Download as PDF 61588 Federal Register / Vol. 88, No. 172 / Thursday, September 7, 2023 / Notices specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. For other information, call (866) 208– 3676 (toll free). For TTY, call (202) 502– 8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202)502–6595 or OPP@ferc.gov. Dated: August 31, 2023. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2023–19301 Filed 9–6–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER23–2729–000] ddrumheller on DSK120RN23PROD with NOTICES1 Robin Hollow Solar, LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding of Robin Hollow Solar, LLC’s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice VerDate Sep<11>2014 19:19 Sep 06, 2023 Jkt 259001 and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is September 20, 2023. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to PO 00000 Frm 00090 Fmt 4703 Sfmt 4703 contact OPP at (202)502–6595 or OPP@ ferc.gov. Dated: August 31, 2023. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2023–19306 Filed 9–6–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 4334–017] EONY Generation Limited; Notice of Denial of Water Quality Certification On January 28, 2021, EONY Generation Limited (EONY) filed an application for a new license for the Philadelphia Hydroelectric Project (project) in the above captioned docket. EONY filed with the New York State Department of Environmental Conservation (New York DEC) a request for water quality certification for the project under section 401(a)(1) of the Clean Water Act on August 26, 2022. On August 22, 2023, the New York DEC denied certification for the project. Pursuant to 40 CFR 121.8, we are providing notice that New York DEC’s denial satisfies the requirements of 40 CFR 121.7(e). Dated: August 30, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–19219 Filed 9–6–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following exempt wholesale generator filings: Docket Numbers: EG23–271–000. Applicants: Arche Energy Project, LLC. Description: Arche Energy Project, LLC submits Notice of Self-Certification of Exempt Wholesale Generator Status. Filed Date: 8/31/23. Accession Number: 20230831–5040. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: EG23–272–000. Applicants: El Sol Energy Storage LLC. Description: El Sol Energy Storage LLC submits Notice of Self-Certification of Exempt Wholesale Generator Status. Filed Date: 8/31/23. E:\FR\FM\07SEN1.SGM 07SEN1 ddrumheller on DSK120RN23PROD with NOTICES1 Federal Register / Vol. 88, No. 172 / Thursday, September 7, 2023 / Notices Accession Number: 20230831–5177. Comment Date: 5 p.m. ET 9/21/23. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER23–1361–002. Applicants: Southwest Power Pool, Inc. Description: Compliance filing: Compliance Filing in Response to August 3 Order in ER23–1361 to be effective 5/15/2023. Filed Date: 8/31/23. Accession Number: 20230831–5157. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2252–001. Applicants: Southwest Power Pool, Inc. Description: Tariff Amendment: 1266R14 Kansas Municipal Energy Agency NITSA and NOA to be effective 9/1/2023. Filed Date: 8/31/23. Accession Number: 20230831–5084. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2280–001. Applicants: Southwest Power Pool, Inc. Description: Tariff Amendment: 1875R6 Kansas Electric Power Cooperative, Inc. NITSA and NOA to be effective 9/1/2023. Filed Date: 8/31/23. Accession Number: 20230831–5093. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2734–000. Applicants: Puget Sound Energy, Inc. Description: § 205(d) Rate Filing: Engineering and Construction Agreement between BP Products and PSE to be effective 6/1/2022. Filed Date: 8/30/23. Accession Number: 20230830–5146. Comment Date: 5 p.m. ET 9/20/23. Docket Numbers: ER23–2735–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: 4115 Steeple Wind Energy GIA to be effective 8/1/2023. Filed Date: 8/31/23. Accession Number: 20230831–5001. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2736–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: 4116 Big Blue Nebraska Wind GIA to be effective 8/1/2023. Filed Date: 8/31/23. Accession Number: 20230831–5002. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2737–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: 4117 Blue Prairie Wind GIA to be effective 8/ 1/2023. VerDate Sep<11>2014 19:19 Sep 06, 2023 Jkt 259001 Filed Date: 8/31/23. Accession Number: 20230831–5003. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2738–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: 4118 K Junction Solar GIA to be effective 8/ 1/2023. Filed Date: 8/31/23. Accession Number: 20230831–5004. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2739–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: 4119 Greeley Wind Nebraska GIA to be effective 8/1/2023. Filed Date: 8/31/23. Accession Number: 20230831–5005. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2740–000. Applicants: Arche Energy Project, LLC. Description: Baseline eTariff Filing: Application for Market-Based Rate Authorization to be effective 9/20/2023. Filed Date: 8/31/23. Accession Number: 20230831–5006. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2741–000. Applicants: Clearwater Energy Resources LLC. Description: § 205(d) Rate Filing: Transmission Services Agreement with Clearwater East to be effective 9/1/2023. Filed Date: 8/31/23. Accession Number: 20230831–5022. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2742–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2023–08–31_Attachment X IC Deposits for D1 D2 to be effective 10/31/2023. Filed Date: 8/31/23. Accession Number: 20230831–5117. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2743–000. Applicants: Alabama Power Company, Georgia Power Company, Mississippi Power Company. Description: Tariff Amendment: Alabama Power Company submits tariff filing per 35.15: Silver Arrow LGIA Termination Filing to be effective 8/31/ 2023. Filed Date: 8/31/23. Accession Number: 20230831–5120. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2744–000. Applicants: The Potomac Edison Company, PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: The Potomac Edison Company submits tariff filing per 35.13(a)(2)(iii: The Potomac Edison Co.’s Request for Order PO 00000 Frm 00091 Fmt 4703 Sfmt 4703 61589 Authorizing Abandoned Plant Incentive to be effective 10/31/2023. Filed Date: 8/31/23. Accession Number: 20230831–5122. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2745–000. Applicants: Tucson Electric Power Company. Description: § 205(d) Rate Filing: Depreciation Rate Update to be effective 9/1/2023. Filed Date: 8/31/23. Accession Number: 20230831–5144. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2746–000. Applicants: El Sol Storage LLC. Description: Baseline eTariff Filing: Application for Market-Based Rate Authorization to be effective 10/31/ 2023. Filed Date: 8/31/23. Accession Number: 20230831–5154. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2747–000. Applicants: SCEF1 Fuel Cell, LLC. Description: Baseline eTariff Filing: Baseline new to be effective 10/31/2023. Filed Date: 8/31/23. Accession Number: 20230831–5162. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2748–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: 1628R24 Western Farmers Electric Cooperative NITSA NOAs to be effective 8/1/2023. Filed Date: 8/31/23. Accession Number: 20230831–5172. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2749–000. Applicants: AEUG Union Solar, LLC. Description: Baseline eTariff Filing: AEUG Union Solar, LLC Market-Based Rate Tariff to be effective 11/1/2023. Filed Date: 8/31/23. Accession Number: 20230831–5176. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2750–000. Applicants: HORIZON HILL WIND, LLC. Description: Baseline eTariff Filing: Application for Market-Based Rate Authorization, Request for Related Waivers to be effective 10/31/2023. Filed Date: 8/31/23. Accession Number: 20230831–5212. Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2751–000. Applicants: WHITE ROCK WIND EAST, LLC. Description: Baseline eTariff Filing: Application for Market-Based Rate Authorization, Request for Related Waivers to be effective 10/31/2023. Filed Date: 8/31/23. Accession Number: 20230831–5218. E:\FR\FM\07SEN1.SGM 07SEN1 61590 Federal Register / Vol. 88, No. 172 / Thursday, September 7, 2023 / Notices Comment Date: 5 p.m. ET 9/21/23. Docket Numbers: ER23–2752–000. Applicants: WHITE ROCK WIND WEST, LLC. Description: Baseline eTariff Filing: Application for Market-Based Rate Authorization, Request for Related Waivers to be effective 10/20/2023. Filed Date: 8/31/23. Accession Number: 20230831–5219. Comment Date: 5 p.m. ET 9/21/23. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: August 31, 2023.. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2023–19302 Filed 9–6–23; 8:45 am] BILLING CODE 6717–01–P ddrumheller on DSK120RN23PROD with NOTICES1 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 6951–018] Tallassee Shoals, LLC; Notice of Waiver of Water Quality Certification On September 15, 2021, Tallassee Shoals, LLC. filed an application for a VerDate Sep<11>2014 19:19 Sep 06, 2023 Jkt 259001 new license for the Tallassee Shoals Hydroelectric Project (project) in the above captioned docket. On August 12, 2022, Tallassee Shoals, LLC. filed with the Georgia Environmental Protection Division, a request for water quality certification for the project under section 401(a)(1) of the Clean Water Act. On September 2, 2022, staff provided the certifying authority with written notice pursuant to 40 CFR 121.6(b) that the applicable reasonable period of time for the state to act on the certification request was one (1) year from the date of receipt of the request, and that the certification requirement for the license would be waived if the certifying authority failed to act by August 12, 2023. Because the state did not act by August 12, 2023, we are notifying you pursuant to 40 CFR 121.9(c), and section 401(a)(1) of the Clean Water Act, 33 U.S.C. 1341(a)(1), that waiver of the certification requirement has occurred. Dated: August 31, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–19293 Filed 9–6–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER23–2730–000] Robin Hollow Solar Lessee, LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding of Robin Hollow Solar Lessee, LLC’s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and PO 00000 Frm 00092 Fmt 4703 Sfmt 9990 assumptions of liability, is September 20, 2023. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: August 31, 2023. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2023–19305 Filed 9–6–23; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\07SEN1.SGM 07SEN1

Agencies

[Federal Register Volume 88, Number 172 (Thursday, September 7, 2023)]
[Notices]
[Pages 61588-61590]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-19302]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Combined Notice of Filings #1

    Take notice that the Commission received the following exempt 
wholesale generator filings:

    Docket Numbers: EG23-271-000.
    Applicants: Arche Energy Project, LLC.
    Description: Arche Energy Project, LLC submits Notice of Self-
Certification of Exempt Wholesale Generator Status.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5040.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: EG23-272-000.
    Applicants: El Sol Energy Storage LLC.
    Description: El Sol Energy Storage LLC submits Notice of Self-
Certification of Exempt Wholesale Generator Status.
    Filed Date: 8/31/23.

[[Page 61589]]

    Accession Number: 20230831-5177.
    Comment Date: 5 p.m. ET 9/21/23.

    Take notice that the Commission received the following electric 
rate filings:

    Docket Numbers: ER23-1361-002.
    Applicants: Southwest Power Pool, Inc.
    Description: Compliance filing: Compliance Filing in Response to 
August 3 Order in ER23-1361 to be effective 5/15/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5157.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2252-001.
    Applicants: Southwest Power Pool, Inc.
    Description: Tariff Amendment: 1266R14 Kansas Municipal Energy 
Agency NITSA and NOA to be effective 9/1/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5084.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2280-001.
    Applicants: Southwest Power Pool, Inc.
    Description: Tariff Amendment: 1875R6 Kansas Electric Power 
Cooperative, Inc. NITSA and NOA to be effective 9/1/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5093.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2734-000.
    Applicants: Puget Sound Energy, Inc.
    Description: Sec.  205(d) Rate Filing: Engineering and Construction 
Agreement between BP Products and PSE to be effective 6/1/2022.
    Filed Date: 8/30/23.
    Accession Number: 20230830-5146.
    Comment Date: 5 p.m. ET 9/20/23.

    Docket Numbers: ER23-2735-000.
    Applicants: Southwest Power Pool, Inc.
    Description: Sec.  205(d) Rate Filing: 4115 Steeple Wind Energy GIA 
to be effective 8/1/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5001.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2736-000.
    Applicants: Southwest Power Pool, Inc.
    Description: Sec.  205(d) Rate Filing: 4116 Big Blue Nebraska Wind 
GIA to be effective 8/1/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5002.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2737-000.
    Applicants: Southwest Power Pool, Inc.
    Description: Sec.  205(d) Rate Filing: 4117 Blue Prairie Wind GIA 
to be effective 8/1/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5003.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2738-000.
    Applicants: Southwest Power Pool, Inc.
    Description: Sec.  205(d) Rate Filing: 4118 K Junction Solar GIA to 
be effective 8/1/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5004.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2739-000.
    Applicants: Southwest Power Pool, Inc.
    Description: Sec.  205(d) Rate Filing: 4119 Greeley Wind Nebraska 
GIA to be effective 8/1/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5005.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2740-000.
    Applicants: Arche Energy Project, LLC.
    Description: Baseline eTariff Filing: Application for Market-Based 
Rate Authorization to be effective 9/20/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5006.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2741-000.
    Applicants: Clearwater Energy Resources LLC.
    Description: Sec.  205(d) Rate Filing: Transmission Services 
Agreement with Clearwater East to be effective 9/1/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5022.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2742-000.
    Applicants: Midcontinent Independent System Operator, Inc.
    Description: Sec.  205(d) Rate Filing: 2023-08-31_Attachment X IC 
Deposits for D1 D2 to be effective 10/31/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5117.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2743-000.
    Applicants: Alabama Power Company, Georgia Power Company, 
Mississippi Power Company.
    Description: Tariff Amendment: Alabama Power Company submits tariff 
filing per 35.15: Silver Arrow LGIA Termination Filing to be effective 
8/31/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5120.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2744-000.
    Applicants: The Potomac Edison Company, PJM Interconnection, L.L.C.
    Description: Sec.  205(d) Rate Filing: The Potomac Edison Company 
submits tariff filing per 35.13(a)(2)(iii: The Potomac Edison Co.'s 
Request for Order Authorizing Abandoned Plant Incentive to be effective 
10/31/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5122.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2745-000.
    Applicants: Tucson Electric Power Company.
    Description: Sec.  205(d) Rate Filing: Depreciation Rate Update to 
be effective 9/1/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5144.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2746-000.
    Applicants: El Sol Storage LLC.
    Description: Baseline eTariff Filing: Application for Market-Based 
Rate Authorization to be effective 10/31/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5154.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2747-000.
    Applicants: SCEF1 Fuel Cell, LLC.
    Description: Baseline eTariff Filing: Baseline new to be effective 
10/31/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5162.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2748-000.
    Applicants: Southwest Power Pool, Inc.
    Description: Sec.  205(d) Rate Filing: 1628R24 Western Farmers 
Electric Cooperative NITSA NOAs to be effective 8/1/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5172.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2749-000.
    Applicants: AEUG Union Solar, LLC.
    Description: Baseline eTariff Filing: AEUG Union Solar, LLC Market-
Based Rate Tariff to be effective 11/1/2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5176.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2750-000.
    Applicants: HORIZON HILL WIND, LLC.
    Description: Baseline eTariff Filing: Application for Market-Based 
Rate Authorization, Request for Related Waivers to be effective 10/31/
2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5212.
    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2751-000.
    Applicants: WHITE ROCK WIND EAST, LLC.
    Description: Baseline eTariff Filing: Application for Market-Based 
Rate Authorization, Request for Related Waivers to be effective 10/31/
2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5218.

[[Page 61590]]

    Comment Date: 5 p.m. ET 9/21/23.

    Docket Numbers: ER23-2752-000.
    Applicants: WHITE ROCK WIND WEST, LLC.
    Description: Baseline eTariff Filing: Application for Market-Based 
Rate Authorization, Request for Related Waivers to be effective 10/20/
2023.
    Filed Date: 8/31/23.
    Accession Number: 20230831-5219.
    Comment Date: 5 p.m. ET 9/21/23.

    The filings are accessible in the Commission's eLibrary system 
(https://elibrary.ferc.gov/idmws/search/fercgensearch.asp) by querying 
the docket number.
    Any person desiring to intervene, to protest, or to answer a 
complaint in any of the above proceedings must file in accordance with 
Rules 211, 214, or 206 of the Commission's Regulations (18 CFR 385.211, 
385.214, or 385.206) on or before 5:00 p.m. Eastern time on the 
specified comment date. Protests may be considered, but intervention is 
necessary to become a party to the proceeding.
    eFiling is encouraged. More detailed information relating to filing 
requirements, interventions, protests, service, and qualifying 
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676 
(toll free). For TTY, call (202) 502-8659.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].

    Dated: August 31, 2023..
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-19302 Filed 9-6-23; 8:45 am]
BILLING CODE 6717-01-P