Dominion Energy South Carolina, Inc.; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests, 60672-60673 [2023-19063]

Download as PDF 60672 Federal Register / Vol. 88, No. 170 / Tuesday, September 5, 2023 / Notices (3) Hand delivering the filing to the Office of Regulation, Analysis, and Engagement at the address listed in the ADDRESSES section. For administrative efficiency, DOE prefers filings to be filed electronically. All filings must include a reference to ‘‘Docket No. 23–87–LNG’’ or ‘‘Lake Charles Exports, LLC Application’’ in the title line. For electronic submissions: Please include all related documents and attachments (e.g., exhibits) in the original email correspondence. Please do not include any active hyperlinks or password protection in any of the documents or attachments related to the filing. All electronic filings submitted to DOE must follow these guidelines to ensure that all documents are filed in a timely manner. The Notice, and any filed protests, motions to intervene, notices of intervention, and comments will be available electronically on the DOE website at www.energy.gov/fecm/ regulation. A decisional record on the Application will be developed through responses to this Notice by parties, including the parties’ written comments and replies thereto. Additional procedures will be used as necessary to achieve a complete understanding of the facts and issues. If an additional procedure is scheduled, notice will be provided to all parties. If no party requests additional procedures, a final Opinion and Order may be issued based on the official record, including the Application and responses filed by parties pursuant to this Notice, in accordance with 10 CFR 590.316. Signed in Washington, DC, on August 29, 2023. Amy Sweeney, Director, Office of Regulation, Analysis, and Engagement, Office of Resource Sustainability. [FR Doc. 2023–19053 Filed 9–1–23; 8:45 am] BILLING CODE 6450–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission ddrumheller on DSK120RN23PROD with NOTICES1 [Project No. 1894–229] Dominion Energy South Carolina, Inc.; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: VerDate Sep<11>2014 18:02 Sep 01, 2023 Jkt 259001 a. Application Type: Temporary variance of seasonal turbine venting period. b. Project No.: 1894–229. c. Date Filed: August 2, 2023. d. Applicant: Dominion Energy South Carolina, Inc. (licensee). e. Name of Project: Parr Project. f. Location: The project is located on the Broad River in Newberry and Fairfield counties, South Carolina, and occupies Federal lands within the Sumter National Forest, administered by the U.S. Department of Agriculture, Forest Service. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Ms. Amy Bresnahan, Dominion Energy South Carolina, Inc., 220 Operation Way, Mail Code B223, Cayce, South Carolina 29033; (803) 217–9965; amy.bresnahan@dominionenergy.com. i. FERC Contact: Joy Kurtz, (202) 502– 6760, joy.kurtz@ferc.gov. j. Deadline for filing comments, motions to intervene, and protests is September 28, 2023. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852. The first page of any filing should include docket number P–1894–229. Comments emailed to Commission staff are not considered part of the Commission record. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person whose name appears on the official service list for the project. Further, if an intervenor files comments or documents with the Commission PO 00000 Frm 00041 Fmt 4703 Sfmt 4703 relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Request: The licensee requests Commission approval to extend the seasonal turbine venting window requirements specified in the project’s Turbine Venting Plan (Plan) through October 31, 2023. The Plan requires the licensee to provide turbine venting annually between June 15 and August 31 in order to increase dissolved oxygen levels downstream of Parr Shoals Dam. Article 401(b) of the project license requires the licensee to obtain Commission approval for extensions exceeding 30 days. The licensee is seeking Commission approval to extend the seasonal turbine venting window through October 31, 2023, in light of requests from the South Carolina Department of Natural Resources and South Carolina Department of Health and Environmental Control, who are concerned that low dissolved oxygen levels may persist at the project through fall of 2023. l. Locations of the Application: This filing may be viewed on the Commission’s website at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. Agencies may obtain copies of the application directly from the applicant. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions To Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Responsive Documents: All filings must (1) bear in E:\FR\FM\05SEN1.SGM 05SEN1 Federal Register / Vol. 88, No. 170 / Tuesday, September 5, 2023 / Notices all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 385.2010. Dated: August 29, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–19063 Filed 9–1–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission ddrumheller on DSK120RN23PROD with NOTICES1 Combined Notice of Filings #1 Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC23–122–000. Applicants: Elgin Energy Center, LLC, Rocky Road Power, LLC, Middle River Power VI LLC, Middle River Power VII LLC Description: Supplement to August 14, 2023, Joint Application for Authorization Under Section 203 of the Federal Power Act of Elgin Energy Center, LLC. Filed Date: 8/22/23. Accession Number: 20230822–5171 Comment Date: 5 p.m. ET 9/28/23. Docket Numbers: EC23–126–000. Applicants: Old Gold Energy Center, LLC. Description: Application for Authorization Under Section 203 of the Federal Power Act of Old Gold Energy Center, LLC. Filed Date: 8/29/23. Accession Number: 20230829–5126. Comment Date: 5 p.m. ET 9/19/23. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER20–2054–003. Applicants: ISO New England Inc., Central Maine Power Company, Versant Power, Fitchburg Gas and Electric Light VerDate Sep<11>2014 18:02 Sep 01, 2023 Jkt 259001 Company, Green Mountain Power Corporation, New England Power Company, New Hampshire Transmission, LLC, NSTAR Electric Company, Public Service Company of New Hampshire, The Connecticut Light and Power Company, The United Illuminating Company, Unitil Energy Systems, Inc., Vermont Electric Cooperative, Inc., Vermont Transco LLC Description: Compliance filing: ISO New England Inc. submits tariff filing per 35: ISO–NE PTOs; Joint Offer of Settlement Re VP, Bangor Hydro District Charges to be effective N/A. Filed Date: 8/29/23. Accession Number: 20230829–5031. Comment Date: 5 p.m. ET 9/19/23. Docket Numbers: ER23–1736–001. Applicants: Big Plain Solar, LLC. Description: Compliance filing: Notice of Commercial Operation and Revised Rate Schedule to be effective 6/30/2023. Filed Date: 8/29/23. Accession Number: 20230829–5097. Comment Date: 5 p.m. ET 9/19/23. Docket Numbers: ER23–1752–001. Applicants: Oak Trail Solar, LLC. Description: Tariff Amendment: Response to Deficiency Letter in ER23– 1752 to be effective 6/30/2023. Filed Date: 8/28/23. Accession Number: 20230828–5408. Comment Date: 5 p.m. ET 9/18/23. Docket Numbers: ER23–2003–001. Applicants: Invenergy Nelson Expansion LLC. Description: Tariff Amendment: Deficiency Letter Response to be effective 7/1/2023. Filed Date: 8/28/23. Accession Number: 20230828–5384. Comment Date: 5 p.m. ET 9/18/23. Docket Numbers: ER23–2035–000. Applicants: ISO New England Inc., Versant Power. Description: Refund Report: ISO New England Inc. submits tariff filing per 35.19a(b): Versant Power; Refund Report—ER23–2035 to be effective N/A. Filed Date: 8/29/23. Accession Number: 20230829–5037. Comment Date: 5 p.m. ET 9/19/23. Docket Numbers: ER23–2189–001. Applicants: Southwest Power Pool, Inc. Description: Tariff Amendment: 1895R12 Evergy Kansas Central, Inc. NITSA NOA to be effective 9/1/2023. Filed Date: 8/29/23. Accession Number: 20230829–5113. Comment Date: 5 p.m. ET 9/19/23. Docket Numbers: ER23–2194–001. Applicants: Southwest Power Pool, Inc. Description: Tariff Amendment: 1892R12 Evergy Kansas Central, Inc. NITSA NOA to be effective 9/1/2023. PO 00000 Frm 00042 Fmt 4703 Sfmt 4703 60673 Filed Date: 8/29/23. Accession Number: 20230829–5093. Comment Date: 5 p.m. ET 9/19/23. Docket Numbers: ER23–2197–001. Applicants: Southwest Power Pool, Inc. Description: Tariff Amendment: 1893R13 Evergy Kansas Central, Inc. NITSA NOA to be effective 9/1/2023. Filed Date: 8/29/23. Accession Number: 20230829–5095. Comment Date: 5 p.m. ET 9/19/23. Docket Numbers: ER23–2198–001. Applicants: Southwest Power Pool, Inc. Description: Tariff Amendment: 1894R12 Evergy Kansas Central, Inc. NITSA NOA to be effective 9/1/2023. Filed Date: 8/29/23. Accession Number: 20230829–5117. Comment Date: 5 p.m. ET 9/19/23. Docket Numbers: ER23–2199–001. Applicants: Southwest Power Pool, Inc. Description: Tariff Amendment: 1978R12 Evergy Kansas Central, Inc. NITSA NOA to be effective 9/1/2023. Filed Date: 8/29/23. Accession Number: 20230829–5119. Comment Date: 5 p.m. ET 9/19/23. Docket Numbers: ER23–2204–001. Applicants: Southwest Power Pool, Inc. Description: Tariff Amendment: 2066R12 Evergy Kansas Central, Inc. NITSA NOA to be effective 9/1/2023. Filed Date: 8/29/23. Accession Number: 20230829–5123. Comment Date: 5 p.m. ET 9/19/23. Docket Numbers: ER23–2213–001. Applicants: Southwest Power Pool, Inc. Description: Tariff Amendment: 2491R11 Evergy Kansas Central, Inc. NITSA NOA to be effective 9/1/2023. Filed Date: 8/29/23. Accession Number: 20230829–5131. Comment Date: 5 p.m. ET 9/19/23. Docket Numbers: ER23–2309–000. Applicants: DCR Transmission, L.L.C. Description: Report Filing: DCRT Supplemental Testimony Filing to be effective N/A. Filed Date: 8/18/23. Accession Number: 20230818–5083. Comment Date: 5 p.m. ET 9/1/23. Docket Numbers: ER23–2363–001. Applicants: HXOap Solar One, LLC. Description: Tariff Amendment: HXOap Solar One, LLC—Amendment Filing to be effective 8/28/2023. Filed Date: 8/29/23. Accession Number: 20230829–5118. Comment Date: 5 p.m. ET 9/19/23. Docket Numbers: ER23–2456–000. Applicants: Platteview Solar, LLC. Description: Supplement to July 21, 2023, Platteview Solar, LLC tariff filing. E:\FR\FM\05SEN1.SGM 05SEN1

Agencies

[Federal Register Volume 88, Number 170 (Tuesday, September 5, 2023)]
[Notices]
[Pages 60672-60673]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-19063]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 1894-229]


Dominion Energy South Carolina, Inc.; Notice of Application 
Accepted for Filing and Soliciting Comments, Motions To Intervene, and 
Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Application Type: Temporary variance of seasonal turbine venting 
period.
    b. Project No.: 1894-229.
    c. Date Filed: August 2, 2023.
    d. Applicant: Dominion Energy South Carolina, Inc. (licensee).
    e. Name of Project: Parr Project.
    f. Location: The project is located on the Broad River in Newberry 
and Fairfield counties, South Carolina, and occupies Federal lands 
within the Sumter National Forest, administered by the U.S. Department 
of Agriculture, Forest Service.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Ms. Amy Bresnahan, Dominion Energy South 
Carolina, Inc., 220 Operation Way, Mail Code B223, Cayce, South 
Carolina 29033; (803) 217-9965; [email protected].
    i. FERC Contact: Joy Kurtz, (202) 502-6760, [email protected].
    j. Deadline for filing comments, motions to intervene, and protests 
is September 28, 2023.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, and protests using the Commission's 
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. 
Commenters can submit brief comments up to 6,000 characters, without 
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact 
information at the end of your comments. For assistance, please contact 
FERC Online Support at [email protected], (866) 208-3676 (toll 
free), or (202) 502-8659 (TTY). In lieu of electronic filing, you may 
submit a paper copy. Submissions sent via the U.S. Postal Service must 
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE, Room 1A, Washington, DC 20426. 
Submissions sent via any other carrier must be addressed to: Kimberly 
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, MD 20852. The first page of any filing should 
include docket number P-1894-229. Comments emailed to Commission staff 
are not considered part of the Commission record.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person whose name appears on the official service 
list for the project. Further, if an intervenor files comments or 
documents with the Commission relating to the merits of an issue that 
may affect the responsibilities of a particular resource agency, they 
must also serve a copy of the document on that resource agency.
    k. Description of Request: The licensee requests Commission 
approval to extend the seasonal turbine venting window requirements 
specified in the project's Turbine Venting Plan (Plan) through October 
31, 2023. The Plan requires the licensee to provide turbine venting 
annually between June 15 and August 31 in order to increase dissolved 
oxygen levels downstream of Parr Shoals Dam. Article 401(b) of the 
project license requires the licensee to obtain Commission approval for 
extensions exceeding 30 days. The licensee is seeking Commission 
approval to extend the seasonal turbine venting window through October 
31, 2023, in light of requests from the South Carolina Department of 
Natural Resources and South Carolina Department of Health and 
Environmental Control, who are concerned that low dissolved oxygen 
levels may persist at the project through fall of 2023.
    l. Locations of the Application: This filing may be viewed on the 
Commission's website at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. You may also register 
online at https://www.ferc.gov/docs-filing/esubscription.asp to be 
notified via email of new filings and issuances related to this or 
other pending projects. For assistance, call 1-866-208-3676 or email 
[email protected], for TTY, call (202) 502-8659. Agencies may 
obtain copies of the application directly from the applicant.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions To Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    o. Filing and Service of Responsive Documents: All filings must (1) 
bear in

[[Page 60673]]

all capital letters the title ``COMMENTS'', ``PROTEST'', or ``MOTION TO 
INTERVENE'' as applicable; (2) set forth in the heading the name of the 
applicant and the project number of the application to which the filing 
responds; (3) furnish the name, address, and telephone number of the 
person protesting or intervening; and (4) otherwise comply with the 
requirements of 18 CFR 385.2001 through 385.2005. All comments, motions 
to intervene, or protests must set forth their evidentiary basis. A 
copy of all other filings in reference to this application must be 
accompanied by proof of service on all persons listed in the service 
list prepared by the Commission in this proceeding, in accordance with 
385.2010.

     Dated: August 29, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-19063 Filed 9-1-23; 8:45 am]