DTE Electric Company; Fermi, Unit 2, 60504-60507 [2023-18920]

Download as PDF 60504 Federal Register / Vol. 88, No. 169 / Friday, September 1, 2023 / Notices Comments’’ or by using the search function. method used. The possible response time to complete a questionnaire or survey may be 3 minutes or up to 2 hours to participate in an interview. Estimated Total Annual Burden Hours: 101,125. Estimated Total Annual Cost to Public: $0. FOR FURTHER INFORMATION CONTACT: IV. Request for Comments Comments are invited on: (1) Whether the proposed collection of information is necessary for the proper performance of the functions of NASA, including whether the information collected has practical utility; (2) the accuracy of NASA’s estimate of the burden (including hours and cost) of the proposed collection of information; (3) ways to enhance the quality, utility, and clarity of the information to be collected; and (4) ways to minimize the burden of the collection of information on respondents, including automated collection techniques or the use of other forms of information technology. Comments submitted in response to this notice will be summarized and included in the request for OMB approval of this information collection. They will also become a matter of public record. William Edwards-Bodmer, NASA PRA Clearance Officer. [FR Doc. 2023–18956 Filed 8–31–23; 8:45 am] BILLING CODE 7510–13–P NATIONAL AERONAUTICS AND SPACE ADMINISTRATION [Notice: 23–092] Name of Information Collection: NASA Complaint of Discrimination Form 1355 National Aeronautics and Space Administration (NASA). ACTION: Notice of information collection. AGENCY: The National Aeronautics and Space Administration, as part of its continuing effort to reduce paperwork and respondent burden, invites the general public and other Federal agencies to take this opportunity to comment on proposed and/or continuing information collections. DATES: Comments are due by October 31, 2023. ADDRESSES: Written comments and recommendations for this information collection should be sent within 60 days of publication of this notice to www.reginfo.gov/public/do/PRAMain. Find this particular information collection by selecting ‘‘Currently under 60-day Review—Open for Public lotter on DSK11XQN23PROD with NOTICES1 SUMMARY: VerDate Sep<11>2014 17:24 Aug 31, 2023 Jkt 259001 Requests for additional information or copies of the information collection instrument(s) and instructions should be directed to Bill Edwards-Bodmer, NASA Clearance Officer, NASA Headquarters, 300 E Street SW, JF0000, Washington, DC 20546, 757–864–7998, or b.edwards-bodmer@nasa.gov. SUPPLEMENTARY INFORMATION: I. Abstract Federal agencies are required by statute not to engage in discrimination on the bases of race, color, religion, sex, national origin, age, disability, genetic information, or retaliation. A Federal employee, former employee, or job applicant who believes s/he was discriminated against has a right to file a complaint with the agency’s office responsible for its Equal Employment Opportunity (EEO) programs. Federal agencies must offer pre-complaint counseling or EEO alternative dispute resolution (EEO ADR) to individuals who allege that they were discriminated against by the agency. If pre-complaint counseling or EEO ADR does not resolve the dispute(s), the individual can file a formal discrimination complaint with the agency’s EEO office. II. Methods of Collection Title 29 of the Code of Federal Regulations (CFR) part 1614 section 104 requires agencies to establish procedures for processing individual and class complaints of discrimination that include the provisions contained in 29 CFR 1614.105 through 1614.110 and in § 1614.204, which are consistent with all other applicable Federal EEO regulations and complaint processing requirements contained in the Equal Employment Opportunity Commission (EEOC) Management Directives (MD). When an individual decides to pursue the formal discrimination complaint process, EEOC MD 110 requires that the formal complaint must be: • In writing; • Specific with regard to the claim(s) that the individual raised in precomplaint counseling and that the person wishes to pursue; • Must be signed by the individual and/or his or her representative; and • Must be filed within fifteen (15) calendar days from the date s/he receives the Notice of Right to File a Discrimination Complaint. Consequently, NASA established NF– 1355P form to ensure the individual who wishes to utilize the EEO process complies with the requirements listed above. PO 00000 Frm 00075 Fmt 4703 Sfmt 4703 III. Data Title: Formal Discrimination Complaint Form. OMB Number: 2700–0163. Type of Review: Reinstatement of existing information collection. Affected Public: Individuals who wish to file a formal discrimination complaint against NASA. Estimated Annual Number of Activities: 60. Estimated Number of Respondents per Activity: 1. Annual Responses: 60. Estimated Time per Response: 30 minutes. Estimated Total Annual Burden Hours: 30 hours. IV. Request for Comments Comments are invited on: (1) Whether the proposed collection of information is necessary for the proper performance of the functions of NASA, including whether the information collected has practical utility; (2) the accuracy of NASA’s estimate of the burden (including hours and cost) of the proposed collection of information; (3) ways to enhance the quality, utility, and clarity of the information to be collected; and (4) ways to minimize the burden of the collection of information on respondents, including automated collection techniques or the use of other forms of information technology. Comments submitted in response to this notice will be summarized and included in the request for OMB approval of this information collection. They will also become a matter of public record. William Edwards-Bodmer, NASA PRA Clearance Officer. [FR Doc. 2023–18960 Filed 8–31–23; 8:45 am] BILLING CODE 7510–13–P NUCLEAR REGULATORY COMMISSION [Docket No. 50–341; NRC–2023–0146] DTE Electric Company; Fermi, Unit 2 Nuclear Regulatory Commission. ACTION: License amendment application; opportunity to comment, request a hearing, and petition for leave to intervene. AGENCY: The U.S. Nuclear Regulatory Commission (NRC, the Commission) is considering issuance of an amendment to Renewed Facility Operating License No. NPF–43, issued to DTE Electric Company, for operation of Fermi, Unit SUMMARY: E:\FR\FM\01SEN1.SGM 01SEN1 Federal Register / Vol. 88, No. 169 / Friday, September 1, 2023 / Notices 2 (Fermi 2). The proposed amendment requests an amendment to the Fermi 2 Technical Specifications (TS) 3.7.2, to allow for a one-time extension of the Condition A Completion Time to allow repair of Division 1 Mechanical Draft Cooling Tower A and C fan pedestals while online. The proposed amendment is being requested due to an exigent circumstance pursuant to NRC regulations. Submit comments by September 15, 2023. Request for a hearing or petitions for leave to intervene must be filed by October 31, 2023. ADDRESSES: You may submit comments by any of the following methods; however, the NRC encourages electronic comment submission through the Federal Rulemaking website. • Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC–2023–0146. Address questions about Docket IDs in Regulations.gov to Stacy Schumann; telephone: 301–415–0624; email: Stacy.Schumann@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document. • Mail Comments to: Office of Administration, Mail Stop: TWFN–7– A60M, U.S. Nuclear Regulatory Commission, Washington, DC 20555– 0001, ATTN: Program Management, Announcements and Editing Staff. For additional direction on obtaining information and submitting comments, see ‘‘Obtaining Information and Submitting Comments’’ in the SUPPLEMENTARY INFORMATION section of this document. FOR FURTHER INFORMATION CONTACT: Surinder S. Arora, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001, telephone: 301–415– 1421, email: Surinder.Arora@nrc.gov. SUPPLEMENTARY INFORMATION: DATES: A. Obtaining Information B. Submitting Comments The NRC encourages electronic comment submission through the Federal Rulemaking website (https:// www.regulations.gov). Please include Docket ID NRC–2023–0146 in your comment submission. The NRC cautions you not to include identifying or contact information that you do not want to be publicly disclosed in your comment submission. The NRC will post all comment submissions at https:// www.regulations.gov as well as enter the comment submissions into ADAMS. The NRC does not routinely edit comment submissions to remove identifying or contact information. If you are requesting or aggregating comments from other persons for submission to the NRC, then you should inform those persons not to include identifying or contact information that they do not want to be publicly disclosed in their comment submission. Your request should state that the NRC does not routinely edit comment submissions to remove such information before making the comment submissions available to the public or entering the comment into ADAMS. Please refer to Docket ID NRC–2023– 0146 when contacting the NRC about the availability of information for this action. You may obtain publicly available information related to this action by any of the following methods: • Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC–2023–0146. • NRC’s Agencywide Documents Access and Management System (ADAMS): You may obtain publicly available documents online in the ADAMS Public Documents collection at II. Introduction The NRC is considering issuance of an amendment to Renewed Facility Operating License No. NPF–43, issued to DTE Electric Company, for operation of Fermi, Unit 2, located in Monroe County, Michigan. The proposed amendment requests an amendment to the Fermi, Unit 2, Technical Specifications (TS) 3.7.2, to allow for a one-time extension of the Condition A Completion Time to allow repair of Division 1 Mechanical Draft Cooling Tower A and C fan pedestals I. Obtaining Information and Submitting Comments lotter on DSK11XQN23PROD with NOTICES1 https://www.nrc.gov/reading-rm/ adams.html. To begin the search, select ‘‘Begin Web-based ADAMS Search.’’ For problems with ADAMS, please contact the NRC’s Public Document Room (PDR) reference staff at 1–800–397–4209, at 301–415–4737, or by email to PDR.Resource@nrc.gov. The ADAMS accession number for each document referenced (if it is available in ADAMS) is provided the first time that it is mentioned in this document. • NRC’s PDR: The PDR, where you may examine and order copies of publicly available documents, is open by appointment. To make an appointment to visit the PDR, please send an email to PDR.Resource@nrc.gov or call 1–800–397–4209 or 301–415– 4737, between 8 a.m. and 4 p.m. eastern time (ET), Monday through Friday, except Federal holidays. VerDate Sep<11>2014 17:24 Aug 31, 2023 Jkt 259001 PO 00000 Frm 00076 Fmt 4703 Sfmt 4703 60505 while online. The proposed amendment is being requested due to an exigent circumstance pursuant to paragraph 50.91(a)(6) of title 10 of the Code of Federal Regulations (10 CFR). On July 18, 2023, the Division II Residual Heat Removal Service Water Mechanical Draft Cooling Tower (MDCT) fan D tripped due to high vibrations caused by a degraded, nonconforming gearbox pedestal. Corrective actions were required to correct the conditions and restore the equipment to an operable status, using extra time allowed by the Notice of Enforcement Discretion approved by the NRC on July 20, 2023. During that time the ultimate heat sink was declared inoperable. During the ‘extent of condition’ review by DTE, it was discovered that the MDCT A and C fan pedestals were also degraded and non-conforming but remained operable and also in need of similar repair. DTE submitted this amendment to repair the Division I MDCT A and C fan pedestals. Additionally, the request provides justification that obtaining an extension of the Completion Time to repair the Division | MDCT fan pedestals online instead of waiting until the next refueling outage. Before any issuance of the proposed license amendment, the NRC will need to make the findings required by the Atomic Energy Act of 1954, as amended (the Act), and NRC’s regulations. Pursuant to 10 CFR 50.91(a)(6) for amendments to be granted under exigent circumstances, the NRC has made a proposed determination that the license amendment request involves no significant hazards consideration. Under the NRC’s regulations in 10 CFR 50.92, this means that operation of the facility in accordance with the proposed amendment would not (1) involve a significant increase in the probability or consequences of an accident previously evaluated; or (2) create the possibility of a new or different kind of accident from any accident previously evaluated; or (3) involve a significant reduction in a margin of safety. As required by 10 CFR 50.91(a), the licensee has provided its analysis of the issue of no significant hazards consideration, which is presented below: 1. Does the proposed change involve a significant increase in the probability or consequences of an accident previously evaluated? Response: No. DTE will use the compensatory measures and Fermi 2 Configuration Risk Management program requirements outlined [in] Section 3.2 and in enclosure 4 [of ML23222A037] during the duration of the proposed extension E:\FR\FM\01SEN1.SGM 01SEN1 lotter on DSK11XQN23PROD with NOTICES1 60506 Federal Register / Vol. 88, No. 169 / Friday, September 1, 2023 / Notices of the Completion Time for the MDCT fan pedestal repair. The risk impact of the proposed Completion Time is deemed acceptable and meets the requirements of RG 1.177 [Risk Evaluation is in Enclosure 4 of ML23222A037]. Therefore, the proposed changes do not involve a significant increase in the probability or consequences of an accident previously evaluated. 2. Does the proposed change create the possibility of a new or different kind of accident from any accident previously evaluated? Response: No. The proposed changes do not involve a change in design, configuration, or method of operation of the plant. The proposed changes will not alter the manner in which equipment is initiated, nor will the functional demands on credited equipment be changed. The proposed changes do not impact the interaction of any systems whose failure or malfunction can initiate an accident. There are no identified redundant components affected by these changes and, thus, there are no new common cause failures or any existing common cause failures that are affected by extending the Completion Time. The proposed changes do not create any new failure modes. Therefore, the proposed changes do not create the possibility of a new or different kind of accident from any previously evaluated. 3. Does the proposed change involve a significant reduction in a margin of safety? Response: No. The proposed changes do not alter the plant design, nor do they affect the assumptions contained in the safety analyses. Specifically, there are no changes being made to the MDCT fan design. The proposed changes have been evaluated and margins of safety ascribed to Emergency Equipment Cooling Water (EECW) [Correction by the Licensee in ML23237B402] availability and to plant risk have been determined to be not significantly reduced. The risk impact of the proposed changes is acceptable to the compensatory measures and other requirements, as outlined in Section 3.2 and in Enclosure 4 [of ML23222A037]. As analyzed in the UFSAR, the loss of the Division | MDCT fans would not cause a significant reduction in safety because the MDCT system is redundant and can perform its function with one division unavailable. The evaluation provided above shows that the proposed changes will not significantly increase the probability or the consequences of any accident VerDate Sep<11>2014 17:24 Aug 31, 2023 Jkt 259001 previously evaluated, create the possibility of a new or different kind of accident from any accident previously evaluated, or involve a significant reduction in the margin of safety. The NRC staff has reviewed the licensee’s analysis and based on this review, the three standards of 10 CFR 50.92(c) are satisfied. Therefore, the NRC staff proposes to determine that the license amendment request involves a no significant hazards consideration. The NRC is seeking public comments on this proposed determination that the license amendment request involves no significant hazards consideration. Any comments received within 14 days after the date of publication of this notice will be considered in making any final determination. Normally, the Commission will not issue the amendment until the expiration of the 14-day notice period. However, if circumstances change during the notice period, such that failure to act in a timely way would result, for example, in derating or shutdown of the facility, the Commission may issue the license amendment before the expiration of the 14-day notice period, provided that its final determination is that the amendment involves no significant hazards consideration. The final determination will consider all public and State comments received. If the Commission takes this action, it will publish in the Federal Register a notice of issuance. The Commission expects that the need to take this action will occur very infrequently. III. Opportunity To Request a Hearing and Petition for Leave To Intervene Within 60 days after the date of publication of this notice, any person (petitioner) whose interest may be affected by this action may file a request for a hearing and petition for leave to intervene (petition) with respect to the action. Petitions shall be filed in accordance with the Commission’s ‘‘Agency Rules of Practice and Procedure’’ in 10 CFR part 2. Interested persons should consult 10 CFR 2.309. If a petition is filed, the presiding officer will rule on the petition and, if appropriate, a notice of a hearing will be issued. Petitions must be filed no later than 60 days from the date of publication of this notice in accordance with the filing instructions in the ‘‘Electronic Submissions (E-Filing)’’ section of this document. Petitions and motions for leave to file new or amended contentions that are filed after the deadline will not be entertained absent a determination by the presiding officer PO 00000 Frm 00077 Fmt 4703 Sfmt 4703 that the filing demonstrates good cause by satisfying the three factors in 10 CFR 2.309(c)(1)(i) through (iii). If a hearing is requested and the Commission has not made a final determination on the issue of no significant hazards consideration, the Commission will make a final determination on the issue of no significant hazards consideration, which will serve to establish when the hearing is held. If the final determination is that the amendment request involves no significant hazards consideration, the Commission may issue the amendment and make it immediately effective, notwithstanding the request for a hearing. Any hearing would take place after issuance of the amendment. If the final determination is that the amendment request involves a significant hazards consideration, then any hearing held would take place before the issuance of the amendment unless the Commission finds an imminent danger to the health or safety of the public, in which case it will issue an appropriate order or rule under 10 CFR part 2. A State, local governmental body, Federally recognized Indian Tribe, or designated agency thereof, may submit a petition to the Commission to participate as a party under 10 CFR 2.309(h) no later than 60 days from the date of publication of this notice. Alternatively, a State, local governmental body, Federally recognized Indian Tribe, or agency thereof may participate as a non-party under 10 CFR 2.315(c). For information about filing a petition and about participation by a person not a party under 10 CFR 2.315, see ADAMS Accession No. ML20340A053 and on the NRC’s public website at https:// www.nrc.gov/about-nrc/regulatory/ adjudicatory/hearing.html#participate. IV. Electronic Submissions (E-Filing) All documents filed in NRC adjudicatory proceedings, including documents filed by an interested State, local governmental body, Federally recognized Indian Tribe, or designated agency thereof that requests to participate under 10 CFR 2.315(c), must be filed in accordance with 10 CFR 2.302. The E-Filing process requires participants to submit and serve all adjudicatory documents over the internet, or in some cases, to mail copies on electronic storage media, unless an exemption permitting an alternative filing method, as further discussed, is granted. Detailed guidance on electronic submissions is located in the ‘‘Guidance for Electronic Submissions to the NRC’’ (ADAMS Accession No. ML13031A056) E:\FR\FM\01SEN1.SGM 01SEN1 lotter on DSK11XQN23PROD with NOTICES1 Federal Register / Vol. 88, No. 169 / Friday, September 1, 2023 / Notices and on the NRC’s public website at https://www.nrc.gov/site-help/esubmittals.html. To comply with the procedural requirements of E-Filing, at least 10 days prior to the filing deadline, the participant should contact the Office of the Secretary by email at Hearing.Docket@nrc.gov, or by telephone at 301–415–1677, to (1) request a digital identification (ID) certificate, which allows the participant (or its counsel or representative) to digitally sign submissions and access the E-Filing system for any proceeding in which it is participating; and (2) advise the Secretary that the participant will be submitting a petition or other adjudicatory document (even in instances in which the participant, or its counsel or representative, already holds an NRC-issued digital ID certificate). Based upon this information, the Secretary will establish an electronic docket for the proceeding if the Secretary has not already established an electronic docket. Information about applying for a digital ID certificate is available on the NRC’s public website at https:// www.nrc.gov/site-help/e-submittals/ getting-started.html. After a digital ID certificate is obtained and a docket created, the participant must submit adjudicatory documents in Portable Document Format. Guidance on submissions is available on the NRC’s public website at https://www.nrc.gov/ site-help/electronic-sub-ref-mat.html. A filing is considered complete at the time the document is submitted through the NRC’s E-Filing system. To be timely, an electronic filing must be submitted to the E-Filing system no later than 11:59 p.m. ET on the due date. Upon receipt of a transmission, the E-Filing system time-stamps the document and sends the submitter an email confirming receipt of the document. The E-Filing system also distributes an email that provides access to the document to the NRC’s Office of the General Counsel and any others who have advised the Office of the Secretary that they wish to participate in the proceeding, so that the filer need not serve the document on those participants separately. Therefore, applicants and other participants (or their counsel or representative) must apply for and receive a digital ID certificate before adjudicatory documents are filed to obtain access to the documents via the E-Filing system. A person filing electronically using the NRC’s adjudicatory E-Filing system may seek assistance by contacting the NRC’s Electronic Filing Help Desk through the ‘‘Contact Us’’ link located on the NRC’s public website at https:// VerDate Sep<11>2014 17:24 Aug 31, 2023 Jkt 259001 www.nrc.gov/site-help/esubmittals.html, by email to MSHD.Resource@nrc.gov, or by a tollfree call at 1–866–672–7640. The NRC Electronic Filing Help Desk is available between 9 a.m. and 6 p.m., ET, Monday through Friday, except Federal holidays. Participants who believe that they have good cause for not submitting documents electronically must file an exemption request, in accordance with 10 CFR 2.302(g), with their initial paper filing stating why there is good cause for not filing electronically and requesting authorization to continue to submit documents in paper format. Such filings must be submitted in accordance with 10 CFR 2.302(b) through (d). Participants filing adjudicatory documents in this manner are responsible for serving their documents on all other participants. Participants granted an exemption under 10 CFR 2.302(g)(2) must still meet the electronic formatting requirement in 10 CFR 2.302(g)(1), unless the participant also seeks and is granted an exemption from 10 CFR 2.302(g)(1). Documents submitted in adjudicatory proceedings will appear in the NRC’s electronic hearing docket, which is publicly available at https:// adams.nrc.gov/ehd, unless excluded pursuant to an order of the presiding officer. If you do not have an NRCissued digital ID certificate as previously described, click ‘‘cancel’’ when the link requests certificates and you will be automatically directed to the NRC’s electronic hearing dockets where you will be able to access any publicly available documents in a particular hearing docket. Participants are requested not to include personal privacy information such as social security numbers, home addresses, or personal phone numbers in their filings unless an NRC regulation or other law requires submission of such information. With respect to copyrighted works, except for limited excerpts that serve the purpose of the adjudicatory filings and would constitute a Fair Use application, participants should not include copyrighted materials in their submission. For further details with respect to this action, see the application for license amendment dated August 10, 2023 (ADAMS Accession No. ML23222A037). Attorney for licensee: Jon P. Christinidis, DTE Electric Company, Expert Attorney—Regulatory, 1635 WCB, One Energy Plaza, Detroit, MI 48226. NRC Branch Chief: Jeff Whited. Dated: August 29, 2023. PO 00000 Frm 00078 Fmt 4703 Sfmt 4703 60507 For the Nuclear Regulatory Commission. Surinder S. Arora, Project Manager, Plant Licensing Branch III, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation. [FR Doc. 2023–18920 Filed 8–31–23; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION [NRC–2023–0113] Draft NUREG: Environmental Evaluation of Accident Tolerant Fuels With Increased Enrichment and Higher Burnup Levels Nuclear Regulatory Commission. ACTION: Draft report; request for comment. AGENCY: The U.S. Nuclear Regulatory Commission (NRC) is issuing for public comment draft NUREG–2266, ‘‘Environmental Evaluation of Accident Tolerant Fuels with Increased Enrichment and Higher Burnup Levels.’’ This study evaluates the reasonably foreseeable impacts of near-term accident tolerant fuel (ATF) technologies with increased enrichment and higher burnup levels to 8 wt% uranium-235 (U–235) and up to 80 GWd/MTU, respectively, on the uranium fuel cycle, transportation of fuel and waste, and decommissioning for light-water reactors (LWRs) (i.e., a bounding analysis). DATES: Submit comments by October 31, 2023. Comments received after this date will be considered if it is practical to do so, but the Commission is able to ensure consideration only for comments received before this date. ADDRESSES: You may submit comments by any of the following methods; however, the NRC encourages electronic comment submission through the Federal rulemaking website: • Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC–2023–0113. Address questions about Docket IDs in Regulations.gov to Stacy Schumann; telephone: 301–415–0624; email: Stacy.Schumann@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document. • Mail Comments to: Office of Administration, Mail Stop: TWFN–7– A60M, U.S. Nuclear Regulatory Commission, Washington, DC 20555– 0001, ATTN: Program Management, Announcements and Editing Staff. For additional direction on obtaining information and submitting comments, SUMMARY: E:\FR\FM\01SEN1.SGM 01SEN1

Agencies

[Federal Register Volume 88, Number 169 (Friday, September 1, 2023)]
[Notices]
[Pages 60504-60507]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-18920]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-341; NRC-2023-0146]


DTE Electric Company; Fermi, Unit 2

AGENCY: Nuclear Regulatory Commission.

ACTION: License amendment application; opportunity to comment, request 
a hearing, and petition for leave to intervene.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC, the Commission) 
is considering issuance of an amendment to Renewed Facility Operating 
License No. NPF-43, issued to DTE Electric Company, for operation of 
Fermi, Unit

[[Page 60505]]

2 (Fermi 2). The proposed amendment requests an amendment to the Fermi 
2 Technical Specifications (TS) 3.7.2, to allow for a one-time 
extension of the Condition A Completion Time to allow repair of 
Division 1 Mechanical Draft Cooling Tower A and C fan pedestals while 
online. The proposed amendment is being requested due to an exigent 
circumstance pursuant to NRC regulations.

DATES: Submit comments by September 15, 2023. Request for a hearing or 
petitions for leave to intervene must be filed by October 31, 2023.

ADDRESSES: You may submit comments by any of the following methods; 
however, the NRC encourages electronic comment submission through the 
Federal Rulemaking website.
     Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2023-0146. Address 
questions about Docket IDs in Regulations.gov to Stacy Schumann; 
telephone: 301-415-0624; email: [email protected]. For technical 
questions, contact the individual listed in the FOR FURTHER INFORMATION 
CONTACT section of this document.
     Mail Comments to: Office of Administration, Mail Stop: 
TWFN-7-A60M, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001, ATTN: Program Management, Announcements and Editing Staff.
    For additional direction on obtaining information and submitting 
comments, see ``Obtaining Information and Submitting Comments'' in the 
SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: Surinder S. Arora, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001, telephone: 301-415-1421, email: [email protected].

SUPPLEMENTARY INFORMATION: 

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID NRC-2023-0146 when contacting the NRC 
about the availability of information for this action. You may obtain 
publicly available information related to this action by any of the 
following methods:
     Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2023-0146.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS 
Search.'' For problems with ADAMS, please contact the NRC's Public 
Document Room (PDR) reference staff at 1-800-397-4209, at 301-415-4737, 
or by email to [email protected]. The ADAMS accession number for 
each document referenced (if it is available in ADAMS) is provided the 
first time that it is mentioned in this document.
     NRC's PDR: The PDR, where you may examine and order copies 
of publicly available documents, is open by appointment. To make an 
appointment to visit the PDR, please send an email to 
[email protected] or call 1-800-397-4209 or 301-415-4737, between 8 
a.m. and 4 p.m. eastern time (ET), Monday through Friday, except 
Federal holidays.

B. Submitting Comments

    The NRC encourages electronic comment submission through the 
Federal Rulemaking website (https://www.regulations.gov). Please 
include Docket ID NRC-2023-0146 in your comment submission.
    The NRC cautions you not to include identifying or contact 
information that you do not want to be publicly disclosed in your 
comment submission. The NRC will post all comment submissions at 
https://www.regulations.gov as well as enter the comment submissions 
into ADAMS. The NRC does not routinely edit comment submissions to 
remove identifying or contact information.
    If you are requesting or aggregating comments from other persons 
for submission to the NRC, then you should inform those persons not to 
include identifying or contact information that they do not want to be 
publicly disclosed in their comment submission. Your request should 
state that the NRC does not routinely edit comment submissions to 
remove such information before making the comment submissions available 
to the public or entering the comment into ADAMS.

II. Introduction

    The NRC is considering issuance of an amendment to Renewed Facility 
Operating License No. NPF-43, issued to DTE Electric Company, for 
operation of Fermi, Unit 2, located in Monroe County, Michigan.
    The proposed amendment requests an amendment to the Fermi, Unit 2, 
Technical Specifications (TS) 3.7.2, to allow for a one-time extension 
of the Condition A Completion Time to allow repair of Division 1 
Mechanical Draft Cooling Tower A and C fan pedestals while online. The 
proposed amendment is being requested due to an exigent circumstance 
pursuant to paragraph 50.91(a)(6) of title 10 of the Code of Federal 
Regulations (10 CFR).
    On July 18, 2023, the Division II Residual Heat Removal Service 
Water Mechanical Draft Cooling Tower (MDCT) fan D tripped due to high 
vibrations caused by a degraded, non-conforming gearbox pedestal. 
Corrective actions were required to correct the conditions and restore 
the equipment to an operable status, using extra time allowed by the 
Notice of Enforcement Discretion approved by the NRC on July 20, 2023. 
During that time the ultimate heat sink was declared inoperable. During 
the `extent of condition' review by DTE, it was discovered that the 
MDCT A and C fan pedestals were also degraded and non-conforming but 
remained operable and also in need of similar repair. DTE submitted 
this amendment to repair the Division I MDCT A and C fan pedestals. 
Additionally, the request provides justification that obtaining an 
extension of the Completion Time to repair the Division [verbar] MDCT 
fan pedestals online instead of waiting until the next refueling 
outage.
    Before any issuance of the proposed license amendment, the NRC will 
need to make the findings required by the Atomic Energy Act of 1954, as 
amended (the Act), and NRC's regulations.
    Pursuant to 10 CFR 50.91(a)(6) for amendments to be granted under 
exigent circumstances, the NRC has made a proposed determination that 
the license amendment request involves no significant hazards 
consideration. Under the NRC's regulations in 10 CFR 50.92, this means 
that operation of the facility in accordance with the proposed 
amendment would not (1) involve a significant increase in the 
probability or consequences of an accident previously evaluated; or (2) 
create the possibility of a new or different kind of accident from any 
accident previously evaluated; or (3) involve a significant reduction 
in a margin of safety. As required by 10 CFR 50.91(a), the licensee has 
provided its analysis of the issue of no significant hazards 
consideration, which is presented below:
    1. Does the proposed change involve a significant increase in the 
probability or consequences of an accident previously evaluated?
    Response: No.
    DTE will use the compensatory measures and Fermi 2 Configuration 
Risk Management program requirements outlined [in] Section 3.2 and in 
enclosure 4 [of ML23222A037] during the duration of the proposed 
extension

[[Page 60506]]

of the Completion Time for the MDCT fan pedestal repair. The risk 
impact of the proposed Completion Time is deemed acceptable and meets 
the requirements of RG 1.177 [Risk Evaluation is in Enclosure 4 of 
ML23222A037].
    Therefore, the proposed changes do not involve a significant 
increase in the probability or consequences of an accident previously 
evaluated.
    2. Does the proposed change create the possibility of a new or 
different kind of accident from any accident previously evaluated?
    Response: No.
    The proposed changes do not involve a change in design, 
configuration, or method of operation of the plant. The proposed 
changes will not alter the manner in which equipment is initiated, nor 
will the functional demands on credited equipment be changed. The 
proposed changes do not impact the interaction of any systems whose 
failure or malfunction can initiate an accident. There are no 
identified redundant components affected by these changes and, thus, 
there are no new common cause failures or any existing common cause 
failures that are affected by extending the Completion Time. The 
proposed changes do not create any new failure modes.
    Therefore, the proposed changes do not create the possibility of a 
new or different kind of accident from any previously evaluated.
    3. Does the proposed change involve a significant reduction in a 
margin of safety?
    Response: No.
    The proposed changes do not alter the plant design, nor do they 
affect the assumptions contained in the safety analyses. Specifically, 
there are no changes being made to the MDCT fan design. The proposed 
changes have been evaluated and margins of safety ascribed to Emergency 
Equipment Cooling Water (EECW) [Correction by the Licensee in 
ML23237B402] availability and to plant risk have been determined to be 
not significantly reduced. The risk impact of the proposed changes is 
acceptable to the compensatory measures and other requirements, as 
outlined in Section 3.2 and in Enclosure 4 [of ML23222A037]. As 
analyzed in the UFSAR, the loss of the Division [verbar] MDCT fans 
would not cause a significant reduction in safety because the MDCT 
system is redundant and can perform its function with one division 
unavailable.
    The evaluation provided above shows that the proposed changes will 
not significantly increase the probability or the consequences of any 
accident previously evaluated, create the possibility of a new or 
different kind of accident from any accident previously evaluated, or 
involve a significant reduction in the margin of safety.
    The NRC staff has reviewed the licensee's analysis and based on 
this review, the three standards of 10 CFR 50.92(c) are satisfied. 
Therefore, the NRC staff proposes to determine that the license 
amendment request involves a no significant hazards consideration.
    The NRC is seeking public comments on this proposed determination 
that the license amendment request involves no significant hazards 
consideration. Any comments received within 14 days after the date of 
publication of this notice will be considered in making any final 
determination.
    Normally, the Commission will not issue the amendment until the 
expiration of the 14-day notice period. However, if circumstances 
change during the notice period, such that failure to act in a timely 
way would result, for example, in derating or shutdown of the facility, 
the Commission may issue the license amendment before the expiration of 
the 14-day notice period, provided that its final determination is that 
the amendment involves no significant hazards consideration. The final 
determination will consider all public and State comments received. If 
the Commission takes this action, it will publish in the Federal 
Register a notice of issuance. The Commission expects that the need to 
take this action will occur very infrequently.

III. Opportunity To Request a Hearing and Petition for Leave To 
Intervene

    Within 60 days after the date of publication of this notice, any 
person (petitioner) whose interest may be affected by this action may 
file a request for a hearing and petition for leave to intervene 
(petition) with respect to the action. Petitions shall be filed in 
accordance with the Commission's ``Agency Rules of Practice and 
Procedure'' in 10 CFR part 2. Interested persons should consult 10 CFR 
2.309. If a petition is filed, the presiding officer will rule on the 
petition and, if appropriate, a notice of a hearing will be issued.
    Petitions must be filed no later than 60 days from the date of 
publication of this notice in accordance with the filing instructions 
in the ``Electronic Submissions (E-Filing)'' section of this document. 
Petitions and motions for leave to file new or amended contentions that 
are filed after the deadline will not be entertained absent a 
determination by the presiding officer that the filing demonstrates 
good cause by satisfying the three factors in 10 CFR 2.309(c)(1)(i) 
through (iii).
    If a hearing is requested and the Commission has not made a final 
determination on the issue of no significant hazards consideration, the 
Commission will make a final determination on the issue of no 
significant hazards consideration, which will serve to establish when 
the hearing is held. If the final determination is that the amendment 
request involves no significant hazards consideration, the Commission 
may issue the amendment and make it immediately effective, 
notwithstanding the request for a hearing. Any hearing would take place 
after issuance of the amendment. If the final determination is that the 
amendment request involves a significant hazards consideration, then 
any hearing held would take place before the issuance of the amendment 
unless the Commission finds an imminent danger to the health or safety 
of the public, in which case it will issue an appropriate order or rule 
under 10 CFR part 2.
    A State, local governmental body, Federally recognized Indian 
Tribe, or designated agency thereof, may submit a petition to the 
Commission to participate as a party under 10 CFR 2.309(h) no later 
than 60 days from the date of publication of this notice. 
Alternatively, a State, local governmental body, Federally recognized 
Indian Tribe, or agency thereof may participate as a non-party under 10 
CFR 2.315(c).
    For information about filing a petition and about participation by 
a person not a party under 10 CFR 2.315, see ADAMS Accession No. 
ML20340A053 and on the NRC's public website at https://www.nrc.gov/about-nrc/regulatory/adjudicatory/hearing.html#participate.

IV. Electronic Submissions (E-Filing)

    All documents filed in NRC adjudicatory proceedings, including 
documents filed by an interested State, local governmental body, 
Federally recognized Indian Tribe, or designated agency thereof that 
requests to participate under 10 CFR 2.315(c), must be filed in 
accordance with 10 CFR 2.302. The E-Filing process requires 
participants to submit and serve all adjudicatory documents over the 
internet, or in some cases, to mail copies on electronic storage media, 
unless an exemption permitting an alternative filing method, as further 
discussed, is granted. Detailed guidance on electronic submissions is 
located in the ``Guidance for Electronic Submissions to the NRC'' 
(ADAMS Accession No. ML13031A056)

[[Page 60507]]

and on the NRC's public website at https://www.nrc.gov/site-help/e-submittals.html.
    To comply with the procedural requirements of E-Filing, at least 10 
days prior to the filing deadline, the participant should contact the 
Office of the Secretary by email at [email protected], or by 
telephone at 301-415-1677, to (1) request a digital identification (ID) 
certificate, which allows the participant (or its counsel or 
representative) to digitally sign submissions and access the E-Filing 
system for any proceeding in which it is participating; and (2) advise 
the Secretary that the participant will be submitting a petition or 
other adjudicatory document (even in instances in which the 
participant, or its counsel or representative, already holds an NRC-
issued digital ID certificate). Based upon this information, the 
Secretary will establish an electronic docket for the proceeding if the 
Secretary has not already established an electronic docket.
    Information about applying for a digital ID certificate is 
available on the NRC's public website at https://www.nrc.gov/site-help/e-submittals/getting-started.html. After a digital ID certificate is 
obtained and a docket created, the participant must submit adjudicatory 
documents in Portable Document Format. Guidance on submissions is 
available on the NRC's public website at https://www.nrc.gov/site-help/electronic-sub-ref-mat.html. A filing is considered complete at the 
time the document is submitted through the NRC's E-Filing system. To be 
timely, an electronic filing must be submitted to the E-Filing system 
no later than 11:59 p.m. ET on the due date. Upon receipt of a 
transmission, the E-Filing system time-stamps the document and sends 
the submitter an email confirming receipt of the document. The E-Filing 
system also distributes an email that provides access to the document 
to the NRC's Office of the General Counsel and any others who have 
advised the Office of the Secretary that they wish to participate in 
the proceeding, so that the filer need not serve the document on those 
participants separately. Therefore, applicants and other participants 
(or their counsel or representative) must apply for and receive a 
digital ID certificate before adjudicatory documents are filed to 
obtain access to the documents via the E-Filing system.
    A person filing electronically using the NRC's adjudicatory E-
Filing system may seek assistance by contacting the NRC's Electronic 
Filing Help Desk through the ``Contact Us'' link located on the NRC's 
public website at https://www.nrc.gov/site-help/e-submittals.html, by 
email to [email protected], or by a toll-free call at 1-866-672-
7640. The NRC Electronic Filing Help Desk is available between 9 a.m. 
and 6 p.m., ET, Monday through Friday, except Federal holidays.
    Participants who believe that they have good cause for not 
submitting documents electronically must file an exemption request, in 
accordance with 10 CFR 2.302(g), with their initial paper filing 
stating why there is good cause for not filing electronically and 
requesting authorization to continue to submit documents in paper 
format. Such filings must be submitted in accordance with 10 CFR 
2.302(b) through (d). Participants filing adjudicatory documents in 
this manner are responsible for serving their documents on all other 
participants. Participants granted an exemption under 10 CFR 
2.302(g)(2) must still meet the electronic formatting requirement in 10 
CFR 2.302(g)(1), unless the participant also seeks and is granted an 
exemption from 10 CFR 2.302(g)(1).
    Documents submitted in adjudicatory proceedings will appear in the 
NRC's electronic hearing docket, which is publicly available at https://adams.nrc.gov/ehd, unless excluded pursuant to an order of the 
presiding officer. If you do not have an NRC-issued digital ID 
certificate as previously described, click ``cancel'' when the link 
requests certificates and you will be automatically directed to the 
NRC's electronic hearing dockets where you will be able to access any 
publicly available documents in a particular hearing docket. 
Participants are requested not to include personal privacy information 
such as social security numbers, home addresses, or personal phone 
numbers in their filings unless an NRC regulation or other law requires 
submission of such information. With respect to copyrighted works, 
except for limited excerpts that serve the purpose of the adjudicatory 
filings and would constitute a Fair Use application, participants 
should not include copyrighted materials in their submission.
    For further details with respect to this action, see the 
application for license amendment dated August 10, 2023 (ADAMS 
Accession No. ML23222A037).
    Attorney for licensee: Jon P. Christinidis, DTE Electric Company, 
Expert Attorney--Regulatory, 1635 WCB, One Energy Plaza, Detroit, MI 
48226.
    NRC Branch Chief: Jeff Whited.

    Dated: August 29, 2023.

    For the Nuclear Regulatory Commission.
Surinder S. Arora,
Project Manager, Plant Licensing Branch III, Division of Operating 
Reactor Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. 2023-18920 Filed 8-31-23; 8:45 am]
BILLING CODE 7590-01-P