this project: you can file a protest to the project, you can file a
motion to intervene in the proceeding, and you can file comments on the
project. There is no fee or cost for filing protests, motions to
intervene, or comments. The deadline for filing protests, motions to
intervene, and comments is 5:00 p.m. Eastern Time on November 13, 2023.
How to file protests, motions to intervene, and comments is explained
below.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
Protests
Pursuant to section 157.205 of the Commission's regulations under
the NGA,\1\ any person \2\ or the Commission's staff may file a protest
to the request. If no protest is filed within the time allowed or if a
protest is filed and then withdrawn within 30 days after the allowed
time for filing a protest, the proposed activity shall be deemed to be
authorized effective the day after the time allowed for protest. If a
protest is filed and not withdrawn within 30 days after the time
allowed for filing a protest, the instant request for authorization
will be considered by the Commission.
---------------------------------------------------------------------------
\1\ 18 CFR 157.205.
\2\ Persons include individuals, organizations, businesses,
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------
Protests must comply with the requirements specified in section
157.205(e) of the Commission's regulations,\3\ and must be submitted by
the protest deadline, which is November 13, 2023. A protest may also
serve as a motion to intervene so long as the protestor states it also
seeks to be an intervenor.
---------------------------------------------------------------------------
\3\ 18 CFR 157.205(e).
---------------------------------------------------------------------------
Interventions
Any person has the option to file a motion to intervene in this
proceeding. Only intervenors have the right to request rehearing of
Commission orders issued in this proceeding and to subsequently
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
To intervene, you must submit a motion to intervene to the
Commission in accordance with Rule 214 of the Commission's Rules of
Practice and Procedure \4\ and the regulations under the NGA \5\ by the
intervention deadline for the project, which is November 13, 2023. As
described further in Rule 214, your motion to intervene must state, to
the extent known, your position regarding the proceeding, as well as
your interest in the proceeding. For an individual, this could include
your status as a landowner, ratepayer, resident of an impacted
community, or recreationist. You do not need to have property directly
impacted by the project in order to intervene. For more information
about motions to intervene, refer to the FERC website at https://
[[Page 63951]]
www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------
\4\ 18 CFR 385.214.
\5\ 18 CFR 157.10.
---------------------------------------------------------------------------
All timely, unopposed motions to intervene are automatically
granted by operation of Rule 214(c)(1). Motions to intervene that are
filed after the intervention deadline are untimely and may be denied.
Any late-filed motion to intervene must show good cause for being late
and must explain why the time limitation should be waived and provide
justification by reference to factors set forth in Rule 214(d) of the
Commission's Rules and Regulations. A person obtaining party status
will be placed on the service list maintained by the Secretary of the
Commission and will receive copies (paper or electronic) of all
documents filed by the applicant and by all other parties.
Comments
Any person wishing to comment on the project may do so. The
Commission considers all comments received about the project in
determining the appropriate action to be taken. To ensure that your
comments are timely and properly recorded, please submit your comments
on or before November 13, 2023. The filing of a comment alone will not
serve to make the filer a party to the proceeding. To become a party,
you must intervene in the proceeding.
How To File Protests, Interventions, and Comments
There are two ways to submit protests, motions to intervene, and
comments. In both instances, please reference the Project docket number
CP23-537-000 in your submission.
(1) You may file your protest, motion to intervene, and comments by
using the Commission's eFiling feature, which is located on the
Commission's website (www.ferc.gov) under the link to Documents and
Filings. New eFiling users must first create an account by clicking on
``eRegister.'' You will be asked to select the type of filing you are
making; first select ``General'' and then select ``Protest'',
``Intervention'', or ``Comment on a Filing''; or \6\
---------------------------------------------------------------------------
\6\ Additionally, you may file your comments electronically by
using the eComment feature, which is located on the Commission's
website at www.ferc.gov under the link to Documents and Filings.
Using eComment is an easy method for interested persons to submit
brief, text-only comments on a project.
---------------------------------------------------------------------------
(2) You can file a paper copy of your submission by mailing it to
the address below. Your submission must reference the Project docket
number CP23-537-000.
To file via USPS: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE, Washington, DC 20426.
To file via any other method: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland
20852.
The Commission encourages electronic filing of submissions (option
1 above) and has eFiling staff available to assist you at (202) 502-
8258 or [email protected].
Protests and motions to intervene must be served on the applicant
either by mail or email (with a link to the document) at: David A.
Alonzo, Manager, Project Authorizations, 700 Louisiana Street, Suite
1300, Houston, Texas 77002-2700, or by [email protected]. Any
subsequent submissions by an intervenor must be served on the applicant
and all other parties to the proceeding. Contact information for
parties can be downloaded from the service list at the eService link on
FERC Online.
Tracking the Proceeding
Throughout the proceeding, additional information about the project
will be available from the Commission's Office of External Affairs, at
(866) 208-FERC, or on the FERC website at www.ferc.gov using the
``eLibrary'' link as described above. The eLibrary link also provides
access to the texts of all formal documents issued by the Commission,
such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. For more information and to register, go to
www.ferc.gov/docs-filing/esubscription.asp.
Dated: September 12, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-20114 Filed 9-15-23; 8:45 am]
BILLING CODE 6717-01-P